FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR...

59
APRIL 2011 ENVIRONMENTAL MANAGEMENT REPORT KIRŞEHİR MUNICIPALITY 40100 KIRŞEHİR – TÜRKİYE Tel: +90 386 2131023 TEMPO ALTYAPI MUHENDİSLİK VE MUŞAVİRLİK A.Ş. 4. Cadde 719. Sokak No.2 06550 CANKAYA / ANKARA - TURKIYE Tel: +90 312 4422080 FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM

Transcript of FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR...

Page 1: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

 

  

APRIL 2011 ENVIRONMENTAL MANAGEMENT REPORT 

   

  

       

KIRŞEHİR MUNICIPALITY 40100 KIRŞEHİR – TÜRKİYE

Tel: +90 386 2131023

TEMPO ALTYAPI MUHENDİSLİK VE MUŞAVİRLİK A.Ş. 4. Cadde 719. Sokak No.2 06550

CANKAYA / ANKARA - TURKIYETel: +90 312 4422080

 

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM 

Page 2: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 2 

TABLE OF CONTENTS 

1.  EXECUTIVE SUMMARY ................................................................................... 6 

2.  RESPONSIBLE PARTY ...................................................................................... 9 

2.1  KIRŞEHİR MUNICIPALITY ................................................................................................. 9 

2.2  CONSULTANT FOR PREPERATION OF EMP (TEMPO ENGINEERS & CONSULTANTS INC.) .. 10 

2.3  ILLER BANK ....................................................................................................................10 

2.4  WORLD BANK ................................................................................................................10 

3.  PROJECT DESCRIPTION ................................................................................. 11 

3.1  PROJECT DEFINITION AND TARGETS ............................................................................11 

3.2  PROJECT’S LEGAL FRAMEWORK ...................................................................................11 

3.2.1  LEGAL OBLIGATIONS OF THE MUNICIPALITIES ................................................11 

3.2.2  EUROPEAN UNION LEGISLATION .....................................................................13 

3.2.3  WORLD BANK PROCEDURES ............................................................................13 

3.3  PROJECT LOCATION ......................................................................................................14 

3.4  GENERAL ENVIRONMENTAL CHARACTERISTICS OF PROJECT LOCATION .....................16 

3.4.1  Population ........................................................................................................16 

3.4.2  General Geology ..............................................................................................16 

3.4.3  Seismicity Characteristics ................................................................................17 

3.4.4  Meteorological Characteristics ........................................................................17 

3.4.5  National Parks, Natural Parks and Nature Protection Parks in the Region .....17 

3.4.6  Ecological Characteristics .................................................................................18 

3.4.7  Cultural Heritage ..............................................................................................18 

3.4.8  Socio‐economical Situation .............................................................................18 

3.5  EXISTING POTABLE WATER, WASTEWATER AND STORM WATER SYSTEM ..................19 

3.5.1  Potable Water System .....................................................................................19 

3.5.2  Water Quality ...................................................................................................21 

3.5.3  Water Losses ....................................................................................................21 

3.5.4  Current Sewerage System And Wastewater Treatment Plant ........................21 

3.5.5  Current Solid Waste Management System ......................................................22 

3.5.6  Stormwater System .........................................................................................22 

3.6  TECHNICAL COMPONENTS OF THE PROJECT ................................................................23 

3.6.1  General.............................................................................................................23 

3.6.2  Potable Water System .....................................................................................23 

4.  MITIGATION PLAN ....................................................................................... 26 

4.1  POSSIBLE ENVIRONMENTAL IMPACTS OF THE PROJECT MEASURES ...........................26 

Page 3: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 3 

4.1.1  Possible Negative Effects during Construction ................................................26 

4.1.2  Possible Negative Effects during Operation ....................................................27 

4.1.3  Possible Positive Effects During Operation ......................................................27 

4.2  MITIGATION PLAN AGAINST POSSIBLE NEGATIVE IMPACTS OF THE PROJECT ............28 

5.  MONITORING PLAN ..................................................................................... 32 

6.  INSTITUTIONAL ARRANGEMENTS ................................................................. 36 

7.  CONSULTATIONS WITH AFFECTED GROUPS AND NON ‐GOVERNMENTAL ORGANISATIONS .......................................................................................... 39 

  APPENDIXES:  APPENDIX 1  : The areas which have not water distribution network in Kırşehir APPENDIX 2  : Problematic areas in Kırşehir Water Distribution Network APPENDIX 3  :  Proposed  Main  Transmission  Line  Alignment  for  Kırşehir  Water 

Supply System APPENDIX 4  : Proposed Water Supply System in Kırşehir APPENDIX 5  :  Presentation  and  Meeting  for  Introduction  of  the  Project  and 

Environmental Management Plan       

Page 4: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 4 

 LIST OF TABLES  Table: 3.1‐ Kırşehir Census Results ................................................................................. 16 

Table: 3.2‐ Project Population Forecasts ........................................................................ 16 

Table: 3.3‐ Meteorological Data ..................................................................................... 17 

Table: 3.4‐ Existing wells and capacities ......................................................................... 19 

Table: 3.5‐ Exisiting Reservoirs and capacities ............................................................... 20 

Table: 3.6‐ Exisiting Pump Stations and Capacities ........................................................ 20 

Table: 3.7‐ Exisiting Network Pipe Diameters and Lengths ............................................ 20 

Table: 3.8‐ Components of Unaccounted for Water ...................................................... 21 

Table: 3.9‐ Water Demand Projections .......................................................................... 23 

Table: 3.10‐ Network pipe lengths in Kırşehir which will be rehabilitated .................... 24 

Table: 3.11‐ Reservoir Requirements ............................................................................. 25 

Table: 3.12‐ Transmission Lines ...................................................................................... 25 

Table: 4.1‐ Possible Negative and Positive Impacts ....................................................... 26 

Table: 4.2‐ Mitigation Plan against Negative Impacts .................................................... 29 

Table: 5.1‐ Monitoring Plan ............................................................................................ 33 

  LIST OF FIGURES  Figure: 3.1‐ Location of the Project Area on Turkey Map .............................................. 15 

Figure: 3.2‐ Project Location ........................................................................................... 15 

Figure: 3.3‐ Seismicity ..................................................................................................... 17 

      

Page 5: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 5 

    Abbreviations   

ACP  Asbestos Cement Pipe 

ASKI  Ankara Metropolitan Municipality Water and Sewage Works Administration 

DSI  State Water Authority 

EA  Environmental Assessment 

EIA  Environmental Impact Assessment 

EMP  Environmental Management Plan 

EU  European Union 

GRP  Glass Reinforced Pipe 

HDPE  High Density Polyethylene 

İB  İller Bank 

MoEF  Ministry of Environment and Forest 

SCADA  Supervisory Control and Data Acquisition 

WB  World Bank 

WWTP  Wastewater Treatment Plant  

 

 

 

 

Page 6: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 6 

1. EXECUTIVE SUMMARY 

Responsible Party 

The main responsible Parties for preparation, control, approval of this “Environmental Management  Plan”  done  under  the  scope  of  “Feasibility  Study  for  Rehabilitation  of Kırşehir Potable Water Transmission Line and Network System” are as follows:  

‐ Kırşehir Municipality 

‐ Consultant (Tempo Engineers & Consultants Inc.) 

‐ Iller Bank 

‐ World Bank 

Responsibilities  after  preparation  of  the  Environmental  Management  Plan  during implementation of the Project (construction and operation) are as follows: 

‐ Kırşehir Municipality 

‐ Contractor 

‐ Construction Supervisor 

‐ Iller Bank 

‐ World Bank 

‐ Ministry of Environment and Forestry 

‐ General Directorate of State’s Hydraulic Works (DSI) 

‐ Ministry of Health 

Project Description 

Improvement of potable water  services  in Kırşehir  towards  the  requirements of  the inhabitants living there but also according to Turkish and EU environmental legislation is required.  

Kırşehir’s potable water system needs to be improved  

‐ The potable water system is not properly available in new parts of the city.  

‐ The  existing  system’s  capacity  is  not  reliable  because  of  the  increasing population. 

Page 7: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 7 

‐ Some components of  the existing system are old and completed  the efficient lifetime and needs renewal. 

In the content of the potable water project, measures  for transmission  lines  (gravity, pressurised),  reservoirs,  pump  stations,  network  is  proposed.  A  SCADA  system  is proposed for robust monitoring and controlling of the whole potable water system.  

Mitigation Plan 

During construction and operational stage of “Rehabilitation of Kırşehir Potable Water Transmission  Line  and Network  System Project”,  there will be positive  and negative impacts to the environment, specifically to the followings:  

‐ Waste Production (solid & liquid wastes) 

‐ Traffic  

‐ Air Quality 

‐ Noise & Vibration 

‐ Landscape  

‐ Archaeological and historical artefacts 

‐ Other existing infrastructure 

‐ Water Quality and Supply 

‐ Health & Safety 

‐ Socioeconomic 

There are some measures to be taken to mitigate the major potential negative impacts on  land,  water,  air  and  other  media  during  planning/design,  construction  and operation period. Contractor, Construction Supervisor and Kırşehir Municipality have the  responsibility  for  the  implementation  of  these  measures  according  to  Turkish environmental legislation and other relevant regulations and standards.  

Monitoring Plan 

For  monitoring  of  the  environmental  impacts  and  implementation  of  mitigation measures, a monitoring plan  is prepared. This monitoring plan shall be executed with the  responsibility  of mainly  Construction  Supervisor,  Kırşehir Municipality  and  also other institutions that are relevant according to Regulations.  

Institutional Arrangements   

The organisations and  institutions  responsible  for  implementation and monitoring of the mitigation measures are as the following: 

‐ Kırşehir Municipality 

‐ Contractor Firm 

‐ Construction Supervisor Firm 

‐ Iller Bank 

Page 8: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 8 

‐ World Bank 

Recommendations  on  implementation  of  the mitigation measures, monitoring  and reporting  responsibilities  during  planning,  construction  and  operational  period  is explained in this Chapter. 

Consultations with Affected Groups and Non‐Governmental Organisations 

A presentation and a meeting  is organised  to  inform  the affected groups and  to get further comments from them about the Project. In this meeting, project components, possible  impacts of the Project, mitigation and monitoring plans  is discussed with the participants. After the meeting, questions of participants are answered. All information about  the  meeting  (meeting  minutes,  announcements  via  web  page  and  local newspapers,  list  of  chambers  invited  via  telephone,  participant  lists)  are  given  in Appendix. 

 

 

   

Page 9: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 9 

2. RESPONSIBLE PARTY  

The  main  responsible  Parties  for  preparation,  control  and  approval  of  this “Environmental Management  Plan”  done  under  the  scope  of  “Feasibility  Study  for Rehabilitation of Kırşehir Potable Water Transmission Line and Network System” are as follows.  

‐ Kırşehir Municipality ‐ Consultant (Tempo Engineers & Consultants Inc.) ‐ Iller Bank ‐ World Bank 

Responsibilities  after  preparation  of  the  Environmental  Management  Plan  during implementation  of  the  Project  are  as  follows.  Responsibilities  of  these  Parties  are detailed in Chapter 6. 

