Dushanbe May 20, 2013

17
Dushanbe May 20, 2013 Progress Update and Planning for Next Steps

description

Progress Update and Planning for Next Steps. Dushanbe May 20, 2013. Kazakhstan. Reserves. :. Oil. 30 billion bbl. Natural Gas. 8 5. TCF. Coal. 31.3 billion tons. Kyrgyz. st. an. Hydro Power. 20,000 M. W. Reserves. :. Oil. 0 .04 billion bbl. Natural Gas. 0.2 TCF. Coal. - PowerPoint PPT Presentation

Transcript of Dushanbe May 20, 2013

Page 1: Dushanbe May 20, 2013

DushanbeMay 20, 2013

Progress Update and Planning for Next Steps

Page 2: Dushanbe May 20, 2013

Kazakhstan Reserves:

Oil 30 billion bbl Natural Gas 85 TCF Coal 31.3 billion tons Hydro Power 20,000 MW

Uzbekistan Reserves:

Oil 594 million bbl Natural Gas 66 TCF Coal 3.3 billion tons Hydro Power 1,700 MW

Turkmenistan Reserves:

Oil 600 million bbl Natural Gas 280 TCF Coal Modest Hydro Power Modest

Tajikistan Reserves:

Oil 0.01 billion bbl Natural Gas 0.2 TCF Coal 3.6 billion tons Hydro Power 40,000 MW

Kyrgyzstan Reserves:

Oil 0.04 billion bbl Natural Gas 0.2 TCF Coal 0.9 billion tons Hydro Power 26,000 MW

Central Asia is endowed with vast energy potential…

Page 3: Dushanbe May 20, 2013

…whereas Afghanistan and Pakistan face severe electricity shortages and rapidly increasing demand

Electricity riots in Rawalpindi, PakistanGuardian photo

Country Population Million

GNI per capita Current US$

Per Capita Electricity Consumption (kWh/year)

Installed Capacity

(GW)Access Rate

Peak shortage

(MW)

Afghanistan 29 310 31 0.5 13% --

Pakistan 166 1000 413 19.8 84% 5,022

Power network in Kabul, AfghanistanKabulkarzaiblogspot photo

Page 4: Dushanbe May 20, 2013

4

The proposed CASA-1000 transmission facilities would:

maximize the use of 1,300 MW renewable summer electricity surplus from existing plants in

Central Asia(Kyrgyz Republic & Tajikistan)

and

provide electricity to consumers in electricity

deficient South Asia (Afghanistan & Pakistan)

Page 5: Dushanbe May 20, 2013

5

Even without new power generation, Kyrgyz Republic and Tajikistan have sufficient electricity

surplus during summers to warrant CASA-1000

3,750 GWh

18,815 GWh

Summer surplus

Domestic consumption

2,150 GWh

14,585 GWh

Power domestic consumption and summer surplus (est. 2016 based on feasibility report)

Tajikistan* Kyrgyz Republic

*Tajikistan spills water from its dams without generating electricity during the summer

Page 6: Dushanbe May 20, 2013

6

The CASA-1000 project includes:

500 kV line Datka-Khudjand (477 km), with Tajik network transferring Kyrgyz exports to Sangtuda.

Tajikistan Grid Strengthening. 1300 MW AC-DC Convertor Station at

Sangtuda. 750 km HVDC line Sangtuda-Kabul-

Peshawar. 300 MW Convertor Station at Kabul

(with both import & export capability).

1300 MW DC-AC Convertor Station at Peshawar.

Page 7: Dushanbe May 20, 2013

7

CASA-1000 benefits all four countries:

• Ensures a steady source of revenue from surplus hydropower exports for

Tajikistan and Kyrgyz Republic, the weakest economies in Central Asia

• Uses excess summer electricity that is currently being spilled

• Alleviates electricity shortages in Pakistan during the peak summer season

• Replaces fuel-based power generation in Afghanistan and Pakistan with

clean hydropower

• Establishes Afghanistan as a viable transit country, enhancing growth

prospects

Requires no new power generation investments

Page 8: Dushanbe May 20, 2013

Project cost estimates per the feasibility study

8

Kyrgyz Republic US$ 200 millionTajikistan US$ 250 millionAfghanistan US$ 300 millionPakistan US$ 200 millionTotal US$ 950 million

• US$1 billion investment in countries with constrained borrowing capacity

• US State Department, AusAid, DFID, ADB, Islamic Development Bank, USAID, IFC and World Bank among the donors supporting pre-preparation activities

Page 9: Dushanbe May 20, 2013

9

Project Status• Preparation work is proceeding with Joint Working Group (JWG) through

monthly VCs and face-to-face meetings.• IGC Secretariat strengthened – Executive Director (ED) appointed; USAID

funding additional Advisor to the ED; Secretariat accounts audited.• Project commercial structure finalized – two options were reviewed (with

and without setting up a separate project company.) The option of “Contractual JV” (without an SPV for CASA) is preferred by JWG; IGC resolution has been developed and endorsed by two countries (Afghanistan and Tajikistan).

