Fort Nelson Progress Pictures Week 16
5
Fort Nelson Progress Pictures Week 16 • Shuttering completed from C6 – C8 and wall poured on Friday 26/11/10
description
Fort Nelson Progress Pictures Week 16. Shuttering completed from C6 – C8 and wall poured on Friday 26/11/10. Fort Nelson Progress Pictures. Steelwork installed to tapered wall and foundation for flank wall 4 and starter bars. Fort Nelson Progress Pictures. - PowerPoint PPT Presentation
Transcript of Fort Nelson Progress Pictures Week 16
Fort Nelson Progress Pictures Week 16
• Shuttering completed from C6 – C8 and wall poured on Friday 26/11/10
Fort Nelson Progress Pictures• Steelwork installed to
tapered wall and foundation for flank wall 4 and starter bars.
Fort Nelson Progress Pictures• Gas meter house
demolished, foundation excavated from C1 – C5 and 50% blinded, 3no column bases excavated
Fort Nelson Progress Pictures Water tank downstand
beams poured, tanks sanded up and insulation and volclay installed.
Fort Nelson Progress Pictures
2no underpins excavated and poured.