FEASIBILITY STUDY OUTLINE (*DAP Format)
1. Project Summary2. Market Study
a. Product Descriptionb.
Demand
c. Supplyd. Demand-Supply Analysise. Price Studyf. Factors Affecting the Marketg. Marketing Program
3. Technical Feasibilitya. Productsb. Manufacturing Processc. Plant Size and Production Scheduled. Machinery and Equipmente. Plant Locationf. Plant Layoutg. Building and Facilitiesh. Raw Materials and Suppliesi. Utilities
j. Waste Disposalk. Production Costl. Labor Requirements
4. Financial Feasibilitya. Major Assumptionsb. Total Project Costc. Sources of Financing the Projectd. Preparation of Financial Statementse. Financial Analysis
5. Socio-economic Study6. Organization and Management Study
a. Form of Ownershipb. Organizational Chartc. Officers and Key Personneld. Project Schedule
-
7/28/2019 FEASIBILITY STUDY OUTLINE.pdf
2/3
Technical Feasibility
1. Products
i. Description of the products (specifically relating to physical,mechanical and chemical properties)
ii. Economic uses of the product2.Manufacturing Process
iii. How shall the product be manufactured? (Show detailed flow chartsindicating material and energy requirement at each step, and the
normal duration of the process)
iv. Other processes and factors considered to determine the process tobe adopted
v. Processes used in existing plants and in similar projects in thePhilippines or abroad
3.Plant Size and Production Schedule
vi. Daily and annual production capacity of the plantvii. Production days per yearviii. Factors used in determining plant sizeix. Expected attainable annual production volume for the next five (5)
years considering start-up and technical factors
4.Machinery and Equipment
x. Machinery layout (Indicate the number, specifications, ratedcapacities of major machineries, prices of equipment, and
balancing of capacities of each major and auxiliary equipment, and
standby units)
xi. Quotations from suppliers, machineries guarantees, delivery, termsof payments and other arrangements
5.Plant Location
xii. Plant location (Show map of the proposed plant)xiii. Is the location desirable in terms of distance to source of raw
materials and markets and other factors?
6.Plant Layout
xiv. Show layoutxv. Effect of layout on materials flow and treatment of materials
handling and storage
xvi. Provision for expansion7.Building and Facilities
xvii. Building/s to be constructedxviii. Cost of constructionxix. Other structures and their respective costsxx. Other improvements (Specifically relates to roads, drainage
facilities, etc.)
xxi. Cost of improvements
-
7/28/2019 FEASIBILITY STUDY OUTLINE.pdf
3/3
8.Raw Materials and Supplies
xxii. Description of raw materials specifically relating to their physical,mechanical and chemical properties
xxiii. Alternative raw materials considered and factors used in selectingthe raw materials
xxiv. Material combinationxxv. Availability of raw materials. Will there be a continuous supply?
xxvi. Current and prospective sources of raw materialsxxvii. Current and prospective costs of raw materials and wil l there be
any long term contract with the suppliers?
9.Utilities
xxviii. Utilities (electricity, fuel, water, steam and supplies) requiredxxix. Uses, quantity required, balances of util ities, availability of sources
and alternative sources and costs
10.Waste Disposal
xxx. Waste and volume to be disposed ofxxxi. Waste disposal method to be adoptedxxxii. Waste disposal methods used in other plantsxxxiii. Cost of waste disposalxxxiv. Clearance and cost and how could it be secured from proper
authorities
11.Production Cost
12.Labor Requirements