Remedial Action
Quality Assurance Project Plan -
Revision 1
Ashland/NSP Lakefront Site
Project I.D.: 15X001
NSPW
Eau Claire, Wisconsin
July 2015 (Addendum 1 for Ashland Breakwater)
A Joint Venture of Foth Infrastructure & Environment, LLC and Envirocon, Inc. X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\R- RA QAPP Rev 1 Add 1.docx
101 International Drive, P.O. Box 16655
Missoula, MT 59808
July 20, 2015
Mr. Jerry Winslow
Project Manager Xcel Energy, Inc., on behalf of NSPW
414 Nicollet Mall, MP 4D
Minneapolis MN 55401
Dear Mr. Winslow:
RE: Remedial Action Quality Assurance Project Plan – Revision 1,
Addendum 1 for Ashland Breakwater
Ashland/NSP Lakefront Site
On behalf of Foth Infrastructure & Environment/Envirocon Joint Venture (FE JV), the
Remedial Action Quality Assurance Project Plan – Revision 1, Addendum 1 for Ashland
Breakwater (RA QAPP Addendum 1) for the Ashland/NSP Lakefront Site is enclosed.
If you have any questions concerning this report, please contact either of the undersigned
at (920) 497-2500.
Sincerely,
Foth Infrastructure & Environment/Envirocon Joint Venture
Steve J. Laszewski, Ph.D. Denis M. Roznowski, P.E.
Management Committee Member Project Manager
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\R- RA QAPP Rev 1 Add 1.docx
Remedial Action Quality Assurance Project Plan - Revision 1,
Addendum 1 for Ashland Breakwater
Distribution
No. of No. of
Copies Sent To Copies Sent To
1 Richard C. Karl
Director, Superfund Division
U.S. Environmental Protection Agency
77 W. Jackson Blvd. (SR-6J)
Chicago IL 60604-3590
1 Jerry Winslow
Project Manager
Xcel Energy, Inc., on behalf of NSPW
414 Nicollet Mall, MP 4D
Minneapolis MN 55401
1 Scott Hansen
Remedial Project Manager
U.S. Environmental Protection Agency
77 W. Jackson Blvd. (SR-6J)
Chicago IL 60604-3590
1 Jamie Dunn
Project Manager
Wisconsin Dept. of Natural Resources
810 W. Maple St.
Spooner WI 54801
1 Steve Laszewski
Management Committee Member
Foth Infrastructure & Environment/
Envirocon Joint Venture
2121 Innovation Ct., Suite 300
De Pere WI 54115
1 Denis Roznowski
Project Manager
Foth Infrastructure & Environment, LLC
2121 Innovation Ct., Suite 300
De Pere WI 54115
1 Alan Buell
Deputy Project Manager and
RA Construction Manager
Envirocon, Inc.
651 Corporate Circle, Suite 114
Golden CO 80401
1 Brian Symons
RD QA Manager
Foth Infrastructure & Environment, LLC
14 Corporate Woods, Suite 650
8717 W. 110th Street
Overland Park KS 66210
1 Master Project Files
Foth Infrastructure &
Environment/Envirocon Joint Venture
Remedial Action Quality Assurance Project Plan - Revision 1,
Addendum 1 for Ashland Breakwater
Project ID: 15X001
Prepared for
NSPW
Eau Claire, Wisconsin
Prepared by
Foth Infrastructure & Environment/
Envirocon Joint Venture
July 2015
Copyright©, Foth Infrastructure & Environment/
Envirocon Joint Venture 2015
101 International Drive, P.O. Box 16655 Missoula, MT 59808
REUSE OF DOCUMENTS
This document has been developed for a specific application and not for general use; therefore, it may not be used without
the written approval of Foth. Unapproved use is at the sole responsibility of the unauthorized user.
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\R- RA QAPP Rev 1 Add 1.docx FE/Joint Venture ii
Table of Contents
Uniform Federal Policy-QAPP Worksheets
QAPP Worksheet #3 Distribution List – Breakwater Construction Project
QAPP Worksheet #4 Project Personnel Sign-Off Sheet
QAPP Worksheet #5 Project Organizational Chart
QAPP Worksheet #9 Project Scoping Session Participants Sheet
QAPP Worksheet #10 Problem Definition – Conceptual Site Model (includes
drawings)
QAPP Worksheet #11 Project Quality Objectives – Systematic Planning Process
Statements
QAPP Worksheets #14 and #16 Project Tasks and Schedule
QAPP Worksheet #20 Sampling Summary Table
QAPP Worksheet #21 Project Sampling SOP Reference Table – Breakwater
Construction
QAPP Worksheet #22 Field Equipment Calibration, Maintenance, Testing, and
Inspection Table
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\R- RA QAPP Rev 1 Add 1.docx FE/Joint Venture iii
List of Abbreviations, Acronyms, and Symbols
A/OT Agencies Oversight Team
AOC Administrative Order on Consent
ASTM American Society of Testing and Materials
BOD Biochemical Oxygen Demand
CCB Continuing Calibration Blank
CCV Continuing Calibration Verification
CFR Code of Federal Regulations
CLP Contract Laboratory Program
cm centimeter
cm2 square centimeter
COC Containment of Custody
COC form Chain-of-Custody form
COMMP Cap Operations, Maintenance and Monitoring Plan
CQAP Construction Quality Assurance Plan
CQA Certified Quality Auditor
CQC Construction Quality Control
CST Column Settling Test
DGPS Differential Global Positioning System
DQI Data Quality Indicator
DQO Data Quality Objective
DRET Dredging Elutriate Test
EDD Electronic Data Deliverable
FCR Field Change Request
FE JV Foth Infrastructure & Environment/Envirocon Joint Venture
GIS Geographic Information System
GPS Global Positioning System
ICAL Initial Calibration
ICV Initial Calibration Verification
IDW Investigation-Derived Waste
IPR Initial Precision and Recovery
LCS Laboratory Control Sample
LIMS Laboratory Information Management System
LTMP Long-Term Monitoring Plan
MDL Method Detection Limit
mg/kg milligrams per kilogram
mg/L milligrams per liter
MNR Monitored Natural Recovery
MPC Measurement Performance Criteria
MS Matrix Spike
MSD Matrix Spike Duplicate
msl mean sea level
NAD North American Datum
NAVD North American Vertical Datum
List of Abbreviations, Acronyms, and Symbols (continued)
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\R- RA QAPP Rev 1 Add 1.docx FE/Joint Venture iv
NTU Nephelometric Turbidity Units
OM&M Operations, Maintenance, and Monitoring
OPR Ongoing Precision and Recovery
PCLT Pancake Column Leach Test
PE Performance Evaluation
PID photoionization detector
ppb parts per billion
PPE personal protective equipment
ppm part per million
ppt parts per trillion
PQO Project Quality Objective
QA Quality Assurance
RA QAPP Remedial Action Quality Assurance Project Plan – Revision 1, Addendum 1 for
Addendum 1 Ashland Breakwater
QC Quality Control
QL Quantitation Limit
RA Remedial Action
RAL Remedial Action Level
RAO Remedial Action Objective
RA Remedial Design
RF Response Factor
ROD Record of Decision
RPD Relative Percent Difference
RSD Relative Standard Deviation
RT Retention Time
RTK Real Time Kinematic
SDG Sample Delivery Group
SOP Standard Operating Procedure
SOW Statement of Work
SQL Sample Quantitation Limit
TBD To Be Determined
TOC Total Organic Carbon
TSS Total Suspended Solids
UFP-QAPP Uniform Federal Policy for Quality Assurance Project Plans
µg micrograms
µg/L micrograms per liter
USEPA U.S. Environmental Protection Agency
USGS U. S. Geological Survey
VER Calibration Verification
WAC Wisconsin Administrative Code
WDNR Wisconsin Department of Natural Resources
WPDES Wisconsin Pollutant Discharge Elimination System
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\R- RA QAPP Rev 1 Add 1.docx FE/Joint Venture v
References
Foth Infrastructure & Environment/Envirocon Joint Venture, 2013a. Phase 1 Pre-Design Study
Work Plan – Revision 1 – Ashland/NSP Lakefront Site, Appendix B: Field Sampling
Plan – Revision 1. September 2013.
