Former Potrero Power Plant Cleanup · 2017-03-24 · activities we have planned at the former...

4
23RD ST. 22ND ST. ILLINOIS ST. 3RD ST. TENNESSEE ST. OFFSHORE SEDIMENT AREA 280 PG&E-Owned Properties NRG Potrero, LLC Owned Properties Port of San Francisco Property Impacted by Historical MGP Activities N Port Property Station A Tank Farm Switchyard/ Construction Yard Northeast Area Hoe Down Yard Former Power Generation Facility Approx. 500 ft. Former Potrero Power Plant Cleanup Project Newsletter March 2014 PG&E Potrero Site To facilitate the remediation process, we have designated seven work areas (shown in the site map below). This allows us to investigate and remediate each area independently, so that potential delays in one area do not hold back progress in other areas. Pacific Gas and Electric Company (PG&E) is providing this update to inform you and other community members about our progress on the environmental investigation and cleanup of the former Potrero Power Plant property. We will continue sending regular updates throughout the cleanup effort. PG&E is working under the oversight of the Regional Water Quality Control Board (Water Board) and other regulatory agencies to investigate and clean up the site, located on Illinois Street along the City of San Francisco’s central waterfront. Pilot Test Work Beginning in May To date, we have made significant progress on the environmental investigation and remediation of the site. We have finished remediation work in two of the seven project areas: the PG&E owned Hoe Down Yard, and the Switchyard and General Construction Yard Area (see Site Map below). This leaves work in five remaining areas: Station A, the Northeast Area (including a portion of the Port Property), the Offshore Sediment Area, the Tank Farm and the Power Generation Facility. While PG&E does not maintain ownership of the remaining areas, we are taking responsibility for the impact of our historical operations and working with current owners (NRG Potrero, LLC and the Port of San Francisco) to complete the cleanup. This year our efforts will focus on developing the cleanup design for the Northeast Area of the site, preparing a proposed cleanup approach for the Offshore Sediment Area, and regulatory closure of the Station A Area. In this update, you will find additional information about these and other upcoming site activities. Page 1

Transcript of Former Potrero Power Plant Cleanup · 2017-03-24 · activities we have planned at the former...

Page 1: Former Potrero Power Plant Cleanup · 2017-03-24 · activities we have planned at the former Potrero Power Plant Site. This spring, PG&E will be developing a detailed cleanup design

23RD ST.

22ND ST.

ILLINO

IS ST.

3RD

ST.

TEN

NE

SSEE

ST.

OFFSHORE SEDIMENT AREA

280

PG&E-Owned Properties NRG Potrero, LLC Owned PropertiesPort of San Francisco Property Impacted by Historical MGP Activities

N

Port Property

Station A

Tank Farm

Switchyard/Construction Yard Northeast

Area

Hoe Down Yard

Former Power Generation Facility

Approx. 500 ft.

Former Potrero Power Plant CleanupProject Newsletter March 2014

PG&E Potrero SiteTo facilitate the remediation process, we have designated seven work areas (shown in the site map below). This allows us to investigate and remediate each area independently, so that potential delays in one area do not hold back progress in other areas.

Pacific Gas and Electric Company (PG&E) is providing this update to inform you and other community members about our progress on the environmental investigation and cleanup of the former Potrero Power Plant property. We will continue sending regular updates throughout the cleanup effort.

PG&E is working under the oversight of the Regional Water Quality Control Board (Water Board) and other regulatory agencies to investigate and clean up the site, located on Illinois Street along the City of San Francisco’s central waterfront.

Pilot Test Work Beginning in MayTo date, we have made significant progress on the environmental investigation and remediation of the site. We have finished remediation work in two of the seven project areas: the PG&E owned Hoe Down Yard, and the Switchyard and General Construction Yard Area (see Site Map below). This leaves work in five remaining areas: Station A, the Northeast Area (including a portion of the Port Property), the Offshore Sediment Area, the Tank Farm and the Power Generation Facility. While PG&E does not maintain ownership of the remaining areas, we are taking

responsibility for the impact of our historical operations and working with current owners (NRG Potrero, LLC and the Port of San Francisco) to complete the cleanup.

This year our efforts will focus on developing the cleanup design for the Northeast Area of the site, preparing a proposed cleanup approach for the Offshore Sediment Area, and regulatory closure of the Station A Area. In this update, you will find additional information about these and other upcoming site activities.

Page 1

Page 2: Former Potrero Power Plant Cleanup · 2017-03-24 · activities we have planned at the former Potrero Power Plant Site. This spring, PG&E will be developing a detailed cleanup design

Safety is PG&E’s top priority. All components of our project work are structured to protect the local community, the environment and site workers. As our work progresses this year, PG&E will implement and enforce all appropriate safety protocols.

