Generator Application and Sizing By: Arnie De Guzman.

39
nerator Application and Sizi By: Arnie De Guzman

Transcript of Generator Application and Sizing By: Arnie De Guzman.

Page 1: Generator Application and Sizing By: Arnie De Guzman.

Generator Application and Sizing

By: Arnie De Guzman

Page 2: Generator Application and Sizing By: Arnie De Guzman.

Generator Duty Cycle/Application

• Power rating - The power of the generating set is the power output available for consumer loads at the generating set terminals excluding the electrical power absorbed by the essential independent auxiliaries.

Page 3: Generator Application and Sizing By: Arnie De Guzman.

Limited-Time running Power(LTP)

• Limited-time running power is defined as the maximum power available, under the agreed operating conditions, for which the generating set is capable of delivering for up to 500 h of operation per year.

Page 4: Generator Application and Sizing By: Arnie De Guzman.

Emergency Standby Power (ESP)

• Typical usage of 50 hours per year with a maximum of 200 hours per year with varying loads. Average variable load factor is 70% of ESP rating. Emergency standby power is the maximum power available during a variable load sequence in the event of a utility power outage or under test conditions for up to 200 hours a year while maintaining per the manufacturer’s specified intervals. The permissible average power output over a 24 hour period shall not exceed 70% of the ESP rating.

• No overload is available. • Not for maintained utility paralleling applications.

Page 5: Generator Application and Sizing By: Arnie De Guzman.

Standby Power (CAT)

• Typical usage 200 hours per year, with a maximum of 500 hours per year with varying loads. Average variable load factor is 70% of Standby rating.

• No overload is available. • Not for maintained utility paralleling applications.

Page 6: Generator Application and Sizing By: Arnie De Guzman.

Prime Power (PRP)

• Unlimited hours of usage. Average variable load factor is 70% of the Prime power rating. 10% overload No overload is available limited to 1 in 12 hours but not to exceed 25 hours per year. The 10% overload is available in accordance with ISO 3046-1 (2002). Life to overhaul of the engine is dependent on operation as outlined in ISO8528 (2005) and time spent operating above the rating guidelines will reduce the hours to engine overhaul.

Page 7: Generator Application and Sizing By: Arnie De Guzman.

Continuous Power (COP)

• Unlimited hours of usage. Non-varying load factor is 70% to 100% of the published Continuous Power. Typical peak demand is 100% of continuous rating for 100% of operating hours.

Page 8: Generator Application and Sizing By: Arnie De Guzman.

Load Factor

• Load factor of a generator set is used as one criterion for rating a genset. It is calculated by finding the product of various loads:

% time x % load

Page 9: Generator Application and Sizing By: Arnie De Guzman.

Example

• For example, assume a facility has a genset rated at 1056 kW and runs it two ours a week. During those two hours, it runs at 950 kW for 1.5 hours. Find the load factor.

0.90 x 0.75= 67.5%

Page 10: Generator Application and Sizing By: Arnie De Guzman.

Mode of Operation

• Island Mode• Grid Mode• Back Synchronization

Page 11: Generator Application and Sizing By: Arnie De Guzman.

• t = time• P = power• a = Emergency Standby

Power or Prime Power• b = Permissible Average

Power output in 24hrperiod(Ppp)

• c = Actual Average Power in (Ppa)24hr period

• d = stop

Page 12: Generator Application and Sizing By: Arnie De Guzman.

Sample Scenario

• We are operating 3 x 9 MW, 6 kV, 50 Hz gas turbines as part of Utilities power house of a large fertilizer complex which has a total load of 22 MW (mostly large induction motors) The power house is not connected with the public utility, i.e., we are operating our power house in an island mode. At the power house, we also have a load shedding system. In case any gas turbine trips, this load shedding system sheds the fertilizer plant load to bring the total load within the capacity of remaining gas turbine(s). The load shedding system actuates instantly on detection of either turbine trip signal or generator circuit breaker opening. All the gas turbines are being operated in droop mode (droop= 4 %).

Page 13: Generator Application and Sizing By: Arnie De Guzman.

Sample Scenario• We are operating 3 x 9 MW, 6 kV, 50 Hz gas turbines as part

of Utilities power house of a large fertilizer complex which has a total load of 22 MW (mostly large induction motors) The power house is not connected with the public utility, i.e., we are operating our power house in an island mode. At the power house, we also have a load shedding system. In case any gas turbine trips, this load shedding system sheds the fertilizer plant load to bring the total load within the capacity of remaining gas turbine(s). The load shedding system actuates instantly on detection of either turbine trip signal or generator circuit breaker opening. All the gas turbines are being operated in droop mode (droop= 4 %).

Page 14: Generator Application and Sizing By: Arnie De Guzman.

