F-35 Joint Strike Fighter Procurement Program in...
Transcript of F-35 Joint Strike Fighter Procurement Program in...
F-35 Joint Strike Fighter
Procurement Program in Canada
Applied Project for Athabasca University
Master of Business Administration Program
APRJ-699
Author: Ken Lin
Word Count: 13,741
Submission Date: April 17th, 2012
Academic Supervisor: Dr. Ike Hall
Page 2 of 76
Executive Summary The CF-18 fighter jet fleet currently serving the Royal Canadian Air Force is expected to reach the end of
its service life between 2016 and 2020. Planning for the replacement aircraft by Canadian Department of
National Defence (DND) started in 1997; since then, Canada has participated with Lockheed Martin’s
concept development phase and system development and demonstration phase for the F-35 Joint Strike
Fighter (JSF) program. The two phases have required $160M of Canadian government investment into
the JSF development program along with funds from eight other partner countries, totaling nearly US$5B.
The Government of Canada announced in 2010 that the F-35 JSF aircraft “has been selected.” However,
a procurement contract had still not been signed by March 2012, when this Applied Project was being
prepared. This project reviews the history of Canadian participation in the JSF program, and the
progression of the sole-source procurement approach taken by the Canadian government to date, along
with procurement status of other international partners in the program. The data used for this analysis is
limited primarily to the various US and Canadian government reports generated between 2005 and early
2012, tracking the progress of the JSF program.
Concerns about the cost and schedule of the JSF program have continued to grow. The time allotted for
the development program has increased significantly, requiring several revisions to the Integrated Master
Schedule, and the cost has also ballooned, requiring funding revisions and a funding freeze for certain
aspects of the program, pending corrective actions being implemented.
The schedule delay and cost increase have also created concerns among all the international partners,
even though they recognize that complex development programs have the potential to develop these
issues. It is the magnitude of the problems in the JSF program that has resulted in international partners,
including Canada, indicating they are reconsidering their options while assessing the potential impact of
the cost increase and schedule delay to their respective fighter replacement programs.
Page 3 of 76
Furthermore, the traditional Industrial Regional Benefit (IRB) program does not apply to the JSF
program. Instead, the program is based on “best value,” with Lockheed Martin selecting companies to
provide services or products for the JSF program. Unlike the traditional IRB program, which is
structured around a “same as contract value” award of business opportunities for each partner nation
based on the value of the JSF aircraft purchased, the “best value” approach provides the advantage of
early industry participation during the development phase and the opportunity for companies to fulfill all
of the JSF production needs, therefore generating the potential to gain business volume that is not
possible under traditional IRB programs. However, the disadvantages of the JSF industrial benefit
approach include uncertain opportunities for companies to gain JSF work, and no opportunity for startup
companies seeking funding to develop a new service or product if it already exists and can be supplied by
an established company at better value.
The Canadian procurement process for the F-35 JSF must ensure that the aircraft matches Canada’s
requirements in future military missions without suffering the same fate as past military procurement
program failures, such as the Avro Arrow and EH-101. It is also important to ensure the aircraft selected
to replace the CF-18 fleet will meet Canada’s future military obligations while taking into consideration
capability, cost, and delivery schedule, and will include any additional cost implications, such as the air-
to-air refueling capability of the F-35A being considered for RCAF, since this variant is incompatible
with current Canadian tanker aircraft, and the possible addition of a drag chute to slow down the aircraft
and combat slippery conditions when landing on remote Arctic runways.
The JSF development program has not met all five objectives in the program performance assessment
framework; the aspects of cost, schedule, and reliability have not performed well, while quality and safety
have. The CF-18 transition must include contingency plans to address and mitigate the impact of potential
delays in the transition to the new fighter aircraft selected by the Canadian government.
Recommendations are:
Page 4 of 76
• Confirm RCAF requirements for the fighter replacement
• Assess pricing and delivery for the selected replacement aircraft
• Assess choices other than the F-35, and assess the impact of withdrawing from the F-35 program
• Liaise with international F-35 partners for greater program management involvement
• Establish a comprehensive and enforceable procurement program should the F-35 remain
Canada’s choice for CF-18 replacement
• Prevent political interference in the selection and procurement process
• Initiate contingency planning to extend the CF-18 operating lifespan to compensate for delayed
delivery of the replacement aircraft
• Ensure industrial benefit is protected
• Maintain political transparency
In conclusion, the Canadian F-35 JSF procurement process requires a reassessment to determine if the F-
35 is the suitable aircraft as the CF-18 replacement for Canada, and to ensure the replacement aircraft
selection process is performed based on sound judgment and the S.M.A.R.T. process.
Page 5 of 76
Table of Contents
1 Introduction ..................................................................................................................................... 8
2 Delimitations ................................................................................................................................... 9
3 Literature Review .......................................................................................................................... 10
3.1 Major Procurement Program Strategy ..................................................................................... 10
3.2 Cost, Schedule, and Performance Requirement ....................................................................... 12
3.3 Offset Obligation Requirement ............................................................................................... 15
4 Research Design ............................................................................................................................ 16
4.1 Method of investigation.......................................................................................................... 16
4.2 Data collection ....................................................................................................................... 17
4.3 Research Questions ................................................................................................................ 17
5 Procurement Practice ..................................................................................................................... 17
5.1 History ................................................................................................................................... 18
5.2 Canadian procurement status .................................................................................................. 19
5.3 International partners procurement status ................................................................................ 20
5.3.1 Norway .......................................................................................................................... 20
5.3.2 Japan .............................................................................................................................. 20
5.3.3 Denmark ........................................................................................................................ 21
5.3.4 United Kingdom ............................................................................................................. 22
5.3.5 Australia ......................................................................................................................... 24
5.3.6 Italy ................................................................................................................................ 24
Page 6 of 76
5.3.7 Turkey ............................................................................................................................ 25
5.3.8 Israel .............................................................................................................................. 25
5.4 Canada’s procurement process ............................................................................................... 26
5.4.1 The sole-source approach ............................................................................................... 26
5.4.2 Requirement definition ................................................................................................... 28
5.5 Large-scale military procurement ........................................................................................... 30
5.5.1 Past Experiences ............................................................................................................. 31
5.5.2 Outcomes ....................................................................................................................... 32
5.5.3 Lessons learned .............................................................................................................. 33
6 Schedule and Cost Factors ............................................................................................................. 34
6.1 Lockheed Martin development program status ........................................................................ 35
6.2 Program schedule performance............................................................................................... 37
6.2.1 Current delivery schedule ............................................................................................... 42
6.2.2 Forecasted delivery for Canada ....................................................................................... 43
6.2.3 Capability concerns ........................................................................................................ 44
6.2.4 Implication to RCAF planning ........................................................................................ 45
6.3 Cost structure ......................................................................................................................... 46
7 Economic Benefit .......................................................................................................................... 48
7.1 Industrial Regional Benefit (IRB) program ............................................................................. 49
7.2 The Lockheed Martin approach .............................................................................................. 50
7.3 Canadian participation ............................................................................................................ 53
Page 7 of 76
8 Recommendations ......................................................................................................................... 53
9 Conclusions ................................................................................................................................... 56
Bibliography ......................................................................................................................................... 59
Appendix 1. F-35 Development Schedule Revisions 2003 to 2012 ......................................................... 71
Appendix 2. F-35 JSF Procurement Quantities 2012 .............................................................................. 74
Appendix 3. F-35 JSF International Development Contribution, ............................................................ 75
Appendix 4. F-35 JSF Procurement Quantity Forecast 2010................................................................... 76
Figure 1. A Quad Constrained Project Management Model (Norrie & Walker, 2004) ............................. 28
Figure 2. F-35 JSF SDD Completion Forecast ....................................................................................... 39
Figure 3. F-35 JSF Program Performance Objectives ............................................................................. 40
Figure 4. Canadian F-35 Price Estimation (Weltman & Yalkin, 2011).................................................... 47
Page 8 of 76
1 Introduction
The largest defense procurement program in the Canadian military history has been undergoing
preliminary technical and financial analysis phases since 2002, when the Canadian Department of
National Defence (DND) signed the memorandum of understanding (MOU) as a Tier III partner
(Government of Canada, 2006) for the system development and demonstration (SDD) of the F-35 Joint
Strike Fighter(JSF) program. The overall price for the Canadian Next Generation Fighter program has
been estimated between $9B to over $30B (CAD). The aircraft procurement program will replace the
aging Royal Canadian Air Force (RCAF) CF-18 Hornet fleet with 65 new planes, and the current sole
candidate for this program is the new Lockheed Martin F-35 Joint Strike Fighter (JSF) which is still under
development.
While the F-35 JSF is considered to be one of the most advanced military fighter jets available amongst
the current contenders, as of early 2012 a formal binding contract had not yet been awarded by the
Canadian government to Lockheed Martin. This scenario is intriguing, since the current Conservative
government previously made an announcement in July 2010 that Canada intends to procure the F-35 JSF
aircraft under sole-source and un-competitive selection process (National Defence and the Canadian
Forces, 2011). There appears to be continued hesitation by the very same Conservative government to
proceed with awarding the contract. This is perhaps due to the criticism about cost, delivery schedule
concerns, lack of industrial benefit commitment, mission requirement, and most significantly, the absence
of a competitive bidding process when the F-35 JSF was chosen.
The uncertain status of the procurement contract allows for an opportunity to continue reviewing some of
the underlying issues with the F-35 JSF procurement development to date.
The topic selected for this AP study will embody the selection process and economic impact of this
procurement program which will not only consume significant Canadian defense budget spending but will
also have long term economic influence in contributing to both present and future Canadian industry
Page 9 of 76
participation relating to this procurement. Specifically, the AP study will review the F-35 JSF
procurement history and process of international customers, and critique the procurement process
conducted by the current Conservative government since 2006. The review framework will be based on
strategic management philosophy, managerial economics assessment, management decisions,
procurement strategy, and financial analysis.
2 Delimitations
Due to the complex and extensive nature of the Next Generation Fighter Replacement Program, this study
will primarily examine the data from 2005 to 2011 while utilizing comparable reference data from 2002
when the original effort for this procurement program was first initiated by the Canadian Government.
The Applied Project will not attempt to address detailed technical issues due to the in-depth technical
knowledge required to perform legitimate assessments.
The information utilized to compile this Applied Project has been retrieved from traceable documented
sources and does not contain information gleaned from verbal discussions. The web site links of the
sources provided in this Applied Project were accurate and active at the time it was produced,, however it
cannot be guaranteed that these web site links will remain active indefinitely.
Finally, as a result of US Congressional reviews on the F-35 JSF program, in particular because of
significant cost increases and schedule delays, the F-35 JSF Program Office and Lockheed Martin had
committed in mid-2011 to producing a revised integrated master schedule (IMS) by early 2012. As of the
end of 2012’s first quarter, this task has not yet been completed or released, when the research of this
Applied Project was being conducted. It had been anticipated this revised IMS would provide an
important reference point to determine the aircraft delivery schedule for Canada and to assess the
potential impact the delivery schedule may have, along with any contingency plan that may be devised.
Due to the absence of the revised IMS, this Applied Project report has been conducted based on best
Page 10 of 76
available information, including the FY11 Annual Report produced by the US government’s Director of
Operational Test and Evaluation, combined with other reports available at the time of printing.
3 Literature Review
3.1 Major Procurement Program Strategy
The Standing Committee on National Security and Defence held several hearings in 2005 with senior
Canadian Forces leadership. The committee produced an interim report to address the state of the
Canadian military and its ability to meet the requirements in defending the nation abroad and at home
(Senate Committee on National Security and Defence, 2005). This report identified the Canadian defense
budget, which had been reduced significantly during the 1990s and which is continuously under scrutiny.
Defense spending must be vigilantly planned to ensure appropriate and best use of the budget that is made
available. Maximizing the benefits will depend on the successful execution of the procurement process to
achieve the desired outcome at completion.
A successful procurement program must ensure:
- The requirements are well defined
- The procured service or product matches the purpose it is intended to serve
- The delivery is completed in a timely manner for deployment
- The total expenditure remains within the allocated budget.
Additionally, military procurement programs should be void of political influence, which can drastically
alter the outcome of the procurement selection process in an adverse manner (Plamondon, 2010).
Additionally, the procurement must remain fair in order to deter a flawed process that is not based on the
competitive merit of quality, schedule, and cost.
Page 11 of 76
There has been an increased use of non-competitive bids or a limited tendering process for Canadian
military procurement over the past decade (Staples, 2007). For example, a sole-source through the
Advance Contract Award Notices (ACAN) process (where an announcement is made by Public Works
and Government Services Canada [PWGSC] that a company has been preselected for a procurement
program) a 15-day public notice is posted to allow other companies to contest the decision. This is often
a rubber-stamping process since there are seldom any valid counter proposals which can be prepared
within such a short time frame given the magnitude of major military procurement programs.
There are circumstances under which adopting this approach is appropriate, such as when time sensitivity
precludes the standard lengthy competitive bid process, or when there are clearly no other viable
alternatives. Additionally, the ACAN process is an intelligent procurement decision when made to avoid
wasted effort conducting an unnecessary and unproductive conventional procurement selection process
based on competitive bidding. However, the overall circumstances of the F-35 JSF as the Next
Generation Fighter replacement for the current RCAF CF-18 fighter fleet is not clear, since several other
viable alternatives exist that may be more suitable for the defense roles Canada is expected to perform in
the future.