Foth Infrastructure & Environment/Envirocon Joint Venture, 2013b. Demolition Plan –
Ashland/NSP Lakefront Site. January 2013.
Foth Infrastructure & Environment/Envirocon Joint Venture, 2014a. Remedial Action Site
Specific-Health and Safety Plan – Ashland/NSP Lakefront Site. April 2014.
Foth Infrastructure & Environment/Envirocon Joint Venture, 2014b. Construction Quality
Assurance Plan – Ashland/NSP Lakefront Site. April 2014.
Foth Infrastructure & Environment/Envirocon Joint Venture, 2014c. Air Management Plan –
Ashland/NSP Lakefront Site. August 2014.
Foth Infrastructure & Environment/Envirocon Joint Venture, 2014d. Noise Management Plan –
Ashland/NSP Lakefront Site. April 2014.
Foth Infrastructure & Environment/Envirocon Joint Venture, 2014e. Vibration Management
Plan – Ashland/NSP Lakefront Site. April 2014.
Foth Infrastructure & Environment/Envirocon Joint Venture, 2014f. Remedial Action Waste
Management Plan – Ashland/NSP Lakefront Site. April 2014.
Foth Infrastructure & Environment/Envirocon Joint Venture, 2014g. Erosion Control and Storm
Water Management Plan – Ashland/NSP Lakefront Site. April 2014.
Foth Infrastructure & Environment/Envirocon Joint Venture, 2014h. Performance Standard
Verification Plan – Ashland/NSP Lakefront Site. April 2014.
Foth Infrastructure & Environment/Envirocon Joint Venture, 2015a. Remedial Action Quality
Assurance Project Plan – Revision 1, Addendum 1 for Ashland Breakwater –
Ashland/NSP Lakefront Site. July 2015.
Foth Infrastructure & Environment/Envirocon Joint Venture, 2015b. Remedial Action Site
Specific-Health and Safety Plan for Ashland Breakwater – Ashland/NSP Lakefront Site.
July 2015.
IDQTF, 2005a. Uniform Federal Policy for Quality Assurance Project Plans, Evaluating,
Assessing, and Documenting Environmental Data Collection and Use Programs, Part 1:
UFP-QAPP Manual, Final, Version 1. Intergovernmental Data Quality Task Force.
EPA-505-B-04-900A / DTIC ADA 427785. March 2005.
References (continued)
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\R- RA QAPP Rev 1 Add 1.docx FE/Joint Venture vi
IDQTF, 2005b. Uniform Federal Policy for Quality Assurance Project Plans, Evaluating,
Assessing, and Documenting Environmental Data Collection and Use Programs, Part 2A:
UFP-QAPP Workbook, Final, Version 1. Intergovernmental Data Quality Task Force.
EPA-505-B-04-900C / DTIC ADA 427486. March 2005.
SW846, 2008. Final Update IV to the Third Edition, Test Methods for Evaluating Solid Waste,
Physical/Chemical Methods. January 3, 2008.
URS, 2007. Remedial Investigation Report - Ashland/ Northern States Power Lakefront
Superfund Site. August 2007.
URS, 2008. Feasibility Study - Ashland/Northern States Power Lakefront Superfund Site.
December 2008.
U.S. Environmental Protection Agency, 1992. Specification and Guidance for Obtaining
Contaminant-Free Sample Containers. EPA 540/R-93/051. OSWER Directive 9240.0-
05A. December 1992.
U.S. Environmental Protection Agency, 1996. Method 1669, Sampling Ambient Water for
Trace Metals at EPA Water Quality Criteria Levels. U.S. Environmental Protection
Agency, Office of Water, Engineering and Analysis Division. July 1996.
U.S. Environmental Protection Agency, 1998. EPA Quality Manual for Environmental
Programs. Order 5360. July 1998.
U.S. Environmental Protection Agency, 1999. USEPA Contract Laboratory Program National
Functional Guidelines for Organic Data Review. EPA-540/R-99-008 (PB99-963506).
October 1999.
U.S. Environmental Protection Agency, 2000a. Guidance for the Data Quality Objectives
Process for Hazardous Waste Sites. EPA QA/G-4HW. EPA 600/R-00/007. January
2000.
U.S. Environmental Protection Agency, 2000b. Instructions on the Preparation of a Superfund
Division Quality Assurance Project Plan, Revision 0. USEPA Region 5. June 2000.
U.S. Environmental Protection Agency, 2000c. Guidance for Data Quality Assessment-Practical
Methods for Data Analysis. EPA QA/G-9. July 2000.
U.S. Environmental Protection Agency, 2000d. Guidance for the Data Quality Objectives
Process. EPA QA/G-4. EPA 600/R-96/055. September 2000.
U.S. Environmental Protection Agency, 2001. EPA Requirements for Quality Assurance Project
Plans. EPA QA/R-5. March 2001.
References (continued)
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\R- RA QAPP Rev 1 Add 1.docx FE/Joint Venture vii
U.S. Environmental Protection Agency, 2004b. USEPA Contract Laboratory Program National
Functional Guidelines for Inorganic Review. OSWER 9240.1-45 / EPA 540-R-04-004.
October 2004.
U.S. Environmental Protection Agency, 2008. Requirements for the 60 Percent Design Report.
April 29, 2008.
Wisconsin Department of Natural Resources, 1997. Method and Manner of Sampling. NR 218.
August 1997.
Wisconsin Department of Natural Resources, 2005. Analytical Test Methods and Procedures.
NR 219. May 2005.
Wisconsin Department of Natural Resources, 2007. Personnel Qualifications for Conducting
Environmental Response Actions. NR 712. September 2007.
Wisconsin Department of Natural Resources, 2008. Laboratory Certification and Registration.
NR 149. April 2008.
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\R- RA QAPP Rev 1 Add 1.docx FE/Joint Venture
Worksheets
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #3
Page Nos. Page 1 of 1
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 03 Rev 1 Add 1.docx
QAPP Worksheet #3
Distribution List - Breakwater Construction Project
QAPP Recipient Title Organization Telephone Number E-mail Address
Scott Hansen Remedial Project Manager USEPA 800-621-8431, x61999 [email protected]
Richard C. Karl Director, Superfund Division USEPA 312-353-2000 [email protected]
Jamie Dunn Project Manager WDNR 715-635-4049 [email protected]
Jerry Winslow Project Manager Xcel Energy, Inc.,
on behalf of NSPW
612-330-2928 [email protected]
Eric Ealy Environmental Compliance
Oversight
Xcel Energy, Inc. 715-682-6904
763-276-6476
Thomas Perry Construction Management
Oversight
Xcel Energy, Inc. 715-682-8948
906-204-6680
Steve Laszewski Management Committee
Member
Foth Infrastructure &
Environment/Envirocon
Joint Venture
920-496-6823 [email protected]
Denis Roznowski Project Manager Foth Infrastructure &
Environment, LLC
920-496-6756 [email protected]
Alan Buell Deputy Project Manager and
RA Construction Manager
Envirocon, Inc. 406-698-2012 [email protected]
Brian Symons RD QA Manager Foth Infrastructure &
Environment, LLC
913-469-0686 [email protected]
Jim Hutchison Project Engineer Foth Infrastructure &
Environment, LLC
920-496-6813 [email protected]
Matthew Clark Project Engineer Baird, Ltd. 608-273-0592 [email protected]
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #4
Page Nos. Page 1 of 4
QAPP Worksheet #4
Project Personnel Sign-Off Sheet
Organization: Response Agencies
Project Personnel Title Telephone Number Signature Date RA QAPP Read
Scott Hansen Remedial Project Manager 800-621-8431, x61999
Jamie Dunn Project Manager 715-635-4049
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #4
Page Nos. Page 2 of 4
Organization: Foth Infrastructure & Environment/Envirocon Joint Venture
Project Personnel Title Telephone Number Signature Date QAPP Read
Steve Laszewski FE JV Mgmt Committee Member,
Foth I&E
920-496-6823
920-562-0321 (cell)
Keith Summers FE JV Mgmt Committee Member,
Foth I&E
920-496-6805
920-562-0328
Pete Joy FE JV Mgmt Committee Member,
Envirocon
406-523-1157
406-544-5825 (cell)
Alan Buell Deputy Project Manager &
RA Construction Manager, Envirocon
303-215-0187
406-698-2012 (cell)
Phil Deakin Corporate Acct. Manager, Envirocon 402-451-7171
John D’Antuono FE JV Mgmt Committee Member,
Director of Contracts, Envirocon
406-523-1152
406-544-1161 (cell)
Brian Bell Dredging Expert, Envirocon 219-548-0042
630-240-9496 (cell)
Brad Hay Site Supervising Construction
Manager, Envirocon
678-822-3568 (cell)
Dan Allen Project Health & Safety Supervisor,
Envirocon
720-404-6325 (cell)
David Hardy Project Health & Safety Manager,
Envirocon
405-308-6115 (cell)
Ken Aukerman Construction Manager, Foth I&E 920-496-6780
920-917-3834 (cell)
Denis Roznowski Project Manager, Foth I&E 920-496-6756
920-819-3513 (cell)
Brian Symons RD QA Manager, Foth I&E 913-469-0686
913-940-0081 (cell)
Jim Hutchison Project Engineer, Foth I&E 920-496-6813
920-819-8015 (cell)
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #4
Page Nos. Page 3 of 4
Project Personnel Title Telephone Number Signature Date QAPP Read
Matthew Clark Project Engineer, Baird 608-273-0592
608-628-6186 (cell)
Chris Seider Project Health & Safety Officer,
Foth I&E
920-496-6819
920-562-0056 (cell)
Ron French Technical Staff, Foth I&E 314-682-1962
314-799-0056 (cell)
Brian Hanks Staff Engineer, Foth I&E 913-469-0686 x3816
Brian Sperrazza Project Geologist, Foth I&E 651-288-8584
