DVM PLUS III line up
Ton HP
6 7.5 36 MBH ~ 93.6 MBH 50~130% 10
8 10 48 MBH ~ 124.8 MBH 50~130% 13
10 12.5 60 MBH ~ 156.0 MBH 50~130% 16
BasicModel
Classification Capacity Total capacity of connectableindoor units (MBH)
RVXVHT125FE
Maximum Number ofconnectable indoor units
Model name
RVXVHT075FE
RVXVHT100FE
![Page 3: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/3.jpg)
Space requirements1) Single installation
2) Group installation
![Page 4: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/4.jpg)
Installing outdoor unit
![Page 5: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/5.jpg)
Anchor bolt position
![Page 6: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/6.jpg)
Remove stopper
■ Remove stopper
√ 10 Ton : 4 pieces of stopper in legs of compressor
The stopper is just using only for transportation, not operation
![Page 7: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/7.jpg)
Piping layouts (HP)
■ Y joint only ■ Y joint with Header joint
![Page 8: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/8.jpg)
EEV Kit
![Page 9: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/9.jpg)
Piping length (HP)
1st Refnet Joint
Main pipeY joint
![Page 10: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/10.jpg)
Piping length (HP)
![Page 11: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/11.jpg)
Piping length (HP)
![Page 12: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/12.jpg)
Main pipe 1 size increasing
Examples
Example) 34 HP With 1 bigger size, it can increase cooling capacity by 16.8
%.
![Page 13: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/13.jpg)
1. 명기된 사양은 개발진행에 따라 변경 될 수 있습니다 .
2. 배관은 미주 지역에서 구입 가능한 배관으로 선정되어 있습니다 .
현지에서 구매가 불가능한 배관을 제외 (1, 1 ¼, 1 ½ ) 하였기에 , 배관 선정 사양이 기존의 DVM PLUS 2 대비 해서 ,
변경될 소지가 있으니 참고 하시길 바랍니다 .
( 위에 말씀 드린 것처럼 첨부된 문서의 설치 사양은 변경될 소지가 있습니다 .)
Selection the refrigerant pipe
![Page 14: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/14.jpg)
■ Definitions
Outdoor unit Branched pipes from outdoor joints to outdoor
Branched pipes between out-door joints
Main Pipes
A1
A2
A3
B Branched pipes between branch joints
C Pipes to indoor units
D Outdoor joints
Branch joints (Indoor joints)E, F
![Page 15: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/15.jpg)
Piping Diameter for each Outdoor unit (A1)
Ton HPLiquid Gas H.P. Gas
mm inch mm inch mm inch
6 7.5 9.52 3/8 19.05 3/4 15.88 5/8
8 10.0 9.52 3/8 22.23 7/8 19.05 3/4
10 12.5 12.70 1/2 28.58 1 1/8 22.23 7/8
A1
■ Step 1 – Select pipes to outdoor units from ‘outdoor joints’
■ Step 2 – Select pipes between outdoor joints
Piping Diameter for between outdoor joints (A2)
Ton HPLiquid Gas H.P. Gas
mm inch mm inch mm inch
6 7.5 9.52 3/8
19.05 3/4 15.88 5/8
8 10.0 22.23 7/8 19.05 3/4
10 12.5 12.70 1/2
28.58 1 1/8
22.23 7/812 15.0
14 17.5
15.88 5/8
28.58 1 1/8
16 20.0
18 22.5
20 25.0
19.05 3/4 34.93 1 3/8
22 27.5
24 30.0
26 32.5
28 35.0 34.93 1 3/8
30 37.5
A2
![Page 16: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/16.jpg)
■ Step 3 – Select “Main” pipes
Piping Diameter for “Main” pipes (A3)
Ton HPLiquid Gas H.P. Gas
mm inch mm inch mm inch
6 7.5 9.52 3/8
19.05 3/4 15.88 5/8
8 10.0 22.23 7/8 19.05 3/4
10 12.5 12.70 1/2
28.58 1 1/8
22.23 7/812 15.0
14 17.5
15.88 5/8
28.58 1 1/8
16 20.0
18 22.5
20 25.0
19.05 3/4 34.93 1 3/8
22 27.5
24 30.0
26 32.5
28 35.0 34.93 1 3/8
30 37.5
A3
![Page 17: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/17.jpg)
■ Step 3 – Upsizing “Main” pipes, When?
