FULL-SCALE VEHICLE CRASH TEST ON NEBRASKA BRIDGE …The test vehicle was a 1982 Honda Civic 3-door...
Transcript of FULL-SCALE VEHICLE CRASH TEST ON NEBRASKA BRIDGE …The test vehicle was a 1982 Honda Civic 3-door...
-
FULL-SCALE VEHICLE CRASH TEST ON NEBRASKA BRIDGE RAIL BARRIER
WITH A MODIFIED NEW JERSEY SHAPE
by
Mr. John A. Magdaleno, E.LT. Graduate Research Assistant
Mr. Ronald K. Faller, E.I.T. Dr. Edward R. Post, P.E. Graduate Research Assistant Professor of Civil Engineering
Sponsored by
Nebraska Department 01 Roads RES1 (0099)P426
Transportation Research Report TRP..{)3..()l6-as
CIVIL ENGINEERING DEPARTMENT W348 NEBRASKA HALL
UNIVERSITY OF NEBRASKA--lINCOLN LINCOLN, NEBRASKA 68568-0531
(402) 472-2371
March 1989
-
ABSTRACT
The New Jersey Shape Ba~rier is one of the most popular
shaped concrete barriers implemented today on American highways.
Previous tests using this barrier have shown that it is worthy of
being a standard for bridge rail barriers on an international
level. This investigation was an attempt to modify the New
Jersey Shape Barrier by increasing the 3 inch initial step to 4
1 /2 :'nches. This extra 1 1 /2 inches would allow more of an
ehposed vertical face which is beneficial in applying future deck
ove rlays. To determine whether or not this modification was
acceptable, a full-scale crash test was performed on the modified
bar r ier shape using an 1800 lb . 1982 Honda Civic at an impact
speed of 60 mph and an impact angle of 20 degrees. The test
results showed that a minicompact sedan, such as the 1982 Honda
Civic, would likely roll under theSE test conditions and barrier
modifications.
-
List of Tables ..... .
List o f Figures
Acknowledgements
Introduction ... .
TABLE OF CONTENTS
. ....... .. ..... . ... . . . . . . . . . . . . . . . . . . ... . ... . . .. . ... . .. . . . . ... . . ................................
Page
ii
iii
iv
1
A. Problem Statement ....•... •. . . .•. ........ .. • . . ..•.... 1
B. Objective ...
C. Goals
Technical Discussion
A. Test Conditi ons
A. l. Test Facility .....
h.2. Test Article
A.3. Test Vehicle
...................
A.4. Data Acquisition Systems ........ .
A. 5 . Tes't Parame'ters ..... . ......... .
A. 6 . Performance Evalua'tion Criteria
B. Test Results ....................... .
Conclusions . . .
References
Appendices
...............
h. Test Facili'ty .
B. Data Acquisition Systems.
C . Graphs o f Accelerome ter Data
i
............ . .. . ........
2
3
4
4
4
4
11
14
15
16
1 7
25
29
30
31
3 8
47
-
LIST OF TABLES
Page
1. Crash Test Conditions 19
2 . NCHRP 230 Criteria f or Evaluating
Bridge Rail Crash Tests ..... ... .... ... ..... . .•• . . •• . ... 27
3. AASHTO Criteria for Evaluating
Bridge Rail Crash Tests ........... .. . ... . . . . . • . . . ... . .. 28
11
-
LIST OF FIGURES
1. 10 ft. Precast New Jersey Concrete Barrier Section
2. NDOR Bridge Rail Barrier
3. Sche~atic of Rigid Steel Frame Backup System ... ... ..... .
4. Photographs of Rigid Steel Frame Backup System .... .• . . ..
5. Surrogate NDOR Bridge Rail Barrier .................• ....
6. Test Vehicle Weights and Dimensions ............ • .... ....
7. Photographs of Test Vehicle ..................... .. ......
8. Test Results and Sequential Photographs ..... ..• . ... • ... .
9. ?hotographs of Barrier Damage ......................... . .
Page
5
7
8
9
10
12
13
20
21
10. Vehicle Trajectory and Final Stopping Position .......... 22
11. Photographs of Test Vehicle Damage . . .. .......... .. ...... 23
12. Roll, Pitch, and Yaw of Test Vehicle .....• ... .... . .•.... 24
iii
-
ACKNOWLEDGEMENTS
The authors wish to express their appreciation and thanks to
the f o llowing people who made a contribution to the outcome o f
t his research project.
Nebraska Department of Roads
Dalyce Ronnau (Materials and Test Division - Research Engineer ) Leona Kolbet (Materials and Test Division - Research Coordinator ) Ge orge Woolstrum (Materials and Test Division
- Special Projects Engineer )
Federal Highway Administration
Milo Cress (Bridge Engineer-Lincoln Division Office ) Charles McDevitt (Project Manager and Research Structural
Engineer-Washington, D.C. Office of Research )
University of Nebraska-Lincoln
Eugene Matson (C.E. Research Technician ) James Dunlap (Photographic Productions Manager ) To~ Grady (E.E. Technician ) Gerald Fritz (Electronics Shop Manager ) Nichael Cacak (Automobile Support Services Manager ) Patrick Barrett (Automobile Support Services Assistant Manager ) William Kelly (Professor and C.E. Chairman) Ron Hoffman (University Maintenance Electrician ) Brian Pfeifer (M.E. Student ) Jim Holloway (C.E . Student ) Todd Noble (C.E. Student ) Virgil Oligmueller (C.E. Student > Mary Lou Tomka (C.E. Administrative Assistant) Narilyn Hues (C.E. Secretary ) Mary Lou Wegner (C.E. Secretary )
iv
-
INTRODUCTION
A. Proble~ Statement
Over the years, concrete safety shaped barriers have become
more and more familiar on American highways due to its
satisfactory performance in redirecting a vehicle; the most
popular being the New Jersey Shaped Barrier (NJ Barrier> The
Nebraska Department. of Roads (NDOR) has designed a bridge rail
that uses the general shape of the NJ Barrier face; however, one
modification was made to the barrier face. HDOR has increased
the 3-in. initial step to 4 1 / 2-in. The modification stemmed
from a desire to increase the initial step of the barrier since
the step provides a complementary edge for future deck overlays.
The problem wi th increasing the ini tial step is tha t the
slope break point of the barrier face is also raised 1 1 / 2-in. to
a height of 14 1 /2-in . above the road surface. The slope break
point is the point o f intersection between the two sloped
surfaces of the barrier face and has been found to be the key
parameter in vehicle rollover potential. One purpose of the
lower sloped surface of any safety shaped barrier is to lift the
vehicle just enough to reduce the friction between the tires of
the vehicle and the road surface.
of the vehicle by the barrier.
This allows easier redirection
However, too much lift of the
vehicle can cause a hazard in vehicle rollover potential . Thus ,
keeping the slope break point to a minimum height is imperative .
1
-
This problem has also been a concern of others such as the
Department of the Environment (DO E ) or of the Department of
Transport (DOT) in Crow thorn , Berkshire; England. The Transport
and Road Research Laboratory (TRRL) has already conducted a test
for t.he DOE and DOT in England on a barrier similar to the NJ
Barrier, but having a 6-in. initial step instead of a 3-in. step
which raised the slope break point of the barrier to a height of
l6-in. above the road surface (1). The test conducted by TRRL
was unsatisfactory because of vehicle r ollover. Because of the
unsatisfactory performance of the barrier in Europe , the Federal
Highway Administration (FHWA) and NDOR were concerned about the
vehicle rollover potential of the NDOR Bridge Rail Barrier due to
the 14 1 / 2-in. height o f the slope break point.
