Ecss m St 10c Rev.1(6march2009)
-
Upload
mazharsaed57 -
Category
Documents
-
view
223 -
download
0
Transcript of Ecss m St 10c Rev.1(6march2009)
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
1/50
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
2/50
ECSSMST10CRev.1
6March2009
2
Foreword
This Standard is one of the series of ECSS Standards intended to be applied together for the
management, engineering and product assurance in space projects and applications. ECSS is a
cooperative effort of the European SpaceAgency, national space agencies and European industry
associationsforthepurposeofdevelopingandmaintainingcommonstandards.Requirementsinthis
Standardaredefinedintermsofwhatshallbeaccomplished,ratherthanintermsofhowtoorganize
andperform thenecessarywork.Thisallowsexistingorganizational structuresandmethods tobe
appliedwheretheyareeffective,andforthestructuresandmethodstoevolveasnecessarywithout
rewritingthestandards.
This Standard has been prepared by the ECSSMST10Working Group, reviewed by the ECSS
ExecutiveSecretariatandapprovedbytheECSSTechnicalAuthority.
Disclaimer
ECSSdoesnotprovideanywarrantywhatsoever,whetherexpressed,implied,orstatutory,including,
butnotlimitedto,anywarrantyofmerchantabilityorfitnessforaparticularpurposeoranywarranty
that the contents of the item are errorfree. In no respect shall ECSS incur any liability for any
damages,including,butnotlimitedto,direct,indirect,special,orconsequentialdamagesarisingout
of,resulting from,or inanywayconnected to theuseof thisStandard,whetherornotbasedupon
warranty,contract,tort,orotherwise;whetherornotinjurywassustainedbypersonsorpropertyor
otherwise;andwhetherornotlosswassustainedfrom,oraroseoutof,theresultsof,theitem,orany
servicesthatmaybeprovidedbyECSS.
Publishedby: ESARequirementsandStandardsDivisionESTEC, P.O. Box 299,
2200 AG Noordwijk
The Netherlands
Copyright: 2009 by the European Space Agency for the members of ECSS
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
3/50
ECSSMST10CRev.1
6March2009
3
Change log
ECSSM10A
19April1996
Firstissue
ECSSM10B
13June2003
Secondissue
ECSSMST10C
31July2008
Thirdissue
This issue combines the contents of ECSSM10B, ECSSM20B and
ECSSM30A.Itsupersedesthesethreestandards.
The descriptive text of the previous standards has been combined and
rewrittentodeleteduplicationsandcorrectinconsistencies.
The requirements of ECSSM10B have been maintained with following
exceptions:
Requirements on function tree have been deleted and moved to
ECSSE10.
Requirementsonmodelmatrixhavebeendeleted.
Some requirements havebeenmoved to newly establishedDRDs (e.g.WBSandWPDRD).
Somerequirementshavebeeneditedtoeliminateinconsistencies.
The requirements of ECSSM20B have been maintained with following
exceptions:
Somerequirementshavebeendeletedbecausetheyareobvious.
Requirementsofclause5.4arecoveredbyECSSMST40.
Somerequirementshavebeeneditedtoeliminateinconsistencies.
ThecontentofECSSM30Ahasbeencompletelyupdatedandrewritten.
ECSSM
ST
10C
Rev.
1
6March2009Third
issue
revision
1
ChangeswithrespecttoversionC(31July2008)areidentifiedwithrevision
tracking.Themainchangesare:
Changed term technical specification to technical requirements
specification.
TableF1updatedtoalignitwithECSSEST10,andTableG1updatedto
identifyDRDreferences.
Insertion of missing Header 4.4.3.2.1 Overview (resp. 4.4.3.3.1
Overview)afterclausenumber4.4.3.2(resp.4.4.3.3)causingrenumbering
ofsubsequentclauses.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
4/50
ECSSMST10CRev.1
6March2009
4
Table of contents
Change log................................................................................................................. 3
Introduction................................................................................................................ 7
1 Scope....................................................................................................................... 8
2 Normative references............................................................................................. 9
3 Terms and definitions .......................................................................................... 10
3.1 Terms defined in other standards............................................................................. 10
3.2 Terms specific to the present standard .................................................................... 10
3.3 Abbreviated terms .................................................................................................... 11
4 Principles .............................................................................................................. 12
4.1 Project planning........................................................................................................ 12
4.1.1 Introduction................................................................................................. 12
4.1.2 Purpose and objectives of the project ........................................................ 12
4.1.3 Availability of and need to develop new technologies ................................ 13
4.1.4 Availability of and need to reuse existing equipments/products ................. 13
4.1.5 Availability of and need for human resources, skills and technicalfacilities....................................................................................................... 13
4.1.6 Risk assessment ........................................................................................ 13
4.1.7 Development approach .............................................................................. 13
4.1.8 Project deliverables .................................................................................... 13
4.1.9 Customer requirements and constraints..................................................... 14
4.1.10 Project requirements documents (PRD)..................................................... 14
4.1.11 Project management plan........................................................................... 14
4.2 Project organization.................................................................................................. 15
4.2.1 Introduction................................................................................................. 15
4.2.2 Organizational structure ............................................................................. 15
4.2.3 Communication and reporting .................................................................... 15
4.2.4 Audits.......................................................................................................... 15
4.3 Project breakdown structures................................................................................... 16
4.3.1 Introduction................................................................................................. 16
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
5/50
ECSSMST10CRev.1
6March2009
5
4.3.2 Function tree............................................................................................... 16
4.3.3 Specification tree ........................................................................................ 16
4.3.4 Product tree................................................................................................ 16
4.3.5 Work breakdown structure (WBS).............................................................. 17
4.3.6 Work package (WP) ................................................................................... 18
4.3.7 Organization breakdown structure (OBS)................................................... 18
4.4 Project phasing......................................................................................................... 19
4.4.1 Introduction................................................................................................. 19
4.4.2 Relationship between business agreements and project phases............... 21
4.4.3 Project phases............................................................................................ 21
4.4.4 Project specific reviews .............................................................................. 28
5 Requirements........................................................................................................ 295.1 Project planning........................................................................................................ 29
5.1.1 Overview..................................................................................................... 29
5.1.2 Requirements on customers....................................................................... 29
5.1.3 Requirements on suppliers......................................................................... 30
5.2 Project organization.................................................................................................. 30
5.2.1 Organizational structure ............................................................................. 30
5.2.2 Communication and reporting .................................................................... 31
5.2.3 Audits.......................................................................................................... 325.3 Project breakdown structures................................................................................... 33
5.4 Project phasing......................................................................................................... 34
Annex A (normative) Project management plan (PMP) DRD ............................ 35
Annex B (normative) Product tree DRD.............................................................. 38
Annex C (normative) Work breakdown structure (WBS) DRD.......................... 40
Annex D (normative) Work package (WP) description DRD ............................. 42
Annex E (normative) Progress report DRD ........................................................ 44
Annex F (informative) ECSS management branch documents delivery perreview................................................................................................................... 45
Annex G (informative) Management documents delivery (periodic orincident triggered)............................................................................................... 47
Annex H (informative) Determination of the appropriate WBS level ofdetail..................................................................................................................... 48
Bibliography............................................................................................................. 50
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
6/50
ECSSMST10CRev.1
6March2009
6
Figures
Figure 4-1: Product tree example........................................................................................... 17
Figure 4-2: WBS example ...................................................................................................... 18
Figure 4-3: Typical project life cycle....................................................................................... 19
Figure 4-4: Review life cycle .................................................................................................. 21
Tables
Table F-1 :Management Documents Delivery per Review..................................................... 46
Table G-1 : Management documents delivery (periodic or incident triggered)....................... 47
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
7/50
ECSSMST10CRev.1
6March2009
7
Introduction
Projectplanning and implementation is theproject function, encompassing a
coherentsetofprocessesforallaspectsofprojectmanagementandcontrol.
Thisisdoneby:
establishing theproject requirements and constraintsderived from the
missionstatement.
defining phases and formal milestones enabling the progress of theproject to be controlled with respect to cost, schedule and technical
objectives(i.e.projectcontrolfunction).
definingprojectbreakdownstructures,whichconstitutethecommonand
uniquereferencesystemfortheprojectmanagementto:
identifythetasksandresponsibilitiesofeachactor;
facilitatethecoherencebetweenallactivitiesofthewholeproject;
performschedulingandcostingactivities.
settingupaprojectorganizationtoperformallnecessaryactivitiesonthe
project.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
8/50
ECSSMST10CRev.1
6March2009
8
1Scope
The scopeof thisECSSStandard is limited todescribing thekeyelementsof
project planning and implementation and identifying the top level
requirements and products that together provide a coherent and integrated
projectplanningacrossthe3ECSSbranches.