If the piping length between outdoor to the farthestindoor unit is over 90m (295ft), use right table.
Main Pipe Diameter (A3) in case of the farthest indoor unit over 90m
Ton HPLiquid Gas H.P. Gas
mm inch mm inch mm inch6 7.5
12.70 1/222.23 7/8 19.05 3/4
8 10.0 28.58 1 1/8
22.23 7/810 12.5
15.88 5/8
28.58 1 1/812 15.0
34.93 1 3/8
14 17.5 19.05 3/416 20.0
18 22.5 20 25.0
22.23 7/8 34.93 1 3/8
22 27.5 24 30.0 26 32.5 28 35.0
41.28 1 5/830 37.5
Main Pipe Diameter (A3)
Ton HPLiquid Gas H.P. Gas
mm inch mm inch mm inch6 7.5
9.52 3/819.05 3/4 15.88 5/8
8 10.0 22.23 7/8 19.05 3/410 12.5
12.70 1/2
28.58 1 1/8
22.23 7/812 15.0 14 17.5
15.88 5/8
28.58 1 1/8
16 20.0 18 22.5 20 25.0
19.05 3/4 34.93 1 3/8
22 27.5 24 30.0 26 32.5 28 35.0
34.93 1 3/830 37.5
Outdoor unit
The farthest indoor unit
A3
A3
![Page 18: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/18.jpg)
■ Step 4 – Select ‘Outdoor joints’
■ Step 5 – Select the first ‘Branch joints’
Model Name Outdoor unit’s capacity
Liquid & low Pressure gas pipe MXJ-T3819K 12 ~ 30 Ton
High Pressuregas pipe MXJ-T3100K 12 ~ 30 Ton
D
Model Name Outdoor unit’s capacity
Liquid & low Pres-sure gas pipe Joints
MXJ-YA2512K 6, 8,10 Ton
MXJ-YA2812K 12 Ton
MXJ-YA2815K 14,16,18,20 Ton
MXJ-YA3119K 22, 24, 26, 28 Ton
MXJ-YA3819K 30 Ton
High Pressuregas pipe Joints
MXJ-YA1500K 6 Ton
MXJ-YA2500K 8, 10, 12, 16, 18 Ton
MXJ-YA3100K 20, 22, 24, 26, 28, 30 Ton
E
![Page 19: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/19.jpg)
(A1)
(A1) (A1)
(A2)
RVXVHT100FE RVXVHT125FE RVXVHT125FE
Liquid : 3/8Gas : 7/8
Liquid : 1/2Gas : 1 1/8
Liquid : 1/2Gas : 1 1/8
Liquid : 5/8Gas : 1 1/8
A2 capacity = A1 capacity + A1 capacityExample)A1 : 7.5 HP → Liquid : 3/8”, Gas : 3/4”A1 : 7.5 HP → Liquid : 3/8”, Gas : 3/4”A2 : 15.0 HP → Liquid : 1/2”, Gas : 1 1/8”
■ Step 5 – Example
![Page 20: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/20.jpg)
Total indoor unit's capac-ity
Pipe Diameter (OD, mm/inch)
Liquid Gas H.P. Gas
mm inch mm inch mm inch
51 MBH↓ 9.52
3/8
15.88 5/8 15.885/8
51 ~ 79 MBH 9.52 19.05 3/4 15.88
79 ~ 96 MBH 9.52 22.23 7/8 19.05 3/4
96 ~ 138MBH 12.70 1/2
28.58
1 1/8
22.237/8
138 ~ 160 MBH 12.70 28.58 22.23
160 ~ 240 MBH 15.88 5/8
28.58 28.581 1/8
240 ~ 336 MBH 19.50 34.931 3/8
28.58
336 ~ 468 MBH 19.50 3/4 34.93 34.93 1 3/8
■ Step 6 – Select branched pipes between ‘branch joints’
■ Step 7 – Select ‘Branch joints’
F
B
Model Name Total indoor unit's capacity
Liquid & low Press-sure
gas pipe Joints
MXJ-YA1509 51 MBH and below
MXJ-YA2512 Over 51 MBH ~ 138 MBH and below
MXJ-YA2812 Over 138 MBH ~ 160 MBH and below
MXJ-YA2815 Over 160 MBH ~ 240 MBH and below
MXJ-YA3119 Over 240 MBH ~ 336 MBH and below
MXJ-YA3819 Over 336 MBH ~ 468 MBH and below
High Pressuregas pipe Joints
MXJ-YA1500K 79 MBH and below
MXJ-YA2500K Over 79 MBH ~ 240MBH and below
MXJ-YA3100K Over 240 MBH ~ 468 MBH and below
![Page 21: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/21.jpg)
■ Step 8 – Select pipes to indoor units
