EMTP-RV use at EPRI

30
© 2015 Electric Power Research Institute, Inc. All rights reserved. EMPT-RV/Powersys Meeting July 10, 2015 EMTP-RV use at EPRI for Open Phase Analysis

Transcript of EMTP-RV use at EPRI

Page 1: EMTP-RV use at EPRI

© 2015 Electric Power Research Institute, Inc. All rights reserved.

EMPT-RV/Powersys Meeting

July 10, 2015

EMTP-RV use at EPRI

for Open Phase

Analysis

Page 2: EMTP-RV use at EPRI

2© 2015 Electric Power Research Institute, Inc. All rights reserved.

Introduction – EPRI Research

EPRI has developed and is further developing application

guides for EMTP-RV

– (2011) Application Guide for Determining Maximum Switching

Transient Overvoltages of Overhead Lines Rated 100 kV and Above

Using Electromagnetic Transients Program (EMTP)

– (2015) Application Guide for Determining Line T-Values used for

Minimum Approach Distances Using Electromagnetic Transients

Program (EMTP)

– (2015) Application Guide for performing Open Phase Analysis Using

Electromagnetic Transients Program (EMTP)

Page 3: EMTP-RV use at EPRI

3© 2015 Electric Power Research Institute, Inc. All rights reserved.

Introduction – EPRI Research

Address many of the

technical issues associated

with detecting an open-

phase condition of a station

auxiliary transformer (SAT)

– Studied several types of

transformer types

Released 4 publicly available documents on the open-phase issue since 2012 that used

EMTP-RV.

Page 4: EMTP-RV use at EPRI

4© 2015 Electric Power Research Institute, Inc. All rights reserved.

Open Phase Modeling Inputs

Transformer model

– Knowledge of transformer type

Windings

Core Configuration

Motor Modeling

– Starting characteristics

EMTP-RV results verified with alternative software.

UTILGEN

S

P

LoadsLoads

Step-Up

XfmrOn-Site

Aux Xfmr

Off-Site

Aux Xfmr

(SAT)

Switchyard

Transfer

Switch

Open-Phase

Fault

Under-Hung

Insulator

Failure

CT/PT

Revenue

Metering

Unit

Break

Location

To SAT

To System

Page 5: EMTP-RV use at EPRI

5© 2015 Electric Power Research Institute, Inc. All rights reserved.

Problem Description

Transformers with wye-grounded connected primaries that have a zero-sequence impedance path i.e. secondary/tertiary delta or 3-legged core

Van =1pu 0°

Vbn =1pu -120°

Vcn =1pu 120°

V3 = 1pu 120°

V2 = 1pu -120°

(1pu -120°) + (1pu 120°) = (1pu 0°)*

V2 + V3 = -V1

*Recreated Voltage

(1pu 0°)*

Voltage remains undistorted even under moderate

loading conditions

Page 6: EMTP-RV use at EPRI

6© 2015 Electric Power Research Institute, Inc. All rights reserved.

Problem Transformers (No Load)

Primary Voltage (pu) Secondary Voltage (pu)

Phase A Phase B Phase C Phase A Phase B Phase C

Wye-Wye

(Shell Core)0 1.0 1.0 0 1.0 1.0

Wye-Wye

(3-Single Phase

Cores )

0 1.0 1.0 0 1.0 1.0

Wye-Wye*

(5-Legged Core)0.54 1.0 1.0 0.54 1.0 1.0

Delta-Wye

(3-Legged Core)0.5 1.0 1.0 0.5 1.0 0.5

Wye-Delta

(3-Legged Core)1.0 1.0 1.0 1.0 1.0 1.0

Wye-Wye

(3-Legged Core)1.0 1.0 1.0 1.0 1.0 1.0

Wye-Delta-Wye

(Shell Core with

Buried Delta)

1.0 1.0 1.0 1.0 1.0 1.0

Phase A opened on high side

Identified which transformer types

exhibited this issue

Page 7: EMTP-RV use at EPRI

7© 2015 Electric Power Research Institute, Inc. All rights reserved.

