Essentials of a valid contract and general principlesiced.cag.gov.in/wp-content/uploads/B-02/Day 4...
Transcript of Essentials of a valid contract and general principlesiced.cag.gov.in/wp-content/uploads/B-02/Day 4...
An interaction on
Essentials of a valid contract
and general principles
sharing the experiences
Essentials Elements of a Valid Contract:
Essentials Elements of a Valid Contract:
1.Proposal and acceptance (NIT/RFP)
2. Consideration -- lawful consideration with a lawful
object
3. Capacity of parties to contract -- competent parties
4. Free consent
5. An agreement must not be expressly declared to be
void
6. Writing and Registration if so required by law.
Essentials Elements of a Valid Contract
7. Legal relationship
8. Certainty (No uncertian clauses : :Cost Plus & Lump Sum )
9. Possibility of performance
10. Enforceable by law
The contract-agreement should ensure :
• A definition of what is to be provided (clear) and requirements
(no idea) to be met (DMS-computerisation ops; IGNOU-ERP)
• An agreed level of service and mechanism for payment
reduction if not met (NQM Vs SQM-PMGSY)
• Means to measure performance
• Pricing mechanisms including where appropriate, milestone
payments, incentivisation/rewards, retentions and, if the
contract is for more than 2 years, price variation mechanisms
Essentials Elements of a Valid Contract
• A plan to cover implementation/transition/rollout
• Acceptance strategy/test plan
• Ownership of assets and intellectual property (Source
Code)
• Escalation and alternative dispute resolution procedures
• Change control procedures (IGNOU, DMS, IMO, OMMAS
PMGSY:Trg given but purpose not served, No Progress)
• Invoicing arrangements
• Communication routes , typically at three levels
• Operational (end users/technical support staff) Very Imp.
• Business (contract manager and relationship manager on
both sides)
Essentials Elements of a Valid Contract
• Strategic (senior management/board of directors)
• • Agreed exit strategy and agreed break options
• • Premises (where the goods/services will be delivered)
• • Sub contractor details
• • Authorities’ responsibilities (Expectations)
• • A good contract not only identifies clearly the obligations
of the provider, but also forms the foundation for a
productive relationship built on communication and trust
• A formal legal advice is always recommended prior to
making or accepting a contract.
GENERAL PRINCIPLES TO BE OBSERVED
The following general principles should be
observed while entering into contracts:
– The terms of contract must be precise, definite
and without any ambiguities. The terms should
not involve an uncertain or indefinite liability,
except in the case of a cost plus contract or
where there is a price variation clause in the
contract. (Most imp, route cause of disputes
later, in-depth knowledge and experience,
otherwise invites conditions in tender – not
alone a & d together; specs revised or not
available)
GENERAL PRINCIPLES TO BE OBSERVED
• Standard forms of contracts should be
adopted wherever possible, with such
modifications as are considered necessary
in respect of individual contracts. The
modifications should be carried out only
after obtaining financial and legal advice.
• In cases where standard forms of
contracts are not used, legal and financial
advice should be taken in drafting the
clauses in the contract.
GENERAL PRINCIPLES TO BE OBSERVED
Iv (a) A Contract document should be executed, with
all necessary clauses to make it a self-contained
contract. If however, these are preceded by
Invitation to Tender, accompanied by General
Conditions of Contract (GCC), Special Conditions of
Contract (SCC), with full details of scope and
specifications, a simple one page contract can be
entered into by attaching copies of the GCC and
SCC, and details of scope and specifications, Offer of
the Tenderer and Letter of Acceptance.
• (b) A Contract document should be invariably
executed in cases of turnkey works or agreements for
maintenance of equipment, provision of services etc.
GENERAL PRINCIPLES TO BE OBSERVED
• No work of any kind should be
commenced without proper execution of
an agreement as given in the foregoing
provisions.
• (vi) Contract document, where necessary,
should be executed within 21 days of the
issue of letter of acceptance. Non-
fulfilment of this condition of executing a
contract by the Contractor or Supplier
would constitute sufficient ground for
annulment of the award and forfeiture of
Earnest Money Deposit.
GENERAL PRINCIPLES TO BE OBSERVED• (vii) Cost plus contracts should ordinarily be avoided.
