E-PASS Inception Project Management and Oversight
-
Upload
epass2015 -
Category
Environment
-
view
576 -
download
1
Transcript of E-PASS Inception Project Management and Oversight
Empowered lives.
Resilient nations.
Project Cycle and
Monitoring & Evaluation
Midori Paxton Regional Technical Adviser, Ecosystems and Biodiversity
E-PASS Project Inception Workshop Bogor, Indonesia, November 19-20, 2015
Outline
1. Global Environmental Facility
2. Project Implementation
Responsibilities and Project Cycle
3. Adaptive Management
4. Reporting
5. Risk Management
What is GEF? Financial mechanism for international
conventions: CBD, UNFCCC, UNCCD, Stockholm Convention on POPs
Mechanism for financing “incremental costs” of new “global environment” actions by developing countries ;
Trust fund established in 1991
Invested $ 31.5 biil, leveraging $ 65 bil. In co-financing, for >3,900 projects in 165 developing countries (29% BD)
UNDP is a GEF implementing agency
UNDP/GEF project implementation responsibilities
Formal
delegation of
authority to
implement the
GEF project
M&E
responsibilitie
s
Reporting
responsibi-
lities
GEF Secretariat (DC)
UNDP/EEG (NY)
UNDP Country Office
– Myanmar
OFP and Government
Executing Agency
PSC PMO
UNDP/EEG Regional
Center - Bangkok
Project Implementation Cycle
Project
Approval
DOA and ProDoc
signature Project staff recruitment
Inception Workshop /
Inception Report Mid-term
Review TT
Terminal Evaluation,
TT
Project Closure
LPAC
GEF GEF
No no-cost extension !
ADAPTIVE MANAGEMENT What is it?
Project is adaptive when it anticipates challenges and
responds effectively
• Focus on “results”:
– Progress towards impact indicators
– Navigate towards the targets under changing environment
• The “process” should change to take account of:
– New risks or change in risk rating
– Monitoring results (current strategy not working)
– Situation changes
– New opportunities
ADAPTIVE MANAGEMENT What changes are allowed?
• Objective level: – Clearance from GEF in Washington D.C. – Revised Project Document – very difficult process – It is basically a new project – so not recommended, as you will need to
resubmit
• Outcome level: – Clearance from UNDP-GEF, reported to GEF – Revised Project Document – Not recommended , resubmission might be necessary
• Output/Activity level: – Clearance from PSC and UNDP-CO, reported to RTA – Revised Workplan, Budget Revision
• Input level: – Agreement with UNDP-Regional Technical Advisor – Substantive Budget Revisions cleared by RCU
REPORTING ON PROGRESS
Inception report
Quarterly report
Project Implementation
Reviews /Annual Project Report
Inception Report 1. Project Inception Update
2. Updated risk analysis and SESP
3. Implementation Plan
4. Workplan for 2016 - 2017
5. Terms of Reference for all the consultancies and subcontracts to be procured in 2016 – a full and advertisement-ready version based on the bullet points provided in the ProDoc
6. Updated Logical Framework
7. Information on project staff, name, qualification and contacts etc
8. Monitoring and Evaluation Plan for monitoring of each indicator in the strategic results framework
9. Gender mainstreaming plan (indicating how gender can be mainstreamed in each output)
10. Sustainability plan (indicating (indicating how each output and outcome will be sustained beyond the project period)
Project Implementation Report (PIR)
Main GEF monitoring tool. Systematic portfolio-wide data and information collected
Annually in July
Excel format
Progress reporting: DO, IP, tracking tool
Performance rating by PMU, EA, CO and Regional Unit
Some issues to monitor in APR/PIRs
4. Partnerships: lessons learned
working with indigenous
communities, NGOs, private Sector,
Small Grants Programme
5. Gender: how being addressed in
project implementation
1. Progress: ratings. Encourage GEF OFP to rate progress as well
Toward development objective (DO) = objective + outcome level,
cumulative Implementation progress (IP) = outputs + inputs,
process + delivery , annual
2. Risk: critical risk in ATLAS + progress ratings = GEF risk system
(high, moderate, low)
3. Evaluation: how will the project address recommendations of MTE
and FE
Value of the APR/PIRs 1. Project implementation: remind project team what the project is
after, signals whether strategies should be adjusted, flags constraints to find solutions
2. UNDP: identifies best practice and lessons to share across the portfolio ,
and to integrate into project design
• UNDP GEF Focal Area Performance reports + UNDP GEF Annual Performance Report
• Information provided to UNDP communications and Executive Office for speeches, UNDP reports to Executive Board, UNDP annual report
• UNDP Evaluation Office uses in country evaluations
3. GEF: • Secretariat prepares Annual Monitoring Report for GEF Council, used by Focal
Areas to adjust strategies
• Evaluation Office uses for strategic evaluations
APR/PIRs MOVING FROM:
• Only a donor requirement
TO:
• Tool for adaptive management + results reporting
Mid-Term Review and Terminal Evaluations
• Mandatory independent evaluation
• Organized by the UNDP CO and
facilitated by the project
• Conduct the Tracking Tools (METT
and Financial Scorecard) before
MTR and TE
• MTE and TE reports sent to GEF
M&E for review and quality control
• Prepare management response
after evaluation
UNDP/GEF Risk Management System
GEF - funded projects are complex and therefore likely to face risks
and challenges
- SEVEN STANDARD RISK CATEGORIES – all projects should monitor
• ENVIRONMENTAL
• FINANCIAL • OPERATIONAL
• ORGANIZATIONAL
• POLITICAL • REGULATORY
• STRATEGIC
• OTHER
2. FINANCIAL External: interest rates, exchange rate fluctuations,
bank collapses etc;
Internal: co-funding difficulties; financial mechanisms
3. OPERATIONAL RISKS
Ineffective Management
Professional negligence
Human error/incompetence
Safety being compromised
Infrastructure failure
Poor monitoring and evaluation
Slow delivery
4. ORGANIZATIONAL RISKS Institutional arrangements. Institutional / Execution
capacity. Implementation arrangements. CO capacity
5. REGULATORY RISKS: New unexpected regulations, policies. Critical policies or legislation fails to pass or
progress in the legislative process
6. POLITICAL RISKS
Government commitment
Political will
Political instability.
Change in government
Armed conflict and
instability.
OTHER RISKS - whatever doesn’t fit in the other categories -
Poaching
Encroachment
Population pressure
RISK CLASSIFICATION BASED ON THE LEVEL OF CONTROL:
• Risks that arise from factors potentially under your control (e.g. ineffective management, poor performance by contractors)
• Risks that arise from wider policy and institutional environment, which are only controllable by decision makers elsewhere (e.g. poor policy environment, institutional weakness, lack of political will)
• Risks that are essentially uncontrollable (e.g. natural disasters, political instability, interest rates)
PROJECT CLASSIFICATION ACCORDING TO RISK
•Standard
-No critical risks
-No unresolved key issues
•Potential problem project
-One or more critical risks
•Actual problem project
One or more key unresolved issues
Identified Risks 1. Poaching pressure fuelled by the existence of
global illegal wildlife trade may decimate wildlife populations (Medium)
2. Provincial and District Governments may be reluctant to promote conservation oriented land use with a fear of losing state revenues(Medium)
3. International and national REDD Plus process does not progress fast enough loses the confidence among the project stakeholders. (Medium)
4. Major natural disasters (earthquake, floods, volcanic eruption etc.) inhibit the increase in national and provincial government investment in PA system (Medium)
5. Climate change may undermines the conservation objectives of the Project (Low)