WhereotherECSSmanagement,engineering,orproductassurance standardscontainmore specific and detailed requirements related to project planning,
referencesareprovidedto identifywherethesecanbefoundwithin theECSS
system.
Thisstandardmaybetailoredforthespecificcharacteristicandconstrainsofa
spaceprojectinconformancewithECSSSST00.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
9/50
ECSSMST10CRev.1
6March2009
9
2Normative references
The following normative documents contain provisions which, through
reference in this text, constitute provisions of thisECSS Standard. Fordated
references,subsequentamendmentsto,orrevisionofanyofthesepublications
donotapply,However,partiestoagreementsbasedonthisECSSStandardare
encouragedto
investigate
the
possibility
of
applying
the
more
recent
editions
of
thenormativedocuments indicatedbelow. Forundated references, the latest
editionofthepublicationreferredtoapplies.
ECSSSST0001 ECSSsystemGlossaryofterms
ECSSMST40 SpaceprojectmanagementConfigurationand
informationmanagement
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
10/50
ECSSMST10CRev.1
6March2009
10
3Terms and definitions
3.1 Terms defined in other standards
For the purpose of this Standard, the terms and definitions from
ECSSSST0001apply.
3.2 Terms specific to the present standard
3.2.1 discipline
specificareaofexpertisewithinageneralsubject
NOTE Thenameof thedisciplinenormally indicates the
typeofexpertise(e.g. intheECSSSystem,system
engineering,mechanicalengineering,softwareand
communications are disciplines within the
Engineeringdomain)
3.2.2 domain
generalareaofinterestorinfluencecoveringanumberofinterrelatedtopicsor
subareas
NOTE Thenameofadomainnormallyindicatesthearea
of interest (e.g. in the ECSS System, the
Management,Engineering,andProductAssurance
branchesrepresentthreedifferentdomains).
3.2.3 function
combination and interaction of a number of operations or processes,which
togetherachieveadefinedobjective
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
11/50
ECSSMST10CRev.1
6March2009
11
3.3 Abbreviated terms
ForthepurposesofthisStandard,theabbreviatedtermsfromECSSSST0001
andthefollowingapply.
Abbreviation Meaning
AR acceptancereview
B/L baseline
CBCP currentbaselinecostplan
CDR criticaldesignreview
CRR commissioningresultreview
DRL documentrequirementslist
EAC estimateatcompletion
EGSE electricalgroundsupportequipment
ELR
endof
life
review
ETC estimatetocompletion
FRR flightreadinessreview
GSE groundsupportequipment
ILS integratedlogisticsupport
ITT invitationtotender
LRR launchreadinessreview
MCR missioncloseoutreview
MDR missiondefinitionreview
MGSE mechanicalgroundsupportequipment
N/A notapplicable
OBCP originalbaselinecostplan
OBS organizationalbreakdownstructure
ORR operationalreadinessreview
PDR preliminarydesignreview
PMP projectmanagementplan
PRD projectrequirementsdocuments
PRR
preliminaryrequirements
review
QR qualificationreview
RFP requestforproposal
RFQ requestforquote
SRR systemrequirementsreview
WBS workbreakdownstructure
WP workpackage
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
12/50
ECSSMST10CRev.1
6March2009
12
4Principles
4.1 Project planning
4.1.1 Introduction
Projectplanningand implementationencompassesallof theprocessescarried
outinordertoplanandexecuteaspaceprojectfrominitiationtocompletionat
all levels in the customersupplier chain in a coordinated, efficient and
structuredmanner.Itisaprojectwideactivityreceivinginputsfromallproject
disciplinesandinvolvingclosecooperationacrosstheprojectdomains.
A space project typically comprises a space segment and a ground segment
whichareimplementedinparallel(seeECSSEST70).Theyrelyon,andhave
interfaceswith the launch service segment.These three segments comprise a
spacesystem.
Inprinciple,aproposal to initiatea spaceprojectcanbe raisedbyanyparty.
However,themostcommoninitiatorsare:
individual governments, or cooperation between a number of
governments;
national,orinternationalspaceagencies,eithersinglyorcollectively;
nationalorinternationalscientificcommunities;
operatorsofcommercialspacesystems.
In thisECSS standard, the top level customer isdefined as the organization
responsible for generating the top level space segment and ground segment
business
agreements
and
for
interface
arrangements
with
other
external
space
systemelements.
Thefollowingclauses4.1.2to4.1.11describethekeyelementstobeaddressed,
assessed,andbalancedwhenplanningaproject.
4.1.2 Purpose and objectives of the project
Thepurposeandobjectivesoftheprojectaredefinedbytheprojectinitiatorin
the mission statement which includes key performance parameters and
technicalandprogrammaticconstraints tobeapplied to theproject.Theyare
normallycoordinatedwiththetoplevelcustomer,ifonehasbeenassigned.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
13/50
ECSSMST10CRev.1
6March2009
13
4.1.3 Availability of and need to develop newtechnologies
This is an assessment carried out jointly by the customer and supplier to
identify the availability of scientific and technological knowhow and the
technologyneeded
to
implement
the
project.
The
result
of
this
assessment,
which canbe a significant cost and scheduledriver, is amajor input to the
assessmentofrequiredresourcesandfacilitiesandtothesubsequenttechnical
andprogrammaticriskassessment.
4.1.4 Availability of and need to reuse existingequipments/products
This is an assessment of the feasibility of reusing existing products and is
typicallycarriedoutasadirectresponsetoacustomerrequirement.Theresult
of this assessment,which also can have a significant influence on cost and
scheduleisamajorinputtotheassessmentofrequiredresourcesandfacilities
andtothesubsequenttechnicalandprogrammaticriskassessment.
4.1.5 Availability of and need for humanresources, skills and technical facilities
This isanassessment carriedoutjointlyby the customerand supplierof the
resources,skillsand facilitiesrequired to implement theproject.The resultof
thisassessmentshowsifrequiredresources,skillsandfacilitiesareadequate,or
ifadditionalskills,resources,orfacilitiesareneededtocompletetheproject.
4.1.6 Risk assessment
Theinitialassessmentsofthetechnicalandprogrammaticrisksofaprojectare
carriedoutbythecustomer,basedontheprojectinitiatorsinputswithrespect
to the purpose and objectives of the project, together with the identified
technicalandprogrammaticconstraintstobeappliedtotheproject.Theinitial
assessment is subsequently regularly expanded to include other relevant
parameters as they become available, and as the project matures.
Comprehensiveriskassessmentsareconductedateachmajorprojectreview.
4.1.7 Development approach
Thedevelopmentapproachforaprojectisjointlydefinedbythecustomerand
suppliertocomplywiththeprojectinitiatorsmissionstatement,requirements
andconstraints,andbalancing thesewith theoutcomeofparagraphs4.1.3 to
4.1.6above.
4.1.8 Project deliverables
The customer has the responsibility for defining the deliverable products,
neededtomeettheprojectinitiatorsmissionstatement,takingintoaccounttheassessmentsnotedinclauses4.1.4to4.1.7above.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
14/50
ECSSMST10CRev.1
6March2009
14
4.1.9 Customer requirements and constraints
Customerrequirementsandconstraintsarepreparedbythecustomerbasedon
theoutputs from4.1.2 to4.1.8aboveandput intoa formatsuitable fordirect
application in an invitation to tender (ITT). They address technical and
programmatic requirements, aswell as political, commercial, and industrial
constraints tobe applied to theproject and collectively represent the project
requirementsdocuments(PRD).
4.1.10 Project requirements documents (PRD)
TheprojectrequirementsdocumentsareanintegralpartofanITT,requestfor
proposal (RFP), or request for quote (RFQ) prepared and released by a
customertopotentialsuppliers.
