Ecss m St 10c Rev.1(6march2009)

download Ecss m St 10c Rev.1(6march2009)

of 50

Transcript of Ecss m St 10c Rev.1(6march2009)

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    1/50

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    2/50

    ECSSMST10CRev.1

    6March2009

    2

    Foreword

    This Standard is one of the series of ECSS Standards intended to be applied together for the

    management, engineering and product assurance in space projects and applications. ECSS is a

    cooperative effort of the European SpaceAgency, national space agencies and European industry

    associationsforthepurposeofdevelopingandmaintainingcommonstandards.Requirementsinthis

    Standardaredefinedintermsofwhatshallbeaccomplished,ratherthanintermsofhowtoorganize

    andperform thenecessarywork.Thisallowsexistingorganizational structuresandmethods tobe

    appliedwheretheyareeffective,andforthestructuresandmethodstoevolveasnecessarywithout

    rewritingthestandards.

    This Standard has been prepared by the ECSSMST10Working Group, reviewed by the ECSS

    ExecutiveSecretariatandapprovedbytheECSSTechnicalAuthority.

    Disclaimer

    ECSSdoesnotprovideanywarrantywhatsoever,whetherexpressed,implied,orstatutory,including,

    butnotlimitedto,anywarrantyofmerchantabilityorfitnessforaparticularpurposeoranywarranty

    that the contents of the item are errorfree. In no respect shall ECSS incur any liability for any

    damages,including,butnotlimitedto,direct,indirect,special,orconsequentialdamagesarisingout

    of,resulting from,or inanywayconnected to theuseof thisStandard,whetherornotbasedupon

    warranty,contract,tort,orotherwise;whetherornotinjurywassustainedbypersonsorpropertyor

    otherwise;andwhetherornotlosswassustainedfrom,oraroseoutof,theresultsof,theitem,orany

    servicesthatmaybeprovidedbyECSS.

    Publishedby: ESARequirementsandStandardsDivisionESTEC, P.O. Box 299,

    2200 AG Noordwijk

    The Netherlands

    Copyright: 2009 by the European Space Agency for the members of ECSS

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    3/50

    ECSSMST10CRev.1

    6March2009

    3

    Change log

    ECSSM10A

    19April1996

    Firstissue

    ECSSM10B

    13June2003

    Secondissue

    ECSSMST10C

    31July2008

    Thirdissue

    This issue combines the contents of ECSSM10B, ECSSM20B and

    ECSSM30A.Itsupersedesthesethreestandards.

    The descriptive text of the previous standards has been combined and

    rewrittentodeleteduplicationsandcorrectinconsistencies.

    The requirements of ECSSM10B have been maintained with following

    exceptions:

    Requirements on function tree have been deleted and moved to

    ECSSE10.

    Requirementsonmodelmatrixhavebeendeleted.

    Some requirements havebeenmoved to newly establishedDRDs (e.g.WBSandWPDRD).

    Somerequirementshavebeeneditedtoeliminateinconsistencies.

    The requirements of ECSSM20B have been maintained with following

    exceptions:

    Somerequirementshavebeendeletedbecausetheyareobvious.

    Requirementsofclause5.4arecoveredbyECSSMST40.

    Somerequirementshavebeeneditedtoeliminateinconsistencies.

    ThecontentofECSSM30Ahasbeencompletelyupdatedandrewritten.

    ECSSM

    ST

    10C

    Rev.

    1

    6March2009Third

    issue

    revision

    1

    ChangeswithrespecttoversionC(31July2008)areidentifiedwithrevision

    tracking.Themainchangesare:

    Changed term technical specification to technical requirements

    specification.

    TableF1updatedtoalignitwithECSSEST10,andTableG1updatedto

    identifyDRDreferences.

    Insertion of missing Header 4.4.3.2.1 Overview (resp. 4.4.3.3.1

    Overview)afterclausenumber4.4.3.2(resp.4.4.3.3)causingrenumbering

    ofsubsequentclauses.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    4/50

    ECSSMST10CRev.1

    6March2009

    4

    Table of contents

    Change log................................................................................................................. 3

    Introduction................................................................................................................ 7

    1 Scope....................................................................................................................... 8

    2 Normative references............................................................................................. 9

    3 Terms and definitions .......................................................................................... 10

    3.1 Terms defined in other standards............................................................................. 10

    3.2 Terms specific to the present standard .................................................................... 10

    3.3 Abbreviated terms .................................................................................................... 11

    4 Principles .............................................................................................................. 12

    4.1 Project planning........................................................................................................ 12

    4.1.1 Introduction................................................................................................. 12

    4.1.2 Purpose and objectives of the project ........................................................ 12

    4.1.3 Availability of and need to develop new technologies ................................ 13

    4.1.4 Availability of and need to reuse existing equipments/products ................. 13

    4.1.5 Availability of and need for human resources, skills and technicalfacilities....................................................................................................... 13

    4.1.6 Risk assessment ........................................................................................ 13

    4.1.7 Development approach .............................................................................. 13

    4.1.8 Project deliverables .................................................................................... 13

    4.1.9 Customer requirements and constraints..................................................... 14

    4.1.10 Project requirements documents (PRD)..................................................... 14

    4.1.11 Project management plan........................................................................... 14

    4.2 Project organization.................................................................................................. 15

    4.2.1 Introduction................................................................................................. 15

    4.2.2 Organizational structure ............................................................................. 15

    4.2.3 Communication and reporting .................................................................... 15

    4.2.4 Audits.......................................................................................................... 15

    4.3 Project breakdown structures................................................................................... 16

    4.3.1 Introduction................................................................................................. 16

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    5/50

    ECSSMST10CRev.1

    6March2009

    5

    4.3.2 Function tree............................................................................................... 16

    4.3.3 Specification tree ........................................................................................ 16

    4.3.4 Product tree................................................................................................ 16

    4.3.5 Work breakdown structure (WBS).............................................................. 17

    4.3.6 Work package (WP) ................................................................................... 18

    4.3.7 Organization breakdown structure (OBS)................................................... 18

    4.4 Project phasing......................................................................................................... 19

    4.4.1 Introduction................................................................................................. 19

    4.4.2 Relationship between business agreements and project phases............... 21

    4.4.3 Project phases............................................................................................ 21

    4.4.4 Project specific reviews .............................................................................. 28

    5 Requirements........................................................................................................ 295.1 Project planning........................................................................................................ 29

    5.1.1 Overview..................................................................................................... 29

    5.1.2 Requirements on customers....................................................................... 29

    5.1.3 Requirements on suppliers......................................................................... 30

    5.2 Project organization.................................................................................................. 30

    5.2.1 Organizational structure ............................................................................. 30

    5.2.2 Communication and reporting .................................................................... 31

    5.2.3 Audits.......................................................................................................... 325.3 Project breakdown structures................................................................................... 33

    5.4 Project phasing......................................................................................................... 34

    Annex A (normative) Project management plan (PMP) DRD ............................ 35

    Annex B (normative) Product tree DRD.............................................................. 38

    Annex C (normative) Work breakdown structure (WBS) DRD.......................... 40

    Annex D (normative) Work package (WP) description DRD ............................. 42

    Annex E (normative) Progress report DRD ........................................................ 44

    Annex F (informative) ECSS management branch documents delivery perreview................................................................................................................... 45

    Annex G (informative) Management documents delivery (periodic orincident triggered)............................................................................................... 47

    Annex H (informative) Determination of the appropriate WBS level ofdetail..................................................................................................................... 48

    Bibliography............................................................................................................. 50

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    6/50

    ECSSMST10CRev.1

    6March2009

    6

    Figures

    Figure 4-1: Product tree example........................................................................................... 17

    Figure 4-2: WBS example ...................................................................................................... 18

    Figure 4-3: Typical project life cycle....................................................................................... 19

    Figure 4-4: Review life cycle .................................................................................................. 21

    Tables

    Table F-1 :Management Documents Delivery per Review..................................................... 46

    Table G-1 : Management documents delivery (periodic or incident triggered)....................... 47

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    7/50

    ECSSMST10CRev.1

    6March2009

    7

    Introduction

    Projectplanning and implementation is theproject function, encompassing a

    coherentsetofprocessesforallaspectsofprojectmanagementandcontrol.

    Thisisdoneby:

    establishing theproject requirements and constraintsderived from the

    missionstatement.

    defining phases and formal milestones enabling the progress of theproject to be controlled with respect to cost, schedule and technical

    objectives(i.e.projectcontrolfunction).

    definingprojectbreakdownstructures,whichconstitutethecommonand

    uniquereferencesystemfortheprojectmanagementto:

    identifythetasksandresponsibilitiesofeachactor;

    facilitatethecoherencebetweenallactivitiesofthewholeproject;

    performschedulingandcostingactivities.

    settingupaprojectorganizationtoperformallnecessaryactivitiesonthe

    project.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    8/50

    ECSSMST10CRev.1

    6March2009

    8

    1Scope

    The scopeof thisECSSStandard is limited todescribing thekeyelementsof

    project planning and implementation and identifying the top level

    requirements and products that together provide a coherent and integrated

    projectplanningacrossthe3ECSSbranches.

