DTI006 – EDW: Implementation - projects.ed.ac.uk · Web viewOLAP is part of the broader...
Transcript of DTI006 – EDW: Implementation - projects.ed.ac.uk · Web viewOLAP is part of the broader...
DTI006 EDW Implementation V01FINL 01/08/2017
DTI006 – EDW: Implementation
1. Document Version ControlVersionNo
Contents DateCreated
Author Comments
V0101 Initial draft 17/07/2017 Chris Lawford Issued to project team for review. V0102 Modified draft 18/07/2017 Chris Lawford Updates from team review.V0103 Modified draft 26/07/2017 Chris Lawford Updates from further stakeholder review.
Submitted to WIS 27/07. V01FINL Approved Brief V01 01/08/2017 Chris Lawford Approved by WIS 28/07.
Small amendments made
2. Document Sign-offName Project Role Date
Signed OffArmstrong, Alison Senior Stakeholder 24/07Berry, Dave Sponsor 27/07Carter, Alex Programme Owner 27/07 Verbal approval given.Fiddes, Iain Senior Resource Manager 26/07 Comments received.
Document updated.Foggo, David Project Team Member 26/07Granum, Geir Project Team Member 26/07Grzesinski, John Project Team Member On holiday.
Will pick up on his return.Henderson, Gillian Project Team Member 18/07 Comments received.
Document updated.Heyn, Ana Project Team Member 18/07 Comments received.
Documents updated.Kraan, Wilbert Project Team Member 19/07Manley, Rob Project Team Member On holiday.
Will pick up on his return
Page 1 of 16
DTI006 EDW Implementation V01FINL 01/08/2017
3. ScopeThe primary objective of the project is to deliver a working EDW capability into the production environment. The project will be scoped to include mainly “must have” deliverables.
From a business perspective, the project aim is to deliver an EDW capability that can begin to support business driven data acquisition projects as soon as possible. This capability achievement is tracked by the ‘production ready’ programme milestone.
This project is concerned with four key areas:
Creation of the technical environments that will underpin the EDW service.
Acquisition of Organisation / Hierarchy data, as a fundamental EDW business data asset.
Creation of associated technical documentation and guidelines, for use by this project and follow-on business driven projects.
The adaptation of existing development, service management and production management organisations to support future change and BAU activity.
There will be a follow-on “embed & optimise” project (DTI021) that will aim to deliver “should haves” and other non-critical items. This will enable the achievement of the ‘enterprise ready’ programme milestone. Refer to the programme plan for more information.
The project follows on from the Proof of concept (COM029) which confirmed the viability of the chosen EDW design methodology.
The procurement and implementation of an ETL tool is outside the scope of this project and is being delivered separately by projects DTI004 “ETL Tool Procurement” and DTI005 “ETL Tool Implementation” respectively.
This project is part of the EDW programme, under the Digital Transformation portfolio.
Page 2 of 16
DTI006 EDW Implementation V01FINL 01/08/2017
4. BackgroundThe creation of EDW will provide the data and information needed by decision makers across the University, giving a consistent view of data across multiple sources, adhering to consistent data definitions. This is in line with the University’s BI/MI Strategy, our reference architecture and the growing requirement for evidence-based planning and decision making.
EDW Landscape
(EDW Landscape V0101 07/04/2017 @ CJL)
DTI006 Scope
The scope items are highlighted in green in the following scope diagram.
Page 3 of 16
DTI006 EDW Implementation V01FINL 01/08/2017
5. Objectives and deliverables
O D Outputs / Associated Deliverables Prty* PrimaryResponsible
AlsoInvolved
O01 Design of the technical environment that will underpin the EDW service.
