Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a...

109
AD-A273 527 US Army Corps of Engineers Hydrologic Engineering Center GENERALIZED COMPUTER PROGRAM ,Trp D2M2 D O Dredged-Material Disposal Managment Model User's Manual July 1984 \\\v6 93-29403 IIIIIIIIll Approved for Public Release. Distribution Unlimited. CPD-47 .•t..2 7 031

Transcript of Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a...

Page 1: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

AD-A273 527

US Army Corpsof EngineersHydrologic Engineering Center

GENERALIZED COMPUTER PROGRAM

,Trp

D2M2 D O

Dredged-Material DisposalManagment Model

User's Manual

July 1984 \\\v6 93-29403IIIIIIIIll

Approved for Public Release. Distribution Unlimited. CPD-47

.•t..2 7 031

Page 2: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

D2M2

Dredged-Material DisposalManagement Model

User's Manual

July 1984

US Army Corps of EngineersHydrologic Engineering Center609 Second StreetDavis, CA 95616-4687

(916) 756-1104 CPD-47

Page 3: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

CONIr 3s

Page

Summary .......................................................... 1

Background ....................................................... 3

Program Capabilities ............................................. 3

Computational Techniques ......................................... 4

Data Requirements ................................................ 5

Hardware and Software Requirements ............................... 5

Error Identification ............................................. 7

Origin of Program ................................................ 7

References ....................................................... 10

Appendix I: Reprint of "Dredged-material Disposal ManagementModel" by David T. Ford ........................... 11

Appendix I1: D2M2 Capacity Expansion Algorithum ................ 29

Appendix III: D2M2 Examples ..................................... 35

Example One: Analysis of Continuous Operation ...... 35

Example Two: Analysis of Operation with Restart .... 52

Example Three: Analysis of Operation with DisposalSite Resting ........................ 63

Example Four: Analysis of Operation with PartialSolution Specified ................... 68

Example Five: Application of Capacity ExpansionCapability ........................... 76

Appendix IV: D2N2 Input Description ............................. 84

Title

I ForTI, T2, T3 Cards ................................ 85 &1

Job Control ed

Jl Card ......................................... 86 .tlo

2 •UAI-U•'•i•E PECTED 3 Distrjbution/

"Ds 1:4

Page 4: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

COMNTTS (cont'd)

Transportation Description

TI Card ....................................... 88TD Card ....................................... 89TC Card ....................................... 90

Disposal Site Description

SI Card ....................................... 91SL Card ....................................... 92SX Card ....................................... 94SR Card ....................................... 97SS Card ....................................... 98SE Card ....................................... 98SA Card ....................................... 99

Dredge-Site Description

DI Card ....................................... 100DL Card ....................................... 101DT Card ....................................... 102DV Card ....................................... 103

User-Specified Solution

FS Card ....................................... 104

it

Page 5: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

SUMARY

The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer thefollowing disposal management questions:

1. If a specified long-term operation policy is followed for anexisting or proposed dredged-material disposal system, what is thefinal status of the system, given the initial conditions, systemphysical and economic characteristics, and dredged-material volumeestimates? What is the cost of following the operation policy?Must additional disposal-site capacity be provided?

2. What is the least-costly long-term operation policy for an existingor proposed disposal system, given initial conditions, systemphysical and economic characteristics, and dredged-material volumeestimates?

3. What is the least-costly method to provide the additional volumerequired? Should expired leases be extended or should new sites beacquired?

4. If new sites are to be acquired, what is the least-costlycombination of sites? What is the least-costly sequence foracquiring these sites?

5. Are alternative material-management alternatives, such astransferring material or resting sites, cost effective?

The information is provided by formulating and solving a mathematicalprograming model in which the disposal system is represented as a network,as illustrated by Fig. 1. The dredging sites and disposal sites arerepresented by nodes of the network. These nodes are connected bycapacitated arcs which represent the facilities for transportation ofmaterial in the system. A unit cost is assigned to "flow" each arc,representing the average cost of moving material within the system. Foranalysis of multiple-period operation, multiple networks are developed andlinked in time. Information for answering the capacity expansion questionsis provided by systematically formulating and solving network-flowprogramming problems which represent alterative expansion schemes; theleast-costly scheme is identified as the best scheme. Details of modelformulation are presented in Appendices I and II.

Input required to use the program includes (1) an estimate of quantityof material dredged at each site each period, (2) a description of physicaland economic characteristics of each disposal site, (3) a description ofphysical and economic characteristics of each material-transportationfacility, and (4) specification of any required movement of material withinthe system. A detailed description of input is presented as Appendix IV.

Page 6: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

Dredging Reach A Disposal Site X

Dredging Reach B

Disposal Site Y

a) Disposal system

Initial Storage Final Storage

Dredging Site A Disposal Site X

Dredging Site B Disposal Site Y"•'/4 --. * Final Storage

Initial Storage

b) Arc-node representation of disposal system

FIG. 1. - Network Representation of Disposal System

2

Page 7: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

BACKGROUND

The Corps of Engineers has been responsible for maintenance of thenavigable waterways of the United States since 1824. The maintenanceincludes excavation and disposal of the sediment deposited in the waterways.Current common practice is to excavate the material with a mechanical orhydraulic dredge and to transport it to a disposal site either by pumpingthrough a pipeline or by carrying the material to the site in barges or inhoppers on the dredge. The disposal site may be an offshore site selected tominimize interference with navigation, or the disposal site may be acontained upland site. Contained disposal sites are natural or man-madeponding areas into which the dredged material is pumped or lifted. In thedisposal site, water gradually drains and evaporates from the dredgedmaterial, and the solids densify and consolidate. The rate of dewatering,densifying, and consolidating can be increased by surface trenching, wicking,surcharging, or pumping. Detailed descriptions of these techniques and othertechnical aspects of dredged-material management are presented in Reference 1and in associated reports of the Corps' Dredge Material Research Program.

Management of the long-term operation of a dredged-material disposalsystem requires selection of excavating and transporting equipment,allocation of disposal-site capacity, selection of appropriate disposal-sitemanagement practices, and identification of capacity expansion schemes. Dueto the complexity of the long-term problem, equipment selection and capacityallocation generally is addressed only for the short-term, with equipment andsites selected for minimum cost at the time the dredging is performed.Physical and environmental limitations may constrain this selection andallocation. Likewise, problems of disposal-site operation and of capacityexpansion generally are addressed with heuristic rules as problems arise.

PROGRAM CAPABILITIES

The Dredged-material Disposal Management Model (D2M2) is asimulation-optimization model for systematic analysis of long-term operationand expansion of a disposal system. Application of D2M2 requires estimatesof volumes dredged, descriptions of the existing and potential disposalsites, and description of the dredging and transporting facilities. With themodel, system disposal capacity expansion alternatives can be analyzed, andthe minimum-cost disposal-site acquisition and lease extension schedule canbe determined. This is accomplished by evaluating automatically the presentvalue of alternative sequences of acquiring new sites and extending leases toidentify the least-costly expansion policy. The cost of any alternativecapacity expansion plan is considered to be the sum of site acquisition cost,fixed operation, maintenance and repair cost, lease cost, and operationcost. To determine the operation cost, D2M2 includes the capability toidentify the minimum-net-cost short-term operation policy for any specifiedsystem. This is accomplished by formulating and solving a mathematicalprogramming problem that represents the problem of allocating efficiently theavailable capacity. If desired, this portion of the program may be usedwithout the capacity expansion evaluation portion.

3

Page 8: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

Disposal-site consolidation rates, containment dike heights, and othercharacteristics of existing and proposed disposal system components arespecified by the model user. Thus, management schemes that involve changesin these parameters may be evaluated by systematic variation and re-executionof the model.

COMPUTATIONAL TECHNIQUES

Program D2K2 employs network-flow programming and a heuristicenumeration scheme to evaluate disposal-system management alternatives.Network-flow programming is used for evaluation of the operation of aspecified disposal system. EK"Ykeration is used for selection of theleast-costly capacity-expansion scheme.

Network-flow Programing. - Program D2H2 models the characteristics ofa system of dredge sites, disposal sites, and material transportationfacilities as a network. This network includes nodes that represent theavailable disposal sites and dredge sites. These nodes are connected by arcsthat represent transportation linkages, material-transfer facilities,material-reuse capabilities, and material storage in disposal sites. Theflow of material through these arcs represents the transporting, or storingmaterial within the disposal system. A detailed description of this networkformulation is presented in Reference 2. A reprint of this reference isincluded as Appendix I.

A unit cost is associated with the flow in each arc; the objective ofthe solution algorithm is to determine the allocation of flow to the variousnetwork arcs to minimize the sum of the product of flow in each arc and thecorresponding -ost. The unit costs assigned to the network arcs are thediscounted 'n.t costs of storing, transporting, or transferring material orthe negative of the unit benefit of reusing material. A specializednetwork-flow programming algorithm is used to determine the minimum-costflows. This algorithm is described by Jensen and Barnes (3).

Annotated examples of applications of the network model are presented inAppendix III.

Enumeration. - The least-costly scheme for acquisition ofuser-specified capacity expansion options is determined in D2M2 byenumeration of a limited number of the possible schedules. Determination ofthe cost of each schedule is accomplished by computing the sum of the presentvalue of the acquisition costs and lease-renegotiation costs and the presentvalue of operation cost of the disposal system with the expansion sitesavailable. This operation cost is determined with the previously describednetwork model of the disposal system.