    WhereotherECSSmanagement,engineering,orproductassurance standardscontainmore specific and detailed requirements related to project planning,

    referencesareprovidedto identifywherethesecanbefoundwithin theECSS

    system.

    Thisstandardmaybetailoredforthespecificcharacteristicandconstrainsofa

    spaceprojectinconformancewithECSSSST00.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    9/50

    ECSSMST10CRev.1

    6March2009

    9

    2Normative references

    The following normative documents contain provisions which, through

    reference in this text, constitute provisions of thisECSS Standard. Fordated

    references,subsequentamendmentsto,orrevisionofanyofthesepublications

    donotapply,However,partiestoagreementsbasedonthisECSSStandardare

    encouragedto

    investigate

    the

    possibility

    of

    applying

    the

    more

    recent

    editions

    of

    thenormativedocuments indicatedbelow. Forundated references, the latest

    editionofthepublicationreferredtoapplies.

    ECSSSST0001 ECSSsystemGlossaryofterms

    ECSSMST40 SpaceprojectmanagementConfigurationand

    informationmanagement

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    10/50

    ECSSMST10CRev.1

    6March2009

    10

    3Terms and definitions

    3.1 Terms defined in other standards

    For the purpose of this Standard, the terms and definitions from

    ECSSSST0001apply.

    3.2 Terms specific to the present standard

    3.2.1 discipline

    specificareaofexpertisewithinageneralsubject

    NOTE Thenameof thedisciplinenormally indicates the

    typeofexpertise(e.g. intheECSSSystem,system

    engineering,mechanicalengineering,softwareand

    communications are disciplines within the

    Engineeringdomain)

    3.2.2 domain

    generalareaofinterestorinfluencecoveringanumberofinterrelatedtopicsor

    subareas

    NOTE Thenameofadomainnormallyindicatesthearea

    of interest (e.g. in the ECSS System, the

    Management,Engineering,andProductAssurance

    branchesrepresentthreedifferentdomains).

    3.2.3 function

    combination and interaction of a number of operations or processes,which

    togetherachieveadefinedobjective

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    11/50

    ECSSMST10CRev.1

    6March2009

    11

    3.3 Abbreviated terms

    ForthepurposesofthisStandard,theabbreviatedtermsfromECSSSST0001

    andthefollowingapply.

    Abbreviation Meaning

    AR acceptancereview

    B/L baseline

    CBCP currentbaselinecostplan

    CDR criticaldesignreview

    CRR commissioningresultreview

    DRL documentrequirementslist

    EAC estimateatcompletion

    EGSE electricalgroundsupportequipment

    ELR

    endof

    life

    review

    ETC estimatetocompletion

    FRR flightreadinessreview

    GSE groundsupportequipment

    ILS integratedlogisticsupport

    ITT invitationtotender

    LRR launchreadinessreview

    MCR missioncloseoutreview

    MDR missiondefinitionreview

    MGSE mechanicalgroundsupportequipment

    N/A notapplicable

    OBCP originalbaselinecostplan

    OBS organizationalbreakdownstructure

    ORR operationalreadinessreview

    PDR preliminarydesignreview

    PMP projectmanagementplan

    PRD projectrequirementsdocuments

    PRR

    preliminaryrequirements

    review

    QR qualificationreview

    RFP requestforproposal

    RFQ requestforquote

    SRR systemrequirementsreview

    WBS workbreakdownstructure

    WP workpackage

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    12/50

    ECSSMST10CRev.1

    6March2009

    12

    4Principles

    4.1 Project planning

    4.1.1 Introduction

    Projectplanningand implementationencompassesallof theprocessescarried

    outinordertoplanandexecuteaspaceprojectfrominitiationtocompletionat

    all levels in the customersupplier chain in a coordinated, efficient and

    structuredmanner.Itisaprojectwideactivityreceivinginputsfromallproject

    disciplinesandinvolvingclosecooperationacrosstheprojectdomains.

    A space project typically comprises a space segment and a ground segment

    whichareimplementedinparallel(seeECSSEST70).Theyrelyon,andhave

    interfaceswith the launch service segment.These three segments comprise a

    spacesystem.

    Inprinciple,aproposal to initiatea spaceprojectcanbe raisedbyanyparty.

    However,themostcommoninitiatorsare:

    individual governments, or cooperation between a number of

    governments;

    national,orinternationalspaceagencies,eithersinglyorcollectively;

    nationalorinternationalscientificcommunities;

    operatorsofcommercialspacesystems.

    In thisECSS standard, the top level customer isdefined as the organization

    responsible for generating the top level space segment and ground segment

    business

    agreements

    and

    for

    interface

    arrangements

    with

    other

    external

    space

    systemelements.

    Thefollowingclauses4.1.2to4.1.11describethekeyelementstobeaddressed,

    assessed,andbalancedwhenplanningaproject.

    4.1.2 Purpose and objectives of the project

    Thepurposeandobjectivesoftheprojectaredefinedbytheprojectinitiatorin

    the mission statement which includes key performance parameters and

    technicalandprogrammaticconstraints tobeapplied to theproject.Theyare

    normallycoordinatedwiththetoplevelcustomer,ifonehasbeenassigned.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    13/50

    ECSSMST10CRev.1

    6March2009

    13

    4.1.3 Availability of and need to develop newtechnologies

    This is an assessment carried out jointly by the customer and supplier to

    identify the availability of scientific and technological knowhow and the

    technologyneeded

    to

    implement

    the

    project.

    The

    result

    of

    this

    assessment,

    which canbe a significant cost and scheduledriver, is amajor input to the

    assessmentofrequiredresourcesandfacilitiesandtothesubsequenttechnical

    andprogrammaticriskassessment.

    4.1.4 Availability of and need to reuse existingequipments/products

    This is an assessment of the feasibility of reusing existing products and is

    typicallycarriedoutasadirectresponsetoacustomerrequirement.Theresult

    of this assessment,which also can have a significant influence on cost and

    scheduleisamajorinputtotheassessmentofrequiredresourcesandfacilities

    andtothesubsequenttechnicalandprogrammaticriskassessment.

    4.1.5 Availability of and need for humanresources, skills and technical facilities

    This isanassessment carriedoutjointlyby the customerand supplierof the

    resources,skillsand facilitiesrequired to implement theproject.The resultof

    thisassessmentshowsifrequiredresources,skillsandfacilitiesareadequate,or

    ifadditionalskills,resources,orfacilitiesareneededtocompletetheproject.

    4.1.6 Risk assessment

    Theinitialassessmentsofthetechnicalandprogrammaticrisksofaprojectare

    carriedoutbythecustomer,basedontheprojectinitiatorsinputswithrespect

    to the purpose and objectives of the project, together with the identified

    technicalandprogrammaticconstraintstobeappliedtotheproject.Theinitial

    assessment is subsequently regularly expanded to include other relevant

    parameters as they become available, and as the project matures.

    Comprehensiveriskassessmentsareconductedateachmajorprojectreview.

    4.1.7 Development approach

    Thedevelopmentapproachforaprojectisjointlydefinedbythecustomerand

    suppliertocomplywiththeprojectinitiatorsmissionstatement,requirements

    andconstraints,andbalancing thesewith theoutcomeofparagraphs4.1.3 to

    4.1.6above.

    4.1.8 Project deliverables

    The customer has the responsibility for defining the deliverable products,

    neededtomeettheprojectinitiatorsmissionstatement,takingintoaccounttheassessmentsnotedinclauses4.1.4to4.1.7above.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    14/50

    ECSSMST10CRev.1

    6March2009

    14

    4.1.9 Customer requirements and constraints

    Customerrequirementsandconstraintsarepreparedbythecustomerbasedon

    theoutputs from4.1.2 to4.1.8aboveandput intoa formatsuitable fordirect

    application in an invitation to tender (ITT). They address technical and

    programmatic requirements, aswell as political, commercial, and industrial

    constraints tobe applied to theproject and collectively represent the project

    requirementsdocuments(PRD).

    4.1.10 Project requirements documents (PRD)

    TheprojectrequirementsdocumentsareanintegralpartofanITT,requestfor

    proposal (RFP), or request for quote (RFQ) prepared and released by a

    customertopotentialsuppliers.