Motor Modeling Examples

Simulations were performed using EMTP-RV to determine if

the 6000 HP Reactor Coolant Pump 1A motor could be

started with an open phase on the high side of the station

auxiliary transformer.

Motor parameters were estimated using available nameplate

data.

Motor was started “across the line” with and without

additional motors being connected to Bus 1A.

Page 8: EMTP-RV use at EPRI

9© 2015 Electric Power Research Institute, Inc. All rights reserved.

Calculated Acceleration Times

14.5 sec

44 sec

80% Voltage

100% Voltage

Page 9: EMTP-RV use at EPRI

10© 2015 Electric Power Research Institute, Inc. All rights reserved.

Load Model

Pump Load Torque Curve

y = -3.7692x4 + 8.1145x3 - 3.7009x2 + 0.3244x + 0.3221

0

0.2

0.4

0.6

0.8

1

1.2

1.4

00.20.40.60.81

Torq

ue

(Pe

r-U

nit

)

Speed (Per-Unit)

Load Torque - Reactor Coolant Pump 1A

Page 10: EMTP-RV use at EPRI

11© 2015 Electric Power Research Institute, Inc. All rights reserved.

Model Validation

EMTP-RV Model Used for Model Validation

600' (2) 750 MCM/phase

+

R910M

0.007958

SpeedTm

+

0.5|1E15|0

?iSW2

+

10M

R14

scope

pu_load_torque

f(u) 1

Fm1

+

VwZ1

?i

4.0kVRMSLL /_0 +

600

i(t) p3

3-ph to seq

a

b

c

zero_mag

zero_rad

pos_mag

pos_rad

neg_mag

neg_rad

60Hz

tr_9

scope

I0

scope

I1

scope

I2

0.707

0.707

0.707

scope

V0

scope

V1

scope

V2

3-ph to seq

a

b

c

zero_mag

zero_rad

pos_mag

pos_rad

neg_mag

neg_rad

60Hz

tr_16v(t)

0.707

0.707

0.707

scope

pu_speed

ASMS

N

ASM1

?m

4kV

6000hp

+RL1

Load Torque

Stiff Source

4 kV

6000 HP

(parameters est.)

Page 11: EMTP-RV use at EPRI

12© 2015 Electric Power Research Institute, Inc. All rights reserved.

Model Validation (Start at 100% Voltage - 4 kV)

4300 Amps

1.8%

Acc. Time ~ 14.5 sec

Pos. Seq. Current (motor)

Page 12: EMTP-RV use at EPRI

13© 2015 Electric Power Research Institute, Inc. All rights reserved.

Model Validation (Start at 80% Voltage – 3.2 kV)

3.8%

Acc. Time ~ 48 sec

Pos. Seq. Current (motor)

Page 13: EMTP-RV use at EPRI

14© 2015 Electric Power Research Institute, Inc. All rights reserved.

System Model

Detailed time-domain

model of system was

constructed using

EMTP-RV.

Motor starting

simulations were

performed with and

without open phase and

with and without

additional motors

connected to Bus 1A.

Page 14: EMTP-RV use at EPRI

15© 2015 Electric Power Research Institute, Inc. All rights reserved.

Motor Start (Normal Conditions – No Other Motors

Connected to Bus 1A)

Pos. Seq. Current (motor)

Rotor Speed

Acc. Time ~ 17.5 sec

Page 15: EMTP-RV use at EPRI

16© 2015 Electric Power Research Institute, Inc. All rights reserved.

Motor Start (Normal Conditions – Motors Connected to

Bus 1A)

Pos. Seq. Current (motor)

Rotor Speed

Acc. Time ~ 20 sec

Page 16: EMTP-RV use at EPRI

17© 2015 Electric Power Research Institute, Inc. All rights reserved.