D01 Technical Architecture Design M Dev Tech
D02 Data Partitioning Strategy S Dev Apps Dev Tech
D03 Data Capacity Planning M Dev Tech Dev Apps
D04 Development Guidelines: ETL Naming Standards M Apps Dev
D05 Development Guidelines: Data Loading S Apps Dev Dev Tech
D06 Development Guidelines: Parallel Processing S Apps Dev Dev Tech
O02 Design of the Data architecture strategy and guidelines for EDW
D07 Meta Data Design Strategy S Info Arch Dev TechTech Mgmt
O03 Design of the Security and Access control for the EDW environment
D08 EDW Security Policy M Info Arch Dev Tech
D09 EDW Security Technical Design M Dev Tech
O04 Creation of the Oracle-based technical environment that will underpin the EDW service. This will encompass DEV / TEST and LIVE
D10 EDW DEV Environment M Dev Tech
D11 EDW TEST Environment M Dev Tech
D12 EDW LIVE Environment M Dev Tech
O05 Creation (completion) of the Microsoft Server environment to support SSIS (TEST & LIVE environments already exist).
D13 SSIS DEV Environment(TEST / LIVE already exist).NB. This deliverable may not be needed, depending upon outcome from DTI004 project.
M Dev Tech
O06 Reference Data Acquisition
D14 Organisation / Hierarchy Data Design(See Notes)
M Info Arch
D15 Organisation / Hierarchy SDS M Apps DevD16 Organisation / Hierarchy Build / Test / Deploy M Apps Dev
Page 4 of 16
DTI006 EDW Implementation V01FINL 01/08/2017
O07 Static Dimension Creation
D17 Time dimension Data Design M Info Arch
D18 Time SDS M Apps Dev
D19 Time Build / Test / Deploy M Apps Dev
O08 Evolve existing stakeholder organisations to support future EDW change and BAU activity.
D20 Development Organisation: Adapted Organisation, Processes, Roles & Responsibilities.
S Senior Supplier
D21 Service Management Organisation: Adapted, Processes, Roles & Responsibilities.
M Service Mgmt
D22 Production Management Organisation: Adapted, Processes, Roles & Responsibilities.
M Prod Mgmt
*The deliverables are prioritised using the MoSCoW prioritisation method (M= Must Have. Has to be satisfied for the final solution to be acceptable in terms of delivery dates, compliance, viability etcS= Should Have. A high-priority requirement that should be included if possible –workarounds may be availableC=Could Have. A nice-to-have requirementW= Want, but will not be part of this project)
6. Out of ScopeWhat Details
OS01 EDW Processor Capacity Planning. We cannot accurately conduct capacity planning at the processor (“horsepower”) level until we have started to acquire business data and understand in detail the design solution.
OS02 Project Services Organisation: Adapted Project Management Model
This will form part of a separate implementation project.
OS03 Acquisition of Business data (other than Org/Hierarchy).
Actual Business Data Acquisition is outside the scope of this project.
7. BenefitsThe project is primarily concerned with the delivery of a capability. The benefit will be accrued by later business driven data acquisition projects.
The benefits of the overall programme have been accurately described within the Digital transformation EDW proposal.
See: https://uoe.sharepoint.com/sites/digitaltransformation/_layouts/15/guestaccess.aspx?guestaccesstoken=GsI0HtJf5jmCBIuUEFJWe288sxnqMFpY%2b1YLdLnxbuU%3d&docid=2_1d0e26d48a9ae4852aefcb24ccd07b7ef&rev=1
Page 5 of 16
DTI006 EDW Implementation V01FINL 01/08/2017
8. Success CriteriaWhat Details
SC1 EDW is deemed to be ‘Production Ready’ and the programme milestone is signed-off.
EDW is capable of supporting a limited service.
SC2 Estates solution for Maintenance Mgmt has been developed in parallel with DTI006, and will be ready for deployment within 3 months of EDW being ‘Production Ready’
9. Project milestones Milestone Date Details1. Project Planning 21-Jul-20172. Design Phase complete 29-Sep-20173. Org Hierarchy ASOR 24-Nov-2017 Org/hierarchy signed off in test.4. Infrastructure build complete 6-Dec-2017 All infrastructure signed off in
dev, test and live.5. Deployment 8-Dec-2017 “Production Ready” programme
milestone reached.6. Project Close 12-Jan-2018
(To be transferred to project website upon approval of brief).
