National Award for Excellence in
Energy Management 2020
ICICI Bank – BOR Bhawan, Jaipur
Presented by:
Deepak Dhar – Retail Infra Head
Munish Behl – Chief Manager
Abhay Pareek- Tower Manager
August 25 - 27, 2020
-
ICICI Bank - Introduction
2
-
ICICI Bank, BOR Bhawan , Jaipur- Orientation
3
-
ICICI Bank Ltd.,BOR Bhawan,Jaipur – Floor Layouts
GF1 F2
-
ICICI Bank, BOR Bhawan, Jaipur
5
Year of
occupation1987
Area 3432 Sq.Mtr.
No. of
Workstations280
HVAC 186 TR
UPS 1 x 30 kVA
Diesel
Generator380 kVA
Connected
load300 kW
-
Load Distribution in FY 18
Type of load Load KW % Load
HVAC 68 64.77%
IT 15 14.28%
Misc 10 9.53%
Lighting 12 11.42%
Total 105 100%
-
Load Distribution as on date
Type of load Load KW % Load
HVAC 280 87.50%
IT 20 6.25%
Misc 15 4.69%
Lighting 5 1.56%
Total 320 100%
HVAC87%
IT6%
Misc5%
Lighting2%
-
SEC Reduction and Variation Trend- EPI
SEC = Total load
----------------
Total Area
22.80% improvement against FY 18
SEC FY17-18 119.64
SEC FY18-19 108.28
SEC FY19-20 97.42
-
RatingEPI
( Annual kWh / Sq. Mtr.)
1 STAR 200 - 175
2 STAR 175 - 150
3 STAR 150 - 125
4 STAR 125 - 100
5 STAR < 100
ECBC Benchmark for Building Efficiency
EPI -97.42
-
Setting Targets – Road Map
FY18
SEC
119.64
FY19
SEC
108.28
FY20
SEC
97.42
• Benchmarking
• Setting targets
• Budgeting & Planning
• Action• Approach & Target
FY 21
PUE
81
We begin with benchmarking
and set checkpoints to
monitor progress
-
Description FY18
Annual Units in Lacs 3.14
Annual Cost in Lacs 29.96
EPI 119.64
Scope to
reduce
Eliminate wastage
Non office hours
loads
Idle/redundant
equipment
Awareness to stop
Wastages
Optimise Capacity
Focus on all
equipment
Check Redundancy
Specific power
consumption of
equipment
Investment
Energy Audit
EE Equipment
Monitoring
mechanism
Rewards and
recognitions
EnCon approach & methodology
-
EnCon projects implemented in FY 2018
-
Remodeling project (First Floor and Cafeteria)– FY 2018
13
Remodeling of First floor and Cafeteria
Replaced old window AC’s with Inverter AC’s
Segregation of AC and Non AC Area
Installed LED lights
Year of action-FY17-18
Investment – Rs. 66 Lacs
Savings – 1 Lac kWh
Payback – 6.4 years
-
LED Lights
Lighting Load ( Before ) Watts 12000
Lighting Load ( After ) Watts 5000
Savings in lighting consumption kWh 23100
Savings in Rs. 231000
Investment Rs. 23000
Payback ( Months ) 12
Year of Action 17-18
-
EnCon projects implemented in FY 2019
-
Remodeling project(Ground Floor and Second Floor) – FY 2019
16
Year of action-FY18-
19Investment – Rs. 50Lacs
Savings – 1.25 Lakh kWh
Payback – 4 years
Remodeling of Ground and Second floor
Replaced old window AC’s with Inverter AC’s
Segregation of AC and Non AC Area
Installed LED lights
-
Other projects – FY 2019
17
Installation of Heat Resistant
window glass(Saint Gobain
ST167) to avoid direct heat
from Sunlight
Year of action-FY18-19
Investment – Rs. 3.5 Lacs
Savings – 0.10 Lakh kWh
Payback – 3.2 year
-
EnCon projects implemented in FY 2020
-
Installation of Hybrid IDEC Unit - FY 2020
19
Hybrid IDEC unit in Server room
Year of Action- FY 19-20
Investment – Rs. 0.50 Lakh
Savings – Rs. 1 lakh
ROI – 6 Months
Other Benefits –
• Based on Natural cooling
• Fall back in case of AC failure
• Power Saving upto 40%
-
Green wall - FY 2020
20
During the day time in peak summer, the
green façade can maintain on average a
temperature i.e 5 degree centigrade
lower than a bare wall, consequently
impacting building cooling load and
improving energy performance
Year of action – FY 19-20
Investment – Rs. 1 Lakh
Savings – Rs.1.3 Lakh
ROI- 8 Months
-
Rain Water Harvesting unit - FY 2020
21
Year of Action-FY 19-20
Investment – Rs. 0.70 Lakh
Savings – 40KL Water ( rainy season)
ROI – 7 Months
Other Benefits –
• Water is used for Horticulture
• Cleaning of basement
-
Summary of EnCon projects
22
EPI reduced from119.64 to 97.42
Sr.Description
Investment
(Lakh)
Savings(lakh/annu
m)Payback
Year of
actionNo.