The largest international defense spending budget is held by the US Department of Defense (DOD). The
spending by the DOD is indirectly under the oversight of the US government Accountability Office
(GAO), an independent, nonpartisan agency that works for the US Congress often described as the
“congressional watchdog” since it investigates how the federal government spends taxpayer dollars. The
GAO publishes many reports each year to address problems and provides information to Congress
concerning emerging and long-term issues (United States GAO, 2012). It is of interest to note that the US
government is facing similar difficulties with its own F-35 JSF procurement program. The GAO reports
relating to the F-35 JSF procurement program, which have parallels with the Canadian one, provide
valuable knowledge for those in charge of the Canadian procurement.
Page 12 of 76
3.2 Cost, Schedule, and Performance Requirement
Within the F-35 JSF development program there have been several major issues, such as cost, delivery
schedule, and performance constraints which have alarmed both the US government and international
customers (including Canada). Among these concerns, the cost factor has clearly risen to the top of the
list. The F-35 development program has once again revealed an often-encountered deficiency with major
weapon system procurement programs: the initial acquisition cost and subsequent operating and support
costs continue to rise beyond reasonable expectations. This is an area where the Canadian F-35
procurement office and government decision-makers must continue to maintain their due diligence with
Lockheed Martin to ensure the program cost does not creep up and escalate beyond the financial
affordability threshold of the Canadian Government.
The Parliament of Canada mandates the Parliamentary Budget Officer (PBO) to provide an independent
analysis on the state of the nation’s finances. It is customary for the PBO to perform these analyses on
large-scale procurements over which the Parliament has jurisdiction (Parliament of Canada, 2012). In
particular, a large-scale procurement such as the F35 with the magnitude of $9 billion-plus will trigger
PBO involvement. The report produced in March 2011 by the PBO to assess the fiscal impact of
Canada’s proposed F-35 JSF fighter acquisition has shown a greater discrepancy in the F-35 JSF
acquisition cost than the figures being presented by the Canadian government officials in recent
presentations and press releases (Yalkin & Weltman, 2011). The inconsistencies of the acquisition cost
demonstrates that there is a departure from the expected acquisition cost being presented to the public and
procurement committees, and will be further discussed in later sections of this applied project.
The long-term cost in operating and supporting major weapon systems has historically accounted for 60%
to 80% of the weapon systems’ total expenses. The product-supporting aspect includes material
management, distribution, technical data management, maintenance, training, cataloging, configuration
management, engineering support, repair parts management, failure reporting and analysis, and reliability
growth (United States Government Accountability Office, 2012). In fact, the US F-35 JSF program
Page 13 of 76
office estimated the life cycle operating and support costs for the US F-35 JSF fleet will cost $1.0 trillion,
and this figure is in addition to the $380 billion in total acquisition costs. The Canadian procurement
team should utilize these figures as a guideline to scale and calculate the approximate total acquisition
costs to replace the CF-18 fleet with the F-35 JSF.
The JSF program is based on the framework of pooling not only technical resources and manufacturing
capabilities of end user-countries but also taking advantage of economies of scale by combining the
purchasing power of many committed end-user countries to ensure the procurement cost remains within a
reasonable and affordable range. Lockheed Martin won the JSF competition in 2001against Boeing in a
funded initial developmental program, without any other US-built competing aircraft. Lockheed Martin
obtained strong “market power,” which increased considerably once the contract to proceed was awarded
by the US government. However, due to the magnitude of the procurement and the collective negotiation
leverage from other customers (i.e., the US government and development funding partner countries such
as Australia, Denmark, the UK, Italy, the Netherlands, Norway, Turkey and Canada), the two parties are
locked in a bilateral monopoly relationship where the market power of the buying organization
(monopsony power) confronts the market power of the seller (monopoly power) and the two parties have
developed a strategic relationship (Markowski & Hall, 2006).
In this bilateral monopoly relationship, the cost factor of the JSF has become a contentious issue between
Lockheed and its customers. In March 2010, the Pentagon acquisition chief (Ashton Carter) informed the
US Senate that the average per unit cost of the JSF had increased substantially from the initial $50M per
unit estimated in 2001 to $95M, which is equivalent to $112M in Fiscal 2011 dollars (Butler, 2010). This
trend has continued, albeit with some reduction of the overall program cost in certain aspects of the
development (such as the cancellation of the alternate F136 GE/Rolls-Royce engine for the JSF in favor
of single-sourcing with Pratt & Whitney an F135 engine) (Norris, 2011),
Page 14 of 76
With the advanced complexity of the F-35 JSF aircraft, it is recognized and accepted that the development
and production may require long delivery lead times. A side effect of the long delivery lead time in
today’s fast-changing technologies is that the National Defense Organizations (NDOs) may take this
opportunity to update their requirements during the development cycle, which can prolong both the
development and delivery cycles (Markowski & Hall, 2006). This risk of late delivery must be
understood, planned, and mitigated by the procurement team to ensure the procurement does not
adversely impact the purpose for which the procurement was intended to fulfill.
A secondary concern with the delivery schedule is that the US government may significantly reduce its
initially planned purchase quantities of 2,456 aircraft in order to accommodate the constraints of the
available budget (Gertler, 2012). This procurement reduction will directly affect how Lockheed Martin
structures its production plans to fulfill the US requirement, and may impact the foreign customers such
as Canada with delayed delivery and higher unit cost due to reduction of the economies of scale benefit
from the original higher production volume. This is also a factor that the Canadian F-35 procurement
team must consider since the effect of the US reduction will likely result in an undesirable impact on the
selection.
At the time of this applied project, the F-35 JSF procurement program in Canada remains effectively a
sole-source program without the benefit of a competitive bidding process to determine the “best bang for
the buck” from eligible suppliers (Staples, 2007). There have been legitimate circumstances in recent
Canadian military procurements, such as the C-17 Globemaster heavy-lift transport aircraft and the CH-
47 Chinook medium-lift helicopter, when either the nature of the product/service, or the immediacy of the
requirement precluded a competitive selection process. This does not appear to be the case for the
procurement of the F-35 at this time, when major cost increases and delayed delivery schedules are
almost unavoidable. Critics strongly argue that the F-35 may not be the right replacement aircraft for the
RCAF CF-18 fleet (Staples, 2010) based not only on the cost increase and delivery delay concerns but
also on the nature of the military missions that the RCAF is expected to undertake in the future.
Page 15 of 76
3.3 Offset Obligation Requirement
The mission statement of Industry Canada is to “foster a growing, competitive, knowledge-based
Canadian Economy” (Industry Canada, 2010, p. 1). One of the mechanisms utilized by Industry Canada
to achieve this objective is the Industrial Regional Benefits (IRB) program, which ensures that Canadian
industry benefits from any defense and security procurement by the Government of Canada. In particular,
this policy requires business activities equal to the same value of the contract awarded by the Canadian
Government to be awarded by the winning contractor to business and industry within Canada (Industry
Canada, 2012). The IRB policy would mean that if Lockheed Martin was awarded with Canada’s next
generation fighter replacement program contract, then the company would be required to fulfill the IRB
requirement to provide work equivalent to the contract value with Canadian business and industry.
Although the IRB requirements from Industry Canada have been in place as an obligation and have been
fulfilled by prime contractors in similar large-scale procurements in the past, Lockheed Martin has not
indicated they will fulfill this Canadian government policy. Furthermore, Canadian Industry Minister
Tony Clement “conceded the current arrangement with Lockheed Martin provides no such (IRB)
guarantees and that Canadian companies will have to bid on opportunities” (Brewster, 2010, p. 1).
Due to the high procurement cost of the Canadian F-35 JSF, the IRB is an important mechanism to offset
and balance government spending by creating business opportunities for Canadian industry. This
important factor should not be overlooked, as similar measures are actively being pursued by other F-35
JSF customers such as Australia. The formation of the Australian JSF Industry Group (AJIG, which
replaced the JSF Industry Advisory Council [JIAG] in 2009) is an effort by the Australian industry to
“discuss any systemic issues impacting on all industry, secure the production opportunities identified in
the Australian JSF Industry Participation Plan and identifying new opportunities for sustainment and
follow-on development” (Australian Government, 2009, p. 1). The Australian approach appears to be
more specific and organized as compared to Canada, where the Aerospace Industry Association of
Canada (AIAC) is entrusted with liaising between the Canadian aerospace industry and Lockheed Martin.
Page 16 of 76
In comparison, the Boeing Company fully complied with Industry Canada’s IRB requirement in the C-17
Globemaster strategic airlift aircraft procurement in 2006 (National Defence of Canada, 2012).
Specifically this meant that for every contract dollar awarded to Boeing, Boeing committed a
corresponding dollar in economic activity in Canada. This is strong evidence that business contracts can
be negotiated in a satisfactory manner between the supplier and the Government of Canada to fulfill the
obligation as laid out in the Industry Canada IRB policy.
For Australia, an international member of the original F-35 SDD team similar to Canada, the effect of the
F-35 procurement program is expected to become a template for future Australian acquisitions.
Traditional offset and work-share arrangement similar to the IRB program in Canada are excluded from
the JSF program, more specifically it is likely that only well-established firms with good track records
will be selected to participate in the JSF supply chain. Rather than developing new industry capabilities
in Australia the successful Australian industry participants within the JSF supply chain will then in turn
be able to provide their service and/or product to all of the F-35 customers (Markowski & Hall, 2006).
4 Research Design
4.1 Method of investigation
This study into the procurement process and economic benefits of the F-35 JSF as the replacement for the
RCAF CF-18 Hornet fleet is conducted based on the following approach and sequence:
1. Compile related defense industry articles from past procurement programs of similar nature to
identify the short comings and lessons learned
2. Compile current defense industry analysis articles and information concerning F-35 cost,
procurement process, delivery schedule, and development trends. The source of articles will be
carefully assessed and taken into consideration to ensure the integrity of the data used as input for
the data analysis is provided in a fair and balanced manner
Page 17 of 76
3. Compile and assess data collected from the articles
4. Compile industrial regional benefit (IRB) data relating to the F-35 procurement
5. Provide recommendations based on this study
4.2 Data collection
Canada joined the JSF program in 2002 as an active Tier III partner. The data being collected as the
source for this Applied Project will primarily be based on publicly available statistics and financial
reports in the public domain over the past ten years, including several detailed US and Canadian
government review publications. This applied project will reference the various sources of information
relating to the F-35 program to collectively compile and assess these data. This will serve to minimize
the potential for opinion-based bias from the authors of some reports.
4.3 Research Questions
Provided the Canadian F-35 procurement process continues to its completion, the estimated program
value will reach $9B for the aircraft acquisition and additional $6B for life cycle service and support. It
will have become the most expensive military procurement program in Canadian defense history.
The applied project will review the procurement progression of other international F-35 JSF customers for
comparison, and critique the current state of the Canadian F-35 procurement program given the on-going
controversy over the government’s insistence to continue with the procurement process. This applied
project will address the following elements:
- Increasing cost
- Risk of delayed delivery
- New industrial benefit approach
- Unclear requirement definition
5 Procurement Practice
Page 18 of 76
5.1 History
The F-35 procurement program was initiated by the US Department of Defence (DOD) in the early
1990’s in anticipation to the retirement of most of the military fighter types (including the A-10, F-16, F-
15, F-18 C/D, AV-8 etc.) starting approximately 2020. The concept of developing one common aircraft
with three variants to fulfill the requirement for most of the Western air forces was conceived to promote
cost-saving by sharing the technical development cost and improving the design cycle and delivery
schedule. This concept was conditionally accepted by several countries including Canada, Australia,
Denmark, Italy, United Kingdom, Norway, Netherlands, and Turkey as part of the Joint Advanced Strike
Technology program in 1997. The US DOD had down-selected Boeing and Lockheed Martin in 1996 as
the two final contenders for the Next Generation Joint Strike Fighter fly-off demonstration. Lockheed
Martin was eventually declared the winner in 2001 and awarded with the JSF contract after a heavily
contested selection.
The initial decision in 1997 by the Canadian government to participate in the Concept Demonstration
Phase of the F-35 JSF program for an investment of US$10M was based on the advantages expected by
being a member of a multi-national team to share the expense of the developmental activities. Canada’s
DND then continued with its participation by signing the MOU in 2002 as a Tier III partner for the
follow-on system development and demonstration (SDD) phase to demonstrate the Canadian
government’s further support and commitment to the F-35 JSF program. This required an additional
US$150M investment by the Canadian government which allowed DND to gain access to some of the
JSF program technology and data, (and management and engineering approaches) as well as an increased
access for Canadian industry to contract their product and services with the JSF program (Lockheed
Martin Company, 2012). The Canadian government gave no firm commitment, nor did any other
international partners, to actually procure the F-35 JSF aircraft at that time.
The current approach taken by the Conservative government of Canada is to sole-source the F-35 JSF as
the replacement for the RCAF CF-18 fleet despite continued evidence of cost and schedule issues with the
Page 19 of 76
technology development program at Lockheed Martin. This has been called to question by the critics of
the sole-source approach and the selection of F-35 JSF (Staples, 2010). The primary concern from the
critics is the government’s continued unwillingness to acknowledge and re-consider the need for a
competitive selection process to evaluate other viable aircraft from several international manufacturers
with capabilities equal to, or potentially more appropriate and at lower cost.
5.2 Canadian procurement status
Since 2006 the current Conservative government of Canada has remained steadfastly committed to the F-
35 JSF procurement despite publicly reported concerns with the F-35 JSF program’s cost increases,
schedule delays, and industry participation. These continuing difficulties are legitimate concerns with
whether the Canadian portions of the F-35 JSF program will remain on track for the benefit of Canada.