Where unavoidable, full justification should be
recorded before entering into the contract. Where
supplies or special work covered by such cost plus
contracts have to continue over a long duration, efforts
should be made to convert future contracts on a firm
price basis after allowing a reasonable period to the
suppliers/contractors to stabilize their production/
execution methods and processes.• Explanation : A cost plus contract means a contract in which the price
payable for supplies or services under the contract is determined on
the basis of actual cost of production of the supplies or services
concerned plus profit either at a fixed rate per unit or at a fixed
percentage on the actual cost of production.
GENERAL PRINCIPLES TO BE OBSERVED
• (viii) (a) Price Variation Clause can be
provided only in long-term contracts,
where the delivery period exceeds 18
months. In short-term contracts firm and
fixed prices should be provided for. Where
a price variation clause is provided, the
price agreed upon should specify the base
level viz, the month and year to which the
price is linked, to enable variations being
calculated with reference to the price
levels prevailing in that month and year.
GENERAL PRINCIPLES TO BE OBSERVED
• (b) A formula for calculation of the price
variations that have taken place between the
Base level and the Scheduled Delivery Date
should be included in this clause. Docs/Bases
for calculating variations should be specified.
• (c) The Price variation clause should also
specify cut off dates for material and labour, as
these inputs taper off well before the scheduled
Delivery Dates.
GENERAL PRINCIPLES TO BE OBSERVED
• (d) The price variation clause should provide for a
ceiling on price variations, particularly where
escalations are involved. It could be a percentage per
annum or an overall ceiling or both. The buyer should
ensure a provision in the contract for benefit of any
reduction in the price in terms of the price variation
clause being passed on to him.
• (e) The clause should also stipulate a minimum
percentage of variation of the contract price above
which price variations will be admissible (e.g. if
resultant increase is less than 2% no price adjustment
will be made in favour of the supplier).
GENERAL PRINCIPLES TO BE OBSERVED
• (f) Where advance or stage payments are made there
should be a further stipulation that no price variations
will be admissible on such portions of the price, after
the dates of such payment.
• (g) Where deliveries are accepted beyond the
scheduled Delivery Date subject to levy of liquidated
damages as provided in the Contract, the liquidated
damages (if a percentage of the price) will be
applicable on the price as varied by the operation of
the Price variation clause.
• (h) No price variation will be admissible beyond the
original Scheduled Delivery Date for defaults on the
part of the supplier.
GENERAL PRINCIPLES TO BE OBSERVED
• (i) Price variation may be allowed beyond the original
Scheduled Delivery Date, by specific alteration of that date
through an amendment to the contract in cases of Force
Majeure or defaults by Government.
• (j) Where contracts are for supply of equipment, goods etc,
imported (subject to customs duty and foreign exchange
fluctuations) and/or locally manufactured (subject to excise duty
and other duties and taxes), the percentage and element of
duties and taxes included in the price should be specifically
stated, along with the selling rate of foreign exchange element
taken into account in the calculation of the price of the imported
item. The mode of calculation of variations in duties and taxes
and Foreign exchange rates and the documents to be produced
in support of claims for such variations, should also be
stipulated in the Contract.
GENERAL PRINCIPLES TO BE OBSERVED
• (k) The clause should also contain, if necessary, the
mode and terms of payment of the price variation
admissible.
• (ix) Contracts should include provision for payment of
all applicable taxes by the contractor or supplier.
• (x) “Lumpsum’ contracts should not be entered into
except in cases of absolute necessity. Where
lumpsum contracts become unavoidable, full
justification should be recorded. The contracting
authority should ensure that conditions in the lumpsum
contract adequately safeguard and protect the
interests of the Government.
GENERAL PRINCIPLES TO BE OBSERVED• (xi) Departmental issue of materials should be avoided as far as
possible. Where it is decided to supply materials
departmentally, a schedule of quantities with the issue rates of
such material as are required to execute the contract work,
should form an essential part of the contract
• .(xii) (a) In contracts where government property is entrusted to
a contractor either for use on payment of hire charges or for
doing further work on such property, specific provision for
safeguarding government property (including insurance cover)
and for recovery of hire charges regularly, should be included in
the contracts.
• (b) Provision should be made in the contract for periodical
physical verification of the number and the physical condition of
the items at the contractors premises. Results of such
verification should be recorded and appropriate penal action
taken where necessary.
GENERAL PRINCIPLES TO BE OBSERVED
• ((xiii) (a) The terms of a contract, including the scope
and specification once entered into, should not be
materially varied.