612-219-8506 (cell)
Felipe Ortega Field Technician, Foth I&E 651-288-8585
507-350-8389 (cell)
Steve Lehrke Data Manager, Foth I&E 920-496-6894
920-562-0329 (cell)
Nick Azzolina Project Hydrogeologist, Foth I&E 920-857-6032 (cell)
Curt Dungey Air Quality Technician, Foth I&E 920-496-6918
920-606-6093 (cell)
Dan Tilly GIS/CAD/SharePoint Specialist,
Foth I&E
920-496-6924
920-246-6883 (cell)
Beth Schuh Administrative Asst., Foth I&E 920-496-6730
920-858-9193 (cell)
Janet Forrest Admin. Asst. (backup), Foth I&E 920-496-6811
Lori Kurowski Work Plan Coordinator, Foth I&E 920-496-6858
Andrea Martin Technical Staff, Foth I&E 920-496-6854
920-676-9230 (cell)
Mitch Vanderydt Technical Staff, Foth I&E 920-496-6792
416-579-5859 (cell)
John Starke Geotechnical Engineer, Foth I&E 651-288-8510
920-427-2661 (cell)
John Whitstone GIS/CAD Specialist, Foth I&E 920-496-6845
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #4
Page Nos. Page 4 of 4
Project Personnel Title Telephone Number Signature Date QAPP Read
Mike Nimmer Technical Staff, Foth I&E 920-496-6764
920-619-5905 (cell)
Mike Mason Technical Staff, Foth I&E 913-468-0686 x3814
Kris Gamble Construction QA Officer, Foth I&E 417-836-3630
417-861-6160 (cell)
Aaron Mika Environmental Engineer, Foth I&E 218-481-6012
715-817-5370 (cell)
Greg Parins Environmental Engineer, Foth I&E 920-496-6833
920-606-4651 (cell)
Scott Janssen Construction QA Officer, Foth I&E 920-496-6817
920-676-9780 (cell)
Marty Sturzl Technical Advisor, Foth I&E 920-496-6888
920-619-1978 (cell)
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #5
Page Nos. Page 1 of 1
QAPP Worksheet #5
Breakwater Construction Project Organizational Chart
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #9
Page Nos. Page 1 of 2
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\QAPP Worksheet 09 Rev_1 Add 1.docx
QAPP Worksheet #9
Project Scoping Session Participants Sheet
Site Name/Project Name: Ashland/NSP Lakefront Site Breakwater
Site Location: Ashland, Wisconsin
Date of Session: Multiple
Scoping Session Purpose: Multiple
Name Title Affiliation Phone # E-mail Address Project Role
Multiple
Comments/Decisions: Preliminary Design, Pre-Final Design, Final Design, QAPP Revision 1-Addendum 1, Weekly
Agency Meetings, Chapter 30 Permit Application for Breakwater
Action Items: Multiple
Consensus Decisions: Multiple
NOTE: Multiple scoping/technical sessions have been, and continue to be held.
Key Decision Points Influencing Monitoring Plan for Ashland Breakwater:
1. Potential PAH-impacted sediments not present in majority of Project area. Mobile silt curtains prove effective on TSS control
on navigational dredging projects in Great Lakes and allow for adjustment to handle changing water depths.
2. Turbidity monitoring to be used as surrogate for TSS.
3. Alert and Action TSS levels for Project consistent with those proposed for Phase 1 Pilot Project.
4. Provisions in Monitoring Plan for Ashland Breakwater to address sheen monitoring and procedures to address sheen, if
encountered.
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #9
Page Nos. Page 2 of 2
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\QAPP Worksheet 09 Rev_1 Add 1.docx
5. Sediment removal reviewed under CERCLA permit equivalency.
6. Breakwater construction reviewed under Chapter 30.
7. Monitoring for water quality impacts requires changing background and area of influence monitoring points due to varying
water currents driven largely by wind direction and speed.
8. Potential for large waves requires the use of handheld turbidity meter due to potential for permanent raft mounted meter to be
damaged.
9. Sediment to be tested following stabilization to properly dispose of or beneficially use on the Phase 1 Site.
10. Following sediment removal, stone placement for breakwater will commence and is not expected to have significant
environmental monitoring concerns due to very low percent fines in stone gradations.
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #10
Page Nos. Page 1 of 17
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
QAPP Worksheet #10
Problem Definition - Conceptual Site Model
Page
Introduction ............................................................................................................................. 3 1.
Site Preparation ....................................................................................................................... 4 2.
Site Security .................................................................................................................... 4 2.1
Pre-Construction Erosion Control Measures .................................................................. 4 2.2
Utility Abandonments and Protection ............................................................................. 4 2.3
Temporary Utilities ......................................................................................................... 4 2.4
Temporary Facilities ....................................................................................................... 5 2.5
Pre- and Post-Construction Inspections .......................................................................... 5 2.6
Erosion Control ............................................................................................................... 5 2.7
Sediment Removal .................................................................................................................. 6 3.
Mobilization and Site Set-Up ......................................................................................... 6 3.1
3.1.1 Wooden Dock Demolition .......................................................................................... 6
3.1.2 Marine Equipment Deployment .................................................................................. 6 3.1.3 Water Conveyance ...................................................................................................... 6
Sediment Removal/Unloading Equipment ..................................................................... 7 3.2
Site Demobilization ........................................................................................................ 7 3.3
Sediment Segregation, Staging, Pre-Processing and Disposal ............................................... 8 4.
Infrastructure Improvements Off-Loading System ......................................................... 8 4.1
Sediment and Debris Offloading .................................................................................... 8 4.2
4.2.1 Segregated Large Debris ............................................................................................. 8 4.2.2 Sediment with Debris .................................................................................................. 8 Hauling from East Peninsula to Sediment Processing Pad ............................................. 9 4.3
4.3.1 Infrastructure Improvements ....................................................................................... 9 4.3.2 Sediment Processing Pad, Sediment Transfer Pad (STP), and Load-Out Pad ............ 9
4.3.3 Operations ................................................................................................................. 10 Sediment Processing Operations .................................................................................. 10 4.4
4.4.1 Debris Removal at Sediment Processing Pad ........................................................... 10 4.4.2 Slack Drying and Soil Conditioning/Stabilization .................................................... 10 Sediment and Debris Transportation and Off-Site Disposal ........................................ 11 4.5
Dewatering Water Collection and Treatment ............................................................... 12 4.6
Breakwater Construction Operations .................................................................................... 14 5.
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #10
Page Nos. Page 2 of 17
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
Stone Materials Staging Area ....................................................................................... 14 5.1
Stone Handling and Loading ........................................................................................ 14 5.2
Control of Stone Placement Line and Grade ................................................................ 15 5.3
Stone Placement ............................................................................................................ 15 5.4
References ............................................................................................................................. 16 6.