ThePRDtypicallycomprise
Statementof
work
Technical requirements documented in Technical Requirements
Specification,asdefinedinECSSEST1006
Managementrequirements
Engineeringrequirements
Productassurancerequirements
Programmaticrequirements
Other, project specific requirements (e.g. geographical distribution,
modelphilosophytobeapplied)
Documentsrequirementslist(DRL)
Tenderrequirements
Under the ECSS system, management, engineering and product assurance
requirementsarecontainedintheM,E,andQstandards,progressivelytailored
byeachcustomerinthecustomersupplierchaintoreflectthetypeandphaseof
the project coveredby thebusiness agreement, aswell as the scope of the
supplierstasksrequiredbythePRD.
4.1.11 Project management planThe top levelprojectplan is theprojectmanagementplanwhichdefines the
projectmanagementapproachandmethodologytobeusedthroughoutthelife
cycle of the project, together with an overview of all elements of project
managementdisciplines. It includes thedefinition of the system engineering
and product assurance management approach or provides references to
separatesystemengineeringandproductassuranceplanswhichtogethermake
upthetotalplanningdocumentationusedtoimplementaproject.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
15/50
ECSSMST10CRev.1
6March2009
15
4.2 Project organization
4.2.1 Introduction
Theestablishment
of
awell
structured
and
coherent
organizational
structure
for
implementing a project at all levels in the customersupplier chain is a key
factor for ensuring an effective and efficientmanagement approach.At each
levelinthecustomersupplierchainaprojectorganizationcanbebuiltasaself
standing project team containing all necessary disciplines within the team
structureor,moreoften,canbebuiltaroundacoreprojectteamcontainingkey
project functionswithothernecessary functionsbeingprovided fromoutside
theprojectteamasexternalsupport.
Irrespectiveoftheorganizationalapproachfollowedforaproject,theelements
summarizedbelowarerelevantatalllevelsinthecustomersupplierchain.
4.2.2 Organizational structure
Itisessentialthattheprojectorganizationalstructureisarrangedtoincludeall
disciplines essential to implement the projectwithwelldefined functions as
wellasclearreportinglines,interrelationshipsandinterfaces.Allprojectactors
below the top levelcustomerandabove the lowest level supplier(s)have the
roles of suppliers and customers, and their organizational structures are
constructedtoaccommodatebothroles.
Theorganizationalstructureprovidesaclearandunambiguousdefinitionand
allocationof individual roles and responsibilities togetherwith thenecessary
authority to implement these within the internal project setup as well astowardsprojectexternalinterfaces.
4.2.3 Communication and reporting
Effectivemeans of communication are essential tools for ensuring clear and
efficient interactionbetweenallprojectactors,aswellasbetween theproject
teamand itsexternal interfaces. Information technology is theprimarymeans
for the exchange of information. Communication serves initially to provide
clarityabouttheprojectsgoalsandobjectivesandsubsequently,tosupportthe
daytodayworkoftheprojectteam.Regularreportingisanimportanttoolfor
exchanginginformationconcerningtheprogressoftheproject.
4.2.4 Audits
Audits are independent examinations to determine whether processes and
proceduresachievethespecifiedobjective.Theyareanessentialtooltoidentify
problemareas.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
16/50
ECSSMST10CRev.1
6March2009
16
4.3 Project breakdown structures
4.3.1 Introduction
Projectbreakdown
structures
provide
the
basis
for
creating
acommon
understanding between all actors. They break the project down into
manageableelementsasdescribedinthefollowingclauses4.3.2to4.3.7.
4.3.2 Function tree
Thefunctiontreeisthebreakdownofthesystemperformancesintofunctions.
Each function is decomposed into subfunctions independent of the type of
productsinvolved.Thefunctionapproachisappliedduringprojectstartup
orduringthesystemdefinitionphase.Moredetailsaboutthefunctiontreeare
giveninECSSEST10,functiontreeDRD.
4.3.3 Specification tree
The specification tree defines the hierarchical relationship of all technical
requirements specifications for thedifferentelementsofa systemorproduct.
More details about the specification tree are given in ECSSEST10,
specificationtreeDRD.
4.3.4 Product tree
Theproduct
tree
is
the
breakdown
of
the
project
into
successive
levels
of
hardware and software products or elements, articulated to perform the
functionsidentifiedinthefunctiontree.However,thefunctionandtheproduct
tree do not necessarily mirror each other. The product tree includes the
developmentmodels, theGSE, the integration tools and test equipment, and
externalitemsnecessarytovalidatetheendproductandILSitems.Itincludes
itemssubmittedtocustomerconfigurationcontrolanditemsthatarethesubject
ofa technicalrequirementsspecification.Theproduct tree forms thebasis for
theelaborationoftheprojectworkbreakdownstructure.
AnexampleofaproducttreeisshowninFigure41.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
17/50
ECSSMST10CRev.1
6March2009
17
SpaceSystem
Space Segment Ground Segment
PayloadPlatform GSEMission Control
CenterPayload Control
CenterCommunications
System
Structure
Thermal control
On-board power
supply
Attitude control
Data handling
Instrument 1 MGSE
EGSEInstrument 2
Instrument 3
Figure41:Producttreeexample
4.3.5 Work breakdown structure (WBS)
TheWBS istheprincipalstructureusedinmanagingaprojectandprovidesa
framework formanaging cost, schedule and technical content. Itdivides the
project intomanageableworkpackages,organizedaccording to thenatureof
theworkbybreaking down the totalwork tobe performed into increasing
levelsofdetail.
TheWBS is derived from the product tree, selected elements ofwhich are
extended to includesupport functions (i.e.management,engineering,product
assurance)andassociatedservices(e.g.testfacilities).
AnexampleofaWBSisshowninFigure42.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
18/50
ECSSMST10CRev.1
6March2009
18
Figure42:WBSexample
4.3.6 Work package (WP)
AWP canbe any element of theWBSdown to the lowest level that canbe
measuredandmanagedforplanning,monitoring,andcontrol.
Controlworkpackagesare identifiedby the supplierat the level in theWBS
where visibility and control is required, and for which reporting is to be
performed.Thecontrolworkpackagesrepresent thetotalworkscopeandare
agreedbythecustomer.
The work of each supplier is explicitly identified in the work breakdown
structurebyatleastonecontrolworkpackage.
4.3.7 Organization breakdown structure (OBS)
TheOBSdepictstheproposedprojectorganization,includingtheinterfaceand
contractual responsibilities, as opposed to company organizationbreakdown
structure,whichdepictsthefunctionalaspectsofthecompany.TheprojectOBS
shows the keypersonnel and the assigned responsibleparties for eachwork
packageintheWBS.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
19/50
ECSSMST10CRev.1
6March2009
19
4.4 Project phasing
4.4.1 Introduction
Thelife
cycle
of
space
projects
is
typically
divided
into
7phases,
as
follows:
Phase0 Missionanalysis/needsidentification
PhaseA Feasibility
PhaseB PreliminaryDefinition
PhaseC DetailedDefinition
PhaseD QualificationandProduction
PhaseEUtilization
PhaseFDisposal
AtypicalprojectlifecycleisillustratedinFigure43.
Project phases are closely linked to activities on system and product level.
Depending on the specific circumstances of a project and the acceptance of
involvedrisk,activitiescanoverlapprojectphases.
At the conclusion of the major activities and the related project reviews
configurationbaselinesareestablished(seeECSSMST40).
Figure43:Typicalprojectlifecycle
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
20/50
ECSSMST10CRev.1
6March2009
20
Phases0,A,andBarefocusedmainlyon
the elaboration of system functional and technical requirements and
identificationofsystemconcepts tocomplywith themissionstatement,
takingintoaccountthetechnicalandprogrammaticconstraintsidentified
bytheprojectinitiatorandtoplevelcustomer.
theidentificationofallactivitiesandresourcestobeusedtodevelopthe
spaceandgroundsegmentsoftheproject,
theinitialassessmentsoftechnicalandprogrammaticrisk,
initiationofpredevelopmentactivities.
PhasesCandDcompriseallactivitiestobeperformedinordertodevelopand
qualifythespaceandgroundsegmentsandtheirproducts.
PhaseEcomprisesallactivitiestobeperformedinordertolaunch,commission,
utilize,andmaintaintheorbitalelementsofthespacesegmentandutilizeand
maintain
the
associated
ground
segment.
PhaseFcomprisesallactivities tobeperformed inorder to safelydisposeall
productslaunchedintospaceaswellasgroundsegment.
