Energy Department Government of Biharenergy.bih.nic.in/docs/hydro-policy.pdf · POLICY ON...
Transcript of Energy Department Government of Biharenergy.bih.nic.in/docs/hydro-policy.pdf · POLICY ON...
( 1 )
Table of Content
1. Objective
2. Title and Enforcement
3. Scope and Coverage
4. Nodal Agency
5. Classification of Projects
6. Allocation of Projects
7. Policy Framework
8. Allotment of Land
9. Taxes and Duties
10. Tariff
11. Sale of Power
12. Wheeling /Banking Charges
13. Transmission of Power
14. Despatch
15. Incentive by Central/ State Govt
16. Time limit for executing projects
17. Due Diligence
18. Overriding Condition
19. General Condition
Prepared by BHPC
( 2 )
DRAFT
Hydro Power Policy - 2012.
Power is a critical requirement for socio economic development. Economic
growth depends on availability of adequate, reliable and quality power at competitive
rate. Bihar is on its path of progress but its sustainable growth is suffering due to non-
availability of adequate power. The per capita power consumption in the state is
around 100 units against the all India average of approx. 700 units. The total installed
capacity of generation in Bihar is around 600 MW against the average demand of 2500
MW and peak demand of 3000 MW. The state has access to 1846 MW including capacity
allocation from central sectors generating stations. The deficit in power which was
around 31 % in 2007-08 has increased to 40% in 2009-10. This is leading to rationing
of power to different categories of consumers. Govt. of Bihar is making its best effort to
increase its generating capacity to bridge the gap. In this process in additional to adding
thermal power projects; it endeavours to exploit hydro power potentials of the state
through its own agency as well as active participation of the Independent Power
Producers (IPP).
1 Objective :
Power system in Bihar is predominant by thermal power generation and the
contribution of hydro power is only 5%. In order to exploit the available renewal
source of energy, Govt. of Bihar is desirous and committed to encourage rapid
development of hydro power in the State at the earliest. The key objective of the policy
is as under.
1.1 To enhance the over all generation capacity of the state including Hydro
power
( 3 )
1.2 To obtain optimal thermal - hydro generation mix of 60:40 ratio
1.3 To encourage the participation of Independent Power Producers by offering
them best policy frame work, and support.
In order to achieve the above objective, the Govt, of Bihar had issued a policy
guideline for private sector participation for developing non-conventional energy
sources in 2003 which included policy for hydro energy. Keeping in view the fast
changing scenario of the Power sector and the guiding policies of the Central/State
Govt., it is felt necessary to review the earlier policy and bring in new Hydro Power
Policy covering projects of all sizes/capacities.
2 Title and Enforcement
2.1 This policy would be known as Bihar State Hydro-power Policy -2012.
2.2 This policy will be effective from the date of its notification.
2.3 The Govt. of Bihar may modify this policy through amendments ( if required).
However, subject to such amendments, this policy will remain valid for a
period of 5 years. All projects awarded within this period under this policy will
be governed by this policy for their entire duration of the project.
3 Scope and Coverage
3.1 The policy will be applicable for development of hydro-power projects from
micro to mega capacity. The Govt. of Bihar has already issued a policy
framework for development of new and renewable energy sources which
includes hydropower projects up to 25 MW vide Resolution dated 24.06.2011.
This policy is in line with aforesaid policy for hydropower projects up to 25 MW
capacity. However, in case of any ambiguity between the two policies, the
provisions of Hydro power policy would prevail upon policy for New and
Renewable Energy Source.
( 4 )
3.2 The policy covers aspects and process of inviting proposal in terms of
Tender/Expression Of Interest from prospective Developers, guidelines for its
evaluation, project approvals, award process and project implementation.
3.3 The policy will be applicable for new projects proposed after its notification.
3.4 The policy will be applicable for following categories of Developer desirous to
develop Hydro Power stations in the State.
3.4.1 National / international organizations,
3.4.2 Central / State Govt. undertakings,
3.4.3 Private Industries/ institutions, partnership firms/ consortium
3.4.4 Panchayati Raj Institutions/ Urban local bodies/ Co-operative and
Registered societies. desirous of install, and generate hydropower in
state.