10. Priority and FundingThis is a priority one project, funded as part of the EDW programme, within the Digital transformation initiative.
The initial internal estimate is 230 days, spread across IS applications.
In addition an £10k is estimated for external consultancy services.
See the estimating work sheet for further information.
11. Impact and DependenciesThe project is dependent upon outputs from COM029 PofC, now completed.
Project DTI004 (ETL Tool Procurement) will run in parallel with this project.A project to install and productionise the chosen ETL tool (DTI005) will follow on from DTI004.
This project will require an ETL tool in order to build organisation / hierarchy.
However, projects DTI004/ DTI005 will not have delivered a tool in time, and our intention is to have a production ready EDW available ASAP. This project will run in parallel with DTI004-DTI005.
A decision will need to need to be taken before the org/hierarchy technical design can commence: - Build using SSIS.- Build using chosen ETL tool, using a temporary or non UofE environment.- build using custom code.Once built, a further decision will need to be taken post project, once an ETL tool is live:- Leave solution as is.- Convert / Migrate to chosen ETL.
Page 6 of 16
DTI006 EDW Implementation V01FINL 01/08/2017
12. High Level Work Breakdown Structure
Phase Activity TaskA Planning
A01 Project Brief
A02 Planning Sign-offB Policies &
StrategiesB01 Security PolicyB02 Meta Data Strategy
C Technical Design
C01 Technical Architecture DesignC02 Security DesignC03 Data Partitioning Strategy
C04 Capacity Planning
C05 Character Sets
D Environment Build & verification
D01 Oracle DEV / TEST / LIVED02 SSIS DEV
E Org / Hierarchy /
Page 7 of 16
DTI006 EDW Implementation V01FINL 01/08/2017
TimeE01 Design (SDS)E02 Build ETL Source -> Foundation
Foundation -> AccessE03 Build UniverseE04 Test System Test
Integration TestE05 DeployF Application
Development Guidelines
F01 ETL Naming StandardsF02 Data Loading GuidelinesF03 Parallel processing guidelinesG OrganisationG01 Development Organisation
RACIG02 Service Management G03 Production ManagementH Project CloseH01 Closure Report
(See the project plan for more information.)
13. COM029 Outstanding ItemsThere are a number of items that have been inherited from the proof of concept project COM029.The table below details the task that have been included in this project.
JIRA Description ActionCOM029-5 Produce detailed (final) ETL flow To be closedCOM029-4 Identify existing Direct MI reports To be closedCOM029-35 Ensure additional security considerations
included in future EDW designsIncluded in project. Part of Security policy / design
COM029-11 Investigate entity naming convention Included in project. Part of naming conventions task
COM029-22 Investigate loading from source to staging area including performance review
Included in project Part of capacity planning
COM029-2 Investigate automated testing of SSIS Not required.COM029-12 Define SSIS naming conventions / standards Not required.
COM029-32 Move SSIS to an database server Not required, unless SSIS chosen as interim tool.
COM029-28 Archiving Strategy Not part of this project. Will be part of DTI021
COM029-7 Review security documents and update TAD Included in project.Part of security policy / design
COM029-26 Determine Metadata Strategy Included in project.COM029-25 Determine Partitioning Licensing and Strategy Included in project
COM029-27 Determine Sizing on EDW Included in projectPage 8 of 16
DTI006 EDW Implementation V01FINL 01/08/2017
Part of capacity planning.COM029-23 Define governance of foundation layer Not part of this project.