Eachoftheaboveprojectphasesincludesendmilestonesintheformofproject
review(s), theoutcomeofwhichdetermines readinessof theproject tomove
forwardtothenextphase.
Requirements on organization and conduct of reviews are provided in
ECSSMST1001.
With the exception of the MDR which normally involves only the project
initiator, and the top level customer, all other project reviews up to and
including theAR are typically carried outby all project actors down to the
lowest level supplier in the customersupplier chain involved in the project
phasescontainingthesereviews.
FromthePRRtothePDR,thesequenceofthereviewsistopdown,starting
withthetoplevelcustomerandhistoplevelsupplier,andcontinuingdownthe
customersupplierchaintothelowestlevelsupplier.FromtheCDRtotheAR,
the sequenceof reviews is reversed to bottomup, startingwith the lowest
level supplier and its customer and continuing up through the customer
supplierchaintothe1stlevelsupplierandthetoplevelcustomer.Thissocalled
VmodelisillustratedinFigure44.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
21/50
ECSSMST10CRev.1
6March2009
21
Figure44:Reviewlifecycle
4.4.2 Relationship between business agreementsand project phases
Abusinessagreementcancoverasingleprojectphase,asequentialgroupingof
projectphasesorsubphases(e.g.phaseB1/phaseB2;phaseB2/phaseC1/phase
C2),dependingonsuch factorsas fundingavailability,competitive tendering,
schedule, perceived risk. Irrespective of the approach used for defining the
scope of individualbusiness agreements, all spaceprojects essentially follow
theclassicalprojectphases insequenceand includeallof themajorobjectives
andkeymilestonesofeachofthesephases.
4.4.3 Project phases
4.4.3.1 GeneralThe clause 4.4.3 provides an introduction and overview of the typicalmajor
tasks,associatedreviewmilestones,andreviewobjectivesforeachofthephases
inaprojectlifecycle.
4.4.3.2 Phase 0 (Mission analysis/needs identification)
4.4.3.2.1 Overview
This is mainly an activity conducted by the project initiator, the top level
customerandrepresentativesoftheendusers.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
22/50
ECSSMST10CRev.1
6March2009
22
4.4.3.2.2 Major tasks:
Elaborate the mission statement in terms of identification and
characterization of the mission needs, expected performance,
dependability and safety goals andmission operating constraintswith
respecttothephysicalandoperationalenvironment.
Developthepreliminarytechnicalrequirementsspecification.
Identifypossiblemissionconcepts.
Performpreliminaryassessmentofprogrammaticaspects supportedby
marketandeconomicstudiesasappropriate.
Performpreliminaryriskassessment.
4.4.3.2.3 Associated review
Themissiondefinitionreview(MDR)isheldattheendofphase0.
Theoutcome
of
this
review
is
used
to
judge
the
readiness
of
the
project
to
move
intophaseA.
4.4.3.2.4 Main review objective(s)
Theprimary objective of this review is to release themission statement and
assess thepreliminary technical requirements specificationandprogrammatic
aspects.
4.4.3.3 Phase A (Feasibility)
4.4.3.3.1 Overview
This ismainly an activity conductedby the top level customer and one or
several first level supplierswith the outcomebeing reported to the project
initiator,andrepresentativesoftheendusersforconsideration.
4.4.3.3.2 Major tasks
Establish the preliminarymanagement plan, system engineering plan
andproductassuranceplanfortheproject.
Elaborate possible system and operations concepts and system
architectures and compare these against the identified needs, to
determinelevelsofuncertaintyandrisks.
Establishthefunctiontree.
Assess the technical and programmatic feasibility of the possible
concepts by identifying constraints relating to implementation, costs,
schedules, organization, operations, maintenance, production and
disposal.
Identifycriticaltechnologiesandproposepredevelopmentactivities.
Quantify and characterize critical elements for technical and economic
feasibility.
Propose the system and operations concept(s) and technical solutions,
including model philosophy and verification approach, to be further
elaboratedduringPhaseB.
Elaboratetheriskassessment.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
23/50
ECSSMST10CRev.1
6March2009
23
4.4.3.3.3 Associated review
Thepreliminaryrequirementsreview(PRR)isheldattheendofPhaseA.The
outcomeofthisreviewisusedtojudgethereadinessoftheprojecttomoveinto
PhaseB.
4.4.3.3.4 Main review objective(s)
Theprimaryobjectivesofthisrevieware:
Releaseofpreliminarymanagement,engineeringandproductassurance
plans.
Releaseofthetechnicalrequirementsspecification.
Confirmationofthetechnicalandprogrammaticfeasibilityofthesystem
concept(s).
Selection of system and operations concept(s) and technical solutions,
including model philosophy and verification approach, to be carried
forwardintoPhaseB.
4.4.3.4 Phase B (Preliminary definition)
4.4.3.4.1 Major tasks
Finalize the project management, engineering and product assurance
plans.
Establishthebaselinemasterschedule.
Elaboratethebaselinecostatcompletion.
Elaboratethepreliminaryorganizationalbreakdownstructure(OBS).
Confirm technical solution(s) for the system and operations concept(s)
andtheirfeasibilitywithrespecttoprogrammaticconstraints.
Conduct tradeoff studies and select the preferred system concept,
togetherwiththepreferredtechnicalsolution(s)forthisconcept.
Establishapreliminarydesigndefinitionfortheselectedsystemconcept
andretainedtechnicalsolution(s).
Determinetheverificationprogramincludingmodelphilosophy.
Identifyanddefineexternalinterfaces.
Prepare the next level specification and related business agreementdocuments.
Initiatepredevelopmentworkoncritical technologiesorsystemdesign
areaswhenitisnecessarytoreducethedevelopmentrisks.
Initiate any longlead item procurement required to meet project
scheduleneeds.
Preparethespacedebrismitigationplanandthedisposalplan.
Conductreliabilityandsafetyassessment.
Finalize the product tree, the work breakdown structure and the
specificationtree.
Updatetheriskassessment.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
24/50
ECSSMST10CRev.1
6March2009
24
4.4.3.4.2 Associated reviews
Thereare2projectreviewsassociatedwithPhaseB.
Thesystemrequirementsreview(SRR)heldduringthecourseofPhaseB.
Thepreliminarydesign review (PDR)held at the end of PhaseB.The
outcomeof this review isused tojudge the readinessof theproject tomoveintoPhaseC.
4.4.3.4.3 Main review objectives - System requirements review
Theprimaryobjectivesofthisrevieware:
Releaseofupdatedtechnicalrequirementsspecifications.
Assessmentofthepreliminarydesigndefinition.
Assessmentofthepreliminaryverificationprogram.
4.4.3.4.4 Main review objectives Preliminary design reviewTheprimaryobjectivesofthisrevieware:
Verification of the preliminary design of the selected concept and
technicalsolutionsagainstprojectandsystemrequirements.
Releaseoffinalmanagement,engineeringandproductassuranceplans.
Releaseofproducttree,workbreakdownstructureandspecificationtree.
Releaseoftheverificationplan(includingmodelphilosophy).
4.4.3.5 Phase C (Detailed definition)
4.4.3.5.1 Major tasks
The scope and typeof tasksundertakenduring thisphase aredrivenby the
modelphilosophyselectedfortheproject,aswellastheverificationapproach
adopted.
Completionofthedetaileddesigndefinitionofthesystematalllevelsin
thecustomersupplierchain.
Production,developmenttestingandprequalificationofselectedcritical
elementsandcomponents.
Productionand
development
testing
of
engineering
models,
as
required
bytheselectedmodelphilosophyandverificationapproach.
Completionofassembly,integrationandtestplanningforthesystemand
itsconstituentparts.
Detaileddefinitionofinternalandexternalinterfaces.
Issueofpreliminaryusermanual.
Updateoftheriskassessment.
4.4.3.5.2 Associated review
Thecritical
design
review
(CDR)
is
held
at
the
end
of
phase
C.
The
outcome
of
thisreviewisusedtojudgethereadinessoftheprojecttomoveintophaseD.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
25/50
ECSSMST10CRev.1
6March2009
25
4.4.3.5.3 Main review objectives
Assessthequalificationandvalidationstatusofthecriticalprocessesand
theirreadinessfordeploymentforphaseD.
Confirmcompatibilitywithexternalinterfaces.
Releasethefinaldesign.
Releaseassembly,integrationandtestplanning.