• (b) Wherever material variation in any of the terms or
conditions in a contract becomes unavoidable, the
financial and other effects involved should be
examined and recorded and specific approval of the
authority competent to approve the revised financial
and other commitments obtained, before varying the
conditions.
• (c) All such changes should be in the form of an
amendment to the contract duly signed by all parties
to the contract.
GENERAL PRINCIPLES TO BE OBSERVED
• (xv) Normally no time extensions ( of delivery
scheduled or completion dates) except in events of
force majeure, or the terms and conditions include
such a provision for other reasons. Extensions so
provided may be allowed through formal amendments
to the contract duly signed by parties to the contract.
• (xvi) All contracts shall contain a provision for recovery
of liquidated damages for defaults on the part of the
contractor.
• (xvii) A warranty clause- requiring supplier to, without
charge, repair/rectify/replace defective goods; delivery
at the buyers premises.
• (xviii) A clause to reserve the right of Government to
reject goods which do not conform to the specs.
•
Thank You
An interaction on
Types of Contracts and the Distinctitive
Approaches and Methodologies in Audit
according to the type of Contracts,
interpretation of Contract Clauses
sharing the experiences
CONTRACT : DEFINITION A contract is defined as
• An agreement between two or more parties, with some
• legal binding enforceable in the court of law.
• A contract is a promise or a set of promises :
• for the breach of which, the law gives a remedy or
• the performance of which, the law in some way recognizes as
a duty.
• There are many stages involved in the formation and acceptance
of a legal contract. The basic stages of any contract includes :
proposal,
offer,
acceptance,
agreement and
consideration.
Types of Contracts
• There may be contracts for procurement of :
• Works,
• Goods,
• Services or
• Consultants/manpower
• PPP, etc
Some of the common types of contracts used in the
engineering and construction Projects are :
• Lump Sum Contract
• Cost Plus Contract
• Unit Price Contract
• Percentage (of Project cost ) or Fee
• Incentive Contracts
Lump Sum Contracts • Percentage (of Project cost ) or Fee
• Incentive Contracts
The contractor agrees to do a described and specified project
for a fixed price.
Often used in engineering contracts.
Also named "Fixed Fee Contract".
It is suitable, if the scope and schedule of the project are so
clear and sufficiently defined as to allow the consulting engineer
to estimate the project costs.
Cost Plus Contract• A contract agreement wherein the purchaser agrees
to pay the cost of all labour and materials plus an
amount for contractor overhead and profit (usually as
a percentage of the labour and material cost).
• The contracts may be specified as :
Cost + Fixed Percentage Contract
Cost + Fixed Fee Contract
Cost + Fixed Fee with Guaranteed Maximum Price
Contract
Cost + Fixed Fee with Bonus Contract
Cost + Fixed Fee with Guaranteed Maximum Price
and Bonus contract
Cost + Fixed Fee with Agreement for Sharing Any
Cost Savings contract
Cost Plus Contract• This type of contracts are favoured where the scope
of the work is indeterminate or highly uncertain and
the kinds of labour, material and equipment needed
are also uncertain.
• Under this arrangement complete records of all time
and materials spent by the contractor on the work
must be maintained.
Cost + Fixed Percentage Contract
Compensation is based on a percentage of the cost.
Cost + Fixed Fee Contract
Compensation is based on a fixed sum independent the
final project cost. The customer agrees to reimburse the
contractor's actual costs, regardless of amount, and in
addition pay a negotiated fee independent of the amount
of the actual costs.
Cost + Fixed Fee with Guaranteed Maximum Price Contract
Compensation is based on a fixed sum of money. The total project cost
will not exceed an agreed upper limit.
Cost + Fixed Fee with Bonus Contract
Compensation is based on a fixed sum of money. A bonus is given if the
project finish below budget, ahead of schedule, etc.
Cost + Fixed Fee with Guaranteed Maximum Price and Bonus
Contract
Compensation is based on a fixed sum of money. The total project cost
will not exceed an agreed upper limit and a bonus is given if the project is
finished below budget, ahead of schedule etc.
Cost + Fixed Fee with Agreement for Sharing Any Cost Savings
Contract
Compensation is based on a fixed sum of money. Any cost savings are
shared with the buyer and the contractor.
Unit Price Contract
This kind of contract is based on estimated quantities of items
included in the project and their unit prices. The final price of the
project is dependent on the quantities needed to carry out the
work.
