Eskom MYPD4 Revenue Application Focus on Regulatory Asset … · 2019-12-13 · Duvha u3 and...
Transcript of Eskom MYPD4 Revenue Application Focus on Regulatory Asset … · 2019-12-13 · Duvha u3 and...
Eskom MYPD4
Revenue Application
Focus on
Regulatory Asset Base,
Capital Expenditure,
Network Business
Nersa Public Hearings
Mbombela
25 January 2019
Depreciation
1
The MYPD methodology through the allowable revenue formula was applied
+ + + + + =
Primary
Energy(incl imports and
DMP)
IPPsOperating
expenditure(incl R &D)
Integrated
Demand
Management
Return on
AssetsRevenue
+
Tax &
Levies
Return on assets = % cost of capital allowed X depreciated replacement asset value
𝐴𝑅= (𝑅𝐴𝐵×𝑊𝐴𝐶𝐶)+𝐸+𝑃𝐸+𝐷+𝑅&𝐷+𝐼𝐷𝑀±𝑆𝑄𝐼+𝐿&𝑇±𝑅𝐶𝐴
Eskom allowed revenue application for 3 year period is R763 billion
Allowable Revenue (R'million) AR FormulaApplication
2019/20
Application
2020/21
Application
2021/22
Regulated Asset Base (RAB) RAB 1 268 310 1 336 120 1 401 506
WACC % ROA X -1.32% -0.21% 1.45%
Returns -16 687 -2 765 20 314
Expenditure E + 56 619 59 820 62 663
Primary energy PE + 73 386 75 876 79 561
IPPs (local) PE + 29 590 34 324 41 002
International purchases PE + 3 533 3 734 3 957
Depreciation D + 64 651 72 919 75 649
IDM I + 189 193 202
Research & Development R&D + 176 187 198
Levies & Taxes L&T + 8 272 8 198 8 147
RCA RCA +
Total R'm 219 730 252 485 291 692
Corporate Social Investment (CSI) - - 192 - 193 - 151
Total Allowable Revenue 219 537 252 292 291 542
Regulatory Asset Base (RAB)
The asset valuation is in compliance with the MYPD methodology
Outcome of the valuation of assets as at 31 March 2016
EXTRACT OF THE
MYPD
METHODOLOGY
Revaluation of existing Regulatory Asset Base
• Revaluation of the existing RAB
undertaken by independent entity
• Is based on benchmarks of similar plant
constructed globally under equitable
conditions
• Is not a factor of Eskom’s actual costs,
Eskom projections, Eskom’s overrruns
• Replacement costs are depreciated in
accordance with the age of the plant
• Replacement cost new (RCN) refers to the
cost if the plant were to be replaced with a
new plant
• Depreciated Replacement Cost (DRC) –
replacement costs are adjusted for ages of
plants to arrive at DRC values
Regulatory Asset Base determined in accordance with NERSA MYPD Methodology
Response to MYPD methodology requirements Compliance to MYPD
methodology requirements
Eskom has undertaken independent valuation exercise for
existing RAB as at 31 March 2016. The value of the RAB has
been rolled forward with assumptions on CPI for value during
application period
Yes
Have included the capex costs and owner development costs –
which are capitalised
Yes
RAB includes capex related to generation, transmission and
distribution of electricity
Yes
Costs have been capitalised, included in RAB, IDC not included Yes
Connections funded by customers excluded Yes
Working capital such as coal stockpiles included Yes
All RAB capex will be subjected to prudency reviews through the
RCA process
Yes
Composition of Regulatory Asset Base
7
-200 000
0
200 000
400 000
600 000
800 000
1 000 000
1 200 000
1 400 000
1 600 000
FY 2016 FY 2017 FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 FY 2024
Ran
d m
illi
on
Assets funded upfront Asset purchases Working capital
WUC Completed assets post 2016 Fixed assets as per valuation
8
Reconciliation of the asset valuation of R853bn in FY2016 to
the overall average RAB value of R1.3 trillion in FY2020
Items Rand (bn)
Asset Valuation as at 31 March 2016 854
Add: Inflation indexing to 2020 193
Less: Depreciation to 2020 - 214
Total for Valuated assets in FY2020 833
Add: Completed assets post 2016 251
Add: WUC balance in FY2020 177
Add: Working capital balance in FY2020 44
Add: Asset purchases balance in FY 2020 2
Less: Assets funded upfront -44
Add: Adjustment from annual closing balance to
average closing balance
5
TOTAL RAB in FY2020 (average) 1 268
Units in Extended Inoperability and Reserve Storage
9
Duvha u3 and Hendrina u3
• have experienced significant failures and are not able to return to service in the short-term.
• Have been placed in Extended Inoperability and removed from the RAB
Grootvlei, Hendrina and Komati
• Are lowest on the merit order (have the highest unit costs of production) and are thus not expected to
be required to operate to meet demand as availability of Eskom’s fleet improves and new capacity
comes on line.
• Approaching their planning end of life.
• Ten units of these stations have reached stage where significant investment (mostly Capex) is
required for them to continue operating. Have thus been shut down and placed in Reserve Storage.
• The remaining units at these 3 stations (14) will be reaching dead stop dates, where significant
investment will be required for them to continue operating, in next 4 years. They will also be shut
down and placed in Reserve Storage. 2 units are only expected to be shut down after MYPD4
period.
Units that are expected to shut down during the MYPD4 period will be removed from the RAB, based
on anticipated shutdown date.
However, these plans are based on various assumptions so should the system require these units in
future, they will be returned to service and changes will be reflected in an RCA and or in future MYPDs.
Definition: Shutdown – Unit has been brought down to zero power, taken out of installed base, skeletal staff remains for
security, ash dam maintenance and services to local communities (water & sanitation)
2 units (Duvha u3 and Hendrina u3) in Extended Inoperability10 units in Reserve Storage
10
Station Unit Capacity Shutdown
date
Duvha u3 575 MW 30/03/2014
Hendrina u3 185 MW 22/05/2018
Hendrina u1 160 MW 01/12/2017
Komati u1 91 MW 01/12/2017
Komati u2 91 MW 12/08/2018
Komati u3 84 MW 30/08/2018
Komati u6 114 MW 21/12/2017
Komati u8 114 MW 22/06/2018
Hendrina u9 185 MW 29/09/2018
Grootvlei u4 190 MW 22/09/2017
Grootvlei u5 180 MW 09/01/2018
Grootvlei u6 180 MW 01/12/2017
7 units from Grootvlei and Komati reach dead-stop dates in the next 4 years and expected to be shut down and placed in Reserve Storage
11
Station Unit Capacity Dead-stop
date
Grootvlei u1 190 MW 31/05/2019
Grootvlei u2 190 MW 08/11/2020
Grootvlei u3 190 MW 02/05/2019
Komati u4 91 MW 08/09/2021
Komati u5 91 MW 03/04/2019
Komati u7 91 MW 28/05/2019
Komati u9 114 MW 05/07/2022
Key insights
Dead-stop dates are determined from allowable turbine operating hours before complete
refurbishment is required.
