Geo Tech Natural Gas

download Geo Tech Natural Gas

of 18

Transcript of Geo Tech Natural Gas

  • 7/25/2019 Geo Tech Natural Gas

    1/18

    A Geotechnical Investigation Report

    For

    Proposed Natural Gas Pipeline Dia 16 inch

    Client. -MM

    Consultant.Petro Chemical Engineering Consultant

    EPC Contractor. Petro Con Pvt.Ltd

    May, 16, 2015

    Geo Tech Report prepared byPEC Licence # 41987

    House no-19 Mah-e- Nor Vills Nisheman Iqbal Lahore.042-35228238

    An overview

    The Geo technical Investigation Report prepared by GDE for Natural Gas Pipeline of FFC focuses on the

    various Geotechnical aspects such as computation of safe bearing capacity, review of site condition

  • 7/25/2019 Geo Tech Natural Gas

    2/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 1

    SUBSURFACE INVESTIGATION AND LABORATORY TESING FOR THEProposed Natural Gas Pipeline dia 16 inch

    TABLE OF CONTENTS

    1.0 Introduction 2

    2.0 Purpose and scope of work 3

    3.0 Field investigation 4

    3.1 Drilling of boreholes 4

    4.0 Laboratory testing. 5

    4.1 Soil classification tests

    4.2 Specific gravity of soil 54.3 Unit weight 5

    5.0 Results of the investigation 7

    5.1 The subsurface strata 7

    5.2 Groundwater conditions 7

    6.0 Geotechnical parameters 7

    6.1 Unit weight 7

    6.2 Shear strength parameters 76.3 Modulus of elasticity (es) 9

    6.4 Selection of foundation type 9

    6.5 Depth of foundation 9

    6.6 Allowable bearing pressures 10

    6.7 Guidelines for placing the foundations 11

    SEPERATORS

  • 7/25/2019 Geo Tech Natural Gas

    3/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 2

    1. INTRODUCTION

    Geo Drillers Engineering (GDE), was engaged by the Petro chemical

    Engineering Consultant, to carry out a subsurface soil investigationcampaign at the site of Proposed natural Gas pipeline. This report pertains

    to the project a brief description of the geotechnical tasks performed at site

    as well as results of the insitu field and laboratory tests. The report

    presents an assessment of the general geotechnical conditions at the

    investigated site. Specific recommendations for the foundation design are

    included in this report.

    The investigation was performed in accordance with the scope of work

    stipulated by the client and comprised several tasks that included drilling of

    boreholes to the designated depths below the existing ground level, in-situ

    testing and sampling of the sub-soil through standard penetration tests

    (SPTs) at different depth horizons, laboratory analysis. The scope of GDE

    services also included preparation of a geotechnical report describing the

    methodology and presenting results of all the geotechnical investigation,

    recommendations for foundation design.

    This report contains the results of field & laboratory investigation and a

    brief description of the techniques employed during the field works as well

    as methods used in performing the laboratory tests.

    The evaluation of geotechnical parameters together with recommendations

    for foundations and geotechnical work related to design & construction of

    foundations is also included in this report.

    The borehole logs and laboratory test results are presented in APPENDIX

    respectively.

  • 7/25/2019 Geo Tech Natural Gas

    4/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 3

    2. PURPOSE AND SCOPE OF WORK

    The purpose of the present investigation was to assess the prevailinggeotechnical conditions at the site and to verify the geo-engineering

    properties of the deeper subsurface soil strata which will significantly affect

    the foundations behaviour. The field investigation program comprised of

    the following:

    1. Drilling and sampling of a total of six (6) boreholes were drilled down

    to a depth 10.0 m from surface level at the different locations

    designated by the consultant.

    2. In-situ testing and sampling of overburden soil by performing Standard

    Penetration Tests (SPTs) at each1.0 m from surface down to maximum

    borehole depth.