Will be part of DTI022
14. COM025 BI ArchitectureAs part of an earlier project to establish a BI architectural strategy, some initial work was done around the service strategy and SLAs/OLAs for EDW. This will be considered in more detail later, as part of the organisational and process tasks. I have added links to two relevant documents here for completeness.
https://uoe.sharepoint.com/sites/com025biarchitecture/_layouts/15/WopiFrame.aspx?sourcedoc=%7BF2CEC126-BAC0-4A98-8085-6DA465577482%7D&file=Service%20Level%20Agreement%20for%20Enterprise%20Data%20Warehouse%20(NEW).docx&action=default)
https://uoe.sharepoint.com/sites/com025biarchitecture/_layouts/15/WopiFrame.aspx?sourcedoc=%7B2EBC2B4A-D5AE-40A0-9725-4AD3C192E51F%7D&file=PoC%20Goal%20and%20outcomes.docx&action=default
15. NotesNote Details
N01 Org / Hierarchy As part of service excellence, a project will be launched to look at the organisation and workflow hierarchies for core systems
This is an extract from the project proposal:“The organisation hierarchy provides a common core for reporting across the University. In addition, it is common for applications to use the organisation hierarchy for approval purposes in management workflows. The current structure of the organisation hierarchy has significant limitations which will impede the successful rollout of new core systems. A report by the BI/MI programme identified a number of limitations, and others arise from consideration of workflow management.This collaborative project will analyse the requirements for hierarchies, noting there may be more than one. It will update the existing hierarchy in light of these requirements and provide models for structuring new core systems.”
This sits within the core system remit (Sally Priestley).
It therefore makes sense that any work we do to create an initial org/hierarchy dimension fits in with this.
16. RisksDescription Impact /
ProbabilityManagement Approach
R01 The use of a non-strategic ETL tool MED / MED Accept
R02 Insufficient capacity (data / processing)
LOW / LOW Reduce by performing capacity planning exercise.
R03 Org / Hierarchy design doesn’t match future strategy
LOW / LOW Reduce, by ensuring close collaboration with Service
Page 9 of 16
DTI006 EDW Implementation V01FINL 01/08/2017
Excellence.R04 EDW not ready in time for EST093. HIGH / LOW Reduce, if necessary by reducing
scope to meet must haves.
R05 Availability of key development staff
HIGH / LOW Reduce. Project is priority 1.Key resource managers have pre-agreed to required EDW programme resource levels.
R06 Delays due to non-availability of SSIS development environment, should we need it.
MED / LOW Avoid. We hope to build using ETL tool of choice. If not we’ll need to create an SSI dev env, possibly in a short timeframe.
R07 Performance issues due to shared SSIS environment
Accept. There is a Test and Live Shared database environment with SSIS installed. However during ETL discussions for DTI004 it was mentioned that SSIS uses a lot of memory and may be better in a dedicated environment. If we do have to build the shared database environment for dev with the aim of using SSIS in this environment we should monitor resources when ETL processes running. Probably acceptable as an interim measure with small dataset
(Risks to be expanded and transferred to the project website upon approval of brief)
17. Stakeholders Sign-off & Communication PlanWho Brief Sign-
off required?
Role Communication Plan
Armstrong, Alison
Y DTI Portfolio manager
Senior Stakeholder
Berry, Dave Y Sponsor Senior Stakeholder
Carter, Alex Y Programme Owner
Service Owner
Senior Stakeholder
Fiddes, Iain Y Senior resource manager
Senior Stakeholder
Foggo, David Y Prod Mgmt lead Project Team
Graham, Nick N Project Services Interested 3rd party
Inter project dependency
Granum, Geir Y Dev apps (BI) lead Project Team
Grzesinski, John Y Service Mgmt Lead Project Team
Page 10 of 16
DTI006 EDW Implementation V01FINL 01/08/2017
Henderson, Gillian
Y Dev Tech lead Project Team
Heyn, Ana Y App Mgmt Lead Project Team
Kraan, Wilbert Y IA Lead Project Team
Lang, Mark N Dev Tech Mgr. Interested 3rd Party
Larnach, Heather
N Tech Mgmt Lead Senior Stakeholder.
Delegated project team responsibility to David Foggo.