Releaseflighthardware/softwaremanufacturing,assemblyandtesting.
Releaseofusermanual.
4.4.3.6 Phase D (Qualification and production)
4.4.3.6.1 Major tasks
Completequalificationtestingandassociatedverificationactivities.
Complete manufacturing, assembly and testing of flight
hardware/softwareandassociatedgroundsupporthardware/software.
Complete the interoperability testing between the space and ground
segment.
Prepareacceptancedatapackage.
4.4.3.6.2 Associated reviews
Thereare3projectreviewsassociatedwithphaseD
Thequalificationreview(QR)heldduringthecourseofthephase.
Theacceptancereview(AR)heldattheendofthephase.Theoutcomeof
thisreviewisusedtojudgethereadinessoftheproductfordelivery.
Theoperationalreadinessreview(ORR),heldattheendofthephase.
4.4.3.6.3 Main review objectives Qualification review
Theprimaryobjectivesofthisrevieware:
To confirm that the verification process has demonstrated that the
design,includingmargins,meetstheapplicablerequirements.
To verify that the verification record is complete at this and all lower
levelsinthecustomersupplierchain.
Toverifytheacceptabilityofallwaiversanddeviations.
Wheredevelopment encompasses theproduction of one or several recurring
products,theQRiscompletedbyafunctionalconfigurationverificationduring
which:
The first article configuration is analyzed from the viewpoint of
reproducibility.
Theproductionmasterfilesfortheseriesproductionsarereleased.
Theseriesproductiongoaheadfileisacceptedbythecustomer.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
26/50
ECSSMST10CRev.1
6March2009
26
4.4.3.6.4 Main review objectives Acceptance review
Theprimaryobjectivesofthisrevieware:
To confirm that the verification process has demonstrated that the
product is free of workmanship errors and is ready for subsequent
operationaluse.
Toverify that theacceptanceverificationrecord iscompleteat thisand
alllowerlevelsinthecustomersupplierchain.
To verify that all deliverable products are available per the approved
deliverableitemslist.
Toverify theasbuiltproductand itsconstituentcomponentsagainst
therequiredasdesignedproductanditsconstituentcomponents.
Toverifytheacceptabilityofallwaiversanddeviations.
ToverifythattheAcceptanceDataPackageiscomplete.
Toauthorizedeliveryoftheproduct.
Toreleasethecertificateofacceptance.
4.4.3.6.5 Main review objectives - Operational readiness review(ORR)
Theprimaryobjectivesofthisrevieware:
Toverifyreadinessoftheoperationalproceduresandtheircompatibility
withtheflightsystem.
Toverifyreadinessoftheoperationsteams.
Toacceptandreleasethegroundsegmentforoperations.
4.4.3.7 Phase E (Operations/utilization)
4.4.3.7.1 Major tasks
Themajortasksforthisphasevarywidelyasafunctionofthetypeofproject
concerned.Therefore,onlyageneraloverviewofactivitiesduringthisphaseis
providedhere.
Perform all activities at space and ground segment level in order to
preparethelaunch.
Conductalllaunchandearlyorbitaloperations.
Performonorbitverification(includingcommissioning)activities.
Performallonorbitoperationsinordertoachievethemissionobjectives.
Performallgroundsegmentactivitiesinordertosupportthemission.
Perform all other ground support activities in order to support the
mission.
Finalizethedisposalplan.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
27/50
ECSSMST10CRev.1
6March2009
27
4.4.3.7.2 Associated reviews
Thereare4projectreviewsassociatedwithphaseE.
Theflightreadinessreview(FRR)isheldpriortolaunch.
Thelaunchreadinessreview(LRR),heldimmediatelypriortolaunch.
Thecommissioningresultreview(CRR),heldaftercompletionoftheon
orbitcommissioningactivities.
Theendoflifereview(ELR)heldatthecompletionofthemission.
4.4.3.7.3 Main review objectives - Flight readiness review (FRR)
The flightreadinessreview isconductedprior to launch.Theobjectiveof this
reviewistoverifythattheflightandgroundsegmentsincludingallsupporting
systemssuchas trackingsystems,communicationsystemsandsafetysystems
arereadyforlaunch.
4.4.3.7.4 Main review objectives - Launch readiness review (LRR)
Thelaunchreadinessreviewisconductedjustpriortolaunch.Theobjectiveof
this review is todeclare readiness for launchof the launchvehicle, the space
and ground segments including all supporting systems such as tracking
systems, communication systems and safety systems and to provide the
authorizationtoproceedforlaunch.
4.4.3.7.5 Main review objectives - Commissioning result review (CRR)
The commissioning result review isheld at the endof the commissioning as
partof the inorbitstageverification. Itallowsdeclaring readiness forroutine
operations/utilization.
This Review is conducted following completion of a series of onorbit tests
designed to verify that all elements of the system areperformingwithin the
specified performance parameters. Successful completion of this review is
typicallyusedtomarktheformalhandoverofthesystemtotheprojectinitiator
ortothesystemoperator.
4.4.3.7.6 Main review objectives End of life review (ELR)
Toverifythatthemissionhascompleteditsusefuloperationorservice.
Toensurethatallonorbitelementsareconfiguredtoallowsafedisposal.
4.4.3.8 Phase F (Disposal)
4.4.3.8.1 Major tasks
Implementthedisposalplan.
4.4.3.8.2 Associated review
Themissioncloseoutreview(MCR)isheldattheendofthisphase.
4.4.3.8.3 Main review objectives
Toensurethatallmissiondisposalactivitiesareadequatelycompleted.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
28/50
ECSSMST10CRev.1
6March2009
28
4.4.4 Project specific reviews
Inadditiontotheprojectreviewsidentifiedabove,anddependingonthetype
ofproject, the applicablebusiness agreement and theoverall implementation
approachadopted,additionalreviewscanbeinsertedintotheprojectplanning
againstagreedsubmilestones/additionalmilestones tomeetparticularproject
needs.
Typicalexamplesofsuchreviewsare:
Detaileddesignreview (software specific review,addressed inECSSE
ST40)
Inorbitoperationsreview(addressedinECSSEST70)
Firstarticleconfigurationreview(serialproductionspecificreview)
Systemdesignreview
Systemqualificationreviewatgroundlevel(launcherspecificreview)
Systemqualificationreviewatflightlevel(launcherspecificreview)
Thesereviewsarenotfurtheraddressedinthisstandard.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
29/50
ECSSMST10CRev.1
6March2009
29
5Requirements
5.1 Project planning
5.1.1 Overview
Projectplanningrequirementsareapplicabletoallactorsofaprojectfromthe
top levelcustomerdown tothe lowest levelsupplier.Projectactorswhohave
theroleofacustomerandasuppliercarrytheresponsibilitiesassociatedwith
bothroles.Thescopeanddetailofrequirementsmadeapplicableisafunction
ofthelevelofeachactorinthecustomersupplierchain,withthefullscopeof
all requirementsapplicable to the top level supplier.Theoverall scopemade
applicable reduces, down through the customersupplier chainbutbecomes
morespecificasa functionof theroleplayedbyeachof theseactorsand the
typeofproduct(s)tobedevelopedanddeliveredbythem.
5.1.2 Requirements on customers
a. Each customer shall prepare business agreements (ITTs, RFPs, or
RFQs),includingtheprojectrequirementsdocuments(PRD)tobemade
applicablebetweenhimandhissupplier(s).
b. Each customer shall use the ECSS standards to establish the project
management, engineering and product assurance requirements
applicablefortheproject.
c. Eachcustomershallmakeapplicable tohissupplier(s)only thoseECSS
standardsrelevant to the typeandphase(s)of theprojectaddressedby
thebusiness
agreement.
d. Each customer shall specify by tailoring the minimum requirements
within theapplicable standardsnecessary forhis supplier(s) toachieve
theprojectobjectives.
e. Each customer shall approve the projectmanagement plans and key
personnelofhissupplier(s).
f. Eachcustomershallverifycomplianceofhissupplier(s)withallproject
requirementsandconstraints.
g. Each customerbelow the top level customer in the customersupplier
chain
shall
in
addition
ensure
that
planning
for
his
suppliers
is
consistent
withtheplanningrequirementsimposedonhimbyhiscustomer.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
30/50
ECSSMST10CRev.1
6March2009
30
5.1.3 Requirements on suppliers
a. Each supplier in the customersupplier chain shall prepare a project
managementplan(PMP)inconformancewithAnnexA.
b. EachsupplierinthecustomersupplierchainshallsubmitthePMPtohis
customerforapproval.
