Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB,...

46
Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services Gillette, Wyoming November 17, 2006

Transcript of Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB,...

Page 1: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

Foundation Coal 4100XPB, Shovel 10P&H Centurion 750

Control System Upgrade

Presented by:P&H MinePro Services

Gillette, WyomingNovember 17, 2006

Page 2: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Overview Overview • Upgrade Packages Available• Centurion / Upgrade Benefits• Machines Upgraded to Date • Foundation Coal, Centurion 750 Background• Upgrade Goals• Installation• Results• Questions

Page 3: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Centurion Upgrade Options

• Centurion – Complete System Upgrade

• Centurion 750– Controller and I/O upgrade to digital system

• Centurion 500– Controller upgrade for digital systems

Page 4: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Centurion “Full” Upgrade

• Analog or Digital system replacement• Complete System Upgrade

– Touch Screens– Controller– Smart I/O– Drives– Complete control cabinet

Page 5: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Centurion UpgradeAnalog Layout Centurion Layout

GUI

GUI

AC 800

DrivesSmartI/O

PanelView PLC

I/O AnalogDrives

PMD

Page 6: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Centurion 750

• Digital system control upgrade– Touch Screens– Controller– Smart I/O

• Uses existing drives and control cabinet• System converted to Centurion

Page 7: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Centurion 750DDC Layout 750 Layout

GUI

OAP

GUI

PLC

RemI/O AC 80

Drives

GUI

GUI

AC 800

DrivesSmartI/O

Page 8: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Centurion 500

• Digital system control upgrade– Touch Screens– Controller

• Uses existing drives, I/O, and control cabinet• Cost effective upgrade with minimal investment

of resources

Page 9: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Centurion 500DDC Layout 500 Layout

GUI

OAP

GUI

PLC

RemI/O AC 80

Drives

GUI

GUI

AC 800

PLC Drives

RemI/O

Page 10: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Centurion Based Upgrades

• Remote Communications• Payload Measurement• Automated Control

Page 11: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

Remote Communications• ShoveLink

– Remote shovel monitoring– Faults, temps, recordings– Data via OPC

• ShoveLink II– Fleet management– Web based – SQL Server 2005– New diagnostic tools– Supporting documentation

“ROCK SOLID SUPPORT”

Page 12: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Payload Measurement

• Payload and Payload Plus– Accuracy of 2% (error)– Precision of 4% (repeatability)– Calibration is very simple

• Reporting software– SQL Server 2005– Remote downloads

Page 13: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Automated Control• OptiDig II• ABSS• 3D Track Protection

– Avoids collisions– Geometric model of

shovel– Predicts position/makes

corrections– Tested and running on

2100BLE and 4100A

Page 14: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Upgrade Benefits Upgrade Benefits PerformancePerformance

Reduced Propel transfer timeReduced cycle times from Crowd extended speed rangeCoordinated motion speedsOpti-Dig IIIntegrated control of machine and driveNext generation automation options

Page 15: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Upgrade Benefits Upgrade Benefits DiagnosticsDiagnostics

High level drive and controller diagnostics from the GUISmart I/O with safer 24V DC control Smart I/O with internal diagnostics and health status from the GUISimple and quick replacement of snap-in Smart I/O modules High bandwidth industry standard Profibus I/O networkImproved noise immunity via fiber optic Profibuscabling

Page 16: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Upgrade Benefits Upgrade Benefits New FunctionsNew Functions

Optional logarithmic joystick function, allows for smoother operation during small joystick movements.A brake set logic tracks time from brake solenoid “off” to pressure below 5 psi. A warning is logged if the time is greater then 500 ms.Soft shutdown logic added, allows controlled shutdowns of independent motions.Swing impact detection with optional alert sounded when impact is detected.Lube system faults will not trigger a immediate shutdown on the first occurrence; allows the operator to re-set the logic in an attempt to free a frozen/ lube line. After three failures or 15 minutes of non-lube operation, will cause trip.RPC bank hysteresis adjusted to allow for more aggressive switching of banks.

Page 17: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Centurion Shovels to Date Centurion Shovels to Date • Upgrades

20 – 4100 / 4100A / 4100XPB17 - 2800XPA / 2800XPB 2 - 2300XPLR

• New shovel sales with Centurion as OE38 – 4100C / 4100XPC / 4100BOSS22 – 2800XPB 2 - 2300XPC

Page 18: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

FoundationFoundation--Centurion 750 Centurion 750 Background Background

4100XPB, SN ES41111, commissioned in October 2001

100,000 hour MARC Agreement

Centurion installed at approximately 33,000 hours started on June 26, 2006

Page 19: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Manpower/TimingManpower/TimingStarted outage June 26, 2006, duration of 11 daysRetrofit was performed in conjunction with a major mechanical outageCenturion can be installed in 8 daysInstallation of hardware took 5 days