The heuristic enumeration procedure incorporated in D2K2 provides for awell-structured, systematic search of the site acquisition and leaserenegotiation options. Enumeration begins with evaluation of the total costif all capacity expansion sites are acquired in the earliest period allowedand if all leases are renegotiated. This capacity expansion scheme isadjusted, based on analysis of disposal site utilization during the period ofanalysis. After each adjustment, the network model of the disposal system is

4

Page 9: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

altered accordingly, and the least-costly operation policy is found. Thecost of acquisition and lease renegotiation for the new expansion scheme isdetermined and is added to the operation cost. The heuristic rules are againapplied, and the process is repeated. This process is described in detail inAppendix II. With careful application of the procedure, acceptablealternative capacity expansion schemes can be identified with reasonablecomputational effort. One such application is presented in Appendix III asexample five.

DATA RUQUIRUIENTS

Physical and economic characteristics of the dredged-material disposalsystem must be defined by the user. A detailed description of the input isincluded as Appendix IV.

Each disposal site must be identified, and the location must be definedas shown in Fig. 2. The distances between disposal and dredge sites aredetermined from the specified locations and are used to select theappropriate unit transportation cost. The initial conditions of the site,the maximum allowable rate of addition, and an average wet-to-dry ratio forthe site must be specified. Constraints on drying the site must be defined,and any fixed disposal rates must be specified. The storage-elevation-surface area relationship must be defined to allow complete reporting ofsimulated disposal-site operation. If capacity-expansion costs are to becomputed, the cost of acquiring, leasing, and maintaining the site must bespecified.

Each dredging site must be identified, and the location must be definedconsistent with definition of disposal-site location. The estimated volumeof material removed each period must be specified, and sites must beidentified in which the material can be disposed. The facilities fordredging and transporting material to the disposal sites must be defined.

The dredging and transporting facilities available within the systemmust be described. A unit-cost vs. distance function must be specified foreach transportation facility; the cost of moving material from dredging sitesto disposal sites is determined with this function and distances computedfrom user-specified locations.

HARDWARE AND SOftMARE REQUIRI EKNT S

Program D2N2 is written in ANSI standard FORTRAN IV. The program wasdeveloped originally on a CYBER 175 computer but has been implemented and ismaintained by HEC staff on a Harris 500 computer. Execution of D2M2 requiresuse of a random access input-output package; such a package is available onmost computers. Compilation of D212 with the Harris computer requires fourcentral-processor seconds. Execution of the example problems of Appendix IIrequires 57, 193, 182, 238, and 716 seconds, respectively, and 1.2 million(octal) 24-bit words of virtual memory.

5

Page 10: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

Otf-river Distance

River Distance

Ok\00o,,,

FIG. 2. - Disposal-site and Dredging-site Location Specification

6

Page 11: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

Program D2M2 uses five scratch files. These files are assigned as

follows:

File Identification Use

TAPE5 User input fileTAPE6 Output fileTAPEll File for storage of capacity-expansion

iteration results. Also used for restartinput file.

TAPE12 Intermediate file to which user input file iscopied.

TAPE99 Direct-access file for network storage

Allocation of available computer memory to the arrays of program D2H2 isproblem dependant and is performed automatically by the program. When thedimensions of the disposal system and the period of analysis are defined, aninternal algorithm subdivides the memory as necesssary to storecharacteristics of the disposal sites, dredge sites, and transportationlinks. Thus operation of a system with many disposal sites and dredge sitescan be analyzed for a few time periods, or operation of a small system can beanalyzed for many time periods. The limitations on disposal system size andperiod of analysis are presented in Appendix IV for the distributed Harris500 version of the progam; users may modify program dimensions to implementthe program on other computers.

ERROR IDENTIFICATION

As the input for program D2M2 is read, the user-specified values arecompared with expected ranges or allowable values. If an error is detected,a message is printed. These messages, which are self-explanatory, are listedin Table 1. Errors are classified as fatal or non-fatal. If a fatal erroris discovered, program execution terminates. If a non-fatal error isdetected, a default or maximum value is used instead of the user-specifiedvalue, a message indicating this is printed, and execution continues.

ORIGIN OF PROGRAM

Program D2M2 was developed originally in the Hydrologic EngineeringCenter (HEC) with financial and technical assistance from the PhiladelphiaDistrict, Corps of Engineers. Subsequent modifications were funded by thePhiladelphia District and the Dredging Divison of the Water Resources SupportCenter through the Waterways Experiment Station, Corps of Engineers. Thesoftware was developed by Rochelle Barkin and the network model and thebranch-and-bound algorithm were formulated by David Ford and Darryl Davis,Chief, Planning Analysis Branch. Dr. Ford managed program development andsupervised preparation of this manual. The subroutines for solution of thenetwork-flow programming problem were provided by Quentin Martin of the TexasDepartment of Water Resources; Dr. Martin provided assistance withapplication of these subroutines. Brian Heverin and William W. L. Lee of thePhiladelphia District assisted with model testing and provided valuabletechnical guidance. Bill S. Eichert was Director of the HEC during modeldevelopment.

7

Page 12: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

Table 1. - Error Messages

Fatal Error Messages

MessaKe User Action

TOO MANY TRANSPORTATION LINKS, DREDGE SITES, Reduce number of transportationDISPOSAL SITES, OR TIME PERIODS. <Equation links, dredge sites, disposalfor program maximum>. CALCULATED = <value sites, or time periods. Seecalculated for user defined system> input description for maximum.MAXIMUM = <program maximum>

TOO MANY NODES IN MODEL. <Equation for Reduce number of disposal sites,program maximum>. CALCULATED = <user value>, dredge sites or time periods, asMAXIMUM = <program maximum> indicated by equation.

<id> CARD EXPECTED. <id> CARD READ. Consult input guide for sequenceof cards.

LATEST ACQUISITION DATE OMITTED FOR Specify latest acquisition date,EXPANSION SITE <site id>. field 3 of SX card.

CARD NO. <number> IHE VALUE OF IEXP Replace value in field I of(<user-specified value>) IS INVALID specified card with 0, 1, 2, or

3.

TOO MANY ARCS ENCOUNTERED IN PERIOD Reduce number of dredge sites,<period number> number of disposal sites, or

number of transportation linksthat originate or terminate atdisposal sites.

INSUFFICIENT AMORTIZATION PERIODS The latest period specified forpossible acquisition of thiscapacity expansion site will notpermit proper amortization.Decrease number of periodsrequired (field 9 of Jl card) orincrease latest period (field 3of SX card).

CARD NO. <number> HAS INVALID DREDGE SITE Replace identifier on specifiedID = <alphanumeric identifier> card with one of identifiers

defined on DI cards.

8

Page 13: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

Message User Action

CARD NO. <number> HAS INVALID DISPOSAL Replace identifier with oneSITE ID = <alphanumeric identifier> defined on SI cards.

CARD NO. <number> HAS INVALID TRANSPORTATION Replace identifier with oneSITE ID = <alphanumeric identifier> defined on TI cards.

THE DISTANCES OF THE DISTANCE-UNIT COST Re-arrange values on TD cards.FUNCTION (<transportation-type identifier>) Values on TC card mustARE NOT INCREASING correspond.

THE UNIT COSTS OF THE DISTANCE-UNIT COST Re-arrange values on TC card.FUNCTION(<transportation-type identifier>) Values on TD card mustARE NOT INCREASING correspond.

Non-Fatal Error Messages

THE VALUE OF NPER (<user-specified value>) Reduce NPER (field 1 of Jl card)ON THE Jl CARD IS GREATER THAN THE MAXIMUM or accept maximum.(<maximum allowable value>) NPER SET EQUALTO MAXIMUM

THE VALUE OF DRATE (<user-specified value>) Accept default or specifyON THE Jl CARD IS INVALID. DRATE SET O< DRATE 9 100.EQUAL TO DEFAULT (1)

THE VALUE OF VMULT (<user-specified value>) Accept default or specifyON THE DL CARD NO. <card number> IS INVALID. VMULT > 0.VMULT SET EQUAL TO DEFAULT (1.0)

THE VALUE OF WDRAT (<user-specified value>) Accept default or specifyON THE SL CARD NO. <card number> IS INVALID. wet-to-dry ratio (WDRAT) > 0.WDRAT SET EQUAL TO DEFAULT (1.0)

THE VALUE OF NREHND (<user-specified value>) Accept default or specifyON THE SR CARD NO. <card number> IS INVALID. NREHND 9 2.NREHND SET EQUAL TO DEFAULT (2)

READIN -- NEXT IDENTIFICATION CODE IS Check card for keypunch error.INVALID, RECORD IGNORED

9

Page 14: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

REFERENCES

1. Corps of Engineers, U.S. Army, "Dredged Material Research ProgramExecutive Overview and Detailed Summary," U.S. Army Engineer WaterwaysExperiment Station, Vicksburg, MS, December, 1978.

2. Ford, D.T., "Dredged-material Disposal Management Model," Journal ofthe Water Resources Planning and Management Division, ASCE, Vol. 16, No.1, Jan., 1984, pp. 57-74 (available also as Hydrologic EngineeringCenter Technical Paper No. 94).

3. Jensen, P.A., and Barnes, J.W., Network Flow Programming, John Wiley andSons, Inc., New York, N.J. 1980.

10

Page 15: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

DREDGED-MATERIAL DISPOSALMANAGEMENT MODEL

By David T. Ford,' M. ASCE

Aae•mA: To identify efficient dredged-material disposal management strat-egies for the Delaware River navigation system near Philadelphia, the systemoperation problem is formulated and solved as a generalized minimum costnetwork flow programming problem. This formulation represents material sourcesand available disposal sites as nodes of the network and transportation linksand carry-over storages as arcs. The dewatering, consolidation, and densifi-cation of dredged material is modeled with an arc gain factor, thereby allowingreduction of the total volume of material within the network but requiring useof a network-with-gains algorithm for solution of the operation problem. Ap-plication of the model defines cost-efficient dynamic schemes for allocation ofmaterial to available disposal sites. A generalized computer program was de-veloped to define automatically the nodes, arcs, and parameters of the arcs ofthe network, given a description of the dredged-material disposal system.Structured analysis and structured programming techniques were used, thusproviding a clear definition of the computations required, the order in whichthey must be accomplished, and the flow of data. This software developmenttechnique reduces the effort required for subsequent modification of the pro-gram to analyze the system capacity-expansion problem.