    ThePRDtypicallycomprise

    Statementof

    work

    Technical requirements documented in Technical Requirements

    Specification,asdefinedinECSSEST1006

    Managementrequirements

    Engineeringrequirements

    Productassurancerequirements

    Programmaticrequirements

    Other, project specific requirements (e.g. geographical distribution,

    modelphilosophytobeapplied)

    Documentsrequirementslist(DRL)

    Tenderrequirements

    Under the ECSS system, management, engineering and product assurance

    requirementsarecontainedintheM,E,andQstandards,progressivelytailored

    byeachcustomerinthecustomersupplierchaintoreflectthetypeandphaseof

    the project coveredby thebusiness agreement, aswell as the scope of the

    supplierstasksrequiredbythePRD.

    4.1.11 Project management planThe top levelprojectplan is theprojectmanagementplanwhichdefines the

    projectmanagementapproachandmethodologytobeusedthroughoutthelife

    cycle of the project, together with an overview of all elements of project

    managementdisciplines. It includes thedefinition of the system engineering

    and product assurance management approach or provides references to

    separatesystemengineeringandproductassuranceplanswhichtogethermake

    upthetotalplanningdocumentationusedtoimplementaproject.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    15/50

    ECSSMST10CRev.1

    6March2009

    15

    4.2 Project organization

    4.2.1 Introduction

    Theestablishment

    of

    awell

    structured

    and

    coherent

    organizational

    structure

    for

    implementing a project at all levels in the customersupplier chain is a key

    factor for ensuring an effective and efficientmanagement approach.At each

    levelinthecustomersupplierchainaprojectorganizationcanbebuiltasaself

    standing project team containing all necessary disciplines within the team

    structureor,moreoften,canbebuiltaroundacoreprojectteamcontainingkey

    project functionswithothernecessary functionsbeingprovided fromoutside

    theprojectteamasexternalsupport.

    Irrespectiveoftheorganizationalapproachfollowedforaproject,theelements

    summarizedbelowarerelevantatalllevelsinthecustomersupplierchain.

    4.2.2 Organizational structure

    Itisessentialthattheprojectorganizationalstructureisarrangedtoincludeall

    disciplines essential to implement the projectwithwelldefined functions as

    wellasclearreportinglines,interrelationshipsandinterfaces.Allprojectactors

    below the top levelcustomerandabove the lowest level supplier(s)have the

    roles of suppliers and customers, and their organizational structures are

    constructedtoaccommodatebothroles.

    Theorganizationalstructureprovidesaclearandunambiguousdefinitionand

    allocationof individual roles and responsibilities togetherwith thenecessary

    authority to implement these within the internal project setup as well astowardsprojectexternalinterfaces.

    4.2.3 Communication and reporting

    Effectivemeans of communication are essential tools for ensuring clear and

    efficient interactionbetweenallprojectactors,aswellasbetween theproject

    teamand itsexternal interfaces. Information technology is theprimarymeans

    for the exchange of information. Communication serves initially to provide

    clarityabouttheprojectsgoalsandobjectivesandsubsequently,tosupportthe

    daytodayworkoftheprojectteam.Regularreportingisanimportanttoolfor

    exchanginginformationconcerningtheprogressoftheproject.

    4.2.4 Audits

    Audits are independent examinations to determine whether processes and

    proceduresachievethespecifiedobjective.Theyareanessentialtooltoidentify

    problemareas.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    16/50

    ECSSMST10CRev.1

    6March2009

    16

    4.3 Project breakdown structures

    4.3.1 Introduction

    Projectbreakdown

    structures

    provide

    the

    basis

    for

    creating

    acommon

    understanding between all actors. They break the project down into

    manageableelementsasdescribedinthefollowingclauses4.3.2to4.3.7.

    4.3.2 Function tree

    Thefunctiontreeisthebreakdownofthesystemperformancesintofunctions.

    Each function is decomposed into subfunctions independent of the type of

    productsinvolved.Thefunctionapproachisappliedduringprojectstartup

    orduringthesystemdefinitionphase.Moredetailsaboutthefunctiontreeare

    giveninECSSEST10,functiontreeDRD.

    4.3.3 Specification tree

    The specification tree defines the hierarchical relationship of all technical

    requirements specifications for thedifferentelementsofa systemorproduct.

    More details about the specification tree are given in ECSSEST10,

    specificationtreeDRD.

    4.3.4 Product tree

    Theproduct

    tree

    is

    the

    breakdown

    of

    the

    project

    into

    successive

    levels

    of

    hardware and software products or elements, articulated to perform the

    functionsidentifiedinthefunctiontree.However,thefunctionandtheproduct

    tree do not necessarily mirror each other. The product tree includes the

    developmentmodels, theGSE, the integration tools and test equipment, and

    externalitemsnecessarytovalidatetheendproductandILSitems.Itincludes

    itemssubmittedtocustomerconfigurationcontrolanditemsthatarethesubject

    ofa technicalrequirementsspecification.Theproduct tree forms thebasis for

    theelaborationoftheprojectworkbreakdownstructure.

    AnexampleofaproducttreeisshowninFigure41.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    17/50

    ECSSMST10CRev.1

    6March2009

    17

    SpaceSystem

    Space Segment Ground Segment

    PayloadPlatform GSEMission Control

    CenterPayload Control

    CenterCommunications

    System

    Structure

    Thermal control

    On-board power

    supply

    Attitude control

    Data handling

    Instrument 1 MGSE

    EGSEInstrument 2

    Instrument 3

    Figure41:Producttreeexample

    4.3.5 Work breakdown structure (WBS)

    TheWBS istheprincipalstructureusedinmanagingaprojectandprovidesa

    framework formanaging cost, schedule and technical content. Itdivides the

    project intomanageableworkpackages,organizedaccording to thenatureof

    theworkbybreaking down the totalwork tobe performed into increasing

    levelsofdetail.

    TheWBS is derived from the product tree, selected elements ofwhich are

    extended to includesupport functions (i.e.management,engineering,product

    assurance)andassociatedservices(e.g.testfacilities).

    AnexampleofaWBSisshowninFigure42.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    18/50

    ECSSMST10CRev.1

    6March2009

    18

    Figure42:WBSexample

    4.3.6 Work package (WP)

    AWP canbe any element of theWBSdown to the lowest level that canbe

    measuredandmanagedforplanning,monitoring,andcontrol.

    Controlworkpackagesare identifiedby the supplierat the level in theWBS

    where visibility and control is required, and for which reporting is to be

    performed.Thecontrolworkpackagesrepresent thetotalworkscopeandare

    agreedbythecustomer.

    The work of each supplier is explicitly identified in the work breakdown

    structurebyatleastonecontrolworkpackage.

    4.3.7 Organization breakdown structure (OBS)

    TheOBSdepictstheproposedprojectorganization,includingtheinterfaceand

    contractual responsibilities, as opposed to company organizationbreakdown

    structure,whichdepictsthefunctionalaspectsofthecompany.TheprojectOBS

    shows the keypersonnel and the assigned responsibleparties for eachwork

    packageintheWBS.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    19/50

    ECSSMST10CRev.1

    6March2009

    19

    4.4 Project phasing

    4.4.1 Introduction

    Thelife

    cycle

    of

    space

    projects

    is

    typically

    divided

    into

    7phases,

    as

    follows:

    Phase0 Missionanalysis/needsidentification

    PhaseA Feasibility

    PhaseB PreliminaryDefinition

    PhaseC DetailedDefinition

    PhaseD QualificationandProduction

    PhaseEUtilization

    PhaseFDisposal

    AtypicalprojectlifecycleisillustratedinFigure43.

    Project phases are closely linked to activities on system and product level.

    Depending on the specific circumstances of a project and the acceptance of

    involvedrisk,activitiescanoverlapprojectphases.

    At the conclusion of the major activities and the related project reviews

    configurationbaselinesareestablished(seeECSSMST40).

    Figure43:Typicalprojectlifecycle

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    20/50

    ECSSMST10CRev.1

    6March2009

    20

    Phases0,A,andBarefocusedmainlyon

    the elaboration of system functional and technical requirements and

    identificationofsystemconcepts tocomplywith themissionstatement,

    takingintoaccountthetechnicalandprogrammaticconstraintsidentified

    bytheprojectinitiatorandtoplevelcustomer.

    theidentificationofallactivitiesandresourcestobeusedtodevelopthe

    spaceandgroundsegmentsoftheproject,

    theinitialassessmentsoftechnicalandprogrammaticrisk,

    initiationofpredevelopmentactivities.

    PhasesCandDcompriseallactivitiestobeperformedinordertodevelopand

    qualifythespaceandgroundsegmentsandtheirproducts.

    PhaseEcomprisesallactivitiestobeperformedinordertolaunch,commission,

    utilize,andmaintaintheorbitalelementsofthespacesegmentandutilizeand

    maintain

    the

    associated

    ground

    segment.

    PhaseFcomprisesallactivities tobeperformed inorder to safelydisposeall

    productslaunchedintospaceaswellasgroundsegment.