‐ Kırşehir Municipality ‐ Contractor ‐ Construction Supervisor ‐ Iller Bank ‐ World Bank ‐ Ministry of Environment and Forestry ‐ General Directorate of State’s Hydraulic Works (D.S.İ.) ‐ Ministry of Health 

 

2.1   KIRŞEHİR MUNICIPALITY  

As Beneficiary of the whole “Rehabilitation of Kırşehir Potable Water Transmission Line and Network  System”, Kırşehir Municipality  is  fully  responsible both  for preparation and  implementation  of  Environmental  Management  Plan.  For  preparation  of  the “Feasibility  Report”  and  “Environmental  Management  Plan”,  the  Municipality  has assigned a Consultant. With the assistance of the Consultant, the Municipality’s main responsibilities shall be as follows: 

• Give  assistance  to  the  Consultant  for  organisation  of  a  Public  Consultation Meeting  to  get  feed‐back  from  affected  groups  and  non‐governmental organisations, 

Page 10: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 10 

• Be  open  to  comments  from  affected  groups  and  local  environmental authorities regarding environmental aspects of project implementation, 

• If required, institutional strengthening through additional training, personnel or equipment.  

2.2 CONSULTANT FOR PREPERATION OF EMP (TEMPO ENGINEERS & CONSULTANTS INC.) 

Tempo Engineers & Consultants Inc. is assigned by the Municipality for preparation of “Feasibility Report” and “Environmental Management Plan”. The main responsibilities of the Consultant shall be as follows: 

• Preparation of the “Environmental Management Plan” synchronously with the Feasibility Report for the same Project, 

• Under  the  scope  of  the  EMP,  evaluation  of  the  possible  impacts  to  the environment, preparation of the mitigation and monitoring plans, guidance on institutional arrangements and organisation of a meeting for consultations with affected groups and non‐governmental organisations, 

• Be  open  to  comments  from  affected  groups  and  local  environmental authorities regarding environmental aspects of project. 

2.3 ILLER BANK  

From “İller Bank – Project Management Unit”, the main responsible for coordination of implementation  of  Environmental  Management  Plan  shall  be  “Environmental Specialist”. The Environmental Specialist’s responsibilities will be as follows: 

• Provide  Municipality  and  Consultants  guidance  on  preparation  of “Environmental  Management  Report”,  organisation  of  public  participation meeting  and  announcing  requirements  in  accordance  with  World  Bank requirements, 

• Provide municipality officials/municipality EA consultants with guidance on WB safeguard  requirements  (documentation  and  procedures)  for  cultural properties, natural habitats, forests, and international waterways, 

• Review  EA  documentation,  provide  written  comments  to  municipality  EA consultants,  ultimately  provide  formal  approval  of  EA  documentation  and procedures in accordance with WB safeguard requirements. 

2.4 WORLD BANK 

As the financial organisation, World Bank has the following responsibilities: 

• Review, comment or approve the “Environmental Management Plan”. 

 

Page 11: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 11 

3. PROJECT DESCRIPTION  

3.1 PROJECT DEFINITION AND TARGETS  

Improvement of potable water  services  in Kırşehir  towards  the  requirements of  the inhabitants living there but also according to Turkish and EU environmental legislation is required. 

To  improve  the  environmental  infrastructure  in  Turkey,  for  the  financing  of  the Municipal Services Projects, Iller Bank, Undersecretariat of Treasury and State Planning Organization  together  as  coordinated  began  the  negotiations with World Bank,  and started activities for the Municipalities in Year 2006.  

Kırşehir Municipality  intended to benefit from World Bank via  Iller Bank for financing of the Project. According to the procedures of World Bank, for the financing of Projects improving  the  infrastructure,  the  first  activity  for  the  application,  planning  and coordination of the works is the preparation of “Feasibility Study”. Later, according to the findings of the feasibility study, “Implementation” stage shall be started.  

The  studies done during preparation of  this document  (Environmental Management Plan)  are  being  executed  parallel  to  the  feasibility  studies.  Among  the  findings mentioned in this report, actions shall be defined to decrease the impact of the Project on environment during both construction and operation.  

3.2 PROJECT’S LEGAL FRAMEWORK  

Legal  framework of  the Project  is defined according  to Turkish and EU Legislation as well  as World  Bank  Procedures.  These  legislative  issues  (law  and  regulations)  and procedures are summarised as following. 

3.2.1 LEGAL OBLIGATIONS OF THE MUNICIPALITIES  

Municipalities Law (5215)  

According  to Article  14  of  the Municipalities  Law, municipalities  are  responsible  for supplying water and sewerage systems. Article 15 of the same law holds municipalities responsible  for  supplying  potable  and  industrial water,  disposal  of wastewater  and stormwater, construction and operation of required plants for these services.  

 

Page 12: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 12 

Environmental Law (2872) 

According  to  Article  8  of  Environmental  Law No:  2872  “Actions  such  as  directly  or indirectly dumping wastes  into receiving media or storage, transportation or removal thereof in such a manner as to create damages to the environment and contrary to the standards and methods prescribed in respective Regulations are banned”.  

Regulation on Quality of Water Intended For Human Consumption  

The purpose of  this Regulation dated 2005 defines  the procedures and principles  for suitability of technical and hygienic conditions of water used for human consumption, ensuring  the  quality  standards  for  supply,  packaging,  labelling,  marketing  and inspection of  spring water  and drinking waters. Relevant  to Kırşehir Project,  regular analysis have been done for ensuring the procedures mentioned in this Regulation. In the next chapters these analysis and requirements are explained.  

Water Pollution Control Regulation 

Water  Pollution  Control  Regulation  provides  the  legal  and  technical  foundations required in order to protect the potential of surface and underground water resources of the Country and to ensure their optimum use within the best manner and prevent their pollution, which are all to be realized in conformity with sustainable development targets.  

Environmental Impact Assessment Regulation 

The  Regulation  on  Environmental  Impact Assessment  (2008)  governs  environmental impact assessment of  investment projects  in Turkey and  is  largely  in  line with the EU Directive on EIA. Since Kırşehir Project is about rehabilitation of potable water systems, it’s not under the scope of EIA Regulation Appendix I and Appendix II List. Accordingly, Project  Introduction  Report  or  Environmental  Assessment  Report  shall  not  be prepared.  However,  an  environmental  assessment  shall  be  done  via  preparing  an “Environmental  Management  Plan”  according  to  the  requirements  of  World  Bank procedures which is mentioned in next chapters. 

Except  these  regulations, below  regulations  shall be  taken  into  consideration during Project and Environmental Management Plan implementation. 

‐ Urban Wastewater Treatment Regulation ‐ Regulation  on  Control  of  Excavation  Material,  Construction  and  Demolition 

Waste  ‐ Regulation on Control of Waste Oils ‐ Regulation on Control of Hazardous Waste ‐ Regulation on Assessment and Management of Environmental Noise ‐ Regulation on Control of Packages and Packaging Waste ‐ Regulation on Control of Soil Pollution ‐ Regulation on Control of Exhaust Emissions sourced from Motor Land Vehicles ‐ All Regulations regarding Health and Safety 

 

 

Page 13: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 13 

3.2.2 EUROPEAN UNION LEGISLATION  

Relevant to our Project, European Union Directives about water sector which is one of the 7 sectors on EU environmental legislation is as follows:  

‐ Water Framework Directive (2000/60/EC) ‐ Urban Wastewater Treatment Directive (91/27/EEC) ‐ Council Directive concerning the protection of waters against pollution caused 

by nitrates from agricultural sources (91/676/EEC) ‐ Council  Directive  on  the  quality  of  water  intended  for  human  consumption 

(98/83/EC) ‐ Council Directive concerning the quality required of surface water intended for 

the abstraction of drinking water in member states (75/440/EEC) ‐ Directive  concerning  the  discharge  of  dangerous  substances  into  water 

(76/464/EEC) ‐ Directive concerning the management of bathing water quality (76/160/EEC) ‐ Directive on  the protection of  the environment,  and  in particular of  the  soil, 

when sewage sludge is used in agriculture (86/278/EEC) ‐ Council Directive on the protection of groundwater against pollution caused by 

certain dangerous substances (80/68/EEC) 

In  scope  activities  for  approximation  of  legislation  with  EU  Legislation,  targets  are defined.  For  the  approximation  of  environmental  legislation,  relevant  targets  and programmes are planned in the content of UÇES (National Environmental Strategy and Action  Plan).  Accordingly,  most  of  these  directives  are  endorsed  into  Turkish environmental  legislation.  Only  approximation  studies  about  “Water  Framework Directive” still continues. 

3.2.3 WORLD BANK PROCEDURES 

Environmental Assessment (OP 4.01) 

Activities carried out under the project will conform to current Turkish Environmental Regulations  and  Procedures  and  the  World  Bank’s  Safeguards  Policies,  specifically including  Environmental Assessment  (EA)  policy  outlined  in Operational  Policy  4.01, and others where applicable. Under the World Bank’s procedure  for EA, the projects are classified under the following categories: 

In means of Environmental Assessment, Turkish Legislation and Worldbank procedures shows some differences. The Regulation on Environmental  Impact Assessment (2008) governs  environmental  impact  assessment  of  investment  projects  in  Turkey  and  is largely in line with the EU Directive on EIA. Since Kırşehir Project is about rehabilitation of potable water systems,  it’s not under  the scope of EIA Regulation Appendix  I and Appendix II List. Accordingly, Project Introduction Report or Environmental Assessment Report shall not be prepared.  

 

 

Page 14: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 14 

According to World Bank procedures, Projects are classified in 3 categories and scope of the environmental assessment of theses 3 categories differs:  

‐ Category A: Project  is  likely  to have significant  impacts  that may be sensitive, irreversible  and  diverse,  or  unprecedented.  The  impacts may  affect  an  area broader that the sites of facilities subject to the physical works. 

‐ Category  B:  The  impact  on  human  population  or  environmentally  important areas  is  less adverse  than  those of Category A projects. The  impacts are  site specific and few, if any, are irreversible. 

‐ Category C: Minimal or no adverse environmental impact 

Kırşehir  Project  is  in  “Category  B”.  Although,  World  Bank  procedures  doesn’t necessitate a full EIA study for Category B projects, but preparation of “Environmental Management Plan” and public participation meeting  is obligatory. Accordingly, during execution  of  the  Project  (construction  &  operation),  mitigation  measures  shall  be taken  to minimize  the environmental effects and monitoring plans shall be prepared for better implementation of these mitigation measures. 

This “Environmental Management Plan” is prepared accordingly.  

Cultural Property (OPN 11.03) 

The principal  issue  is the  identification of “chance  finds” during construction. Turkish laws and practices meet the World Bank requirements. Law No. 2863 dd. 21.07.1983 on  the  Protection  of  Cultural  and  Natural  Assets  (revised  through  the  amendment issued on 27.07.2004 dated Official Gazette) as well as the Regulation on Researches, Drillings  and  Excavations  in  Relation  to  the  Cultural  and Natural  Assets, which was published  in  the Official Gazette No. 18485 dd. 10.08.1994,  for example, define  the proceedings  and  obligations  concerning  the  cultural  and  natural  assets  found  out during construction. The Municipalities are responsible for the application of the said law and regulation. As part of the regular reporting, the Municipalities will inform IB of the historical and cultural findings, if any, as well as the actions taken. 