B. Objective
The primary objective of this study was to test the
modification of increasing the height of the slope break point
on the NJ Barrier face to 14 1 / 2-in. and to evaluate the results.
Testing procedures and evaluation of the results were to be in
accordance with the saftey performance criteria inferred from the
"Recommended Procedures for the Safety Performance Evaluation of
Highway Appurtenances" by the National Cooperative Highway
Research Program Report 230 (NCHRP 230) (~), and the "Standard
Specifications for Highway Bridges" by the American Association
of State Highway and Transportation Officials (AASHTO) (~) .
2
-
J
C. Goals
Goals for this test are (1) that the vehicle should be
smoo'thly redirec'ted, (2) that the vehicle shall remain upright
throughout the collision, and (3) its after-collision trajectory
should not present undue hazard to other traffic.
As stated in NCHRP 230 and AASHTO, "Keeping vehicles upright
during all crash tests is a worthy goal as occupant risks are
generally more severe and less predictable in vehicle rollover."
3
-
TECHNICAL DISCUSS I ON
A. Test Conditions
A.l Test Facility
The test site facility where the full-scale vehicle
crash testing is conducted is located approximately 7 miles
northwest from the University at the Lincoln Municipal Airport on
the northwest end of the west apron. Appendix A expl ains the
facility in greater detail and shows the guidance and towing
methods used.
A.2 Test Article
It was decided by NDOR and the FHWA that since the
barrier to be tested was similar to the New Jersey Safety Shape,
that 10 ft. precast sections of temporary New Jersey Concrete
Barrier, shown in Figure 1, could be used as a surrogate for the
NDOR Bridge Rail Barrier as long as certain requirements were
met . The first requirement was that the dimensions of the face
for the precast barrier sections be made identical to that of
NDOR's bridge barrier shown in Figure 2. This only called for
elevating the precast barrier sections 1 1/2-in . above the road
surface so that the initial step of the barr i er would be 4 1 / 2-
in. instead of 3-in. No other change in the dimensions of the
precast barrier sections were necessary since elevating
4
-
, •
'\ r- 24"-1
A-A
FIGURE 1 .
I • -0 f--19 0
I I 10" - f--• I
" L..A ~ , 10 10 ft. Precast New Jersey Concrete Barrier Section
them 1 1/2-in. made all face dimensions between the precast
sect ion barriers and the NDOR Bridge Rail Barrier identical. The
second requirement was that the precast barrier sections be
reinforced on the opposite side of impact with a rigid steel
frame backup system to provide lateral support for the barrier.
This was imperative so that the section barri.:rs would not
deflect in any way, simulating the NDOR Bridge Rail Barrier.
Figure 3 shows the reinforcement details used in making the
precast barrier sections rigid while Figure 4 shows the rigid
steel frame backup system in place behind the precasted barriers.
Using the 10 ft: precasted sections of barri er instead of
constructing an actual bridge rail barrier, as well as the bridge
deck , was a significant savings in co nducting the full - scale
crash test. The barrier was 100 ft. long (ten 10 ft . precasted
barrier sections) and was elevated to the desired height by
setting the barrier sections on constructed wooden pallets that
were 1 1/2-in. thick. Thre e vertical joints between the 10 ft.
5
-
barrier sections were grouted near the point of impact to provide
a smooth transi tion for an impacting vehicle, as would be with
the NDOR Bridge Rail Barrier . The grouted vertical joints were
the vertical joint upstream from the point of impact and the next
two downstream; all other vertical joints were not grouted
because of the anticipated duration of time that the vehicle
would be in contact with the barrier . The barrier system was
also grouted underneath the precast barriers at impact to give a
uniform initial step near the area of impact. Photographs of the
grouted surrogate NDOR Bridge Rail Barrier are shown in Figure 5.
6
-
'-3" Gutter Une
7" 2',' 6"
.... -~~
~ I
t • , ~ ...
~ ......
• '"S ~ ~-~~ ~ 0) ,
::fn.' £I] F ~ Q "-, mn [Ij
• ~---_IJ
___ -.;r- (-
----•
). }i\ • ~ •
Center of .81 ft. GravIty
"*" C oomfer /J 17 rryplco
No.4 Bar * s at 15" rna x. I~' CI.m.1n.
No.5 at 15"
Bors* max.
FIGURE 2. NCOR Bridge Rail Barrier
7
-
1'95" 9 "BOLT 1~"¢x I2 "BOLT --------~,
2-SPAC£RS 3 "" ~" ,
" 3 I,D. PIPE 1/ II S/ /1
2 - TS 5 ,, 3x / /1.
I 1/ /I 3-1/2 r/>x 6 BOLTS ---"
2 -BA RS 4"" I " --_____ ---,
:~J
II "j ll 2-TS 3,,2,,)4
H
.~-H"' "'i'----..., I I
",..+0/0 S;!'"""..s50-.. J
2 "
\
11 I
" ,I r'-/----l-2/~-~" ~ " II ~~ - -khf----+----;--:-.;;;----j..=±'~' -+--
" 1/+ ¢x 12"BOLT
2 -SPAC E_R-"S=-3,","X_I __ ~ _______ ---f,..~,'1~~:a-+ -~- , __ ~ _ ,t!!'i , __ ~ ~ +12" 'I: PL ?/~ J2/~ ~ " ~~ L ~L6/~4~ %" C;j
NOTES, ~ 4 -%"Jlfx 3 H BOLTS "'f/ ANCHORS I, STRUCTURAL TUBI NG - TS
2. PLATE - PL SCALE: ( = /0 " FIGURE 3. Schematic of Rigid Steel Frame Backup System
-
FIGURE 4. Photographs of the Rigid Steel Frame Backup System
9
-
FIGURE 5. Surrogate NDOR Bridge Rail Barrier
10
-
h.3 Test Vehicle
The test vehicle was a 1982 Honda Civic 3-door weighing
approximately 1800 lbs. The vehicle's dimensions and relative
weights are shown in Figure 6, while photographs of the test
vehicle are shown in Figure 7 . The test vehicle was prepared for
testing by removing such articles as the driver's seat, rear seat
(f ront passenger seat was left in the vehicle for anthropomorphic
dummy), and the spare tire and rim in order to get the desired
weight recomreended by the NCHRP Report 230 (£) guidelines for a
1800 lb. minicompact sedan. The vehicle was instrumented with
two triaxial accelerometer units , brake system, anthropormorphic
dummy, and an FH multiplexer. Camera targets and flashbulbs were
also positioned on the vehicle to aid in the high-speed film
analysis. This instrumentation and high-speed film analysis is
explained in greater detail in Appendix B.
The front wheels of the vehicle were aligned to a toe-in
valUE of zero-zero so that the vehicle would track properly along
the guide cable .