In January and April 2011, Prime Minister Harper made a statement suggesting a “contract,” presumably
for the purchase of F-35 JSFs for RCAF, has been in place, when in fact no F-35 JSF procurement
contract for Canada had been signed. After the March, 2012 F-35 program update meeting at the
Canadian Embassy in Washington the statements from the Associate Minister of National Defence Julian
Fantino and Prime Minister Harper indicated and confirmed that Canada had not signed a procurement
contract with the F-35 JSF manufacturer (Lockheed Martin).The statement further suggested that Canada
may delay the procurement of F-35 JSF until the aircraft is in full production by Lockheed Martin in order
to capitalize on the lower production costs in order to meet the $9B target for the currently planned 65
aircraft procurement for RCAF (Payton, 2012).
Furthermore, while in the past the Conservative government and Defense Minister Peter McKay have
both maintained their unwavering support to procure the F-35 JSF since 2006, the government has now
suggested that the option to consider other alternatives for the RCAF has not been ruled out (Berthiaume,
2012). Therefore it appears that the past commitment by the Canadian government to procure the F-35
Page 20 of 76
JSF is being reconsidered as a result of on-going concerns and public criticism while cost and schedule
difficulties continued to be the primary topics under scrutiny.
5.3 International partners procurement status
The concerns expressed by the critics of the Canadian F-35 JSF procurement program are shared by the
other international F-35 JSF partners. The apprehension over the cost and/or delivery schedules are well
founded when the pertinent details of the cost and schedule performance from the Lockheed Martin
development program are continuing to be identified by the US government and analyzed by many of the
program stakeholders (including partner nations and the industry participants).
The summary of the international partner procurement status is listed in Appendix 2.
5.3.1 Norway
Norway will purchase 4 initial JSF for 4.9 billion Norwegian kroner ($844M), however this budget
includes funding to continue with the Joint Strike Missile indigenously developed by Kongsberg Defence
Systems (Wall, 2011). The initial plan by the Norwegian government to purchase 48 F-35 aircraft was
approved in May 2009 at a cost of $3.4B with unit cost of $70.8M each and this has been observed by
aerospace industry experts as unrealistically low (Sweetman, Norway's Parliament Endorses JSF, But....,
2009) Additional the US Air Force document also shows $90.3M per aircraft was estimated for FY2013
(US Air Force, 2008).
The firm-fixed pricing negotiation is not expected to occur until 2014.
5.3.2 Japan
While not a participant of the initial and subsequent JSF development team, Japan announced in
December 2011 that it has selected the F-35 JSF over Boeing’s F/A-18 Super Hornet and Eurofighter
Typhoon. Japan will procure 42 F-35 JSF at a cost of $8B, with the unit cost of each jet to be $114M,
and the first aircraft is to be delivered in 2016 (Kallender-Umezu, 2011).
Page 21 of 76
Since Japan did not participate in the JSF development program, its’ cost of purchase will be channeled
through the Foreign Military Sales program with the US government, Lockheed has offered a potential
production line final assembly and checkout (FACO) facility to be constructed in Japan, which may
increase the per aircraft cost as a result due to additional investment by the Japanese Government
(Kallender-Umezu, 2011).
The recent development of a F-35 price increase has already resulted in concerns being expressed in early
2012 by Japan’s chief cabinet secretary Osamu Fujimura (only two months after the initial selection
announcement in December 2011 was made). The Japanese Ministry of Defence will take the position
that if prices rises “without valid reasons, there is a possibility that a procurement could be cancelled”
(Waldron, 2012, p. 1).
5.3.3 Denmark
The Danish Defence Command announced in 2010 that it is no longer considering the JSF as Denmark’s
only candidate for the Danish fighter aircraft replacement program, and will begin evaluating Boeing’s
F/AF-18 Super Hornet and the Eurofighter as potential alternate candidates. This was as a result of
concerns over the delayed delivery date from 2012 to 2016 and with the per-aircraft cost increase by
100% from $50M to nearly $100M (Pugliese, 2010). The decision for the Danish Fighter Replacement
program has now been postponed to 2015 as a result.
In the meantime, an industry organization FAD (Danish Defence & Security Industries Association) with
interests in supporting the selection process by DALO (Defence Acquisition and Logistics Organization),
was formed in November 2011 to continue working with all present and future potential candidates for
the Danish fighter replacement program (FAD, 2012). The benefit to the Danish aerospace industry will
be substantial regardless which aircraft type is chosen at the end of the selection process.
It is worth noting that while Denmark is also an initial Tier III participant of the JSF development
program similar to Canada, Denmark has not confined itself to selecting the F-35 JSF despite having
Page 22 of 76
made a $135M investment in the JSF international partnership program. The Danish government has in
fact taken tangible actions to demonstrate its resolve to select an alternate aircraft other than the F-35 JSF
in order to ensure responsible defense expenditures. This is despite having already contributed significant
funding towards the JSF program development cost.
5.3.4 United Kingdom
As the sole Tier I partner of the JSF program, the United Kingdom (UK) has contributed $2.5B to the JSF
development program, and is the second largest customer for the F-35 JSF aircraft with initial plans to
order 150 of the F-35 JSF aircraft for $19B. However this plan is now under review and reconsideration
and the UK is likely to reduce the aircraft numbers due to the increasing cost and budget limitations faced
by the UK Ministry of Defence (MoD) (JSF UK Industry Team, 2012).
Although the UK has provided the largest investment contribution of all international JSF partners, it has
not precluded itself from the impact of cost increases for the F-35 aircraft. The original estimated cost of
£37M ($58.6M) had escalated to £62M ($98M) in 2010, prompting suggestions of, albeit unlikely,
reduction of the order from 140 aircraft down to 70 (Norton-Taylor, 2010). Another suggested action to
reduce the UK JSF program cost is to shift the F-35B short take-off vertical landing (STOVL) variant
originally planned for the UK aircraft carriers to the F-35C conventional aircraft carrier variant
(Schwellenbach, 2010).
The UK originally planned to purchase the F-35A for the Royal Air Force and F-35B for the Royal Navy
to be deployed onboard the two new Queen Elizabeth Class aircraft carriers under construction since
2009. However, the aircraft carrier requirement has forced the UK MoD to face a unique issue which the
other international customers will not have to address (except for Italy who also plans to procure F-35B
variant), in particular the two UK aircraft carriers were initially designed to support only the STOVL
(short take-off vertical landing) F-35B variant and cannot accommodate any conventional aircraft
(Murphy, 2012). However, the continued JSF cost overrun had forced the UK MoD to table the
Page 23 of 76
possibility in its 2010 Strategic Defense & Security Review to change the UK’s purchase of STOVL F-
35B to the conventional F-35C carrier based variant for the Royal Navy.
Since the US Marine Corp, Italian Navy, and Royal Navy are currently the only known customers of the
F-35B STOVL aircraft, a decision change by the UK MoD to shift its requirement from F-35B to F-35C
will reduce the total F-35B production quantity, this will undoubtedly impact the F-35B production plan
with unavoidable cost increases for the F-35B aircraft. This may then propagate the reduction of quantity
the US Marine Corp F-35B had intended to procure in order to align with allocated budgets made
available by the Pentagon.
However, while the change from F-35B to F-35C will save approximately $10M per aircraft, further
assessment has recently identified that this change will require the aircraft carrier design to undergo major
revisions to install the catapult and arrester cable systems to launch and recover the F-35C. The total life
cycle costs for F-35C (with lower initial unit cost and modification to the aircraft carriers) have now been
calculated to be greater than the cost of maintaining the existing aircraft carrier design and purchasing the
F-35B at a higher initial unit cost. As a result of this assessment, the potential now exists that UK MoD
will soon reverse its decision and shift its procurement for the Royal Navy back to the F-35B STOVL
variant (Wall, 2012). A second major decision by the UK MoD to reduce defense expenditure is to
reduce the two aircraft carriers down to one, with a corresponding reduction of the F-35B variant required
(Jones, 2012).
Given the magnitude of the $2.5B development investment and as the second highest aircraft quantity
customer after the US government, and coupled with the complexity of deploying two variants of the F-
35 JSF for the Royal Air Force and Royal Navy, suffice it to say the UK’s procurement program has
become the most complex of the F-35 JSF international customers.
Predictably UK has now deferred its decision on the quantity of F-35 JSF purchase to 2015, although a
firm order for three test and evaluation aircraft has been placed with Lockheed Martin at $632M. The
Page 24 of 76
Queen Elizabeth Class aircraft carrier is reported to contain 40 fighter aircraft (Naval-Technology, 2011)
and may be used as an initial point of reference to estimate the UK’s likely purchase quantity for the F-
35B JSF variant.
5.3.5 Australia
The Royal Australian Air Force (RAAF) had planned to acquire 100 F-35A JSF aircraft for US$17B with
a purchase order placed for 14 initial aircraft (Royal Australian Air Force, 2012). Amongst the potential
international F-35 JSF customers Australia is the only country which has not only accurately predicted the
risk of delayed F-35 JSF delivery, but Australia also had the foresight to have proactively implemented an
interim solution for the RAAF by placing an order for AUD$3B (or US$2.4B based on 2002 exchange
rate) with Boeing in 2007 to purchase 24 Boeing F/A-18 E/F Super Hornets to fill the strategic gap when
the RAAF F-111 bombers were retired ahead of planned schedule (Defense Industry Daily, 2012).
The 24 Super Hornet procurement program has been completed with all aircraft delivered to the RAAF by
late 2011. This has not only bridged the gap the aircraft were intended to fill, it appears they will now
also serve as a “buffer” to cushion some of the impact the delayed F-35 JSF delivery schedule may have
on RAAF’s future planning.
5.3.6 Italy
Italy is one of two Tier II F-35 JSF international team members alongside the Netherlands, and has
invested $1B to date in the program to assist with significant related activities within Italy, including
construction of a 20-storey building with a 646,000 square-foot final assembly and check-out (FACO)
facility at Cameri Air Force Base in northern Italy to perform final assemblies of aircraft for Italy, the
Netherlands, and Norway. This program is expected to involve 20 Italian companies throughout its life
cycle (Peruzzi, 2012).
The original Italian plan was to procure total of 131 aircraft split between 69 F-35A and 62 F-35B
variants. However the defense procurement spending cut in 2012 is anticipated to result in reduction of
Page 25 of 76
the quantity by approximately 30 units of the F-35B variant, and to extend the balance of procurement
over longer periods of time (Reuters, 2012).
In the mean time Italy announced in that Feb 2012 it has ordered its first three F-35A at $80M per unit
price, and that the STOVL F-35B variant will be operated by both the Italian Air Force and the two
aircraft carriers of the Italian Navy (Cenciottis, 2012)
5.3.7 Turkey
As a Tier III international partner of the F-35 JSF program, Turkey has planned to procure 100 F-35 JSF
at $16B program cost, however Turkish government was unsatisfied over US government’s refusal to
share the software source code which controls and navigates the advanced F-35 JSF (UPI, 2011). Despite
the disagreement with access to software source code, an initial purchase order for two aircraft for has
been placed with Lockheed Martin to provide in-country logistics training, although the original plan had
been to purchase four aircraft for this purpose (Munoz, 2012).
5.3.8 Israel
Through the foreign military sales (FMS) funding program, Israel is now expected to procure 75
F-35A JSF aircraft in total, with an initial purchase of 20 (Katz, 2010).
Similar to several international customers, Israel is negotiating with the US government to gain
access to the F-35A software code in order to integrate indigenously designed avionics and
weapon systems into the aircraft.
Page 26 of 76
5.4 Canada’s procurement process
5.4.1 The sole-source approach
The F-35 JSF program will not only be the most expensive military procurement program for
Canada; it is also expected to be the most expensive weapon procurement program in history
globally, based on the total estimated acquisition cost of all international customers combined.
From the perspective of global economic strategy, multiple international customers combining
resources and jointly collaborating in the JSF program fits the “trading industry
internationalization model” integral to the program’s aerospace/military nature (Grant,
2008).The technology developed by Lockheed Martin is exported from a single location, the US,
to exploit international markets and capitalize on the efficiency benefit; Lockheed Martin then
collects the combined financial resources of the multinational participants in order to continue
carrying out JSF development.
The strategy to facilitate international collaborative involvement in the JSF program required the
participating partner countries to sign additional MOUs in 2006 committing them to additional
funding in exchange for preferred benefits from the JSF program. Canada agreed to provide
additional funding along with other countries. While a commitment to purchase aircraft was still
not required, in Section 7.3, the 2006 MOU does indicate that companies in countries actually
buying the aircraft will, in fact, have preferential status, subject to providing “best value” (Hicks,
2010). Thus, Lockheed Martin’s contract award process will provide contracts only to the most
competitive companies in the industry for the value-added benefit of the JSF program, rather
than employing the typical “patronage” reward arrangement.
Page 27 of 76
The Canadian government agreed to participate in the JSF program through several phases
beginning in 1997, and continues to participate, intending to amalgamate Canadian funding with
that of other interested countries to provide greater financial resources to support the
development program. This is an appropriate and prudent approach for maximizing the economic
power of the participating nations.
However, in a partnership program such as the JSF, the desire to maintain this relationship in
order to protect the industry business interests within each country can result in persistent
industry and/or even political pressure to continue with the program, even when experts have
legitimate concerns and identify them for the decision-makers. The Canadian government’s
ongoing sole-source procurement approach for the F-35 JSF has been criticized for its inability to
exert necessary pressure on Lockheed Martin concerning cost controls and delivery commitment.
Nevertheless, the Aerospace Industries Association of Canada (AIAC), representing around 90
of the country’s most significant aerospace companies, continues to support the selection of the
F-35 JSF for the RCAF, since the program could theoretically bring $12B in economic benefits
to companies throughout Canada, as the AIAC identified in an open letter on their web site
(AIAC, 2010).