In general this contract is only suitable for construction and
supplier projects where the different types of items, but not their
numbers, can be accurately identified in the contract documents.
It is not unusual to combine a Unit Price Contract for parts of the
project with a Lump Sum Contract or other types of contracts.
Incentive Contracts
Compensation is based on the engineering and/or contracting performance
according to an agreed target - budget, schedule and/or quality.
The two basic categories of incentive contracts:
Fixed Price Incentive Contracts (Lump Sum) :
Fixed Price Incentive Contracts are preferred when contract costs and
performance requirements are reasonably certain.
Cost Reimbursement Incentive Contracts (Cost Plus)
Cost Reimbursement Contract provides the initially negotiated fee to be
adjusted later by a formula based on the relationship of total allowable
costs to total target costs. This type of contract specifies : a target cost, a
target fee, minimum and maximum fees, and a fee adjustment formula.
After project performance, the fee payable to the contractor is determined
in accordance with the formula.
Percentage of Construction Fee Contracts
Common for engineering contracts. Compensation is
based on a percentage of the construction costs :
Planning & Architectural Works
DPRs preparations
Consultations
Designing & Drawing
Audit of ContractsBroadly Contracts relate to Procurement of :
A. Works
B. Goods
C. Services
D. Consultancy (manpower)
In PPP Mode
Accordingly,
• appropriate methods of procurement are adopted,
• contracts meeting the specific needs of the procurement are entered in to and
• Audit approaches and methodologies are decided.
We first discuss the common audit aspects and later share the Audit experience in each case.
Audit : Common Aspects
Info Analysis: Budget, Programmes and Schemes, Annual
Reports, Sanctions issued, Scrutiny of Govt Accounts received
in SAI office – especially the major payments , Internal Audit
Reports, Compliance with earlier Audits, Persistent Irregularities.
Minutes of the Project Progress/Review/ Evaluation/ Meetings
(incomplete/substantially time and cost over ran procurements,
arbitration cases, etc) , Quality Inspection Reports, Feed Backs
and Representations from Stack Holders, Media Reports, etc
Based on the initial study of the Schemes / Project Guidelines
select the Contracts and accordingly develop a strategy for
conducting contract audits.
Audit : Common Aspects
Why and what of Contract Audit
•Contract audits common in both public and private
sectors.
•There are many reasons for conducting contract
audits,
•all related to risk management.
•Perform risk analysis of contracts to determine which
ones to audit.
•Contract risks include:
Time and cost overruns;
Audit : Common Aspects
frauds; duplicate billing or billing of unrelated costs; compliance with government regulatory agencies; Abondoned WorksIncomplete procurementsSubstandard qualityOver-projections of BenefitsArbitration, etc
and many more.
Audit : Common Aspects Because of limited resources, it may be impractical or
impossible to audit all contracts. Resources may need
to be concentrated on new contractors and contracts
over a certain amount. Other factors to consider may
be the complexity of the contract, type of project,
importance or sensitivity of the project and regulatory
issues.
Decide who will conduct the audits: Assign specific
contracts to specific auditors or audit groups.
Obtain information to plan specific audits.
Audit : Common Aspects Auditors should obtain:
contract files,
budgets,
project and/or engineering plans,
accounting records
any other documents they need to plan the specific audits.
documentation of direct costs and indirect costs charged to
the contract,
records documenting compliance with contract provisions,
regulatory matters
and contract deliverables.
Audit : Common Aspects auditors should review these documents and update themselves on
the contract and to develop the audit procedures.
They should review these documents and update themselves
on the contract and to develop the audit procedures.
Auditors will need to obtain documentation of direct costs
and indirect costs charged to the contract and records
documenting compliance with contract provisions, regulatory
matters and contract deliverables.
Audit : Common Aspects They will verify billings from the contractor by
examining the contract costs incurred by the contractor.
Auditors will execute the audit procedures.
Auditors will select samples of direct and indirect costs
and test those costs to determine if they are allowable to
the contract in accordance with applicable criteria.
For government agencies, the criteria will include
government cost principles and the terms of the
contract;
for companies the criteria will be the terms of the
contract.
Audit : Common Aspects Auditors conduct an exit conference at the end of their
fieldwork.
They present the Auditee with a list of findings and issues to
be resolved.
The Auditee should be provided a reasonable amount of
time to review the list and produce any additional evidence
or information applicable to resolving the issues.
The auditors review the additional information and revise
their list of findings and issues for any that are resolved.