DELAWARE RIVER DISPOSAL MANAGEMENT PROBLEM

Background.-The Corps of Engineers has been responsible for main-tenance of the navigable waterways of the United States since 1824. Themaintenance includes excavation and disposal of the sediment depositedin the waterways. Current common practice is to excavate the materialwith a mechanical or hydraulic dredge (10) and to transport it to a dis-posal site either by pumping through a pipeline or by carrying the ma-terial to the site in barges or in hoppers on the dredge. The disposal sitemay be an offshore site selected to minimize interference with naviga-tion or the disposal site may be a contained upland site. Contained dis-posal sites are natural or manmade ponding areas into which the dredgedmaterial is pumped or lifted. In the disposal site, water gradually drainsand evaporates from the dredged material, and the solids densify andconsolidate. The rate of dewatering, densifying, and consolidating canbe increased by surface trenching, wicking, surcharging, and pumpingwith well pants. Detailed descriptions of these techniques and othertechnical aspects of dredged-material management are presented in Ref.3 and in .associated reports of the Corps' Dredged Material ResearchProgram.

Management of the long-term operation of a dredged-material dis-posal system requires selection of the equipment to be used for exca-vating and transporting the material from the channel to the disposalsites, allocation of the capacity of the available disposal sites to satisfy

1Hydr. Engr., The Hydrologic Engrg. Center, U.S. Army Corps of Engr., Davis,Calif. 95616.

Note.-Discussion open until June 1, 1984. To extend the dosing date one month,a written request must be filed with the ASCE Manager of Technical and Profes-sional Publications. The manuscript for this paper was submitted for review andpossible publication on October 14, 1982. This paper is part of the Journal ofWater Resources Planning and Management, Vol. 110, No. 1, January, 1984.CASCE, ISSN 0733-94%/84/0001-0051/$01.00. Paper No. 18526.

11

Page 16: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

the demand for storage imposed by the dredging operation, selection ofappropriate disposal-site management practices, and identification of ca-pacity expansion schemes if the system capacity is exhausted at sometime. Due to the-complexity of the long-term problem, equipment se-lection and capacity allocation generally is addressed only for the short-term, with equipment and sites selected for minimum cost at the timethe dredging is performed. Physical and environmental limitations mayconstrain this selection and allocation. Likewise, problems of disposal-site operation and of capacity expansion generally are addressed withheuristic rules as problems arise.

Delaware River System.-The Delaware River, Delaware Bay, and as-sociated tributaries are maintained in a navigable condition by the Phil-adelphia District, Corps of Engineers. Within this area, shown in Fig. 1,23 Federal navigation projects yield approximately 8,100,000 cu yd(6,200,000 M3) of dredged material annually. Non-Federal maintenancedredging contributes an additional 3,400,000 cu yd (2,600,000 M3). Thematerial is disposed in 21 containment sites. According to estimates pub-lished in a 1979 study, by 1999 all these sites will be filled or unavailabledue to lease expiration with continued- maintenance dredging at current

PENNSYLVANIA .. Trenton

Phi•, Camden

ii NEW JERSEY

vel,,wr* Rliver

OCEANMARYLAND •[eed

DELAWARE . APPROXIMATS DISPOSALSIiTE LOCATION

FIG. 1.-Delaware River System

12

Page 17: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

rates and with no change in management practices (4). This in turn wouldmean reduction or cessation of dredging and consequent reduction orcessation of navigation. The 1979 study identifies a number of manage-ment alternatives that may be employed, including:

1. Capacity expansion alternatives: (a) Acquisition of new upland sites;(b) open-water disposal of dredged material; and (c) extension of leaseson sites.

2. Operation alternatives: (a) Dewatering of disposal sites; (b) increasein containment dike height; (c) reuse of dredged material; (d) reductionof maintenance dredging; (e) use of deposition basins to reduce shoal-ing; (f) reduction of sediment erosion; and (g) improvements in sitemanagement.

MANAGEMENT MODEL DESCRIPTIO

Model Objective.-The dredged-material disposal management modelwas developed for systematic evaluation of and comparison of alterna-tive management schemes. With the model, capacity expansion alter-natives can be analyzed, and the minimum-cost combination and sched-ule can be determined for new site acquisition and lease extension. Also,the minimum-net-cost operation policy for any specified system can bedetermined. This policy is required both for long-term system operationplanning and for solution of the expansion problem; the total cost ofany alternative capacity expansion scheme is a function of site acquisi-tion, lease extension, and operation costs. The minimum operation costand the associated operation policy are determined by formulating amathematical programming model that represents the problem of allo-cating efficiently the available capacity. Disposal-site dewatering rates,containment dike heights, and other characteristics of the disposal sys-tem are specified by the model user, so management schemes that in-volve changes in these parameters are evaluated by systematic variationand re-execution of the model.

Initial development of the disposal management model is limited toformulation of the mathematical programming model presented hereinfor analysis of operation of a defined system. Ultimately the model willbe expanded to address the capacity expansion problem, using a branch-and-bound algorithm which iteratively enumerates a limited number ofalternative site acquisition and lease renegotiation schemes, evaluatesthe efficiency and feasibility with the operation model, and identifiesefficient schemes for expanding the system. The branch-and-bound pro-cedure provides rules for eliminating from consideration many costly orinfeasible schemes without actual evaluation with the operation model.

Mathematical Programming Formulation .- The mathematical pro-gramming formulation of the dredged-material disposal system opera-tion problem includes continuity constraints for material sources and fordisposal sites, transportation link and disposal-site capacity constraints,and carry-over storage constraints. The continuity and capacity con-straints define the operation problem for each period. The carry-overstorage constraints relate conditions within each period, yielding a multi-period operation problem. Unit costs are associated with transportation

13

Page 18: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

and disposal of dredged material. The objective is to minimize the totaldiscounted cost of system operation. This formulation is similar to thesolid-waste disposal model formulated by Marks and Liebman (13) andto the wastewater disposal model formulated by Brill and Nakamura (2).

A continuity constraint is included for each material source and foreach disposal site for each period of analysis. The form of the equationfor each material source, I, for each period T isNDISP

F F(1,J,T) = V (,T) .......................................... (1)I-1

in which J = index of disposal sites; NDISP = total number of disposalsites; F (J, T) = volume of material transported from source I to site Iin period T; and V(I, T) = total volume of material dredged at source Iduring period T. The form of the equation for each disposal site I foreach period T is

S(J, T- 1) + VF(J)* F(I,,T) + T RT (I',J,T)

-RT (J,',T)] - RU (J,T) = S(J,T) .............................. (2)

in which NDRG = total number of dredged-material sources; S(J, T -1) = volume of material stored at site I at beginning of period T and atthe end of period T - 1; S (J, T) = volume of material stored at site I atend of period T; RT (1, 1',T) = volume of material transferred to site Ifrom site I'; RT (1 ', , T) = volume of material transferred from site I tosite I' in period T; RU (1, T) = volume of material from site I removedand sold for reuse; and VF (J) = an average volume-reduction factor.The volume reduction factor reflects: (1) The wet-to-dry volume ratio ofthe dredged material; and (2) the efficiency of the disposal site manage-ment practices. The wet-to-dry volume ratio defines the average volumeof dry material per time period that must be stored at the disposal siteas a fraction of the total volume of material in situ. E.g., a wet-to-dryratio of 2.0 indicates that the dredged material, when wet, will occupytwice the volume .xcupied by the dried material. In this formulation thevolume reduction As assumed to occur within one period. The efficiencyof the disposal site in terms of achievement of the reduction dependson the site management teWJniques. If the techniques employed are 100%efficient, VF (1) will equal tne reciprocal of the wet-to-dry ratio; other-wise, VF (]) will equal the product of this reciprocal and the estimatedefficiency of the dewatering techniques used at the site. Typical valuesof VF (1) range from 0.50 to 1.00.

The total volume of material to be transported to or from a disposalsite is constrained by the characteristics of the pipeline, hopper, or otherdevice used for transportation. Likewise, the volume of material depos-ited at a site each period T is conb:rained by the size of the site. Theselimitations are expressed madtematically as

F(I,J,T) < FM AX(1,J) .......................................... (3)

14

Page 19: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

RT(,J1',T): -RTM AX (J,I') ..................................... (4)

SR(UMJ , (1) .......................................... (5)

S(1, T) 5 S ,MAX (/) ............................................. (6)

in which FMAX(IJ) = capacity of the transportation link betweendredged-material source I and disposal site 1; RTMAX(J,J') = capacityof the facilities for removing material from disposal site I and transfer-ring it to site I'; RUMAX(J) = capacity of the facilities for removingmaterial from disposal site I for reuse; and SMAX(J) = storage capacityof disposal site 1.