This level of industry support cannot be overlooked from a political angle, when industry
lobbyists can raise legislative support or gain institutional approval to reach an objective, and in
doing so reinforce established policy or defeat proposed policy shifts (Baker). Observing the
continued industry and government support to sole-source the F-35 JSF contract with Lockheed
Martin, despite recent validated concerns about cost increases and delayed delivery, a pattern of
government and industry supporting each other’s objectives emerges, and it is clear these actions
are taken not necessarily for the right reasons, when all factors are considered.
Page 28 of 76
5.4.2 Requirement definition
In order to successfully complete a program, a company’s objective is to meet the three
constraints of quality, schedule, and budget in a balanced manner. However, some scholars argue
that the fourth constraint of a successful program is the dimension of meeting the program’s
strategy objectives. The “balanced scorecard” framework is used to include strategic alignment
as the fourth constraint in the modified constrained model in Figure 1 (Norrie & Walker, 2004).
Figure 1. A Quad Constrained Project Management Model (Norrie & Walker, 2004)
The primary strategic objective for Canada’s next generation fighter replacement program is to
select the appropriate aircraft for the RCAF’s strategic obligations in future domestic and
international military operations; this strategic objective will have to be balanced with the other
traditional three constraints of budget, quality, and schedule.
Once all four constraints have been clearly defined, the planning process can proceed to
determine the appropriate approach to achieve the objectives.
Page 29 of 76
By reviewing the available Canadian F-35 JSF program information to date, it is evident that
while the Canadian government began participating in the JSF program in 1997, a clear
definition of the Canadian requirements has not yet been released to the public. This has made
the definition requirements for the CF-18 replacement program difficult to qualify and quantify.
Some of the questions raised after the JSF selection decision was announced by the Canadian
government include
Does Canada require the stealth capability of the JSF?
Historically, the American military has carried out “first-day” strike activities in recent
campaigns such as the Gulf Wars and other international conflicts. This approach is
taken to suppress and destroy most of the opponents’ electronic detection capabilities.
Allied nations such as Canada then provide follow-on air superiority coverage, with
minimal risk from other electronic threats that the stealth capability can be of benefit.
Is the JSF’s claimed top speed of Mach 1.6 sufficient?
The roles of tactical air power to be served by the next RCAF fighter jet will include
domestic combat air patrol for potential terrorist hijack scenarios, sovereignty patrol in
the vast Northern Arctic areas of Canada, and participation in allied combat air patrol
during international military campaigns, all of which will benefit from higher top speed
performance. The JSF has lagged behind other fighter aircraft the critics have suggested
Canada consider in lieu of the F-35 JSF, such as the F-18 E/F (Mach 1.8+) and F-15
(Mach 2+).
Is the single engine JSF safe for pilots, given the vast, unpopulated Arctic area which
the RCAF routinely patrols?
Page 30 of 76
While the Chief of Air Staff Lieutenant-General André Deschamps assured the public
that the safety performance of the new generation single engine and twin-engine fighters
is similar (Deschamps, 2010), it remains to be seen if the single engine JSF can provide
adequate safety and reliability. The RCAF had similar concerns when it selected the twin-
engine CF-18 rather than the single-engine F-16 in the previous fighter selection program
of the early 1980s. This concern has proven valid, since a number of CF-18 pilots have
been able to land safely rather than being forced to eject after one of their two engines
suffered in-flight failures.
5.5 Large-scale military procurement
After several decades of declining defense funding which has resulted in a reduction of Canadian
military capabilities, the current Conservative government has begun the rebuilding process as
laid out in their Canada First Defence Strategy (CFDS) to enable the Canadian Forces to meet
existing and future roles, challenges, and threats.
Since 2007, the Canadian government has made positive leadership decisions to fast-track
several large-scale defense procurement programs to support Canadian Forces personnel during
international deployments into regions with military conflict. The RCAF components of the fast-
tracked programs include
• CDN$3.4B for four CC-177 Globemasters; strategic airlift program (Defense Industry
Daily, 2008)
• CDN$2.1B for seventeen CC-130J Super Hercules; tactical airlift program (Royal
Canadian Air Force, 2010)
Page 31 of 76
• CDN$4.9B for fifteen CH-147F Chinook; medium-lift helicopters program (DeMille &
Priestley, 2010)
The effort put forth by Canadian government personnel to successfully complete all three
procurement programs in support of the CFDS initiatives should be applauded; the inclusion of
all three types of aircraft greatly assisted the Canadian Forces’ ability to conduct its operational
activities in a safe and effective manner during recent military operations in Afghanistan and
Libya, and these capabilities have also provided humanitarian relief in operations elsewhere
around the world.
5.5.1 Past Experiences
It has been a long-standing pattern since the First World War that Canada has not been
successful in the procurement from or development of an indigenous defense industry. There
have been some rare exceptions, but the bulk of the major military development programs in
Canada were not deemed fully successful due to budgets, schedules, and at times political
interference.
One notable example is that of the CF-105 Avro Arrow long-range interceptor program initiated
in the 1950s to address the threat of a Soviet bomber penetrating Canada’s Northern Arctic
airspace during the Cold War. While the Avro project has great sentimental value from a
historical perspective, it ran over budget and was delayed due to necessary redesigns of the
airframe and weapons control systems. The Liberal government in power at the time continued
to fund the program despite criticism from the Chief of the General Staff, Lieutenant-General
Guy Simonds, who argued that the project was consuming too much of the defense budget and
that the government was ignoring other developing strategic trends, such as ground-to-air
Page 32 of 76
missiles that could serve the purpose the Avro arrow was built for at a much reduced cost
(Plamondon, 2008).
Another prime example of failed Canadian military procurement was the initial Sea King
replacement program. In July 1992, the Conservative government led by Brian Mulroney
announced that they had awarded a contract to EHI (EH Industries) for fifty EH-101 helicopters
to replace the aging Sea King fleet that had been in service since the 1960s. The total cost of the
program was $4.4B (CAD), with significant benefit for Canadian defense industry participants.
While this was a major expenditure, the failing reliability of the Sea King helicopters, the safety
of their aircrews, and the expected expense to upgrade and maintain the aging fleet supported the
logical justification to proceed with the EH-101 procurement program (Plamondon, 2010).
5.5.2 Outcomes
The CF-105 Avro Arrow project continued to consume too much of the Canadian defense budget
under the Liberal government, until a Conservative government led by John Diefenbaker was
elected into office. The Soviets launched Sputnik I into orbit in 1957, the same day the first
prototype Avro Arrow rolled out of its assembly plant in Milton, Ontario. The significance of the
intercontinental ballistic missile age became clear with the launch of the Soviet satellite, the
purpose and benefit of the Avro Arrow was called into question, and the Avro Arrow project was
terminated in 1959 by the Diefenbaker government, thus closing a chapter on one of the most
well-known Canadian military development/procurement programs (Plamondon, 2008).
The Sea King replacement program initiated in the early 1990s met a similar fate in 1993, when
the newly elected Liberal government terminated the procurement contract for the EH-101s. This
act was primarily justified by the Liberal political platform and their election campaign promise
Page 33 of 76
to reduce government spending. Winning the election meant that new Prime Minister Jean
Chrétien had to fulfill his campaign promise, regardless of the direct financial loss of
CDN$478M in termination penalties, and significant losses in Canadian defense industry
investment and jobs (Plamondon, 2010).
5.5.3 Lessons learned
On the one hand, the CF-105 Avro Arrow program demonstrated a case in point for the
importance to ensure the procurement decision is supported by appropriate and defendable
strategic requirements, because without these the procurement is unlikely to gain continued
support or remain on track, and is therefore at risk of being cancelled.
On the other, the EH-101 Sea King helicopter replacement program cancelled in 1993 was the
victim of political influence. The Opposition Party used the program’s expenditures as political
leverage during the election campaign. Its cancellation resulted in a significant financial loss due
to the termination penalty and a major delay in acquiring badly needed helicopters that is only
now being met with the anticipated arrival of the first deliverable CH-148 Cyclone to Canada.
This is happening nearly 20 years after the original procurement contract was awarded and then
cancelled, primarily as a result of political influence.
These two examples demonstrate the importance of stakeholder theory in strategic management,
particularly the five steps of stakeholder analysis (Carpenter, Sanders, & Harling, 2012):
1. Identify the value chain
2. Identify the stakeholders
3. Determine the stakeholders’ expectations
4. Determine stakeholders’ power and influence over decisions
Page 34 of 76
5. Determine which stakeholders will be satisfied and how
The Avro Arrow program cancellation can be attributed to three factors:
- Loss of value-chain: the Avro Arrow no longer served its purpose when unmanned
intercontinental ballistic missile technology became a viable alternative to manned high-
speed long-range tactical bombers.
- As a stakeholder, the United States government provided American-made aircraft as a
more economical option to Canada and protected its own aerospace industry at the
expense of the Canadian one.
- The Canadian aerospace industry became a secondary stakeholder.
The cancellation of the EH-101 Sea King replacement program can be attributed to three factors:
- Fulfilling political campaign promises became the overriding factor in the value chain
once the Liberal government was elected.
- The political stakeholders satisfied their needs at the expense of replacing the aging
helicopter fleet
- Timing of the procurement during economic uncertainty.
Both program cancellations had a notable negative impact on the Canadian aerospace industry.
However, the stakeholders with the most influence succeeded in implementing their decisions
over the rest.
6 Schedule and Cost Factors
The mounting development-related delays and cost escalation have resulted in significant
concerns expressed by not only the US government (the F-35 JSF’s prime customer) but also a
Page 35 of 76
contingent of other international customers, including Canada. Lockheed Martin’s development
problems and cost increases for the F-35 program were identified by all potential international
customers, and they have raised serious concerns that the result will be an unavoidable reduction
of procurement quantities, increasing the unit cost and delaying the aircraft delivery schedule
(Fulghum, Warwick, Wall, & Ben-David, 2011).
6.1 Lockheed Martin development program status
While the F-35 JSF program has endured critical delays in recent years, it has also achieved
several major milestones in the 12 months preceding this applied project. Achieving every one
of the many program milestones contributes to the successful continuation of the overall
program, but there are some key milestones that have great significance, including but not
limited to (US Government/Dep of Defense, 2012)
- 2,500 flight test hours
- First STOVL testing at sea
- First in-flight fuel transfer
- Completion of F-35B initial ship suitability testing
- First catapult launch of F-35C
- First flight with external weapon payload
- Reached highest altitude to date of 43,500 feet
- First night flight operation
- F-35B program probation lifted one year ahead of schedule
- Receiving Air Force-issued flight release to begin initial operation of F-35As at Eglin Air
Force Base, Florida
Page 36 of 76
However, as can be expected with any complex technology development programs, there have
also been many delays due to technical issues found during the F-35 JSF flight testing phase,
including but not limited to
- A defective wing structure beam, which reduces the operational life to less than one-sixth
of the design target (Aero News Network, 2011)
- Underrated design for the power supply of electro-hydrostatic actuators that caused a
near-accident early on in the flight testing (Boeder, 2007)
- F-35C power generator mistakenly designed to give only 65% of the required electric
output (Boeder, 2007)
- Gearbox of the F135 engine for the JSF requires redesign to accommodate increased
power from the generator (Boeder, 2007)
- Fuel tank system to prevent explosion from damaged fuel tank failed to insert the fuel
tank spaces throughout combat flight envelopes evaluated (Department of Defense, 2012)
- Handling characteristics will require additional evaluation and changes in flight control
software and potential airframe modification (Director of Operational Test and
Evaluation, 2012)
- F-35C deficiencies, such as a tail hook that is unable to engage the arrester cable and
missing components that are critical to catapult launch for aircraft carrier operations
(Director of Operational Test and Evaluation, 2012)
- F-35B aircraft vertical lift components require redesign to accommodate higher than
expected operating temperature (Gilmore, 2011)
The recently released FY2011 report by the US DOD Director of Testing and Evaluation
expressed concern with the flight testing progress, and the growing use of concurrency testing by
Page 37 of 76
Lockheed Martin and the JSF Program Office in the mission systems flight test plan. The report
stated concurrency testing “creates difficulty of managing multiple configurations on test and
operational flight lines to assure use of appropriate software, increasing rework of software, and
the potential for greater than expected regression flight tests are significant challenges to the
program.” (Director of Operational Test and Evaluation, 2012, p. 34)
Furthermore, the JSF Operational Test Team has determined that the F-35 program is not on
track to meet operational effectiveness or suitability requirements, specifically in the areas of
human system integration with helmet-mounted display and night vision capability, aircraft
handling, as well as the maneuvering performance for F-35A’s combat radius and F-35C’s
acceleration. (Director of Operational Test and Evaluation, 2012)
The combined problems of test delays, an aggressive testing philosophy, and tangible technical
difficulties will create significant challenges for the JSF program to accelerate and meet its
original program plan for flight testing, initial delivery, and international customer delivery.
6.2 Program schedule performance
The ongoing technical issues identified during flight testing has resulted in the restructuring of
the system development and demonstration (SDD) plans, resulting in a 16-month extension of
the SDD phase for the F-35 JSF program to (Gilmore, 2011)
- accommodate more flight test sorties
- address STOVL F-35B flight performance difference and complexity
- provide the time and effort (previously underestimated) required to develop and integrate
the mission system software
Page 38 of 76
In March 2009, the GAO identified in a report to the US Congressional Committees of its
concerns that Lockheed Martin and the JSF Program Office’s use of substantial concurrent and
overlapping development, test, and production activities is flawed. This caution was not heeded
by the DOD, which appears to be a cause of additional risk to cost and schedule increases for the
program. The 2009 report estimated a 3-year schedule extension would be required and delay
the completion of development until October 2016 (US Government Accountability Office,
2009).