11
-
I
• p "heel base
Tiro db ___ +.....;rL+_
\/h .. 1 db ----h-----"-tt--
b
'v.. I
Geometry - I in. ) a. 62 . 2 d. 53 . 2 b. 29.5 e . 28 . 0 c. 88 . 6 t. 148.4
Test Mass - lb. Inert.ial
Ml l150 M2 650 MT 1800 h - (in . ) 33.0 9 - (in. ) 21. 5
---
.-h
•
f
g. 21. 5 1. 33.0 j. 18.0 n. 4.5 k . 21. 5 o. 10.0
Gross • Static • •
1965
* Ready for test but excludes passenger /cargo payload
p . r. s .
.* Gross ready for test including passenger/cargo payload
FIGURE 6. Test Vehicle Weights and Dimens ions
12
ct vehlc:1e
f d
53.5 14 . 2 22.6
-
FIGURE 7 . Photographs o f Test Vehicle
13
-
~.4 Data Acquisition Systems
The data acquisition systems used in the full-scale
crash tescing includes piezoresistive accelerometers, high-speed
ph o tography, and an electronic speed trap. The six
accelerometers placed in the test vehicle were used to measure
the longitudinal, lateral, and vertical accelerations of the
vehicle. One triaxial unit (three accelerometers ) was placed at
the center of gravity of the vehicle and the other triaxial unit
v,'as placed at a known distance from the C . G. Figures and
p:J.otographs of the accelerometer positions are included in
Appendix 8 where the data acquisition systems are explained in
greater detail.
The high-speed photography included three l6mm cameras that
ran at approximately 500 frames per second. The cameras were
st.rategically placed for analysis and documentation of the test
resl.!lts. Appendix B gives a more in-depth explanation o f the
camera positions as well as a schematic of the camera layouts .
A speed trap made of tape pressure switches was also used as
one source to determine the speed of the vehicle before and after
i:r:pact. Appendix B also explains the speed trap in greater
de-r.a il.
-
A.5 TesL Parameters
The full-scale crash test was conducted on Lhe Nebraska
Department of Roads Bridge Rail Barrier with a Modified New
Jersey Shape as men~ioned in part A. 2 of the Technical
Discussion. An 1800 lb. 1982 Honda Civic 3-Door impacted the
barrier at a target impact speed of 60 mph and a target impact
angle of 20 degrees.
The location of impact on the barrier was at a point 35 ft.
from the upstream end of the cons~ructed barrier. Since the main
concern of this test was the roll motion of the vehicle af~er
impact due to the critical inertial properties of the vehicle,
the veh i cle was impacted at the center of one of these 10 ft.
barrier sections. This insured that the vehicle trajectory was
caused solely by the interaction of the vehicle and the barrier
faCe; not by barrier deflection or vehicle snagging.
15
-
A.6 Performance Evaluation Criteria
The safety performance objective of a highway appurtenance
is to minimize the consequences of a vehicle leaving the roadway
to create an off-road incident. The safety goal is satisfactory
when the appurtenance smoothly redirects the vehicle away from
another hazardous situation wi thout subjecting the vehicle
occupants to forces which may produce major injury .
Because test conditions are sometimes difficult to control,
a co~posite tolerance limit, called the impact severity ( IS ), is
presented in the NCHRP Report 230 (~)
target and actual. are given in Table 1.
The IS values, both
The formula used t o
calculate impact severity is given as follows:
IS = ~m{vsine)2
where, m = vehicle test inertial mass (slugs)
v = impact velocity (fps)
e = impact angle (degrees)
Safety performance of a highway appurtenance cannot be
measured directly, but can be evaluated by three major factors
which are defined and explained by both NCHRP 230 (~) and hASHTO
( ~). The factors are: (l) structural adequacy , (2) occupant
risk, and (3) vehicle trajectory, A matrix of these factors for
both NCHRP 230 and ASSHTO are shown in Tables 2 and 3 in the
Conclusion of this report (pp . 26 and 27).
16
-
B. Test Results
A matrix of the crash test conditions is given in Table 1,
while a summary of the full-scale crash test is presented ~n
Figure 8.
Immediately after impact, the vehicle started to climb up
the face of the barrier, as shown from the tire marks in Figure
9, and became completely "air-born" at a time of approximately
0 . 142 seconds. A point marked on the rear part of the vehicle
and at the C.G. height of 21 1/2-in., showed that at that point,
the vehicle's maximum distance from the ground surface was
approximately 54 inches . After losing contact with the barrier,
the vehicle started a looping trajectory path back toward the
extended centerline of the barrier. Figure 10 shows a schematic
of the vehicle's trajectory as well as a photograph of the
vehicle's final stopping position which was 203 ft. downstream
from the point of impact. The vehicle started to roll at a time
of 1.82 seconds and was rolled over onto its roof at a time of
3.08 seconds when the brakes were applied in the vehicle.
Sequential photographs during the time when the vehicle was
in contact with the barrier are shown Figure 8. At a time of
O. 074 seconds, the anthropomorphic dummy in the vehicle breaks
the passenger door window. At 0.110 seconds, the damaged right
front end of the vehicle loses contact with the barrier and at
0.162.seconds, the vehicle is parallel with the barrier.
Finally, at 0 .270 seconds, the rear part of the vehicle loses
contact with the barrier.
17
-
Longitudinal and lateral accelerometer traces for the tes't
may be found in Appendix C. The accelerometer traces show the
deceleration of the vehicle, the vehicle change in velocity, and
the occupant displacement for both triaxial units. From this
data, one can find the occupant impact velocity and the average
10 millisecond occupant ridedown acceleration as presented in
Figure 8.
Photographs of the vehicle damage are shown in Figure 11,
while Figure 12 shows
vehicle after impact.
the roll, pitch, and yaw of the test
The damage of the vehicle was classified
according ~o the Traffic Accident Data (TAD) scale ( ! ) , and the
Vehicle Damage Index (VDl) scale (~). Classifications of the
vehicle damage are also presented in Figure 8 .
18
-
TARGET IMPACT TARGET nIP ACT EVALUATION
APPURTENANCE TEST VEHICLE SPEED ANGLE SEVERITY I '1 PACT pOIln CRITERIA
DESIGNATION TYPE (mph) (deg ) (ft-kips) (IICHRP 230)
Longitudinal Barrier
NOOR Bridge S13 1800 lb. 60 20 25 -2 , +4 35 f t. from A. O. E, F-H . I Rail Barrier ±50 upstream end
of barrier
TABLE 1. Crash Test Conditions
-
N o
0.270 s 0.162 s
Vehicle
TEST NO .............................. NDR-1 DATE . ............................. 9-20-88 INSTALLATION .. . ...... . MODIFIED NEW JERSEY
SECTION BARRIER LENGTH ... . .. . ............. 100 ft. VEHICLE
MODEL ............... 1982 HONDA CIVIC WEIGHT -
- TEST INERTIAL ...... 1800 lb. - DUMMY ............... 165 lb. - GROSS .............. 1965 lb.