In addition to the restrictions on transportation, disposal-site man-agement practices may pose a limitation on the rate of addition of "wet"material to the site. This limitation is imposed each period by the fol-lowing constraint:NDRG

F F(1,,,T) s- ADDM AX(J) .................................... (7)!I-1

in which ADDMAX(J) = maximum allowable volume addition per period.The operation problem is to determine the "best" scheme for allocat-

ing the material dredged each period to the available sites over the plan-ning horizon. The efficiency of operation is defined as the algebraic sumof the present value of costs of disposal and transportation and the ben-efits of reuse. Mathematically, this is expressed as

NPERS rrNDRG NDISP

Z = E (1+R R)-T E Y, CF(I,J)*F(I,J,T)~T=1 I 11 1=1

+ CS(J)* F L } + { ". E CRT(IJ')*RT(JJ',T)

I ',#1

NDISP 1- CRU (J)*RU (1,T) .................................... (8)

in which Z the present value of system net benefits for the period ofanalysis; R = discount rate; NPERS = number of time intervals; CF (I, J)= unit cost of transporting material from dredge site I to disposal siteJ; CS(J) = unit cost of adding material to disposal site 1; CRT(1,1') =unit cost of removing material from site J, transporting to and disposingin site J'; and CRU(J) = unit benefit of reuse of material from site J.These costs and benefits are assumed to be constant over time. The ob-jective is minimization of the net cost, Z.

Mathematical Programming Problem Solution.-The dredged-mate-rial system operation model as presented includes linear constraints anda linear objective function, so a linear programming (LP) algorithm canbe used to determine the optimal allocation of dredged material to theavailable sites. However, the constraints define only conservation re-quirements and transportation limitations, and the costs and benefits arefunctions of the volume of material transported or stored, so the oper-

15

Page 20: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

ation problem can be formulated as a network-flow programming prob-lem. In a network-flow problem, the decisions required are visualizedas flows in the arcs connecting the nodes of a network, and the objectiveis to choose the flow in each arc to optimize some efficiency measure,such as total cost. The arcs of the network are characterized by the al-lowable direction of flow, the maximum and minimum amounts of flowthat can pass through each arc, the unit cost of use of the arc, and again that represents the fraction of flow that is lost (or gained) in eacharc. The constraints are limited to conservation of flow at the nodes ofthe network and to upper and lower bounds on flows in the arcs. Al-gorithms for solution of the network-flow problems are more efficientthan those for solution of the general LP problems. Ford and Fulkerson(8) and Jensen and Barnes (12) provide detailed descriptions of the char-acteristics of network-flow problems.

The network-flow model of the disposal operation problem representsmaterial sources and available disposal sites as nodes and transportationlinks and carry-over storage as arcs. The network representation of asmall disposal system is shown as Fig. 2. Nodes I and 2 represent thePedricktown North disposal site, nodes 3 and 4 represent the Pedrick-town South site, and nodes 5 and 6 represent Overflow Site 1. Nodes7, 8, and 9 represent the Marcus Hook, Bellevue, and Cherry Islanddredge sites, respectively. The arcs connecting nodes 7, 8, and 9 withnodes 1, 3, and 5 represent the transportation links between the materialsources and disposal sites. The "flows" in these arcs represent the vol-umes of material allocated to the disposal sites. For a more complex sys-tem, arcs are included to connect each source with each site availablefor disposal of the material from that source. An upper bound is im-posed on flow in these arcs, as dictated by the transportation method repre-sented.

Removal of material from the disposal sites for reuse is representedby an arc originating at the disposal site node and terminating at a node

IPEDRICKTOWNNOTH

MARCUS HOOKRE ACM

PEORICKTOWN

SOUTHaSELLEVUEREACH

CHERRY ISLANDRE A CH

FIG. 2.-Single-Period Example of Network Representation

16

Page 21: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

that represents the point of sale of the reused material. Material re-moved from the Pedricktown South site and transferred to the Pedrick-town North site is represented by flow in the arc originating at node 4and terminating in node 2.

The arc originating at node 1 and terminating at node 2, the arc orig-inating at node 3 and terminating at node 4, and the arc originating atnode 5 and terminating at node 6 are included as a computational mech-anism to represent the drying of material added to a disposal site andto limit the rate of addition of material to the site. The gains for thesearcs are the volume reduction factors [VF(J) of Eq. 2], and the upperbounds are the maximum allowable rates of disposal [ADDMAX(J) ofEq. 7].

Material is introduced to the network at the nodes that represent thedredged-material sites. In the terminology of Jensen and Barnes (12),these volumes are node external flows; the quantity of flow entering thenetwork is fixed.

The dashed arcs of Fig. 2 represent the storage of material in the sys-tem disposal sites. The flow in the storage arc that terminates at node2 represents the net volume of dried material deposited in the Pedrick-town North site in all periods prior to the current period [S(1, T - 1) ofEq. 2]. The storage arc originating at node 2 represents the cumulativevolume of dried dredged-material deposited in the site after the additionand removal of material in the period shown [S(1, T - 1) of Eq. 2]. Whenthe network is expanded for analysis of multiple-period operation, thesestorage arcs link the networks that represent single-period problems. Thisis shown in Fig. 3.

A unit cost is associated with the flow in each arc; the objective of thesolution algorithm is to determine the allocation of flow to the variousnetwork arcs to minimize the sum of the product of flow in each arcand the corresponding cost. The unit costs assigned to the network arcsare the discounted units costs of storing, transporting, or rehandlingmaterial [CS(J), CF(I,J), and CRT(J,J') of Eq. 8] and the negative ofthe unit benefit of reuse [CRU (1)].

The traditional network flow programming solution algorithms, suchas the out-of-kilter algorithm (5,7,9) were developed for problems in which

-----------------------

PERIOD I PERIOD 2 PERIOD 3

FIG. 3.-Multiple-Period Network Representation

17

Page 22: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

all gain factors are unity and, thus, are not applicable. Consequently,for solution of the management problem as formulated, a specializednetwork-with-gains algorithm is employed. This algorithm solves thegeneralized minimum-cost network flow problem with any nonnegativegain factors using a flow-augmentation algorithm. In this application,the algorithm begi.,. with flow in all arcs set equal to zero. The mini-mum cost per unit of additional flow to each node of the network andthe path over which that flow may be obtained is determined. The totalflow through the network is increased along the minimum-cost path un-til the flow in one or more arcs in the path exceeds the bounds. Thisprocess continues iteratively until the required system input flows aresatisfied or a maximum possible flow through the network is obtained.This algorithm guarantees achievement of a feasible, global optimal so-lution if such a solution exist. Additional details of the algorithm arepresented by Jensen and Bhaumik (11) and by Jensen and Barnes (12);a previous application of the algorithm is described in Ref. 14.

SOFTWARE DEVELOPMENT

A generalized computer program was developed to implement theproposed disposal-system management model to evaluate alternativesystem capacity expansion plans. The program development employedstate-of-the-art software engineering techniques, including structuredanalysis and structured programming (1).

Structured Analysis.-Structured analysis is a logical process fortransforming information about program requirements into specifica-tions for the program that is to be developed. This approach is contraryto usual engineering program development activities in which everyoneeagerly gets on to the "real" work-writing code. As described by De-marco (6), the structured analysis approach has the following charac-teristics: (1) It yields a paper model of the program-to-be; (2) the pro-

EXECUTIVEROUTINE

CAPACITYPRE- EXPANSION POST-

PROCESS MODEL PROCESS

(INPUT) (PROCESS) (OUTPUT)

I LO .0 4.0

FIG. 4.-Top Level of Control

18

Page 23: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

CAPACITY

EXPANSIONMODEL

8..

DETERMINE CHECK FORl EVALUATE

NEXT SUFFICIENT COST OF

PLAN CAPACITY PLAN

FIG. 5.--Capacfty Expansion Component

gram is designed in a top-down, hierarchical fashion with a smoothprogression from abstract definition of program components to a de-tailed definition; (3) it yields a set of connected "mini-specifications" ofthe identified program components; and (4) it uses diagrams for com-munication of ideas, especially between the program user, program de-signer, and computer system analyst.

Top-down program design begins with the establishment of firm re-quirements for the tasks to be accomplished by the program and withthe definition of data required to accomplish the tasks. The overall pro-gram structure (top-level) is then defined, with progressive refinementof lower-level components of the program. Fig. 4 shows the organizationof the top level of the dredged-material disposal management program.

EVALUATECOST OF PLAN

8.8

COMPUTE COMPUTE COMPUTE COMPUTE SUM

PUtESENT VALUE PRESENT VALUE PRESENT VAIL PRESENT VALUE COSTSOF ACQUISITO OF omi OF LEASE OF OPERATION

COSTS COSTS EXTENSION COTi$COSTS

38.1$ 8..8. a.8.8 8.8.4 8.8.8

hL

FIG. 6.-Cost Evaluation Component

19

Page 24: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

COMPUTE PRESENTVALUE OF

OPERATION COSTS

POOMMUATE SOLVE MINIMUM-

WETWORK-FLOW COST NETWOWK-

PROU.EM FLOW PIOBLEM

MO. 7.-Opwa• n.C•t Evaluaton Componwnt

The program consists of an "executive" routine controlling an "input,"a "process," and an "output" routine. Figs. 5 and 6 show further re-finement of the process component; specification of the other compo-nents is refined in a similar manner. Development of the system man-agement model was planned (and funded) for completion in two separatestages: stage 1 includes only the operation model development, whilestage 2 addresses the capacity expansion problem in more detail. In stage1, several of the components shown were defined only in conceptualterms. For example, detailed specification of computational techniqueswas delayed initially in the case of component 3.1. Nevertheless, thedata transfers and the required results of execution of each module weredefined.

The network-flow programming model formulated to determine theoptimal allocation of dredged material is identified as component 3.3.4in Figs. 6 and 7. As one of the goals of program development is to pro-duce a management model usable by engineers and planners who arenot familiar with mathematical programming techniques, component3.3.4.1 is included here to translate disposal-system descriptive data intothe node-arc representation. The resulting generalized minimum-costnetwork-flow problem is solved with code included in component 3.3.4.2.Definition of this component is further refined to include componentsof the network-with-gains algorithm.