4. Nodal Agency
At present Bihar State Hydroelectric Power Corporation (BHPC), (A Govt. of
Bihar Enterprise), registered under Company Act 1956 is responsible for
development of hydro power projects in the state.
Under Bihar State Hydro-Power Policy -2012, BHPC will be the Nodal Agency
on behalf of, Govt. of Bihar for notifying hydropower locations, inviting proposals,
examining the techno-commercial feasibility of projects (under the purview of the
State), its processing, conveying govt. approvals, approving technical proposals
and monitoring physical progress of the work. The technical appraisal for the
projects under the purview of Central Govt. will he done by the Central Electricity
Authority (CEA) as per provision of Indian Electricity Act. 2003.
( 5 )
The approval for investment proposals for projects under the purview of State
Govt will be given by BHPC and for projects under the purview of Central Govt. will
be given by an Inter-Departmental committee of the Govt. of Bihar (to be
notified separately).
The list of hydro power projects for development by Independent Power
Producer (IPP) will be notified by BHPC from time to time in its website.
However, the Developers will have option to identify/ select site at its own. In
case of new sites, Pre- feasibility reports / DPR will be prepared by the developer
and same will be submitted to BHPC for its techno-commercial appraisal/
approvals before award of sites.
5. Classification of Projects
Depending upon installed capacity, the hydro projects are classified as under:
5.1 Micro Hydro projects with installed capacity below 3 MW
5.2 Mini hydro projects with installed capacity from 3 MW to 25MW
5.3 Medium hydro projects with installed capacity above 25MW and upto 100
MW and
5.4 Big hydro projects with installed capacity beyond 100 MW.
6. Allocation of projects
6.1 All the identified potential project/sites shall be advertised through Notice
Inviting Proposals in various news papers for global invitation of bids from
eligible bidders as per the policy framework.
6.2 The projects upto 3 MW will be allocated on input cost basis and preference
will be given to developers within the states. In case of self identified projects
upto 25 MW input based cost may be allowed to the developers.
( 6 )
6.3 Allotment of identified Projects greater than 3 MW will be based on tariff
based bidding process as per guidelines issued by GoI.
6.4 Successful Bidders shall pay fixed upfront charges to Nodal Agency/Govt. of
Bihar as defined below:
Sl No. Capacity in MW Upfront payment
(lakh)/MW
1 <3 MW 5
2 3-25 MW 10
3 Between 25 and 100 MW 10 ( Max.5 crore)
4 >100 MW 10 crore (fixed)
6.5 The cost of Detailed Projects Reports and Project development charge shall
be recovered from the successful bidders.
6.6 Acceptance of offer: Government shall have power to accept or reject the
offer considering the financial viability and other parameters at its
discretion.
6.7 The Developer shall have the option for setting up the project under a Special
Purpose Vehicle (SPV) as defined in the Electricity Rules under EA 2003.
7 Policy Framework
7.1 Once approved, the developer will not be allowed to change its core structure
including equity holding and transfer its right to others entity / interested
party till the completion of the project. However, in post completion period
change in Company structure may be allowed with prior written approval
from Nodal Agency / Govt. of Bihar.
7.2 After allocation of site/ project, the developer need to sign an implementation
agreement (IA) within three months from the date of allocation with
( 7 )
mutually agreed milestone including financial closure for implementation of
the project.
7.3 The project will be allotted on the basis of tentative installed capacity as
mentioned in the notice inviting proposal and on self identified basis. The
nodal agency shall ensure that the self identified projects do not interfere
with other existing / identified projects.
7.4 In case the capacity of awarded project increases / decreases by 20% , the
award conditions will not change . But in case of higher deviation in declared
capacity i.e. beyond 20% , the developer shall be required to sign a
fresh/revised MOU/IA with the Govt. of Bihar.
7.5 The scope of work would include all aspect from concept to commissioning
and operation thereafter. The transmission system for evacuation of power
shall form part of the project cost and it will be finalised in consultation with
power distribution Company and nodal agency and this will be applicable for
micro and small hydro power projects also.
7.6 The project developed by private developers on Build – own –operate –
transfer (BOOT) model would have a validity period of 40 years from the
date of commissioning of the project and the same would revert back to the
Govt. of Bihar after the expiry of this time i.e. 40 years free of cost with all
encumbrance.