SAFETYFIRST

A Pilot Test this spring will help advance the cleanup design for the Northeast Area.

Northeast Area Cleanup Preparations Moving Forward

In December 2012, the Water Board approved a preferred cleanup approach for the Northeast Area (see site map). Part of this approach calls for MGP residues to be solidified in place, limiting their mobility. Limited excavation will take place on the Port Property.

This spring, PG&E will advance the cleanup design by conducting an on-site, in-place soil solidification test (referred to as the Pilot Test). The Pilot Test, which will take about two months to

complete, will help refine the solidification mix formula and confirm the equipment needed for mixing it into the soil.

As part of our commitment to keep the community informed, we are holding an open house to provide additional information about the test and how it may affect the community (e.g., the anticipated work schedule and planned work hours). We encourage you to attend. You can meet the project team and learn more about the upcoming work (see back page for open house details).

Page 2

Former Potrero Power Plant Cleanup

Page 3: Former Potrero Power Plant Cleanup · 2017-03-24 · activities we have planned at the former Potrero Power Plant Site. This spring, PG&E will be developing a detailed cleanup design

PG&E Continues Focus on Station A Closure

PG&E, NRG Potrero, LLC (the current owner of the Station A Area) and the Water Board are continuing efforts to finalize closure documents for the Station A Area (see map on front). These documents, which include a Risk Management Plan and a Land Use Covenant, will describe the institutional and engineering controls proposed to address and effectively manage the environmental impacts found within the area. Prior to being finalized by the Water Board, the documents will be available for public review and comment.

Remedial Investigation of Offshore Sediments Complete

PG&E has completed its efforts to investigate sediments located in the San Francisco Bay offshore of the property to determine the impacts from our former operations. A report (called the Potrero Offshore Sediment Area Remedial Investigation Report) detailing the investigation findings and potential cleanup recommendations has been submitted to the Water Board, and other supporting agencies, for review. The report is expected to be approved this spring.

Since 2009, four phases of investigation have been performed in the Offshore Sediment Area. This approximate 16-acre area includes sediments in the San Francisco Bay near the former power plant property and also along the Pier 70 property. The purpose of these investigations, collectively known as a Remedial Investigation, was to identify any potential impacts from PG&E’s historic operations and outline basic cleanup recommendations.

On the evening of November 20, 2013, PG&E held a community open house that focused on the Remedial Investigation process. During this informational event, held at the Dogpatch Café, attendees were able to meet with members of the project team and learn more about the investigation, the findings, and how the findings will help shape cleanup plans for the Offshore Sediment Area. We appreciate those community members who were able to attend the meeting.

PG&E is now in the process of preparing a Feasibility Study for the area, which will be submitted to the Water Board for review this year. The Water Board will be seeking public comments on the Feasibility Study prior to its final approval. Some additional investigation activities will take place this spring.

Extensive sampling was conducted during four phases of sediment investigations.

PG&E, NRG Potrero, LLC and the Water Board are continuing efforts to finalize closure documents for the Station A Area (currently owned by NRG, Potrero LLC)

Page 3

March 2014

Page 4: Former Potrero Power Plant Cleanup · 2017-03-24 · activities we have planned at the former Potrero Power Plant Site. This spring, PG&E will be developing a detailed cleanup design

03/13/14

Printed on 100% recycled paper, using 100% post-consumer content.

“PG&E” refers to Pacific Gas and Electric Company, a subsidiary of PG&E Corporation. ©2014 Pacific Gas and Electric Company. All rights reserved.

Former Potrero Power Plant Cleanup

Project Newsletter March 2014

Open for more information about the cleanup of the former Potrero Power Plant property.

Zeynep UngunPG&E 3401 Crow Canyon RoadSan Ramon, CA 94583

Presorted Standard

U.S. Postage PAID

San Francisco, CA Permit #XXXXX

You are invited…PG&E invites you to a community open house to learn about cleanup activities we have planned at the former Potrero Power Plant Site.

This spring, PG&E will be developing a detailed cleanup design for a portion of the former Potrero Power Plant site, and will perform an on-site soil solidification test. Solidification of soils is part of the approved cleanup approach. On March 27, we are hosting a community open house to share our plans. Come meet our project team and learn more about the upcoming work and the progress we are making with the cleanup. We look forward to seeing you there.

Thursday, March 27, 2014 6:30 pm to 8:00 pm

Dogpatch Café 2295 3rd Street San Francisco, CA 94107

For more information, please visit www.pge.com/potrero, contact the PG&E Environmental Remediation Information and Response Line at 1-866-247-0581 or email us at [email protected].

Thank You.