    Eachoftheaboveprojectphasesincludesendmilestonesintheformofproject

    review(s), theoutcomeofwhichdetermines readinessof theproject tomove

    forwardtothenextphase.

    Requirements on organization and conduct of reviews are provided in

    ECSSMST1001.

    With the exception of the MDR which normally involves only the project

    initiator, and the top level customer, all other project reviews up to and

    including theAR are typically carried outby all project actors down to the

    lowest level supplier in the customersupplier chain involved in the project

    phasescontainingthesereviews.

    FromthePRRtothePDR,thesequenceofthereviewsistopdown,starting

    withthetoplevelcustomerandhistoplevelsupplier,andcontinuingdownthe

    customersupplierchaintothelowestlevelsupplier.FromtheCDRtotheAR,

    the sequenceof reviews is reversed to bottomup, startingwith the lowest

    level supplier and its customer and continuing up through the customer

    supplierchaintothe1stlevelsupplierandthetoplevelcustomer.Thissocalled

    VmodelisillustratedinFigure44.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    21/50

    ECSSMST10CRev.1

    6March2009

    21

    Figure44:Reviewlifecycle

    4.4.2 Relationship between business agreementsand project phases

    Abusinessagreementcancoverasingleprojectphase,asequentialgroupingof

    projectphasesorsubphases(e.g.phaseB1/phaseB2;phaseB2/phaseC1/phase

    C2),dependingonsuch factorsas fundingavailability,competitive tendering,

    schedule, perceived risk. Irrespective of the approach used for defining the

    scope of individualbusiness agreements, all spaceprojects essentially follow

    theclassicalprojectphases insequenceand includeallof themajorobjectives

    andkeymilestonesofeachofthesephases.

    4.4.3 Project phases

    4.4.3.1 GeneralThe clause 4.4.3 provides an introduction and overview of the typicalmajor

    tasks,associatedreviewmilestones,andreviewobjectivesforeachofthephases

    inaprojectlifecycle.

    4.4.3.2 Phase 0 (Mission analysis/needs identification)

    4.4.3.2.1 Overview

    This is mainly an activity conducted by the project initiator, the top level

    customerandrepresentativesoftheendusers.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    22/50

    ECSSMST10CRev.1

    6March2009

    22

    4.4.3.2.2 Major tasks:

    Elaborate the mission statement in terms of identification and

    characterization of the mission needs, expected performance,

    dependability and safety goals andmission operating constraintswith

    respecttothephysicalandoperationalenvironment.

    Developthepreliminarytechnicalrequirementsspecification.

    Identifypossiblemissionconcepts.

    Performpreliminaryassessmentofprogrammaticaspects supportedby

    marketandeconomicstudiesasappropriate.

    Performpreliminaryriskassessment.

    4.4.3.2.3 Associated review

    Themissiondefinitionreview(MDR)isheldattheendofphase0.

    Theoutcome

    of

    this

    review

    is

    used

    to

    judge

    the

    readiness

    of

    the

    project

    to

    move

    intophaseA.

    4.4.3.2.4 Main review objective(s)

    Theprimary objective of this review is to release themission statement and

    assess thepreliminary technical requirements specificationandprogrammatic

    aspects.

    4.4.3.3 Phase A (Feasibility)

    4.4.3.3.1 Overview

    This ismainly an activity conductedby the top level customer and one or

    several first level supplierswith the outcomebeing reported to the project

    initiator,andrepresentativesoftheendusersforconsideration.

    4.4.3.3.2 Major tasks

    Establish the preliminarymanagement plan, system engineering plan

    andproductassuranceplanfortheproject.

    Elaborate possible system and operations concepts and system

    architectures and compare these against the identified needs, to

    determinelevelsofuncertaintyandrisks.

    Establishthefunctiontree.

    Assess the technical and programmatic feasibility of the possible

    concepts by identifying constraints relating to implementation, costs,

    schedules, organization, operations, maintenance, production and

    disposal.

    Identifycriticaltechnologiesandproposepredevelopmentactivities.

    Quantify and characterize critical elements for technical and economic

    feasibility.

    Propose the system and operations concept(s) and technical solutions,

    including model philosophy and verification approach, to be further

    elaboratedduringPhaseB.

    Elaboratetheriskassessment.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    23/50

    ECSSMST10CRev.1

    6March2009

    23

    4.4.3.3.3 Associated review

    Thepreliminaryrequirementsreview(PRR)isheldattheendofPhaseA.The

    outcomeofthisreviewisusedtojudgethereadinessoftheprojecttomoveinto

    PhaseB.

    4.4.3.3.4 Main review objective(s)

    Theprimaryobjectivesofthisrevieware:

    Releaseofpreliminarymanagement,engineeringandproductassurance

    plans.

    Releaseofthetechnicalrequirementsspecification.

    Confirmationofthetechnicalandprogrammaticfeasibilityofthesystem

    concept(s).

    Selection of system and operations concept(s) and technical solutions,

    including model philosophy and verification approach, to be carried

    forwardintoPhaseB.

    4.4.3.4 Phase B (Preliminary definition)

    4.4.3.4.1 Major tasks

    Finalize the project management, engineering and product assurance

    plans.

    Establishthebaselinemasterschedule.

    Elaboratethebaselinecostatcompletion.

    Elaboratethepreliminaryorganizationalbreakdownstructure(OBS).

    Confirm technical solution(s) for the system and operations concept(s)

    andtheirfeasibilitywithrespecttoprogrammaticconstraints.

    Conduct tradeoff studies and select the preferred system concept,

    togetherwiththepreferredtechnicalsolution(s)forthisconcept.

    Establishapreliminarydesigndefinitionfortheselectedsystemconcept

    andretainedtechnicalsolution(s).

    Determinetheverificationprogramincludingmodelphilosophy.

    Identifyanddefineexternalinterfaces.

    Prepare the next level specification and related business agreementdocuments.

    Initiatepredevelopmentworkoncritical technologiesorsystemdesign

    areaswhenitisnecessarytoreducethedevelopmentrisks.

    Initiate any longlead item procurement required to meet project

    scheduleneeds.

    Preparethespacedebrismitigationplanandthedisposalplan.

    Conductreliabilityandsafetyassessment.

    Finalize the product tree, the work breakdown structure and the

    specificationtree.

    Updatetheriskassessment.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    24/50

    ECSSMST10CRev.1

    6March2009

    24

    4.4.3.4.2 Associated reviews

    Thereare2projectreviewsassociatedwithPhaseB.

    Thesystemrequirementsreview(SRR)heldduringthecourseofPhaseB.

    Thepreliminarydesign review (PDR)held at the end of PhaseB.The

    outcomeof this review isused tojudge the readinessof theproject tomoveintoPhaseC.

    4.4.3.4.3 Main review objectives - System requirements review

    Theprimaryobjectivesofthisrevieware:

    Releaseofupdatedtechnicalrequirementsspecifications.

    Assessmentofthepreliminarydesigndefinition.

    Assessmentofthepreliminaryverificationprogram.

    4.4.3.4.4 Main review objectives Preliminary design reviewTheprimaryobjectivesofthisrevieware:

    Verification of the preliminary design of the selected concept and

    technicalsolutionsagainstprojectandsystemrequirements.

    Releaseoffinalmanagement,engineeringandproductassuranceplans.

    Releaseofproducttree,workbreakdownstructureandspecificationtree.

    Releaseoftheverificationplan(includingmodelphilosophy).

    4.4.3.5 Phase C (Detailed definition)

    4.4.3.5.1 Major tasks

    The scope and typeof tasksundertakenduring thisphase aredrivenby the

    modelphilosophyselectedfortheproject,aswellastheverificationapproach

    adopted.

    Completionofthedetaileddesigndefinitionofthesystematalllevelsin

    thecustomersupplierchain.

    Production,developmenttestingandprequalificationofselectedcritical

    elementsandcomponents.

    Productionand

    development

    testing

    of

    engineering

    models,

    as

    required

    bytheselectedmodelphilosophyandverificationapproach.

    Completionofassembly,integrationandtestplanningforthesystemand

    itsconstituentparts.

    Detaileddefinitionofinternalandexternalinterfaces.

    Issueofpreliminaryusermanual.

    Updateoftheriskassessment.

    4.4.3.5.2 Associated review

    Thecritical

    design

    review

    (CDR)

    is

    held

    at

    the

    end

    of

    phase

    C.

    The

    outcome

    of

    thisreviewisusedtojudgethereadinessoftheprojecttomoveintophaseD.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    25/50

    ECSSMST10CRev.1

    6March2009

    25

    4.4.3.5.3 Main review objectives

    Assessthequalificationandvalidationstatusofthecriticalprocessesand

    theirreadinessfordeploymentforphaseD.

    Confirmcompatibilitywithexternalinterfaces.

    Releasethefinaldesign.

    Releaseassembly,integrationandtestplanning.

    Releaseflighthardware/softwaremanufacturing,assemblyandtesting.