For some Units, additional statutory works on pressure vessels are also required prior to
the turbine dead-stop dates.
Komati u9 expected to be shut down after MYPD4 period.
7 units from Hendrina reach their dead-stop dates in the next 4 years and are expected to be shut down and placed in Reserve Storage
12
Station Unit Capacity Dead-stop
date
Hendrina u2 190 MW 08/11/2022
Hendrina u4 190 MW 04/08/2021
Hendrina u5 190 MW 12/10/2021
Hendrina u6 190 MW 01/03/2022
Hendrina u7 158 MW 23/01/2021
Hendrina u8 190 MW 18/06/2019
Hendrina u10 185 MW 13/07/2020
Key insights
Dead-stop dates determined from allowable turbine operating hours before
complete refurbishment is required.
For some Units, additional statutory works on pressure vessels also required prior to
turbine dead-stop dates.
Hendrina u2 expected to be shut down after MYPD4 period.
Impact of excluding units in extended inoperability
and reserve storage on RAB
13
Decrease in the Average
RAB (R'million)
2019/20 2020/21 2021/22
Application 1 268 310 1 336 120 1 401 506
Revised RAB 1248 018 1 311 056 1 374 448
Decrease in the RAB (20 293) ( 25 064) (27 058)
Return on assets is kept at -1.32%, -0.21% and 1.45% as per MYPD 4 application
Above change in RAB translates into following changes in revenue requirement
Impact on the revenue
requirement (R’million)
2019/20 2020/21 2021/22
Depreciation (2 760) (3 327) (4 025)
Return on assets 267 52 (392)
Change in the revenue
requirement
(2 493) (3 275) (4 417)
Removing assets in extended inoperability and reserve storage from RAB results in:
14
Conclusion on Regulatory Asset base
The regulatory asset base was determined in accordance with MYPD methodology.
Whilst all units in extended inoperability and reserve storage have been excluded
from RAB, it is important to note that should the system require these units in future,
they will be returned to service and changes will be reflected in an RCA and or in
future MYPDs.
The units that reach shutdown date in MYPD 3 window (i.e. FY2014 to FY2018) are
not factored into MYPD 3 RCA’s as MYPD methodology only allows for capital
expenditure variances in computation of CECA. These units are: Duvha u3,
Hendrina u1, Komati u1 and 6, Grootvlei u4 and 5
Generation New Build Capex
Generation Capital Requirement FY20-22
1. New build and major projects:
Construction of Medupi and Kusile (coal power
stations) and other major projects including
environmental projects.
2. Technical plan projects:
Generating plant requires large initial
investment and significant further expenditure
to continue operations over its intended life.
The technical plan projects reflect the
modifications and improvements that may be
required to address any changes in plant
condition, operation, capacity, legislative
requirements (safety, health and environment),
primary energy supply and operational
lifespan.
3. Outages:
There are numerous cyclical maintenance
interventions required on a power station. If an
activity is required at least twice in the life of a
station and will require plant shutdown, it is
referred to as an outage.
4. Future Fuel
Coal future fuel is the capital requirement for
the cost plus coal mines.
Nuclear future fuel is the nuclear fuel purchase
costs for Koeberg
16
14 150
82 148
532
23 230
8 073
New Build projects
Renewables
Technical plan projects
Outages
Equipment&vehicles
Future fuel
Total Generation Capex
(Rm)
Application
2019/20
Application
2020/21
Application
2021/22
New build and major
projects
35 557 23 732 22 859
Outage capex 7 340 7 890 8 000
Technical plan capex 4 847 4 919 4 384
Renewables 11 39 23
Future fuel 1 597 3 301 3 175
Nuclear future fuel 605 1 186 665
Coal future fuel 992 2 115 2 510
Asset purchases 169 178 185
Total Gx License Capex-
NERSA
49 521 40 058 38 627
Geographical overview of current New Build Programme
17
Limpopo
Kwa-Zulu Natal
Mpumalanga
MEDUPI POWER STATION PROJECTDESCRIPTION: Supercritical, coal-fired power stationLOCATION: Lephalale, LimpopoCAPACITY: 4,764MW (6 x 794MW)PROJECT COST (P80): R145 bn (excl. IDC)
KUSILE POWER STATION PROJECTDESCRIPTION: Supercritical, coal-fired power station
LOCATION: Witbank, MpumalangaCAPACITY: 4,800MW (6 x 800MW)PROJECT COST (P80): R161.4 bn (excl. IDC)
INGULA PUMPED STORAGE SCHEME DESCRIPTION: Pumped Storage SchemeLOCATION: Drakensberg mountain range, near Ladysmith CAPACITY: 4 X 333 MW Units = 1,332 MWPROJECT COST (P80): R29.8bn (excl. IDC)
Gourikwa OCGT(746 MW)
Western Cape
Northern Cape
Eastern Cape
North West
• Majuba Rail Project (68km railway)• Generation Coal and Emission Projects• Majuba Silo Recovery• Return to Service Programme (3,741 MW)
Wind Facility Hydro PowerCoal-Fired Power Plant Rail Gas Power
Ankerlig OCGT(1,338MW)
TRANSMISSION (Power Delivery) ProjectsPROJECT COST: R65.2 billion (excl. IDC)
Free State
PDP Transmission Lines
• Koeberg Steam Generator Replacement Project
• Ankerlig Transmission Koeberg Second Supply (ATKSS)
• Open Cycle Gas Turbine (OCGT) dual fuel conversion
• Koeberg Unit 2 improved efficiency (30MW)
Sere Wind Facility(100MW)
Medupi Flue Gas Desulphurisation (FGD) retrofit project
Battery Storage Phase 1: 800MWhPhase 2: 640MWh
Completed project
25-Jan-19 18
17 67034 390
2 5253 580 3 790 2 090 2 435 2 300 540
37 440
Inceptionto Mar-11
Mar-12 Mar-13 Mar-14 Mar-15 Mar-16 Mar-17 Mar-18 Mar-19 Total todate
FY 18/19 target: 1 040 MVA
Substation capacity commissioned, MVA
3 268 7 470631,0
787,0 811,0 319,0 346,0 585,4 722,3 334,0
7 804FY 18/19target: 595.8km
Generation capacity commissioned, MW
5 221 535261 120 100 794
1 332
2 387 0
10 750
• To date, the construction work that has been completed has added ~ 10 750MW of capacity, ~ 7 804km oftransmission network and ~ 37 440 of MVAs
FY 18/19 target: 800 MW
2 510
Transmission and other lines built, km
A large amount of construction work has been
completed from the start of the build programme in
2005 to date…
9 312
7 804
1 508
Target Completed Remaining
Remaining construction work over the next five years until financial year 2024
19
17 132
10 750
6 382
Target Completed Remaining
MVAs Commissioned
Substations
Km Lines builtTransmission
MWs Commissioned
Megawatts
1 Target refers to the target of the total capacity expansion programme
FY
20
18
–F
Y 2
02
3
(Me
du
pi, K
usile
)
FY
20
18
–F
Y 2
02
4
FY
20
18
–F
Y 2
02
4
• Once completed by 2023FY, Eskom’s capacity
expansion programme will increase generation
capacity by 17,132MW, transmission lines by
9,312km and substation capacity by 42,850MVA.