5.2 Project organization
5.2.1 Organizational structure
5.2.1.1 Requirements on customers and suppliers
a. Each customer and supplier shall define the authority for project
managementandbusinessagreementsigning.
b. If theprojecthas linkswithotherprojects,eachcustomerand supplier
shall define the responsibilities relating to the definition and the
managementofinterfaces.
c. Whereacustomer,orsupplier,employsconsultantsorotherspecialists
toassisthiminperforminghisduties,thentheroles,responsibilitiesand
authorityoftheseconsultantsandspecialistsshallbedefined.
d. When a customer supplies a product to a supplier he shall have the
responsibilityofasupplierinrespectofthatproduct.
5.2.1.2 Requirements on suppliers
a. Thesuppliershallsetuptheprojectmanagementorganizationinsucha
waythatadequateresourcesareallocatedtotheprojecttoensuretimely
completionofthebusinessagreement.
b. Thesuppliershallnominateaprojectmanagerwithaprojectteamunder
hisauthorityandreportingdirectlytohim.
c. The supplier shallensure that theprojectmanagerhas theauthority to
executealltasksneededunderthebusinessagreementwithdirectaccess
to his company management hierarchy to resolve conflicts at the
appropriatelevel.
d. Thesuppliershallidentifythekeypersonneltobedeployedonthework,
andincludethemintheprojectorganization.
e. Thesuppliershalldemonstratethatthekeypersonnelhavethenecessary
qualification,skillsandexperiencetoperformthetaskforwhichtheyare
allocated.
f. Thesuppliersprojectmanagementorganizationshallexerciseanactive
monitoringandcontrolover itsownand lower tiersuppliersactivities
and lead its lower tier suppliers in the execution of subcontracted
activitiesto
ensure
that
their
services
conform
to
the
customers
requirements.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
31/50
ECSSMST10CRev.1
6March2009
31
g. Ifasupplierisresponsibleformorethanonebusinessagreementwithin
a project, and thebusiness agreements have different customers, then
eachbusiness agreement shallbe clearly identified and accomplished
accordingtotheappropriaterelationships.
h. The first levelsuppliershallestablish,maintainanddistributeaproject
directoryincludingkeypersonnel,asaminimum.
5.2.2 Communication and reporting
5.2.2.1 Requirements on customers and suppliers
a. Thetoplevelcustomershall:
1. specifyareportingsystemfortheproject;
2. specifyanactionmonitoringsystemfortheproject.
b. Each customer and supplier in the customersupplier chain shall
implement and maintain the project reporting an action monitoring
systems.
c. Formalmeetingsbetweenthecustomerandhissupplier(s)shallbeheld
toreviewprogressagainstapprovedprojectplanningandaddressmajor
deviationsorchangesproposedtotheprojectrequirementsdocuments.
d. The frequency, location and schedule of customersupplier project
meetingsshallbeagreedbyallparticipatingparties.
e. Customersuppliermeetingsshallbebasedonanagreedwrittenagenda.
f. Achairpersonandsecretaryshallbedesignatedat thebeginningof themeeting.
g. The resultsof themeeting shallbedocumented in the agreedminutes
signedbyallpartiesinvolvedinthemeeting.
h. Agreedactionsshallbedocumentedinanactionitemlist.
i. Eachactionshallbeallocated
1. auniqueidentification,
2. theidentificationoftheorigin(e.g.meeting),
3. theinitiator,
4. thedescriptionoftheaction(clearandconcise),
5. thepersonresponsiblefortheaction,
6. thecloseoutdate,
7. thecurrentstatus,and
8. thecloseoutreference(e.g.document,letter).
j. Actionitemsshallbereviewedateachmeeting.
k. Anymattersdocumentedintheminutesofmeetinghavingimpactonthe
businessagreementshallbesubjecttothecontractchangeprocedureforimplementation.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
32/50
ECSSMST10CRev.1
6March2009
32
5.2.2.2 Requirements on suppliers
a. Thesuppliershallprepareandsubmitprogressreportstohiscustomerin
conformancewithAnnexE.
b. Thesuppliershallprepareminutesofprogressmeetingsforapprovalof
thecustomer.
c. Thesuppliershallnotifythecustomerwithinanagreedperiodoftimeof
anyeventthatcouldsignificantlyaffecttheachievementofthebusiness
agreement objectives in terms of cost, technical performance and
schedule, and any situation resulting in a substantial schedule or
planningchangedemandingimmediatecustomerinvolvement.
5.2.3 Audits
5.2.3.1 General requirementsa. Every audit performed shallbe followedby a report preparedby the
auditorandcontainingtheviewsofbothparties.
b. Theconclusionsoftheauditandthedraftreportshallbediscussedwith
thesupplier,beforefinalizationandrelease.
c. In the event of disagreement with any of the audit conclusions, the
suppliermayaddhisobservationsandcomments.
d. Thefinalauditreportshallnotbedivulgedwithouttheagreementofthe
auditedsupplier.
5.2.3.2 Requirements on customers
a. Thecustomershallnotifythesupplierinduetimeof
1. hisintentiontoperform anaudit;
2. theobjectivesandthescopeoftheaudit;
3. thedesignatedauditorandhistermsofreference;
4. theauditschedule.
5.2.3.3 Requirements on suppliers
a. The supplier shall accept tobe auditedby the customer orby a third
partyagreedbetweenthecustomerandthesupplierintheframeworkof
thebusinessagreement.
b. Thesuppliershallhavetherighttodemandthattheauditbeperformed
byathirdparty,andthatthethirdpartyobtainauthorizationeachtime
theauditnecessitatesaccess to information concerningpatent rightsor
confidentialityassociatedwithdefencesecrecy.
c. Thesuppliershallperformauditsofhisownprojectactivitiesandofthe
projectactivitiesofhislowertiersupplier(s)toverifyconformancewith
project
requirements.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
33/50
ECSSMST10CRev.1
6March2009
33
d. The supplier shall provide right of access for participation by the
customerinhisownauditsandinauditsofhislowertiersuppliers.
e. Thesuppliershallprovidehiscustomeraccess tohis facilitiesanddata
whicharerelevantintheframeofthebusinessagreement.
5.3 Project breakdown structures
a. Thesuppliershalldeveloptheproducttreeforhisproductsdowntothe
deliverable end items, incorporating the product trees of each of his
lowertiersuppliers,inconformancewithAnnexB.
b. TheproducttreeshallbeestablishedatstartofphaseBandfinalizednot
laterthanPDR.
c. The rules for product item identification shallbe uniformwithin the
project.
d. Auniqueidentificationshallbeassignedtoeachitemwithintheproduct
tree.
e. The identification shall remainunchangedduring theproduct lifetime,
unlessamodificationcausesdiscontinuationofinterchangeability.
f. Theproducttreeshallbesubjecttocustomerapproval.
g. The supplier shall maintain the product tree uptodate under
configurationcontrol.
h. Thesuppliershallestablishtheworkbreakdownstructure(WBS)forhis
workshare,incorporatingtheWBSofeachofhislowertiersuppliers,in
conformancewithAnnexC.
i. Work related to manufacturing, assembly, integration and test of all
productmodelsshallbeshownintheWBS.
j. Support functions (management, engineering, product assurance) shall
beidentifiableinconnectionwithitsrelatedproducttreeelements.
k. TheWBSshallbesubjecttocustomerapproval.
l. EachsuppliershallmaintainuptodatetheWBSforhisworkshareinthe
project.
m. Thesupplier
shall
identify
control
work
packages
based
on
the
approved
WBS,andthelevelofvisibilityrequiredbythecustomer.
n. The supplier shall establishwork package (WP) descriptions for each
workpackageshowninhisWBSinconformancewithAnnexD.
o. EachWPshallhaveasingleresponsibleWPmanager.
p. The supplier shallestablishaprojectorganizationbreakdown structure
(OBS),whichincludes.
1. theinterfaceandcontractualresponsibilitiesamongsttheinvolved
parties
2. thekey
personnel
and
the
assigned
responsible
parties
for
each
workpackageintheWBS
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
34/50
ECSSMST10CRev.1
6March2009
34
q. TheprojectOBSshallbesubmittedtothecustomerforapproval.
r. The supplier shallmaintain theapprovedOBS,keep ituptodate, and
issueittothelowertiersuppliersandthecustomer.