    Releaseofusermanual.

    4.4.3.6 Phase D (Qualification and production)

    4.4.3.6.1 Major tasks

    Completequalificationtestingandassociatedverificationactivities.

    Complete manufacturing, assembly and testing of flight

    hardware/softwareandassociatedgroundsupporthardware/software.

    Complete the interoperability testing between the space and ground

    segment.

    Prepareacceptancedatapackage.

    4.4.3.6.2 Associated reviews

    Thereare3projectreviewsassociatedwithphaseD

    Thequalificationreview(QR)heldduringthecourseofthephase.

    Theacceptancereview(AR)heldattheendofthephase.Theoutcomeof

    thisreviewisusedtojudgethereadinessoftheproductfordelivery.

    Theoperationalreadinessreview(ORR),heldattheendofthephase.

    4.4.3.6.3 Main review objectives Qualification review

    Theprimaryobjectivesofthisrevieware:

    To confirm that the verification process has demonstrated that the

    design,includingmargins,meetstheapplicablerequirements.

    To verify that the verification record is complete at this and all lower

    levelsinthecustomersupplierchain.

    Toverifytheacceptabilityofallwaiversanddeviations.

    Wheredevelopment encompasses theproduction of one or several recurring

    products,theQRiscompletedbyafunctionalconfigurationverificationduring

    which:

    The first article configuration is analyzed from the viewpoint of

    reproducibility.

    Theproductionmasterfilesfortheseriesproductionsarereleased.

    Theseriesproductiongoaheadfileisacceptedbythecustomer.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    26/50

    ECSSMST10CRev.1

    6March2009

    26

    4.4.3.6.4 Main review objectives Acceptance review

    Theprimaryobjectivesofthisrevieware:

    To confirm that the verification process has demonstrated that the

    product is free of workmanship errors and is ready for subsequent

    operationaluse.

    Toverify that theacceptanceverificationrecord iscompleteat thisand

    alllowerlevelsinthecustomersupplierchain.

    To verify that all deliverable products are available per the approved

    deliverableitemslist.

    Toverify theasbuiltproductand itsconstituentcomponentsagainst

    therequiredasdesignedproductanditsconstituentcomponents.

    Toverifytheacceptabilityofallwaiversanddeviations.

    ToverifythattheAcceptanceDataPackageiscomplete.

    Toauthorizedeliveryoftheproduct.

    Toreleasethecertificateofacceptance.

    4.4.3.6.5 Main review objectives - Operational readiness review(ORR)

    Theprimaryobjectivesofthisrevieware:

    Toverifyreadinessoftheoperationalproceduresandtheircompatibility

    withtheflightsystem.

    Toverifyreadinessoftheoperationsteams.

    Toacceptandreleasethegroundsegmentforoperations.

    4.4.3.7 Phase E (Operations/utilization)

    4.4.3.7.1 Major tasks

    Themajortasksforthisphasevarywidelyasafunctionofthetypeofproject

    concerned.Therefore,onlyageneraloverviewofactivitiesduringthisphaseis

    providedhere.

    Perform all activities at space and ground segment level in order to

    preparethelaunch.

    Conductalllaunchandearlyorbitaloperations.

    Performonorbitverification(includingcommissioning)activities.

    Performallonorbitoperationsinordertoachievethemissionobjectives.

    Performallgroundsegmentactivitiesinordertosupportthemission.

    Perform all other ground support activities in order to support the

    mission.

    Finalizethedisposalplan.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    27/50

    ECSSMST10CRev.1

    6March2009

    27

    4.4.3.7.2 Associated reviews

    Thereare4projectreviewsassociatedwithphaseE.

    Theflightreadinessreview(FRR)isheldpriortolaunch.

    Thelaunchreadinessreview(LRR),heldimmediatelypriortolaunch.

    Thecommissioningresultreview(CRR),heldaftercompletionoftheon

    orbitcommissioningactivities.

    Theendoflifereview(ELR)heldatthecompletionofthemission.

    4.4.3.7.3 Main review objectives - Flight readiness review (FRR)

    The flightreadinessreview isconductedprior to launch.Theobjectiveof this

    reviewistoverifythattheflightandgroundsegmentsincludingallsupporting

    systemssuchas trackingsystems,communicationsystemsandsafetysystems

    arereadyforlaunch.

    4.4.3.7.4 Main review objectives - Launch readiness review (LRR)

    Thelaunchreadinessreviewisconductedjustpriortolaunch.Theobjectiveof

    this review is todeclare readiness for launchof the launchvehicle, the space

    and ground segments including all supporting systems such as tracking

    systems, communication systems and safety systems and to provide the

    authorizationtoproceedforlaunch.

    4.4.3.7.5 Main review objectives - Commissioning result review (CRR)

    The commissioning result review isheld at the endof the commissioning as

    partof the inorbitstageverification. Itallowsdeclaring readiness forroutine

    operations/utilization.

    This Review is conducted following completion of a series of onorbit tests

    designed to verify that all elements of the system areperformingwithin the

    specified performance parameters. Successful completion of this review is

    typicallyusedtomarktheformalhandoverofthesystemtotheprojectinitiator

    ortothesystemoperator.

    4.4.3.7.6 Main review objectives End of life review (ELR)

    Toverifythatthemissionhascompleteditsusefuloperationorservice.

    Toensurethatallonorbitelementsareconfiguredtoallowsafedisposal.

    4.4.3.8 Phase F (Disposal)

    4.4.3.8.1 Major tasks

    Implementthedisposalplan.

    4.4.3.8.2 Associated review

    Themissioncloseoutreview(MCR)isheldattheendofthisphase.

    4.4.3.8.3 Main review objectives

    Toensurethatallmissiondisposalactivitiesareadequatelycompleted.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    28/50

    ECSSMST10CRev.1

    6March2009

    28

    4.4.4 Project specific reviews

    Inadditiontotheprojectreviewsidentifiedabove,anddependingonthetype

    ofproject, the applicablebusiness agreement and theoverall implementation

    approachadopted,additionalreviewscanbeinsertedintotheprojectplanning

    againstagreedsubmilestones/additionalmilestones tomeetparticularproject

    needs.

    Typicalexamplesofsuchreviewsare:

    Detaileddesignreview (software specific review,addressed inECSSE

    ST40)

    Inorbitoperationsreview(addressedinECSSEST70)

    Firstarticleconfigurationreview(serialproductionspecificreview)

    Systemdesignreview

    Systemqualificationreviewatgroundlevel(launcherspecificreview)

    Systemqualificationreviewatflightlevel(launcherspecificreview)

    Thesereviewsarenotfurtheraddressedinthisstandard.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    29/50

    ECSSMST10CRev.1

    6March2009

    29

    5Requirements

    5.1 Project planning

    5.1.1 Overview

    Projectplanningrequirementsareapplicabletoallactorsofaprojectfromthe

    top levelcustomerdown tothe lowest levelsupplier.Projectactorswhohave

    theroleofacustomerandasuppliercarrytheresponsibilitiesassociatedwith

    bothroles.Thescopeanddetailofrequirementsmadeapplicableisafunction

    ofthelevelofeachactorinthecustomersupplierchain,withthefullscopeof

    all requirementsapplicable to the top level supplier.Theoverall scopemade

    applicable reduces, down through the customersupplier chainbutbecomes

    morespecificasa functionof theroleplayedbyeachof theseactorsand the

    typeofproduct(s)tobedevelopedanddeliveredbythem.

    5.1.2 Requirements on customers

    a. Each customer shall prepare business agreements (ITTs, RFPs, or

    RFQs),includingtheprojectrequirementsdocuments(PRD)tobemade

    applicablebetweenhimandhissupplier(s).

    b. Each customer shall use the ECSS standards to establish the project

    management, engineering and product assurance requirements

    applicablefortheproject.

    c. Eachcustomershallmakeapplicable tohissupplier(s)only thoseECSS

    standardsrelevant to the typeandphase(s)of theprojectaddressedby

    thebusiness

    agreement.

    d. Each customer shall specify by tailoring the minimum requirements

    within theapplicable standardsnecessary forhis supplier(s) toachieve

    theprojectobjectives.

    e. Each customer shall approve the projectmanagement plans and key

    personnelofhissupplier(s).

    f. Eachcustomershallverifycomplianceofhissupplier(s)withallproject

    requirementsandconstraints.

    g. Each customerbelow the top level customer in the customersupplier

    chain

    shall

    in

    addition

    ensure

    that

    planning

    for

    his

    suppliers

    is

    consistent

    withtheplanningrequirementsimposedonhimbyhiscustomer.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    30/50

    ECSSMST10CRev.1

    6March2009

    30

    5.1.3 Requirements on suppliers

    a. Each supplier in the customersupplier chain shall prepare a project

    managementplan(PMP)inconformancewithAnnexA.

    b. EachsupplierinthecustomersupplierchainshallsubmitthePMPtohis

    customerforapproval.

