Flexible BudgetingChapter 07, 08
![Page 2: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/2.jpg)
9-2
Performance evaluation
BudgetAct
ualPerformance evaluation by
comparing actual results with
budgeted numbers.
![Page 3: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/3.jpg)
9-3
Deficiencies of the Static BudgetLarry’s Static Budget
![Page 4: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/4.jpg)
9-4
Deficiencies of the Static BudgetLarry’s Actual Results
![Page 5: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/5.jpg)
9-5
Deficiencies of the Static BudgetLarry’s Actual Results Compared with the Static Budget
![Page 6: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/6.jpg)
9-6
Static Budgets and Performance Reports
Static budgets are prepared for a single, planned level of activity.
Performance evaluation is difficult when actual activity
differs from the planned level of
activity.
Hmm! Comparingstatic budgets withactual costs is likecomparing apples
and oranges.
![Page 7: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/7.jpg)
9-7
The relevant question is . . .
“How much of the cost variances are due to higher activity and how much is due to cost control?”
To answer the question,we mustthe budget to theactual level of activity.
The relevant question is . . .
“How much of the cost variances are due to higher activity and how much is due to cost control?”
To answer the question,we mustthe budget to theactual level of activity.
Deficiencies of the Static Budget
![Page 8: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/8.jpg)
9-8
Improve performance evaluation.
May be prepared for any activity level in the relevant range.
Show costs that should have beenincurred at the actual level ofactivity, enabling “apples to apples”cost comparisons.
Help managers control costs.
Let’s look at Larry’s Law Consultancy
Characteristics of Flexible Budgets
![Page 9: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/9.jpg)
9-9
Preparing a Flexible BudgetLarry’s Flexible Budget
![Page 10: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/10.jpg)
9-10
Sales-Volume VariancesLarry’s Flexible Budget Compared with the Static Budget
![Page 11: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/11.jpg)
9-11
Flexible-Budget VariancesLarry’s Flexible Budget Compared with the Actual Results
![Page 12: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/12.jpg)
9-12
Performance report
![Page 13: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/13.jpg)
9-13
Variance Analysis
Standard Cost Variances
Price Variance
The difference betweenthe actual price and the
standard price
Efficiency Variance
The difference betweenthe actual quantity andthe standard quantity
![Page 14: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/14.jpg)
9-14
A General Model for Variance Analysis
Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price
Price Variance Efficiency Variance
Standard price is the amount that should have been paid for the resources acquired.
![Page 15: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/15.jpg)
9-15
Price Variance Efficiency Variance
Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price
A General Model for Variance Analysis
Standard quantity is the quantity allowed for the actual good output.
Standard input per unit of outputtimes amount of good output.
![Page 16: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/16.jpg)
9-16
A General Model for Variance Analysis
AQ(AP - SP) SP(AQ - SQ)
AQ = Actual Quantity SP = Standard Price AP = Actual Price SQ = Standard Quantity
Price Variance Efficiency Variance
Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price
![Page 17: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/17.jpg)
9-17
Hanson Inc. has the following direct material standard to manufacture one
Zippy:
1.5 pounds per Zippy at $4.00 per pound
Last week 1,700 pounds of material were purchased and used to make 1,000 Zippies.
The material cost a total of $6,630.
Material VariancesExample
Zippy
![Page 18: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/18.jpg)
9-18
What is the actual price per poundpaid for the material? a. $4.00 per pound.b. $4.10 per pound.c. $3.90 per pound.d. $6.63 per pound.
What is the actual price per poundpaid for the material? a. $4.00 per pound.b. $4.10 per pound.c. $3.90 per pound.d. $6.63 per pound.
Quick Check Zippy
![Page 19: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/19.jpg)
9-19
Hanson’s material price variance (MPV)for the week was:a. $170 unfavorable.b. $170 favorable.c. $800 unfavorable.d. $800 favorable.
Hanson’s material price variance (MPV)for the week was:a. $170 unfavorable.b. $170 favorable.c. $800 unfavorable.d. $800 favorable.
Quick Check Zippy
![Page 20: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/20.jpg)
9-20
The standard quantity of material thatshould have been used to produce1,000 Zippies is:a. 1,700 pounds.b. 1,500 pounds.c. 2,550 pounds.d. 2,000 pounds.
The standard quantity of material thatshould have been used to produce1,000 Zippies is:a. 1,700 pounds.b. 1,500 pounds.c. 2,550 pounds.d. 2,000 pounds.
Quick Check Zippy
![Page 21: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/21.jpg)
9-21
Quick Check
Hanson’s material efficiency variance (MEV)for the week was:a. $170 unfavorable.b. $170 favorable.c. $800 unfavorable.d. $800 favorable.