Based on the Block 1, 2, and 3 developmental testing which makes up the SDD phase, the chart
in Figure 2 summarizes the progression of the F-35 JSF program SDD schedule from 2003 to
2012 with briefing information provided by the US government, including the JSF top-level
2008 SDD program schedule (Davis, 2008) originally presented in September 2008 by USAF
Major General Charles R. Davis, then the F-35 JSF Program Executive Officer. The schedule in
2008 as compared to the most recently available data in 2011 has already been delayed between
3 to 3.5 years for Block 2 and Block 3 SDD development testing phases. See Appendix 1 for
detailed data.
Figure
The trend of schedule delays is expected to
the previous phases of the program
setbacks in the future have been
In reviewing the documented history of the F
identified by the GAO in several reports since
performed well. Using the framework based on five operations performance objectives
Chambers, & Johnson, 2010)
program will have all five objectives balanced
one or more of the objectives
Figure 2. F-35 JSF SDD Completion Forecast
is expected to continue until the technical development
previous phases of the program have been successfully addressed, and provision for
have been mitigated with contingency plans.
In reviewing the documented history of the F-35 JSF development program and the issues
in several reports since 2005, it is evident that the JSF
Using the framework based on five operations performance objectives
of Quality, Speed, Dependability, Flexibility, and Cost, an ideal
program will have all five objectives balanced with one another. However
one or more of the objectives to gain favorable precedence over those that remain
Page 39 of 76
technical development setbacks in
provision for potential
35 JSF development program and the issues
SF program has not
Using the framework based on five operations performance objectives (Slack,
of Quality, Speed, Dependability, Flexibility, and Cost, an ideal
owever, it is not unusual for
remain, and quite
often this means some objectives are compromised when
higher visibility, priority, and additional focus in the program
given less priority and allowed
For the JSF program, it is apparent
emphasis on the quality, flexibility, and dependability objectives
modified set of performance objectives
Figure 3.
The values assigned for the performance parameters in
- Quality : The performance validation
identifying and integrating additional test points into the test program despite the
objectives are compromised when others considered
and additional focus in the program. As a result, certain
ed to degrade as they are “sacrificed” within the program.
is apparent that cost and schedule objectives have given way to
the quality, flexibility, and dependability objectives as shown in
modified set of performance objectives:
. F-35 JSF Program Performance Objective
The values assigned for the performance parameters in Figure 3 are based on the assessment
: The performance validation process and test results have be
identifying and integrating additional test points into the test program despite the
Page 40 of 76
others considered more critical capture
As a result, certain objectives are
within the program.
given way to more
as shown in Figure 3, with a
JSF Program Performance Objectives
are based on the assessment of
process and test results have been highly effective,
identifying and integrating additional test points into the test program despite the
Page 41 of 76
daunting pressure from the program schedule and cost correction process (Gilmore,
2011).
- Safety: The test program has not compromised safety practice or performance in
exchange for a lower cost or shorter schedule, no major mishap has occurred to date, with
only minor incidents throughout the flight test (not uncommon for an advanced aircraft
flight testing program), and has not resulted in any loss of aircraft or personnel
injury/death. This safety record is commendable, given that over 1,700 test flights have
been conducted since December 2006 (Lockheed Martin, 2012).
- Reliability: The flight test aircraft fleet has required significant maintenance, which
contributed toward fly rates that were lower than planned (US Government
Accountability Office, 2011).
- Cost: The program cost has increased significantly and required multiple reviews to gain
additional funding, and restructuring the procurement plan may result in a reduction in
procurement quantities (Fulghum, Warwick, Wall, & Ben-David, 2011).
- Schedule: An estimated four to five years delay has been accumulated since the
beginning of the F-35 JSF program. This has caused doubts and concerns for potential
international customers, so that some have reconsidered the F-35 JSF as their
replacement fighter choice. In fact, Australia has decided to purchase 24 of Boeing F/A-
18 E/F Super Hornets as interim measure to address the delay of the F-35 JSF delivery
(Defense Industry Daily, 2012) while other nations remain in the F-35 JSF program for
the time being.
Page 42 of 76
6.2.1 Current delivery schedule
As a result of US Congressional reviews of the F-35 JSF program, examining in particular the
alarming cost increases and schedule delays, the F-35 JSF Program Office and Lockheed Martin
committed in mid-2011 to produce a revised integrated master schedule (IMS) by early 2012.
This task has not been completed by the end of 2012’s first quarter, when the research for this
Applied Project was being conducted, therefore the following information has been compiled
based on the best available data at the time, including the FY11 Annual Report by the US
Government Director of Operational Test and Evaluation, which included a detailed summary of
the FY11 activities related to the JSF program.
As a result of the Technical Baseline Review done in 2010 on the system development and
demonstration (SDD) phase, the SDD completion schedule was delayed by 13 months, and the
full-rate production moved to November 2015 (Gertler, 2012). With anticipated aircraft delivery
as shown in Appendix 4, the following schedule milestones have been adjusted and extended
accordingly:
- Block 2 mission systems capabilities to early 2015 (was mid-2012)
- Block 3 mission systems capabilities to spring 2017 (was mid-2013)
To put this into perspective, Block 2 is the second of three capability phases in the F-35 JSF
program. Block 3 is the planned completion of the F-35 JSF test flight to measure full aircraft
capability as well as hardware and software configuration that will become the operational
baseline.
Ideally, the production of the deliverable F-35 JSF aircraft fleet will not commence until all three
SDD phases are complete and all of the issues identified during the flight test trials have been
Page 43 of 76
resolved. However, realistically this approach would require a significant extension to the
program schedule, and delaying aircraft delivery again in an already much-delayed program;
therefore, a low rate initial production (LRIP) approach has been adopted to produce small
quantity of aircraft in parallel with the SDD flight test program to facilitate initial transition
activities such as pilot and maintenance training. This approach is taken with the understanding
that while there is an advantage to initiating the production process, the disadvantage is that
some of these LRIP aircraft may require various updates as issues are identified and resolved
during the ongoing SDD flight test program. These updates can potentially be costly, even
though the LRIP is not an uncommon practice in the aerospace industry.
As a result of this approach, the USAF has obtained approval from the Pentagon to initiate F-35
JSF flight operations at Eglin Air Force Base in March 2012 (Majumdar, 2012), a historical
milestone for the F-35 JSF program that was only possible due to the implementation of the
LRIP.
With the Pentagon’s reduction of its initial purchase and the restructure/replanting of the
program, full production of the F-35 JSF is now expected to commence in 2015 (Gertler, 2012).
6.2.2 Forecasted delivery for Canada
The F-35B STOVL variant is expected to undergo another 60 months of flight science test flights
until 2017, but this should not have a critical impact on Canadian procurement since only the F-
35A conventional take-off variant aircraft is expected to be procured. Similarly, additional
issues identified during flight tests for the F-35C aircraft carrier-based variant are not factored
into the delivery schedule analysis for Canadian procurement of the F-35A.
Page 44 of 76
While the initial forecast for aircraft delivery of Canada’s F-35 JSF was previously estimated and
planned for 2016 (National Defence and the Canadian Forces, 2012), this date appears to be
increasingly unrealistic, given the delays of the flight test program. The full-rate production
delay to November 2015 will result in most aircraft initially produced being delivered to the US
military rather than international customers. Only a few of the early production aircraft will be
delivered to international customers for initial training purposes, while the remaining delivery
will be negotiated to accommodate Lockheed Martin’s JSF production schedule and the
Pentagon’s delivery requirements.
Furthermore, it is understood that the first batch of full-rate production aircraft will likely cost
more than later batches; therefore, the Canadian DND can lower program costs by delaying the
delivery of the aircraft until after the original 2016 deadline. The Canadian government appears
to be considering this option, indicating that it has some flexibility to extend the operational life
of the current CF-18 Hornet fleet, such that they can delay the F-35 JSF delivery to between
2017 and 2023 (Payton, 2012) rather than the originally planned 2016 to 2020 replacement
period.
6.2.3 Capability concerns
Two capability related items must be addressed during the Canadian procurement of the F-35
JSF: these are in-flight refueling capability and drag chute capability (JSF NIEUWS, 2011).
The RCAF in-flight refueling capability with its current fleet of CC-150 and CC-130 tankers is
based on a flexible drogue chute which mates to an extended probe from the receiving aircraft
such as that used by the CF-18 Hornet. However, this refueling system is not compatible with
Page 45 of 76
the F-35A variant of the JSF Canada will be purchasing, since it has receptacles requiring a rigid
boom refueling system. Therefore, two options exist to address this problem:
- Refit the Canadian F-35A aircraft with the in-flight refueling system from the F-35B/C
variant, which is compatible with the Canadian Forces tankers
- Update existing tankers or purchase new tankers with a compatible in-flight refueling
system.
The drag chute requirement is still under assessment to address potential landing difficulties
associated with shorter runways in Northern Canadian airfields; the drag chute at the tail of the
aircraft will be deployed upon touchdown to assist in decelerating on slick runways, a problem
during the winter months.
Both of these issues will further impact the schedule and cost of the Canadian procurement
program, since these are unique requirements not yet shared by other international customers of
the F-35A variant.
6.2.4 Implication to RCAF planning
The CF-18 fleet currently operated by the RCAF is expected to remain in service until 2020,
when most of the airframes will reach the end of their design life cycles. The current transition
schedule from CF-18 to F-35 had been planned based on the delivery of the first aircraft in 2016
to allow adequate phase-in transition within the Canadian Forces infrastructure (Deschamps,
2010). The planned 2016 initial delivery schedule of the RCAF F-35 would allow for personnel
training, supply chain provision, support equipment installation, and implementation of overall
infrastructure in preparation for the F-35 phase-in process.
Page 46 of 76
However, the ongoing development delays of the F-35 program in the US have the potential to
jeopardize the 2016 target date for the initial aircraft delivery to Canada. If this delay does occur
as expected, it will force the RCAF to continue operating its current CF-18 aircraft fleet longer
than initially planned. Delaying the retirement of the CF-18 fleet will likely affect Canada’s
ability to carry out military roles, and operating costs will have to increase to support the aging
CF-18 fleet. This is a legitimate concern which has been clearly demonstrated in the past by the
nearly 20-year delay of the Maritime Helicopter Replacement Program for the Sea King
helicopter fleet.
6.3 Cost structure
In conjunction with the schedule delays, F-35 JSF critics have also focused on program costs, as
the estimated price of the aircraft continues to increase.
The current acquisition price for Canada has been estimated at approximately $150M per aircraft
in the Parliamentary Budget Officer’s report dated March 10, 2011 (Weltman & Yalkin, 2011),
while in late 2010, the RCAF Chief of Air Staff (CAS) Lieutenant-General André Deschamps
stated that the procurement price would only be $70M for each aircraft based on the expected
production and delivery timeframes (Deschamps, 2010). Clearly, there is a significant
discrepancy in the financial figures presented.
A counter-analysis was produced by the DND on March 18, 2011 in response to the PBO report,
citing inconsistencies and incorrect assumptions (Kaluzny, 2011) to discount the $148.5M per
aircraft cost estimate. The DND’s response made two notable observations:
- The PBO report overestimated the aircraft unit cost by $19.9M, inferring the aircraft cost
was still $128M per unit
Page 47 of 76
- according to the CAS, “Canada could anticipate to pay under $90M per aircraft,”
inferring each F-35 JSF aircraft is unlikely to cost much less than approximately $90M,
which is still $20M, or 28.7% higher than the figure presented by the RCAF CAS in
2010.
To address DND’s response, the PBO then provided its own counter-counter analysis on March
23, 2011 clarified the rationales used in its original report, identified inconsistencies within
DND’s counter-response, and referenced a US GAO report dated March 15, 2011 (United States
Government Accountability Office, 2011) to support estimates compiled by the PBO.
Figure 4. Canadian F-35 Price Estimation (Weltman & Yalkin, 2011)
Page 48 of 76
The average procurement cost chart in Figure 4 was compiled from the March 15, 2011 United
States Government Accountability Office report on the F-35 JSF restructuring process, indicating
not only the extent of the unit cost increase but also the strong likelihood that the unit cost of the
F-35 JSF may double in value. The current effort to accelerate the LRIP while the SDD flight
testing phase is ongoing creates the potential for a costly retrofit process that would be required
for early production aircraft in order to rectify issues not yet identified or resolved while the
LRIP aircraft were being built (US Government Accountability Office, 2009).
Given the level of uncertainty and the numerous variables contributing to the aircraft unit cost
calculation, and based on the best information available currently, it would be prudent and
reasonable to suggest that the F-35 JSF aircraft unit cost for RCAF procurement will likely to
range from the
- “Suggested minimum” of $70M by RCAF CAS
- To the “expected minimum” of $90M by DND
- The “likely maximum” of $128M by DND
- Or up to the “potential maximum” of $150M by PBO
The DND and its officials recognized the lack of a single, authoritative unit cost for the F-35 JSF
in recent months (Berthiaume, 2012), and have provided a range of publicly presented and
speculated cost figures as a result.
7 Economic Benefit
Dan Middlemiss, one of the few authors who writes about Canadian military procurement argued
that defense procurement is a vital component of defense policy. “It is what puts the ‘arms’ into
Page 49 of 76
the armed forces and because of the many (sometimes very large) contracts and jobs involved, it
is also ‘big business’ in Canada” (Plamondon, 2008, p. 17).