• This will enable Eskom to provide security of
electricity supply to South African homes and
businesses, powering economic expansion and
extending electricity to millions of households
who currently rely on other fuel sources for
domestic cooking and heating.
42 850
37 440
5 410
Target Completed Remaining
A single Engineer, Procure, Construct (EPC) contract (Turnkey)
10 to 12 EPC-type contracts
Multiple packages - 30 to 40 furnish and erect packages
Multiple contracts involving 60 to 70 packages
Four contracting strategies were considered for the execution of Medupi and Kusile, ultimately pursuing a multiple packages strategy
20
• Most of the objectives were best met with multiple packages, but it also determined that the personnelresource constraints would limit the number of packages
• Nominally, the 30 to 40 package scenario was chosen
Eskom resources Meet project objectivesContracting Strategies
Least
Most
Least
Most
• Minimize life-cycle cost
• Maximize reliability
• Generate competition within construction, equipment and material markets
• Compress schedule for earlier 1st unit CO date
• Fully use available Eskom engineering personnel and other resources
• Meet/exceed BEE goals
• Maximize benefits to the SA economy
• Develop contracting model for future projects
• Shifting/managing risk
• Eskom’s depleted resource base having experience implementing generation projects of this type and magnitude
• Lack of resource depth in the South African construction and equipment supply markets that service power plant projects
• Heavy workload worldwide in the Power Industry
• Complexity of global economy and financial markets
The projects created risk-adjusted schedules to provide a more realistic view on schedule and funding, including our Priority 1 risks
21
We continue to monitor and manage our Priority 1 risks…
Stability atConstruction Sites
Partnership Agreement driven together with the external and internal stability plan
Strict monitoring of compliances by contractors and employees to agreed processes
Visibility of Employee Relations (ER) personnel on the ground External Stakeholder engagement Skills development and transfer programmes Internal and External stability plans in place
Inadequate Capacity, Productivity and / or Competency amongst Contractors
Productivity improvement initiatives, including focused contractors management
Increased on site contract management resources to improve associated processes such as claims management and contract oversight
Increased Technical Oversight Monitoring & Assurance being instituted throughout projects
Risk-adjusted schedules developed to cater for the major risks that the projects are currently facing.
It is based on the current contractor performance and risk provision for risks outside the control of the project (e.g. Weather, Political situation like National Elections), based on historical events.
A P80 schedule is provided when cost certainty is critical, the portfolio is not capital constrained, and the portfolio typically comes in under budget.
P80 refers to a 80% chance of these risks materializing.
P80 Schedule
Contractors’ non-financial viability
Obtain market/business/project intelligence on the identified high risk contracted companies.
Assess industry economic trends and perform financial analysis on the high risk companies.
Play monitoring and oversight role to identify potential related issues and assisting with the necessary mitigating actions to reduce/eliminate the impact on the business.
Inability to execute the Capital Programme
Eskom Project Life Cycle Model (PLCM) Project development readiness assessment (PDRA) Investment structures (committees) Project development and design framework / standards
Medupi Project
22
The Medupi Project near Lephalale in the Limpopo
Province is a green-fields coal-fired power plant
comprising of six units rated in total at 4 764MW
installed capacity.
Medupi incorporates super critical technology with its
boilers and turbines, which is able to operate at higher
temperatures and pressures than Eskom’s previous
generation plant, and most importantly operates with
greater efficiency, resulting in better use of natural
resources, for example, water and coal, and will have
improved environmental performance. The plant uses
direct dry-cooling due to the water scarcity in the area. In
this process, all the water will be re-used in the electricity
generation process.
Once completed, the power station will be the fourth
largest coal-fired plant and the largest dry-cooled
power station in the world. The planned operational life
of the power station is 50 years.
Unit Six (6) achieved commercial operation on the 23
August 2015, Unit Five (5) on 3 April 2017 and Unit Four
(4) on 28 Nov 2017.
PROJECT Unit
MYPD 4
Application
CO Date
Latest
Forecast
CO Date
Medupi Unit 3 31-Oct-18 30-Apr-19
Medupi Unit 2 31-May-19 30-Apr-19
Medupi Unit 1 31-May-20 30-Nov-19
Medupi
Percentage completion as at December 2018
Unit 1 Overall progress 84.54%
Unit 2 Overall progress 98.61%
Unit 3 Overall progress 100.00%
Unit 4 Overall progress 100.00%
Unit 5 Overall progress 100.00%
Unit 6 Overall progress 100.00%
23
Kusile Project is a greenfield coal fired power plant
project comprising 6 units with a total installed
capacity of 4 800 MW. The Kusile site is about 1 355
hectares in size, and is situated on the Hartbeesfontein
and Klipfontein farms in the Nkangala District of the
Mpumalanga Province.
Kusile will be the first power station in South Africa to
have Flue Gas Desulphurization (FGD) installed. FGD
is the current state of the art technology used to remove
oxides of sulphur (SOx), e.g. sulphur dioxide (SO2), from
the exhaust flue gases in power plants that burn coal or
oil. This technology is fitted as an atmospheric emission
abatement technology, in line with current international
practice, to ensure compliance with air quality standards,
especially since the power station located in a priority
airshed.
Unit One (1) achieved commercial operation on the 30
August 2017.
PROJECT Unit
MYPD 4
Application
CO Date
Latest
Forecast
CO Date
Kusile Unit 2 31-Oct-18 31-May-19
Kusile Unit 3 31-Aug-19 31-Dec-19
Kusile Unit 4 31-Dec-20 31-Dec-20
Kusile Unit 5 31-Aug-21 31-Aug-21
Kusile Unit 6 30-Jun-22 30-Jun-22
Kusile
Percentage completion as at December 2018
Unit 1 Overall progress 100.00%
Unit 2 Overall progress 98.65%
Unit 3 Overall progress 96.03%
Unit 4 Overall progress 82.19%
Unit 5 Overall progress 71.49%
Unit 6 Overall progress 62.95%
Kusile Project
Comparing costs of constructing different power plants is challenging, due to difference in size, construction time, inflation, technology, location, etc.