5.4 Project phasing
a. The customer shall organize the project into sequential phaseswhich
includeallprojectspecificreviewsanddecisionmilestones.
NOTE Phasesandreviewsaredefinedinclause4.4.3.
b. The customer shall prepare project review procedures for all project
reviews.
c. Thecustomershallensurethattheprojectreviewsofhissupplier(s)are
in linewith the topdown /bottomup sequence of the overall project
reviewplanning.
d. Thecustomershalltakethedecisiontomovefromonephasetothenext
onthebasisoftheoutcomeoftheassociatedendofphasereview.
NOTE1 Information concerning the expected delivery of
ECSSmanagementbranchdocumentsper review
isprovidedinAnnexF.
NOTE2 Information concerning additional documents
whicharedefinedasoutputsof themanagement
standardsrequirementsandwhicharenotpartof
reviewdatapackagesisprovidedinAnnexG.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
35/50
ECSSMST10CRev.1
6March2009
35
Annex A (normative)Project management plan (PMP) DRD
A.1 DRD identification
A.1.1 Requirement identification and source document
ThisDRDiscalledfromECSSMST10,requirement5.1.3a.
A.1.2 Purpose and objective
ThePMP isprepared tostate thepurposeandprovideabrief introduction to
theprojectmanagementsystem.Itcoversallaspectsofthelatter.
A.2 Expected response
A.2.1 Scope and content
Introduction
a. ThePMP shall contain adescription of the purpose, objective and the
reasonprompting itspreparation(e.g.programorprojectreferenceand
phase).
Applicableandreferencedocuments
a. The PMP shall list the applicable and reference documents used insupportofthegenerationofthedocument.
Objectivesandconstraintsoftheproject
a. ThePMPshallbrieflydescribetheobjectiveandconstraintsoftheproject
inconformancewiththeprojectrequirementsdocuments.
Projectorganization
a. The PMP shall describe the project organization approach in
conformancewith
the
requirements
as
defined
in
clause
5.2.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
36/50
ECSSMST10CRev.1
6March2009
36
Projectbreakdownstructures
a. The PMP shall describe the projectbreakdown structures approach in
conformance with the project breakdown structure requirements as
definedinclause5.3andidentifythetitleofindividualdocumentscalled
upbytheserequirements.
Configuration,informationanddocumentation
management
a. The PMP shall describe the configuration, information and
documentation management approach, as defined in ECSSMST40,
AnnexA.
b. If the configuration, information and documentation management
approach is contained in a rolledout configurationmanagement plan,
thePMPmayincludeonlyabriefdescriptiontogetherwithareferenceto
theconfiguration,informationanddocumentationmanagementplan.
Costandschedulemanagement
a. ThePMPshalldescribethecostandschedulemanagementapproach,as
definedinECSSMST60.
b. If thecostandschedulemanagementapproach isdescribed inarolled
out cost and schedulemanagementplan, thePMPmay includeonly a
brief description together with a reference to the cost and schedule
managementplan.
Integratedlogisticsupport
a. The PMP shall describe the integrated logistic support approach, as
definedinECSSMST70.
Riskmanagement
a. ThePMPshallbrieflydescribe theriskmanagementapproachwhich is
describedinmoredetailinarolledoutriskmanagementpolicyandplan,
asdefinedinECSSMST80,AnnexesAandB.
Productassurancemanagement
a. The PMP shall describe the product assurancemanagement approach,
includingtheproposedbreakdownintoPAdisciplinesandtheinterfaces
betweenthesedisciplines,asdefinedinECSSQST10,AnnexA.
b. Iftheproductassurancemanagementapproach isdescribed inarolled
outPAplan,thePMPmayincludeonlyabriefdescriptiontogetherwith
areferencetotheproductassuranceplan.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
37/50
ECSSMST10CRev.1
6March2009
37
Engineeringmanagement
a. The PMP shall describe the engineering management approach,
including theproposedbreakdown intoengineeringdisciplinesand the
interfaces between these disciplines, as defined in ECSSEST10,
AnnexD.
b. If the engineeringmanagement approach is described in a rolledout
systemengineeringplan, thePMPmay includeonlyabriefdescription
togetherwithareferencetothesystemengineeringplan.
A.2.2 Special remarks
None.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
38/50
ECSSMST10CRev.1
6March2009
38
Annex B (normative)Product tree DRD
B.1 DRD identification
B.1.1 Requirement identification and source document
ThisDRDiscalledfromECSSMST10,requirement5.3a.
B.1.2 Purpose and objective
Theobjectiveoftheproducttreedocumentistodescribe,inasingledocument,
thehierarchicalpartitioning of adeliverableproductdown to a level agreed
betweenthecustomerandsupplier.
Theproducttreeispartofthedesigndefinitionfile.Itisthestartingpointfor
selecting configuration items (as specified inECSSMST40) and establishing
the work breakdown structure. It is a basic structure to establish the
specificationtree(asdefinedinECSSEST10).
B.2 Expected response
B.2.1 Scope and content
Introduction
a. Theproduct
tree
shall
contain
adescription
of
the
purpose,
objective
and
the reasonprompting itspreparation (e.g.programorproject reference
andphase).
Applicableandreferencedocuments
a. Theproduct treeshall list theapplicableandreferencedocumentsused
insupportofthegenerationofthedocument.
Treestructure
a.
The
product
tree
shall
provide
the
breakdown
of
lower
level
products
constitutingthedeliverableproduct.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
39/50
ECSSMST10CRev.1
6March2009
39
b. For each item identified in theproduct tree, the following information
shallbeprovided:
1. identificationcode;
2. itemname;
3. itemsupplier;
4. applicablespecification.
c. Theproduct treeshallbepresentedeitherasagraphicaldiagramoran
indenturedstructurewheretheproduct(i.e.atthetoplevelofthetree)is
decomposedintolowerlevelproducts.
d. Eachproductitemselectedasconfigurationitemshallbeidentifiedinthe
producttree.
e. When recurrent products from previous space projects are used, they
shallbeidentifiedinthetreestructure.
B.2.2 Special remarks
None.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
40/50
ECSSMST10CRev.1
6March2009
40
Annex C (normative)Work breakdown structure (WBS) DRD
C.1 DRD identification
C.1.1 Requirement identification and source document
ThisDRDiscalledfromECSSMST10,requirement5.3h.
C.1.2 Purpose and objective
Theobjectiveoftheworkbreakdownstructure(WBS)istoprovide,inasingle
document,aframeworkforprojectincostandschedulemanagementactivities
(as defined in ECSSMST60) and formanaging technical content. It assists
projectsactorsin:
conductingtendercomparisonsandbusinessagreementnegotiations;
optimizingthe
distribution
of
work
amongst
the
different
suppliers;
monitoringthescheduleoftheproject.
TheWBS divides the project intomanageablework packages, organizedby
natureofwork.It identifiesthetotalworktobeperformeddowntoa levelof
detailagreedbetweenthecustomerandsupplier.
Information concerning the determination of the appropriate WBS level of
detailisprovidedinECSSMST10,AnnexH.
C.2 Expected response
C.2.1 Scope and contents
Introduction
a. TheWBS shall contain adescription of the purpose, objective and the
reasonprompting itspreparation(e.g.programorprojectreferenceand
phase).
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
41/50
ECSSMST10CRev.1
6March2009
41
Applicableandreferencedocuments
a. The WBS shall list the applicable and reference documents used in
supportofthegenerationofthedocument.
Treestructure
a. The WBS shall provide a logical and exhaustive breakdown of the
product tree elements, that includes the customers defined support
functions (e.g. project management, engineering, product assurance
support)necessary toproduce the end itemdeliverables (development
and flight models) and the necessary services as appropriate for the
project.
b. A coding scheme for WBS elements that represents the hierarchical
structurewhenviewedintextformatshallbeused.
NOTE1 A common coding system facilitates
communicationsamongallprojectactors.