SPEED (mph) IMPACT .............. 60.0, (88.0 fps) EXIT ....... . ........ 53.4, (78.4 fps)
0.110 s 0.074 5 Impact
VEHICLE REBOUND DISTANCE . .....•....... 15.0 ft. ANGLE (degrees)
IMPACT ..... . . . . . .. .. .... . ... . .• .. .... 20.9 EXIT ......... .. . .. .............. . . . . < 1.0
OCCUPANT IMPACT VELOCITY (fps) LONGITUDINAL ......................... 17.2 LATERAL .. .... ... .. .... . ...•.......... 17.2
OCCUPANT RIDEDOWN ACCELERATION (g's)
-
FIGURE 9. Phot ographs of Barrier Damage
21
-
- - ' ----- 201 -' ------------·~I --v-- IZ __ FINAL VEHICLE
/ POSITION I
8- " ,B~R ,RI,E~ " = - Ic't -- -, - J - - --- --- ----- - - ----C;~~JECTORY OF- -VEHICLE e.G.
FIGURE 10. Vehicle Trajectory and Final Stopping Position
22
-
·'
_ ""r. ... ___ ... _ ... _
. . '''-...
F I GURE 1 1.
Photographs of Test Veh icl e Damage
23
-
~------------'--~~~~~~---'~~~~~~~--------------~ R'_' LL. ~r~J:~ A tU , 'H~_' __ '~ _TEST \}CIC
-
CONCLUS I ONS
A summary of the safety evaluation guidelines , as provided
by NCHRP 230 (~) and AASHTO (~.l for longitudinal barriers, is
gi ven in Tables 2: and 3.
There was no barrier deflection or vehicle snagging during
the test and the impact severity was within the allowable limits.
Therefore, the results from this test with the constructed
surrogate barrier for the Nebraska Bridge Rail Barrier were
considered valid. Results of the full-scale crash tes~ revealed
the following:
1. Though the change to the New Jersey Barrier face seemed
small, raising the slope break point from the standard
13-in. to 14 1/2-in. proved to be unsatisfactory as far
as keeping the vehicle upright is concerned . ThE!
barrier redirected the vehicle at an exit angle
which was satisfactory; however, the lift of the vehicle
was excessive. The vehicle lift. along with the roll
and yaw motions of the vehicle, caused the vehicle to
roll.
o .. The occupant impact velocities and occupant ridedown accelerations Here satisfactory as well as the all of
the evaluation criteria. except the vehicle rollover
specifications. This sugge:.ts that if the vehicle
would have remained upright , it may !",ave been deemed an
acceptable bridge rail barrier.
25
-
3. The after-impact trajectory of the vehicle showed the
vehicle's lateral rebound distance to be 15 ft. The
rebound distance was measured from the impact face of
the barrier to the ~ide of the vehicle closest to the
barrier. This distance of 15 ft. was acceptable
according to the AASHTO performance criteria . but was
marginal according NCHRP 230.
In summary. it is believed that the increased height of the
slope break point was the cause of the rollover motion of the
test vehicle. As previous tests have shown . the dynamics of a
vehicle impacting a bridge barrier gradually change once the
initial step of the barrier exceeds 3- in. The higher the initial
step . the more drastic the change and therefore. the less
predictable is the vehicle ' s performance. It is the belief of
the University of Nebraska Civil Engineering Department that had
the slope break point for the Nebraska Bridge Rail Barrier been
designed at the standard height of 13-in .• the barrier may have
passed . This may have been achieved by decreasing the slope of
the lower sloped surface of the barrier face. The University of
Nebraska Civil Engineering Department realizes that this
suggestion is purely speculative and cannot be proven without
confirmation from a full-scale crash test.
Based upon the results of this test . the Nebraska Bridge
Rail Barrier with a Modified New Jersey Shape is deemed
unacceptable according to NCHRP 230 and AASHTO safety perfo rmance
guidelines.
26
-
E",;aluation Criteria N!:OR Tesr
Par~ ' _. Test art:.cle shaL s:TOOthly redire:t the ·,;eluele ; the v€lucl€ shall not ". penetrate or go OVer the installation although controll€'3 lateral deflection of Sans:actorj the test a:ticl€ is acceptable.
Part D: Detached e:enH.tS , fra~nts or other debris from the test article shall not pel1arate or shall' p:::ltential for penetratl1lg the passenger ca:Lpartment or SatisfactOl-j present undue hazard to other traffic.
Pi'.!'"~ =.: ~ne vehicle shall terrain upright during and after collision although moderate roll , pitching, and yaWlIlg are acceptable. Integrity of the passenger Unsatlsfactory coo.))a,rtment must be maintained with essentially no deformation or intrusion.
Pa!·t F: lnpa~t veloclty of hypothetical front seat passenger against vehicle interior, calculated froc vehicle accelerations and 24 in. forward and 12 in . lateral Satisfactor'y m.spla::-ene.l"l.t, shall be less than:
Cccupant Impact Velocity : ~ !.oogJ.tudinal Lateral
30 20
and vehicle hlqhest 10 IDS average accelerations subsequent to instant of hypotheti:::a1 passenger ir;I.pact should be less than:
Cccupant Ridedown Accelerations: [2: Longi tui!inal Lateral
15 15
:Part p.: Afte:- collislon, vehicle trajectory and final stopping lXlsition shall Harginal llltruOl;;- a min:imum distance, if at all, intO adjacent traffic lanes.
Pa!'"t I: In test where the vehicle is judged to be redirected into or stopped while lil adjacent traffic lanes , vehicle speed change dU!"ing test article collision Satisfacto:-y snoulc be less than 15 ~ and the exit angle frar: the- test artich, should be iess tha~ 60 percent of test impact angle, both measured at tine of vehicle loss of conta:::t with test deviCE:.
PCHP,P Criteria For Evalue:ing Bridge Rai~ C~ash Tes:~
-
~cUuation Criteria NOOR Test
A: The test article shall contain the vehicle; neither the vehicle nor its cargo shall penetrate or go over the installatioo. Coo.trolled. lateral deflectioo of the test Satisfactory article is acceptable.
B: Detached elements. fragments , or other debris fran the test article shall not penetrate or show potential for penetrating the passenger canpartment or present Satisfactory undue hazard to other traff i c.
c: Integrity of the passenger canpartment Il!USt be maintained with no intrusion and Satisfactory essentially no deformatioo.
D: The Vehicle shall remain upright during and after collision. Unsatisfactory
r : The test article shall smoothly redirect the vehicle. ;. redirection is deemed srrootrl if the rear of the vehicle does not yaw IOOre than 5 degrees away fran the Satisfacto=1' raihng fran time of impact unt il the vehicle separates f ran the railing .
: : Tho; SI!;O;Jthness of the vehicle-railing interaction is fur t her assessed by the effectlve coefficien~ of friction ~; where u = (c0s8 - Vp/ v )/ sine. Sat isfactory
~ Assessment 1 lFO.09 0.0 - 0.25 Good
0.26 - 0.35 Fair ) 0.35 Marginal
G: ThE. l.T,'.lact velocity of a hyp:lthetica1 f ront-seat passenger against the vehicle mte~·ior . calculated fran vehlc1e accelerations and 2.0 ft. longitudnal and 1.0 ft. Satisfacto~"y l at eral dlsp~acements . shall be less than:
O:c\lpant ~ Velocity : ~ Ipngi tudinal Lateral
30 25
a~ for the vehicle highest ID-ms average accelerations subsequent to the instant :Jf hypothetical passenger impaC't should be l ess than:
Occupant Ridedown ~elerations : !l2. Longitudinal Lateral
15 15
H: Vei'.l.c1c exit angle froo. the barrier shall not be IOClte than 12 degrees. Vithin 10:1 ft. ph)!; !.he length of the test vehicle fran the p:lint of initial impact with Satisfacto~' thE.- r allmg . the railing side of the vehicle shall move no morE. than 20 ft. fra:-th: l ine of the traffi c face of the railing .