Lawford, Chris Y Programme / Project Manager
N/A
Lee, Bill N Apps Dev Manager Interested 3rd Party
Ma, Defeng N Apps Dev Manager Interested 3rd Party
Manley, Rob Y Dev Apps lead Project Team
McFarlane, Andrew
N Service Mgmt BI Manager
Interested 3rd Party
Middlemass, Craig
N MI/BI SME Interested 3rd Party
Priestley, Sally N Service Excellence Programme Manager
Interested 3rd Party
TBA N Service Operations Manager
Interested 3rd Party
Communication Plan Details01 Senior Stakeholder - Receives Monthly Project report
- Receives regular updates from Programme Manager
02 Project Team - Attends regular team meetings
03 Interested 3rd Party - Receives Monthly Project report
04 Inter project dependency - Regular catch-up meetings between PMs(To be transferred to project website upon approval of brief)
Page 11 of 16
DTI006 EDW Implementation V01FINL 01/08/2017
Glossary of TermsTerm Description
Access Layer A conceptual space within EDW.
Data is transferred from the Foundation layer, using ETL tooling.
It is the layer that contains the solution specific data marts and start schemas, and is designed for targeted, quick and efficient access.
The access layer utilises the concept of dimensional modelling.
It is normally considered an externally focussed space, with many users accessing data via tools such as Business objects etc.
BI Business intelligence (BI) can be described as “a set of techniques and tools for the acquisition and transformation of raw data into meaningful and useful information for business analysis purposes”.
Business Objects (BO)
Part of SAP BI Suite. Toolset used to creates the semantic layer (universe) and reports.
Dashboard In management information systems, a dashboard is “an easy to read, often single page, real-time user interface, showing a graphical presentation of the current status (snapshot) and historical trends of an organization’s or computer appliances key performance indicators to enable instantaneous and informed decisions to be made at a glance.
Data Mart A data mart is the access layer of the data warehouse environment that is used to get data out to the users. The data mart is a subset of the data warehouse that is usually oriented to a specific business line or team. Data marts are small slices of the data warehouse.
A popular form of Data Mart is a Star Schema.
Data Model A data model is an abstract model that organizes elements of data and standardizes how they relate to one another and to properties of the real world.
Data Warehouse (DW)
A data warehouse (DW or DWH) is a system used for reporting and data analysis. DWs are central repositories of integrated data from one or more disparate sources. They store current and historical data and are used for creating analytical reports for knowledge workers throughout the enterprise.
Dimensional Data Mart
See Star Schema
DW See Data Warehouse
EDW Enterprise Data Warehouse
Generic term for the Corporate Data Warehouse, storing data from across the University.
The Enterprise Data Warehouse service will: provide a platform to store University data translated into University terminology
for management information and business intelligence purposes manage a service for the extraction and translation of data from source systems
Page 12 of 16
DTI006 EDW Implementation V01FINL 01/08/2017
ensuring that data is consistent with the source system provide high quality, performant, access to the data in the EDW for consumption
by BI tools curate data definitions and purpose for each of the EDW elements advise and respond to changes required to support strategic decision making and
University reporting needs reduce the coupling with source systems and BI tools, thus simplifying the
migration from one vendor to another
ETL Extract, Transform and Load (ETL) refers to a process in database usage and especially in data warehousing that:
- Extracts data from operational systems- Transforms the data for storage in a proper, long-term format- Loads it into the final target subject area.
Foundation Layer A conceptual space within EDW.
Data is transferred from the Staging layer, using ETL tooling.
It is the layer that contains the enterprise data model, and is at the very heart of EDW.
The enterprise data model utilises the concept of hyper generalised modelling.
It is considered an internal space, with only very specialist users able to gain access.Hyper Generalised Modelling (HG)
A technique for modelling data and its relationships.
This is used within the foundation layer.
MI A management information system (MI or MIS) focuses on the management of information systems to provide efficiency and effectiveness of strategic decision making. The concept may include systems termed decision support system, expert system, or executive information system.
Normalisation / De-normalisation
Database normalisation is the process of organizing the columns (attributes) and tables (relations) of a relational database to minimize data redundancy.Normalization involves decomposing a table into less redundant (and smaller) tables without losing information; defining foreign keys in the old table referencing the primary keys of the new ones. The objective is to isolate data so that additions, deletions, and modifications of an attribute can be made in just one table and then propagated through the rest of the database using the defined foreign keys. Typically used in OLTP systems, not designed for efficient reporting. Implies that one piece of data (e.g. Building name) is only stored in 1 place.