Overnight cost is an internationally accepted method used to compare the construction cost of different power plants on a common basis.
Includes costs associated with civils and construction, mechanical equipment, electrical work, control and instrumentation, project management and
development. Interest capitalised to the project is excluded
Is defined as the cost incurred if a power plant could be built overnight
Cost is expressed in terms of USD cost per kilowatt of installed capacity converted to the same base year, thereby enabling a like-for-like comparison. To ensure
like-for-like comparisons, international benchmarks are adjusted to a common base.
Efficiency of Eskom Generation New Build is best measured by overnight cost of construction
24
25
Power Station unit technology type was
either supercritical or ultra-supercritical
The size of the units were between
800 and 900 MW
Sufficient data was available to
make a comparison
The technology used was consistent
throughout the build (all units were
the same technology type)
Only 3 of the 22 power stations built in the same period
allowed a fair comparison with Medupi Power Station
Units constructed in the same period (2006-2015)
as Medupi unit 1 and that meet five criteria were
considered
Criteria include:
A set of four criteria was used to evaluate projects
constructed in the same period for comparison
• Basic (base) value of the project; dictated in the main by scope and price in the market.
• It is possible to include claims in this component.
• Inflationary adjustment to the basic plant cost and is applicable to the variable portion of the basic plant cost and can be in a local or foreign currency.
• CPA adjustments are driven by market volatility such as general increases in labour cost, steel prices, material cost, fuel cost etc.
• Positive or negative cost adjustment of the foreign portion of a contract.
• Calculated as the movement in cost from the tender/contract exchange rate to the spot cover rate when the foreign currency exposure is hedged and the commitment finally paid.
• Forward premium that is payable when the foreign component of a contract is hedged against foreign currency fluctuations.
• This premium is determined by adjusting the spot cover rate with the interest rate differential between SA and the foreign country. The foreign currency fluctuation risk is mitigated through hedging once the contracts are placed.
• For unplaced contracts with foreign components, the business remains exposed to currency fluctuations.
• Allocation of interest to a project during the construction phase.
• The interest allocation is calculated by applying a pre-determined interest percentage, based on Eskom’s gearing, on the project inception to date balance until the project is transferred to commercial operation.
• Cost to the owner to establish and manage the project.
• These include project management, project engineering and the utilisation of resources to oversee the project.
• Risk allowance for unknown future costs.
• Contingency forecasts are done by project management based on the perceived risk in the project.
RATE OF EXCHANGE ADJUSTMENT COST OF COVER
INTEREST DURING CONSTRUCTION (IDC)
CONTINGENCY PROVISIONOWNERS DEVELOPMENT COST
(ODC)DESIGNS
ESCALATION OR COST PRICE
ADJUSTMENT
Total Project Cost Components
26
The Medupi overnight cost are within the range of the international benchmarks provided by Lazard
and the International Energy Agency (IEA). Medupi is higher than the benchmarks for EPRI and the
World Bank. (For World Bank it is not clear if the benchmark value include or exclude FGD)27
Benchmark Medupi overnight cost of
construction excluding FGD
The Kusile overnight cost are within the range of the international benchmarks provided by Lazard and
EPRI. Kusile is higher than the benchmarks for IEA & World Bank. (For World Bank it is not clear if the
benchmark value include or exclude FGD)
28
Kusile overnight cost of construction including
FGD
Levelised cost evaluates overall cost of electricityincluding financing and fuel cost – challenge to obtain accurate benchmarks
Ad-
vantage
• Good way to evaluate the overall unit cost of
electricity from a particular type of a plant and
is thus useful to compare the economic
feasibility of different technologies
Disad-
vantage
• Direct comparisons of electricity cost per unit
are dependent on assumptions about costs,
technical performance and electricity
production over the full operational life cycle
Desc-
ription
• Calculates the present-value cost of energy
production and includes capital cost, as well
as fuel and all fixed and variable operating and
maintenance costs expressed in USD/ MWh.
Interest rates1/cost of capital, inflation and
taxation are also taken into account
Levelised Cost of Electricity (LCOE)
• Varying assumptions (technology, plant design, base year, exchange rate, etc.) and commercially sensitive numbers
• Changing/Increasing costs (rising demand for equipment; movement in commodity prices
• Contextual issues (localisation, supply chain, economic cycles/ para-meters, economies of scale)
• Life cycle operational costs, technical performance and electricity production required for calculation of LCOE (in addition to total capital cost /investment)
Challenge to obtain
consistent and accurate
benchmarks
1 Taken into account through the discount rate
The projected levelised cost for Medupi and Kusileare below available international benchmarks –comparability is a challenge
Projected levelised cost comparison, USD/MWh, as at 2016 values
KusileMedupi
Lazard
IEA
P80
Min Max
9586
EPRI
Projected levelised costs for Medupi and Kusile are below available international benchmarks.
Levelised cost numbers were not provided in the World Bank report.
Min Max
7871
Min Max
15065
Min Max
15065
Min Max
10776
Min Max
10776
Approach taken in comparable projects shows investment in front end engineering and design reduces execution time and increases schedule certainty
Medupi
(800MWx 6)
Concept to
1st Unit CO
Tata Mundra
PS India
(800MW x 5)
Concept to
1st Unit CO
Project schedule
and estimates
change resulting
in loss of
confidence
Repeatability
and forward
planning
produced better
cost and
schedule
certainty
FEED
start
Construction
start1st unit
CO
1 yr development Est. 8.5 yrs for construction
2006 2007 2015
FEED
start
Construction
start
1st unit
CO
3 yrs development 4 yrs for construction
Opole PS,
Poland
(900MW x 2)
Concept to
1st Unit CO
Forward
planning
produced better
cost and
schedule
certainty
FEED
start
Construction
start
1st unit
CO
5 yrs development 4.5 yrs for construction
GKM AG,
Germany
(900MW x 1)
Concept to
1st Unit CO
Forward
planning
produced better
cost and
schedule
certainty
FEED
start
Construction
start
1st unit
CO
4 yrs development 6 yrs for construction
Tech.