~a bl e 3 . hSSHTO C~iteria For Evaluating Bridge Ra~l Crash Tes ts
28
-
1. Jehu, V.J., Passenger Transport Berkshire;
REFERENCES
Pearson. L . e., "Impacts of European Coach Against Shaped Concrete and Road Research Laboratory ,
England , TRRL Laboratory Report 801.
Cars and a Barriers. " Crowthorn.
1977 .
2. NCHRP 230 Report . "Recommended Procedures for the Safety Performance Evaluation of Highway Appurtenances," National Cooperative Highway Research Program Report, Transportation Research Board, March 1981.
3. AASHTO. "Guide Specifications for Bridge Railings. An hlternative to Bridge Railing Specifications in the AASHTO Standard Specifications for Highway Bridges ," American hssociation of State Highway and Transportati on Officials , Proposed March 7 , 1988.
4. "Vehicle Damage Scale for Traffic Accident Investigators," Traffic Accident Data Project Technical Bulletin No.1 , National Safety Council, Chicago, Ill., 1971.
5 . "Collision Deformation Classificacion, Recommended Practice J224 Mar 80. " SAE Handbook Vol. 4. society of Automocive Engineers . Warrendale . Penn., 1985 .
6 . Hinch, J .• Yang, T-L. and Owings. R. , "Guidance Systems for Vehicle Testing," ENSCO , Inc . , Springfield. VA, 1986.
29
-
APPENDICES
30
-
Appendix A. Test Facility
31
-
1. Test Site
The location of the test site. with respect to the Lincoln
Municipal Airport is shown in Figure AI . An 8 ft. high chain-
linked fence surrounds the facility to ensure security for the
test article and any test equipment that is setup and left on the
facility grounds.
2. Vehicle Tow System
A reverse cable tow system. with a 1:2 mechanical advantage.
was used to propel the test vehicle. Using this tow system
allows the tow vehicle to travel half the distance at half the
speed than that of the test vehicle. A sketch of the cable tow
system is shown in Figure A2. The test vehicle was released from
the tow cable approximately 10 ft . before impact with the
Nebraska Bridge Rail Barrier. Photographs of the tow vehicle and
the attached fifth-wheel are shown in Figure A3. The fifth-
wheel . built by Nucleus Corporation. was used f o r accurately
towing the test vehicle at the required target speed with the aid
of a digital speedometer in the tow vehicle .
32
-
3. Vehicle Guidance System
A vehicle guidance system, developed by Hinch (£), was used
to steer the test vehicle. A sketch of the guidance system is
shown in Figure A2, while photographs of the guidance system
before and after impact are shown in Figure A4. The guide flag
was attached to the front left wheel of the test vehicle and was
sheared off (at the distances stated above) before impact with
the Nebraska Barrier. The 3/8 in. diameter cable was tensioned
to 3,000 Ibs . . and was supported laterally and vertically every
100 ft . by hinged stanchions which stood upright while holding up
the guide cable. When the vehicle passed, the guide flag struck
each stanchion and knocked it to the ground. The vehicle
guidance system was approximately 1,000 ft. in length.
33
-
.-
UNL TESTING
ElEV 1195
ANNUAl lATE Of CHANGE V JULY ~ 171-J5R 0.2- W 546, T60 P:wy 17R·35l ....... 5100, 1"100, n.oo
f(WY 14-32 5100, Tl70.
•
fIElD ElE'" 121"
.,
~, , 'LfV 1110
~
GENERAL AVIATION
-", PARKING
,/
~ ,
&;>
NEIRASKA •• ,~,"\ NATIONAL GUARD •
.. ",
Elf'" 1175
1,
FIGURE Al . Full-Scale Vehicle Crash Testing Facility 34
-
GUIDE WI FLAG ~ 1 SHEARED ' OFF
I '---Co-I J T E
(TOW CABLE)
, RELEASED I
~-I I
" l }s DIA. GUI:JE I CABL E
I "
I~ ['/1'.. TOW 16 CABLE
Tal'! VEHICLE
rSTANCHIONS
I .l I I
1
FIGURE A2.
/: 2 MFCHAN/~;'L AD V~NTAGE
YC SCAL E
and Guidance Systems Sketch of Tow 35
-
FIGURE A3. Photographs of Tow Vehicle with Fifth-Wheel
36
-
FIGURE A4. Photographs of Vehicle Guidance System
37
-
Appendix B. Data Acquisition Systems
38
-
1. Accelerometers
Endev co triaxial piezoresistive accelerometers (Model 7264)
with a range of 200 g's were used to measure the accelerations in
the longitudinal, lateral, and vertical directions of the test
The accelerometers were rigidly attached to metal
blocks mounted at the center of mass and at the rear of the test
veh:'cle. A photograph of the accelerometers mounted in the test
vehicle is shown at the top of Figure 61, while Figure 62 shows a
schematic of the accelerometer locations. The signals from th~
a cc=lerometers w.ere received and conditioned by an onboard
vehicle I'letraplex unit shot-m at the bottom of Figure 61. The
~ul tiplexed signal was then sent through a single coaxial cable
to the Honeywell (l01) Analog Tape Recorder in the central
control van. Photographs of the system located in the centrally
contr~:'led step-van are shown in Figures 63 and 64, and a
flowc~ :~ t of the accelerometer data aquisition syste~ is shown in
figure 65 . The latest state-of-the-art computer software: ,
. Conputerscope' and . nsP' "'z.s used to analyze and plot thE:-
acceleromet.er data on a Cyclone 386 / AT , "'h ich uses a very high
speed data aquisition board.
~. High-Speed Photography
Thr ee high-speed IG mm came ras were used to fil m the crash
tEoStS. The cameras ran at approximately 500 frames per second.
The overhead camera was a Red Lake Loc arr. wit.h a wide angle :2.5
:i . il:'i!C.e~e r le!".s. It was placed 50 ft. abOV e the concrete apron
39
-
over the point of impact . The perpendicular camera was a Photec
IV with a 55 millimeter lens and was located 165 ft. from the
vehicle point of impact. The parallel upstream camera was also a
Photec IV with a 80 millimeter lens. It was located 185 ft.
upstream from the point of impact and was in line with the
barriers front face.
in Figure B6.
A schematic of the camera layouts is shown
A 100 ft. long by 20 ft. wide grid layout was painted on the
concrete slab in front of the barrier. The white grid was
incremented with 5 ft. divisions to produce a visible reference
system which could be used in the analysis of the overhead high-
speed film.
3. Speed Trap Switches
Eight tape pressure switches spaced at 5 ft. intervals were
used to determine the speed of the vehicle before and after
impact. Each tape switch fired a blue 5B flashbulb located near
each switch on the concrete slab as the left front tire of the
test vehicle passed over it . The average speed of the test
vehicle between the tape switches was determined by knowing the
distance between the tape switches, the calibrated camera speed,
and the number of frames, from the high-speed film, between
flashes. In addition. the average speed was determined from
electronic timing mark data recorded on the oscilloscope software
used with the 386/AT computer as the test vehicle passed over
each tape switch.