Involuntary Resettlement (OP/BP 4.12) 

A  Land  Acquisition  Framework  which  meets  the  requirements  of  this  OP  will  be prepared and will be utilized 

3.3 PROJECT LOCATION 

Kırşehir city  is  located  in  inner Kızılırmak part of Central Anatolian Region. Centrum  is located  at  34  degrees,  10 minutes  east  longitude  and  39  degrees  8 minutes  north latitude. The city  is neighbouring Nevşehir, Aksaray, Kırıkkale, Ankara and Yozgat.  It’s height from the sea level is averagely 985 m.  

Kırşehir Region  is  part  of Central Anatolian Massif.  “Kırşehir Massif” which  is  inside Kızılırmak  arch  is  one  of  the  9  biggest massifs  of  Turkey.  It’s  presumed  that  it  also continues under Salt Lake. Kırşehir Massif has a thickness about 2000‐2500 m. 

Kırşehir  has  a  surface  area  of  6.665  km2.  It  has  a  total  (city  centre  and  villages) population of 223.102.  It  is at 985 meters above sea  level.  Its districts are Akcakent, 

Page 15: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 15 

Akpinar,  Boztepe,  Cicekdagi,  Kaman,  and Mucur.  The  location  of  Project  is  Kırşehir Province,  city  centre.  Project  location  on  Turkey map  and  Kırşehir  Province Map  is given in Figure 3.1 and Figure 3.2.  

 Figure: 3.1‐ Location of the Project Area on Turkey Map 

 

 Figure: 3.2‐ Project Location 

 

KIRŞEHİR 

Page 16: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 16 

3.4 GENERAL ENVIRONMENTAL CHARACTERISTICS OF PROJECT LOCATION  

3.4.1 Population  

Project shall serve to the population  living  in Kırşehir central area. Kırşehir city centre populations  are  as  the  following  according  to  census  and  address based population system received from Turkish State Statistics Institute.  

Table: 3.1‐ Kırşehir Census Results 

  1980  1985  1990  2000  2007  2009 

Kırşehir ‐ Centrum  49.913  64.754  73.538  88.105  99.832  105.826

During  feasibility  and  design  stages,  population  projections  for  future  are  done considering  the  previous  populations  and  also  the  previous  studies  (development plans, infrastructural projects etc). The forecasted populations are as the following:  

Table: 3.2‐ Project Population Forecasts 

  2020  2030  2040 

Kırşehir ‐ Centrum  113.000  176.000  275.000 

3.4.2 General Geology  

Kırşehir region is a part of Middle Anatolian Massive. It is guessed that Kırşehir Massif is the biggest of Turkey’s 9 big massifs  in Kızılırmak Arch;  lay out under the Tuz Lake. Kırşehir  massif  has  approximately  2000‐2500  m  thickness.  Surface  shape  of  the province  and  Central  Anatolia  consist  of  crystaled  old  rock  have  occurred  in  Third Geological Age’s Mesoic up Reosen era. It is possible to observe all examples of carstic structures  in Kırşehir.  It  is at the east of Central Anatolian basin which biggest closed basin of Turkey. This basin  is an  important effect for surface shape and climate. Third Age properties are observed for occurrence of natural structure of region. Region has got  its main  structure during  convolution of Alps.  If  region  is  inspected geologically, four different types of occurrence and era can be observed. New alluviums takes place in a wide area at east of line (Seyfe Lake settling land) for fault lay through Northwest Southeast  direction,  crystaled  schist  in metamorphosis  series,  on  the west marbled limestone and  small amount of dolomite also exists. Other  locations are  covered by sediments till third age’s second half. 

Direction of Central Anatolian metamorphosis  series of  the  regions crystaled masses differ region to region. This region is around Kırşehir‐Kaman and northwest southeast direction. Marbles of Kervansaray Mountains next to Kırşehir  is pushed onto  layers of southeast  lutesyen. Metamorphosis age of Kırşehir crystaled massifs are not defined certainly. But it is well known that age of metamorphosis of Kaman Karalan Mountains is in Cretaceous age. It is assumed that occurrence under metamorphosis layers belong to Palaeozoic age.  If northwest of Kırşehir  investigated through Kalkanlı Kargasekmez 

Page 17: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 17 

chain of mountains’ northeast‐southwest with horizontal section, schist with lime, fillat and  green  schist, marble  zones,  fine  particled  crystallised  quartz  and musco  schist, calcite and marble strata are seen respectively. 

3.4.3 Seismicity Characteristics  

Kırşehir is located on Middle Anatolia fault line. Most parts of the city is under 1st or 2nd degree earthquake zone as can be seen from the below figure. There are 2 important fault  lines; one on northwest‐southeast direction and  the other  is on Ankara‐Kırşehir border. 

 Figure: 3.3‐ Seismicity 

3.4.4 Meteorological Characteristics 

In Kırşehir, typical terrestrial climate  is observed. In winter time,  it’s cold and though, in summer time it’s hot and dry. According to results of State’s Meteorological Works – Regional Directorate analysis results, some meteorological data is as follows: 

Table: 3.3‐ Meteorological Data 

  Months

1  2  3 4 5 6 7 8 9  10  11 12Average temperature ( Co ) 

‐5,1  ‐3,4  9,3 13,2 14,7 20,7 23,7 24,8 19,4  12,5  7,7 0,1

Average precipitation (mm) 

35,1  28,0  34,9 27,0 31,7 45,6 2,5 0 35,4  66,9  34,9 0,6

Average relative moisture (%) 

77,8  76,9  60,4 55,6 52,0 43,5 37,1 39,2 50,3  68,7  75,6 87,8

Average wind speed(m/s) 

2,3  2,0  2,1 2,4 2,1 2,9 4,3 2,9 2,4  2,4  1,6 1,7

3.4.5 National Parks, Natural Parks and Nature Protection Parks in the Region  

Inside  the  borders  of  Kırşehir,  there  is  no  national  park,  natural  park  or  natural monument. Only, Seyfe Lake and its surrounding 10.700 ha area is defined as “Natural 

Seismicity zones 

1. Degree 

2. Degree 

3. Degree 

4. Degree 

5. Degree 

Page 18: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 18 

Protection Area” with the decision of Council of Ministers in 1990. The lake’s water is salty and its sodium content is high. It has a depth of maximum 165 cm. Seyfe Lake is at 16 km  far  in the north of Mucur District and on the northeast part of Kırşehir city centre (30 km far). It’s classified as “A” type wetland. Seyfe catchment area covers an area  of  152.200  ha, which  23.585  ha  is  defined  as  “1st  Degree  Site  Area”  in  1989, 10.700 ha  around  Lake  is defined  as  “Natural Protection Area”  and  also  included  in RAMSAR Convention  in 1994. So  it’s committed  to protect  the natural structure and ecological characteristics.  

3.4.6 Ecological Characteristics 

Kırşehir’s vegetation is observed as steppes, there are also bushes in some places. The only forest area exist in north parts of Çiçekdağı region, around Akçakent District which consists oak and juniper trees. Forest area covers 2% of whole city area.  

For  Kırşehir,  there  isn’t  any  study  available  related  to  flora,  fauna,  species  and populations.  However  there  are  some  studies  done  around  Seyfe  Lake  and  its surrounding. According  to  these  studies, 289  floral  species  that belong  to  53  family have been  identified.  27 of  them  (2%)  are  classified  as  endemic  and  2 of  them  are classified  as  rare  (Class  R).  Related  to  fauna,  there  are  some  species  exists  around Seyfe Lake which is included in Appendix 2, Appendix 3 and ERL list of Bern Convention and which needs special attention and protection.  

3.4.7 Cultural Heritage 

There are some historic and archaeological artefacts which are registered by Ministry of Culture. In city centre there are many structures built in the past that is still in use. Most commonly known are, Alaeddin Mosque, Cacabey Mosque, Alenderbaba Tomb, Kapucu Mosque, Ahi Evran Hermitage, Kesikköprü Caravanserai and bridge which are built during Ottoman and Seljuk Era.   The artefacts found in archaeological excavations in the region are exhibited in Kırşehir Cultural Center. In  light of the excavations and findings, from the Chalcolithic ages till today,  Kırşehir  has  a  history  of  7000  years.  Coins,  stone works  and  ceramics  from Greek,  Byzantine,  Roman  and  Islamic  ages  are  exhibited  in  Kırşehir  Museum.  In Çağırkan town which is located in Kaman District, clay pots from Phrygian period have been found. Excavations are continuing.  

3.4.8 Socio‐economical Situation  

In Kırşehir, economic  life  is mainly depend on agriculture.  Industrialisation has been increased  after  the  Province  is  defined  as  a  “prioritised  cities  for  development”  in 1973.  In  the beginning periods of  industrialisation, Entities preferred  locations which are  close  to  Centrum,  district  centres  and  places  where  raw  material  is  easily accessible. Today entities also prefer  the most economical and appropriate  locations for  production  and  trading.  The  industries  begin  to  gather  in  Organised  Industrial Region which  is newly established  in Gölhisar‐İğdecik region, 12 km far to city centre. 

Page 19: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 19 

According to 2002 data, in the city there are 19 flour factories, 4 animal feed factories, 1  drill  bit  factory,  1  lime  factory,  1  steel  ball  factory,  1  brick  factory,  1 mushroom factory, 1 crude oil factory, 1 filling station, 1 rubber factory, 1 sugar factory, 1 calcite production factory, 1 integrated meat factory, 1 dairy, 1 painting industry exists.  

3.5 EXISTING POTABLE WATER, WASTEWATER AND STORM WATER SYSTEM  

3.5.1 Potable Water System 

Kırşehir’s potable water demand is supplied from underground sources. Total capacity of the wells are 695,68 l/sec. Total 15 wells are located at 4 different well field (Özbağ, Selafur, Ökse, İtfaiye) areas.  

Table: 3.4‐ Existing wells and capacities 

Well Name  Elevation (m)  Flow Rate (l/sec)  Pump Head (m) 

Özbağ 1  1043,00  20,83  103,00 

Özbağ 2  1043,00  36,67  104,50 

Özbağ 3  1047,00  40,28  103,00 

Özbağ 4  1051,00  30,56  100,50 

Özbağ 5  1050,00  37,78  102,50 

Selafur 1  1024,00  50,00  104,60 

Selafur 2  1023,00  67,50  103,80 

Selafur 3  1024,00  50,00  99,48 

Selafur 4  1024,00  67,50  100,10 

Ökse 1  1134,00  66,67  43,20 

Ökse 2  1142,00  66,67  42,70 

Ökse 3  1141.00  28,00  45,00 

Ökse 4  1135.00  61,00  45,00 

İtfaiye 1  998  36,11  105,00 

İtfaiye 2  998  36,11  105,00 

 There are both gravity and pressurised transmission lines to carry water from the wells to reservoirs or between reservoirs. There are both steel pipes and asbestos cement pipes with diameters between DN250 up  to DN800.  Some of  the  transmission  lines need repair or maintenance due to damages occurred.  In total, there are 14 reservoirs in Kırşehir, supplying water to the city via gravity. Total storage  volume  of  the  distribution  reservoirs  amounts  to  19,700 m³.  Some  of  the reservoirs were  found  to  be  in  a  rather  poor  state  of  repair.  All  of  the  reservoirs showed  signs  of  cracks  through  which  water  leaks.  Water  stored  in  reservoirs  is chlorinated before it is distributed into the network.   