Industry Canada’s Industrial and Regional Benefit (IRB) program ensures Canadian industry will
benefit from a major government procurement expenditure to a foreign supplier such as the F-35
JSF program, expected to cost a minimum of $9B. However, Industry Minister Tony Clement
“conceded the current arrangement with Lockheed Martin provides no such (IRB) guarantees
(Brewster, 2010, p. 1). Therefore, the Canadian government has so far not followed the
traditional IRB policy with Lockheed Martin for the F-35 JSF program. The reasons for this
approach will be discussed in the following sections.
7.1 Industrial Regional Benefit (IRB) program
Historically, it has been the prerogative of the Canadian government to require foreign
companies with large government contracts to establish an investment with the “same value as
the contract” in Canada. This clause was included in the contract to fulfill the Industrial and
Regional Benefits (IRB) policy, intended to ensure Canadian industries will benefit from major
government defense and security procurement with a foreign supplier (Industry Canada, 2011).
The IRB program was established by the Canadian government to ensure the necessary balance
between financial outflow from major defense spending with a foreign company and inflow of
reciprocal economic benefit. It is particularly important for the Canadian F-35 JSF program,
given that the procurement value is currently estimated at a minimum of $9B.
Recent precedents from Canadian IRB benefit agreements in RCAF procurements with foreign
suppliers include
Page 50 of 76
- Four CC-177 Globemaster strategic airlift aircraft purchased by DND from Boeing
Military Aircraft company, with an IRB value of approximately US$1.5B (Industry
Canada, 2012)
- Fifteen CH-47 Chinook medium-to-heavy lift helicopters purchased by DND from
Boeing Military Aircraft Company, with an IRB value of approximately $4.7B for the
helicopters plus in-service support (National Defence and the Canadian Forces, 2012)
- Seventeen CC-130J Hercules tactical airlift transport aircraft purchased by DND from
Lockheed Martin, the manufacturer of the F-35 JSF, with an IRB value of $1.4B for the
aircraft purchase plus an additional amount for 20 years of in-service support (National
Defence and the Canadian Forces, 2011)
7.2 The Lockheed Martin approach
While IRB programs directly generate economic benefits in the country the product is sold to,
there is usually a premium associated with this arrangement since the supplier cannot actually
provide “full” economic benefit at the lowest price relative to the true value of the product.
Financial stakeholders, in particular the shareholders of the supplier company (in this case,
Lockheed Martin) will demand profit in exchange for their financial investment, so the supplier
company must typically raise the product’s sale price in order to recover their earned profit from
the sales contract and satisfy their shareholders.
In order to maintain a competitive sale price for customers, Lockheed Martin has used a different
methodology from the traditional IRB program, they have implemented an Industrial Share
Program (ISP) with partnership countries, where the opportunity for industry participation is
primarily based on achieving “best value” for the overall F35 JSF program rather than allocating
contracts to specific countries which participated in the SDD or procured the F35 JSF aircraft.
Page 51 of 76
This approach gives a competent and competitive supplier a better opportunity to gain access to
all of the F-35 JSF business opportunities rather than being limited to the country where it is
based.
The ISP approach taken by Lockheed Martin is based on the management philosophy of
establishing a “strategic alliance” framework, with all the suppliers providing “best value” to the
F-35 JSF program. As opposed to the traditional “in-country, dollar-for-dollar” IRB approach,
the “best value” approach enhances the effectiveness of each company’s strategy (Carpenter,
Sanders, & Harling, 2012), thus creating
- Exchange of knowledge associated with technology, skills, or products
- Trust in the management of the alliance
- Success for the alliance, dependent on the collaborative effort of participating companies
It should also be noted that the VRINE (Valuable, Rare, Inimitable, Non-substitutable,
Exploitable) model, another strategic management assessment framework, provides additional
support for the alliance strategy used by the F-35 JSF program. The VRINE model demonstrates
sustainable competitive advantages since the alliance initiated by Lockheed Martin with the
industry partner companies satisfies most if not all of the VRINE objectives. The potential for
company participation at an international level also means this strategic alliance has a global
presence, with all the attendant benefits such an alliance is capable of generating.
Therefore, it is expected that the innovative ISP approach implemented by Lockheed Martin for
the F-35 JSF program, as opposed to the traditional IRB approach, will provide four benefits
(Caccuitto & Vehmeier, 2003):
It will
Page 52 of 76
- Facilitate Canadian industrial participation in JSF program
- Evaluate the JSF as a potential candidate for the RCAF fighter replacement program
- Promote interoperability between the US, British, and Canadian militaries
- Gain insight into US procurement methodologies and best practices
It should be noted that the traditional IRB program is typically more suited to the procurement of
a developed product with a known and fixed price, and is often executed after the product
delivery to include post-delivery sustainment contracts. The ISP approach provides the
significant advantage of early engagement in business activities for eligible companies in the
development and production of the F-35 JSF aircraft.
However, there is a downside to the ISP approach; new companies expecting to receive funding
to develop new technologies are unlikely to become a participant company if another company
already exists that fits the “best value” criteria.
The ISP approach is also expected to provide financial savings for the overall F-35 JSF program;
however, other stakeholders may have different prerogatives and misgivings about Lockheed
Martin using the ISP approach, including those who expect the traditional IRB arrangement to
benefit many in-country companies by distributing contracts across Canada based on population
size and density, which not only makes the process more “fair” by allocating opportunities more
evenly across the country but also earns political support from voters. The conflicting benefits
and interests between these two very different approaches will factor into how Lockheed Martin
and the Canadian government resolve the IRB mandate during the negotiations prior to any
possible contract award process.
Page 53 of 76
7.3 Canadian participation
There are currently over 50 Canadian firms already listed as partners of the F-35 JSF program
(Thornley Fallis, 2012), including broad range of company sizes and types.
In total, Industry Canada has summarized the combined industrial benefit resulting from
Canadian participation in the F-35 JSF program to be $435M as of the end of 2011 (Industry
Canada, 2011)
It should be noted that while certain industrial benefits have been or are continuing to be
received by some of the Canadian companies listed as F-35 JSF partners, other partnering
companies may be precluded, reduced, or potentially removed from ISP opportunities with
Lockheed Martin if Canada chose to stop the F-35 JSF procurement program in favor of a
different aircraft made by a different manufacturer. The economic impact of this potential
scenario must also be taken into account during the review of the industrial benefit elements that
are part of the F-35 JSF procurement decision.
8 Recommendations
The foresight exhibited by US government in the mid-1990s to initiate the Joint Strike Fighter
program demonstrated the effectiveness of the alliance strategy for combining technical and
financial resources from both the US government and multinational partners to obtain
commitment for participation. The combined resources were then utilized to develop a common
platform for next generation fighter aircraft while tailoring three variants: conventional take-off,
short take-off vertical landing (STOVL), and aircraft carrier landing.
The X-35 prototype design by Lockheed Martin successfully beat the X-36 design from Boeing
Military Aircraft Company in a 2001 fly-off competition, resulting in Lockheed becoming the
Page 54 of 76
prime contractor for the F-35 JSF. Their success was followed by the signing of the system
development and demonstration contract in 2002 between Lockheed Martin and multiple
international customers, including Canada.
At the time I was writing this Applied Project report, the SDD phase of the F-35 JSF program
had been going on for 10 years; while the company has been quite successful developing the
technology, schedule and cost performances have not been as stellar. The project is close to 5
years behind schedule, and unit costs have doubled from US$50M to almost $100M, according
to estimates in the US Government Accountability Office reports. After reviewing the F-35 JSF
program’s history and the Canadian government’s participation in it, I have developed 10
recommendations for the Canadian procurement process:
1. Review the anticipated RCAF missions and objectives to understand how Canada will be
involved in domestic and international conflicts. This will reaffirm the specific
requirements of the replacement fighter program for Canada, and will determine if the F-
35 JSF is still the most suitable choice over other aircraft choices available today.
Factors such as absolute need for stealth and total sensor fusion technology, single engine
safety, maximum performance requirements in speed and range, and so on, must all be
considered.
2. Perform a realistic assessment of the delivery schedule and pricing structure for the F-35
JSF, with specific Canadian customizations such as the “drogue and probe” refueling
system compatible with current RCAF tanker aircraft, and drag chute provision to
improve safe landing distances on Canadian Arctic runways, since both factors will
negatively impact the delivery date and cost.
Page 55 of 76
3. Determine technical options and financial consequences should the Canadian government
choose to withdraw from the F-35 JSF program, including alternative aircraft choices and
their delivery schedules, loss of SDD investment, loss of in-country economic benefit,
and any financial/contractual penalties.
4. Liaise with other international customers and actively engage Lockheed Martin and the
JSF Program office to address the schedule and cost issues, with cost being the higher
priority. While this is a difficult task, it is a necessary one if the cost and delivery of the
F-35 JSF fleet are to remain realistic as an option for Canada to replace the CF-18 fleet.
5. Increase international stakeholder participation. It is unclear what the current level of
direct involvement is from the international partners of the F-35 JSF program, since the
program has predominately been funded by the US government. However, international
partners have contributed nearly US$5B toward the estimated overall development cost
of US$50B, starting with the concept demonstration phase in 1997 and the system
development and demonstration phase since 2002 (see Appendix 3); this level of
financial investment qualifies the international participants as stakeholders who should
have proportional input in the management of the development program.
6. Establish fair, meaningful, tangible, and enforceable procurement contract provisions to
address schedule and cost performance issues if and when the F-35 JSF procurement
contract for Canada is negotiated. The current F-35 JSF development program in the US
has effectively become a cost-plus program. The US government has had little leverage
over Lockheed Martin’s schedule and cost performance since the commencement of the
SDD phase in 2002, after which the schedule continued to be delayed and costs to rise
beyond what can be expected as reasonable.
Page 56 of 76
7. Ensure the procurement process is not adversely affected by political interference, and is
achieved while addressing the Canadian requirements that must be served by the new
RCAF fighter jet selection.
8. Initiate risk and contingency assessment processes to extend the operation of the CF-18
fleet operation beyond the originally planned retirement date of 2020; this is a necessary
step in anticipation of the delayed F-35 JSF delivery.
9. Address Canadian industry participation in a fair and equitable manner, regardless of
whether the F-35 JSF is selected as the RCAF replacement for the aging CF-18 fleet.
10. Maintain political transparency during the procurement process, and avoid intentionally
disseminating inaccurate information or deliberate misrepresentation. Examples of these
questionable approaches include the public statements made in 2010 and 2011 by senior
government officials that F-35 JSF contract “has been signed,” and that “Canadian
companies will lose JSF related work if Canada withdraws from the F-35 JSF program”,
only for these officials to concede in March 2012 that the contract had, in fact, not been
signed, and Canadian companies will remain involved in F-35 project (Berthiaume &
Davis, 2012)
9 Conclusions
A well known management framework is the S.M.A.R.T. process (Specific, Measurable,
Achievable, Relevant, and Timely); this framework can be mapped onto the objectives of a
successful replacement fighter procurement program for Canada, which must ensure that
- The requirements are well defined = Specific
- The total expenditure remains within the allocated budget = Measureable
Page 57 of 76
- The project is free of undue influence = Achievable
- The procured service or product serves the purpose for which it is intended = Relevant
- The delivery is completed in a timely manner for deployment = Timely
In a complex and prolonged procurement process such as the Canadian replacement fighter
program, it is suggested a derivation of the S.M.A.R.T. process that includes continued
Evaluation and Re-evaluation (i.e., S.M.A.R.T.E.R.) to account for the changing scenarios which
can develop. Adding these two steps could address some of the issues experienced during
Canada’s involvement in the F-35 JSF program over the 10 years since Canada signed the SDD
MOU in 2002 to join the development program.
It should be noted that it is not uncommon for a large-scale military development program to
exceed its originally planned schedule and cost. However, the F-35 JSF program in the US has
developed into a classic case of schedule and cost overrun, and shares some similarities to the
recent €20+ billion Airbus Industries A-400M Atlas military medium-lift transport aircraft
development program, where the “customer” was a partnership of defense departments from
seven nations, including France, Germany, Spain, the United Kingdom, Turkey, Belgium, and
Luxembourg.
The similarity between the F-35 JSF and A-400M Atlas programs does not end at the number of
combined international customers. The A-400M program also ran into schedule and cost
difficulties, but since the procurement contract was signed very early in the development
program with a fixed pricing clause, Airbus Industries was forced to take the unprecedented step
of publicly requesting additional funding from the partnering nations, who would otherwise risk
the program being cancelled and a financial loss of over €5.7 billion. The situation was resolved
Page 58 of 76
when the partnering nations agreed to provide a €3.5 billion loan to maintain this program and
avoid the risk of cancellation (Tran, 2010).
Due to the large funding sum already invested in the $50B development program (Butler, 2010),
it is unrealistic to expect the US government will allow the F-35 JSF program funding to
deteriorate to the point that Lockheed Martin might threaten to cancel the project. This “sunk
cost”, in conjunction with the F-35 JSF being the only realistic fifth-generation fighter option
available to the military had made it highly unlikely, extremely difficult, and very costly for the
F-35 JSF program to be cancelled by the US government. However, the sunk cost invested by
Canada in the F-35 JSF program is $160M at the end of the SDD phase. This smaller investment
may give Canada the possibility to withdraw from the JSF program and accept the loss (i.e., sunk
cost) in order to find an alternate aircraft solution, such as the F-18 Super Hornet from Boeing
Military Aircraft Company, which has a currently published unit price of $53M (Sweetman,
2011), and requires lower infrastructure update costs for Canada when compared to the
transitions necessary for the F-35 JSF. Taking this approach will result in a significant overall
procurement cost reduction compared to the F-35 JSF, an opinion shared in a 2003 US
Congressional Research Service report (Bolkcom, 2003).