Drawings from the Final Design for Ashland Breakwater
Drawing 2 Existing Conditions
Drawing 5 Site Plan and Haul Routes
Drawing 6 Dewatering Flow Plan
Drawing 8 Breakwater Plan View
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #10
Page Nos. Page 3 of 17
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
Introduction 1.
The purpose of the work described in this Remedial Action Quality Assurance Project Plan -
Revision 1, Addendum 1 for Ashland Breakwater (RA QAPP Addendum 1) is to construct a
breakwater to protect the Phase 2 sediment dredging activities. This RA QAPP Addendum 1 is
focused on work detailed in the Final Design for Ashland Breakwater (FE JV, 2015a) addressing
a specific portion of the offshore area outside of the designated remedial area. Numerous studies
and investigation have been performed to date in an effort to understand the Site contaminants
and conditions. The Conceptual Site Model within the URS Remedial Investigation Report
(URS, 2007) report and the Remedial Action Quality Assurance Project Plan - Revision 1
(FE JV, 2014) detail the history of the site and the known contaminants and their suspected
sources and extent. The Monitoring Plan for Ashland Breakwater (FE JV, 2015b), which is
Appendix F in the Final Design, details the performance standards to be evaluated along with a
summary of the known key sediment parameters in the vicinity of the construction area.
The following sections of this RA QAPP Addendum 1 present the Scope of Work for
construction of the Ashland/NSP Lakefront Site breakwater (breakwater). The breakwater
design and construction will be performed by the Foth Infrastructure & Environment/Envirocon
Joint Venture (FE JV). The FE JV is supported in the breakwater design by W.F. Baird &
Associates Ltd. (Baird) and J.F. Brennan Company, Inc. (Brennan). Additional marine
contractors will be selected for actual breakwater construction.
The focus of the work to be performed is construction of the breakwater. PAH-impacted
sediments from the Ashland/NSP Lakefront Site may be present in the eastern portion of the
dredging operation. However, most of the work described in subsequent sections of this
worksheet will be outside of potentially impacted areas. Thus the primary focus of the
monitoring for this project is on turbidity/total suspended solids, as for a typical navigational
dredge operation. However, water column samples will be collected in the eastern 400 feet of
the propose breakwater structure during sediment removal to monitor for the presence of
contaminants of concern, consistent with the proposed Wet Dredge Pilot Study (Anchor QEA,
2015).
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #10
Page Nos. Page 4 of 17
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
Site Preparation 2.
The following describes certain general tasks to be completed in preparation for breakwater
construction. Due to Phase 1 RA activities that have preceded the proposed breakwater
construction, site preparation activities will be minimal. One specific site preparation activity
under evaluation is the use of a water-side facility for stone material staging. The stone staging
location would provide for a material (stone) stockpiling area and a location to load stone
materials onto barges for subsequent placement and construction of the breakwater.
The connection of the breakwater wall to the mainland will be to the western arm of the Prentice
Avenue Boat Launch (also referred to as the east peninsula) in the Kreher Park area. This site
will serve as the main access point for the unloading of sediment and debris material into tandem
dump trucks with sealed tailgates for transport to the materials staging/processing area.
Drawing 2 shows the existing site conditions, the proposed breakwater footprint and the location
of the proposed stone materials staging area.
Site Security 2.1
Access to the Kreher Park portion of the Phase 1 RA area (proposed for use in sediment
staging/processing, dewatering and water treatment) will be secured during execution of this
activity. Temporary traffic controls will be implemented, as necessary, in the vicinity of work
areas in and near city streets.
Pre-Construction Erosion Control Measures 2.2
Erosion control measures will be implemented to meet best management practices (BMP) at all
areas where land disturbance will occur in excess of required minimum limits. It is expected that
erosion control measures will be necessary for: 1) sediment dewatering activities in the Kreher
Park portion of the Phase 1 RA area, 2) site preparation activities on the east peninsula that
extends from the Prentice Avenue Boat Launch parking lot to the proposed breakwater
connection, and 3) the stone materials staging area. Sediment staging and dewatering areas to be
used for the breakwater construction project will include pads already constructed and currently
occupied by Allsite and Mahaffey structures or other Site areas used for the Phase 1 RA
activities (Drawings 2 and 5). The Allsite structure was removed in April 2015.
Utility Abandonments and Protection 2.3
Existing utilities within the Phase 1 RA area and within the breakwater footprint area will be
identified through Wisconsin Diggers Hotline and protected as necessary for safe execution of
the work. Known utilities within the Phase 1 RA area shown on Drawings 5 and 6, including
utilities installed in support of the Phase 1 activities.
Temporary Utilities 2.4
Electric service is required for the operation of pumps, air monitoring devices, lighting, and other
support activities. New transformers for electrical services were established for the former
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #10
Page Nos. Page 5 of 17
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
Allsite structure and the Temporary Water Treatment System (Temporary WTS) and protected
with 3,000 lbs concrete blocks where on-site traffic was/is expected.
Temporary Facilities 2.5
The existing field office located at the northeast corner of 3rd Avenue and U.S. Highway 2 will
be used for the breakwater project. Additionally, the breakwater construction contractor will
establish an office trailer near the stone materials staging area.
Pre- and Post-Construction Inspections 2.6
Pile driving, large truck traffic, and other construction activities could potentially damage nearby
facilities and roadways. Pre-construction conditions and post-construction conditions will be
documented by photography, videos, and documented inspections.
Erosion Control 2.7
Grading for haul roads and working areas will be established in the Kreher Park area prior to
construction of the breakwater. Similarly, haul roads and stockpile areas will be prepared at the
stone materials staging area. Drainage control for these areas will focus on limiting run-on and
run-off to/from work areas. Details for erosion controls are presented on Drawing 11.
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #10
Page Nos. Page 6 of 17
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
Sediment Removal 3.
Mobilization and Site Set-Up 3.1
Mobilization of sediment removal personnel and equipment to the Ashland location is expected
to take approximately three weeks. A pre-construction bathymetric survey will be obtained to
document existing mudline conditions in the proposed breakwater footprint.
3.1.1 Wooden Dock Demolition
The deck will be removed with an excavator and placed in roll off containers or trucks for direct
local landfill disposal or on-site sizing, if necessary, prior to disposal. The pilings will be
removed utilizing conventional removal methods. The condition of the pilings is not currently
known. Older pilings have a tendency to break off at the ground/mudline. The team will work
to remove all pilings, as necessary, to allow for sediment removal and breakwater construction.
Pilings will be inspected and if suspected of being or are impacted with tPAH, they will be
disposed of at the VONCO landfill Subtitle-D disposal facility, located in Duluth, Minnesota.
Non-impacted pilings and deck boards will be disposed of at the Ashland Construction &
Demolition Landfill facility.
3.1.2 Marine Equipment Deployment
FE JV will deploy to the water sectional barges, an excavator for the sediment removal plant, as
well as a small tugboat for movement of material barges and additional ancillary equipment, as
necessary. All waterborne equipment deployments will take place at the city marina, as
coordinated with the marina operator. Two great lakes hopper barges for the active storage and
transport of excavated materials will be mobilized to the area as well. The off-loader will be
staged on a barge and will be used to off-load sediments from hopper barges to haul trucks.
Containment curtains or material slides may also be used in order to capture any leakage from
the off-loader bucket that may occur. The off-loading of excavated materials shall be done in a
clean and efficient manner.
3.1.3 Water Conveyance
Residual water remaining in the hopper barges will be removed by an on-site dewatering system.
Once a loaded hopper barge is brought to the off-loading area, the majority of the residual water
will be removed by pumping it to a pretreatment filtration geotextile bag (geobag) system prior
to pumping to the existing Temporary WTS. A small hydraulic submersible pump, as shown on
Illustration 4-24, will be placed into the barge prior to sediment being off-loaded. This 3-inch
pump has the ability to pass 1.5-inch solids and will be suspended into the barge just below the
water surface. The pump will transport the water via a 4-inch high density polyethylene (HDPE)
pipe to the initial water filtration facility. This type of pipe is heat fused so that there are no
mechanical joints that could possibly leak. The pump-off work is performed by a deckhand who
will be stationed on the off-load barge. In this way, the operator of the material handler (off load
machine) does not have responsibility for any of the water pumping duties and can focus on
loading trucks.