40
-
FIGURE 81. Photographs of Onboard Data Acquisition System
41
-
FIGURE B2.
... ~ul. '0. 5uhl '0. Caill> •. hn ... .... , "'. .... , IP24N .... , .,,,. N ... 4 IUlH .... , 1J1>2H '0. • In7N
NO.4 ~
3,211 .vlR 2.IB .v/ , 2.640.v/, 2.22' .v/, 2.438.v/, 2.~46 .\'1 , fFRONT
19 •
IVO./~
17'% ..
64.4 ..
~
61 ~"
IVQ 6
¥ r... ' Ir-I~
NO. 2
20" "
GROUND SURFACE~
·1 I ,
-I "- IV O. 5
'1 "- NO. 3
64 %,"
Schematic of Accelerometer Locations in Vehicle
42
-
FIGURE 83. Photographs of Central Control Van
-
FIGURE B4. Photographs of 38G/AT Computer and Computer Software
44
-
L
Con.t.roI. v ••
I L
End.G¥CO End .... eo PICIOn=.IeIIn: P,e1.CI"U",U", ,"OUM rom. to. r l.C
-
-P""~lz
BARRIER t----- 18s'-----...j~1 ,S'-j
, 16S
nl
I
OVERHEAD LOCAM (SO')
_L--__ 181 PHOTEC rr
181 PHOTEC JY:
20°
L VEHICLE PATH
FIGURE B6. Schematic of High-Speed Camera Locations
-
Appendix C. Graphs of Accelerometer Data
47
-
---------._--
-
,[ ( . , (! - - --c--.-- ----,------ ------
.. ----. ----t-.---- - .-.----
" , f) - - ~ N- Lo.,N --------1----- ---- ----~.-. ---
_ ..
-" .. -
NDOR DATE : GRAPH
-
CONCRETE BRIDG 9-20- 88 OF LONGITUDIN
-------_.-. ', " .
E RAIL BARRIER TEST
AL DECELERATION AT e.G . .. 0 "" VERTICAL UNITS ...... .... •. G' s HORIZONTAL UNITS .... ACCELEROMETER NO. J
--
..... . seconds (AM44 )
---+---- - .--
~~F 1tE-' 'L. -- f' r, r··, ,~ ... '-'- V v'l'"
---- .. - .---- ._ .. ,---. ,---_ .. . . --" • 0) o , , 'J , !! " . .. ,.' , , " .
~~----~-~~---" • :::: __ ...c'...c' , :. ___ '_ .. ' ..:. • ..;',_ '.' , ':0 1 ."
-
rr/~,£'"c) .,.+ ' __ .' ~.
----:-==:=====_= __ ===_=_::1:_ =---- ==---=-==r ----- ------:==
-------- ---------- --- ---- -- --------t--- ------ ---7"
;,::- I! , 0", - __ , ___ _
1 0,0 - ----- ------1---
,' , , (I n , ;::
" -'
--------------
MOOR CONCRETE BRIDGE RAIL RAP.RIER TEST DATE: 9-20-88 GRAPH OF LONGITUDINAL CHANGE IN VELOCITY AT C.G. VERTICAL UNITS .. __ .• _ .... _ft/sec HORIZONTAL UNITS ......... . s~conds ACCELEROMETER NO. 3 (AM44)
--f--- --J---------L-- ----.--L- -1-------,', , ,+ ':' . !:' " , ,;: .:' • :" (, , . t, , ':0 j , " ._--_ .... _.
-
'" o
----_____ ......,,.,.. __ ... _.~...,...,..,..,.,.-- --...,.---0_----___ 0 _________ _ r,1 ,'1.111 111:1 i . (·tJC., "I ll', J T ', IIPl .'E
,- " , ,",
" . "
- t" . (.
I, • I) ,~ I) , 1 (I
----.----~------
NOOR CONCRETF. BRIDGE RAIL BARRIER TEST OATE: 9-20- 88 GRAPH OF LONGITUDINAL CHANGE IN VELOCITY AT C.G . VERTICAL UNITS ............ ft / sec HORIZONTAL UNITS .....•. . .. s~conds ACCELEROMETER NO. 3 (AM44)
" ,. '.' ,., , ~; I;
---------~~----".
-
L··tl'-, [._r :"; 1"'LI'=I CF:" I I r::11 I , • tI , .)- .. , . '-' - ._._- --- ------ ------ -- --- --T -- -- -- - -- - - --
,:. 1"1 () . 0 f--- - - - -- -.' .r
/" NDOR CONCRF.TE BRIDGE RAIL 8,1\RRIER TEST /'
/' DATE : 9-20-88 /' "II • 0 --- GRAPH OF LONGITUDIN1\L DISPLACEMENT AT C.G. ---- ----17 ... ··• - f--- ---VERTICAL inches .' UNITS. . . . . . . . - - - - //. HORIZONTAL UNITS . - - - . - - - . . seconds
ACCELEROMETER NO. J (AM44 , , ...... ." ," r-~' --
--~.".... """ ---"",,
I (0 l' , ., --"-- - - - -.,-..... -----"
--.-" --
, -' .... -.-~ ------' ,-, , .) - - - -- -- - -- - - --- - .- -_.--:---- ----- ----,- -- - -- ------- - -- - ----- ---'"-' - - ---"-- ---,-_.-,-, • 1) ".1 (' . ;::; ( .. 7;: 0) • '-1 .) • r:: ,) , ,- ( .. 0 " -' 0) , .[ " -
-
-----,-- '--..,,-----'-- :::";";7""~=_:c~~=--"-- ,---------
~ ' .. , . (,
'I /, , I)
" " • (I
, I)
I " . r)
" , ,", -
I ,', , (0
_ I ': 11 , t.'
r 1_ I.'!. t " \.! I' L I .! I ~ ',' r.r'::: !' l 11' "" , ri l l' LlI'?'.}r'.:
------- ----
-----.- ---+--
----------j---
------ ---------
... ,.~ ..
~' .' ---.. ---- '---'-"-------;,-;::» ,"
NOOR CONCRETE BRIDGE RAIL BARRIER TEST DATE: 9- 20-88 GRAPH OF LONGITUDINAL DISPLACEMENT AT C_G_ VERTICAL UNITS ..... . . .. .. . inch e s HORIZONTAL UNITS ... .. ... . . s ~ c onds ACCELEROMETER NO_ 3 (AM44)
------- -- I ._-,-_ .. _--_ .. _-> ... _ ....... ,- --I ---- -- -- " .. _._-- --'-_, _____ ·c'..;..' "(0",'-_____ ...::";..:., -',~') _______ '_' ! ' ________ " , • " 0) , ,;: ,- ',', .. :::,-, '. r:
-
L 1"""1 T E R 1'1 L n I . .' I, r;> (I' 01' ------.-,-.-.. -.~ ._._._-----.-----~ - .- _._----- - --_.-
,-" ,. , 'J - ---·--HI
1 0 , 0 -1-----11--1+1--- - .. -- ._---1--
._----
NDOR CONCRETE BRIDGE RAIL D~RRIER TEST DATE: 9-20-88 GRAPH OF LATERAL DECELERATION AT C. G. VERTICAL UNITS ....... . .... G' s HORIZONTAL UNITS .......... seconds ACCELEROMETER NO. 5 !SJ62H)
.- -------·--·>----1
- t (, ,0 ··1------ -,----+ --- --- -_._--+-_._.- -------_ .. --_.- - --- ....