Indoor unit's capacity
Pipe Diameter (OD, mm/inch)
Liquid Gas
mm inch mm inch
6 ~ 20 MBH 9.52 3/8 12.70 1/224 ~48 MBH 12.70 1/2 15.88 5/8
![Page 22: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/22.jpg)
Additional refrigerant
√ Additional refrigerant has to be charged according to the length and size of liquid pipe.
Liquid pipe size (O.D. mm) Additional refrigerant charging (lbs/ft)
Φ 1/4 (Φ 6.4) 0.01344
Φ 3/8 (Φ 9.5) 0.04032
Φ 1/2 (Φ 12.7) 0.08400
Φ 5/8 (Φ 15.9) 0.12095
Φ 3/4 (Φ 19.1) 0.18143
Φ 7/8 (Φ 22.2) 0.23519
MCU lbs
Each MCU 1.1
Liquid line after expanding(From Sing EEV kits, or From MCUs) lbs
Each liquid line 0.022
![Page 23: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/23.jpg)
Outdoor joint (HP, HR)
Ex) MXJ-T3819*, MXJ-T4422 - Liquid connection - Gas connection
![Page 24: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/24.jpg)
Outdoor joint (HR Only)
Ex) MXJ-T3100* - High pressure gas connection
![Page 25: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/25.jpg)
Y- joint (HP, HR)
Ex) MXJ-YA1509
![Page 26: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/26.jpg)
Ex) MXJ-YA1500 ~ MXJ-YA3800
Y- joint (HR Only)
![Page 27: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/27.jpg)
Header- joint (HP only)
Ex) MXJ-HA2512
![Page 28: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/28.jpg)
■ Refrigerant piping should be the same level or lower than connecting position.
Outdoor units piping
Correct piping work Wrong piping work
Accumulating of oil
![Page 29: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/29.jpg)
■ Refrigerant piping should be connected with side direction.
Correct piping work Wrong piping work
Unbalancing of Ref. & oil distribution
Refrigerant can excessively leans to one direction.
Outdoor units piping
![Page 30: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/30.jpg)
■ Refrigerant piping should be connected with side direction.
Correct piping work Wrong piping work
Refrigerant can excessively leans to one direction.
Outdoor units piping
![Page 31: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/31.jpg)
■ Refrigerant piping should be installed in a horizontal direction.
Correct piping work Wrong piping work
Min. 4 inch
Be horizontal
Outdoor units piping
![Page 32: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/32.jpg)
■ Vertical trap
Correct piping work Wrong piping work
Vertical trap
Outdoor units piping
40 inch
80 inch
80 inch
8 ~ 12 inch
![Page 33: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/33.jpg)
■ Connecting the outdoor unit pipe
Single installation Module installation
Outdoor units piping
Front connection
Bottom connection
Front connection
Bottom connection
Oil valve size : 1/4 inch
![Page 34: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/34.jpg)
Y joint installation
Refnet Y Joint Installation
Y Joint
Vertically installed
Horizontally installed
Vaporized refrigerant leans to upper direction in Y joint.