Hanson’s material efficiency variance (MEV)for the week was:a. $170 unfavorable.b. $170 favorable.c. $800 unfavorable.d. $800 favorable.
Zippy
![Page 22: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/22.jpg)
9-22
1,700 lbs. 1,700 lbs. 1,500 lbs. × × × $3.90 per lb. $4.00 per lb. $4.00 per lb.
= $6,630 = $ 6,800 = $6,000
Price variance$170 favorable
Efficiency variance$800 unfavorable
Actual Quantity Actual Quantity Standard Quantity × × × Actual Price Standard Price Standard Price
Material Variances Summary Zippy
![Page 23: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/23.jpg)
9-23
Hanson Inc. has the following direct labor standard to manufacture one Zippy:
1.5 standard hours per Zippy at $12.00 perdirect labor hour
Last week 1,550 direct labor hours were worked at a total labor cost of $18,910
to make 1,000 Zippies.
Labor Variances ExampleZippy
![Page 24: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/24.jpg)
9-24
What was Hanson’s actual rate (AR)for labor for the week?
a. $12.20 per hour.
b. $12.00 per hour.
c. $11.80 per hour.
d. $11.60 per hour.
What was Hanson’s actual rate (AR)for labor for the week?
a. $12.20 per hour.
b. $12.00 per hour.
c. $11.80 per hour.
d. $11.60 per hour.
Quick Check Zippy
![Page 25: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/25.jpg)
9-25
Hanson’s labor price variance (LPV) for the week was:
a. $310 unfavorable.
b. $310 favorable.
c. $300 unfavorable.
d. $300 favorable.
Hanson’s labor price variance (LPV) for the week was:
a. $310 unfavorable.
b. $310 favorable.
c. $300 unfavorable.
d. $300 favorable.
Quick Check Zippy
![Page 26: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/26.jpg)
9-26
The standard hours (SH) of labor thatshould have been worked to produce1,000 Zippies is:
a. 1,550 hours.
b. 1,500 hours.
c. 1,700 hours.
d. 1,800 hours.
The standard hours (SH) of labor thatshould have been worked to produce1,000 Zippies is:
a. 1,550 hours.
b. 1,500 hours.
c. 1,700 hours.
d. 1,800 hours.
Quick Check Zippy
![Page 27: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/27.jpg)
9-27
Hanson’s labor efficiency variance (LEV)for the week was:
a. $590 unfavorable.
b. $590 favorable.
c. $600 unfavorable.
d. $600 favorable.
Hanson’s labor efficiency variance (LEV)for the week was:
a. $590 unfavorable.
b. $590 favorable.
c. $600 unfavorable.
d. $600 favorable.
Quick Check Zippy
![Page 28: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/28.jpg)
9-28
Actual Hours Actual Hours Standard Hours × × × Actual Rate Standard Rate Standard Rate
Labor Variances Summary
Price variance$310 unfavorable
Efficiency variance$600 unfavorable
1,550 hours 1,550 hours 1,500 hours × × × $12.20 per hour $12.00 per hour $12.00 per hour
= $18,910 = $18,600 = $18,000
Zippy
![Page 29: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/29.jpg)
9-29
Hanson Inc. has the following variable manufacturing overhead standard to
manufacture one Zippy:
1.5 standard hours per Zippy at $3.00 perdirect labor hour
Last week 1,550 hours were worked to make 1,000 Zippies, and $5,115 was spent for
variable manufacturing overhead.
Variable ManufacturingOverhead Variances Example
Zippy
![Page 30: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/30.jpg)
9-30
What was Hanson’s actual rate (AR) for variable manufacturing overhead rate for the week?
a. $3.00 per hour.
b. $3.19 per hour.
c. $3.30 per hour.
d. $4.50 per hour.
What was Hanson’s actual rate (AR) for variable manufacturing overhead rate for the week?
a. $3.00 per hour.
b. $3.19 per hour.
c. $3.30 per hour.
d. $4.50 per hour.
Quick Check Zippy
![Page 31: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/31.jpg)
9-31
Hanson’s spending variance (VOSV) for variable manufacturing overhead forthe week was:
a. $465 unfavorable.
b. $400 favorable.
c. $335 unfavorable.
d. $300 favorable.
Hanson’s spending variance (VOSV) for variable manufacturing overhead forthe week was:
a. $465 unfavorable.
b. $400 favorable.
c. $335 unfavorable.
d. $300 favorable.
Quick Check Zippy
![Page 32: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/32.jpg)
9-32
Hanson’s efficiency variance (VOEV) for variable manufacturing overhead for the week was:
a. $435 unfavorable.
b. $435 favorable.
c. $150 unfavorable.
d. $150 favorable.