Sample Scenario• On March 14, 2011, only two gas turbines were running

normal (in droop mode) with a plant load of 15 MW. One of the gas turbines tripped on failure of turbine enclosure pressure (which occurred during ventilation fan changeover activity). Tripping of one gas turbine was followed by instant load shedding. However, the 2nd gas turbine also tripped (on generator over-frequency) resulting in total power failure. The plant management afterwards decided to always run all three gas turbines whenever the fertilizer complex total load exceeded 15 MW. The generator under frequency/over-frequency trip settings were: Under-Freq=49,0 Hz / 2.0 s, Over-Freq=51.0 Hz / 0.5 s. power failure.

Page 15: Generator Application and Sizing By: Arnie De Guzman.

Sample Scenario

• On May 10, 2011, we were operating all three gas turbines (in droop mode) with a plant load of 21 MW. Tripping of one gas turbine (on actuation of a gas detector installed in the turbine enclosure) was followed by load shedding and the remaining two gas turbines remained stable, i.e., saved power failure.

Page 16: Generator Application and Sizing By: Arnie De Guzman.

Sample Scenario

• In July 2011, the under-frequency/over-frequency trip settings of the generator were revised to have a wide band in frequency. The revised settings are: Under-Freq=47.5 Hz / 2.0 s, Over-Freq = 52.5 Hz / 3.0 s.Now referring back to the incident of March 14, 2011, the investigation team has recommended to run at least one gas turbine in Isochronous mode to prevent total power failures. You are requested to comment on whether switching one gas turbine to Isochronous mode (while the other machines shall remain in droop mode) shall help in preventing blackouts in case any gas turbine trips.

Page 17: Generator Application and Sizing By: Arnie De Guzman.

Sample Scenario

• In continuation of the above:Suppose a situation when plant total load is 20 MW with following distribution: GT1 (Isochronous mode)=4 MW, GT2 (Droop mode)= 8 MW, GT3 (Droop mode)=8 MW and without any gas turbine tripping, a big block of load like 8 MW is shed (for example, due to a feeder tripping). What would be the response of Isochronous machine in this case? Will it go into reverse power in an attempt to maintain bus frequency? Please keep in mind that there is no communication link between the three turbines for load sharing and the power house is in island mode (i.e., not connected with public utility).

Page 18: Generator Application and Sizing By: Arnie De Guzman.

De-rate factor and Ambient Condition

• Site conditions and power requirements will also play a key role in generator selection. Careful consideration must be given to the environment that the package will be operating in.

Page 19: Generator Application and Sizing By: Arnie De Guzman.

Voltage

• Voltage plays a key role in generator rating and must be considered. In some cases, generator voltage will not match the preferred operating voltage. A voltage regulator can provide voltage adjustment capability, however, when “dialing down” generator voltage, the current will increase for a given rating. This will increase generator heat and may require generator derating. An alternative to generator derating is to use a larger generator to maintain the standard rating. The standard set by NEMA allows a generator to be adjusted up or down by five percent (― 5%) as installed.

Page 20: Generator Application and Sizing By: Arnie De Guzman.

Environmental Condition

• Altitude and temperature most heavily influence engine ratings.

• The higher the altitude, the lower the air density. Clean dense air is needed for efficient combustion.

• Likewise, an increase in temperature lowers air density.

Page 21: Generator Application and Sizing By: Arnie De Guzman.

Sample altitude/temperature derate curveSource: http://www.cummins.co.kr/new/images/product/ndata/C1250D6/3.%20fr6250.pdf

Page 22: Generator Application and Sizing By: Arnie De Guzman.

Specifications Required

• Voltage • Frequency• Fuel Type• Installation type• Application• Duty Cycle• Phase

• Island• Grid• Sycnhronised• Peak Shaving• Peak Lopping• Motor Starting

Page 23: Generator Application and Sizing By: Arnie De Guzman.

The Load

Considerations• Type of load in terms of application.• PF to be maintained.• Voltage Dip Consideration

Page 24: Generator Application and Sizing By: Arnie De Guzman.

Type of Loads

• Single-phase loads and load imbalance: Single phase loads should be distributed as evenly as possible between the three phases of a three-phase generator set in order to fully utilize generator set capacity and limit voltage imbalance.

• Peak loads: Peak loads are caused by loads that cycle on and off—such as welding equipment, medical imaging equipment, or motors. Taking cyclic loads into account can significantly increase the size of the recommended generator set despite painstaking efforts to place loads in a step starting sequence.

Page 25: Generator Application and Sizing By: Arnie De Guzman.

Type of Loads

• Motor loads: Calculating specific motor loads is best handled by sizing software which will convert types of motors into load starting and running requirements.

• None-Linear Loads: Due to harmonics caused by electronic rectifiers, larger alternators are required to prevent overheating and to limit system voltage distortion by lowering alternator reactance.

Page 26: Generator Application and Sizing By: Arnie De Guzman.