For uniform refrigerant distribution
![Page 35: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/35.jpg)
Header joint installation
Refnet Head Joint Installation
Liquid head Joint
Vaporized refrigerant leans to one of direction in branch joint.
Header Joint
Gas head Joint
Do not install vertically.
Header Joint
![Page 36: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/36.jpg)
Header joint installation
Connect according to larger capacity of indoor unit in order
![Page 37: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/37.jpg)
Piping work
Nitrogen replacement before brazing
Without nitrogen gas blowing With nitrogen gas blowing
Taping
![Page 38: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/38.jpg)
Insulation work
※ Application condition : indoor temperature : 80 , 80% RH℉
![Page 39: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/39.jpg)
Insulation work
![Page 40: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/40.jpg)
Insulation work
![Page 41: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/41.jpg)
Wiring work
3 Phase 3 wiresCaution
Be sure to install the switch and the fuse to the power line of each equipment.(Field wiring work)
![Page 42: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/42.jpg)
Wiring workCaution of wiring work
Note
Use ring terminal for wiring terminal block
Hold wiring with using cable tie
208 ~ 230V
208 ~ 230V208 ~ 230V
![Page 43: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/43.jpg)
Wiring work
![Page 44: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/44.jpg)
Leak test
![Page 45: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/45.jpg)
Vacuum drying
Oil piping should be performed a vacuum
![Page 46: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/46.jpg)
Setting option switch
PCB
Transformer
CT Sensor
Magnet
Power TB
Outdoor-indoor unit communicationOutdoor – outdoor unit communication
BLDC FanDriver
Filter PCB
Outdoor’s control part
![Page 47: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/47.jpg)
Setting option switch
220 V outputSensor
![Page 48: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/48.jpg)
Setting option switch
![Page 49: DVM PLUS III INSTALLATION (Preliminary)](https://reader038.fdocuments.net/reader038/viewer/2022102819/568161c5550346895dd1aa70/html5/thumbnails/49.jpg)
Tool Using reason Specification
Manifold gauge
•R410A is composed H-F-C as different as R22 is composed C-F-Cl.•Don't use mineral oil when gauge pressure to prevent contamination.•Only for R410A.
•High pressure gauge : -0.1~5.3㎫•Low pressure gauge : -0.1~3.8㎫•Connection port diameter : 5/16 flare•No oil used
Manifoldcharginghose
•Change in service port diameter•R410A has high pressure as compared with R22.•It should be made of materials are not affected a using refrigerant.
•Working pressure : 5.08㎫•Bursting pressure : 25.4㎫•Connection port diameter : 5/16 flare
Vacuum pump
•R410A is used with a ploy ester oil but a vacuum pump uses a conventional mineral oil.
•The degree of vacuum is 5torr Need a check valve to prevent re� -verse oil flow if using a conventional vacuum pump
Flaring Tool
•Need a flare gauge for R410A.•When using a conventional flare tool, the pipe extension margin should be 1.0~1.5mm or 1.5~2.0.
Torque spanners
•R410A has high pressure as compared with R22. •Increase a connecting torque.
*Adding a proper torque to the pipe using R410A when connect pipes to flare nuts.
Refrigerantoil
•Coat the connection with refrigerant oil film. If not, leakage is possible because of the pressure of R410A.•Coat after flare work on pipe connection.
•All refrigerants are available as using a synthetic oil•High rust resistance •Long stability over long period time
Gas leak tester
•Since R410A don't have chlorine, the tester must can detect Hydrogen.
•R410A,R407C(E),R404A,R507A,R134a,R12,R22,R502,R500 are detected.•Available in the range of 0 to 40 .℃
nominal dimension Torque (N·m)6.35 14.2~17.29.52 32.7~39.912.70 49.5~60.315.88 61.8~75.4
DA(㎜ )
flare tool fit on R410A conventional flare toolclutch type wing nut type
6.35 0~0.5 1.0~1.5 1.5~2.09.52 0~0.5 1.0~1.5 1.5~2.0
12.70 0~0.5 1.0~1.5 1.5~2.015.88 0~0.5 1.0~1.5 1.5~2.0