Going forward, it is this “re-evaluation” step which the Canadian government should undertake
as part of the S.M.A.R.T.E.R. process recommended for this procurement program.
Page 59 of 76
Bibliography
Aero News Network. (2011, Sep 7th). Another Setback For JSF: Testing finds flaws in F-35 wing
structure. Retrieved from Aero News Network: http://www.aero-
news.net/index.cfm?do=main.textpost&id=cda18e02-755b-4e87-aa7d-0037e72ac1fc
AIAC. (2010, Sep 28th). Aerospace Industry Leaders Affirm Support for F-35 Purchase. Retrieved from
Aerospace Industry Association of Canada: http://www.aiac.ca/en/news.aspx?id=1237
Australian Government. (2009). Australian JSF Industry Group (AJIG). Retrieved from Australian
Governement: http://www.innovation.gov.au/Industry/Defence/JSF/Pages/AJIG.aspx
Baker, D. (n.d.). Business Influence on Governent and Public Policy, Chapter 12. USA. Retrieved Mar
20, 2012, from www.sba.pdx.edu/faculty/brendae/385/Ch12.ppt
Berthiaume, L. (2012, February 29th). Defence Department concerned about lack of definitive F-35 cost
estimate. Retrieved from Montreal Gazette:
http://www.montrealgazette.com/technology/Defence+Department+concerned+about+lack+defin
itive+cost+estimate/6230225/story.html
Berthiaume, L. (2012, March 3rd). F-35 partner nations ponder fighter's progress. Retrieved from
Postmedia News: http://www2.canada.com/topics/news/national/story.html?id=6246004
Berthiaume, L., & Davis, J. (2012, March 27th). Canada's companies will remain involved in F-35
project: Harper. Retrieved from Canada.com:
http://www.canada.com/business/Canada+companies+will+remain+involved+project+Harper/63
64532/story.html
Boeder, J. (2007, December 3rd). F-35 JSF Hit by Serious Design Problems. Retrieved from Defense
Industry Daily: http://www.defenseindustrydaily.com/f-35-jsf-hit-by-serious-design-problems-
04311/
Page 60 of 76
Bolkcom, C. (2003, July 11th). Joint Strike Fighter (JSF) Program: Background, Status, and Issues.
Retrieved from Defense Technical Information Center:
http://www.dtic.mil/dtic/tr/fulltext/u2/a472774.pdf
Brewster, M. (2010, September 15). Tory Ministers Defend $9B F-35 Fighters. Retrieved from Toronto
Star: http://www.thestar.com/news/canada/article/861439--tory-ministers-defend-9b-f-35-fighters
Butler, A. (2010, March 12). Carter Confirms JSF Unit Price Nearly Doubled. Aviation Week. Retrieved
from
http://www.aviationweek.com/aw/generic/story_generic.jsp?channel=aerospacedaily&id=news/as
d/2010/03/12/01.xml
Caccuitto, M., & Vehmeier, D. (2003). JSF International Industrial Participation: A Study of Country
Approaches and Financial Impacts on Foreign Suppliers. Washington: Office of Deputy Under
Secretary of Defense. Retrieved from
http://www.ledevoir.com/documents/pdf/etude_internationale_defense_americaine.pdf
Carpenter, M., Sanders, G., & Harling, K. (2012). Stragegic Management, A Dynamic Perspective,
Canadian Edition. Toronto: Pearson Canada Inc.
Cenciottis, D. (2012, February 8th). Italy buys its first three F-35s. With a shocking announcement: "A
JSF will cost less than a Eurofighter Typhoon". Retrieved from The Aviationist: Italy is in
process of purchasing the first 3 aircraft for $240M for initial training logistics
Davis, M. C. (2008, September 30th). Economic Development Council presentation. Retrieved from
Florida Economic Development Council: http://www.florida-
edc.org/Roundtable/MGen%20Davis%20F-35%20Sept08.pdf
Page 61 of 76
Defense Industry Daily. (2008, May 17th). Canada Joining the Anglosphere C-17 Club with CC-177.
Retrieved from Defense Industry Daily: http://www.defenseindustrydaily.com/canada-joining-
the-anglosphere-c17-club-02388/
Defense Industry Daily. (2012, February 22nd). Australia Buying 24 Super Hornets As Interim Gap-
Fillers. Retrieved from Defense industry Daily: http://www.defenseindustrydaily.com/australia-
to-buy-24-super-hornets-as-interim-gapfiller-to-jsf-02898/#contracts
Defense Industry Daily. (2012, February 22nd). Australia Buying 24 Super Hornets As Interim Gap-
Fillers. Retrieved from Defense Industry Daily: http://www.defenseindustrydaily.com/australia-
to-buy-24-super-hornets-as-interim-gapfiller-to-jsf-02898/#contracts
DeMille, D., & Priestley, S. (2010, November). Canadian Medium-Lift Helicopters in Afghanistan.
Retrieved from Canadian American Strategic Review: http://www.casr.ca/ft-helicopters-5-years-
on-1.htm
Department of Defense. (2012, January 17th). JSF Test Report. Retrieved from
https://s3.amazonaws.com/s3.documentcloud.org/documents/274989/2010f35jsf.pdf
Deschamps, L.-G. A. (2010, Winter Vol. 11, No. 1). Meet the F-35 Lightening II - Canada's Next Fighter.
Retrieved Jan 22nd, 2012, from Canadian Military Journal:
http://www.journal.dnd.ca/vo11/no1/doc/10-deschamps-eng.pdf
Director of Operational Test and Evaluation. (2012, January). FY 2011 DOTE Annual Report. Retrieved
from DOTE:
http://www.dote.osd.mil/pub/reports/FY2011/pdf/other/2011DOTEAnnualReport.pdf
FAD. (2012, February 28th). Danish Industry Fighter Aircraft Team (DIFAT). Retrieved from Danish
Defence & Security Industries Association:
http://fad.di.dk/about%20fad/danishfighteraircraftteam/pages/default.aspx
Page 62 of 76
Fulghum, D. A., Warwick, G., Wall, R., & Ben-David, A. (2011, March 23rd). JSF Cost Predications
Rattle Foreign Customers. Retrieved Jan 22nd, 2012, from Aviation Week:
http://www.aviationweek.com/aw/generic/story.jsp?channel=defense&id=news/awst/2011/03/21/
AW_03_21_2011_p27-297530.xml&headline=JSF&next=20
Gertler, J. (2012). F-35 Joint Strike Fighter (JSF) Program. Washington: Congressional Research
Service. Retrieved from http://www.fas.org/sgp/crs/weapons/RL30563.pdf
Gilmore, D. J. (2011, May 19). Joint Strike Fighter Technical Baseline Review (TBR) and Re-planning
Flight Test. Retrieved from Senate Armed Services Committee: http://armed-
services.senate.gov/statemnt/2011/05%20May/Gilmore%2005-19-11.pdf
Government of Canada. (2006, December 12th). Canada's new government signs on to phase III of Joint
Strike Fighter program. Retrieved from Canada News Centre: http://news.gc.ca/web/article-
eng.do?crtr.sj1D=&mthd=advSrch&crtr.mnthndVl=7&nid=262049&crtr.dpt1D=&crtr.tp1D=&cr
tr.lc1D=&crtr.yrStrtVl=2002&crtr.kw=joint%2Bstrike%2Bfighter&crtr.dyStrtVl=1&crtr.aud1D=
&crtr.mnthStrtVl=1&crtr.yrndVl=2010&crtr.dyndVl=23
Grant, R. (2008). Contemporary Strategy Analysis. Oxford: Blackwell Publishing Ltd.
Hicks, R. (2010, September 21st). Memorandum of Understanding on F-35s. Retrieved from CBC News,
Inside Politics Blog: http://www.cbc.ca/news/politics/inside-politics-blog/2010/09/memorandum-
of-understanding-n.html
Industry Canada. (2010, December 23th). About Industry Canada. Retrieved from Industry Canada:
http://www.ic.gc.ca/eic/site/ic1.nsf/eng/h_00007.html
Industry Canada. (2011, November 21st). Canada's Next Generation Figher Capability. Retrieved from
Industry Canada: http://www.ic.gc.ca/eic/site/ad-ad.nsf/eng/ad03863.html
Page 63 of 76
Industry Canada. (2011, December 7th). Industrail and Regional Benefits. Retrieved Jan 22nd, 2012,
from Industry Canada: http://www.ic.gc.ca/eic/site/042.nsf/eng/home
Industry Canada. (2012, February 6th). Industrial and Regional Benefit - Strategic Airlift. Retrieved from
Industry Canada: http://www.ic.gc.ca/eic/site/043.nsf/eng/00005.html
Industry Canada. (2012, February 2nd). Industrial Regional Benefits. Retrieved from Industry Canada:
http://www.ic.gc.ca/eic/site/042.nsf/eng/home
Jones, R. (2012, February 7th). Britain won't decide on F-35 fighter numbers till 2015. Retrieved from
Reuters: http://uk.reuters.com/article/2012/02/07/uk-lockheed-britain-f-
idUKTRE8160YZ20120207
JSF NIEUWS. (2011, February 7th). Canada: Extra costs for aerial refuelling and drag chute JSF.
Retrieved from JSF NIEUWS: http://www.jsfnieuws.nl/?p=599
JSF UK Industry Team. (2012). Additional Details. Retrieved from JSF UK Industry Team:
http://www.jsf.org.uk/JSF-and-the-UK/Additional-details.aspx
Kallender-Umezu, P. (2011, December 20th). Japan F-X Competition Win Victory for JSF Program.
Retrieved from DefenseNews:
http://www.defensenews.com/article/20111220/DEFSECT01/112200301/Japan-F-X-
Competition-Win-Victory-JSF-Program
Kaluzny, D. B. (2011, March 18). ANALYSIS OF PARLIAMENTARY BUDGET OFFICER COST
ESTIMATION MODELS FOR THE JOINT STRIKE FIGHTER PROJECT. Gatineau: Defence R
& D Canada – Centre for Operational Research and Analysis. Retrieved from National Defence
and the Canadian Forces: http://www.forces.gc.ca/site/pri/2/pro-pro/ngfc-fs-ft/drdc-rddc-eng.asp
Page 64 of 76
Katz, Y. (2010, August 8th). Israel to finalize JSF purchase plans. Retrieved from The Jerusalem Post:
http://www.jpost.com/Israel/Article.aspx?id=184007
Kopp, D. C. (2008, May 17th). Assessing Progress on the Joint Strike Fighter. Air Power Australia
Analyses. Retrieved from http://www.ausairpower.net/APA-2008-03.html
Lockheed Martin. (2012, February 23rd). F-35 Flight Test and production Progress Report. Retrieved
from F-35 Canada: http://f-35.ca/2012/f-35-flight-test-and-production-progress-report/
Lockheed Martin Company. (2012). Canadian Government Involvement. Retrieved from F35, Canada's
Next Generation Fighter: http://f-35.ca/canadian-government-involvement-en/
Majumdar, D. (2012, March 3rd). U.S. Air Force Approves JSF Flight Operations. Retrieved from
Defense News: http://www.defensenews.com/article/20120303/DEFREG02/303030001/U-S-Air-
Force-Approves-JSF-Flight-Operations-Sources
Markowski, S., & Hall, P. (2006). Defence Procurement and Industry Development: Some Lessons from
Australia. (U. Berkok, Ed.) The Claxton Papers. Retrieved from
http://www.queensu.ca/dms/publications/claxton/Claxton7.pdf
Munoz, C. (2012, January 6th). Lochheed Scores Another Win; Turkey To Buy Two F-35s. Retrieved
from AOL Defense: http://defense.aol.com/2012/01/06/jsf-program-racks-up-another-win-with-
turkey-deal/
Murphy, J. (2012, March 2nd). The government must end the uncertainty over its F-35 plans. Retrieved
from Defence Management: http://www.defencemanagement.com/feature_story.asp?id=18813
National Defence and the Canadian Forces. (2011, January 1st). Equipment Procurement - CC-130J
Hercules. Retrieved from National Defence and the Canadian Forces:
http://www.forces.gc.ca/site/pri/2/pro-pro/hercules-eng.asp
Page 65 of 76
National Defence and the Canadian Forces. (2011, October 10th). F-35 Joint Strike Fighter Next
Generation Fighter Capability. Retrieved from National Defence and the Canadian Forces:
http://www.forces.gc.ca/site/pri/2/pro-pro/ngfc-eng.asp
National Defence and the Canadian Forces. (2012, January 13th). Equipment Procurement - CH-47
Chinook - Canadian F-Model Medium-to-Heavy Lift Helicopters. Retrieved from National
Defence and the Canadian Forces: http://www.forces.gc.ca/site/pri/2/pro-pro/chinook-eng.asp
National Defence and the Canadian Forces. (2012, March 9th). F-35 Joint Strike Fighter Next Generation
Fighter Capability. Retrieved from National Defence and the Canadian Forces:
http://www.forces.gc.ca/site/pri/2/pro-pro/ngfc-eng.asp
National Defence of Canada. (2012, January 13). CC-177 Globemaster III - Strategic Airlift. Retrieved
from National Defence and the Canadian Forces: http://www.forces.gc.ca/site/pri/2/pro-
pro/globemaster-eng.asp
Naval-Technology. (2011). Queen Elizabeth Class (CVF), United Kingdom. Retrieved from Naval-
Technology: http://www.naval-technology.com/projects/cvf/
Norrie, J., & Walker, D. (2004). A Balanced Scorecard Approach to Project Management Leadership.