Auditors write the audit report, duly including the response
from the Auditee.
After the report is issued, the Auditee will agree or disagree
with the audit findings.
Audit of works Contracts
The aim of audit is to see that all works were executed within
the minimum possible cost and in accordance with the
procedure laid down for the purpose.
There are four main Stages connected with a project
clearance – which contain the contract management
problems which surface later:
1. Administrative Approval
2. Financial Sanction
3. Technical Sanction and
4. Appropriation or Re-appropriation of funds
Audit Points: contd..
Universal Audit Observations in India:
Time Over Run &
Cost Over Run Or
Efficiency : At the cost of Economy and Effectiveness
(anicuts)
Poor quality (Not yielding targeted results)
Incomplete/abandoned works; etc
Time Over Run :
Non Availability of the Project/Work Site
Change in Scope of Work – Inadequate surveys
Change in Design and Drawings – Inadequate
site/soil survey/technology-poor DPRs
Dispute with Contractor
Audit Points: contd..
Time Over Run continued :
Contractor has run away – Fin & Tech Bids /
inadequate capabilities.
For awarding work at Risk and Cost; formalities
are delayed or not completed.
Non/delayed availability of funds.
Progress monitoring mechanism not in place.
Delays in ATRs of quality monitors.
Works completed but final bill not setelled.
Cost Over Run: Adequate contractual capacity not available in the States. Award
at higher rates.
Adequate competition not generated:
e-procurement/tendering
Cost escalation due to time over run
Disputes with Contractor : Arbitration
Turn key Projects: Defective agreements/vague terms
and conditions.
LD charges are levied correctly and recovered.
Some Interesting Examples
Administrative approval (A/A): Necessity for the work by
the administrative department for Air strip but later
abandoned the work due to technical reasons .
A/A issued based on Guestimates (46/24 quarters At
Minimum possible cost) and necessary preliminary
plans (for land availability / basic amenities) not
provided.
Boulders/ Earth exacavated : for Land levelling – cost
and cartage.
Transformers procured but remained unutilized due to
change in scope of work.
Quality control (Mckinzys comparison of observations
of SQC and NQC) and action taken on the quality
related observations - effect in payment.
Maintenance – DLP –post construction : Pb case
DPRs/ Design and Drawings: To be based on proper field
and site surveys, necessary soil/field investigations
(seldom found/normally noticed at the execution stage in
the form of large deviations/variations in scope of
work/quantities)
Road alignments based on transact walk (normally
dispute with forest department/land owners)
Proper soil surveys in works (building , dams, canals
which do not come up timely or never used or
breached or washed away)
DPRs: Main problem in India. Quality
depends on accuracy of the data and facts
including technology (DPR preparation is
outsourced to consultants).
Comparison of work items and quantities
executed with those prescribed in the DPRs
(STAs view points, WBM v/s WMM, CD
works, CC works, etc.)
• Analysis of ALR and AHR in the financial bids,
justification/ markets trends (when prepared?)
• Bank guarantees genuine,
• Manintenace of contractor ledger, Inspection Book, Site
Register
• Comparison of items and quantities: between DPR & G
schedule and G schedule and MB (Normally financial
implications are checked)
• Final Bill pendency
When contractor leaves the work:
See his profile (works in hand)/financial standing
Technical evaluation
Recoveries
Invocation of BG and
Formalities for risk and cost award.
• Funds remain idle/Unspent Funds :Investment
Appropriateness of the action taken on the
observations of quality monitors
Comparison of observations of different quality
monitors
PPP
Huge infrasture being created
(roads/water/ellectricity, projects schemes etc)
their subsequent Maintenance and
Renewal
Huge funds are required and gain from the best
managerial and technical skills avalaible in the
private sector.
New ways of Financing
PPP contd….
Requirement of huge funds:
Tools for meeting funds requirement - Diferrent Models:
PPP - JVs and
Others:
BOLT (Built, Operate, Lease and
Transfer/MCA-TCS)
BOOT (Built, Operate,Own and Transfer)
BOT (Built, Operate and Transfer/TCS-
IGNOU)
SPVs (opens a company for the purpose)
PPP contd…Financing:
Toll (Estimation of Receipts & Payments/
Cost Benefit Analysis)
Cess on users who can afford (Mining and
other commercial users)
Annuity (Where Toll/Cess not possible):
Bunching to ivite financially and
technically sound big players.
Thank you