Type
Super
critical
Super
critical
Rapid
development
with shortcuts
taken in design
and
engineering
inevitably
cause
uncertainty,
design
changes,
integration
issues and
accompanying
delay and cost
escalation
Cost and
schedule
confidence
can be
achieved with
sufficient
development
time
Ultra-
super
critical
Super
critical
and
ultra-
super
critical
The programme is continuing to have a significant impact on local industry, skills, jobs, infrastructure and regional development
A large share of Medupi, Kusile
and Ingula spend goes into
the economy
(*contribution of 0,72% to
national GDP)
The build programme has fueled demand
for relevant graduates and artisans and have grown SA’s wide
required skill base of
engineers, artisans, R&D
and project management
experts
Across Medupi, Kusile, Ingula
and Power Delivery
Projects new employment opportunitieshave touched
the lives of thousands of
people
> 42 000 total employees and
contractors employed at
peak of construction
Medupi, Kusile & Ingula
supports the national & local infrastructure
E.g. roads & maintenance, trains, water,
catering & workforce supplies,
hotels, housing, water,
sanitation, local transport, social
facilities
Each project will impact the
local towns through local
spend & investment
Lephalale (Medupi) – 95%
Delmas (Kusile) – 25%
Ladysmith (Ingula) – 7%
Local
ContentLocal Skills
Development Jobs InfrastructureRegional
Development
Sufficient Front-end engineering and
development (FEED)
Funding and stakeholder plans
Governance and internal processes
Less reliance on the contractors
Additional owner’s oversight
Additional owner’s supervisory requirements
Adopt international benchmarked project
management methodologies,
processes & systems
Suitably capacitated contract management
capability
Established monitoring, oversight and assurance
function
Adequate project pipeline to prevent the
loss of skills and capabilities
Engage international asset creation
community
Improved Labour Management
33
Key lessons learned from the New Build
Programme
Eskom Emission Reduction Plan and associated costs
Legislation
• 1 April 2010, Minimum Emission Standards (MES) were published in terms of the
National Environmental Management: Air Quality Act (NEM:AQA)
• Standards took effect on 1 April 2015 (‘existing plant limits’) and 1 April 2020 (‘new
plant limits’). Existing plants to comply with new plant limits by 1 April 2020.
• Eskom was required to reduce Sulphur dioxide, particulate matter and Nitrous oxides
by 2015 and now stricter limits by 2020.
• Eskom has an emission reduction plan which is based on a phased approach which focuses on the control of particulate emissions.
• Given the high cost to control sulphur dioxide and taking into consideration the associated health impact, a cost benefit analysis and the remaining life of plant Eskom is proposing that only Medupi is retrofitted with FGD. Kusile is being commissioned with FGD.
• Eskom will submit an application for postponement, suspension or alternate limits according to the status of each power station by 31 March 2019. (two rounds of public participation took place in 2018)
35
Eskom Emission Reduction Plan
36
Power Station Retrofit 15/16 16/17 17/18 18/19 19/20 20/21 21/22 22/23 23/24 24/25 25/26 26/27 27/28 28/29 29/30 50-year life
Kusile Fully compliant
Medupi Flue Gas Desulphurisation 2064-
Majuba Low Nox Burners 2046-2051
Kendal HFPS +ESP upgrade 2038-2043
Kendal FGD-Pilot 2038-2043
Matimba FGD-Pilot 2037-2041
Kendal FGD 2038-2043
Matimba FGD 2037-2041
Matimba HFPS +ESP upgrade 2037-2041
Lethabo HFT +ESP / SO3 upgrade 2035-2040
Tutuka FFP 2035-2040
Tutuka LNB 2035-2040
Duvha (4 & 6) HFT +ESP upgrade 2030-2034
Duvha NH3 2030-2035
Matla HFT +ESP upgrade 2029-2033
Matla LNB D 2029-2033
Kriel HFPS +ESP upgrade D D D D 2026-2029
Arnot FFP installed D D D D D 2021-2029
Hendrina FFP installed SD SD SD SD SD D D D D 2020-2026
Camden FFP installed, LNB complete D D D D 2020-2023
Grootvlei FFP complete SD SD SD SD SD D D D D 2025-2028
Komati No commitments SD SD SD D D D D 2024-2028
Legend
Completed projects
Future projects
0% production 0%
Shut down/Decomissioning SD/D
Requested suspension
Legislation: Water and Ashing Facilities
• The National Waste Management Act 2008 and associated regulations require lining
for new or extended ashing facilities.
• Several power stations are required to extend or building new ashing facilities.
• Eskom has carried our several studies to ensure the most appropriate and cost
efficient liners are authorised by the Department of Environmental Affairs and
Department of Water Affairs. Decisions are expected over the next 6 – 12 months.
• Several water management projects must be implemented in accordance with the
conditions of Water Use Licenses issued to power stations.
37
Generation Emission project costs
38
Costs are based on Eskom’s proposed postponement application, if not approved the costs would
increase significantly due to the requirement to install flue gas desulphurisation at 7 power
stations@ R 20 – 30 billion per plant.
R million excl COC & IDC2017/18
Acual2018/19 2019/20 2020/21 2021/22 2022/23 2023/24
Total
19 - 23
Technical Plan Environmental Projects - Gx 14.5 327.0 544.8 1 203.9 786.9 48.0 - 2 910.6
Technical Plan Environmental Projects - New Build 943.6 1 889.9 2 949.2 2 071.7 366.0 2.0 - 7 278.8
Emissions Projects - New Build 270.1 904.5 4 267.8 6 788.2 13 092.7 14 509.8 17 743.3 39 563.0
TOTAL ENVIRONMENTAL PROJECTS 1 228.2 3 121.4 7 761.8 10 063.8 14 245.6 14 559.7 17 743.3 49 752.3
Transmission Licensee
Context & Key Aspects
• This revenue application is being made for a three year period (2019/20 –2021/22).
• This revenue application is aligned with the NERSA MYPD methodology, with aphasing-in of return on assets being applied
• It is recognized that there is a need for cost containment initiatives to limittariff impacts to customers
• Key aspects of the Transmission Revenue application includes:
• Operational Expenditure average annual escalation contained to 1.1%per annum relative to 2017/18 actual expenditure
• Capital investments of R 29.3 bn are planned for the MYPD4 period toenable new generation and customer connections and meet sustainabilityand compliance requirements
40
Transmission’s position in the electricity value chain
41
Transmission Licensee Scope includes
• Transmission Network Service Provider
• System Operator
• Grid Planning
Transmission system reliability performance
So what is a System Minute?
MW load lost x Duration in min
System annual peak in MW
System Minutes < 1: measures severity of smaller interruptions
No of Major Incidents: counts number of large interruptions of ≥1SM
42
Therefore, 1 System Minute lost = loss of entire Eskom system for 1
minute at the time of system peak
Primary KPI performance trends
Performance Improvement trends in recent years are attributed to system
strengthening (N-1), reduced number of line faults, effective maintenance execution
and human performance.