• Project commercial contract framework and Model PPA developed and is under review/discussion by the countries.

• IFC Agreement to support procurement of constructor/operator signed by all. The Joint Working Group is working closely with the IFC to prepare bidding documents for procuring engineer/procure/construct/operate services for the project.

• CASA-1000 included in the CAREC Energy Work Plan (2013-15).• Communications established online (www.casa-1000.org)

Page 10: Dushanbe May 20, 2013

10

The CASA IGC and JWG

AfghanistanWG

KyrgyzWG

PakistanWG

TajikistanWG

Joint Working Group

Intergovernment Council

AfghanistanIGC member

KyrgyzIGC member

PakistanIGC member

TajikistanIGC member

IGC Secretariat

Page 11: Dushanbe May 20, 2013

• Two Main Options for Project Structure– Option A: Contractual Joint Venture – Option B: Corporate Joint Venture

• Countries preferred the Option A

Project Structure

Page 12: Dushanbe May 20, 2013

HGA

HGA

Standard Transmission Terms & Conditions ( Commercial Rules and Technical Rules) (STCs)

Government of Kyrgyzstan (GOK)

Government of Tajikistan (GOT)

Government of Afghanistan (GOA)

Government of Pakistan (GOP)

IGC

EPC ContractorDC Facilities O&M

Contractor

National Electric Grid JSC

OJSHC BarkiTojik

DABSCentral Power Purchase AgencyPower Purchase Agreements incorporating the STCs

Consortium Agreement ?

O&M Agreement re DC Line

Figure 1: Option A- The Contractual Joint Venture

IFIs and Donors

Construction Agreements

Project Agreements

HGA

HGA

Debt De

bt

Debt De

bt

Page 13: Dushanbe May 20, 2013

13

Project past milestones

MOU and Inter-Governmental

Agreement (IGA) for CASA signed by all

four countries

Feasibility Study Update

Completed

First Inter-Governmental Council (IGC) meeting after

feasibility update

in Bishkek

Joint Working Groups (WG) established

Second IGC meeting in Dubai agrees on

project implementation

mobilizing finances

Most of supporting

studies completed; Commercial

framework and model

agreements drafted

Aug’08

Feb ‘11

Sep ‘11

Nov ‘11

May ‘12

Dec ‘12

Page 14: Dushanbe May 20, 2013

14

Key challenges for Project preparation• Country capacity and commitment to work on commercial

deal– Maintain continued commitment and build capacity (country advisors) to

sustain the overall momentum of the Project.– One country’s slowness affects the entire process.– Support in bidding process (bidding advisors - IFC)– Perception from outside (links to Rogun/Kambarata, security in Afghanistan,

etc.)

• Financing gap – a critical issue– A key assumption for the preferred structure is that the project will be fully

financed by IFIs (no private investments).– Two committed financiers (WB and IsDB); Gulf Coordination Group (aka “Arab

Funds”) interested in financing via IsDB; the Russian offer remains on the table but its terms/conditions are not clear.

– Donor’s conference and visits to capitals planned for 2013.– A narrow window – late 2013 – for approvals and much yet to do

Page 15: Dushanbe May 20, 2013

15

Proposed plan and actions

IFC Agreement is signed by

all countries

IFC to secure funding (from

Donors) for services / commence

work

Complete selection of

Country Advisors

Model PPA; Master

Agreement and IGC

resolution on key

principles

Adopting the IGC

resolution

Visit major donor

capitalsFirst Donor Conference

Lending PCN review

meeting

Jan ‘13

Jan ‘13

Feb ‘13

Finalize commercial framework

Mar ‘13

End-May ‘13

Dec ‘13

Filling the financing gap

May ‘13

Oct ‘13

Commercial negotiations completed

Bank Board Date

Page 16: Dushanbe May 20, 2013

Project building blocks

16

A. Countries ownership and readiness

• Dedicated Working Group headed by Deputy Minister level meets every month;

• Ministerial Inter Governmental Council (IGC) undertakes high level decisions;

• Full-time IGC Secretariat ED and international advisors in place

B. Project structuring and legal framework

• Project Structure is agreed;

• Commercial framework designed;

• The Model Power Purchase Agreement (PPA) drafted;

C. Project financing

• World Bank with IDB and Gulf Coordination Group (GCG) indicated their willingness to finance.

• Other potential co-financiers include KfW of Germany, Asian Development Bank, JICA of Japan, DFID of UK, and Russia

D. Preparatory studies and assessments

• Project Feasibility Study completed

• Environment and Social Assessment and Avian Risk management study for the project completed

• Community Benefit sharing studies ongoing

• Security Risk Assessment and Mitigation Plan completed

• Development of open access rules ongoing

Page 17: Dushanbe May 20, 2013

17www.casa-1000.org