Ferry free E39/The Coastal Highway Route - Statens vegvesen · 2019. 10. 28. · The Coastal...
Transcript of Ferry free E39/The Coastal Highway Route - Statens vegvesen · 2019. 10. 28. · The Coastal...
Progress and development strategy, Kjartan J Hove, Håvard Austvik and Kjetil Strand, Norwegian Public Roads Administration
Teknologidagene 2019 Trondheim
Ferry free E39/The Coastal Highway Route
The Coastal Highway Route E39
The «Golden Coast» ofNorway:
● 1/3 of the country’spopulation (1 870 000)
● Approx. 60 % of ourexport value
Ferry Free E39
Kjartan J Hove
MØRE OG ROMSDAL
266 274
SOGN OG FJORDANE
110 266
HORDALAND
519 963
Rogaland
472 024
SØR-TRØNDELAG
317 363
VEST-AGDER
184 116
Kjartan J Hove
Fjord Length(km)
Depth(m)
Halsafjorden 2 5-600
Julsundet 1.6 5-600
Romsdalsfjorden 13 330
Sulafjorden 3.8 500
Vartdalsfjorden 2.1 600
Nordfjorden 1.4 500
Sognefjorden 3.7 1250
Bjørnafjorden 5 550
Langenuen 1.3 500
Boknafjorden 27 390
= subsea tunnel
Ambitions
● NTP 2018-2029
– E39 will be improved and ferryfree
– Progress planned in accordance with financialplanning and technological development
● NTP 2022-2033
– ?
● The route, from Kristiansand to Trondheim, is approximately 1100 km long. It runs through six counties, and the cities of Stavanger, Bergen, Ålesund and Molde. Travel time today is 21 hours, and seven different ferry connections. The aim is to create an improved E39, which will reduce travel time by half. The route will be almost 50 kilometres shorter.
Coastal Highway Route E39
Kjartan J Hove
Kjartan J Hove
Alternative solutions for the large fjord crossings
• Suspension bridge• Floating bridge (combined with
suspension/cable-stayed bridges)• Submerged floating tube bridge
(floating tunnel)• Immersed tunnel/
subsea rock tunnel • Frequent ferries
Kristiansand - Stavanger
● Statens vegvesen and Nye veier are two parts planning E39 south ofStavanger
● Statens vegvesen buildingStavanger sentrum/Eiganes (picture), opening 2019/20
● Stavanger north, planning area for start subsea tunnel under Boknafjorden
Progress E39
Photo: Statens vegvesen Kjartan J Hove
Stavanger - Bergen
● Boknafjorden
● Start 4th Jan 2018
● Access, south and north, finish
● Main tunnel
● 27 km long
● 395 mbl
● Rogfast (subseatunnel)
Progress
Photo: Statens vegvesen Kjartan J Hove
Rogfast
Kjartan J Hove
E02
E03
E04Tender E02 in 2018, approx 1/3 of the«Rogfast-project»
Cansell october 2019. One bid/one company
Tender E03 and E04 delay because of this
Costs uncertain. Cut ofcosts?
● Existing road approx. 130 km + ferry
● Distance:
1. Bokn – Stord: 69 km
2. Stord: 7 km
3. Stord-Os: 52 km
● We are underway with the central government zoning plan in the south. In the north we have axept for crossing the Langenuenfjord in south.
● Planning time: 5 yearsConstruction start: To be decided through NTP 2022-2034
3
2
1
E39 Bokn-Os/Bergen
Kjartan J Hove
Bjørnafjorden
Langenuen
Bømlafjorden
Os
Stord
Bokn
Bergen - Stavanger● Bjørnafjorden
– Status and progress summary
• Municipal planning
• Environmental loads, measuringlocal weather conditions (waves,
wind, tidal effects, temperature)
• Geological conditions
• Risk assessment, accidents
• Engineering, conceptdevelopment
• Model based project execution
• Inspection, operation and maintenance
Progress
Kjartan J Hove
Illustrasjon: Vianova/Baezeni
Bjørnafjorden
● Engineering, concept development
• Continously improving design basis
• Concept development of floatingbridge through 2019
• Feasibility study through 2020
• End anchored or side anchoredfloating bridge or a best fitcombination of those.