NOTE2 E.g.:toeachWBSelementisassignedacodeused
for its identification throughout the life of the
project.Itcanbeasimpledecimaloralphanumeric
coding system that logically indicates the levelof
an element and related lowerlevel subordinate
elements.
c. TheWBSshallidentifyallcontrolworkpackages.
d. Thecontrolworkpackagesmaybefurtherbrokendownbythesupplier
inseveralmoredetailedworkpackages.
e. Alldefinedworkpackagestogethershallcoverthetotalworkscope.
f. The WBS shall be presented either as a graphical diagram or an
indenturedstructure.
C.2.2 Special remarks
None.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
42/50
ECSSMST10CRev.1
6March2009
42
Annex D (normative)Work package (WP) description DRD
D.1 DRD identification
D.1.1 Requirement identification and source document
ThisDRDiscalledfromECSSMST10,requirement5.3n.
D.1.2 Purpose and objective
Theobjectiveoftheworkpackagedescriptionistodescribethedetailedcontent
ofeachelementoftheWBSasdefinedinECSSMST10,AnnexC.
D.2 Expected response
D.2.1 Scope and content
a. TheWPdescriptionshallcontainthefollowingelements:
1. projectnameandprojectphase;
2. WPtitle;
3. uniqueidentificationofeachWPandissuenumber
4. supplierorentityinchargeoftheWPperformance;
5. WPmanagersnameandorganization;
6. supplierscountry;
7. product towhich the tasks of theWP are allocated (link to the
producttree);
8. descriptionoftheobjectivesoftheWP;
9. descriptionofthetasks;
10. listoftheinputsnecessarytoachievethetasks;
11. interfacesorlinkswithothertasksorWPs;
12. listofconstraints,requirements,standards,andregulations;
13. listoftheexpectedoutputs;
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
43/50
ECSSMST10CRev.1
6March2009
43
14. listofdeliverables;
15. locationofdelivery;
16. starteventidentificationincludingdate;
17. endeventidentificationincludingdate;
18. excludedtasks.
D.2.2 Special remarks
None.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
44/50
ECSSMST10CRev.1
6March2009
44
Annex E (normative)Progress report DRD
E.1 DRD identification
E.1.1 Requirement identification and source document
ThisDRDiscalledfromECSSMST10,requirement5.2.2.2a.
E.1.2 Purpose and objective
The objective of the progress report is to provide all actors with actual
informationconcerningthestatusoftheproject.
E.2 Expected response
E.2.1 Scope and content
a. Theprogressreportshallcontainthefollowinginformation:
1. The project managers assessment of the current situation in
relation to the forecasts and risks, at a level of detail agreed
betweentherelevantactors.
2. The status of the progress of work being performed by the
supplier.
3. Statusandtrendsofagreedkeyperformanceandengineeringdata
parameters.
4. Adverse trends in technical and programmatic performance and
proposalsforremedialactions.
5. Planningforimplementationofremedialactions.
6. Aconsolidatedreportderivedfromthelowertiersuppliersstatus
reports.
7. Progressonallactionssincethepreviousreport.
E.2.2 Special remarksNone.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
45/50
ECSSMST10CRev.1
6March2009
45
Annex F (informative)ECSS management branch documents
delivery per review
TableF1provides the information concerning theexpecteddeliveryofECSS
managementbranchdocumentsperreview.
NOTE This table constitutes a first indication for thedata package content at various reviews. The
fullcontentofsuchdatapackageisestablished
as part of thebusiness agreement,which also
defines thedelivery of thedocumentbetween
reviews.
The various crosses in a row indicate the increased levels of maturity
progressivelyexpectedversusreviews.Thelastcrossinarowindicatesthatat
thatreviewthedocumentisexpectedtobecompletedandfinalized.
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
46/50
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
47/50
ECSSMST10CRev.1
6March2009
47
Annex G (informative)Management documents delivery
(periodic or incident triggered)
TableG1liststhedocumentswhicharedefinedasoutputsofthemanagement
standardsrequirementsandwhicharenotpartofreviewdatapackages.
TableG1:Managementdocumentsdelivery(periodicor
incidenttriggered)
DocumentTitle DRDref.
Costbreakdownstructure ECSSMST60,AnnexA
Scheduleprogressreport ECSSMST60,AnnexC
CompanyPriceBreakdownForms ECSSMST60,AnnexD
GeographicalDistributionReport ECSSMST60,AnnexE
CostEstimatingPlan ECSSMST60,AnnexF
MilestonePaymentPlan ECSSMST60,AnnexH
InventoryRecord ECSSMST60,AnnexI
CostandManpowerReport ECSSMST60,AnnexJ
OBCPandCBCPforCostReimbursement ECSSMST60,AnnexK
OBCPandCBCPforFixedPrice ECSSMST60,AnnexL
EACandETCforCostReimbursement ECSSMST60,AnnexM
EACforFixedPrice ECSSMST60,AnnexN
ContractChangeNotice ECSSMST60,AnnexO
Changerequest ECSSMST40,AnnexG
Changeproposal ECSSMST40,AnnexH
Requestfordeviation ECSSMST40,AnnexI
Requestforwaiver ECSSMST40,AnnexJ
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
48/50
ECSSMST10CRev.1
6March2009
48
Annex H (informative)Determination of the appropriate
WBS level of detail
Themainchallengeassociatedwithdevelopingtheworkbreakdownstructure
(WBS)istodeterminethebalancing between theprojectdefinitionaspects
of
the
WBS
and
the
requirements
for
data
collecting
and
reporting.
One
has
tokeep inmind that theWBS isa tooldesigned toassist theprojectmanager
whendecomposingtheprojectonlytothelevelsnecessarytomeettheneedsof
theproject,thenatureofthework,andtheconfidenceoftheteam.
An excessive WBS levels can lead to unrealistic levels of maintenance and
reporting,andconsequentlytoaninefficientandovercostlyproject.Thetheory
thatmoremanagement data equates tobettermanagement control hasbeen
proven false many times over in the last decades when assessing systems
performance.On theotherhand, ifnotdetailedenough itmakes theelement
difficulttomanageortheriskunacceptable.
Among thedifferentquestionsarisingwhendevelopingaWBS,an important
oneis:shouldtheWBSbedecomposedfurther?
Tohelpansweringthisquestion,weproposethefollowinglistofquestions.If
mostof thequestions canbeansweredYES, then theWBSelementanalyzed
should be decomposed. On the contrary, if most of the questions can be
answeredNO, then this is not necessary. If the answers are approximately
50/50,thenadditionaljudgmentisneeded.
Is there a need to improve the assessment of the cost estimates or
progressmeasuringoftheWBSelement?
Is theremore than one individual responsible for theWBS element?
Oftenavariety
of
resources
are
assigned
to
aWBS
element,
aunique
individual is assigned the overall responsibility for the deliverable
createdduringthecompletionoftheWBSelement.
Does theWBS element content includemore than one type of work
processorproducesmorethanonedeliverableatcompletion?
Isthereaneedtoassessthetimingofworkprocessesthatareinternalto
theWBSelement?
Is thereaneed toassess thecostofworkprocessesordeliverables that
areinternaltotheWBSelement?
Are
there
interactions
between
deliverables
within
a
WBS
element
to
anotherWBSelement?
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
49/50
ECSSMST10CRev.1
6March2009
49
Are there significant time gaps in the execution of thework processes
thatareinternaltotheWBSelement?
DoresourcerequirementschangeovertimewithinaWBSelement?
Are there acceptance criteria, leading to intermediate deliverable(s),
applicablebefore
the
completion
of
the
entire
WBS
element?
Arethereidentifiedrisksthatrequirespecificattentiontoasubsetofthe
WBSelement?
Can a subsetof thework tobeperformedwithin theWBS elementbe
organizedasaseparateunit?
-
7/31/2019 Ecss m St 10c Rev.1(6march2009)
50/50
ECSSMST10CRev.1
6March2009
Bibliography
ECSSSST00 ECSSsystemDescription,implementationand
generalrequirements
ECSSEST10 SpaceengineeringSystemengineeringgeneral
requirements
ECSSEST40 SpaceengineeringSoftwaregeneralrequirements
ECSSE
ST
70
Space
engineering
Ground
systems
and
operations
ECSSMST1001 SpaceprojectmanagementOrganizationand
conductofreviews
ECSSMST60 SpaceprojectmanagementCostandschedule
management
ECSSMST70 SpaceprojectmanagementIntegratedlogistic
support
ECSSMST80 SpaceprojectmanagementRiskmanagement
ECSSQST10 SpaceproductassuranceProductassurance
management