Page 20: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 20 

Table: 3.5‐ Exisiting Reservoirs and capacities 

Reservoir Name 

Supplying Storage volume (m³) 

Maximum water level (m) 

Minimum water level (m) 

Merkez 1  Zone 8 5.000 1064,94 1059,94 Merkez 2  Zone 8 2.500 1065,28 1060,78 

Kümbetaltı 1  Zone 7 3.000 1030,43 1026,43 Kümbetaltı 2  Zone 7 2.000 1029,28 1025,78 

Kındam  Zone 9 700 1133,50 1029,00 Bağbaşı 1  Zone 6 1.500 1039,40 1035,40 Bağbaşı 2  Zone 5‐4 1.500 1089,21 1085,21 Mehtap 1  Zone 3 2.500 1084,02 1079,52 Mehtap 2  Zone 2 600 1144,15 1139,65 Mehtap 3  Zone 1 400 1202,20 1198,70 

 

There  are  a  total  of  4  potable  water  pumping  stations  in  Kırşehir.  They  were constructed  to  convey  the water  from  Zone  3  reservoirs  to middle  and  high  zone reservoirs of the area.  

Table: 3.6‐ Exisiting Pump Stations and Capacities 

Pumping station name  Head  of pump (m) 

Flow Capacity (l/sec) Number of pumps

Merkez PS  ‐ 29 1 Duty+1 StandbyBağbaşı PS  58 39 1 Duty+1 StandbyMehtap Hill 1 PS  72 35 1 Duty+1 StandbyMehtap Hill 2 PS  68 14 1 Duty+1 Standby

 The potable water distribution system of Kırşehir  is subdivided  into 9 pressure zones. These are designed to be supplied from dedicated reservoirs. Pipe material is generally asbestos cement (ACP). The existing network system doesn’t cover all settlement area in urban development plans. The other problem in water supply system is intermittent supply  in  some  areas.  Usually  supplies  are  alternated  such  that  one  area  receives water  in the morning and the other  in the evening. This  is assumed to be due to  low pressures  at  high  demand.  The  network  systems  in  these  areas  are  laid  primitively without  design  by  the  municipality.  According  to  information  received  from  the municipality,  pipe  diameters  and  lengths  of  the  network  are  given  in  the  following table. 

Table: 3.7‐ Exisiting Network Pipe Diameters and Lengths 

Pipe diameter (mm) Length (m)80  160100  327.771125  22.327150  39.421175  1.620200  22.565250  12.622300  11.034350  4.313400  7.182500  4.172Total  453.187

Page 21: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 21 

3.5.2 Water Quality 

Stored water  in  reservoirs  is  chlorinated  before  it  is  distributed  into  the  networks. Chlorination  is performed  in Merkez  1, Kındam, Bağbaşi  2  and Mehtap  1 Reservoir. Chlorination equipments  consist of a dosing pump and a  control panel. Chlorination dosing is done automatically. 

Water quality samples are taken  from the network and reservoirs on a regular once‐per‐day  basis.  The  analyses  are  done  daily  to measure  chlorination  balance  in  the water. Sampling  results are  safe  to drink at  the  locations  checked. Also  samples are taken  from  the  reservoir  on  once‐per  year  and  sent  to  National  Reference  Lab  in Ankara to be analyzed.  

3.5.3 Water Losses 

The difference between daily water production amount and daily billed water for one year can give roughly a figure for water loss in Kırşehir Water Supply System. With this approach daily billed water  is 10,918 m³/day. Billed daily water  is 23 % of daily water production.  The  remaining  part  of  the water  production  constitutes  the water  loss. Compared with billed consumption  it amounts to 77 %. Components of unaccounted for water are given in the following table: 

Table: 3.8‐ Components of Unaccounted for Water  

Total Demand  The total of water produced from all sources.  Billed Water  This represents the total amount of water that has been billed to 

customers.  There  are  two  elements,  volumes  obtained  from meter  reading  and  volumes  determined  by  assessment  for example unmetered customers or when meter readings are not available because of stopped meters. 

Free Water  Water  supplied  free.  For  example  to mosques,  public  drinking water  taps  and  fountains,  parks  and  cemeteries,  municipal buildings.  

Metering Losses  Losses  arising  as  a  result  of  the  inaccuracies  of  customer  and source meters. 

Illegal Use/Illegal Connection  Water  taken  from  illegal  connections  to  the  water  supply  or unregistered connection. 

Leakage from house connection  All  leakage  between  the main  and  the  customer  meter.  This includes  the  connection  to  the main  and  losses on  the private supply pipe. 

Leakage from Mains All leakage from pipes and valves.Production Losses  Leakage from storage reservoirs.Billing Losses  Estimated readings, assessed readings

3.5.4 Current Sewerage System And Wastewater Treatment Plant  

Kırşehir wastewater collection system is designed to be by means of separate systems. The existing sewage network has currently a total length of approx. 238 km with 13 km main collectors (diameter bigger than 400 mm up to 1.200 mm) and covers an area of more  than 5000 ha within  the  city.  In  these days  the  sewage water  is produced by approx. 105.826 Inhabitants and some industries. The domestic wastewater of the city 

Page 22: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 22 

of Kırşehir  is currently discharged  to  the  receiving water bodies Kılıçözü Creek which flows to Kızılırmak at the end without any treatment. 

The  collection  network  in  the most  cases  consists  of  pipes with  diameter  200 mm. These pipes are  in many places under dimensioned or  laid to flat gradient what  leads to  blockages.  The  main  discharge  point  of  the  domestic  wastewater  collected  in Kırşehir  is  in the south of the city nearby Demircidere. This main outfall sewer with a final  diameter  of  1,200 mm  collects  the wastewater  from  two main  sewers  located both sides of Kılıçözü Creek and discharges  into  the Kızılırmak River. There are  three main problems within the city's networks: 

1. Collection  systems  are  not  available  everywhere.  New  houses  have  been constructed where only one  system  is available, and  this has  consequently been used for the connection regardless of its original designation.  

2. Even for the main collectors the separation is not consequently kept. 

3. The  hydraulic  capacity  of  the  systems  is  not  reliable  anymore  in  parts  and  this result in flooding. 

Additionally,  the natural valleys are often blocked by buildings which  cause  flooding during the winter time in the rainy season. 

Municipal wastewater treatment plant is under construction and it’s financed by ASKİ to  prevent water  pollution  of  Kızılırmak  River.  The wastewater  treatment  plant  has capacity of 25.000 m³/day and planned for 155.000 population equivalent in 2023. The construction  is  started  in  2008  November,  targeted  to  operate  in  2010  March. Presently,  95%  of  the  construction  is  finished.  The  treatment  process  is  Extended Aeration Active Sludge Process with Nitrogen and Phosphorus. 

3.5.5 Current Solid Waste Management System  

Solid waste  is  collected  from  houses  via  plastic  bags  by  Kırşehir Municipality  trucks (compactor  trucks)  and  sent  to  dumpsite.  The  dumpsite  is  located  in  Kervansaray region, Boztepe Road area. It is 9 km far to city centre.   Project  activities  on  Sanitary  Landfill  are  completed  by  the Municipality.  The  new sanitary landfill is located in Kusdili Region Ekizağıl road. It is 7 km far to city centre. It’s construction  Works  are  finalised,  temporary  acceptance  is  made.  it  will  be commissioned.  

3.5.6 Stormwater System 

Due to the topography of Kırşehir, considerable stormwater quantities are discharging into the city through natural slopes that drain to the Kılıçözü Creek and its tributaries. These natural catchment areas are located south and east of the city with a total area of approx. 10.000 ha.  

The storm water system  is not available all over  the city.  It consist mostly pipes  laid without proper design studies. The storm water drainage  is  the main problem  in  the 

Page 23: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 23 

central part of  the  city  especially  at both  sides of Kılıçözü Creek. Currently, Kırşehir Municipality  is  executing  the  design  and  construction  of  stormwater  system  with another Project. 

3.6 TECHNICAL COMPONENTS OF THE PROJECT 

3.6.1 General 

Kırşehir’s potable water system needs to be improved  

‐ The potable water system is not properly available in new parts of the city.  

‐ The  existing  system’s  capacity  is  not  reliable  because  of  the  increasing population. 

‐ Some components of  the existing system are old and completed  the efficient lifetime and needs renewal. 

In the content of the potable water project, measures  for transmission  lines  (gravity, pressurised),  reservoirs,  pump  stations,  network  is  proposed.  A  SCADA  system  is proposed for robust monitoring and controlling of the whole potable water system.  

These are summarised as follows. 

3.6.2 Potable Water System 

Future potable water requirements of Kırşehir city centre is calculated as: 

Table: 3.9‐ Water Demand Projections 

  2025  2040 Water demand  407 l/s  716l/s 

 

Transmission Line 

The  existing  main  transmission  line  has  to  be  replaced,  since  it  is  in  very  poor condition. The alignment foreseen in previously prepared Iller Bank Project is followed since land expropriation has been solved largely. This alignment follows Kılıçözü Creek route in flow direction up to city centre.  

The transmission line is hydraulically divided by two sections which is; 

‐ Özbağ well water storage reservoir and Selafur well water connection point 

‐ Selafur well water connection point and Merkez 1 Reservoir 

Total 11.700 m with diameters of DN450 and DN650 mm pipes shall be laid. The wash out valves, air valves and line valves shall also be installed in required locations. There will be total 10 washout valves, 9 air valve chamber, 9 line valves. 

Proposed Main Transmission Line Alignment for Kırşehir Water Supply System is shown in the Drawing given as Appendix 3. 

 

Page 24: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 24 

Network  

Iller Bank has prepared a project in 2002 and approved asbestos cement pipe material with  diameter  ranging  from DN200  to DN600  and  PVC  pipe material with  diameter ranging from DN100 to DN150. Since asbestos cement pipes are not used today for the reason  that  they  cause  health  problems  on  people  and  material  are  brittle  and breakable  material.  On  the  other  hand,  asbestos  cement  pipe  are  not  produced anymore.  Accordingly,  in  the  content  of  our  Project,  pipe material  is  chosen  as  PE (DN100‐DN500) and GRP (DN600) 

In  İller  Bank  project  total  pipe  length  is  51.213  m  for  network.  This  amount corresponds  to 11% of  total existing network according  to  the pipe  lengths  received from the municipality. However, the areas marked as problematic and the areas which don’t have water network on the town plans cover 29% of all town development plans (Problematic  areas  cover %  25  of  the whole  and  the  areas which  don’t  have water distribution network cover %4 of  the whole). This amount covers  the network pipes which have been proposed in İller Bank Project (11%) and the network pipes which are the extension  areas  to  complete  to 29% of whole  area  (18%).  The determined pipe lengths according to the pipe diameters are listed in the following table: 

Table: 3.10‐ Network pipe lengths in Kırşehir which will be rehabilitated 

Pipe Diameter (mm) 

İB Pipe Length (m) 

Extension Pipe Length (m) 

Total Pipe Length (m) 

100  36.703  60.057  96.760 125  833  1.363  2.196 150  7.188  11.762  18.950 200  2.946  4.820  7.766 250  1.887  3.088  4.975 300  837  1.370  2.207 350  150  245  395 400  219  358  577 500  150  245  395 Total  51.213  83.308  134.521 

The areas which have not water distribution network and which have problems are shown in drawings in Appendix 1 and Appendix 2.  