● Risk asessment, Ship collission
• Scenario evaluations
• Mitigating actions and action effects
• Uncontrollable ship scenario
• Dimensioning strategy ship impactenergy
● Geological conditions nearly completed
• Geophysics (sediment conditionsand subsea landslidesinvestigations)
• Geotechnics (Anchor design parameters)
Status and Progress, summary
E39 Bergen - Ålesund
01.11.2018
● E39 Sulafjorden, E39 Vartdalsfjorden og E39 Halsafjorden– Development of new technology– One project organisation for all
three crossings
● E39 Romsdalsfjorden– Well known technology– Sub-sea road-tunnel– Suspension bridge with main
span 1625 m
E39 Sulafjorden – preliminary loads
● Wind (10 min average)
● 100 years est.● Kvitneset, (93 m)● 37,5 m/s● Langeneset (95 m)● 38,2 m/s● Trælbodneset (77 m)● 35,9 m/s● Kårsteinen (63 m)● 37,9 m/s
Kjartan J Hove
Wind (10 min average) 100 years est.
Kvitneset, (93 m) 37,5 m/s
Langeneset (95 m) 38,2 m/s
Trælbodneset (77 m) 35,9 m/s
Kårsteinen (63 m) 37,9 m/s
Waves 100 years est.
Sulafjorden A - wind 1,8 m
Sulafjorden A - swell 8,1 m
Sulafjorden B - wind 1,6 m
Sulafjorden B - swell 5,2 m
● Climat models are very close to measurements
● Big loads make it one of the most complicatedfjord crossings on the E39
E39 Sulafjorden – schedule
● Contracts for the next stages is about to be signed
Kjartan J Hove
Sulafjorden-Bridge consepts
Update onPossibilityStudies
Concept study Concept with25% uncertainty
Concept with10% uncertainty
Suspensionbridge with onespan (corridor 1)
2020 2021 2023 -
Suspensionbridge with twospans (corridor 1)
2020 2021 2023 -
Suspensionbridge with twospans (corridor 2)
2020 2021 2023 -
Submerged tube bridge
2020 2021 2023 -
Suspensionbridge with twospans on TLP
2020 2021 2023 -
DG-1 DG-2 DG-3
Only the best alternativs from every decission gate (DG)
E39 Romsdalsfjorden
● Concept for new E39 Ålesund-Molde and thecrossing of Romsdalsfjorden is decided by The Ministry of Transport i 2014
● New considerations for all projects to newNational Transport Plan 2022-2033– Mission: Reduce cost or increase benefit
● Three main alternatives– Varieties of the accepted concept– Alternativ route (Romsdalsaksen)– High frequency ferries
● Alternativ route includes 3 km floating bridge– Assessment will be based on climat loads
from Bjørnafjorden
Kjartan J Hove
Molde
Ålesund
• Technologically feasible
• Feasible from a planning perspective
• Large positive Socio-Economic impact
• Financially challenging
Development strategy
Prefered solution on the following crossings (known technology, butstreched):
● Boknafjorden
● Romsdalsfjorden
● Development of new technology and more knowledge– Five highly challenging fjord crossings
– Looking at offshore methodology for technology development and qualification
– Studying wind, wave and current conditions
● Building competenceMore than 50 PhDs from the Norwegian University of Science and Technology (NTNU), Chalmers, the University of Stavanger (UiS) and others (including postdocs)
● Funding– Development costs: Requires funds to be allocated at an earlier stage than for traditional road
projects
● Design and Building– Contracting practice
Development strategy
Example of possible funding plan for the project
Coastal Highway Route E39
0
5 000
10 000
15 000
20 000
25 000
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050
mill
ion
ar k
ron
er
Statlege investeringar og bompengebruk pr. å - forsiktig
Statleg finansiering Bompengefinansiering (potensial ved full utnytting)
What remains?
● 2/3 av E39 (680 km) will not be completedwithin 2022
● Different progress onthe various stretches
– Nye Veier AS
Coastal Highway Route E39
Kjetil Strand, leder av delprosjekt Strategi i Ferjefri E39
Stavanger
Ålesund
Thank you!☺