7.7 By virtue of its presence in the area , the developer company will have no
right on other proposed / identified project sites in upstream and
downstream of the water stream.
7.8 The developer shall provide 12% free power to the state as royalty. Out of
above 12%, 2% free power will be provided to the surrounding areas
/villages in the radius of 1 km from the project site as social obligation and
( 8 )
the distribution infrastructure required has to be develop by the project
developer in consultation with distribution company and nodal agency. In
case of projects upto 3 MW the quantum of free power will be 2% for social
welfare.
7.9 The developer company will meet all statutory rules and regulation likes
labour laws, safety norms, environmental laws and all norms imposed by
other local authorities from time to time.
7.10 The nodal agency or any other regulatory body of central / state Govt. will
have right to inspect the generating stations and its allied structures at
reasonable interval and time to ensure security and safety of the
installations . The regulating instructions in respect of operation of project
as well as its safety and security of the system will be binding on the
operating company failing to which the Govt. will have right to take over the
project with due compensation to developer.
7.11 In case of storage type projects , minimum quantity of water as decided by
the state Govt. shall be released in the down stream even during lean
discharge period and at the cost of generation .
8 Allotment of land
8.1 Once the project site is awarded to developer, the developer will acquire land
from its owner as per norms defined by thee government. If required, the
nodal agency will extend help in coordinating activity with Govt.
departments.
9 Taxes & Duties:
9.1 All entry tax and electricity tax will he exempted for projects upto 25 MW.
9.2 All other taxes and duties as applicable from time to time by State
Government/local bodies shall be paid by the developers.
( 9 )
10 Tariff
10.1 The tariff for sale of energy from the project shall be decided by Bihar State
Regulatory Commission through tariff based bidding in case of identified
projects >3 MW or on the basis of actual project cost in case of self identified
projects upto 25 MW and identified projects upto 3 MW. In case any
government subsidy is provided in development of project, such component
of project cost shall be excluded for determination of tariff.
10.2 In case of sale of energy to any particular bulk consumer or the definite
group of people/cooperative/society(having load requirement of 1MW and
above) the mutually agreed tariff rate between the developer company and
consumer unit shall be allowed.
11 Sale of Power :
11.1 For Micro projects upto 3 MW capacity, the developer company will have
option to consume power in the local vicinity in the capacity of decentralised
distributed generator. He will have option to feed a surplus power for any of
the local grid of Distribution Company at the rate of tariff notified by
Regulatory Commission.
11.2 For Mini hydroelectric project i.e. upto 25 MW the developer company will
have to make agreement with Distribution Company for use of its distribution
network on mutually agreed terms & conditions or they have to construct
suitable sub transmission facility to deliver the power to the nearest GSS/PSS
of the distribution company. The applicable tariff for such power shall be as
per approved rate by BERC.
11.3 The project developer may sell to third party/utilize generated power at the
place of generation or at any other place for the captive use, through BSEB
network on payment of applicable Open Access charges surcharges &
BSEB
suggested
its deletion
( 10 )
additional surcharge and any other charges as approved/notified by Bihar
Electricity Regulatory commission (BERC) and as per BERC (Terms &
Conditions for Open Access) Regulation, 2006 as amended from time to time.
11.4 A separate Power Purchase agreement in this respect shall be signed by the
IPP and Distribution Company as per provisions contained in Electricity Act,
2003 and subsequent amendment/ notifications issued by CERC/ BERC from
time to time.
11.5 For Hydro power projects above 3 MW, the BSEB shall contract to take off
minimum 60% of the total power for sale at the rate notified by Regulatory
Commission. The Developer will have the option to sell the remaining 40% of
the total power to any HT consumer.
12. Wheeling/ Banking Charges:
12.1 The infrastructure and facilities of BSEB/DISCOMs, as may be available, will
be made available to all IPPs for wheeling the generated on chargeable
basis.
12.2 Wheeling charges for wheeling the generated energy to bulk
purchaser/third party consumers inside or outside the State will be as
determined by the Bihar Electricity Regulatory Commission (BERC).
12.3 No wheeling charges are applicable in cases of sales to the BSEB/Successor
Company in case power is supplied directly to BSEB.