    5.2 Project organization

    5.2.1 Organizational structure

    5.2.1.1 Requirements on customers and suppliers

    a. Each customer and supplier shall define the authority for project

    managementandbusinessagreementsigning.

    b. If theprojecthas linkswithotherprojects,eachcustomerand supplier

    shall define the responsibilities relating to the definition and the

    managementofinterfaces.

    c. Whereacustomer,orsupplier,employsconsultantsorotherspecialists

    toassisthiminperforminghisduties,thentheroles,responsibilitiesand

    authorityoftheseconsultantsandspecialistsshallbedefined.

    d. When a customer supplies a product to a supplier he shall have the

    responsibilityofasupplierinrespectofthatproduct.

    5.2.1.2 Requirements on suppliers

    a. Thesuppliershallsetuptheprojectmanagementorganizationinsucha

    waythatadequateresourcesareallocatedtotheprojecttoensuretimely

    completionofthebusinessagreement.

    b. Thesuppliershallnominateaprojectmanagerwithaprojectteamunder

    hisauthorityandreportingdirectlytohim.

    c. The supplier shallensure that theprojectmanagerhas theauthority to

    executealltasksneededunderthebusinessagreementwithdirectaccess

    to his company management hierarchy to resolve conflicts at the

    appropriatelevel.

    d. Thesuppliershallidentifythekeypersonneltobedeployedonthework,

    andincludethemintheprojectorganization.

    e. Thesuppliershalldemonstratethatthekeypersonnelhavethenecessary

    qualification,skillsandexperiencetoperformthetaskforwhichtheyare

    allocated.

    f. Thesuppliersprojectmanagementorganizationshallexerciseanactive

    monitoringandcontrolover itsownand lower tiersuppliersactivities

    and lead its lower tier suppliers in the execution of subcontracted

    activitiesto

    ensure

    that

    their

    services

    conform

    to

    the

    customers

    requirements.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    31/50

    ECSSMST10CRev.1

    6March2009

    31

    g. Ifasupplierisresponsibleformorethanonebusinessagreementwithin

    a project, and thebusiness agreements have different customers, then

    eachbusiness agreement shallbe clearly identified and accomplished

    accordingtotheappropriaterelationships.

    h. The first levelsuppliershallestablish,maintainanddistributeaproject

    directoryincludingkeypersonnel,asaminimum.

    5.2.2 Communication and reporting

    5.2.2.1 Requirements on customers and suppliers

    a. Thetoplevelcustomershall:

    1. specifyareportingsystemfortheproject;

    2. specifyanactionmonitoringsystemfortheproject.

    b. Each customer and supplier in the customersupplier chain shall

    implement and maintain the project reporting an action monitoring

    systems.

    c. Formalmeetingsbetweenthecustomerandhissupplier(s)shallbeheld

    toreviewprogressagainstapprovedprojectplanningandaddressmajor

    deviationsorchangesproposedtotheprojectrequirementsdocuments.

    d. The frequency, location and schedule of customersupplier project

    meetingsshallbeagreedbyallparticipatingparties.

    e. Customersuppliermeetingsshallbebasedonanagreedwrittenagenda.

    f. Achairpersonandsecretaryshallbedesignatedat thebeginningof themeeting.

    g. The resultsof themeeting shallbedocumented in the agreedminutes

    signedbyallpartiesinvolvedinthemeeting.

    h. Agreedactionsshallbedocumentedinanactionitemlist.

    i. Eachactionshallbeallocated

    1. auniqueidentification,

    2. theidentificationoftheorigin(e.g.meeting),

    3. theinitiator,

    4. thedescriptionoftheaction(clearandconcise),

    5. thepersonresponsiblefortheaction,

    6. thecloseoutdate,

    7. thecurrentstatus,and

    8. thecloseoutreference(e.g.document,letter).

    j. Actionitemsshallbereviewedateachmeeting.

    k. Anymattersdocumentedintheminutesofmeetinghavingimpactonthe

    businessagreementshallbesubjecttothecontractchangeprocedureforimplementation.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    32/50

    ECSSMST10CRev.1

    6March2009

    32

    5.2.2.2 Requirements on suppliers

    a. Thesuppliershallprepareandsubmitprogressreportstohiscustomerin

    conformancewithAnnexE.

    b. Thesuppliershallprepareminutesofprogressmeetingsforapprovalof

    thecustomer.

    c. Thesuppliershallnotifythecustomerwithinanagreedperiodoftimeof

    anyeventthatcouldsignificantlyaffecttheachievementofthebusiness

    agreement objectives in terms of cost, technical performance and

    schedule, and any situation resulting in a substantial schedule or

    planningchangedemandingimmediatecustomerinvolvement.

    5.2.3 Audits

    5.2.3.1 General requirementsa. Every audit performed shallbe followedby a report preparedby the

    auditorandcontainingtheviewsofbothparties.

    b. Theconclusionsoftheauditandthedraftreportshallbediscussedwith

    thesupplier,beforefinalizationandrelease.

    c. In the event of disagreement with any of the audit conclusions, the

    suppliermayaddhisobservationsandcomments.

    d. Thefinalauditreportshallnotbedivulgedwithouttheagreementofthe

    auditedsupplier.

    5.2.3.2 Requirements on customers

    a. Thecustomershallnotifythesupplierinduetimeof

    1. hisintentiontoperform anaudit;

    2. theobjectivesandthescopeoftheaudit;

    3. thedesignatedauditorandhistermsofreference;

    4. theauditschedule.

    5.2.3.3 Requirements on suppliers

    a. The supplier shall accept tobe auditedby the customer orby a third

    partyagreedbetweenthecustomerandthesupplierintheframeworkof

    thebusinessagreement.

    b. Thesuppliershallhavetherighttodemandthattheauditbeperformed

    byathirdparty,andthatthethirdpartyobtainauthorizationeachtime

    theauditnecessitatesaccess to information concerningpatent rightsor

    confidentialityassociatedwithdefencesecrecy.

    c. Thesuppliershallperformauditsofhisownprojectactivitiesandofthe

    projectactivitiesofhislowertiersupplier(s)toverifyconformancewith

    project

    requirements.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    33/50

    ECSSMST10CRev.1

    6March2009

    33

    d. The supplier shall provide right of access for participation by the

    customerinhisownauditsandinauditsofhislowertiersuppliers.

    e. Thesuppliershallprovidehiscustomeraccess tohis facilitiesanddata

    whicharerelevantintheframeofthebusinessagreement.

    5.3 Project breakdown structures

    a. Thesuppliershalldeveloptheproducttreeforhisproductsdowntothe

    deliverable end items, incorporating the product trees of each of his

    lowertiersuppliers,inconformancewithAnnexB.

    b. TheproducttreeshallbeestablishedatstartofphaseBandfinalizednot

    laterthanPDR.

    c. The rules for product item identification shallbe uniformwithin the

    project.

    d. Auniqueidentificationshallbeassignedtoeachitemwithintheproduct

    tree.

    e. The identification shall remainunchangedduring theproduct lifetime,

    unlessamodificationcausesdiscontinuationofinterchangeability.

    f. Theproducttreeshallbesubjecttocustomerapproval.

    g. The supplier shall maintain the product tree uptodate under

    configurationcontrol.

    h. Thesuppliershallestablishtheworkbreakdownstructure(WBS)forhis

    workshare,incorporatingtheWBSofeachofhislowertiersuppliers,in

    conformancewithAnnexC.

    i. Work related to manufacturing, assembly, integration and test of all

    productmodelsshallbeshownintheWBS.

    j. Support functions (management, engineering, product assurance) shall

    beidentifiableinconnectionwithitsrelatedproducttreeelements.

    k. TheWBSshallbesubjecttocustomerapproval.

    l. EachsuppliershallmaintainuptodatetheWBSforhisworkshareinthe

    project.

    m. Thesupplier

    shall

    identify

    control

    work

    packages

    based

    on

    the

    approved

    WBS,andthelevelofvisibilityrequiredbythecustomer.

    n. The supplier shall establishwork package (WP) descriptions for each

    workpackageshowninhisWBSinconformancewithAnnexD.

    o. EachWPshallhaveasingleresponsibleWPmanager.

    p. The supplier shallestablishaprojectorganizationbreakdown structure

    (OBS),whichincludes.

    1. theinterfaceandcontractualresponsibilitiesamongsttheinvolved

    parties

    2. thekey

    personnel

    and

    the

    assigned

    responsible

    parties

    for

    each

    workpackageintheWBS

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    34/50

    ECSSMST10CRev.1

    6March2009

    34

    q. TheprojectOBSshallbesubmittedtothecustomerforapproval.

    r. The supplier shallmaintain theapprovedOBS,keep ituptodate, and

    issueittothelowertiersuppliersandthecustomer.