New Reservoirs  

Total storage demand  is calculated as 20.625 m3 for Year 2040. So, 925 m³ additional reservoir  is  required. Merkez  2,  Kındam,  Bağbaşı  1  and  Bağbaşı  2, Mehtap  2  and Mehtap 3 reservoirs shall be abandoned because of very poor conditions and pressure zone divisions in network. The abandoned and proposed reservoir volumes are given in the following table. 

 

 

 

Page 25: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 25 

Table: 3.11‐ Reservoir Requirements 

Abandoned Reservoir  Abandoned Reservoir volume (m³) 

Proposed Reservoir 

Proposed Reservoir volume (m³) 

Mehtap 2  600 Mehtap 2 1.000Mehtap 3  400 Mehtap 3 1.000Bağbaşı 1  1.500 Bağbaşı 1 2.000Bağbaşı 2  1.500 Bağbaşı 2 1.000Kındam  700 Kındam 1 3.000Merkez 2  2.500 Kındam 2 2.000Total Volume (m³)  7.200 10.000

 

The reservoirs in Mehtap which will feed the middle and high zones of the network in this area are immediate solutions because of insufficiency and bad conditions. Also the reservoirs in Bağbaşı which will feed low pressure zone and high pressure zone of the network  is  an  urgent  solution  due  to  the  same  reasons.  On  the  other  hand,  The construction of new  reservoirs  in Kındam are  indispensable. Because  this  region  is a new development area of Kırşehir and the volume of existing reservoir is not sufficient for the all inhabitants. Also there is no water distribution network partly, although this region  is a  residential area. As a  result  the  the construction of new  reservoirs which will  feed  low  and  high  pressure  zone  of  the  network  should  be  considered immediately.  

Proposed Water Supply System in Kırşehir is shown in the drawing given as Appendix 4. 

New Pumping Station and Transmission Lines between Pump Stations and Reservoirs 

As also mentioned  in  İller Bank Project, the construction of a new pumping station  in Kındam is proposed. Its flow capacity shall be 43 l/s and pumping head shall be 60 m. The proposed PE pressurised transmission lines are as the following: 

Table: 3.12‐ Transmission Lines 

Line  Pipe diameter (mm)  Length (m) 

The  pressure  line  from  the  new pumping station to Kındam 2 reservoir 

315  1.523 

The pressure line from Mehtağ 1 PS to Mehtap 3 reservoir 

315  1.109 

The  pressure  line  from Bağbaşı  PS  to Bağbaşı 2 reservoir 

355  997 

Page 26: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 26 

4. MITIGATION PLAN  

4.1 POSSIBLE ENVIRONMENTAL IMPACTS OF THE PROJECT MEASURES 

During construction and operational stage of “Rehabilitation of Kırşehir Potable Water Transmission Line and Network System”, there will be positive and negative impacts to the environment which are summarised as follows: 

Table: 4.1‐ Possible Negative and Positive Impacts 

Possible Impacts  CONSTRUCTION  OPERATION Waste Production (solid & liquid wastes)  ‐ ‐ ++Traffic   ‐ ‐ o Air Quality  ‐ o Noise & Vibration  ‐ ‐ o Landscape   ‐ ‐ ++Archaeological and historical artefacts  ‐ o Other existing infrastructure  ‐ o Water Quality and Supply  ‐ ++Health & Safety  ‐ ++Socioeconomic  ‐ ++‐      Low level of negative effect‐ ‐    High level of negative effect +     Low level of positive effect ++   High level of positive effect o     No certain effect 

 

4.1.1 Possible Negative Effects during Construction  Solid And Liquid Wastes ‐ Excavation waste shall be produced. ‐ Old, unused pipes like old asbestos cement pipes, HDPE and steel pipes might 

be dangerous if they are not disposed properly. ‐ There is a risk of spill outs from construction equipment (fuel, lubricants, 

antifreeze etc.) which may result in the pollution of ground, surface and underground water. 

Page 27: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 27 

‐ Domestic type wastewater and solid waste shall be produced from construction site. 

 Traffic ‐ There can be interruptions on the roads where construction is progressing. ‐ There can be a danger risk for public and transportation vehicles if warning and 

informative signs are not used properly.  

Air Quality ‐ Excavations and material transportation may cause dust.  ‐ There will be extra exhaust gases emitted from construction equipment. 

 Noise & Vibration ‐ Noise and vibration shall be occurred sourced from the construction 

equipment.  

Damages To Landscape, Archaeological & Historical Artefacts ‐ Damage to trees and vegetation may occur.  ‐ Deposit of excavated soil, erosion, landslides or sedimentation may occur.  ‐ Damage on archaeological and historical heritage may occur. 

 Water And Wastewater Services ‐ Periodic interruptions in water supply shall be occurred. ‐ During installation of new pipes, water pollution may happen if construction 

measures is not followed properly.  

Worker’s Health and Safety ‐ Worker’s health and safety may be under risk if measures are not followed 

properly.  

4.1.2 Possible Negative Effects during Operation  Water Services ‐ Periodic blockages of the pipes are possible  

 Public and Worker’s Health & Safety ‐ Damages may occur on network, pollution of the network is possible ‐ Chlorine can be a risk factor for the operators, if it is not handled properly 

4.1.3 Possible Positive Effects During Operation  Health & Safety of Public and Workers ‐ Potable water supply conditions shall be improved in means of quality. ‐ Potable water supply condition shall be improved in means of quantity and the 

expansion of the regions having potable water system.    

Page 28: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 28 

Socio‐Economical  ‐ Intermittent supplies to some areas of the city shall be ended. Since water 

services will be improved; there will be an improvement on life quality of the people living there. 

 4.2 MITIGATION PLAN AGAINST POSSIBLE NEGATIVE IMPACTS OF THE PROJECT  

Steps to be taken during planning/design, construction and operation, to mitigate the major potential negative  impacts on  land, water,  air  and other media  is  given  as  in below table. The table also give responsibilities for each group of mitigation method. 

Since some costs for environmental protection and mitigation measures for decreasing the  environmental  impact  is  included  in  construction  costs  of  the  Contractor  firm during construction stage; and operational costs of the Municipality during operation stage, these are not indicated as separate in below table. 

 

  

 

 

 

 

Page 29: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM  ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 29  

Table: 4.2‐ Mitigation Plan against Negative Impacts 

Phase  Issue  Mitigation Measures  Comments  Institutional Responsibility 

CONSTRU

CTION PHASE 

 

Solid and Liquid Wastes 

Excavation waste  

‐ Stone, soil and other materials that may be reused shall be utilized in the procedure of project realization. If it’s not suitable for the Project, then it can be used as filling material on roads or cover material in Landfill.  

‐ All non‐dangerous waste and excavated material generated in the course of construction and that can be used again has to be deposited in the landfill and in a manner that is not harmful to the environment.  

‐ For temporary or final storage sites Kırşehir Municipality have responsibility to advise a location, and then the Contractor should transfer this waste to temporary or final disposal area without disturbing the environment (noise, dust, etc.) via certified transfer companies. 

All measures shall be in compliance with requirements of Regulation on Excavation and construction waste (2004) 

‐ Contractor (supervised by Construction Supervisor),  

‐ Kırşehir Municipality  

Replaced material (Pipes etc) 

‐ Materials that cannot be used and dangerous waste should be removed in compliance with relevant regulation. 

‐ Since asbestos cement pipes have serious health effects just caused by inhalation of the asbestos dust during replacement of the pipes, it’s highly recommended to be left underground instead of taking them out. (In case of any contact, workers wearing respirator masks with special filters on shall ensure the proper isolation). 

‐ Other possible hazardous waste should be transferred to “hazardous waste disposal area” (either Izaydas or others) for final disposal via licenced transfer companies.  

All measures shall be in compliance with requirements of Regulation on Control of Hazardous Waste (2005) 

‐ Contractor (supervised by Construction Supervisor) 

Spill outs from equipment (fuel, lubricant etc.)  

‐ Periodic examination of the condition of vehicles and other machinery and equipment used in the course of the performance of works should be done regularly.  

‐ Compliant warehousing of fuel and lubricant should be provided, and in case of a spill out, isolation and cleaning of the location shall be done.  

‐ The waste fuels should be temporary stored and disposed (recovered) according to relevant regulation. 

All measures shall be in compliance with requirements of Regulation on Control of Waste Oil (2004) 

‐ Contractor (supervised by Construction Supervisor) 

Domestic type solid waste & wastewater from construction site 

‐ Wastewater sourced from the construction site should be discharged to nearest sewage system, if the sewage system is far to Site, then isolated septic tanks should be used for later disposal to WWTP. 

‐ Solid waste should be collected in containers for final disposal of Kırşehir Municipality to municipal waste disposal area. 

All measures shall be in compliance with requirements of Water Pollution Control Regulation (2008) 

‐ Contractor (supervised by Construction Supervisor), 

‐ Kırşehir Municipality  

Traffic Traffic ‐Interruptions in transport  

‐ Residents should be informed about the location of the works at least one week before the construction. 

‐ Clear warning and information signs should be positioned around the construction zone.  

  All measures shall be with full cooperation and in compliance 

‐ Contractor (supervised by Construction Supervisor) 

Page 30: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM  ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 30  

Phase  Issue  Mitigation Measures  Comments  Institutional Responsibility 

‐ Imposing time constraints (e.g. 7AM to 5 PM) for works.  ‐ Alternative roads (roundabouts) should be located and marked.  

with procedures of “Provincial Directorate of Security – Traffic Department”   

Public & Transport safety 

‐ Clear warning and information signs should be positioned around the construction zone.  

‐ Imposing time constraints for works.  ‐ Alternative roads (roundabouts) should be located and marked.  ‐ Temporary pedestrian crossings will be organised for safety of pedestrians 

‐ Contractor (supervised by Construction Supervisor) 

Air Quality 

 Dust  

‐ Close or cover trucks for the transport of materials.  ‐ Water should be sprayed on the ground where dust is generated. ‐ Disposal of excess material and cleaning the location should be done upon the finalization of works.  

‐ Protective covers or curtains should be applied for zone where the largest amounts of dust are generated. 

 ‐ Contractor (supervised by Construction Supervisor) 

Exhaust gases from equipment  

‐ Construction equipment and vehicle’s emission and inspection licences should be inspected regularly  

‐ Imposing time constraints for works (e.g. 7AM to 5 PM). 