Hanson’s efficiency variance (VOEV) for variable manufacturing overhead for the week was:
a. $435 unfavorable.
b. $435 favorable.
c. $150 unfavorable.
d. $150 favorable.
Quick Check Zippy
![Page 33: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/33.jpg)
9-33
Spending variance$465 unfavorable
Efficiency variance$150 unfavorable
1,550 hours 1,550 hours 1,500 hours × × × $3.30 per hour $3.00 per hour $3.00 per hour
= $5,115 = $4,650 = $4,500
Actual Hours Actual Hours Standard Hours × × × Actual Rate Standard Rate Standard Rate
Variable ManufacturingOverhead Variances
Zippy
![Page 34: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/34.jpg)
9-34
Zippy’s actual production required 3,200 standard machine hours. Actual fixed overhead was $8,450.
The budgeted fixed overhead was $9,000. The allocation fixed overhead rate was $3 per machine
hour.
Compute the fixed overhead spending and production-volume variances.
Fixed Overhead Variances – Example
Zippy
![Page 35: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/35.jpg)
9-35
Fixed Overhead Variances
Spending Variance
Production - VolumeVariance
FR = Standard Fixed Overhead RateSH = Standard Hours Allowed
SH × FR
Actual Fixed Fixed Fixed Overhead Overhead Overhead Incurred Budget Allocated
![Page 36: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/36.jpg)
9-36
3,200 hours × $3.00 per hour
Spending variance$550 favorable
Fixed Overhead Variances – Example
$8,450 $9,000 $9,600
Production - Volume variance$600 favorable
SH × FR
Actual Fixed Fixed Fixed Overhead Overhead Overhead Incurred Budget Applied
Zippy
![Page 37: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/37.jpg)
9-37
Fixed Overhead Variances
Volume
Cost
3,000 Hours ExpectedActivity
$9,000 budgeted fixed OH
Fixed overhead
applied to products
Zippy
![Page 38: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/38.jpg)
9-38
Fixed Overhead Variances
$8,450 actual fixed OH
Volume
Cost
3,000 Hours ExpectedActivity
$9,000 budgeted fixed OH
Fixed overhead
applied to products
$8,450 actual fixed OH$550Favorable
Budget Variance
{
Zippy
![Page 39: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/39.jpg)
9-39
{
Fixed Overhead Variances
$8,450 actual fixed OH
3,200 machine hours × $3.00 fixed overhead rate
$600FavorableVolume
Variance
$9,600 applied fixed OH
3,200 StandardHours
Volume
Cost
3,000 Hours ExpectedActivity
$9,000 budgeted fixed OH
Fixed overhead
applied to products
{$550
FavorableBudget
Variance
{ $8,450 actual fixed OH
Zippy
![Page 40: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/40.jpg)
9-40
Sales variances
Selling price
variance
= Actual selling price
Budgeted selling price- x Actual units
sold
Sales volume variance
=Actual
units soldBudgeted units sold- x
Budgeted margin per
unit
![Page 41: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/41.jpg)
9-41
$ $Budgeted ProfitSales variances: Selling price Sales volume
Actual sales minus budgeted costs(F) (U)$ $
Cost variances Material price Material efficiency Direct labor price Direct labor efficiency Vaiable OH spending Variable OH efficiency Fixed OH spending Fixed OH production-volume
Actual Profit
ZippyPerformance report
![Page 42: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/42.jpg)
9-42
Example - Leather LtdOne of the departments of Leather Ltd manufactures leather briefcases. The standard cost schedule applicable for April is set out below.Standard cost schedule per briefcase(assuming monthly production of 640 items)
£Leather 0.7 m2 at £30 per m2 21.00Labor 2 hours at £16 per hour 32.00Variable OH 2 hours at £2 per hour 4.00Fixed OH 2 hours at £6 per hour 12.00Total standard cost 69.00Margin 23.50Selling price 92.50 OH are allocated on the basis of standard labor hours.
![Page 43: Flexible Budgeting Chapter 07, 08. 9-2 Performance evaluation Budget Actual Performance evaluation by comparing actual results with budgeted numbers.](https://reader036.fdocuments.net/reader036/viewer/2022062322/5697bfbd1a28abf838ca20fa/html5/thumbnails/43.jpg)
9-43
The actual figures for April are set out below. There were no changes in stock levels.
£ £Sales: 700 briefcases 63,000
Less expensesLeather: 525 m2 16,800Labor: 1,350 hrs 22,275Variable OH 2,600
Fixed OH 8,00049,675
Profit for April 13,325