    3. Conducting necessary laboratory tests on selected soil samples

    retrieved from the boreholes.

    4. Preparation of a geotechnical report presenting the investigation

    procedures and the results of the in-situ and laboratory tests together

    with recommendations for foundations design and construction.

  • 7/25/2019 Geo Tech Natural Gas

    5/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 4

    3. FIELD INVESTIGATION

    A total of six (6) boreholes were drilled at site down to a depth 10.0 m from

    surface level. The borehole logs are presented in APPENDIX-A.

    3.1 DRILLING OF BOREHOLES

    The drilling at each borehole location was carried out using percussion

    drilling method. Drilling was carried out through a 5 hollow stem auger,

    using augering method. The Standard Penetration Tests (SPTs) were

    performed at surface and thereafter at a depth interval of 1.0 m in

    accordance with ASTM D1586. The drive assembly of SPT consisted of

    hammer of 140 lb. weight, a driving head and a guide permitting free fall of

    30 inch. The assembly was equipped with split spoon sampler to collect the

    disturbed samples for necessary identifications and testing. The samples

    retrieved from the split spoon sampler were examined for their visual

    identification, packed in airtight polyethylene bags and sent to the

    laboratory for further evaluation and testing. A record of field observation

    was maintained in the form of field logs describing the visual identifications

    (ASTM-2488) of the subsurface materials encountered at different depths,

    the sampling details and recording the blow count observed in the SPT.

    These logs were later on refined by incorporating the laboratory test results

    and are presented in APPENDIX-B.

  • 7/25/2019 Geo Tech Natural Gas

    6/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 5

    4. LABORATORY TESTING

    Representative soil samples retrieved from the split spoon sampler (SPT)

    were selected from each borehole. The representative SPT samples weretested in laboratory. The SPT samples were subjected to moisture content,

    gradation and Atterberg limits in order to identify the subsurface materials.

    The tests were performed according to relevant American society for

    testing Materials ASTM. The laboratory test results are presented in

    LABORATORY TESTING separator.

    4.1 SOIL CLASSIFICATION TESTS (ASTM D422)

    The classification test performed on selected representative samples of

    subsurface materials consisted of determination of natural moisture

    content (ASTM D2216), Liquid Limit and Plastic Limits (ASTM D4318) and

    Grain-size Analysis (ASTM D422) and sedimentation test by Hydrometer

    (ASTM D4221-99).

    4.2 SPECIFIC GRAVITY OF SOIL (ASTM D 854-06)

    Specific gravity tests were performed on selected representative samples of

    subsurface materials according to (ASTM D854-06).

    4.3 UNIT WEIGHT (AASHTO T233-02)

    The soil samples retrieved from the boreholes were subjected to density

    measurement according to AASHTO T233-02 measuring the weight and

    volume by immersion in water.

  • 7/25/2019 Geo Tech Natural Gas

    7/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 6

    Measurements of soil properties in the Laboratory in Table-1 lists various

    laboratory tests on Un disturbed and disturbed samples soil samples

    collected from various depths to find physical properties and strength

    characteristics.

    Table 1 Measurements of soil properties

    Sr.No Tests Performed

    procedure

    Type

    sample

    1 Sample preparation ASTM(D 2487) DS/UDS

    2 Moisture content ASTM(D 2216) UDS

    3 Dry unit weight ASTM(C 29) UDS

    4 Specific Gravity ASTM(D 854 & C127) UDS

    5 Grain size Analysis ASTM(D 422) DS/UDS

    6 Direct shear test ASTM(D 3080) UDS

    7 N- observed ASTM(D 2166) DS

    8 Unconfined

    compressive Strength

    ASATM(D2166) UDS

    9 LL & PL ASTM (D422) DS

  • 7/25/2019 Geo Tech Natural Gas

    8/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 7

    5. RESULTS OF THE INVESTIGATION

    5.1 THE SUBSURFACE STRATA

    The description of the subsurface soil strata is based on the inspection of

    soil samples retrieved from the field and later refinements done after

    laboratory test results. Based upon the results of the field investigation a

    representative subsurface soil profile has been developed described as

    follows:

    Near Railway Track Change=14 +275

    BH.no Layer

    Encounter

    Type of

    soil

    SPT-N

    value

    Layer

    Up to

    Total

    thickness

    1

    Layer-1 SM 1~3 0~2.0 m 2 m

    Layer-2 CL 3~5 2~7 m 5 m

    Layer-3 ML 3 7~8 m 1m

    Layer-4 SM 7~11 8~10 m 2 m

    Groundwater was encountered at 1 m depth in the 1stweek of May 2015

    Near Masu Wah Canal Change=13 +650

    BH.no Layer

    Encounter

    Type of

    soil

    SPT-N

    value

    Layer

    Up to

    Total

    thickness

    2

    Layer-1 CL 1~3 0~3.0 m 3 m

    Layer-2 SM 4~6 3~8 m 5 m

    Layer-3 SP-SM 7 8~10 m 2m

    Groundwater was encountered at 2 m depth in the 1stweek of May 2015

  • 7/25/2019 Geo Tech Natural Gas

    9/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 8

    Near Canal Road Crossing Kandyaro change=10 +775

    BH.no Layer

    Encounter

    Type of

    soil

    SPT-N

    value

    Layer

    Up to

    Total

    thickness

    3

    Layer-1 SM 5 0~3.0 m 3 m

    Layer-2 SP 1~3 3~4 m 1 m

    Layer-3 CL 3~8 4~10 m 6m

    Groundwater was encountered at 2.5 m depth in the 1stweek of May 2015

    Near Dher wah lower, change=6 +825

    BH.no Layer

    Encounter

    Type of

    soil

    SPT-N

    value

    Layer

    Up to

    Total

    thickness

    4

    Layer-1 CL 3 0~4.0 m 4 m

    Layer-2 ML 4~5 4~6 m 2 m

    Layer-3 CL 5~8 6~10 m 4 m

    Groundwater was encountered at 3 m depth in the 1stweek of May 2015

    Near narli wah Canal change=1 +080

    Near Mari Mani Fold Change =0+100

    BH.no Layer

    Encounter

    Type of

    soil

    SPT-N

    value

    Layer

    Up to

    Total

    thickness

    5,6Layer-1 ML 3~4 0~3.0 m 3 mLayer-2 CL 3~5 3~5 m 2 m

    Layer-3 SP-SM 6~14 5~10 m 5 m

    Groundwater was encountered at 3 m depth in the 1stweek of May 2015

  • 7/25/2019 Geo Tech Natural Gas

    10/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 9

    6. GEOTECHNICAL PARAMETERS

    The geotechnical parameters refer to the parameters related tocharacteristics of the subsurface materials for design and construction of

    foundation and execution of earthwork. These parameters have been

    developed on the basis of evaluation of the engineering characteristics of

    the subsurface strata as determined through drilling records, field

    exploration, in-situ testing (SPTs) and laboratory testing of the

    representative samples of materials obtained from the boreholes. The

    selection of parameters is discussed as follows:

    6.1 UNIT WEIGHT

    The unit weight of the subsurface material was estimated through

    inspection and laboratory classification of the samples retrieved from

    boreholes and through correlation with the SPT data. Typically, for the

    purpose of calculations the bulk unit weight (bulk) of the representative soil

    materials has been considered as 1.585 ~1.647 g/cm3. Following relation

    should be used for submerged conditions.

    (Sub= bulk- w) sub = Buoyant Unit Weight

    w = Unit Weight of Water

    In view of the fact that the site might be flooded or due to effects of future

    rise in the groundwater table use of buoyant unit weight is recommended

    for design purposes.