The inspection licenses are given by centres which is authorised by “Ministry of Environment and Forestry” and “Ministry of Transportation”  

‐ Contractor (supervised by Construction Supervisor) 

Noise and Vibrations  

‐ Imposing time constraints for works (works in the course of daytime (e.g. 7AM to 5 PM).  

‐ Schedules and/or other forms should be established for specific limitations for works. 

‐ Environmental noise levels on construction site should be below Ldaytime < 70 dBA 

Measures shall be according to requirements of Regulation on Assessment and Management of Env. Noise (2010) 

‐ Contractor (supervised by Construction Supervisor) 

Damages  (to Landscape, Archaeological Artifacts, Subterranean utilities )  

Damage to vegetation or roads, pavements 

‐ Minimizing the areas requiring the removal of vegetation. ‐ Upon finalization of works, replace/restore removed vegetation or roads, pavements 

 ‐ Contractor (supervised by Construction Supervisor) 

Deposit of excavated soil (erosion, landslides or sedimentation risk) 

‐ Depositing all excess excavated material in a compliant manner into a carefully selected landfill determined by relevant municipal bodies for utility affairs. 

 ‐ Contractor (supervised by Construction Supervisor) 

Damage to archaeological and cultural heritage 

‐ In case of any chance findings, works on the relevant construction site should stop and responsible authorities from Ministry of Tourism and Culture should be contacted.  

‐ Organise all necessary measures to protect the location.  ‐ No works to proceed until official notification is received 

All measures shall be with full cooperation and in compliance with procedures of “Ministry of Tourism and Culture”  

‐ Contractor (supervised by Construction Supervisor) 

Page 31: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM  ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 31  

Phase  Issue  Mitigation Measures  Comments  Institutional Responsibility 

Damages to existing infrastructure 

‐ Before commencing of the works relevant organisations shall be informed (gas, electricity, telecommunication, fuel lines etc.) and permit shall be obtained not to damage any other structure 

All measures shall be taken in full cooperation with and in compliance with procedures of Electric, Natural Gas, Telecommunication Companies 

‐ Contractor (supervised by Construction Supervisor) 

Water Services 

Periodic interruptions in water supply 

‐ Interruptions in water supply should be scheduled. ‐ The population should be informed about water cut‐off schedules with the objective of minimizing the negative effect on the population 

 ‐ Contractor (supervised by Construction Supervisor) 

‐ Kırşehir Municipality 

Pollution risk ‐ During installation of new pipes, initial cleaning, disinfection, final cleaning should be done according to requirements of the regulations 

 ‐ Contractor (supervised by Construction Supervisor) 

Worker’s Health and Safety  

‐ During all construction activities, following the requirements stated in all the regulations, by‐laws and rules issued under Work Law should be ensured. Contractor shall assign a responsible Engineer for this.  

‐ Equipment required for worker’s health and safety (mask, steel top boots, gloves etc.) should be ready to use and as spare. Especially as mentioned above, if a possible contact with asbestos cement pipes happens, respirator masks with special filters should be used.  

All measures shall be taken according to the requirements of regulations, by‐laws and rules issued under Work Law (Regulation and By‐law on Worker’s Health and Safety, Regulation on Heavy and Dangerous Works, Regulation on Manual Carriage, Regulation on Health and Safety Conditions During Usage of Working Machines, Regulation on Personal Protective Equipment, etc.) 

‐ Contractor (supervised by Construction Supervisor) 

OPERA

TIONS PH

ASE 

 

Water Services 

Blockages of the pipes and damages  

‐ Continuous control of compliance of the entire water supply system.  ‐ In the case of a blockage, urgent removal of the causes of the blockage.  ‐ In the case of damage, urgent repair and maintenance 

  ‐ Kırşehir Municipality 

Water Quality 

‐ Regular analysis should be done in sources and in some locations in network. ‐ In case of changes in water quality, take the necessary measures. (i.e. if bacterial pollution, inspect the chlorine dosing, if any other pollutant parameter find the pollutant source and find solution for further treatment) 

Measures shall be according to requirements of Regulation on Water Used for Human Consumption (2005) 

‐ Kırşehir Municipality 

Health and Safety 

Chlorine safety 

‐ Safety and isolation of chlorine tanks and chlorination rooms should be ensured for health and safety of the operators. 

‐ Regular control and maintenance of dosing equipment should be done for health and safety of the Public. 

  ‐ Kırşehir Municipality 

 

Page 32: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 32 

5. MONITORING PLAN  

For  the  above  mentioned  impacts  and  mitigation  measures,  a  monitoring  plan  is created. This monitoring plan shall ensure that the construction and operation of the project is in conformance with Turkish law and other relevant norms and standards.  

Since some costs for monitoring of the implementation of the mitigation measures for decreasing  the  environmental  impact  is  included  in  construction  costs  of  the Contractor  firm during  construction  stage; and operational  costs of  the Municipality during operation stage, these are not indicated as separate in below table. 

   

Page 33: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM  ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 33  

Table: 5.1‐ Monitoring Plan 

 Phase 

Which parameters shall be monitored 

Where shall the parameters be monitored 

How shall the parameters be monitored 

When shall the parameters be monitored 

Why shall the parameters be monitored 

Responsibility 

CONSTRU

CTION PHASE 

Solid and Liquid Waste 

Excavation waste ‐ On the construction site ‐ On the storage/ usage area 

‐ Visual examination during construction 

Daily during construction 

‐ Health and safety of the public 

‐ Construction Supervisor ‐ Kırşehir Municipality 

Replaced material (Pipes etc) 

‐ On the construction site ‐ On the storage area 

‐ Visual examination during construction 

Daily during construction 

‐ Health and safety of the public 

‐ Construction Supervisor ‐ Kırşehir Municipality 

Spill outs from equipment (fuel, lubricant, antifreeze etc.) 

‐ Below and around the place where materials are stored and used.  

‐ Near the vehicles and around the vehicles 

‐ Visual examination during construction 

Daily during construction 

‐ Protection of soil, subterranean and surface water 

‐ Construction Supervisor ‐ Kırşehir Municipality 

Domestic type solid waste & wastewater from construction site 

‐ On the construction site  ‐ Visual examination during construction 

Daily during construction 

‐ Protection of environment (receiving media and soil) 

‐ Construction Supervisor ‐ Kırşehir Municipality 

Traffic 

Interruptions of transport 

‐ On the location and around the location 

‐ According to complaints of the population in the vicinity or transport participants 

Daily during construction 

‐ Safety of the population, transport and workers 

‐ Construction Supervisor ‐ Kırşehir Municipality 

Transport safety ‐ On the location and around the location 

‐ Warning and informative signs shall be inspected 

‐ Complaints or comments shall be taken into consideration 

Daily during construction 

‐ Safety of the population, transport and workers 

‐ Construction Supervisor ‐ Kırşehir Municipality 

Air Pollution 

Dust generation ‐ On the location and around the location 

‐ Visually, on the basis of irritation of the breathing system, complaints of the population in the vicinity 

Daily during construction 

‐ Safety of the population and workers 

‐ Construction Supervisor ‐ Kırşehir Municipality 

Exhaust Gases ‐ On the location and around the location 

 

‐ Visually, on the basis of irritation of the breathing system,  

‐ Complaints of workers and the population in the vicinity 

‐ Checking the inspection licenses 

Weekly during construction 

‐ Safety of the population and workers and protection of air quality 

‐ Construction Supervisor ‐ Kırşehir Municipality ‐ Authorised exhaust inspection organisations 

Page 34: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM  ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 34  

 Phase 

Which parameters shall be monitored 

Where shall the parameters be monitored 

How shall the parameters be monitored 

When shall the parameters be monitored 

Why shall the parameters be monitored 

Responsibility 

Noise and vibration ‐ On the location and around the location 

‐ By listening, complaints of the population in the vicinity and workers weekly, 

‐ By regular noise measurements monthly 

Weekly and monthly during construction 

‐ Safety of the population and workers, reduction of the nuisance 

‐ Construction Supervisor ‐ Kırşehir Municipality 

Damages  (to 

Landscape, Archaeologi

cal Artefacts, Subterranean utilities ) 

Removal of vegetation and subsequent replanting of the area 

‐ On the location and around the location 

‐ Visually during construction, ‐ Examination and photographing before and after the works 

 Before and after the works on construction 

‐ Conservation of natural resources, esthetic reasons 

‐ Construction Supervisor ‐ Kırşehir Municipality 

Deposit of excavated soil (erosion, landslides or sedimentation risk) 

‐ On the location 

‐ Visual examination during construction,  

‐ Geotechnical examinations if required 

 Before the initiation of works and during construction 

‐ Safety of workers, transport safety and protection of soil 

‐ Construction Supervisor ‐ Kırşehir Municipality 

Discovery of artefacts and other items of cultural and historical value 

‐ On the location and around the location 

‐ Visually during construction  Daily during construction 

‐ Protection of cultural heritage 

‐ Construction Supervisor ‐ Kırşehir Municipality ‐ Ministry of Tourism and Culture 

Damages to existing subterranean utility installations and devices 

‐ On the location and around the location 

‐ From available drawings of existing infrastructure  

‐ Visually in the course of works, from construction site  

 Daily during construction 

‐ Safety of the population and workers, 

‐ Functionality of installations 

‐ Construction Supervisor ‐ Kırşehir Municipality Owners of installations, relevant inspection bodies 

Water Services 

Periodic interruptions in water supply  

‐ On the location and throughout the water supply system 

‐ Public information, on the basis of minutes. 

 Daily during construction 

‐ Reduction of harmful effects on the timeliness and quality of supply 

‐ Construction Supervisor ‐ Kırşehir Municipality 

Pollution risk  ‐ On the location  ‐ Visually in the course of works  Daily during construction 

‐ Reduction of harmful effects  

‐ Construction Supervisor ‐ Kırşehir Municipality 

Worker’s Health and Safety  ‐ On construction site ‐ Visually in the course of works and also according to the Safety Engineer’s reporting 

Daily during construction 

‐ To decrease accident risk  

 ‐ Construction Supervisor Kırşehir Municipality  

Page 35: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM  ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 35  

 Phase 

Which parameters shall be monitored 

Where shall the parameters be monitored 

How shall the parameters be monitored 

When shall the parameters be monitored 

Why shall the parameters be monitored 

Responsibility 

 

OPERA

TION PHASE 

Water Services 

Blockage of the pipeline 

‐ On the location and around the location 

‐ Visually and via SCADA system, by continuous control of system operations  

‐ Reports of the population 

Continuously ‐ Health and safety of the population 

‐  Transport safety, ‐ Kırşehir Municipality 

Water Quality ‐ In all water storage tanks and also network  

‐ Via on‐line SCADA system monitoring equipment  

‐ Sampling and analysis in various locations in network Ş 

Continuous(SCADA) Weekly (Network sampling) 

‐ Health and safety  ‐ Kırşehir Municipality 

Health and safety 

Damages to the pipeline 

‐ On the location 

‐ Visually and via SCADA system, by continuous control of system operations  

‐ Reports of the population 

Continuously ‐ Health and safety of the population 

‐  Transport safety, 

‐ Kırşehir Municipality,  ‐ Ministry of Environment and Forestry 

  

Page 36: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 36 

6. INSTITUTIONAL ARRANGEMENTS  

The organisations and  institutions  responsible  for  implementation and monitoring of the mitigation measures are as the following: 

Kırşehir Municipality: 

Since Kırşehir Municipality  is the main Beneficiary of the Project, generally  it has the main  responsibility  for environmental management during planning,  implementation and  operation  of  the  Project. Municipality  has  the  capacity  to  properly  implement environmental management plan.  In future  if required, the Municipality would retain environmental  specialist  consultants  to  assist  them  in  supervising  the works  carried out by the contractor and ensuring that the EMP is followed adequately. Municipality’s responsibilities  for  preparation  of  EMP  are  given  generally  in  Chapter  2.  The responsibility  after  EMP  is  prepared  ‐during  implementation  of  the  Project,  i.e. construction and operation of the Project‐ is as follows: 

‐ During  planning  stage,  Kırşehir Municipality  is  responsible  to  ensure  all  the mitigation measures and monitoring plan  is  included  in tender documents  for selection of Contractor and Construction Supervisor Firm. So,  this will  inform the firms about the  importance of the environmental measures  in the Project during  tendering  phase  and  ensure  they  prepare  tender  dossier  accordingly. Tendering Committee will do the evaluation of the dossiers also considering the environmental approach of the firms. 