Structured Programming.-The actual computer code to implementthe disposal management model was developed from the structuredanalysis using structured programming techniques. Each of the com-ponents was translated into one or more subprograms that perform in-dependently single tasks required for solution of the operation problem.The benefits of this approach are: (1) The actual development time isreduced because a number of programmers may simultaneously developthe modules, or existing code may be used easily; (2) complex programsmay be tested in parts, with each module verified independently; (3) the

20

Page 25: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

code is easier to understand and to maintain; (4) the resulting code isflexible and may be modified by changing single modules indepen-dently; and (5) documentation of the code is easier. Items 3, 4, and 5are significant given the environment within which the computer codedescribed here will be used. Although a single application motivateddevelopment, application to other disposal operation problems is likelyand despite careful program design, past experience indicates a frequentneed for special-case modification. Often these modifications must beperformed by someone other than the original program writer, thus theneed for understandable code.

APPLICATION

Operation Evaluation.-The operation model has been used to eval-uate the operation of various existing and proposed configurations ofthe Delaware River dredged-material disposal system, including the sub-system between Philadelphia and the sea. As modeled, this subsystemincludes 19 dredge sites and 8 disposal sites (of which two are imaginarysites for overflow if the system capacity is insufficient). Pertinent datadescribing the disposal sites are presented in Table 1. Material is dredgedat average annual rates shown in Table 2 and is transported by barge,hopper, or pipeline to the disposal sites. The dredging and transportingcosts depend on the machinery used and the distance which the materialis transported; costs vary from $1.62 to $25.00/cu yd and are shown inTable 3. The unit costs of placing the material in the system disposalsites vary from $0.00 to $0.50/cu yd, as indicated in Table 1.

The operation of the Philadelphia-to-sea subsystem was analyzed for50 yr using 25 consecutive 2-yr intervals. The resulting network con-sisted of 877 nodes and 3,709 arcs. Time required for definition of thenetwork parameters and for solution of the minimum-cost optimizationprogram on a commercial Cyber 175 computer system used by the Corpswas approximately 59 CP sec. The minimum present-value net cost forsystem operation with an annual discount rate of 7-5/8% is $273 x 106.

Figs. 8-11 are reproductions of portions of the computer program out-put. Fig. 8 is a summary of the dimensions of the system to be analyzed.

TABLE 1.-Disposal Site Information

Disposal cost,Capacity remaining, Wet-to-dry in dollars per

Disposal site in cubic yards ratio cubic yard(1) (2) (3) (4)

Artificial Island 16,500,000 1.50 0.32Overflow Site 1 99,000,000 1.00 0Overflow Site 2 99,000,000 1.00 0National Park 7,100,000 1.50 0.50Killcohook 36,900,000 1.50 0.11Penns Neck 16,000,000 1.50 0.25Pedricktown North 21,700,000 1.50 0.16Pedricktown South 21,700,000 1.50 0.17

Note: I cu yd = 0.765 m3 ; 1 acre = 0.405 ha.

21

Page 26: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

TABLE 2.-Dredging Ratw, In Cubic Yards Pw Yew

Dredge ufte Volmne(1) (2)

Eddystone 12,300Chester 890Marcus Hook 1,850,300Bellevue 49,900Cherry Island 180,900Deepwater Point 1,402,900Bulkhead Bar 28,700Newcastle 1,269,400Reedy Island 28,000Baker 10,800Liston 220,800Miah Maull 41,000Brandywine 1,500W. Horseshoe 25,800Mifflin 67,400Billingsport 5,600Tinicum 43,200Upper Philadelphia Harbor 6,500Lower Philadelphia Harbor 181,500

Note: 1 cu yd = 0.765 m 3 .

TABLE 3.-Dredging and Transporting Coet, In Dollars per Cubic YardOippeul Sim

Pedrick- Pedrik-Artificial Overflow Overflow National KI~co- Perm town town

Dredge Site Island Site I Site 2 Park hook Neck North South(1) (2) (3) (4) (5) (6) (7) (8) (9)

Eddystone 6.99 25.00 25.00 17.89 * 2.83 3.06Chester 6.57 25.00 25.00 * 2.42 2.65Marcus Hook 6.12 25.00 25.00 17.01 * 1.99 2.22Bellevue 4.91 25.00 25.00 * 2.47 2.09 1.86Cherry Island * 25.00 25.00 15.40 * 2.0 2.48 2.25Deepwater Point 3.57 25.00 25.00 .2.01 1.95 * 3.23Bulkhead Bar 3.16 25.00 25.00 * 1.61 2.35Newcastle 2.48 25.00 25.00 * 1.98 3.02Reedy Island 1.62 25.00 25.00 * 2.84 3.90Baker 1.63 25.00 25.00 * 3.25 4.29Liston 2.22 25.00 25.00 * 3.85 4.86Miah Maull 7.25 19.25 19.25 * 8.88 9.94Brandywine 8.70 15.24 15.24 " 10.33 11.36W. Horseshoe 8.56 25.00 25.00 19.30 * 4.37 4.60Mifflin 8.09 25.00 25.00 19.02 " 3.93 4.15Billingsport 7.85 25.00 25.00 18.78 * • 3.69 3.93Tinicum 7.23 25.00 25.00 18.14 " * 3.07 3.31Upper Philadelphia

Harbor 9.69 25.00 25.00 19.30 0 * 5.50 5.75Lower Philadelphia

Harbor 9.24 25.00 25.00 19.30 * 5.29 5.04

Note: * Indicates sites not linked (1 cu yd - 0.765 m3).

22

Page 27: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

WMUSO or 933111 Or 060L1016 2S INISE or OISWU*L elm...... arim" ,Um ........ I supsinor OG SrIT". ...... 19

ISCIJU M" M PMs ....... 1S.76 CRUMO YORNMPOIrMI ?vTM..HUMPI Non or 1936011116...- 0 OUPU COIL 91816....... 0sun"i or MS6INIT2MIOW PUSCS. is

Z.moy GONPIU I SPN

OINISCU SM0."0 1260.0 "N2O.00 1116040.90 110400.00 21130S.00 246000.60 3160040.00 432446.00126600.00MIT amp 1.40 3.00 2.90 4.71 G.M 6.4" 16.20 11.60 IS." 19.30

M0 - 2791P93 27-ZKas CW3ICY pw..xua ==

1 2 3 4 1 6 7 9 1 IsDiUOISCM IS"." 1140.00 1691M.00 11000.00 21910.00 22M0.00 1329G.0 33000.00 161604.94 0.900C101 cin .46 .10 1.10 2.10 2.11 3.00 2.00 4.16 IS."0 0.90

TO - 9=112 WT1 MUIN 00=

2 3 4 1 6 9 a10Ims1m18, 1200.00 47120.00 12600.00 100320.00 19140.00 1912.00 1048000.00 311120.00 3104000.00 12600.00UNIT 006T 4.10 4.10 4.40 4.40 4.10 4.70 4.00 4.90 1.20 21.00

Mb - M 12 12C9 99CI 0611 0190 INUMLiN

1 2 3 4 1 6 7 0 9 16K61lM S200.00 47S26.00 12600.00 100330.00 I0160.00 17012.60 16400.00 311120.00 310000.00 62000.00MTV MOT? 1.21 1.31 1.61 1.61 1.91 S.61 G.A1 C.IS .41 as."

FIG. 6.-System Dimensions and Transpoutation Gost Reoimt

Also, for each type of dredge, a function relating the unit excavating andtransporting cost to distance transported is presented. Fig. 9 is one of 8disposal site reports. In this report, the physical and economic charac-teristics of the disposal site are summarized. Site acquisition and leaserenegotiation data are included for future use when the program is ex-panded to address the capacity expansion problem. Fig. 10 is one of 19dredge site reports for this system. The alternative sites for disposal of

InI - KIUAO ZILL1100 DISPOSAL SITS

Into sm SM193 U1 ...... 1.211000.00 0411201. 370301................. 0.000rr Re1y Sm1 01009813...........7000.0 061-10-069 PATIO0..................1a"t 613 MOS*YM10 "Pa.. MAX133 ACOIIICN/PMUI....369004000.

O0390SM. CWT?....................11

sm&~m ITON am aaa9 Oft"

huMMO am6... NOF4t O ..............0 .. o-aae99102WAMNhi IWII ................... IU I1AY!COST6................

L&IST a tO PERIOD 311.... 1

11110 am~ 1990 611 100

...... SIM 0.hIL&U CU0 MD.... 1M

06NIT ANnl&3 ................... 0.00

W.I....................00

3 3 4 S 6 7 U 9CARICIY 0. 1000. e"0. 390400. 16900000. 3690000. 261008000. 36900600. 3090006.E*1116 .0 1.0 2.0 30. 1 40.00 1.0 1.0 1.0 .0

S.00 S 0.M 21.0 1P0.00 1100.00 11"0.0 110.0 11000 1200

FIG. 9.-Disposl Shte Report

23

Page 28: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

TO - MCIM ls u mt m GM

IN" em 3t11Rte0l2 e ....... 14023.460 voS or TmUIWCINTm I N -, 6C8- MIN 9 IN 0 We ......... 0.00 NI MtiALL 1O0 IMtIIW M ...... I.0M

OIUCIL 3115 10 I~1U In, ira U 1,10 5,vP8 •In moil ,3ga1 5ntwo mi N mau s wit mI e

0006WW 21600.4 0.29111AD Moao 0 214"m.90I 3.348-13 NOsPW 3160•.00IS ."