System Minutes < 1 Major Incidents
43
Transmission network service provider
Apollo is the only
HVDC transmission
scheme operational
in the country,
enabling the import of
power from
Mozambique
The Transmission
Grid consists of 168
substations and
±32 000km of
transmission lines
Maintenance is
planned based on
Asset Management
principles utilizing
specialized
equipment and skills
Committed towards
Safety, Environmental
management and
continuous
improvement
This includes
Engineering &
Project
Management to
renew and expand
the Grid
We operate,
maintain and
restore the
Transmission
Network on a
national basis
Asset age profile - the need for sustained high levels of maintenance and asset replacement
45
System Operator – balancing supply and demand
• The process starts with the day-ahead hourly demand forecast:
• Key factors are historical seasonal demand profile, forecasted renewable energy, weather patterns, day of the week, public and school holidays etc.
• In terms of the Scheduling and Dispatch Rules, thermal and hydro power plants are then optimized and dispatched based on economic merit order of each unit’s marginal cost of production, while considering system security and constraints
• Emergency resources such as gas turbines are scheduled to manage system emergencies and Ancillary services reserves are optimised in order to minimize the total cost of production
46
47
System Operator - meeting demand on a typical day
Coal
HVDC
PV
Nuclear
PS &
HydroCSP
Wind
Ramp up Ramp down
• The bulk of demand is met by coal, nuclear and HVDC imports. Coal provides the primary capability to ramp up and down during the daily load cycle.
• Pumped Storage, Hydro & OCGT’s are mainly utilized to manage peak demand
• Renewable generators continue to make a valuable contribution throughout the day
Wind generation variability over system peak – emerging trend (2017 and 2018)
48
High load factors over evening peaks in summer can be observed, dropping during the
winter months
Depreciation
The MYPD methodology was applied through the relevant allowable revenue formula
49
++=
Operating
expenditure(incl R &D)
Return on
AssetsRevenue
Return on assets = % cost of capital allowed X depreciated replacement asset value
𝐴𝑅= (𝑅𝐴𝐵×𝑊𝐴𝐶𝐶)+𝐸+𝐷±𝑆𝑄𝐼+𝐿&𝑇±𝑅𝐶𝐴
Depreciation
Review of planned operating expenditure
50
++=
Operating
expenditure(incl R &D)
Return on
AssetsRevenue
𝐴𝑅= (𝑅𝐴𝐵×𝑊𝐴𝐶𝐶)+𝐸+𝐷±𝑆𝑄𝐼+𝐿&𝑇±𝑅𝐶𝐴
Transmission operating expenditure
includes:
• Employee Benefit Costs
• Maintenance Costs
• Other operating costs
• Corporate Overheads
Transmission operating expenditure –average annual escalation of 1.1%
51
World Bank report methodology - incorrect conclusions on Tx & Dx optimal staffing levels
52
Extract - 2016
World Bank ReportExtract - 2015 Eskom
Integrated Report
• A benchmark methodology based solely on number of customers per employee is flawed
• The WB Report conclusion that optimal Eskom Transmission and Distribution (T&D)
staffing should be 9 596 is therefore erroneous
• Based on WB report data, Eskom T&D’s 6.24 employees / 100 km of line compares
favorably with benchmark cluster average of 7.22
53
Employee expenditure (R’m) and Number
of employeesThe drivers for employee benefit cost
are the following:
• Employee benefit expenses consist
of both direct & indirect expenses
(such as training & development)
and are nett of capitalization
• A driver for employee benefit cost
increases is the outcome of
negotiations concluded with Trade
Unions in 2018
The workforce will reduce over the MYPD4 period whilst balancing operational requirements and
a growth in the Grid asset base
1 443 1 538 1 520 1 573
1 644
2 182
1 938 1 851 1 820 1 802
0
500
1 000
1 500
2 000
2 500
2017/18… 2018/19… 2019/20 2020/21 2021/22
Employee benefitcost
The application considered the
tariff impact and incorporated
additional efficiency improvements
resulting in Employee Benefit costs
escalating by 3.3% on average per
annum over the 5 year period
MYPD 4
Transmission operating expenditure -employee benefit costs escalate by 3.3% p.a.
54
Transmission Maintenance cost (R’m) The key drivers for the maintenance
expenditure are:
• Increased asset base with
associated increased operating,
inspection and maintenance
workload
• A high percentage of assets are
beyond mid-life requiring increased
maintenance
• Safe operation of network with
minimum impact to environment
The escalation is contained to a moderate inflation based increase of 5.5% p.a.
Notwithstanding the increased
asset base, the revenue application
pursued efficiency improvements to
contain the escalation.
MYPD 4
729 788
827 869
902
0
100
200
300
400
500
600
700
800
900
1 000
2017/18Actual
2018/19Proj
2019/20 2020/21 2021/22
Transmission operating expenditure –maintenance costs escalation contained to 5.5% p.a.
Transmission other operating costs
55
Other operating costs (R’m) The main contributors to Other
operating costs are the following:
• The main contributors to Other
operating costs includes:
o Insurance premiums (48%) –
Reduced premium proportioned to
Transmission
o Security cost - Guarding Services;
Access Control and patrols of
substation and national key points
(15%)
o Telecommunications – monitoring
and controlling of the network from
control centers (11%)
o Fleet and Travel cost – operational
transport cost (8%)
o Facilities and Leases – properties
rental/maintenance, utilities
rates/taxes (7%)
An average annual reduction of 3.3% is projected over the 5 year period
MYPD 4
626 617
535 556 570
0
100
200
300
400
500
600
700
800
900
1 000
2017/18Actual
2018/19Proj
2019/20 2020/21 2021/22
Depreciation
Review of planned capital expenditure
56
++=
Operating
expenditure
(incl R &D)
Return on
AssetsRevenue
𝐴𝑅= (𝑅𝐴𝐵×𝑊𝐴𝐶𝐶)+𝐸+𝐷±𝑆𝑄𝐼+𝐿&𝑇±𝑅𝐶𝐴
• As per the MYPD 4 methodology, return on asset and depreciation (after assets are in commercial operation) has been included with the revenue application
• The following slides reviews planned Capital Expenditure over the MYPD4 period
Transmission Development Plan - planned capital investments
57
• The Transmission Development Plan (TDP) is published annually following consultation with NERSA, stakeholders and the public
• Public consultation was held on 26 October 2018
• The scope of the TDP includes planned capital investments in system strengthening, expansion, asset replacements, lands & rights and production equipment
• Planned capital expenditure conforms to the Grid Code investment criteria requirements
• Audits are conducted annually by NERSA to verify adherence
• A capital investment of R 29.4 bn is planned over the MYPD4 period
Transmission Development Plan - major projects planned for the period 2020 – 2029
•5858
Transmission Development Plan – planned capital expenditure of R 29.4bn over MYPD 4
• Primarily driven by reliability and strengthening requirements (+/- 54% of plan) as well as deep system strengthening for Generation and Customer connections (+/- 24% of plan)
• 12% of planned investments are for asset replacement / renewal
59
Asset replacement planning based on condition, criticality & risk
60
Plan Semi-constrained to
reflect bottle necks in the
Capital Plan value chain
• Starting point: assets identified
based on condition rolled up
per bay.