3 men on days3 men on nights

Testing and commissioning took 3 days2 men on days

Page 20: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Upgrade Goals/Upgrade Goals/KPIKPI’’ss• Demonstrate an improvement of .5 seconds in the dig cycle• Demonstrate an improvement of 3 seconds (+/- .25 seconds) in propel

transfer time each direction (6 seconds total)• System-wide minimum availability is to be 88% for all hours of operation

during the trial period• All systems must pass an MSHA safety inspection for safe and efficient

operation• All electrical and control systems must demonstrate full integration and meet

all electrical codes • All components and equipment must be designed and installed for

reasonable ease of access and maintenance

Page 21: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Project InstallProject Install

Page 22: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Lower Lower Works I/O Works I/O (located on (located on the lower the lower works)works)

Lube Room I/OLube Room I/OTransfer Transfer Cabinet I/OCabinet I/O

Converter I/OConverter I/O

RPC I/ORPC I/O

Auxiliary I/OAuxiliary I/O

Front Machine Front Machine House Wall I/OHouse Wall I/O Operator Operator

Cab Cab Touch Touch ScreenScreenOperator Operator

Cab I/OCab I/OControl Control Cabinet I/O Cabinet I/O and and ControllerController

Control Control Room Room Touch Touch ScreenScreen

Hoist I/OHoist I/O

Page 23: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Operator’s Cab

Hall effectErgonomicLogarithmic

New GUI’sIndependentNew screens

Page 24: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Lower Lower Works I/O Works I/O (located on (located on the lower the lower works)works)

Lube Room I/OLube Room I/OTransfer Transfer Cabinet I/OCabinet I/O

Converter I/OConverter I/O

RPC I/ORPC I/O

Auxiliary I/OAuxiliary I/O

Front Machine Front Machine House Wall I/OHouse Wall I/O Operator Operator

Cab Cab Touch Touch ScreenScreenOperator Operator

Cab I/OCab I/OControl Control Cabinet I/O Cabinet I/O and and ControllerController

Control Control Room Room Touch Touch ScreenScreen

Hoist I/OHoist I/O

Page 25: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Control CabinetAB SLCABB AC 80

ABB AC 800Siemens Smart I/O

Page 26: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Control CabinetABB DrivesOld GUI

Fiber Optic Branching UnitFilter, Power Supply, Resolver Module

Page 27: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Lower Lower Works I/O Works I/O (located on (located on the lower the lower works)works)

Lube Room I/OLube Room I/OTransfer Transfer Cabinet I/OCabinet I/O

Converter I/OConverter I/O

RPC I/ORPC I/O

Auxiliary I/OAuxiliary I/O

Front Machine Front Machine House Wall I/OHouse Wall I/O Operator Operator

Cab Cab Touch Touch ScreenScreenOperator Operator

Cab I/OCab I/OControl Control Cabinet I/O Cabinet I/O and and ControllerController

Control Control Room Room Touch Touch ScreenScreen

Hoist I/OHoist I/O

Page 28: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Auxiliary Cabinet Old Flex I/O Siemens Smart I/O

Page 29: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Lower Lower Works I/O Works I/O (located on (located on the lower the lower works)works)

Lube Room I/OLube Room I/OTransfer Transfer Cabinet I/OCabinet I/O

Converter I/OConverter I/O

RPC I/ORPC I/O

Auxiliary I/OAuxiliary I/O

Front Machine Front Machine House Wall I/OHouse Wall I/O Operator Operator

Cab Cab Touch Touch ScreenScreenOperator Operator

Cab I/OCab I/OControl Control Cabinet I/O Cabinet I/O and and ControllerController

Control Control Room Room Touch Touch ScreenScreen

Hoist I/OHoist I/O

Page 30: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

RPC Control

Old Flex I/OSelf Contained RPC ControlPLC, Smart I/O, kVAR xducer, firing board, sync xfmr, filter, power supply

Page 31: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Lower Lower Works I/O Works I/O (located on (located on the lower the lower works)works)

Lube Room I/OLube Room I/OTransfer Transfer Cabinet I/OCabinet I/O

Hoist I/OHoist I/O

Converter I/OConverter I/O

RPC I/ORPC I/O

Auxiliary I/OAuxiliary I/O

Front Machine Front Machine House Wall I/OHouse Wall I/O Operator Operator

Cab Cab Touch Touch ScreenScreenOperator Operator

Cab I/OCab I/OControl Control Cabinet I/O Cabinet I/O and and ControllerController

Control Control Room Room Touch Touch ScreenScreen

Page 32: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Transfer Cabinet

Flex I/OSmart I/OFilter & power supply

Page 33: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Lower Lower Works I/O Works I/O (located on (located on the lower the lower works)works)