8=m12 loa m 21640.00 as."Mutio mio s, 0o 21040.0 1.63

WAVORIAL Va IMISIMNma PMm - 1

I 2 3 4 3 4 7 9 9 1021640.00 31400.0W 31464 21400. .21400. 2160.60 314 00. 2100.00 2104 44.00 3W.0214C." 31600.00 21600.00 2%G00.04 21640.00 21600.0M 21600.00 21400.00 216401. 004M.0421600.06 3140G.40 1000.00 21000.00 2100G.4

FIG. 10.--Drde Ste Repot

material are shown, and the capacity and the unit cost of excavating andtransporting material to each site is tabulated. (The unit cost is deter-mined from the appropriate unit cost versus distance function.) The es-timated volumes of material to be removed each period are shown. (Notethat the value shown for each period in Fig. 10 is twice the correspond-ing value from Table 2 because each period in the analysis correspondsto 2 yr.)

The results of optimal operation of the dredged-material disposal sys-tem are presented as a tabulation of material added to each disposal siteeach period and of end-of-period storage and the corresponding eleva-tion and surface area. Fig. 11 is an example of the tabulation for onesite. The results of the minimum-cost operation are summarized in Table4. All disposal sites except the overflow sites will be filled by the endof the 50-yr model. Overflow Site 1 is used initially in the ninth 2-yrinterval, indicating that system capacity falls short of demand within 18yr of the first year. This conclusion is significant but is difficult to drawwith traditional mass analysis techniques because of the complex inter-connections.

Systematic Evaluation of Operation Alternatives.-Evaluation of dis-posal site management alternatives is accomplished by systematic ap-plication of the operation model with variation of the appropriate inputparameters. For example, to evaluate the cost effectiveness of use oftrenching devices that speed the drying of deposited material in the dis-posal sites, the volume-reduction factor, VF(J), and the maximum al-lowable volume addition per period, ADDMAX(J), are changed to re-flect the improvement possible, and the disposal cost, CS(J), is alteredas appropriate. The operation problem is resolved to determine the least-costly operation scheme. The cost of the trenching machinery is addedto the operation cost to determine the total system cost. This total costis compared with the total cost without the trenching devices; if the costis less, the trenching device is cost effective.

Any management alternative can be evaluated by systematic analysiswith the operation model, if the improvements attributable to thatalternative can be expressed in terms of the volume-reduction factor,

24

Page 29: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

02660661. 6rM - EUU KILLCO66M 01690661. 62W

$11ION PMOC - I 6WY-140-R RATI0O 1.50

-W MMwaza uý OM aMa is MI.

SLMmCmz mO TMmaIOa - 0

Sam we. 00 OULCSE VE'A TOM*

76920 000 0fl 0 **61 * 90LUS 01* 9060?* 1*:*** '"T"94 USE * 06

I 1 s~ f 2650.* 47209". 1,5740. *79666 * 2530800. * 43432"4. 0 S402000. * 9M29252.

* 2 * 2665464. * 426693 * 7400. 6 9011. 2304060. * 3751957. * 5402000. * 0029761. ** 3 *39005660. *3635792 . S 7400. S95016. MOM310. *3241152. - 5402000. * 4936S60.-* 0 26056006. * 3140602. S 7400. SI5150. * 2538600. * 2799669. * 5402000. 9 S992190.

s * 260580. * 2713261. S 7400. " 4886. * 2536800. * 2416702. & S402060. & 5176391. *& * 260580. *2343616. * 57400. 36431. *2366000. 38269411. - 5402000. * 447146.O *

* 7 * 260500R. 20364720. * S7400. $ 3199. * 2536600. * 1604950. * 5402000. * 3662670.*a 6 8205660. 0 1749067. e S7460. 0 26679. *25368600. * 159210. * 5402000. 0 3336964.

* 9 *2605600. * 151094. * 57400. * 24775. *2366000. 1394494. * 5402000. * 2602457.* O'20G6500. 96092. * 7400. * 21402. IS236600. 1163543. 9 4441000. - 2 1056. *

* II f 0. a 0.* 7400. 0 1646. * 1725600. * 643271. * 1783200. 0 701759.* 1 * 0.0 0 57400. 9 15971. * 0. * 0. ft 57400. - 15971. *

* 13 :t 0 t 6 7400. * 13797. - 0. *0. * 57400. * 13797.* 14' 0. 0.' S7400. * 11910. * 0. 0. * 57400. * title. a

*~~ IS . . 74N0. 10290. 0.S. 7400.'* 10296.'* 1 * . f 0.* 7400. GM 604S .* 0 7400. em 664 FUD

* 17 * .* 0 .* 0 .*0. 0.*.

* 19 0. 0. 0. ' 0. * 0. * 0. * 0. *0

* 1 0 * 0.' . 0. 0.* 0. ft 0. *0.* 23 0. ' 0. 0. ' 0. '0. *0. * 0. 4 .

23 0. ' 0. 0. ' 0. 0. ft0. 0. 0.24s 0. ' 0. ' 0. ' 0. '0. '0. ' 0. '0.

fTOTA 27317000. 27140133. 916400. '530353. 27113600. ZS2202316. S553000.' 52692605.

DISPOGAL ITRP 6?A~TM (DAY)SOMmia FM6 ITSMATION - 0

"P.MOfttf'f"MRA M Mft't or ran DISPOSAL'*'f'ft' T"*ftft VfT*"'"*'"'fdwt*'*ftamt

ftPO S ft T ftft t

1t 9620 10333. 309 1333 5133261. igY .VA". 2 WAiAM

4t I f 3601333. ft 30133. ' 1330913. * 20.19 * 490.624 f

ft S ft 3601333. t 16006447. ' 26461i. &t 40.55 f 1101.11 f

6 ' 3401). f 21606000 ' 46943. f 23 t 16.1 f

ft f 3601 33. f 252011333 213323. "4.5 Is 110631ft ft 360 333. 3182610447. 164260. ft 45.96 * 1111.91ft 9 ft 301,333. f 32412000. I 19192. 47 6 ft 11 51 t

ft to 31070607. ft 35519067. ft 1166 . ft 49.31 ft 11186.2 f

It 1166600. ft 347006447. ' 3921S. ' 49.90 ft 1110.01' 12 ft 32627. ft 36744933. t 1090. ft 49.92 1 11ý.. as

' 13 343627. ft 36705200. 0 942. * 49.94 *t 1lls.69

ft 14 * 36247. f 36623447. f 614. *t 49.96 ft 1119.92 *t

ft S ' 2627. t 346461733. * 703. * 49.99 ft M19.96 *

' ~ ~ 16 3627 * 490000. W 0. ft 5.00 f 1130.00ft 17 ft0 t 36900000. 6 . ft 5.00 ft 1120.00 f

Is6' 0. 36900000.' 0.' 56.00 1120.00'

ft 20 ft 0 t 34900000 O ' 0. : 56.0 0, 11 0.0ft21' . 6000' 0' 5.0 1120.00'

ft 2' .'34900000.' 0.' 56. 00' 12.0ft 23 f0. t 36900000. *0. ft 56.00 ft 1120.00

as24 f 0. ft 3490000. 6 . SO 5600 ft 1120 .60

lam 25 90060.' 369000.' 0.' 60' 12.0

........ ........ ........ .....................

FIG. I11.-Operation Report

25

Page 30: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

TABLE 4.-Volume of rgd-MutsrW Disposed, In MiNon Cubic Yards before

-ecls- Site

Vo k eeWntownArW" Over Sf Ne * Par Kox Pene town ton

Dredge Site Wanid Sit I S1te 2 Pwc hook Neck North South(1) (2) (3) (4) (5) (6) (7) (6) (9)

Eddystone 0 0.20 0 0.05 * 0.20 0.17Chester 0 0.02 0 " 0.01 0.01Marcus Hook 0 29.25 0 8.63 * 27.25 27.39Bellevue 0 0.90 0 1.00 0 0.60Cherry Island * 2.17 0 1.45 * 5.43 0 0Deepwater Point 0 25.25 0 * 27.32 17.58 " 0Bulkhead Bar 0 0.52 0 * 0.92 0Newcastle 14.92 21.44 0 * 27.11 0Reedy Island 0.95 0.45 0 0 0 *Baker 0.37 0.17 0 * 0 0Liston 7.51 3.53 0 * 0 0Miah Maull 0.98 1.07 0 S 0 0Brandywine 0.02 0.05 0 * 0 0 *W. Horseshoe 0 0.52 0 0.05 * 0.36 0.36Mifflin 0 1.35 0 0 * 0.94 1.08Billingsport 0 0.10 0 0.01 0 * 0.09 0.06Tinicurn 0 0.78 0 0.09 * 0.69 0.60Upper Philadelphia

Harbor 0 0.13 0 0.01 * 0.10 0.06Lower Philadelphia

Harbor 0 3.63 0 0.36 * 2.90 2.18Total 24.75 91.53 0 10.65 55.35 24.01 32.54 32.55

Note: * Indicates sites not linked (1 cu yd = 0.765 Mi).

maximum allowable addition per period, maximum storage, capacity oftransfer facilities, capacity of reuse facilities, or the time at which facil-ities are available. Techniques that alter the volume of time distributionof dredged material that must be disposed can be analyzed in the samesystematic manner because the volumes are specified by the user foreach period.

CONCLUSIONS

To identify efficient dredged-material disposal management strategies,the system operation problem can be formulated and solved as a gen-eralized minimum-cost network flow programming problem. In this for-mulation, the material sources and disposal sites are represented as nodes,and the transportation links and carry-over storages are represented asarcs. The network-with-gains algorithm is used for solution, thereby al-lowing modeling of the drying of material in the disposal sites.