‐ During  construction  stage, Kırşehir Municipality  is  responsible  for monitoring the  Contractor  and  Construction  Supervisor  implementing  all  the mitigation measures written in this EMP and tender documents and to forward this info to Iller Bank and World Bank regularly. 

‐ During  operational  stage,  Kırşehir Municipality  is  responsible  for monitoring the operation is ensured to decrease the minimum environmental effect and to forward this info to Iller Bank and World Bank regularly. 

Kırşehir Municipality shall inform Iller Bank and World Bank about the implementation of mitigation plan and monitoring activities during  construction and operation  stage via reports prepared regularly. 

Municipality  will  request  from  Contractor  and  Construction  Supervisor  to  add information on EMP implementation to their monthly, quarterly and biannual progress reports. As addition to these information, considering the observations and inspections 

Page 37: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 37 

done  on  site  and  public’s  comments,  Municipality  will  add  information  on implementation of EMP to Project Progress Reports as separate chapter and send it to Iller Bank regularly.  

Contractor Firm 

‐ During  Construction  stage,  the  Contractor  is  fully  responsible  to  take  all mitigation measures  written  in  this  “Environmental Management  Plan”  and also in the construction tender documents. 

Construction Supervisor 

‐ During  construction  stage,  the  construction  supervisor  is  responsible  to monitor/supervise  the  Contractor  to  ensure  the  Contractor  is  taking  all  the mitigation measures  written  in  this  “Environmental Management  Plan”  and also in the construction tender documents. 

‐ Construction Supervisor is responsible for reporting to the Kırşehir Municipality and Iller Bank about implementation of the mitigation measures written in this EMP.  Supervisor will  create monthly,  quarterly  an  biannual  progress  reports and add a also add a part in these reports to summarise the implementation of this EMP. 

Iller Bank 

Iller  Bank,  Project  Management  Unit  will  continue  to  include  an  environmental specialist  to  coordinate  the  implementation  of  the  Environmental  Framework.  The Environmental Specialist’s responsibilities will be as follows: 

‐ During  construction  and  operational  stage,  Iller  Bank  is  responsible  for supervision  and  monitoring  of  Kırşehir  Municipality  for  implementation  of mitigation measures and monitoring plan. For this  İB will regularly  inspect the Project during  construction  and operation. When  IB notices  any problems  in EMP  implementation  it will  inform  the  Kırşehir Municipality  and  agree with them on steps to rectify these problems. 

‐ Iller Bank is responsible for reporting to the World Bank about implementation of  the mitigation measures written  in  this  EMP.  In  the  Project  Reports  sent every  six  months,  IB  will  also  add  a  part  in  this  report  to  summarise  the implementation of this EMP 

‐ Iller Bank will also create the EA status table titled “Environmental Assessment Status  of  Project  Components  by  Municipality”.  The  table  will  include information on  the WB  EA  category,  review of  the  EA  TOR by  IB,  consultant hiring, public consultation meetings, status  (drafting, revision and  finalization) of the EA report. IB will share this document with the WB upon request 

    

Page 38: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 38 

World Bank 

‐ World  Bank  shall  be  informed  about  the  implementation  of  environmental management plan  via  the Project progress  reports  that will be  submitted by Iller Bank regularly and follow up the implementation. 

‐ World Bank project team will on occasion, and as required, also visit project sites as part of project supervision. 

 

Ministry of Environment and Forestry: The targets of the Ministry are; protection and  improvement of environment, proper and effective usage and protection of urban and rural areas and natural resources, protection of natural vegetation and animal presence and natural resources of country, prevention of all environmental pollutions. For prevention of pollution in Kırşehir’s water resources, Ministry with the  help  of  Regional  Environmental  Directorate  shall  inspect,  control  and cooperate with  the Municipality,  Public  and  Industries,  so  it  is  considered  as  a stakeholder with high importance and influence. 

 State Hydraulic Works (DSI):  DSI  is  the  primary  executive  state  agency  of  Turkey  for  Nations  overall  water resources  planning,  managing,  execution  and  operation.  DSI  is  responsible  for water  development,  management  and  allocation  (surface  and  groundwater), monitoring  water  quantity  and  quality,  construction  of  irrigation  schemes  and dams. In Kırşehir Project, DSI has high influence for control of water resources.  Ministry of Health: It is charged with the responsibility of providing quality health care  for  all  citizens  so  that  they may  lead  economically  and  socially  productive lives. Ministry  of  Health  is  responsible  for  setting  water  quality  standards  and monitoring and controlling them through the Provincial Health Directorates.  

 

Page 39: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Page 39 

7. CONSULTATIONS WITH AFFECTED GROUPS AND NON  ‐

GOVERNMENTAL ORGANISATIONS  

A presentation and a meeting  is organised  to  inform  the affected groups and  to get further comments from them about the Project. The announcement of the meeting is done from Web site of the Municipality, via 3  local newspapers, via calling  important chambers and via megaphone announcement  to  the city centre. The meeting details are as follows: 

‐ Date of consultation    : 22 October 2010 ‐ Location of consultation  : Kırşehir Municipality ‐ Meeting Program    : As the following; 

Opening  speech  of Mech.  Engineer  Özer Sezen from Kırşehir Municipality 

Project Introduction and Targets  Kırşehir’s  existing  infrastructure  ‐ 

Understanding the Problem   Proposed Project Measures  Possible negative  and positive  impacts of 

the Project  Mitigation Measures  Monitoring Plan  Discussion Session 

 The  meeting  minutes,  announcements  (web  page  and  local  newspapers),  list  of chambers invited via telephone, participant lists are given in Appendix 5.      

Page 40: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

APPENDIX 1 THE AREAS WHICH HAVE NOT WATER  DISTRIBUTION NETWORK IN KIRŞEHIR 

 

Page 41: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL
Page 42: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

 APPENDIX 2   

PROBLEMATIC AREAS IN KIRŞEHIR WATER DISTRIBUTION NETWORK  

Page 43: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL
Page 44: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

 APPENDIX 3   

PROPOSED MAIN TRANSMISSION LINE ALIGNMENT  FOR KIRŞEHIR WATER SUPPLY SYSTEM 

Page 45: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL
Page 46: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

 APPENDIX 4 

PROPOSED WATER SUPPLY SYSTEM IN KIRŞEHIR  

Page 47: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL
Page 48: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

APPENDIX 5 PRESENTATION AND PUBLIC MEETING FOR INTRODUCTION OF THE 

PROJECT AND ENVIRONMENTAL MANAGEMENT PLAN  

Page 49: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

Appendix 5 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Appendix 5 ‐ Page 1

 

 

APPENDIX 5 ‐ PRESENTATION AND PUBLIC MEETING FOR INTRODUCTION OF THE PROJECT AND ENVIRONMENTAL MANAGEMENT PLAN 

A.5.1  MINUTES OF MEETING  

QUESTION  (Haluk  Türedi  –  Representative  from  Kırşehir  Chamber  of  Civil Engineers):  Shall  the  existing  potable water  sources  be  sufficient  to  increase  the water production  from 48.000 m3/day to 76.000 m3/day  in year 2040? From where the  difference  amount  shall  be  supplied  from?  Currently  there  is  total  20.000 m3 storage volume, and 10.000 m3 shall be constructed. Where are the new locations of new reservoirs?  

ANSWER (Civ. Eng. Türkan Özkuş/Tempo): The existing wells are being used with the flowrates stated  in  the conditions of Protocol between DSI  (State Hydraulic Works) and Municipality. The wells are being operated 60%  capacity  in winter and only  in summer  with  100%  capacity.  Current  water  losses  have  been  calculated  as  77%. Considering these water  losses shall be decreased and the current operation rate of the wells  shall  be  increased,  it’s  determined  that  the  existing water  resources  are sufficient. For 275.000 population  total 20.625 m3 storage  tank volume  is  required. There are 10 storage tanks with 19.700 m3 capacity. Since some of the storage tanks with a  total volume of 7.200 m3  shall be out of order and  storage  tanks with  total 10.000 m3 volume shall be newly constructed, there won’t be any problem for year 2040. 

ANSWER  (Mech. Eng. Özer Sezen/ Kırşehir Municipality): Since the current sources are  sufficient  there  isn’t any project measure  foreseen as opening a new well. For year 2040, as standby, if required and if the efficiency of the wells decreases then we can negotiate with DSI and new locations for new wells can be determined.  

 

QUESTION  (Haluk  Türedi  –  Representative  from  Kırşehir  Chamber  of  Civil Engineers):  What is the material of pipe which will be laid near Kılıçözü river? What is  the main characteristic of  the pipe?  Is  it plastic or steel based? Can  the material used in geo‐thermal projects used in here also? 

ANSWER  (Civ.  Eng.  Türkan  Özkuş/Tempo):  According  to  design  criteria  and Municipality’s requests ductile font pipe is chosen as pipe material. Ductile font pipe is made of cast iron covered with concrete. In geo‐thermal applications GRP material is used. Considering economical and usage criteria (connection method, fragility etc) ductile font pipe is found more suitable. 

ANSWER  (Mech. Eng. Özer Sezen/ Kırşehir Municipality): We had two alternatives, wither PE or ductile font pipe would be chosen. GRP pipe is not found appropriate.  

QUESTION  (Nihat Sönmez‐Kamu Sen)  : Shall  the new storage  tanks constructed on the same locations? Considering the elevations, there may be locations which would have pressure problems, for example Kervansaray region would have some problems.  