    6.2 SHEAR STRENGTH PARAMETERS

    The angle of internal friction applicable to the sub-soil layers encountered

    at site has been estimated on the basis of N-values determined through

    performance of SPTs at different locations in the area and at different

    horizons within the layer. Most of the N-values determined in the subsoil

  • 7/25/2019 Geo Tech Natural Gas

    11/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 10

    fall in the range of to 22 blows/12 Inch. Corresponding to these values, a

    value of 29.2 to 32.3 degrees is considered applicable to the sub-strata.

    Conservative value of = 24 degrees has been adopted for calculation

    purposes.

    In case of select fill, the angle of internal friction should be taken as 32

    degrees.

    6.3 MODULUS OF ELASTICITY (Es)

    The immediate settlement of foundation depends upon the elastic

    properties of the load bearing strata, characterised by Modulus of Elasticity

    (Es). The Modulus of Elasticity of soils is directly proportional to N-values

    recorded in SPTs. The constant of proportionality depends upon the type of

    soils in which the tests are carried out. For the strata, encountered in this

    particular investigation, following relationship between Es and N-values

    was used for calculation of immediate settlement:

    Es= 500 (N + 15), kPa SAND layer

    Es= (500 ~ 1,000), Su Clay layer

    The above expression can also be used for select fill and N should be taken

    as 15 in case select fill.

    6.4 SELECTION OF FOUNDATION TYPE

    Considering the anticipated structural loads and the load carrying

    characteristics of the sub-soil strata at the site, Spread Footing/Mat footing

    is considered technically feasible for the proposed Structures.

    6.5 DEPTH OF FOUNDATION

    All foundations must be laid at a safe depth that is free from the influence of

    seasonal, climatic and environmental changes. Such safe depth must ensure

    foundation safety and stability form the effects of wind erosion and erosion

  • 7/25/2019 Geo Tech Natural Gas

    12/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 11

    from surface run off. At the same time all foundations must be placed on

    firm natural soil after removing any loose or undesirable soil. The

    recommended minimum foundation depth for Spread footing/Mat footing

    for the proposed structure is 3~5 feet measured from the existing ground

    level.

    Any loose and undesirable soil layer, if encountered during the excavation

    for the foundations shall be replaced with structural backfill, rock fill or

    lean concrete.

    6.6 ALLOWABLE BEARING PRESSURES

    The allowable bearing pressure for the design of foundations must not

    exceed the allowable bearing capacity of the load carrying soil with respect

    to shear failure. At the same time the settlement corresponding to the

    allowable bearing pressure must not exceed the maximum allowable limit

    of settlement for the particular foundation / structure system. In the

    present case it is the allowable settlement criteria and not the shear failure

    which will determine the allowable bearing pressure for design of

    foundations.

  • 7/25/2019 Geo Tech Natural Gas

    13/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 12

    Allowable Bearing Capacity (qall) for Spread Footings(Near Railway Track Change=14 +275)

    Depth ofFoundation (ft)

    Width ofFoundation (ft)

    SBC(ton/ft)

    Settlement(mm)

    2.5 4.0 0.53 13.52.5 5.0 0.61 23.02.5 6.0 0.75 25.134

    Qult = cNc Sc + y DfNqSq+0.5yBNySyQall = Qult/FOS

    Note:1. The calculations, presented above, are based on Terzaghis Bearing Capacity

    equation.

    2. The value of Ng ,Nq ,Nc in the formula was taken by (Vesic)

    3. The value of Ng ,Nq ,Nc in the formula was taken by (Vesic)

    4. Factor of Safety of 3 has been considered for the calculations above.

    5. Settlement analysis have been made using Braja M. Das, (Principles of

    Geotechnical Engineering, 5th

    edition, 2002)

    Recommendations

    A. The tolerance of structures to settlement is function of type and size of

    foundations.

    The allowable total settlement for such structures as reported in the literature

    Terzaghis Criteria of 25mm,which is considered maximum limit of the settlement

    tolerable for spread/isolated footing.