    5.4 Project phasing

    a. The customer shall organize the project into sequential phaseswhich

    includeallprojectspecificreviewsanddecisionmilestones.

    NOTE Phasesandreviewsaredefinedinclause4.4.3.

    b. The customer shall prepare project review procedures for all project

    reviews.

    c. Thecustomershallensurethattheprojectreviewsofhissupplier(s)are

    in linewith the topdown /bottomup sequence of the overall project

    reviewplanning.

    d. Thecustomershalltakethedecisiontomovefromonephasetothenext

    onthebasisoftheoutcomeoftheassociatedendofphasereview.

    NOTE1 Information concerning the expected delivery of

    ECSSmanagementbranchdocumentsper review

    isprovidedinAnnexF.

    NOTE2 Information concerning additional documents

    whicharedefinedasoutputsof themanagement

    standardsrequirementsandwhicharenotpartof

    reviewdatapackagesisprovidedinAnnexG.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    35/50

    ECSSMST10CRev.1

    6March2009

    35

    Annex A (normative)Project management plan (PMP) DRD

    A.1 DRD identification

    A.1.1 Requirement identification and source document

    ThisDRDiscalledfromECSSMST10,requirement5.1.3a.

    A.1.2 Purpose and objective

    ThePMP isprepared tostate thepurposeandprovideabrief introduction to

    theprojectmanagementsystem.Itcoversallaspectsofthelatter.

    A.2 Expected response

    A.2.1 Scope and content

    Introduction

    a. ThePMP shall contain adescription of the purpose, objective and the

    reasonprompting itspreparation(e.g.programorprojectreferenceand

    phase).

    Applicableandreferencedocuments

    a. The PMP shall list the applicable and reference documents used insupportofthegenerationofthedocument.

    Objectivesandconstraintsoftheproject

    a. ThePMPshallbrieflydescribetheobjectiveandconstraintsoftheproject

    inconformancewiththeprojectrequirementsdocuments.

    Projectorganization

    a. The PMP shall describe the project organization approach in

    conformancewith

    the

    requirements

    as

    defined

    in

    clause

    5.2.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    36/50

    ECSSMST10CRev.1

    6March2009

    36

    Projectbreakdownstructures

    a. The PMP shall describe the projectbreakdown structures approach in

    conformance with the project breakdown structure requirements as

    definedinclause5.3andidentifythetitleofindividualdocumentscalled

    upbytheserequirements.

    Configuration,informationanddocumentation

    management

    a. The PMP shall describe the configuration, information and

    documentation management approach, as defined in ECSSMST40,

    AnnexA.

    b. If the configuration, information and documentation management

    approach is contained in a rolledout configurationmanagement plan,

    thePMPmayincludeonlyabriefdescriptiontogetherwithareferenceto

    theconfiguration,informationanddocumentationmanagementplan.

    Costandschedulemanagement

    a. ThePMPshalldescribethecostandschedulemanagementapproach,as

    definedinECSSMST60.

    b. If thecostandschedulemanagementapproach isdescribed inarolled

    out cost and schedulemanagementplan, thePMPmay includeonly a

    brief description together with a reference to the cost and schedule

    managementplan.

    Integratedlogisticsupport

    a. The PMP shall describe the integrated logistic support approach, as

    definedinECSSMST70.

    Riskmanagement

    a. ThePMPshallbrieflydescribe theriskmanagementapproachwhich is

    describedinmoredetailinarolledoutriskmanagementpolicyandplan,

    asdefinedinECSSMST80,AnnexesAandB.

    Productassurancemanagement

    a. The PMP shall describe the product assurancemanagement approach,

    includingtheproposedbreakdownintoPAdisciplinesandtheinterfaces

    betweenthesedisciplines,asdefinedinECSSQST10,AnnexA.

    b. Iftheproductassurancemanagementapproach isdescribed inarolled

    outPAplan,thePMPmayincludeonlyabriefdescriptiontogetherwith

    areferencetotheproductassuranceplan.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    37/50

    ECSSMST10CRev.1

    6March2009

    37

    Engineeringmanagement

    a. The PMP shall describe the engineering management approach,

    including theproposedbreakdown intoengineeringdisciplinesand the

    interfaces between these disciplines, as defined in ECSSEST10,

    AnnexD.

    b. If the engineeringmanagement approach is described in a rolledout

    systemengineeringplan, thePMPmay includeonlyabriefdescription

    togetherwithareferencetothesystemengineeringplan.

    A.2.2 Special remarks

    None.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    38/50

    ECSSMST10CRev.1

    6March2009

    38

    Annex B (normative)Product tree DRD

    B.1 DRD identification

    B.1.1 Requirement identification and source document

    ThisDRDiscalledfromECSSMST10,requirement5.3a.

    B.1.2 Purpose and objective

    Theobjectiveoftheproducttreedocumentistodescribe,inasingledocument,

    thehierarchicalpartitioning of adeliverableproductdown to a level agreed

    betweenthecustomerandsupplier.

    Theproducttreeispartofthedesigndefinitionfile.Itisthestartingpointfor

    selecting configuration items (as specified inECSSMST40) and establishing

    the work breakdown structure. It is a basic structure to establish the

    specificationtree(asdefinedinECSSEST10).

    B.2 Expected response

    B.2.1 Scope and content

    Introduction

    a. Theproduct

    tree

    shall

    contain

    adescription

    of

    the

    purpose,

    objective

    and

    the reasonprompting itspreparation (e.g.programorproject reference

    andphase).

    Applicableandreferencedocuments

    a. Theproduct treeshall list theapplicableandreferencedocumentsused

    insupportofthegenerationofthedocument.

    Treestructure

    a.

    The

    product

    tree

    shall

    provide

    the

    breakdown

    of

    lower

    level

    products

    constitutingthedeliverableproduct.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    39/50

    ECSSMST10CRev.1

    6March2009

    39

    b. For each item identified in theproduct tree, the following information

    shallbeprovided:

    1. identificationcode;

    2. itemname;

    3. itemsupplier;

    4. applicablespecification.

    c. Theproduct treeshallbepresentedeitherasagraphicaldiagramoran

    indenturedstructurewheretheproduct(i.e.atthetoplevelofthetree)is

    decomposedintolowerlevelproducts.

    d. Eachproductitemselectedasconfigurationitemshallbeidentifiedinthe

    producttree.

    e. When recurrent products from previous space projects are used, they

    shallbeidentifiedinthetreestructure.

    B.2.2 Special remarks

    None.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    40/50

    ECSSMST10CRev.1

    6March2009

    40

    Annex C (normative)Work breakdown structure (WBS) DRD

    C.1 DRD identification

    C.1.1 Requirement identification and source document

    ThisDRDiscalledfromECSSMST10,requirement5.3h.

    C.1.2 Purpose and objective

    Theobjectiveoftheworkbreakdownstructure(WBS)istoprovide,inasingle

    document,aframeworkforprojectincostandschedulemanagementactivities

    (as defined in ECSSMST60) and formanaging technical content. It assists

    projectsactorsin:

    conductingtendercomparisonsandbusinessagreementnegotiations;

    optimizingthe

    distribution

    of

    work

    amongst

    the

    different

    suppliers;

    monitoringthescheduleoftheproject.

    TheWBS divides the project intomanageablework packages, organizedby

    natureofwork.It identifiesthetotalworktobeperformeddowntoa levelof

    detailagreedbetweenthecustomerandsupplier.

    Information concerning the determination of the appropriate WBS level of

    detailisprovidedinECSSMST10,AnnexH.

    C.2 Expected response

    C.2.1 Scope and contents

    Introduction

    a. TheWBS shall contain adescription of the purpose, objective and the

    reasonprompting itspreparation(e.g.programorprojectreferenceand

    phase).

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    41/50

    ECSSMST10CRev.1

    6March2009

    41

    Applicableandreferencedocuments

    a. The WBS shall list the applicable and reference documents used in

    supportofthegenerationofthedocument.

    Treestructure

    a. The WBS shall provide a logical and exhaustive breakdown of the

    product tree elements, that includes the customers defined support

    functions (e.g. project management, engineering, product assurance

    support)necessary toproduce the end itemdeliverables (development

    and flight models) and the necessary services as appropriate for the

    project.

    b. A coding scheme for WBS elements that represents the hierarchical

    structurewhenviewedintextformatshallbeused.

    NOTE1 A common coding system facilitates

    communicationsamongallprojectactors.

    NOTE2 E.g.:toeachWBSelementisassignedacodeused

    for its identification throughout the life of the

    project.Itcanbeasimpledecimaloralphanumeric

    coding system that logically indicates the levelof

    an element and related lowerlevel subordinate

    elements.

    c. TheWBSshallidentifyallcontrolworkpackages.

    d. Thecontrolworkpackagesmaybefurtherbrokendownbythesupplier

    inseveralmoredetailedworkpackages.

    e. Alldefinedworkpackagestogethershallcoverthetotalworkscope.

    f. The WBS shall be presented either as a graphical diagram or an

    indenturedstructure.

