Environmental Assessment
and Programmatic 4(f) Evaluation
for Old M14(Ann Arbor Rd) and
Hines Dr. Livonia, MichiganDecember 2016
Project Background InformationFeasibility Study (June 2012)
• Identified Numerous Illustrative Alternatives
• Reduced to Four Practical Alternatives
• Identified a Preferred Alternative
EA approved by FHWA Review (October 2016)
• Funding Priorities Shifted Which Caused a Delay in Schedule
• Public Comment Period November 16 through January 3rd
• Public Hearing December 1st 2016
• FONSI Anticipated in early 2017
Anticipated Schedule
FONSI anticipated in early 2017
ROW activities to begin once FONSI is received and could take at least 1 year. ROW Certification Spring of 2018
Plan Completion (100%) in May 2018
Construction beginning in the 2019 construction season (Spring)
Questions and Comments
• Court Reporter
– Private
• Comment Forms
– Fax
• Talk to Staff