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #10
Page Nos. Page 7 of 17
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
Off-loading will begin on the opposite end of the hopper barge from the pump which causes the
barge to list towards the pump. This aids in decanting the water from the sediment as the water
gravitates towards the pump.
During the dewatering process some silt, sand, and small debris will enter the pump-off system.
The hydraulic pump is equipped with a grated screen over the intake to prevent large debris from
entering. This particular pump has been chosen because it has enough total dynamic head (TDH)
and horsepower to adequately pump the turbid water to the initial water filtration system.
Sediment Removal/Unloading Equipment 3.2
For the removal of sediments and debris, FE JV will utilize a Liebherr 954 excavator equipped
with specially designed, environmental level cut bucket (Illustration 4-25) on a sectional barge
with a built in moon pool, encompassed by a turbidity curtain. The excavator will remove
woody debris and sediment with the environmental bucket inside the moon pool and place the
materials into adjacent hopper barges. Large debris, anticipated in the form of dimensional
timber or trees, will be placed into roll-off boxes located on the marine plant and transported to
the off-load area where it will be off-loaded for disposal. The specialized environmental bucket
was chosen due to its ability to sufficiently handle debris such as the timber present on the
lakebed at the Site. It has the ability to “pinch” closed and not allow free material from exiting
the bucket, while trapping minimal free water in the process.
Two hopper barges, with a capacity of approximately 600 cy each, will be used to transport
sediment to the off-loading area. Two barges were chosen for maximum efficiency of the
process and limited operating space. One barge will be loaded at the marine plant while the
other can be unloaded at the off-load area. These hopper barges will be moved to the off-load
area by a vessel selected from FE JV’s fleet of push boats. Depending on allowable drafts, it is
likely the full capacity of the hopper barges will not be utilized. Cycle times will be adjusted to
the most efficient loading capacity.
Once a barge arrives at the off-load area, it will be off-loaded by a barge-mounted hydraulic
material handler utilizing a clam bucket. The material will then be loaded into tandem dump
trucks, equipped with sealed tail gates. Remaining free water within the barge, which is
anticipated to be no more than 40,000 gallons per day (average of approximately 24,200 gallons
per day is expected), will be hydraulically pumped to a geobag located as shown in Drawing 6
for initial filtration, then to a 100,000 gallon modutank, before processing through the existing
on-site Temporary WTS.
Site Demobilization 3.3
At the completion of all sediment removal activities, all sediment removal equipment will be
removed from the Site. All areas used during the sediment removal and off-loading operations
will be restored. The off-load platform will be removed at the request of NSPW but could
possibly stay in place for the Phase 2 RA. FE JV anticipates demobilization to take about one
week to complete.
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #10
Page Nos. Page 8 of 17
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
Sediment Segregation, Staging, Pre-Processing and 4.
Disposal
The following section describes off-loading operations of the sediment transport barges at the
east peninsula.
Infrastructure Improvements Off-Loading System 4.1
Once a haul road is constructed on the east peninsula, as further discussed in Section 4.9, FE JV
will construct an unloading and staging area. The purpose of the marine unloading area is to
provide a point at which all hopper barges can be efficiently unloaded into trucks. The location
of the off-load area is immediately outside the footprint of the breakwater, on the northwestern
corner of the east peninsula as shown on Drawing 5. The purpose of locating the off-loading
area here is to take advantage of the greatest water depth, while still not infringing on the
breakwater footprint or the boat landing.
Sediment and Debris Offloading 4.2
Once a hopper barge arrives at the off-load area, sediment will be off-loaded, utilizing a barge-
mounted hydraulic material handler employing a clamshell bucket, into tandem dump trucks
with water tight sealed gates. The off-loading material handler and trucks will be staged in a
manner to minimize the reach from the barge to truck.
4.2.1 Segregated Large Debris
Large amounts of organic debris in the form of dimensional timber, trees and/or piling is
expected to be encountered. Large pieces removed during the sediment removal process will be
segregated and temporarily stored in roll-off boxes on the marine plant. On a periodic basis, or
when the roll-off container is full, the marine plant will be moved to the off-load area; and the
roll-off will be lifted and set on the peninsula and transferred, via roll-off truck, to the former
Allsite pad (Drawing 5). The box will be dumped, as necessary and wood debris will be
properly sized for acceptance at VONCO landfill. Once sized, the debris will be loaded back
into the roll-off box utilizing a mini-excavator with thumb attachment, manifested and ready for
shipment to VONCO landfill. Smaller debris will be mixed with conditioned sediment and
loaded for transport and disposal at the Load-out Pad (LOP).
4.2.2 Sediment with Debris
During the sediment removal process smaller debris that remains co-mingled with the sediment
will not be segregated. For the off-loading process, a spill apron will be placed on the ground
between the material handler and truck to collect any residual sediment that falls from the
bucket. Additionally, plastic will be placed on the fence, adjacent to the truck, to prevent any
splattering of sediment on the rip-rap on the east side of the haul road. Once the truck is loaded,
the tailgate, side boards, and wheels will be cleaned with brooms, as necessary, before
proceeding to the sediment processing pad (SPP).
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #10
Page Nos. Page 9 of 17
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
Hauling from East Peninsula to Sediment Processing Pad 4.3
4.3.1 Infrastructure Improvements
Several improvements are required on-site to facilitate the hauling of materials from the off-
loading area to the sediment processing pad. Within the footprint of the east peninsula,
improvements will occur once erosion and sediment controls have been installed. Such controls
include silt fence and/or sediment filtration tubes (wattle) installed around the perimeter of the
peninsula. On the east side of the peninsula, temporary fence panels will be installed from the
north end of the peninsula extending south along the top of bank, and further south just west of
the existing Prentice Avenue Boat Launch boardwalk and then tying into the existing fence along
the east side of Prentice Avenue. Additionally, light poles that exist within the middle of the
peninsula must be relocated to an alignment just west of the boardwalk and fence in order to
provide lighting to boaters at night. Several trees will need to be removed within the peninsula
to allow for construction of a haul road. See the planned site plan and haul routes indicated on
Drawings 5 and 6.
A gravel haul road will be constructed from the north end of the peninsula to northern edge of
the existing asphalt pad (former Allsite pad). Another gravel haul road will be constructed from
the west end of the asphalt pad (formerly the treated soil bin stockpile area) and it will traverse
north of the existing Temporary WTS to the SPP. The haul roads will be constructed of
approximately 6 inches of 1-1/2-inch stone (poorly sorted) over 12 inches of breaker rock, which
is underlined by non-woven geo-fabric. Road widths vary, but generally are proposed at 14-feet
wide. A D5 dozer and rubber tire wheel loader will place the breaker rock, while the dozer will
be used to place the smaller stone. Compaction of the smaller stone will be completed with a
vibratory roller with aid of water, as needed.
The haul road that exits the peninsula crosses the existing shoreline bulkhead sheet pile wall and
will be located west of an existing storm water drain inlet. This inlet is protected with wattle.
Course stone (rip-rap) will be placed on the south side of the wall to allow storm water to flow
from the west to the inlet. Gravel will be placed over the wall and 1 inch thick road plates will
span the wall alignment in order to dissipate the load across the wall. The haul road that
traverses north of the Temporary WTS will cross an existing storm water drainage swale. To
bridge this swale, a 38 x 24 inch arched CMP will be installed, with the haul road constructed
above it.
4.3.2 Sediment Processing Pad, Sediment Transfer Pad (STP), and Load-Out Pad
Drawing 5 depicts the location of the three main pads that are used for sediment processing
operations. Sediment management capabilities are sized to accommodate an expected high-side
average of 600 cy of in-place sediments per day, 7 days per week. The SPP consists of the pad
that was constructed for the Wet Dredge Pilot Study (Anchor QEA, 2014) sediment processing,
located west of the Temporary WTS. This pad is enclosed by a Mahaffey fabric structure where
sediment debris removal, slack drying and conditioning with reagent will take place. Adjacent to
the SPP, is the STP area (not enclosed) where dried and conditioned sediment will be staged and
loaded for transfer to the former Allsite pad located to the east and north side of Kreher Park
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #10
Page Nos. Page 10 of 17
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
project area. This pad will be used to stage and stockpile conditioned sediment and debris for
load-out for off-site transportation and disposal at the VONCO landfill and is denoted as the
LOP.