Project Management Journal, 35(4), 47-57. Retrieved from http://0-
web.ebscohost.com.aupac.lib.athabascau.ca/ehost/detail?vid=3&hid=21&sid=a89b5901-99f3-
4e02-999e-
90d54b01e985%40sessionmgr12&bdata=JkF1dGhUeXBlPXVybCxpcCx1aWQmc2l0ZT1laG9z
dC1saXZl#db=ofm&AN=510429110
Norris, G. (2011, December 5th). GE, Rolls Give Up on F136 JSF Alterate Engine. Aviation Week.
Retrieved from
Page 66 of 76
http://www.aviationweek.com/aw/generic/story_channel.jsp?channel=defense&id=news/awx/201
1/12/02/awx_12_02_2011_p0-401195.xml
Norton-Taylor, R. (2010, January 12). MoD to slash jet fighter orders as it struggles to save aircraft
programme. Retrieved from The Guardian: http://www.guardian.co.uk/uk/2010/jan/12/defence-
aircraft-jet-fighters-budget
Parliament of Canada. (2012, March). Library of Parliament. Retrieved March 2nd, 2012, from
Parliament of Canada: http://www.parl.gc.ca/PBO-DPB/index.aspx?Language=E
Payton, L. (2012, March 16th). F-35 delivery could be delayed to save money. Retrieved from CBC
News: http://www.cbc.ca/m/touch/canada/story/2012/03/16/pol-fantino-f35s-could-be-
delayed.html
Peruzzi, L. (2012, February 3rd). Italy committed to F-35 programme but may cut order. Retrieved from
Flightblobal: http://www.flightglobal.com/news/articles/italy-committed-to-f-35-programme-but-
may-cut-order-367733/
Plamondon, A. (2008). Equipment Procurement in Canada and the Civil-Military Relationship: Past and
Present. (D. J. Ferris, Ed.) Calgary Papers in Military and Stratgic Studies, 2. Retrieved from
http://cpmss.synergiesprairies.ca/cpmss/index.php/cpmss/article/view/35/27
Plamondon, A. (2010). The Politics of Procurement, Military Acquisition in Canada and the Sea King
Helicopter. Vancouver: UBC Press. Retrieved from
http://www.ubcpress.ca/books/pdf/chapters/2009/ThePoliticsOfProcurement.pdf
Pugliese, D. (2010, March 23rd). Defense Watch. Retrieved from Ottawa Citizen:
http://blogs.ottawacitizen.com/2010/03/23/new-head-of-jsf-program-nominated-denmark-backs-
away-from-jsf-successful-jsf-flight-takes-place/
Page 67 of 76
Reuters. (2012, February 10th). Update1 - Italy widely expected to scale back F-35 orders. Retrieved
from Reuters: http://www.reuters.com/article/2012/02/10/defence-italy-fighter-
idUSL5E8DAC5T20120210
Royal Australian Air Force. (2012). Joint Strike Fighter F-35 Lightning II. Retrieved from Royal
Australian Air Force: http://www.airforce.gov.au/aircraft/jsf.aspx
Royal Canadian Air Force. (2010, June 4th). New generation of CC-130J Hercules arrives in Canada.
Retrieved from National Defence: http://www.rcaf-arc.forces.gc.ca/8w-8e/nr-sp/index-
eng.asp?id=10624
Schwellenbach, N. (2010, October 9th). British Shift to F-35C: A Blow to the Beleaaguered Join Strike
Fighter "B" Model. Retrieved from Project On Government Oversight:
http://pogoblog.typepad.com/pogo/2010/10/british-shift-to-f-35c-a-blow-to-the-beleaguered-
joint-strike-fighter-b-model.html
Senate Committee on National Security and Defence. (2005). Wounded, Canada's Military and the
Legacy of Neglect. Ottawa: Canada. Senate Committee Reports. Retrieved March 7th, 2012, from
http://0-site.ebrary.com.aupac.lib.athabascau.ca/lib/athabasca/docDetail.action?docID=10325609
Slack, N., Chambers, S., & Johnson, R. (2010). Operations Management (6th ed.). Essex: Pearson
Education Limited.
Staples, S. (2007, June). No Bang for the Buck: Military Contracting and Public Accountability. Foreign
Policy Series, 2(2). Retrieved Mar 6, 2012, from http://0-
site.ebrary.com.aupac.lib.athabascau.ca/lib/athabasca/docDetail.action?docID=10174547
Staples, S. (2010, Oct). Pilot Error - Why the F-35 stealth Fighter is Wrong for Canada. Foreign Policy
Series. Retrieved from
Page 68 of 76
https://s3.amazonaws.com/policyalternatives.ca/sites/default/files/uploads/publications/National
%20Office/2010/10/Pilot_Error.pdf
Sweetman, B. (2009, June 8th). Norway's Parliament Endorses JSF, But.... Retrieved from Aviation
Week:
http://www.aviationweek.com/aw/blogs/defense/index.jsp?plckController=Blog&plckScript=blog
script&plckElementId=blogDest&plckBlogPage=BlogViewPost&plckPostId=Blog%3A27ec4a5
3-dcc8-42d0-bd3a-01329aef79a7Post%3A99b5964e-7c9a-4557-aa2a-03992f92731b
Sweetman, B. (2011, May 31st). Boeing Calls Lockheed Martin On Cost Claims. Retrieved from Aviation
Week:
http://www.aviationweek.com/aw/blogs/defense/index.jsp?plckController=Blog&plckScript=blog
Script&plckElementId=blogDest&plckBlogPage=BlogViewPost&plckPostId=Blog:27ec4a53-
dcc8-42d0-bd3a-01329aef79a7Post:e23773c7-5b69-4675-8717-765648aaddd8
Thornley Fallis. (2012). F-35 Canadian Partners. Retrieved Jan 22, 2012, from F-35 Canada's Next
Generation Fighter: http://f-35.ca/canadian-partners-en/
Tran, P. (2010, March 8th). A400M Cost Overrun Set at 10%. Retrieved from Defense News:
http://www.defensenews.com/article/20100308/DEFSECT01/3080303/A400M-Cost-Overrun-
Set-10-
United States GAO. (2012). GAO-Our Products. Retrieved March 6th, 2012, from U.S. Government
Accountability Office: http://www.gao.gov/about/products/
United States Government Accountability Office. (2011, March 15). Joint Strike Fighter, Restructuring
Should Improve Outcomes, but Progress Is Still Lagging overall. Retrieved from United States
Government Accountability Office: http://www.gao.gov/new.items/d11450t.pdf
Page 69 of 76
United States Government Accountability Office. (2012). Defense Logistics: Improvement needed to
enhance oversight of estimated long-term costs for operating and supporting major weapon
systems. Washington: U.S. Government General Accountability Office. Retrieved from
http://ezproxy.athabascau.ca:2050/toc.aspx?bookid=45523
UPI. (2011, March 25th). U.S. - Turkey F-35 deal stalled. Retrieved from UPI:
http://www.upi.com/Business_News/Security-Industry/2011/03/25/US-Turkey-F-35-deal-
stalled/UPI-33521301049204/
US Air Force. (2008, February). US Air Force Committee Staff Procurement Backup Book FY 2009
Budget Estimates. Retrieved from US Air Force:
http://www.saffm.hq.af.mil/shared/media/document/AFD-080204-081.pdf
US Government Accountability Office. (2009). Joint Strike Fighter, Accelerating Procurement before
Completing Development Increases the Government's Financial Risk. Washington: March.
Retrieved from http://www.gao.gov/new.items/d09303.pdf
US Government Accountability Office. (2011). Joint Strike Fighter, Restructuring Places Program on
Firmer Footing, but Progress Still Lags. Washington. Retrieved from
http://www.gao.gov/new.items/d11325.pdf
US Government/Dep of Defense. (2012, March). JSF News. Retrieved from JSF Program Office website:
http://www.jsf.mil/news/index.htm
Waldron, G. (2012, February 28th). Japan wary of F-35 cost escalation. Retrieved from Flightglobal:
http://www.flightglobal.com/news/articles/japan-wary-of-f-35-cost-escalation-368869/
Wall, R. (2011, October 10). Norway Sets JSF Buy In New Budget. Retrieved from Aviation Week:
http://www.aviationweek.com/aw/generic/story_channel.jsp?channel=defense&id=news/asd/201
1/10/10/01.xml
Page 70 of 76
Wall, R. (2012, March 13th). Lockheed Martin Awaits U.K. F-35 Decision. Retrieved from Aerospace
Daily and Defense Report:
http://www.aviationweek.com/aw/generic/story_generic.jsp?channel=aerospacedaily&id=news/as
d/2012/03/13/02.xml&headline=Lockheed%20Martin%20Awaits%20U.K.%20F-35%20Decision
Weltman, P., & Yalkin, T. (2011). Comparing PBO and DND Cost Estimates on Canada's Proposed
Acuqisition of the F-35 Joint Strike Fighter: Some Preliminary Questions and Answers on Key
Issues. Ottawa: Office of the Parliamentary Budget officer. Retrieved from
http://www.parl.gc.ca/pbo-dpb/documents/F35_QA_EN.pdf
Yalkin, T. R., & Weltman, P. (2011). An Estimate of the Fiscal Impact of Canada's Proposed Acquisition
of the F-35 Lightening II Joint Strike Fighter. Ottawa: Office of the Parliamentary Budget
Officer. Retrieved from http://www.parl.gc.ca/PBO-DPB/documents/F-
35_Cost_Estimate_EN.pdf
Page 71 of 76
Appendix 1. F-35 Development Schedule Revisions 2003 to 2012
2003 F-35 JSF Program Schedule1 (Kopp, 2008)
1 http://www.ausairpower.net/APA-2008-03.html
Page 72 of 76
2006 F-35 JSF Program Schedule2 (Kopp, 2008)
2 http://www.ausairpower.net/APA-2008-03.html
2008 F-35 JSF Program Schedule3
3 http://www.florida-edc.org/Roundtable/MGen%20Davis%20F
3 (Davis, 2008)
edc.org/Roundtable/MGen%20Davis%20F-35%20Sept08.pdf
Page 73 of 76
Page 74 of 76
Appendix 2. F-35 JSF Procurement Quantities 2012
Country Original Initial Current Procurement Status
Australia 100 144 755 Bought F/A-18 E/F Super Hornet as interim gap measure,
program under audit/review6
Canada 65 ? 65 Government agreed to restructure procurement process after
Auditor General report Spring 20127
Denmark ? ? Delayed selection to 20148
Israel 75 20 ? Through FMS funding9
Italy 131 90 Defense Minister announced cut to order10
Japan 42 411 42 Announced selection in Dec 2011, announced risk of
cancellation if cost increases12
Netherland 85 2 50 ?13 Decision for final order not yet made14
Norway 48 4 52 52 include 6 as options15
Turkey 120 2 100 Placed order for two initial delivery aircraft16
United
Kingdom
138 ? Delayed decision to 2015
United States 1763+680
= 2,443
? Under heavy scrutinizing due to cost and schedule over-runs
4 http://www.defence.pk/forums/military-forum/40004-australia-approves-jsf-purchase-plans-initial-order-14-ctols.html 5 http://defense-studies.blogspot.ca/2012/03/australia-looking-at-average-us70m-per.html 6 http://www.defensenews.com/article/20111027/DEFSECT01/110270305/Australia-Launches-F-35-Review 7 http://www.cbc.ca/news/canada/story/2012/04/02/f-f35-cost-concerns.html 8 http://www.defensenews.com/article/20100324/DEFSECT01/3240310/Denmark-Delays-Fighter-Purchase-up-4-Years 9 http://www.jpost.com/Israel/Article.aspx?id=184007 10 http://www.ft.com/intl/cms/s/0/6fa9b130-57f2-11e1-bf61-00144feabdc0.html 11 http://www.aviationweek.com/aw/generic/story_channel.jsp?channel=defense&id=news/awst/2012/01/02/AW_01_02_2012_p26-409910.xml&headline=null&next=10 12 http://www.cbc.ca/news/canada/story/2012/04/02/f-f35-cost-concerns.html 13 http://www.aviationweek.com/aw/blogs/defense/index.jsp?plckController=Blog&plckScript=blogScript&plckElementId=blogDest&plckBlogPage=BlogViewPost&plckPostId=Blog:27ec4a53-dcc8-42d0-bd3a-01329aef79a7Post:736625a5-954f-473f-a0eb-003a908f4459 14 http://www.thehollandbureau.com/2011/12/18/jsf-hanging-in-there/ 15 http://www.defenseindustrydaily.com/f35-lightning-ii-faces-continued-dogfights-in-norway-03034/ 16 http://www.defenseindustrydaily.com/f35-lightning-ii-faces-continued-dogfights-in-norway-03034/
Page 75 of 76
Appendix 3. F-35 JSF International Development Contribution17,18
Concept Demonstration
Phase
Systems Development
Demonstration Phase
Total
Australia $150M $150M
Canada $10M $150M $160M
Denmark $10M $125M $135M
Italy $10M $1B $1.01B
UK $200M $2B $2.02B
Norway $10M $125M $135M
Turkey $175M $175M
The Netherland $800M $800M
Total $240M $4.525B $4.765B
17 http://www.dtic.mil/dtic/tr/fulltext/u2/a472774.pdf 18 http://www.jsf.mil/program/prog_intl.htm
Page 76 of 76
Appendix 4. F-35 JSF Procurement Quantity Forecast 201019
19 http://www.aviationweek.com/aw/blogs/defense/index.jsp?plckController=Blog&plckScript=blogScript&plckElementId=blogDest&plckBlogPage=BlogViewPost&plckPostId=Blog%3A27ec4a53-dcc8-42d0-bd3a-01329aef79a7Post%3A690b140b-f361-40b6-b88e-f06d44f63bcb