13 Transmission of Power
13.1 For projects above 25 MW capacity the detailed project for power
evacuation system will be indicated in the DPR and the total evacuation
system shall either be constructed by the developer company at its own
( 11 )
cost or it may be developed by the Distribution Company of the area on its
behalf on deposit basis.
13.2 BSEB will determine the specifications of the evacuation facilities required,
including the interconnection point and voltage and the same would be
specified in the project information document (PFR/DPR).
13.3 Construction and maintenance of transmission facilities up to the nearest
interconnection point as directed by the Board shall be such that
interfacing with the State grid/BSEB grid is done as per the latter's
specifications & requirements/Indian Electricity Grid Code/ Bihar Grid
Code as applicable and amended from time to time.
14 Despatch
14.1 In order to promote use of renewable sources, priority will be accorded for
hydro projects over other source of energy during preparation of
generation schedule. This point will be ensured by State Load Despatch
Centre.
15 Incentives by Central/State Government
15.1 The financial/fiscal incentives for small hydropower development available
from Ministry of Non Conventional Energy Sources, Govt. of India shall be
facilitated/extended to IPPs
16 Time Limit for Executing the Project
16.1 The IPPs shall make necessary applications for obtaining the statutory
clearances of the project and approvals of the concerned authorities shall
be responsible for completeness of all submissions within 6 months from
the date of allotment or any other period deem fit by the GOB. Failure to
( 12 )
do so within the stipulated time frame shall be treated as non-compliance
with the requirement stipulated in this paragraph.
16.2 Nodal Agency shall accord the approval of the DPR/ application within 3
months from its submission. IPP shall enter into an implementation
agreement with the nodal agency within one month from the date of
approval of the project or three months from issue of letter of intent as
the case may be.
16.3 The IPP/Users society shall achieve the financial closure within 12 months
from the date of receipt of all statutory approvals and clearances given by
the State and Central Governments or signing of the Implementation
Agreement. Financial closure would imply firm commitments for
financing the entire project, with all pre-disbursement conditions having
been fulfilled and the loan documentation being complete.
16.4 The project should be made operational within 24 to 60 months (depending
on the capacity of the project and as specified in the IA) from the date of
Financial Closure.
16.5 The failure to reach the milestone mentioned in 16.1 above will result in
automatic cancellation of the allotment of the site and forfeiture of
upfront premium amounts. No compensation would be payable to the
IPPs/Users society in such instance.
16.6 The failure to reach to milestone as in 16.2 above would result in a liability
to pay penalty by the IPP to the GOB, computed at the equivalent royalty
revenue that would have been payable to the GOB had the project met the
milestone. In case the project enjoys an exemption from royalty in the
initial years, the duration of royalty exemption would be reduced by the
period of delay.
( 13 )
16.7 The IPP may surrender the allotment back to GOB if on completion of the
DPR, within the stipulated time frame, if it has grounds to establish that
the project is not techno-economically viable. On such surrender, the GOB
would refund any premium amount paid by the IPP till the date of
surrender.
17 Due Diligences
17.1 The applicant/IPP shall be responsible for carrying out due diligence
with regard to his compliance responsibilities under various applicable
Central/State/other laws, rules and regulations, and ensure compliance
with the same.
18 Over riding condition :
18.1 Government of Bihar reserve the right to withdraw award of
project/stopped operation of project in case the pattern of use of water
changes in the locality due to municipal/irrigational /environmental
reasons etc.
18.2 The Government or its authorised representative will have right to inspect
the power stations to ensure implementation of statutory norms like
labour rules/safety/operation norms etc..
18.3 The project developer will have no right for consumptive use of water
unless it is specifically mentioned in the contract or separately allowed
by competent authority.
18.4 In case situation arises leading to any of the above condition, the State
Government will have right to takeover the power projects for operation
by Government Agency or renegotiate the terms with the Developer after
due compensation.
( 14 )
19. General Condition :
This policy supersedes all the policy guideline instructions issued in past
including earlier hydro energy policy, 2003.
Notwithstanding anything contained in the forgoing sections the Government of
Bihar reserves the right to modify/amend/relax/issue clarifications in this policy
guideline. The interpretation by Govt. of Bihar on any clause/matter contained in this
policy documents shall be final and binding to all concern.
By order of the Governor of Bihar,
Principal Secretary (Energy) Govt. of Bihar