    C.2.2 Special remarks

    None.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    42/50

    ECSSMST10CRev.1

    6March2009

    42

    Annex D (normative)Work package (WP) description DRD

    D.1 DRD identification

    D.1.1 Requirement identification and source document

    ThisDRDiscalledfromECSSMST10,requirement5.3n.

    D.1.2 Purpose and objective

    Theobjectiveoftheworkpackagedescriptionistodescribethedetailedcontent

    ofeachelementoftheWBSasdefinedinECSSMST10,AnnexC.

    D.2 Expected response

    D.2.1 Scope and content

    a. TheWPdescriptionshallcontainthefollowingelements:

    1. projectnameandprojectphase;

    2. WPtitle;

    3. uniqueidentificationofeachWPandissuenumber

    4. supplierorentityinchargeoftheWPperformance;

    5. WPmanagersnameandorganization;

    6. supplierscountry;

    7. product towhich the tasks of theWP are allocated (link to the

    producttree);

    8. descriptionoftheobjectivesoftheWP;

    9. descriptionofthetasks;

    10. listoftheinputsnecessarytoachievethetasks;

    11. interfacesorlinkswithothertasksorWPs;

    12. listofconstraints,requirements,standards,andregulations;

    13. listoftheexpectedoutputs;

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    43/50

    ECSSMST10CRev.1

    6March2009

    43

    14. listofdeliverables;

    15. locationofdelivery;

    16. starteventidentificationincludingdate;

    17. endeventidentificationincludingdate;

    18. excludedtasks.

    D.2.2 Special remarks

    None.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    44/50

    ECSSMST10CRev.1

    6March2009

    44

    Annex E (normative)Progress report DRD

    E.1 DRD identification

    E.1.1 Requirement identification and source document

    ThisDRDiscalledfromECSSMST10,requirement5.2.2.2a.

    E.1.2 Purpose and objective

    The objective of the progress report is to provide all actors with actual

    informationconcerningthestatusoftheproject.

    E.2 Expected response

    E.2.1 Scope and content

    a. Theprogressreportshallcontainthefollowinginformation:

    1. The project managers assessment of the current situation in

    relation to the forecasts and risks, at a level of detail agreed

    betweentherelevantactors.

    2. The status of the progress of work being performed by the

    supplier.

    3. Statusandtrendsofagreedkeyperformanceandengineeringdata

    parameters.

    4. Adverse trends in technical and programmatic performance and

    proposalsforremedialactions.

    5. Planningforimplementationofremedialactions.

    6. Aconsolidatedreportderivedfromthelowertiersuppliersstatus

    reports.

    7. Progressonallactionssincethepreviousreport.

    E.2.2 Special remarksNone.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    45/50

    ECSSMST10CRev.1

    6March2009

    45

    Annex F (informative)ECSS management branch documents

    delivery per review

    TableF1provides the information concerning theexpecteddeliveryofECSS

    managementbranchdocumentsperreview.

    NOTE This table constitutes a first indication for thedata package content at various reviews. The

    fullcontentofsuchdatapackageisestablished

    as part of thebusiness agreement,which also

    defines thedelivery of thedocumentbetween

    reviews.

    The various crosses in a row indicate the increased levels of maturity

    progressivelyexpectedversusreviews.Thelastcrossinarowindicatesthatat

    thatreviewthedocumentisexpectedtobecompletedandfinalized.

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    46/50

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    47/50

    ECSSMST10CRev.1

    6March2009

    47

    Annex G (informative)Management documents delivery

    (periodic or incident triggered)

    TableG1liststhedocumentswhicharedefinedasoutputsofthemanagement

    standardsrequirementsandwhicharenotpartofreviewdatapackages.

    TableG1:Managementdocumentsdelivery(periodicor

    incidenttriggered)

    DocumentTitle DRDref.

    Costbreakdownstructure ECSSMST60,AnnexA

    Scheduleprogressreport ECSSMST60,AnnexC

    CompanyPriceBreakdownForms ECSSMST60,AnnexD

    GeographicalDistributionReport ECSSMST60,AnnexE

    CostEstimatingPlan ECSSMST60,AnnexF

    MilestonePaymentPlan ECSSMST60,AnnexH

    InventoryRecord ECSSMST60,AnnexI

    CostandManpowerReport ECSSMST60,AnnexJ

    OBCPandCBCPforCostReimbursement ECSSMST60,AnnexK

    OBCPandCBCPforFixedPrice ECSSMST60,AnnexL

    EACandETCforCostReimbursement ECSSMST60,AnnexM

    EACforFixedPrice ECSSMST60,AnnexN

    ContractChangeNotice ECSSMST60,AnnexO

    Changerequest ECSSMST40,AnnexG

    Changeproposal ECSSMST40,AnnexH

    Requestfordeviation ECSSMST40,AnnexI

    Requestforwaiver ECSSMST40,AnnexJ

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    48/50

    ECSSMST10CRev.1

    6March2009

    48

    Annex H (informative)Determination of the appropriate

    WBS level of detail

    Themainchallengeassociatedwithdevelopingtheworkbreakdownstructure

    (WBS)istodeterminethebalancing between theprojectdefinitionaspects

    of

    the

    WBS

    and

    the

    requirements

    for

    data

    collecting

    and

    reporting.

    One

    has

    tokeep inmind that theWBS isa tooldesigned toassist theprojectmanager

    whendecomposingtheprojectonlytothelevelsnecessarytomeettheneedsof

    theproject,thenatureofthework,andtheconfidenceoftheteam.

    An excessive WBS levels can lead to unrealistic levels of maintenance and

    reporting,andconsequentlytoaninefficientandovercostlyproject.Thetheory

    thatmoremanagement data equates tobettermanagement control hasbeen

    proven false many times over in the last decades when assessing systems

    performance.On theotherhand, ifnotdetailedenough itmakes theelement

    difficulttomanageortheriskunacceptable.

    Among thedifferentquestionsarisingwhendevelopingaWBS,an important

    oneis:shouldtheWBSbedecomposedfurther?

    Tohelpansweringthisquestion,weproposethefollowinglistofquestions.If

    mostof thequestions canbeansweredYES, then theWBSelementanalyzed

    should be decomposed. On the contrary, if most of the questions can be

    answeredNO, then this is not necessary. If the answers are approximately

    50/50,thenadditionaljudgmentisneeded.

    Is there a need to improve the assessment of the cost estimates or

    progressmeasuringoftheWBSelement?

    Is theremore than one individual responsible for theWBS element?

    Oftenavariety

    of

    resources

    are

    assigned

    to

    aWBS

    element,

    aunique

    individual is assigned the overall responsibility for the deliverable

    createdduringthecompletionoftheWBSelement.

    Does theWBS element content includemore than one type of work

    processorproducesmorethanonedeliverableatcompletion?

    Isthereaneedtoassessthetimingofworkprocessesthatareinternalto

    theWBSelement?

    Is thereaneed toassess thecostofworkprocessesordeliverables that

    areinternaltotheWBSelement?

    Are

    there

    interactions

    between

    deliverables

    within

    a

    WBS

    element

    to

    anotherWBSelement?

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    49/50

    ECSSMST10CRev.1

    6March2009

    49

    Are there significant time gaps in the execution of thework processes

    thatareinternaltotheWBSelement?

    DoresourcerequirementschangeovertimewithinaWBSelement?

    Are there acceptance criteria, leading to intermediate deliverable(s),

    applicablebefore

    the

    completion

    of

    the

    entire

    WBS

    element?

    Arethereidentifiedrisksthatrequirespecificattentiontoasubsetofthe

    WBSelement?

    Can a subsetof thework tobeperformedwithin theWBS elementbe

    organizedasaseparateunit?

  • 7/31/2019 Ecss m St 10c Rev.1(6march2009)

    50/50

    ECSSMST10CRev.1

    6March2009

    Bibliography

    ECSSSST00 ECSSsystemDescription,implementationand

    generalrequirements

    ECSSEST10 SpaceengineeringSystemengineeringgeneral

    requirements

    ECSSEST40 SpaceengineeringSoftwaregeneralrequirements

    ECSSE

    ST

    70

    Space

    engineering

    Ground

    systems

    and

    operations

    ECSSMST1001 SpaceprojectmanagementOrganizationand

    conductofreviews

    ECSSMST60 SpaceprojectmanagementCostandschedule

    management

    ECSSMST70 SpaceprojectmanagementIntegratedlogistic

    support

    ECSSMST80 SpaceprojectmanagementRiskmanagement

    ECSSQST10 SpaceproductassuranceProductassurance

    management