• Rolled up into substation
• Phased using criticality,
importance and impact
• Generated projects to cost and
enter into plan
In conclusion this application requires a balance between consumer interest & financial sustainability
• Eskom requires the recovery of efficient costs and reasonable return to be financially viable.
• There is a need for cost containment to limit tariff impacts on customers
• The Transmission Licensee revenue application for operational expenditure was contained well below inflation levels
• Planned capital investments are aligned with Grid Code compliance requirements and investment justification criteria
• Decisions with respect to return-on-asset and depreciation should consider Eskom’s cashflow requirements and ability to satisfy investor confidence on its ability to service such debts
61
Distribution Licensee
Distribution Licensee scope
63
The Licensee shall operate the Distribution System within the Licensed Area
of Supply subject to the provisions of the Act and the license conditions.
The Licensee shall provide a Network Service, Distribute and Supply
electricity within the Licensed Area of Supply.
The Licensee shall not discriminate between categories of Customers,
regarding access, tariff or prices, conditions of service or conditions of Supply,
except for objectively justifiable and identifiable differences approved by the
NERSA
Licencee’s position in the electricity value chain
64
Distribution is at the heart of Eskom’s customer interface, connecting new
customers and providing safe and reliable electricity to South Africans.
Distribution has connected more than 200 000 customers per annum to the
network during the past few years.
Licensee operating footprint
65
Provincial footprint
Licensee activities in providing a service to the customer
66
Wires Business
(Engineering/Network)
Network master planning
Network designing
Network Construction
Network Maintenance and
refurbishment
Network strengthening
Network Operating
Provincial stakeholder
management
Customer Service
Quotations
Connections
Debt management
Disconnections and reconnections
Availability and quality of
supply
Support energy losses
management
Outage Management
Residential
Traction
Agriculture
Commercial
Redistributors
Prepaid
Mining & Industrial
Develop & Market Products &
Services
Optimise Customer Interaction
Acquire Customers
Manage Revenue
Cycle
Network Asset
Creation
Manage Availability of Supply
Maintain Network
Value Chain
Application salient aspects
67
Operational expenditure is contained to 1% increase per annum.
Capital investments of R18.4bn to enable, capacity for future growth,
maintaining network performance and compliance requirements.
Optimise the workforce while maintaining the critical and scarce skill
requirement.
The allowable revenue in the application translates to a 15% annual
increase, with a phased-in return on assets
Key aspects of this revenue application are:
Allowable revenue applied
Depreciation
++=
Operating
expenditure(incl. IDM)
Return on AssetsRevenue
Allowable Revenue = (RAB X WACC) + E +D + IDM ± RCA
Allowable Revenue (R'millions) AR Formula2019/20
Application
2020/21
Application
2021/22
Application
Regulated Asset Base (RAB) RAB 111 391 116 895 123 063
WACC % ROA X -1.32% -0.21% 1.45%
Returns -1 466 -242 1 784
Expenditure E + 23 584 24 787 26 342
Depreciation D + 6 903 7 422 8 029
IDM I + 189 193 202
RCA RCA + 0 0 0
Total Allowable Revenue R'm 29 210 32 161 36 356
Based on the MYPD Methodology the total allowable revenue
is R97.7billion
68
Growth in network asset and customers with associated performance
69
0
5
10
15
20
25
FY2014 FY2017FY2016FY2015 FY2018
0
50
100
150
200
250
300
350
400
450
FY2017FY2014 FY2016FY2015 FY2018
55.5
51.5
54.452.6
45.8
41.9
37.0 36.238.6 38.9 38.8
30
35
40
45
50
55
60
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
SAIDI
25.424.2 24.7 25.3
23.722.2
20.2 19.720.5
18.9 18.7
10
12
14
16
18
20
22
24
26
28
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
SAIFI
55.5
51.5
54.452.6
45.8
41.9
37.0 36.238.6 38.9 38.8
30
35
40
45
50
55
60
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
SAIDI
25.424.2 24.7 25.3
23.722.2
20.2 19.720.5
18.9 18.7
10
12
14
16
18
20
22
24
26
28
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
SAIFI
320 992
349 643
300 000
310 000
320 000
330 000
340 000
350 000
360 000
2012/13 2017/18
Lines & Cables (km)
320 089
382 842
300 000
320 000
340 000
360 000
380 000
400 000
2012/13 2017/18
Number of transformers
62 753 (20%)
89 959
134 632
0
25 000
50 000
75 000
100 000
125 000
150 000
2012/13 2017/18
Installed capacity (MVA)
44 673 MVA (50%)
2012/13 2017/18
Other 139 442 138 494
Residential 4 874 004 6 120 122
300 000
2 300 000
4 300 000
6 300 000
8 300 000
Number of customers
1.2m customers (25%)
28 651km (9%)
320 992
349 643
300 000
310 000
320 000
330 000
340 000
350 000
360 000
2012/13 2017/18
Lines & Cables (km)
320 089
382 842
300 000
320 000
340 000
360 000
380 000
400 000
2012/13 2017/18
Number of transformers
62 753 (20%)
89 959
134 632
0
25 000
50 000
75 000
100 000
125 000
150 000
2012/13 2017/18
Installed capacity (MVA)
44 673 MVA (50%)
2012/13 2017/18
Other 139 442 138 494
Residential 4 874 004 6 120 122
300 000
2 300 000
4 300 000
6 300 000
8 300 000
Number of customers
1.2m customers (25%)
28 651km (9%)
320 992
349 643
300 000
310 000
320 000
330 000
340 000
350 000
360 000
2012/13 2017/18
Lines & Cables (km)
320 089
382 842
300 000
320 000
340 000
360 000
380 000
400 000
2012/13 2017/18
Number of transformers
62 753 (20%)
89 959
134 632
0
25 000
50 000
75 000
100 000
125 000
150 000
2012/13 2017/18
Installed capacity (MVA)
44 673 MVA (50%)
2012/13 2017/18
Other 139 442 138 494
Residential 4 874 004 6 120 122
300 000
2 300 000
4 300 000
6 300 000
8 300 000
Number of customers
1.2m customers (25%)
28 651km (9%)
320 992
349 643
300 000
310 000
320 000
330 000
340 000
350 000
360 000
2012/13 2017/18
Lines & Cables (km)
320 089
382 842
300 000
320 000
340 000
360 000
380 000
400 000
2012/13 2017/18
Number of transformers
62 753 (20%)
89 959
134 632
0
25 000
50 000
75 000
100 000
125 000
150 000
2012/13 2017/18
Installed capacity (MVA)
44 673 MVA (50%)
2012/13 2017/18
Other 139 442 138 494
Residential 4 874 004 6 120 122
300 000
2 300 000
4 300 000
6 300 000
8 300 000
Number of customers
1.2m customers (25%)
28 651km (9%)
Eskom Distribution
World bank average (adjusted*)
Eskom Distribution
World bank average (adjusted*)
Benchmark Performance Network Performance - Quality Growth Asset & Customer
km of network per employee
No. of customers per employee
SAIDI improved by 35% from
2008
Target = 39 hrs
SAIFI improved by 42% from
2008
Target = 20 interruptions
* World Bank benchmark omitted 78% of Eskom T&D Line Assets
Customer satisfaction
Customer Service performance outcome
70
8,0 8,49,7 9,9
0,0
2,0
4,0
6,0
8,0
10,0
12,0
FY2015 FY2016 FY2017 FY2018
Customer Care
Customer performance outcome
comments
• Enhanced MaxiCare measures
customer satisfaction levels as rated
by customers in the Agricultural,
Commercial, Industrial, Residential
Billed & Prepaid segments
• Eskom Key Care measures customer
satisfaction levels of the key industrial
/ top customers.