Motor Start (With Open Phase – No Other Motors

Connected to Bus 1A)

Pos. Seq. Current (motor)

Rotor Speed

Unable to accelerate rotor to appropriate speed!

Page 17: EMTP-RV use at EPRI

18© 2015 Electric Power Research Institute, Inc. All rights reserved.

Motor Start (With Open Phase –Motors Connected to

Bus 1A)

0.45 p.u.

Pos. Seq. Current (motor)

Rotor

Speed

Pos. Seq. Voltage (motor)

Unable to accelerate rotor!

Page 18: EMTP-RV use at EPRI

19© 2015 Electric Power Research Institute, Inc. All rights reserved.

Conclusions

The parameters of the EMTP-RV motor model were

estimated using available nameplate data.

The response of the model was compared to simulation

results provided by the manufacturer. A reasonable

comparison was obtained using the proposed model.

Simulation results (with and without additional motor load)

indicate that Reactor Coolant Pump 1A can not be started

when an open phase condition occurs on the primary side of

the station auxiliary transformer.

– Additional motors connected to Bus 1A causes additional voltage drop

at motor terminals resulting in reduced starting torque compared with

the case where no motors are connected to Bus 1A.

Page 19: EMTP-RV use at EPRI

20© 2015 Electric Power Research Institute, Inc. All rights reserved.

Fault Placement

Open-Phase A on Secondary on Winding Y

Phase A Open

Bus 1-F

Page 20: EMTP-RV use at EPRI

21© 2015 Electric Power Research Institute, Inc. All rights reserved.

Light-Load Case – Bus 1-F

Open-Phase A on Secondary on Winding Y

V12 =120 V

V12 =57 V

V23 =120 V V23 =119.03 V

V31 =120 V

V31 =62 V

Phase A Opened

Page 21: EMTP-RV use at EPRI

22© 2015 Electric Power Research Institute, Inc. All rights reserved.

Heavy-Load Case – Bus 1-F

Open-Phase A on Secondary on Winding Y

V12 =118 V

V12 =45 V

V23 = 118 V V23 =97 V

V31 = 118 V

V31 =51.4 V

Phase A Opened

Page 22: EMTP-RV use at EPRI

23© 2015 Electric Power Research Institute, Inc. All rights reserved.

Double Open-Phase Analysis

Transformer Core/Winding

Configurations

– The goal of this research was to

understand if detecting a double

open-phase condition of a station

auxiliary transformer would be

affected by its connection and/or

core configuration.

– For use in the analysis and

determining, in general, the

response of the system(s) during

a double open-phase event.

Sys IM

(Shell Core)

(5-Legged Core)

(Shell Core w/

Buried Delta)

(3-Legged Core)

Page 23: EMTP-RV use at EPRI

24© 2015 Electric Power Research Institute, Inc. All rights reserved.

No-Load Conditions

No-load conditions, both primary and secondary exhibit low voltage

conditions.

Unable to start 3-phase induction motors.

Primary Line-Ground Voltage (pu) Secondary Line-Ground Voltage (pu)

Wye-Wye

(Shell Core)0 0 1 0 0 1

Wye-Wye

(5-Legged Core)0 0.44 1 0 0.44 1

Delta-Wye

(3-Single Phase Cores)1 1 1 0 0 0

Wye-Wye

(3-Legged Core)0.5 0.5 0.99 0.86 0 0.86

Wye-Delta

(3-Single Phase Cores)0.5 0.5 0.99 0.86 0 0.86

Wye-Wye

(Shell Core with Buried

Delta)

0.5 0.5 0.99 0.86 0 0.86

Page 24: EMTP-RV use at EPRI

25© 2015 Electric Power Research Institute, Inc. All rights reserved.