    B. Based on the project subsurface soil condition and bearing capacity analysisperformed, the recommended Allowable bearing capacity is restricted up to0.51 ton/ft based on the allowable settlement criteria.

    C.Note

    The Road Base layer should be of 0.25 m thickness each and compacted by avibrator system to achieve 95 % Modified proctor.

    The degree of Compaction should be confirmed by In-situ Density tests.

    Ground at foundation level should be properly compacted prior to laying of

    structural fill.

  • 7/25/2019 Geo Tech Natural Gas

    14/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 13

    Allowable Bearing Capacity (qall) for Spread Footings

    (Near Masu Wah canal Change=13 +650)

    Depth ofFoundation (ft)

    Width ofFoundation (ft)

    SBC(ton/ft)

    Settlement(mm)

    4.5 4.0 0.51 17.54.5 5.0 0.61 25.04.5 6.0 0.75 27.11

    Qult = cNc Sc + y DfNqSq+0.5yBNySyQall = Qult/FOS

    Note:

    6. The calculations, presented above, are based on Terzaghis Bearing Capacity

    equation.

    7. The value of Ng ,Nq ,Nc in the formula was taken by (Vesic)8. The value of Ng ,Nq ,Nc in the formula was taken by (Vesic)

    9. Factor of Safety of 3 has been considered for the calculations above.

    10.Settlement analysis have been made using Braja M. Das, (Principles of

    Geotechnical Engineering, 5th

    edition, 2002)

    Recommendations

    B. The tolerance of structures to settlement is function of type and size of

    foundations.

    The allowable total settlement for such structures as reported in the literature

    Terzaghis Criteria of 25mm, which is considered maximum limit ofthe settlement

    tolerable for spread/isolated footing.

    B. Based on the project subsurface soil condition and bearing capacity analysisperformed, the recommended Allowable bearing capacity is restricted up to0.61 ton/ft based on the allowable settlement criteria.

    C.Note

    The Road Base layer should be of 0.25 m thickness each and compacted by a

    vibrator system to achieve 95 % Modified proctor.

    The degree of Compaction should be confirmed by In-situ Density tests. Ground at foundation level should be properly compacted prior to laying of

    structural fill.

  • 7/25/2019 Geo Tech Natural Gas

    15/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 14

    Allowable Bearing Capacity (qall) for Spread Footings

    (Near Canal road crossing Kandyaro Change=10 +775)

    Depth ofFoundation (ft)

    Width ofFoundation (ft)

    SBC(ton/ft)

    ImmediateSettlement

    (mm)4 4.0 0.73 11.54 5.0 0.85 17.04 6.0 1.05 26.13

    Qult = cNc Sc + y DfNqSq+0.5yBNySyQall = Qult/FOS

    Note:

    11.The calculations, presented above, are based on Terzaghis Bearing Capacity

    equation.12.The value of Ng ,Nq ,Nc in the formula was taken by (Vesic)

    13.The value of Ng ,Nq ,Nc in the formula was taken by (Vesic)

    14.Factor of Safety of 3 has been considered for the calculations above.

    15.Settlement analysis have been made using Braja M. Das, (Principles of

    Geotechnical Engineering, 5th

    edition, 2002)

    Recommendations

    C. The tolerance of structures to settlement is function of type and size of

    foundations.

    The allowable total settlement for such structures as reported in the literature

    Terzaghis Criteria of 25mm, which is considered maximum limit of the settlementtolerable for spread/isolated footing.

    B. Based on the project subsurface soil condition and bearing capacity analysisperformed, the recommended Allowable bearing capacity is restricted up to0.78 ton/ft based on the allowable settlement criteria.

    C.Note

    The Road Base layer should be of 0.25 m thickness each and compacted by a

    vibrator system to achieve 95 % Modified proctor.

    The degree of Compaction should be confirmed by In-situ Density tests.