" .. -, " . .,'--__ t, , " .- -_ ... _-_.-----
-
L. I-I T ERAI_ C I-II-.II' r I t! '.!E I_n , 'l r , 0: F r ; EC: :. 0_+ ': . '.' , -- - ---.------ ----- ----- -- _._-----_.- ~---_ =--=.::- --=----r--===--::r::; -.--==.- -::=- = - -.= . c:.:==. ----:,-: = =-: r : .. -==--
/ --"."
3 " ,0 - .- - r y · .... f' _._--
j'fV ... --..... -................ " \....1 ..... " ... '-- r --· ....... "'-.. - ' -----", ......--."' --' ......... - ..... .
(' f-----;:' " , (, - - - ---_. -----
( t (. , (. - - / .- .- .- - ----. --
/ NDOR CONCRF.TE BRIDGE RUL BARRIER. TEST -j
DATE: 9 -20-88 GRAPH OF LATERAL CHANGE IN VELOCITY AT C.G. .-.
" . " - - - . -- VERTICAL tmITS . . .. . · ..... . ft /sec HORIZONTAL UNITS. . . · . . . . . .s f'!cond~ ACCELEROMETER NO. 5 (RJ62H)
------- --_._._- _. -1---- I . I .- I .--1----. .. _ . . -" . (. ': . . , " ,~ " ~ " , ' I " , " · ,; " : c, ~: " .. ,_._-" .
-
, ( , , (I -f---I--
" , t,
- 1 (, , (I
(I • 1 (I (, • 1'~
,.'--.,.----,- ~- ----~-- , ---
-1~--+--1- -- I--j---j---
-----+--- --- ~ -~--
,------j--+--,- - +-- f------
NDOR CONCRF.TR BRIDGE RAIL BARRIER TEST DATE: 9-20- 88 GRAPH OF LATERAL CHANGE IN VELOCITY AT C. G. VERTICAL UNITS _ ...... __ . _ . ft / sec HORIZONTAL UNITS . _0 ••••••• sp.conds ACCELEROMETER NO. 5 (SJ62H)
-----~~ --~--l~-~-L=J~~~~l-- --- r-=--J--_-",.:0..:,..:,..:'-' ___ ..:':;." ';" .::2..:' ____ ~')~ .. -,·,.::.' ___ ,_..:.:..:,~~, ___ "..:' 4,. __ _
-
--,-------
,', (! (t -1-----+----4------
.'": ,., ( • • D +----+-----1 --- --
i ··.... () +----+- ----1----
.... ,...-. ",..-.-----.-
,-, • ('! - ------l-~"
----1------+---
• 0'" ,"
------ ------- -- - -- _. - --,-_.---- - .. --- _ ._- -----
.. ,., , ~ ...
-1------,----+--- - - --I-----f--- -
-+--_.- --- --------
-- -1--"""'.-' ... , .... ~ . ..--" -- -- - -----,-~' .. /
NDOR CONCRETE BRIDGE RAIL BARRIER TEST DATE: 9-20 - 88
___ . GRAPH OF LATERAL DISPLACEHENT AT e . G. VERTICAL UNITS . .. . ..... ... inches HORIZONTAL UNI TS. ___ ..... . ~econds ACCELEROMETER NO _ 5 CBJ62 " i
------_ -J -- - .I ___ I L--.. -'-, ____ '~'.:..;,:.' __ ...:O'-'--'J ___ ~':.' .:..:2'-__ .:.":..:.. ____ ;;(':..:..' ::4 ___ :;"-,-":..· __ ~ ____ " ____ ::'''''':''-' ____ :';.' :..,:' ___ _
-
E'L ,"I .l t l Ll r ' L I"'1 TEF'AL r' t :~ p L.I1 C E r i F. IJ T ,U F"f------- ---------~ --- ---_ ..
2
-
- --'-'--....' ----,------ --"-1 "(o ' "~ G, ,"1"(" i" "I" '('F'': f~ I _ I ::: Ffil1..('11 '" "::r)-BI'IC I ,F ''1,:11 --,--,-_. __ ._-,-, -----",--_._, . - --_ .. _--" - -,-~ -,--- ,- ---"- - --,-~.,-
1'-' , 0)
,.., ,I) - ."'--'-'.".'-
- lo', , ':' -, - '------
,. '.' , (I
" , f' ,., " " 1 " "
tl\.:-f 'I:;".-f'--/ \;_,J::J" '[\.t;. ,-' L~~':;""',:r
\, J \)
I I
U NDOR CONCRETE BRIDGE RAIL BARRIER TEST DATE: 9-20-88 GRAPH OF LONGITUDINAL DECELERATION VERTICAL UNITS .....••. • ... G·s
AT BACK OF VEHICLE
HORIZONTAL UNITS .. ........ seconds ACCELEROMETER NO. 6 (BF57H)
" , ," ,-, , "'I" ,', " 'I"
-
'" '"
l (,t-.l( •• ---------- --- --- -- r --- - -- ----,--
, 0.0 -1------1-----1 --,--- I- -- -'~. --.,.......-
-~--- -~ -~ ~ ~----
.-0-""'- ,,-.-'
~-' ." •• 0 -1---- 11-- 7 .-Ji; ~~=~....f::=""'---:::"·:....j------I-----' 1-----
I " . 0 -1----+-1'- ---, I
// f, .1,1 -v-~-- .---" --
NOOR CONCRETE BRIDGE R~IL B~RRIER TEST DATE: 9-20-88 GRAPH OF LONGITUDINAL CHANGE IN VELOCITY VERTICAL UNITS .... ... . .... ft/sec HORIZONTAL UNITS .. . .. . . . . . seconds ACCELEROMETER NO. 6 (BF57H)
AT BACK OF VEHICLE
---1.--- --L-.-- -1.---.. J .- -.-- I 1,1 ;;: t) I '!:: " , ;: ,-, I , '.; I (, ~! ,', t, ,'I'
-
---r---
-- ---, ------------
l (0 0 ( ) - --- ----I-- -/
/ - - ./ /
. /~/
Co 0 ( 0 - i- ,--- ~.:: 1-- -- --,--"'
-~ 0 (0 +- --- --"-'- --'-'-1---, -~-I----,
- OJ 0 (I ;:: ( I 0 'J ,:;
,
---,---_.,- -- , ------~---.. ' -- ............ -. .r"'- • , __ r~r-~E/'-\ /\
/ J '--"
t=~--~-~ --- ----"
NDOR CONCRETE BRIDGE RAIL BARRIER TEST DATE: 9-20-88 GRAPH OF LONGITUDINAL CHANGE IN VELOCITY AT BACK OF VEHICLE VERTICAL UNITS ............ ft/sec HORIZONTAL UNITS._ ...... . . seconds ACCELEROMETER NO. 6 (BF57H)
-t--~ 1~~~~--- L -~,- =--~1----1-= (I 0 1 "
-
'" ...