Light Load (<10% Transformer Rating)

Delta – Grounded Wye (230kV:4.16kV 25 MVA )

Motors stop spinning

V1 V0 V2

Primary (H) 0 pu 0.99 pu 0 pu

Secondary (X) 0 pu 0 pu 0 pu

Van =1pu 0°

Vbn =1pu 0°

Vcn =1pu 0°

Van =0pu 0°

Vbn =0pu 0°

Vcn =0pu 0°

Page 25: EMTP-RV use at EPRI

26© 2015 Electric Power Research Institute, Inc. All rights reserved.

Van =0.95pu 0°

Vbn =0.95pu 0°

Vcn =1pu 0°

Van =0.95pu 0°

Vbn =0.95pu 0°

Vcn =1pu 0°

Light Load (<10% Transformer Rating)

Shell Core, Grounded Wye – Grounded

Wye (230kV:4.16kV 25 MVA )

Motors stop spinning

V1 V0 V2

Primary (H) 0 pu 0.97 pu 0 pu

Secondary (X) 0 pu 0.97 pu 0 pu

56 Arms

56 Arms

112 Arms

Page 26: EMTP-RV use at EPRI

27© 2015 Electric Power Research Institute, Inc. All rights reserved.

Van =0.92pu -15°

Vbn =0.84pu -121°

Vcn =1pu 120°

Van =0.99pu -39°

Vbn =0.85pu -162°

Vcn =0.90pu 93°

From

sourceTo

Loads

Light Load (<10% Transformer Rating)

3-Single Phase Cores, Grounded Wye – Delta

(230kV:4.16kV 25 MVA )

Motors keeps spinning

V1 V0 V2

Primary (H) 0.91 pu 0.01 pu 0.09 pu

Secondary (X) 0.91 pu 0 pu 0.08 pu

I1 (A) I0 (A) I2 (A) %I0/I1 %I2/I1

Primary (H) 8.3 8.3 8.3 100 100

Secondary (X) 453 0 457 0 101

to= 10sec

25 Arms25 Arms

0 Arms

0 Arms 790 Arms

5 Arms

788 Arms

Primary LG Voltage (After Open)

Secondary LG Voltage (After Open)

Sequence Currents

Sequence Voltages

Motor Speed

to= 10sec

Page 27: EMTP-RV use at EPRI

28© 2015 Electric Power Research Institute, Inc. All rights reserved.

General Conclusions

No-load conditions result in low voltage conditions

Transformers that exhibit the issues with a double open-

phase are the same transformers that exhibit the issues with

a single open-phase.

– Voltage distortion becomes greater with larger loads.

Conventional voltage relaying can be used for other

transformer configurations

Page 28: EMTP-RV use at EPRI

29© 2015 Electric Power Research Institute, Inc. All rights reserved.

Other Work Conducted at EPRI

Performed switching studies in response to OSHA’s

mandate on maximum switching transient values (T-levels)

Scope

– Identify critical parameters that drive voltage magnitudes

– Conduct sensitivity analysis across critical parameters

– Develop technical basis for categorizing lines by T-values

Scripted in EMTP-RV multiple variable perturbations

>150k simulations run.

0

0.5

1

1.5

2

2.5

3

3.5

4

0 10 20 30 40 50 60 70 80 90 100

Peak V

oltage (

pu)

Measurement Location (miles)

No MitigationClosing ResistorSurge arrestor at open circuit endSurge arrestors at both ends

Page 29: EMTP-RV use at EPRI

30© 2015 Electric Power Research Institute, Inc. All rights reserved.

Other Work Conducted at EPRI

Switching studies

Ferroresonance

Lightning / Insulation

Coordination

Control Circuits

System Imbalance

Motor Starting

Electrical cars

Distributed

Generation

Etc.

Phase B

Opened

PPAG on Phase B

Page 30: EMTP-RV use at EPRI

31© 2015 Electric Power Research Institute, Inc. All rights reserved.

Together…Shaping the Future of Electricity