4.3.3 Operations
Tandem trucks will be used to haul the off-loaded sediment from the sediment off-loading area
to the SPP. Large debris that has been segregated during sediment removal operations in
containers is hauled to the LOP for final sizing and load-out to transportation and disposal.
Sediment containing smaller debris will be hauled to the SPP, where smaller debris may be
removed, and the sediment is slack dried and conditioned using pebble lime reagent or alternate
material as defined in the specifications. From the STP, the material will be loaded into an
articulated truck for staging at the LOP where the conditioned sediment and debris, confirmed to
pass the paint filter test, will be loaded for transportation and disposal to VONCO landfill.
Once in the structure, the material will be dumped where necessary to be strategically introduced
into the processing sequence. Empty trucks may exit at the west end of the structure depending
on the current activities in the structure or on the STP, which is east of the SPP and Mahaffey
structure. Once emptied, trucks will proceed back to the east peninsula platform. To avoid
congestion along the haul route, empty trucks traverse the haul south of the Temporary WTS,
then turn toward the LOP and access the newly constructed haul road (Drawing 5).
Sediment Processing Operations 4.4
Sediment and debris processing operations include operations conducted on the SPP, STP, and
LOP. The objective is to produce a final product that is loaded for transportation and disposal at
the VONCO landfill after it is verified to meet acceptance criteria, which includes passing the
paint filter test and meeting the waste profile characterization.
4.4.1 Debris Removal at Sediment Processing Pad
Large debris will be removed, segregated and staged at the LOP during sediment removal
operations for sizing. Sediment containing smaller wood/debris will be hauled and dumped on
the SPP. Operations personnel subsequently will use a trackhoe bucket with thumb to process
and pick out the larger remaining wood and debris pieces and segregate it. Segregated wood and
debris will be transported to the LOP for final sizing, if necessary, and load-out. Smaller wood
debris remains in the sediment will be stabilized along with the sediment without adverse effect
to the slack drying and sediment conditioning operations.
4.4.2 Slack Drying and Soil Conditioning/Stabilization
The objective of processing the sediment is to meet VONCO landfill disposal acceptance criteria,
which includes passing the paint filter test. The dredged sediment will be primarily fine sand, at
times, containing some silt and woody debris. At the SPP, the sediment will be further decanted,
dried and conditioned as necessary before being loaded for staging at the LOP and finally loaded
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #10
Page Nos. Page 11 of 17
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
for off-site transportation and disposal. The dredge spoils will be placed on the SPP, mixed and
stockpiled for decanting, drying and stabilization.
Based on treatability tests and experience, some conditioning reagent is added to the sediments
to aid in slack drying in order to pass the paint filter test. FE JV proposes to use a granular
pebble quick-lime product provided by Graymont Corporation of Superior, Wisconsin. This
product was used successfully during the Phase 1 Upland Remediation project in 2014. It is
expected that approximately 2%-3% of pebble lime will be used to complete slack drying and
conditioning. It will be introduced at an early stage in the slack drying operations. A front-end
loader will be used to mix the pebble lime in with the sediments in discrete batches. Operations
personnel will ensure that potential dust and odor generation is minimized during reagent mixing
operations.
After the sediment has been initially mixed, operations personnel will again mix and stack the
sediment an average of approximately 4 feet in height. Mixing and slack drying will continue as
needed for proper conditioning of the sediment. The high average projected daily sediment
removal rate is 600 in-place cy per day. The average planned storage time for sediment on the
SPP is more than 4 days. The average daily stabilization rate corresponds to the high average
daily sediment removal rate of approximately 600 in-place cy per day.
Operations personnel will air-dry the sediments by bucket-turning stockpiled materials using a
loader. The weight of the stockpile will aid in passive gravimetric dewatering. All decant water
(as well as any precipitation contact water from the STP) will be collected on the SPP an STP in
the collection swale sump and pumped from the northeast end of the STP to the Temporary WTS
for treatment.
Ellis Avenue will be used for access for lime delivery. Bulk loads of pebble lime will be
delivered to the inside of the Mahaffey structure on the SPP. From there, the pebble lime will be
off-loaded and used as needed for conditioning sediments. The lime will be delivered into the
west side of the Mahaffey structure to keep vehicle delivery tires in a clean condition. If needed,
based on prevailing conditions, tires will be decontaminated at exit.
Sediment and Debris Transportation and Off-Site Disposal 4.5
Conditioned sediment will be staged at the LOP for load-out to an off-site disposal facility, or for
beneficial use if an appropriate end use can be identified and approved. Tarps will be used as
necessary to cover stockpiled materials to minimize precipitation water impacts to the LOP, or
fugitive dust generation. A WA380 front-end loader (or equivalent) with bucket scale will be
used to load trucks for hauling off-site. This loader can also handle geobag change-outs when
necessary. The anticipated hauling quantity is expected to be approximately 500 tons per day at
five days per week, based on vendor hauling capacity availability.
The haul route for the off-site haul trucks are indicated on Drawing 5. The trucks access from
Prentice Avenue and enter the LOP from the east entrance. From the LOP, the sediments and
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #10
Page Nos. Page 12 of 17
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
debris which are verified to meet the disposal criteria will be loaded onto haul trucks for off-site
transportation and disposal. Passing the paint filter test will be verified before loading. A rubber
tired front-end loader with bucket scale will be used to load the 22-ton capacity trucks. The scale
will be calibrated and checked weekly and allows trucks to be loaded to within 100 pounds of
optimal loads, without exceeding Wisconsin Department of Transportation regulations. The
loader will have the back-up alarm turned off until 7:00 a.m. and uses a strobe light during night
times of operation.
Before exiting, trucks pulls forward and engage the tarp system. The trucks will be inspected
and dry decontaminated with a broom, as needed. A manifest will be provided to the driver for
the VONCO landfill. The loaded trucks will egress from the northeast corner of the LOP back
onto Prentice Avenue. It is expected that approximately 25 trucks will be loaded and shipped per
day on average. Load-out operations will occur from 6:00 a.m. to 5:00 p.m., Monday through
Friday, with possible operations of 6:00 a.m. to noon on Saturdays.
Dewatering Water Collection and Treatment 4.6
Dewatering operations to be conducted in support of the sediment removal operations include the
following sources of water generated to be collected and treated in the Temporary WTS:
Barge decant water from sediment transport barges
Decant water from SPP operations
Precipitation water to be collected and treated from STP and LOP
These sources and estimated volume and flow rates are discussed further below. Drawing 6
presents the flow path for collected dewatering flows. In general, the dewatering flow
management includes the following approach:
Barge decant water from sediment transport barges.
This water is pumped during and after sediment off-loading operations from the off-
loading area. The operations are discussed in Section 4.7, but basically include pumping
to a geobag for primary filtration, then to a 100,000 gallon Modutank #1 for settling and
surge storage (both located on the south side of the LOP), and ultimately pumping to the
Temporary WTS for treatment via Middle Sump #2 on the LOP.
SPP decant water.
This water is collected and pumped from the northeastern end of the SPP/STP drainage
swale sump to a 100,000 gallon Modutank #2 for storage and sedimentation (located on
the northern portion of Kreher Park), and subsequently pumped to the Temporary WTS
for treatment.
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #10
Page Nos. Page 13 of 17
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
Precipitation contact water from STP and LOP.
The water from the STP is pumped to the Temporary WTS via the drainage sump at the
northeastern end of the SPP/STP to the Modutank #2. Precipitation contact water from
the LOP is pumped via Sumps #1, #2, and #3 to the Temporary WTS directly for
treatment. If significant storm events occur (e.g., greater than 1-inch rain event), the
contact water from the LOP may be pumped to either Modutank #1 or #2 as available for
surge capacity storage.
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #10
Page Nos. Page 14 of 17
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
Breakwater Construction Operations 5.
Stone Materials Staging Area 5.1
The Bay Front bulkhead wall, to be utilized for staging and loading of stone (Drawing 7), will be
fenced to prevent unauthorized pedestrian and vehicle traffic. Signs will be posted which
delineate the area as a hard hat construction zone and to identify truck routes.