Lube Room I/OLube Room I/OTransfer Transfer Cabinet I/OCabinet I/O

Converter I/OConverter I/O

RPC I/ORPC I/O

Auxiliary I/OAuxiliary I/O

Front Machine Front Machine House Wall I/OHouse Wall I/O Operator Operator

Cab Cab Touch Touch ScreenScreenOperator Operator

Cab I/OCab I/OControl Control Cabinet I/O Cabinet I/O and and ControllerController

Control Control Room Room Touch Touch ScreenScreen

Hoist I/OHoist I/O

Page 34: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Converter Cabinet

Old Flex I/OSmart I/OFilter & power supply

Page 35: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Lower Lower Works I/O Works I/O (located on (located on the lower the lower works)works)

Lube Room I/OLube Room I/OTransfer Transfer Cabinet I/OCabinet I/O

Converter I/OConverter I/O

RPC I/ORPC I/O

Auxiliary I/OAuxiliary I/O

Front Machine Front Machine House Wall I/OHouse Wall I/O Operator Operator

Cab Cab Touch Touch ScreenScreenOperator Operator

Cab I/OCab I/OControl Control Cabinet I/O Cabinet I/O and and ControllerController

Control Control Room Room Touch Touch ScreenScreen

Hoist I/OHoist I/O

Page 36: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Hoist I/O Drop

• Added for more localized control and cabling

• Room for expansion for RTD’s

Page 37: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Lower Lower Works I/O Works I/O (located on (located on the lower the lower works)works)

Lube Room I/OLube Room I/OTransfer Transfer Cabinet I/OCabinet I/O

Converter I/OConverter I/O

RPC I/ORPC I/O

Auxiliary I/OAuxiliary I/O

Front Machine Front Machine House Wall I/OHouse Wall I/O Operator Operator

Cab Cab Touch Touch ScreenScreenOperator Operator

Cab I/OCab I/OControl Control Cabinet I/O Cabinet I/O and and ControllerController

Control Control Room Room Touch Touch ScreenScreen

Hoist I/OHoist I/O

Page 38: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Lube RoomSmart I/OFilter & power supplyOld Flex I/O

Page 39: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Lower Lower Works I/O Works I/O (located on (located on the lower the lower works)works)

Lube Room I/OLube Room I/OTransfer Transfer Cabinet I/OCabinet I/O

Converter I/OConverter I/O

RPC I/ORPC I/O

Auxiliary I/OAuxiliary I/O

Front Machine Front Machine House Wall I/OHouse Wall I/O Operator Operator

Cab Cab Touch Touch ScreenScreenOperator Operator

Cab I/OCab I/OControl Control Cabinet I/O Cabinet I/O and and ControllerController

Control Control Room Room Touch Touch ScreenScreen

Hoist I/OHoist I/O

Page 40: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Front Machine House I/O Drop

• Added for more localized control and cabling

• Old system split this control between the lube room and right hand room

• Room for expansion

Page 41: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Lower Lower Works I/O Works I/O (located on (located on the lower the lower works)works)

Lube Room I/OLube Room I/OTransfer Transfer Cabinet I/OCabinet I/O

Converter I/OConverter I/O

RPC I/ORPC I/O

Auxiliary I/OAuxiliary I/O

Front Machine Front Machine House Wall I/OHouse Wall I/O Operator Operator

Cab Cab Touch Touch ScreenScreenOperator Operator

Cab I/OCab I/OControl Control Cabinet I/O Cabinet I/O and and ControllerController

Control Control Room Room Touch Touch ScreenScreen

Hoist I/OHoist I/O

Page 42: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Lower Control Cabinet

Siemens Smart I/OAll new componentsFlex I/O

Page 43: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

New 24vdc ComponentsTypical Brake BoxTransducers & new 24vdc brake solenoids

Solenoid (MAC) Valves24vdc coils

Page 44: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Results Results Demonstrated an improvement of 0.52 seconds in the dig cycleDemonstrated an improvement of 6.73 seconds improvement in the time it takes to switch from dig to propel and back System-wide availability was 93% for all hours of operation during the trial period and has been 93-94% post commissioningAll systems passed MSHA regulations for safe and efficient operationAll electrical and control systems fully integrated and met all electrical codes All components and equipment were designed and installed for reasonable ease of access and maintenance

Page 45: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Questions?

Page 46: Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control … … · Foundation Coal 4100XPB, Shovel 10 P&H Centurion 750 Control System Upgrade Presented by: P&H MinePro Services

“ROCK SOLID SUPPORT”

Vision StatementVision Statement

Our vision is to be the surface mining industry’s preferred partner -- continuously

striving to provide reliable, innovative products and services that reduce our

customers’ costs