    Ground at foundation level should be properly compacted prior to laying of

    structural fill.

  • 7/25/2019 Geo Tech Natural Gas

    16/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 15

    Allowable Bearing Capacity (qall) for Spread Footings

    (Near Dher Wah Lower, Change=6 +825)

    Depth ofFoundation (ft)

    Width ofFoundation (ft)

    SBC(ton/ft)

    Settlement(mm)

    5.0 4.0 0.63 18.55.0 5.0 0.71 24.19665.0 6.0 0.85 29.4

    Qult = cNc Sc + y DfNqSq+0.5yBNySyQall = Qult/FOS

    Note:

    16.The calculations, presented above, are based on Terzaghis Bearing Capacity

    equation.17.The value of Ng ,Nq ,Nc in the formula was taken by (Vesic)

    18.The value of Ng ,Nq ,Nc in the formula was taken by (Vesic)

    19.Factor of Safety of 3 has been considered for the calculations above.

    20.Settlement analysis have been made using Braja M. Das, (Principles of

    Geotechnical Engineering, 5th

    edition, 2002)

    Recommendations

    D. The tolerance of structures to settlement is function of type and size of

    foundations.

    The allowable total settlement for such structures as reported in the literature

    Terzaghis Criteria of 25mm, which is considered maximum limit of the settlementtolerable for spread/isolated footing.

    B. Based on the project subsurface soil condition and bearing capacity analysisperformed, the recommended Allowable bearing capacity is restricted up to0.70 ton/ft based on the allowable settlement criteria.

    C.Note

    The Road Base layer should be of 0.25 m thickness each and compacted by a

    vibrator system to achieve 95 % Modified proctor. The degree of Compaction should be confirmed by In-situ Density tests.

    Ground at foundation level should be properly compacted prior to laying of

    structural fill.

  • 7/25/2019 Geo Tech Natural Gas

    17/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 16

    Allowable Bearing Capacity (qall) for Spread Footings

    (Near Narli Wah Canal Change=1 +080

    Near Mari Mani Fold ,Change 0+100)

    Depth ofFoundation (ft)

    Width ofFoundation (ft)

    SBC(ton/ft)

    ImmediateSettlement

    (mm)3 4.0 0.73 11.53 5.0 0.81 17.03 6.0 0.95 26.

    Qult = cNc Sc + y DfNqSq+0.5yBNySyQall = Qult/FOS

    Note:

    21.The calculations, presented above, are based on Terzaghis Bearing Capacity

    equation.

    22.The value of Ng ,Nq ,Nc in the formula was taken by (Vesic)

    23.The value of Ng ,Nq ,Nc in the formula was taken by (Vesic)

    24.Factor of Safety of 3 has been considered for the calculations above.

    25.Settlement analysis have been made using Braja M. Das, (Principles of

    Geotechnical Engineering, 5th

    edition, 2002)

    Recommendations

    E. The tolerance of structures to settlement is function of type and size of

    foundations.

    The allowable total settlement for such structures as reported in the literatureTerzaghis Criteria of 25mm, which is considered maximum limit of the settlement

    tolerable for spread/isolated footing.

    B. Based on the project subsurface soil condition and bearing capacity analysisperformed, the recommended Allowable bearing capacity is restricted up to0.80 ton/ft based on the allowable settlement criteria.

    C.Note

    The Road Base layer should be of 0.25 m thickness each and compacted by a

    vibrator system to achieve 95 % Modified proctor.

    The degree of Compaction should be confirmed by In-situ Density tests.

    Ground at foundation level should be properly compacted prior to laying of

    structural fill

    For & on Behalf of Geo Drillers Engineering

  • 7/25/2019 Geo Tech Natural Gas

    18/18

    Geo Drillers Engineering (GDE)

    Natural Gas Pipeline 16 inch diaNo. 17

    IN-Situ Testing on Proposed Site for Natural gas Pipeline