Two improved minimum 22-foot wide gravel road surfaces will be installed from the proposed
stone stockpile area through cuts made in the berm on the east side of the site to provide access
from the stockpile area to the barge loading area. (Detail 3/11, Drawing 11). At the entrance to
the stone stockpile area a gravel tracking pad will be constructed to help control tracking of
material onto city streets by trucks (Detail 2/11, Drawing 11). Any material tracked on to the
public roads would be promptly cleared. The laydown area for stone stockpiling will be
prepared with an isolation barrier to prevent coal from contaminating the breakwater stone.
Crane mats will be used as needed to create a stable surface for stone loading onto barges along
the east wall of the Bay Front bulkhead wall. A loading ramp will be used to provide drive-on
access for loaders directly onto the barges for transport of bedding, core and filter stone. Light
duty, three-pile, clusters will be installed along the ramp area of the bulkhead wall face to hold
the barges off the wall while loading and to accommodate the downward position of the loading
ramp and to prevent barges from contacting and damaging the wall.
A crane barge will also tie up to the bulkhead wall area and self-load armor stone that is fed to it
by front end loaders.
Stone Handling and Loading 5.2
Bedding, core, and filter stone brought to the Bay Front site via truck will be dumped on the
prepared pad and pushed up into the stock pile. Armor stone brought to the site via truck and
semi-trailer will be unloaded with a loader equipped with forks. Bedding, core, and filter stone
will be loaded onto deck barges using rubber tire front-end loaders. They will travel to the
bulkhead wall face on the constructed road cut through the berm and enter the barge via a ramp.
The ramp will have a hinge point so that it is in a downward position when barge loading
commences and in an upward position upon completion. The two deck barges used to transport
stone will be equipped with 4 foot tall timber sidewalls to contain the stone and prevent the
loader from driving off the edge.
Armor stone will be loaded by a crane barge positioned along the east side of the bulkhead wall.
Armor stone will be loaded using a stone grab bucket by moving the stone directly from a stone
staging area (small stockpile formed by loaders) within the crane’s reach.
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #10
Page Nos. Page 15 of 17
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
Control of Stone Placement Line and Grade 5.3
A hydrographic survey of the breakwater area and stone loading area will be performed prior to
stone placement. Piles will be driven along the centerline of the proposed breakwater structure at
100-foot spacing to delineate a visual alignment for the stone placement crew (Drawing 8).
Batter boards will be attached to these piles at the maximum upper tolerance of the under layer
limit and then later at the upper limit of the armor stone layer. These batter boards will allow the
stone placement crew and QC personnel to easily monitor stone placement progress along the
water line. A gage board will be set using a total station for use in sounding stone underwater as
it is placed. Soundings will be performed manually by a crew member working off a raft aligned
perpendicular to the centerline of the structure. Distances from the centerline of the structure
will be marked on the ramp and soundings will be taken to verify stone placement as it takes
place and in advance of any QC survey. Upon completion of any layer and before it is covered
with the next size stone, QC surveys will be performed with a total station in accordance to the
specifications.
Stone Placement 5.4
Bedding, core and filter stone (Drawing 9) will be placed by a crane barge equipped with an
approximate 100-ton crane. It will utilize a seven tine rock grapple bucket to place the stone.
Stone placement will be verified by the placement crew by pole sounding and by visual
observation sighting across the batter boards. Two deck barges will be used for this operation.
One barge will be at the Bay Front site being loaded while the other is at the breakwater
placement site. The barges will work in a cycle, constantly supplying stone to the placement
derrick. A tug will tow the loaded barge over to the placement derrick and swap out the empty
barge. Completed bedding and core stone will not be placed more than 100 feet in advance of
filter stone to prevent damage from inclement weather.
Armor stone will be placed by the large crane barge with a 140-ton crane. This barge has
enough deck space and capacity to carry 350 ton of stone on its own deck. The armor stone will
be placed utilizing a 4-finger stone grab. The line and grade of all stone will be verified by the
placement crew as stone is set. Barges loaded with stone at the Bay Front bulkhead wall will be
towed to the project site where the stone will be placed to build the breakwater. When the stone
has been emptied from the deck of the barge, it will be towed back to be loaded again and start
another cycle.
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #10
Page Nos. Page 16 of 17
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
References 6.
Anchor QEA, LLC, 2015. Monitoring Plan Wet Dredge Pilot Study – Ashland Lakefront
Superfund Site. Prepared for Northern States Power – Wisconsin. January 2015.
Foth Infrastructure & Environment/Envirocon Joint Venture, 2015a. Final Design for Ashland
Breakwater – Ashland/NSP Lakefront Site. July 2015.
Foth Infrastructure & Environment/Envirocon Joint Venture, 2015b. Monitoring Plan for
Ashland Breakwater, Appendix F of the Final Design for Ashland Breakwater –
Ashland/NSP Lakefront Site. July 2015.
URS, 2007. Remedial Investigation Report Ashland/Northern States Power Lakefront Superfund
Site. August 31, 2007.
U.S. Environmental Protection Agency, 2010. Record of Decision. September 2010.
U.S. Environmental Protection Agency, 2012. Consent Decree between the United States,
Wisconsin, Northern States Power Company, and the Bad River and Red Cliff Bands of
The Lake Superior Tribe of Chippewa Indians. June 2012.
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 10 Rev 1 Add 1.docx
Drawings from the Final Design for Ashland Breakwater
N
1, 7 4-6,0DD E
1,745,000 E
+
524,000 N
523,000 N
LEGEND PROPOSED SEDIMENT REMOVAL
----- FOR BREAKWATER CONSTRUCTION
--595 - EXISTING CONTOUR (SEE NOTE 2)
KREHER PARK AREA
522,000 N
NOTES:
1. COORDINATE SYSTEM - WISCONSIN STATE PLANE, NORTH ZONE. U.S FEET. HORIZONTAL DATUM IS NAD83. VERTICAL DATUM IS NAVD88.
2. THE BASE MAP CONTOURS COMPILED FROM THE FOLLOWING SURVEYS:
UPLAND SURVEY FROM FOTH/ENVIROCON JOINT VENTURE DATED MAY, 2015. BROWN CONTOURS.
BATHYMETRIC SURVEY PERFORMED BY J.F. BRENNAN. ON 06/12/2015. ORANGE CONTOURS.
BASE MAP MODIFIED FROM OCTOBER 12. 2012 IMAGERY. FEATURES ALTERED TO REFLECT ANTICIPATED CONDITIONS POST -PHASE 1 RA.
521,000 N
0
EXISTING CONomoNS
HORIZONTAL SCALE:
200'
2
z Ui z 8 "' 3E
400'
• 201~ FOTH INFRASTRUCTURE tt ENVIRONMENT, U.C
LEGEND
Loading and Disposal Haul Route
Sediment Haul Route
Stabilized Sediment Transport Route
NOTES:
1. BASE MAP FEATURES (MONITORING WELLS, FENCES, BUILDINGS, ROADS) AND UTILITIES ARE CURRENT AS OF JUNE, 2015
2. BASE MAP PREPARED FROM OCTOBER 12, 2012 IMAGERY.
0
~ ... i • E I ~~
~~~ 0~8! i"~ ~~~ ~~.; ~i~
UlOa~
§~~~ ~fl;~~ g:~o of2~i
~r=~ g t; w::;"'=> ~og~ ~~~~ ~ ,_ r
~ g
~
~ 5
~ ~
z Ui z 8 "' 3E
SI1E PLAN AND
HAUL ROUTES
HORIZONTAL SCALE:
50' 100'
5 • 201~ FOTH INFRASTRUCTURE tt ENVIRONMENT, U.C
LEGEND
----e•• Existing Pipeline
Proposed Pipeline
NOTES:
1. BASE MAP FEATURES (MONITORING WELLS. FENCES, BUILDINGS, ROADS) AND UTILITIES ARE CURRENT AS OF JUNE. 2015
2. BASE MAP PREPARED FROM OCTOBER 12, 2012 IMAGERY.
0
DEWATERING FlDW PLAN
HORIZONTAL SCALE:
60'
6
z Ui z 8 "' 3E
120'
• 201~ FOTH INFRASTRUCTURE tt ENVIRONMENT, U.C
523,500 N
523,000 N
522,500 N
N
LEGEND ~595~ EXISTING CONTOUR
(SEE NOTE 2)
BREAKWATER SLOPE INTERCEPT LINE
----- BREAKWATER CONSTRUCTION AREA
NOTES: 1. COORDINATE SYSTEM - WISCONSIN STATE PLANE,
NORTH ZONE. U.S FEET. HORIZONTAL DATUM IS NAD83, VERTICAL DATUM IS NAVOBB.