The proposed disposal system operation model can be used for theevaluation of alternative management schemes by systematically varyingthe appropriate model parameters, re-executing the model, and com-paring the net operation cost to determine the effectiveness of the scheme.In the future, this model will be linked with a branch-and-bound algo-rithm to identify efficient disposal system expansion schemes.

26

Page 31: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

A generalized computer program to implement the proposed opera-tions model was developed using software engineering methods. Struc-tured analysis techniques were used to define the program require-ments, and structured programming was used to transform the require-ments into executable computer code.

The dredge-material disposal management model has been used suc-cessfully to evaluate the operation of the Delaware River disposal system.

Ac~owwamms

The Philadelphia District, Corps of Engineers, provided the funds fordevelopment of the dredged-material disposal management model andassisted in model formulation and verification. The special assistance ofBrian Heverin of that office is appreciated. The software engineeringconcepts were introduced at the Hydrologic Engineering Center by Ro-chelle Barkin, who patiently guided development of the FORTRAN pro-gram that implements the solution technique.

APPENDIX I.-REFERENCES

1. Boehm, B. W., "Software Engineering," Classics in Software Engineering, E. N.Yourdon, ed., Yourdon Press, New York, N.Y., 1979.

2. Brill, E. D., and Nakamura, M., "A Branch and Bound Method for Use inPlanning Regional Wastewater Treatment Systems," Water Resources Research,Vol. 14, No. 1, Feb., 1978, pp. 109-118.

3. Corps of Engineers, U.S. Army, "Dredged Material Research Program Ex-ecutive Overview and Detailed Summary," U.S. Army Engineer WaterwaysExperiment Station, Vicksburg, Mich., Dec., 1978.

4. Corps of Engineers, U.S. Army, "Delaware River Dredging Disposal Study,Stage I Reconnaissance Report," U.S. Army Engineer District, Philadelphia,Pa., June, 1979.

5. Classen, R. J., "The Numerical Solution of Network Problems Using the Out-of-Kilter Algorithm," Rand Memorandom RM-5456-PR, Santa Monica, Calif.,1968.

6. Demarco, T., "Structured Analysis and System Specification," Classics in Soft-ware Engineering, E. N. Yourdon, ed., Yourdon Press, New York, N.Y., 1979.

7. Durbin, E. P., and Kroenke, D. M., "The Out-of-Kilter Algorithm: A Primer,"Rand Memorandum RM-5472-PR, Santa Monica, Calif., 1967.

8. Ford, L. R., and Fulkerson, D. R., Flows in Networks, Princeton UniversityPress, Princeton, N.J., 1962.

9. Fulkerson, D. R., "An Out-of-Kilter Method for Solving Minimal Cost FlowProblems," 51x.X.rtv of Industrial and Applied Mathematics Journal of Applied Math-ematics, Vol. 9, 161, pp. 18-27.

10. Huston, J., H.,lraulic Dredging: Thworetical and Applied, Cornell Maritime Press,Inc., Cambridge, Mass., 1970.

11. Jensen, P. A., and Bhaumik, G., "A Flow Augmentation Approach to theNetwork with Gains Minimum Cost Flow Problem," Management Science, Vol.23, 1977, pp. 631-643.

12. Jensen, P. A., and Barnes, J. W., Network Flow Programming, John Wiley andSons, Inc., New York, N.Y., 1980.

13. Marks, D. H., and Liebman, J. C., "Mathematical Analysis of Solid WasteCollection," Public Health Service Publication No. 2104, U.S. Department ofHealth, Education, and Welfare, Washington, D.C., 1970.

14. Texas Water Development Board, "AL-V Surface Water Resources AllocationModel," UM-35, Austin, Tex., 1981.

27

Page 32: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

APPENoux IL--.OTAYO

The following symbols are used in this paper:

ADDMAX (1) - maximum allowable volume addition per period, siteI;

CF(IJ) - unit cost of transporting material from source I todisposal site 1;

CRT(1,1') = unit cost of rehandling material from disposal site /to site I';

CRU(J) - unit benefit of reuse of material from site 1;CS(J) = unit cost of adding material to site 1;

F(I], T) = volume of material transported from source I to siteI in period T;

FMAX(Ij) - capacity of transportation link between dredged-ma-terial source I and disposal site I;

NDISP = number -of disposal sites;NDRG = number of dredged-material sources;NPERS = number of the periods;

RT(1,1', T) = volume of material transferred from site I to site I',period T;

RTMAX (1,1') = capacity of transfer facilities between site I and site I';RU(J, T) = volume of material removed from site I and sold for

reuse, period T;RUMAX(/) = capacity of reuse facilities, disposal site I;

S (1, T) = volume stored in disposal site 1, period T;SMAX(J) = capacity of disposal site I;

V(I, T) = total volume of material dredged at source I duringperiod T;

VF(J) = volume reduction factor, disposal site 1; andZ = net system operating cost.

SubscriptsI = dredged-material source;I = disposal site; andT = time period.

28

Page 33: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

APPENDIX II

D2M2 CAPACITY EXPANSION ALGORITIM

The capacity expansion module of program D2M2 selects, from auser-specified set of alternatives, the least-costly plan for acquiring orleasing disposal sites to expand the capacity of a disposal system. Theleast-costly plan is determined by systematic enumeration and comparison of alimited number of acquisition and lease-renegotiation schedules. The cost ofeach is the present value of acquisition and lease-renegotiation cost plusthe present value of disposal-system operation cost. The operation cost isdetermined by formulating a network-flow model of the alternative schedulesand solving the minimum-cost flow problem to determine optimal allocation ofthe available space. A branch-and-bound enumeration procedure is used toselect candidate expansion plans for evaluation.

BRANCH-AND-BOUND-M-ETHODS

General Properties. - Branch-and-bound methods are intelligentlystructured techniques for evaluating and comparing solutions to optimizationproblems. With these methods, only a small fraction of all possiblesolutions actually are enumerated. The remaining solutions are eliminatedfrom consideration through establishment of progressively stricter bounds onthe cost or benefit of solutions (the objective function). These bounds aidin identification of inferior solutions without requiring extensivecomputation to evalute those solutions.

Branch-and-bound techniques consist of two basic operations: (1)dividing the set of possible solutions into subsets (branching), and (2)establishing bounds on the value of the objective function, so inferiorsolutions can be eliminated (bounding). The methods involve recursiveapplication of these operations, with specific rules for the operationsdepending on the characteristics of the problem.

References. - The general characteristics of branch-and-bound methodsand applications of the methods have been presented in the management scienceand operations research literature. Lawler and Wood (6) present a survey ofthe essential features of branch-and-bound methods for constrainedoptimization problems and describe application to integer and nonlinearprogranning problems, to the traveling-salesman problem, to the quadraticassignment problem, and to non-mathematical programming problems. Mitten (9)describes the general properties of branch-and-bound methods and presents, ingeneral terms, the conditions for branching and for bounding the results ofoptimization problems. Garfinkel and Nemhauser (5) describe branch-and-boundmethods applicable to integer programming problems.

Branch-and-bound methods have been applied in resource planning toproblems of sizing, selecting, sequencing, and scheduling projects. Marksand Liebman (8) suggest using a branch-and-bound procedure for locatingsolid-waste management facilities. Brill and Nakamura (3) and Nakamura andBrill (11) propose application of a branch-and-bound method for generatingsystematically alternative plans for regional wastewater treatment systemsand for evaluating these alternative plans. Application of branch-and-bound

29

Page 34: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

methods for selection of the optimal combination of discrete alternatives isaddressed by Efroymson and Ray (4), by Morin (10) and by Ball, Bialas, andLoucks (1).

The branch-and-bound procedure incorporated in program D2N2 is anadaptation of the procedure suggested by Lesmo, Himelblau, Jensen, andShanmugham (7) and the procedure suggested by Bickel (2). Theme referencesprovide a mathematically vigorous explanation of the procedure.

CAPACITY KIPANSIOU ALGORITHM

The branch-and-bound algorithm of program D2K2 identifies the least-costly capacity expansion plan by (1) defining, for each site, a time windowduring which the site may be acquired, (2) partitioning this time windowrepeatedly, (3) determining a lower bound on the cost if the sites areacquired within the partitions, (4) analyzing the utilization of each disposalsite within the defined partitions, (5) estimating the cost of alternativepartitions for each site, (6) reducing the partition for the site which willyield the greatest reduction in overall cost, and (6) repeating the processuntil the partition for each site is reduced to a single period or until aniteration limit is exceeded.

Branching. - The branch-and-bound procedure partitions the set of allpossible capacity expansion plans into progressively smaller subsets andcompares the cost of these subsets. The partitioning, or bounding, isaccomplished using an acquisition time window. For each expansion site, theprogram user defines the earliest and latest acceptable acquisition periods.The many alternative acquisition options represented by this acquisition timewindow are evaluated by partitioning repeatedly the initial window into smallcandidate segments and evaluating the cost of each. Each of these segmentsrepresents a capacity-expansion plan with site acquisition sometime betweentwo periods within the user-specified time window The partitioning continuesuntil the candidate segments are reduced to a single period; this defines theacquisition period.

Fig. 3 shows how the branch-and-bound algorithm might partition auser-specified acquisition time window for evaluation. Site acquisition ispossible between 2000 and 2050. For analysis of system operation with thesite acquired after 2000 and before 2050, a partition is made yiwlding twocandidates: acquisition after 2010 and in or before 2050. Analysis of theseoptions leads to partitioning of the latter candidate. (The option ofacquiring the site between 2000 and 2010 will be evaluated later.) Thepartition yields two candidate plans: acquisition between 2010 and 2020 oracquisition between 2020 and 2050. Following analysis of system operation,the option of acquiring the site between 2011 and 2020 is partitioned. Theresulting candidates specify acquisition between 2011 and 2015 or between 2016and 2020. The earlier acquisition promises to provide greater cost reduction,so it is analyzed, and an additional partition is made. In this partition,the site may be acquired in 2011 or in or after 2012 and in or before 2015.If the first option is feasible a, solution to the capacity expansion problemhas been found.