99,7
96,4 95,897,7
108,7
104,3107,0 105,9
85,0
90,0
95,0
100,0
105,0
110,0
FY2015 FY2016 FY2017 FY2018
Enhanced MaxiCare Key care
Targets: MaxiCare = 93.7 & Key Care = 104
Target = 8.2
71
Cost management forecast, RmLicensee costs will be managed
optimally by:
0
5 000
10 000
15 000
20 000
25 000
30 000
2018/192019/202020/212021/22
Impairment costs
Corporate cost
Other cost
Maintenance
Employee benefitcost
• Maintaining the network to deliver reliable
network performance to sustain revenue
streams
• Adequate maintenance spend in support
of regulatory compliance
• Optimise manpower cost through a
reduction of the workforce while
maintaining the critical and scarce skills.
• Improved productivity levels
• Impairments are limited to 1% of revenue
applied for.
The current impairment is 3% of
revenue. This translates to R4.4bn
over the MYPD4 period not included in
the application cost base
• The increasing cost of additional
electrification connection, to be funded
from internal efficiencies.
The Licensee intends to manage all cost optimally by limiting year on year growth below
inflation
CAGR 1.0%
Licensee Operational cost as per Methodology
72
Employee expenditure (R’m) and Number
of employeesThe drivers for employee benefit cost
are the following:
• Growth in network and customers of
approximately 9% over application period
• Sustaining operations of network and its
performance
• Customer operations in support of
improved service to the customer
• Remuneration of employees is a function
of employee numbers and annual salary
increases
The workforce is expected to reduce over the MYPD4 control period whilst balancing current
operations with a growth in customer numbers as well as satisfying customer expectations
10 454 10 290 10 541 11 033
17 710 16 841
16 198 16 027
0
2 000
4 000
6 000
8 000
10 000
12 000
14 000
16 000
18 000
20 000
2018/19 2019/20 2020/21 2021/22
Employee benefitcost
Headcount
The average growth rate of the employee
benefit cost is 1.8% per annum while the
workforce reduce by 3.3% over the
MYPD4 planning period
Employee expenditure and number of employees
Maintenance cost
73
Maintenance cost (R’m) The key drivers for the maintenance
expenditure are:
• The span of the network and ability to
respond to customer outage within the
prescribed standards
• Sustained network performance
• Quality of supply to the customer
• Servicing the growing network and new
customers to ensure supply
• Safe operations of network with minimum
impact to environment
• Regulatory compliance is entrenched
within operations
The annual growth of 6% is in line with inflation
2 682 3 000 3 348 3 549
2 284 2 264
2 232 2 366
0
1 000
2 000
3 000
4 000
5 000
6 000
7 000
2018/19 2019/20 2020/21 2021/22
Planned/Unplanned maintenance
Planned Unplanned
4 9665 264
5 5805 915
HV Network 7% MV Network
12%
LV Network5%
Substation16%
Vegetation 7%
Wood Pole 7%
Major Mtce5%
Unplanned 41%
Maintenance by category(3 years)
Planned maintenance of assets is based
on prescribed standards
Unplanned maintenance addresses
interruption of supply
Other costs
74
Other costs (R’m) The main contributors to Other
operating costs are the following:
• Insurance cost – premium and repairs
• Security cost - safeguard assets/national
key points
• Information technology – cost of providing
information systems
• Facility cost – rental of properties,
water/lights, rates/taxes and maintenance
• Fleet and Travel cost – cost of travelling
across country mainly in deep rural areas
• Telecommunications – cost to transfer
data from network control centre to
equipment
• Customer related expenses:
− Vending commission – cost paid to
agents to sell prepaid electricity on
behalf of Eskom.
− Revenue management - customer
billing and meter reading expenses
The annual growth of 5.5% is in line with inflation.
3 223
3 399
3 592
3 785
2 000
2 500
3 000
3 500
4 000
2018/19 2019/20 2020/21 2021/22
Insurance22%
Business related expenses
3%
Security cost10%
Information technology costs
6%Fleet cost
11%
Facilities cost14%
Telecoms6%
Customer related28%
Other cost by category (3 years)
75
Capital expenditure (Rm) Contributory factors for capex are:
• Enabling capacity for future growth.
• Progressing towards regulatory and
statutory requirements.
• IPP Integration and technological
advancements.
• Capital for strengthening and refurbishing
of existing networks.
• Maintaining technical performance.
• Electrification is excluded – funded by
DOE
Capital investments of R 18.4 bn to enable, capacity for future growth, maintaining network
performance and compliance requirements
3 938
5 7836 284 6 332
0
1 000
2 000
3 000
4 000
5 000
6 000
7 000
2018/19 2019/20 2020/21 2021/22
IPP Connections3% Asset Purchases
7%
Direct Customers26%
Land & Rights1%
Strengthening42%
Refurbishment21%
Capex by category (3 years)
Capital expenditure
SAIFI measures the average number of supply interruptions experienced by a connected customer per annum.
SAIDI measures the average duration of supply interruptions experienced by a connected customer per annum.
76
• Network performance is a function of capital and maintenance vested in networks
• The SAIDI/SAIFI performance over the past number of years have improved arising from capital
and maintenance spend
Network performance vs capital expenditure
77
The Licensee overall operating cost is maintained to within the inflationary increase
except for impairment that is limited to 1% of revenue.
The workforce is expected to reduce over the period whilst balancing current
operations with a growth in customer numbers as well as satisfying customer
expectations.
The capital investment programme supports the establishment of the capacity to
meet the future electricity demand while the network is maintained at an acceptable
level of reliability and performance.
Summary of Licensee’s application