2. NAVD88 601.0' = 0.0' LOW WATER DATUM (LWD).
3. NAVIGATION AIDS TO BE APPROVED BY USCG PRIOR TO INSTALLATION.
4. THE BASE MAP CONTOURS COMPILED FROM THE FOLLOWING SURVEYS:
UPLAND SURVEY FROM FOTH/ENVIROCON JOINT VENTURE DATED MAY, 2015. BROWN CONTOURS.
BATHYMETRIC SURVEY PERFORMED BY J.F. BRENNAN. ON 06/12/2015. ORANGE CONTOURS.
5. BASE MAP MODIFIED FROM OCTOBER 12, 2012 IMAGERY. FEATURES ALTERED TO REFLECT ANTICIPATED CONDITIONS POST -PHASE 1 RA.
521,500 N
0
BRE'AKWAlER PLAN VIEW
HORIZONTAL SCALE:
100'
8
z Ui z 8 "' 3E
200'
• 201~ FOTH INFRASTRUCTURE tt ENVIRONMENT, U.C
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #11
Page Nos. Page 1 of 1
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 11 Rev 1 Add 1.docx
QAPP Worksheet #11
Project Quality Objectives - Systematic Planning Process Statements
The overall objective is to monitor environmental conditions within the water column of
Chequamegon Bay during sediment removal and breakwater construction activities. PAH-impacted
sediments above the site-specific cleanup goals may be present in the eastern 400 feet of the
proposed breakwater footprint and will be removed and disposed off-site. Only changed or updated
Worksheet #11 information, relevant to the breakwater project, is presented here; otherwise refer to
the RA QAPP, Revision 1 (FE JV, 2012).
WHAT WILL THE DATA BE USED FOR?
Turbidity monitoring data will be used to assess the effectiveness of suspended sediment
containment and control Best Management Practices (BMP) in place to maintain water quality in
Chequamegon Bay during sediment removal in the breakwater footprint and subsequent
construction of the breakwater. In the eastern 400 feet of the proposed breakwater footprint,
monitoring for contaminants of concern in the water column will confirm if turbidity monitoring is
a good surrogate for monitoring potential mobilization of PAH-related compounds during sediment
removal activities. The specific monitoring approach is described in the Monitoring Plan for
Ashland Breakwater (Monitoring Plan) submitted as Appendix F to the Final Design for Ashland
Breakwater (FE JV, 2015).
WHAT TYPES OF DATA ARE NEEDED?
Water turbidity via field instrumentation will inform the field team regarding whether BMPs
employed during sediment removal and breakwater construction are below the Alert and Action
levels established for the project in the Monitoring Plan, as well as when water conditions are
suitable to move the turbidity barriers (moon pool) as the dredging progresses.
WHERE, WHEN, AND HOW SHOULD THE DATA BE COLLECTED/GENERATED?
The samples will be collected from the water column in Chequamegon Bay in a manner as
described in the Monitoring Plan. Sampling will be performed at the specified frequency in that
document.
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheets #14 and #16
Page Nos. Page 1 of 1
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 14 and 16 Rev 1 Add 1.docx
QAPP Worksheet #14 and #16
Project Tasks and Schedule
The current project schedule, including a detailed breakdown of project tasks, is included in the
Final Design for Ashland Breakwater (FE JV, 2015) as Appendix G.
Title
Revision No.
Revision Date
Section No.
Page Nos.
Matrix
Code Location
Rounds of
Sampling(3)
Field
Duplicates
Eqpt.
Blanks MS/MSD
Field
Parameters
Field
Instrument
Used
Laboratory
Parameters
Laboratory
Analytical Method
Sample
Preservation Sample Container
Sample
Holding
Time
# Sample
Tests
VOCs EPA 8260NaHSO4, MeOH, 4
C3 - 40 ml Vials 14 Days 61
SVOCs EPA 8270 4° C 1 - 1 L amber jar 7 Days 61
Sulfide SM 4500-S2Zinc Acetate,
4° C250mL - plastic 7 days 61
TSS 2540D 4° C 1 - 100 ml plastic jar 7 Days 61
Total Organic
CarbonSW 9060 HCL, 4° C 250mL - plastic 28 days 61
All Dredging
Areas4 2 1,600 None None None YSI 6 Series None None None None None 12,800
1 1 1 1 1 TVOCsMiniRAE
3000 PIDNone None None None None 13
2 1 None None NonePM10
particulates
Thermo
Scientific
DataRAM 4
None None None None None 20
1 Details of the sampling and monitoring to be performed can be found in Sections 3 and 5 of the Monitoring Plan for Ashland Breakwater , Appendix F to the Final Design for Ashland Breakwater . Prepared by: mgm
2 The number of samples reflects the number of samples per round of sampling where applicable. Surface water samples will be collected for water quality analyses from 3 locations plus a Checked by: kda1
background location at two water depth intervals twice per week during sediment removal in the eastern 400 ft section of the proposed breakwater.
3 15 days Duration of sediment removal in the eastern 400 ft of breakwater area, during which water quality samples will be collected.
25 days Duration of sediment removal, during which turbidity monitoring will be conducted every two hours (assuming a 14 hour work day).
60 days Duration of breakwater construction, during which air quality samples will be collected.
Air
Sampling Summary(1)
Ashland/NSP Lakefront Site - Breakwater
Sample Matrix
(see Matrix Code)
Number of
Locations /
Samples(2)
Water Quality
Meter
YSI 6 Series
Eastern End of
Dredging Area
Water Column
Air Monitoring
Locations10A
5 5 3Temperature
TurbiditySurface Water SW
4 2 6
RA Quality Assurance Project Plan
Revision 1, Addendum 1
July 2015
QAPP Worksheet #20
Page 1 of 1
QAPP Worksheet #20
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 20 Rev 1 Add 1 - Sampling Summary.xlsx Sampling
Title:Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #21
Page Nos. Page 1 of 1
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 21 Rev 1 Add 1.docx
QAPP Worksheet #21
Project Sampling SOP References Table - Breakwater Construction
Reference
Number Title
Revision
Date
Originating
Organization Equipment Type
Modified for
Project
Work?
(Y/N)
Comments
1610 Water Quality Sampling of Surface
Water
6/4/2015 Foth I&E Peristaltic Pump N See Appendix A of
Monitoring Plan
for Ashland
Breakwater (FE JV,
July 2015)
1611 Turbidity Monitoring 2/13/2014 Foth I&E YSI, 6-Series meter N See Appendix A of
Monitoring Plan
for Ashland
Breakwater (FE JV,
July 2015)
Title: RA Quality Assurance Project Plan
Revision No. Revision 1, Addendum 1
Revision Date July 2015
Section No. QAPP Worksheet #22
Page Nos. Page 1 of 1
X:\FOTH\IE\Xcel\15X001-00\10000 Reports\RA QAPP-Rev 1, Add 1\RA QAPP Worksheet 22 Rev 1 Add 1.docx
QAPP Worksheet #22
Field Equipment Calibration, Maintenance, Testing, and Inspection Table
Field
Equipment
Calibration
Activity
Maintenance
Activity
Testing/
Inspection
Activity
Frequency Acceptance Criteria Corrective
Action
Responsible
Person SOP Reference
YSI 6 Series
Turbidity Meter
Calibrate
with Standard
Reference
Solutions
N/A N/A Weekly; anytime
anomaly
suspected
+/-2% of reading or 0.3
NTU, whichever is
greater
Replace unit FE JV
Sampler
(oversight
by RD QA
Manager)
SOP 1611 –
Turbidity
Monitoring
N/A N/A Visual
Inspection
Prior to day’s
activities
No defects noted Replace unit
N/A Check/replace
battery
N/A Prior to day’s
activities;
anytime anomaly
suspected
Acceptable
calibration/operation
Replace
power cords;
replace unit