De-normalisation is the process of attempting to optimize the read performance of a database by adding redundant data or by grouping data. This is a technique typically used in Dimensional (Star Schema) Data marts and are designed for efficient reporting.Implies that one piece of data (e.g. Building name) could be stored in many places.
OLAP On line analytical processing, or OLAP is an approach to answering multi-dimensional analytical queries swiftly. OLAP is part of the broader category of business intelligence, which also encompasses relational database, report writing and data mining.
OLTP On line transaction processing, or OLTP, is a class of information systems that facilitate and manage transaction-oriented applications, typically for data entry and retrieval transaction processing. E.g. Archibus, eFinancials.
Page 13 of 16
DTI006 EDW Implementation V01FINL 01/08/2017
Semantic Layer A semantic layer is a business representation of corporate data that helps end users access data autonomously using common business terms. It maps complex data into familiar business terms such as product, customer, or revenue to offer a unified, consolidated view of data across the organization.This is the purpose of a Business objects universe.
Slowly Changing Dimension (SCD)
Dimensions that change slowly over time, rather than changing on regular schedule, time-base.
A good example is the universities organisational structure. This data is relatively static, but does change from year to year. However, it is usually important to track these changes, to enable accurate historical reporting.
Staging Layer A conceptual space within EDW.
The staging layer is used for ETL activities such as loading, validating and transforming data.
It is normally considered an ‘internal’ space, not accessible to users.Star Schema Star schema is the simplest style of data mart schema and is the approach most widely
used to develop data warehouses and dimensional data marts. The star schema consists of one or more fact tables referencing any number of dimension tables.Also known as dimensional data marts.
Static Dimension Data that is required within a data Warehouse but doesn’t change (as part of any regular update activity).Static dimensions are not extracted from the original data source, but are created within the context of the data warehouse. A static dimension can be loaded manually — for example with status codes — or it can be generated by a procedure, such as a date or time dimension.
Subject Area The foundation layer within EDW will conceptually be made up of business specific containers known as subject areas.
These subject areas will be built over time, as and when business driven projects deliver data into EDW. The subject areas can be linked together in many different ways, to provide enterprise wide information.
Universe A semantic layer provided by Business Objects
Page 14 of 16
DTI006 EDW Implementation V01FINL 01/08/2017
18. Document Revision Details
VersionNo
Comment / Response Date
Who
Document Updated? In Version?When?
V0101 C: From the estimation; we are missing the deployment checklist and also the handover to production; for both task you will need to book Application and Technology Management plus the developers for the handover.Also in the scoped under Reference, it says “Production Management (Ops)” but I cannot see any deliverable for that; what do we want to achieve there.R: I will update the estimate sheet with the tasks you mentioned. For the scope diagram, it is supposed to represent (at a high level) that something ‘new’ is coming into the production environment, even if it is going onto existing infrastructure. I think it’s reasonable to expect that we may assess some of the production management support processes, particularly between yourselves and service mgmt. I would expect there to be some sort of high level RACI available that explains these support processes. All up for discussion later. I will add a small deliverable into the planning so we don’t forget.
17/07
Ana Heyn
Yes.V010218/07
V0101 C: As discussed as some of these are joint responsibilities spanning teams, might be useful to have main teams/resources listed along with one team for overall responsibility. Although I can see the teams are included in the task breakdown.
D02 – Data Partitioning Strategy is combined work of Development Technology and Development Team. I will feed into and review strategy in conjunction with developer and Dev Tech would implement this.
D03 – Similarly Data Capacity Planning is combined work of Development Technology and Development Team with some Business Input. I will carry out some investigation in conjunction with developer but need input from someone with detailed understanding of subsets of data being migrated and level of change.
D05 – Development Guidelines: Data Loading – Development Technology will input into this. This is one of key steps where performance may be an issue.