ANSWER  (Civ.  Eng.  Türkan  Özkuş/Tempo):  Only  Kındam  storage  tank  shall  be constructed in a different location. The storage tanks for Kervansaray region, Mehtap 

Page 50: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

Appendix 5 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Appendix 5 ‐ Page 2

 

1  and  2  shall  be  constructed  in  the  same  locations  on  1200 m  elevation.  During preparation  of  implementation  project  according  to  final  topographical measurements,  if  there will  be  areas which would  have  pressure  problems,  then booster pump set for some areas or new tank locations would be determined.  

ANSWER (Mech. Eng. Özer Sezen/ Kırşehir Municipality): This is a feasibility project, during  preparation  of  the  implementation  projects,  for  these  details  final arrangements shall be done. 

 

QUESTION  (Nihat  Sönmez‐Kamu  Sen(Public  Union)):  Where  did  you  get  the population projections? We have different data for year 2025 as 145.000.  

ANSWER  (Civ.  Eng.  Türkan Özkuş/Tempo): We  have  used  different mathematical methods. The populations are calculated according to arithmetical, geometrical, Bank of  Provinces  methods,  and  then  it’s  compared  with  UN,  TÜİK  and  previous infrastructure  project’s  projections.  Finally  for  year  2040  population  projection, 275.000 is found as appropriate.  

 

QUESTION (Özgür Sağkal‐Chamber of Drivers/General Secretariat): Did any reserve calculations done on the potable water?  

ANSWER(Mech. Eng. Özer Sezen/ Kırşehir Municipality  ‐  İnş. Müh. Türkan Özkuş/ TEMPO):  In  this  subject DSİ  (State’s Hydraulic Works)  are being worked.  So  in  the content of this project no study has been executed. There is a protocol which states the flowrate that DSI gives permission to be used by the Municipality. And we cannot use more than this. If required a new study or protocol can be negotiated with DSI. 

 

QUESTION  (Nihat  Sönmez‐Kamu  Sen(Public  Union)):The  hardness  ratio  of  water from Okse region would be high.  

ANSWER  (Civ.  Eng.  Türkan  Özkuş/Tempo):  According  to  chemical  analysis  results parameters of the well water are found as appropriate. We can only use the water if analysis is OK.  

ANSWER (Env. Eng. MSc. Bilgen Özenirler/Tempo): Hardness doesn’t have negative effect on human health if it is not over the limits. Also in regulations for water to be used for human consumption, the  limits are not too  low. According to consumption reason  (hotel  laundries,  laboratories  etc.),  sometimes  hardness  removal  is  being applied. However treatment process which is done with resin or etc can increase the Na  ratios and can be more harmful  than hard water. Since hardness  ratios are not over the limits, such processes are not required.  

QUESTION  (Halil  Koyuncu‐  Municipality  of  Kırşehir/Directorate  of  Research  and Project): How is the pH parameter of the well water?  

ANSWER  (Env.  Eng.  MSc.  Bilgen  Özenirler/Tempo):  pH  (and  other  pollution parameters)  are  not  over  the  regulation  limits,  so  no  treatment  measure  is recommended.  However  during  operation,  as  it’s  also  given  in  Environmental Management  Plan,  regular  sampling  and  analysis  shall  be  done. And  if  any  of  the pollution  parameters  are  found  over  the  limits,  then  treatment measures  shall  be 

Page 51: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

Appendix 5 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Appendix 5 ‐ Page 3

 

applied. For example if ph increases or decreases then this will be solved via chemical dosing.  If any other pollutant parameter  is  found,  then as addition  to chlorination, recommendation of conventional or advanced treatment methods (according to type of  parameter)  is  possible.  However  the  quality  of  the  current well water  doesn’t require such measure.  

 

QUESTION (Nihat Sönmez‐Kamu Sen(Public Union)):For potable water ozone is being used in Europe, do you have any recommendation related with this? 

ANSWER  (Env.  Eng. MSc. Bilgen Özenirler/Tempo):  To  prevent  the  bacteriological pollution disinfection is a must. Disinfection can be done via chemicals or ultraviolet. The most frequently used chemicals are chlorine and ozone for disinfection. Ozone is a  chemical  with  high  oxidation  and  disinfection  effect.  However  it  doesn’t  have residual effect  i.e. when  it’s dosed to water  it enables high disinfection but  it won’t have  any  effect  afterwards,  to  the  pollutants  that  may  occur  in  the  network. Ultraviolet devices works as same, when  it’s apllied  it gives high disinfection effect, but  since  it  doesn’t  also  have  residual  effect  it  cannot  protect  water  against pollutants that may come  in water distribution system. Usage of chlorine  is because of it’s residual effect. After chlorine is dosed, it disinfects water, also chemical agent; it continues its disinfection and protective effect till the end part of network.  

 

QUESTION  (Nihat  Sönmez‐Kamu  Sen(Public  Union)):Does  the  ozoning  affect  the asbestos pipelines?  

ANSWER (Env. Eng. MSc. Bilgen Özenirler/Tempo): In the content of the project, it’s recommended  to  change  the  asbestos  pipelines.  Because  of  the  health  effects asbestos pipe is not preferred in potable water projects. Ozone as we told earlier is a highly  efficient  disinfection method,  however  since  it’s  residual  effect  is  not  like chlorine, we haven’t recommended it.  

 

QUESTION (Halil Tan – Municipality of Kırşehir / Deputy Manager): How is the time periods foreseen for the project? 

ANSWER  (Civ. Eng. Türkan Özkuş/Tempo): 2It’s  foreseen  the  construction  shall be finished in 2011 and 2012.  

 

QUESTION  (Nihat Sönmez‐Kamu Sen(Public Union)): Shall all of  the asbestos pipes be changed?  

ANSWER  (Civ.  Eng.  Türkan  Özkuş/Tempo):  As  priority  problematic  areas  shall  be changed.  

ANSWER (Haluk Türedi – Representative from Kırşehir Chamber of Civil Engineers ): 134 km shall be renewed as it’s mentioned. 

 

QUESTION  (Halil  Tan  –  Municipality  of  Kırşehir  /  Deputy  Manager):  You  have recommended “Water Administration” to be established. Is this highly indispensible?  

Page 52: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

Appendix 5 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Appendix 5 ‐ Page 4

 

ANSWER  (Civ.  Eng.  Türkan  Özkuş/Tempo):  This  recommendation  is  foreseen  as institutional measure  as  addition  to  the  technical  Project measures.  For  all  these services mentioned,  there are different departments  in Kırşehir Municipality. These different departments and  responsibilities can cause some problems and effect  the performance  of  the  departments.  For  this  reason  to  unite  these  services  in  one directorate  as  “Water  and  Sewage  Administration”  is  indispensible  and  it  will enhance better execution of all these services. 

ANSWER(Mech. Eng. Özer Sezen/ Kırşehir Municipality):  In our Municipality,  these services are executed by 3 departments which are Directorate of Utilities, Directorate of  Financial  Services,  Directorate  of  Water  Works.  In  other  provinces,  these directorates  are  gathered  in  one  directorate  just  to  give  service  on  water  and wastewater  issue,  it’s  budget  is  also  separate.  This  is  an  effective method  also  to prevent water  leakages  and  losses. We have observed  an  example  in Antalya.  For example ASAT executed an effective study on water meters. And they have inspected 25% difference between 1., 2. and 3. type water meters. Similarly, we can decrease water  losses  via  changing  the  water  meters.  However  inspection,  changing  and decreasing the water losses can only be achieved by the coordinated working of one department like “Water and Sewage Administration”.  

 

QUESTION (Nihat Sönmez‐Kamu Sen(Public Union)):This project shall be financed by World  Bank.  Some  of  this  potable water  shall  be  used  also  for  irrigation  by  some consumers.  Beside  this  Project,  can  another  project  for  supplying  irrigation water from Kızılırmak river also considered as alternative project?  

ANSWER  (Civ. Eng. Türkan Özkuş/Tempo): This project only  consist potable water component.  In  these  kinds  of  projects  there  is  a  limited  budget,  and  project components  can  not  be  out  of  this  budget.  Irrigation  can  also  be  considered  as  a separate project  like wastewater  and  stormwater.  For  those  there must be  a new separate budget and a new feasibility study can be executed for this.  

 

QUESTION (İsmet Yanık‐ KIRÇED): Did the water come from Kızılırmak river cause any problems in Ankara?  

ANSWER  (Env.  Eng.  MSc.  Bilgen  Özenirler/Tempo):  Ankara  supplies  water  from Çamlıdere, Kurtboğazı and Akyar Reservoirs. For the future supply systems from Bolu or Kızılırmak river was planned. However because of the dry season in previous years, as emergency solution water transmission line from Kızılırmak river is constructed in a very short time. But because of the problems that may occur in treatment plant, in the  old  buildings  which  has  old  steel  pipes  and  corosivity  of  the  water,  some problems (yellow colour of the tap water) are observed in Ankara.    

Page 53: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

Appendix 5 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Appendix 5 ‐ Page 5

 

A.5.2  ANOUNCEMENT IN MUNICIPALITY’S WEB PAGE  

 

 

 

 

 

Page 54: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

Appendix 5 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Appendix 5 ‐ Page 6

 

 

 

A.5.3  INVITED VIA TELEPHONE: 

  NAME OF THE N.G.O.   1  Chamber of merchants and craftsmen   Professional Chamber 2  Chamber of Trade and Industry  Professional Chamber 3  Cooperative of Merchants and Craftsmen   Cooperative 4  Chamber of Agriculture  Professional Chamber 5  Kırşehir Ahi Businessman Association   Association 6  Village Headmen Association   Association 7  Chamber of Electrical Engineers   Professional Chamber 8  Chamber of Civil Engineers   Professional Chamber 9  Chamber of Topography Engineers   Professional Chamber 10  Chamber of Mechanical Engineers   Professional Chamber 11  Turkish Standards Institute Provincial Directorate  Institute 12  Chamber of Architects  Professional Chamber 13  Chamber of Agricultural Engineers   Professional Chamber 14  Chamber of Drivers   Professional Chamber 15  Hizmet‐İş   Syndicate 16  Yerel‐is Syndicate  Syndicate 17  Kamu‐Sen  Syndicate 18  Bembirsen  Syndicate 19  KTV  Local TV 20  Ahi TV  Local TV 

 

 

 

 

 

 

 

 

 

 

 

 

Page 55: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

Appendix 5 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Appendix 5 ‐ Page 7

 

A.5.4  ANOUNCEMENT VIA 3 LOCAL NEWSPAPERS: 

 

 

 

Page 56: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

Appendix 5 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Appendix 5 ‐ Page 8

 

A.5.5  LIST OF PARTICIPANTS

Page 57: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

Appendix 5 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Appendix 5 ‐ Page 9

 

 

 

 

 

Page 58: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

Appendix 5 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Appendix 5 ‐ Page 10

 

A.5.6  PHOTOS FROM THE MEETING 

 

 

 

Page 59: FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR … · 2015-09-01 · FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL

FEASIBILITY STUDY FOR REHABILITATION OF KIRŞEHİR POTABLE WATER TRANSMISSION LINE AND NETWORK SYSTEM ENVIRONMENTAL MANAGEMENT PLAN 

Appendix 5 

 

Kırşehir Municipality‐ Tempo Engineers & Consultants Inc.  Appendix 5 ‐ Page 11