1
Remodeling of Ground floor and
Canteen with AC - Non AC area
Segregation, LED Lights and
inverter AC's
66 10 78 months FY 2018
2
Remodeling of First and Second
floor with AC - Non AC area
Segregation, LED Lights and
Inverter AC's
50 12.5 48 months FY 2019
3 Roof Top Solar Installation 0 1.36 0 FY 2019
4Installation of Heat Resistant Glass
in windows3.5 0.10 35 months FY 2019
5Installtion of Hybrid IDEC unit in
server room0.50 0.10 6 months FY 2020
6 Green wall 1 1.3 8 months FY 2020
7 Rain water harvesting 0.70 0.1 7 months FY 2020
-
Plans for reduction in SEC i.e. EPI in FY 2021
23
Sr. No. Activity
1 Ecosavers on ductable Package HVAC
2Replacement of 30 KVA Hi pulse UPS with
Modular UPS
-
EPI Projection post project execution
24
119.64108.28
97.4281
0
20
40
60
80
100
120
140
FY2018 FY2019 FY2020 FY2021
EPI
-
Renewable Energy – 0.072 MW Solar Project
Roof Top Solar Power Plant
Capacity : 130 kWp
Installed in Feb 2018Roof Top Solar Power Plant
Capacity : 130 kWp
Installed in Feb 2018
Monthly Generation:
15600 kWh
Monthly Generation:
15600 kWh
Technology (Electrical)
Type of Energy
Onsite/offsite
Installed capacity
Generation million kwh
% of overall electrical energy
Electrical Solar Onsite 0.072MW 0.096KWH 32%
-
Utilization of Renewable Energy – 0.072 MW Solar
•Sourcing 0.072MW Solar power through PPA. Zero investment
•Commissioned in Nov 18
•Power generation from Nov 18 till date– 1.6 Lakh Kwh / annum
•Annual Savings – ` 6.56 Lakh
•Further reduction in GHG emissions
-
GHG emission quantification & certification
27
As a responsible Corporate,
we have quantified, verified
& certified the GHG
emissions due to Noida Sec-
16 operations
Due to lockdown, GHG
inventorisation certification
is pending
Financial Year CO2
emission (Tons)
FY 2017 364.02
FY 2018 286.36
FY 2019 247.76
FY 2020 218.18
-
Monitoring, control & resources
28
Equipment based monitoring & control – HVAC, UPS, DG,
Energy meters
Daily consumption & efficiency reporting
Monthly Energy review – Chaired by Group Head
EnCon Budget – Rs. 50 Mn p.a. ( Central )
Training & certification of Tower Manager for IGBC AP
-
29
Rooftop Solar plant used for building
Electronic Field Service Report (EFSR)
Use of low VOC paints
Use of Green Ink for fascia printing
Electronic Annual Reports
Electronic PIN generation for Credit/Debit Cards
Green Supply Chain
-
30
-
31
Regional Heads Energy Manager
ZIFH- Rajasthan
North
Tower Manager
Head - Infrastructure
Management &
services Group
EnCon Management
-
Long term vision on energy efficiency
32
By
2022
All large offices to be in 5 STAR category
Renewable energy consumption to be 15% of
annual energy requirement
Sourcing cheaper energy to reduce cost by 5%
Deploy measures / systems / processes to sustain
the current efficiency levels
Require technical support as well as supplier engagement
-