D06 – Development Guidelines: Parallel Processing – Development Technology will input into this and assist in implementation. This is another step where performance may be an issue.
D07 – Dev Tech/Tech Man should input into this for some infrastructure related statistics.
D08 – EDW Security Policy –Dev Tech Input into this
D13 –There is a Test and Live Shared database environment with SSIS installed. However during ETL discussions for DTI004 it was mentioned that SSIS uses a lot of memory and may be better in a dedicated environment. If we do have to build the shared database environment for dev with the aim of using SSIS in this environment we should monitor resources when ETL processes running. Maybe this will be acceptable as interim measure with small dataset – A more detailed risk around this would be wise.
Other than that I’m happy with the content of the brief.R: Thanks for the feedback. I have split the column in section 3 into ‘primary responsible’ and ‘involved’ to reflect your comments. I have also added a risk around SSIS.
18/07
Gillian Henderson
Yes. V010219/07
V01 Production mgmt Responsibilities. Added David Foggo as Heather’s delegate.
19/07
Heather Larnach
Yes.V010219/07
Page 15 of 16
DTI006 EDW Implementation V01FINL 01/08/2017
V02 Just a couple of silly questions from me. Under COM025 we started an SLA for the EDW Service, is this something that will be completed as part of the Service Management BAU? It would be useful in helping shape the service and the supporting processes (https://uoe.sharepoint.com/sites/com025biarchitecture/_layouts/15/WopiFrame.aspx?sourcedoc=%7BF2CEC126-BAC0-4A98-8085-6DA465577482%7D&file=Service%20Level%20Agreement%20for%20Enterprise%20Data%20Warehouse%20(NEW).docx&action=default). There were some supporting process maps at the back of the Outcomes and recommendations (https://uoe.sharepoint.com/sites/com025biarchitecture/_layouts/15/WopiFrame.aspx?sourcedoc=%7B2EBC2B4A-D5AE-40A0-9725-4AD3C192E51F%7D&file=PoC%20Goal%20and%20outcomes.docx&action=default)
CL: This is interesting. From my perspective I think it’s hard to talk about EDW as a service, where the service is actually supplied end-to-end via a BI service. I think any SLA has to be created from that perspective. Within that, it may be appropriate to create an OLA for EDW, so that we can define what levels of support we can expect from production mgmt /application mgmt / service mgmt.The process maps looks useful – I will add some references to COM025 in the brief, so we can dig them out when the times comes. I’ve copied John, Ana, David in case they would like to comment.
25/07
Craig Middlem
ass
YesV010326/07
V02 Organisation / Hierarchy data. I can well understand why you’ve identified this as a fundamental building block of first delivery & readiness. It’s obviously necessary. Is it sufficient? It occurs to me that a Time / Calendar dimension (which presumably you’ll need) might also have the potential to generate costly subsequent reworking if not got right very early in the design & development process.
CL: Time dimension is included within scope. But I need to make it more explicit.
26/07
Nick
Yes.V0103.26/07
V02 P10 – Communication Plan. As an interested 3rd party, specifically concerned with the dependencies around tool choice, I think we might want to agree & document something closer than receipt of monthly report as formal comms link between DTI004 & DTI006 – say a regular active review of risks and dependencies around the choice of ETL tool?
CL: Good point. I’ll add something into the brief to cover what we would have done anyway.
26/07
Nick Graham
Yes.V0103.26/07.
V02 Chris, can I ask how you feel about the milestones for the project? I’m wondering if we have a satisfactory number given the duration of the work and the importance that we track its progress satisfactorily?Otherwise happy to proceedIainCL: Hi Iain, fair point, I will add some. I think we can usefully track the set-up of the live environment, deployment of org/hierarchy data.
26/07
Iain Fiddes
Yes.V010327/07
V03 Mark Ritchie to add note on Gartner questionsWIS noted that Bill Lee should be added to the project as an interested 3rd party in order to give more oversight on tech aspects
28/07
WIS
Yes.V01FINL01/08
Page 16 of 16