Type of Load• Lighting loads: In addition to lamp wattages, ballast wattages and

starting and running power factors should be considered.• Regenerative loads: For loads such as elevators, cranes and

hoists, the power source is often relied upon for absorbing power during braking. That is usually not a problem when the utility is supplying power because it can be considered as an infinite power source with many loads. A generator set, in comparison, is able to absorb far less power, especially with no other loads connected. Generally, the regeneration problem can be solved by making sure there are other connected loads which can absorb the regenerative power. Excessive regenerative load can cause a generator set to over-speed and shut down.

Page 27: Generator Application and Sizing By: Arnie De Guzman.

Voltage Dip Calculation• Here are some reasons why voltage dip calculation is

important; 1. Flickering Light - The human eye is sensitive to slight lighting

fluctuations. Even a decrease of 1/2 volt on a 110 volt incandescent bulb is noticeable. A one volt dip, if repeated, becomes objectionable.

2. Medical Imaging Equipment – to maintain high quality imaging, the voltage dip is limited to 10%.

3. Equipment Undervoltage protection may trip4. Motors to be started may not start as torque is proportional

to voltage, induced motors typically designed to start at terminal voltage >80%

Page 28: Generator Application and Sizing By: Arnie De Guzman.

Why do the calculation?

• This calculation is more or less done to verify that the largest motor does not cause system wide problems upon starting. Therefore it should be done after preliminary system design is complete.

Page 29: Generator Application and Sizing By: Arnie De Guzman.

G1

M1

S1

S2

Tx1

C1

C2 C3

11kV Bus

0.4kV Bus

Sg1 = 4000kVAVg1 = 11,000VX’d = 0.33pucos ᶿ = 0.85Size = 500mm2

Length = 50mR = 0.0522 Ω/kmX = 0.0826 Ω/km

Size = 35mm2

Length = 150mR = 0.668 Ω/kmX = 0.115 Ω/km

SS1 = 950kVAVg1 = 11,000Vcos ᶿ = 0.84

PM1 = 250kWVg1 = 11,000VILRC = 106.7 AILRC/ IFLC = 6.5pucos ᶿm = 0.85cos ᶿs = 0.30

Size = 120mm2

Length = 60m R = 0.196 Ω/kmX = 0.096Ω/km

STx1 = 1600kVVt1 = 11,000VVt2 = 400VUk = 0.06puPkt = 12700Wtap= 0.0%

SS1 = 600kVAVg1 = 400Vcos ᶿ = 0.80

Step 1.

Page 30: Generator Application and Sizing By: Arnie De Guzman.

G1

C1

Sg1 = 4000kVAVg1 = 11,000VX’d = 0.33pucos ᶿ = 0.85

Calculate all ImpedancesStep 2.

Synchronous Generator Impedance G1

Page 31: Generator Application and Sizing By: Arnie De Guzman.

G1

C1

Sg1 = 4000kVAVg1 = 11,000VX’d = 0.33pucos ᶿ = 0.85Size = 500mm2

Length = 50mR = 0.0522 Ω/kmX = 0.0826 Ω/km

Cable Impedances C1,C2,C3

Page 32: Generator Application and Sizing By: Arnie De Guzman.

Transformer Impedances TX1

Tx1

C3

0.4kV Bus

11kV Bus

STx1 = 1600kVVt1 = 11,000VVt2 = 400VUk = 0.06puPkt = 12700Wtap= 0.0%

Page 33: Generator Application and Sizing By: Arnie De Guzman.

S1

11kV Bus Base Load Impedances S1,S2

S2

0.4kV Bus

SS1 = 600kVAVg1 = 400Vcos ᶿ = 0.80

SS1 = 950kVAVg1 = 11,000Vcos ᶿ = 0.84

Page 34: Generator Application and Sizing By: Arnie De Guzman.

Motor Impedances M1

M1

C2

Page 35: Generator Application and Sizing By: Arnie De Guzman.

Computed Impedances

Page 36: Generator Application and Sizing By: Arnie De Guzman.

Referring the LV Impedances to HV side

415V Standing Load Referred to 11kV Impedance

R = 161.33333 Ω and X = 121.00 Ω.

Step 3.

Page 37: Generator Application and Sizing By: Arnie De Guzman.

G1

Zg1

ZC1

ZS1

ZC2

ZM1

ZTX1

ZS2

11kVBus

0.4kVBus

ZC3

G1

Zg1

ZEq

PCC

Step 4.

Equivalent Circuit

Page 38: Generator Application and Sizing By: Arnie De Guzman.

Step 5.

Calculate Initial Source Voltage

G1

Zg1

ZC1

ZS1

ZTX1

ZS2

11kVBus

0.4kVBus

ZC3

Motornotconnected

Page 39: Generator Application and Sizing By: Arnie De Guzman.

Step 6.

Calculate Voltage Dip during stating