I. (t C' , .;,
HDOR CONCRETE BRIDGE RAIL BARRIER TEST DATE: 9-20-88 GRAPH OF LONGITUDINAL DISPLACEMENT AT BACK OF VEHICLE VERTICAL UNITS . •..... .. ... inches HORIZONTAL UNITS ....... .. . seconds ACCELEROMETER NO. 6 (BF57HI
," ,
" ,
,J ",
. ' ,~
, "
"
, . ,/
,. 'Jt
-
'" N
';:--;-:7:7:'"--::-:;C:-:::7":::-:::';:-T.~;-;-~7-------'-----·-"---~~-'BL,:tI ·1I1 UP L t)tl(., to I""Pl f l'-E H EtJ r f ' LJP ')E ,------- ----,-----------, ----,,-, -- ---------
' f Co , (.
---
- "- 1.1 , OJ
" -... _-
_~ .... I
",..:::::::::: ____ ,. __ ' ___ 0-_.>.,. __ • _____ ' ••• __ , __ , •• ______ • ____ • __
NOOR CONCRETE BRIDGE RAIL BARRIER TEST DATE: 9-20-88 GRAPH OF LONGITUDINAL DISPLACEMENT AT BACK OF VEHICLE VERTICAL UNITS .......... . . inches HORIZONTAL UNITS .......... seconds ACCELEROMETER NO_ 6 (BF57H)
'" -,-1---,--L -,- --1-,,--.-, , ~: (, I,' • "
-
'" w
,,"'-- ----:-=,... --~--------------- ... _,-------------'-' t_n T. n', ' '::' . j,' r ,l~ D E ',:E L E r::' A TT, " tt .:0:- ':f:!' P r=:I C " ( ' .r " '-'. H.
~. (, , ( , - ---------,-
L (, • I) - -._-- _._-- - ---"
NDaR CONCRETE BRIDGE RAIL B~RRIER TEST DATE : 9-20 - 88 GRAPH OF LATERAL DECELERATION AT BACK OF VEHICLE VERTICAL tJNITS ....•.. .. . .. G ' 5 HORIZONTAL UNITS .......... seconds ACCELEROMETER NO . 4 IBR47~'
._.-:.':...' :... ':....,_ __.:c':':....:..;., _____ "_. =' ______ :.:.' ... , ~: .- .. - -~ '--"._---" . y
-
-------:-::-:-:-::--:::-::-::-'---"-----"-7":-------------'-·
L .'~ T , I~.H_'-_II!':'~_·I! ! ,~_' ~_-_LOC l. T, .: F"r .,- ''''.F."O::c::' __ I rt£~_' '}':"" ~ '.:.., 11,_,'--__ _
-------..,--------T--- .,-_._------ --------- - -----------
--. ~ ....... "'I:;: = "' .
/ ..........-~-. .-..'"
---+---- -- .- ---------
RAIL BARRIF.R TEST
AT BACK OF VEHICLE
(' :? Ii , (I -I--------+ -------¥-
// '0," +------- --.rj --.-- -NOOR CONCRETE- :RIDGE
/
' DATE: 9-20-88 GRAPH OF LATERAL CHANGE IN VELOCITY
-..J,.....,r ... , VERTICAL UNITS ............ ft/sec (I , 0 - ",,-=-,,~-'----.-,- --_.-.---"-_ .. - HORIZONTAL UNITS .. ........ second s
ACCELEROMETER NO. 4 (BR47H)
I --- ,
e---._-- ------.- .. -- -.--- ----L ___ -,";.c.' :.;" _____ ..;:;,'..:'.;,'-" ____ ...:.":..:..' "-':' (~ , :;' " . "j .', , ' " , " ~----.-~~.----.-,-----.-.. _,,---,---- _.- -_.- -_.
-
::.: I) , 0,) -1------
::: (. , 0 -f-- +---- ---- ----
------_._--- .. ---. ----- .. _ -f---+-
----\--+-/
-+---1/-
........ . / /
VI
.r"~-'
-----
.. ~............ . --'--
lO:' , r:. +-- 1---- - .. - .. --- ---- -"._-' (
--I-i --~--> - --- -. ------... -
" , 0) - _ -- - -..r::::=-
- I " , (I
~' ... ~-.'.
NDOR CONCRETE nRIOGE RAIL B~~RIF,R TEST DATE: 9-20-88 GRAPH OF LATERAL CHANGE IN VELOCITY AT BACK OF VEHICLE VERTICAL UNITS . . ...... . ... ft/sec HORIZONTAL UNITS ....... ___ s econds ACCELEROMETER NO. 4 (BR47H)
'---- 1------ -- ---- 1--- -1-. -- 1 - -I J -- I ____ ~O::.:,~,)::.:.:" _ ____ ~'::..:' . .-. y r, , " " , J .:; ___ ". I, ,. ,', . ,; '~ ,. 'w ____ , __ ' .. _"" .... _ ' .. _,_... _ . __ ' __ ._, __ ,_. __ . ________ ' __ •
-
'" '"
LATERAL DlSP l. ACEMEN'!" ( IN '
._---- --- - - ---
:=:. 0) (I , I) -r ------·-l-----·------l
NDOR CONCRETE BRIDGE RAIL BARRIER TEST DATE: 9-20-88
lS0 , (, ------- GRAPH OF LATERAL DISPLACEMENT AT BACK OF VEHICLE _.,_,., ___ . __
1 (I';' , .)
VERTICAL UNITS •••••••.•.•• inches HORIZONTAL UNITS .......... seconds ACCELEROMETER NO. 4 COR07H)
._ ---_.- --_._--_._.
... r-'~
",'
- _._---_._._._. - ------"'-,/
.-'" " .. "-.-------~.--.- .....,.., ... --.--.--,-.-~- ' ----_ .. -......
// , .......... ~
, .... ~~ -' . ....----~ .... ' .; (I , (0 -~----.---i===.----... - ---"-----._. -.----.------... _. .._--'--_.'-- ,.- .---,_._-'----'-'- -,._--.'_.--' -' -'-"-'-
\-____ • ___ ._ L. ____ ... ___ ... _._. _____ ._. _ __ _ __ .
I) , (I '-' , to), :::: . .:,. . -: ___ (. , ',' ____ _ . . - ._--- ---- 0' • ",. " , ,;;
-
r------------::c~7:_:_~~_;==;___,=_===~~~;;;;_:~-------- .J!'!_ ') 1,1 I I LIP L I-='TEEAL :C1_t:3F'LHCEt'11~~IIT C UR"!! 1----------------- --------- ----------- ---!~ II , (0
I-I i, • (0 _
NOOR CONCRETE BRIDGE RAIL BARRIER TEST DATE: 9 - 20-88 GRAPH OF LATERAL DISPLACEMENT AT BACK OF VEHICLE VERTICAL UNITS .. ......... . inches HORIZONTAL UNITS ........ .. s~conds ACCELEROMETER NO. 4 (BR47H)
----- ---- ----_.- ----
---_. __ .---- --.-- --_._- . --_.
t ,., , (I ---.------- -
.-. • I) !' f' • I ,., , ___ .:..c...:; __ _
---1-'----
,,-,,-
--r····,; /'
--- ---1-- ---
....-./
.'
.-..... ---.'
--,r