30

Page 35: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

2000 2050

* / ', \

* a,,," -* a

* a *•a

2001 2010:521• •22

. a-*.....a/* a.-...

20 1*2 1 a[1

FIG.3. acusto TieWno atiinn xml

* a 3a

Page 36: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

If several capacity expansion sites are available, the capacityexpansion plans are partitioned based on combinations of the acquisitionperiods. For example, the program user may specify that site A can beacquired between 2000 and 2050, and site B can be acquired between 1990 and2010. The solution can be partitioned into candidates in which A is acquiredbetween 2000 and 2025 with B acquired between 1990 and 2010 and candidates inwhich A is acquired between 2026 and 2050 with B acquired between 1990 and2010. The first solution can be partitioned further into solutions in whichA is acquired between 2000 and 2025 with B acquired between 1990 and 1998 andsolutions with the same acquisition window for A but with B acquired between1999 and 2010. This partitioning continues until a single acquisition periodis found for each site.

Evaluating Cost. - The true cost of each capacity-expansion plan isthe present value of acquistion and lease-renegotiation cost plus the presentvalue of disposal-system operation cost. If the acquisition period for eachsite is known, this cost can be computed by discounting appropriately theacquisition cost from the period of acquisition, adding the discounted OKIcost, and adding the discounted operation cost. The discounted operationcost is computed by formulating a network model and solving to define theleast-costly operation. During the search for the optimal capacity-expansionplan with partitions of the acquisition time window, the period ofacquisition for any candidate capacity-expansion plan is known only to fallbetween the earliest and latest periods which define the partition.Consequently the acquisition and lease renegotiation cost cannot be computedexactly. For each disposal site it is estimated as a function ofdisposal-site utilization as follows:

1. The annual equivalent of the acquisition cost is determined using auser-specified amortization period. The annual ONR cost is added.

2. The resulting cost is divided by the capacity of the site, yieldinga unit cost approximation.

3. This unit cost is added to the user-specified cost of disposingmaterial in the site. The present value of the unit cost isdetermined for each period between the earliest and latest definedby the partition. The resulting unit costs are assigned to thenetwork model arcs representing storage in the disposal site.

The total cost computed using the estimate described always under-estimates or is exactly equal to the true cost. Lesso, Himmelblau, Jensen,and Shanmugham (7) prove this. This fact is critical for eliminatinginferior solutions without explicitly evaluating the solutions. If twoalternative expansion plans are compared, the plan with the greatest cost isinferior, regardless of the size of the partition. Even if another, smallerpartition of the inferior plan is defined, the cost will not decrease. Thusall solutions in which the site is acquired between the periods defining thepartition can be eliminated from further consideration. Any effort toincrease the earliest period or to decrease the latest period is wasted.

Bounding. - The branch-and-bound procedure estimates the cost of eachcandidate solution and compares the cost with an upper bound on the totalcost. This upper bound is the value of the best solution found in theiterative procedure and is updated when better solutions are found. If the

32

Page 37: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

value of any candidate solution exceeds the upper bound, the candidate may beeliminated from further consideration. Furthermore, because the cost of thecandidate represents a lower bound for solutions that might result fromadditional partitioning, all additional partitions can be eliminated also.

Estimating Cost Reduction. - Selection of the partition of theacquisition time window for further investigation is accomplished byestimating possible cost reduction. Each capacity expansion site isconsidered in turn, and the cost of the unused capacity is estimated. Lateracquisition of a site should decrease this cost, but it also renders theproject unusable in earlier periods, so additional cost is incurred then.The algorithm computes the sum of the possible cost decrease and the costincrease due to modification of the acquisition period. The site thatpromises the greatest cost decrease is selected for further partitioning ofthe solution. The partition is made in the period which yields this decrease.

Reiterating. - When a site is selected for partitioning and a periodis selected in which the partitioning is to occur, the latest or earliestperiod for acquisition of the site is redefined to equal the selectedperiod. Thus a new partition of the acquisition time window is defined forthat site; the partition is smaller than the originally-defined window. Thecosts are then re-estimated and the evaluation is repeated. The procedureterminates when the earliest and latest acquisition periods coincide for eachproject or when a user-specified iteration limit is reached.

REFENCES

1. Ball, 1.O., Bialas, W.F., and Loucks, D.P., "Structural Flood-controlPlanning," Water Resources Research, Vol.14, No. 1, Feb., 1978, pp.62-66.

2. Bickel, T.C., "The Optimal Capacity Expansion of a Chemical ProcessingPlant via Nonlinear Integer Progranming," thesis presented to theUniversity of Texas, at Austin, TX, in 1978, in partial fulfullment ofthe requirements for the degree of Doctor of Philosophy.

3. Brill, E.D., and Nakamura, M., "A Branch-and-bound Method for Use inPlanning Regional Wastewater Treatment Systems," Water ResourcesResearch, Vol. 14, No. 1, Feb., 1978, pp. 109-118.

4. Efroymson, M.A., and Ray, T.L., "A Branch-and-bound Algorithm for PlantLocation," Operations Reserach, Vol. 14, May-June, 1966, pp. 361-368.

5. Garfinkel, R.S., and Nemhauser, G.L., Integer Progranming, John Wileyand Sons, New York, NY, 1972.

6. Lawler, E.L., and Wood, D.E., "Branch-and-bound Methods: A Survey,"Operations Research, Vol. 14, 1966, pp. 699-719.

7. Lesso, W.G., Himmelblau, D.M., Jensen, P.A., and Shanmugham, C.V.,"Capacity Expansion Model of Water Resource Facilities for a Major RiverSystem," Technical Report CRWR-115, Center For Research in WaterResources, University of Texas, Austin, TX, 1975.

33

Page 38: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

8. Marks, D.H., and Liebman, J.C., "Mathematical Analysis of Solid WasteCollection," U.S. Dept. of Health, Education, and Welfare, Bureau ofSolid Waste Management, Washington, D.C., 1970.

9. Mitten, L.Z., "Branch-and-bound Methods: General Formulation andProperties,' Operations Research, Vol. 18, 1970, pp. 24-34.

10. Morin, T.L., "Solution of Some Combinational Optimization ProblemsEncountered in Water Resources Development," Enuineering Optimization,Vol. 1, No. 2, 1975, pp. 155-157.

11. Nakamura, M., and Brill, E.D., "Generation and Evaluation of AlternativePlans for Regional Wastewater Systems: An Imputed Value Method," WaterResources Research, Vol. 15, No. 4, pp. 750-756.

34

Page 39: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

APPENDIX III

D2M2 EXAMPLES

Program D212 provides the capability to model a variety of disposalsystems and to simulate a variety of system operation criteria. Thisappendix includes five examples which illustrate program capabilities. Eachexample includes a description of the problem, with input to and output fromprogram D2M2. Key items of the input and output are numbered for convenienceof explanation.

Example one illustrates application of D2M2 to analyze the continuousoperation of an existing disposal system. In example two, the restartcapability of the program is used to analyze operation for two successive25-year planning periods. Example three is a modification of example one,with provisions for "resting" the Edgewood site for two periods after eachthree periods of availability. Example four illustrates simulationspecification of a portion of the operation policy. The capacity expansioncapability of the program is illustrated by example five.

EXAMPLE ONE: ANALYSIS OF CONTINUOUS OPERATION

This example illustrates application of program D2M2 to determine thestatus of and operation cost of a dredged-material disposal system if theleast-costly operation policy is followed for 50 periods, each of which isone year in duration. The system consists of two dredging sites from whichmaterial may be transported to four disposal sites, as illustrated by Fig.4. Analysis begins in 1981. The ocean disposal site and the WilliamsonHarbor and Edgewood sites are available in 1981 and remain availablethroughout the 50-year analysis period. The lease on the Edgewood site is tobe renegotiated in 1999 at a cost of $10,000. The Williamson Harbor Southdisposal site is not available until 1987, when it is acquired at a cost of$1,725,000. This cost is amortized with 7-5/8% per period discount rate.The present value of all costs is determined using the same discount rate.Two dredging and transporting techniques are employed: a 16-inch pipelinedredge and a government-owned hopper dredge. The unit cost of dredging andtrarnporting the material is a function of the distance from the dredgingsite to the disposal site.

Reproductions of selected portions of the D2M2 output are includedherein. Key items are numbered for convenience of explanation.

The program banner page (item 1) identifies the version of the programand the latest revision of the users manual. The date and time of programexecution are also shown.

Item 2 is a list of all user-provided input, exactly as read by theprogram. The cards are numbered for subsequent reference. The input forthis example includes three title cards (cards 1, 2, and 3), and a J1 card(card 4) for system dimension specification and job control. The values onthe Jl card indicate that 50 periods will be analyzed, beginning in 1981(fields 1 and 2). Each period in this case is one year, but the calculationsperformed do not require or assume this duration. Fields 4, 5, and 6 of theJ1 card define the number of disposal sites, number of dredge sites, andnumber of dredged-material transportation methods. The value in field 9

35

Page 40: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

Ocean Disposal Site(OCEAN 1)

Williamson HarborDredging Site(WIU4A)

Williamson HarborDisposal Site (WILHAR)

Edgewood Disposal Site(EDGEWD)

Williamson Harbor BDredging Site(WIULBO)

Williamson Harbor SouthDisposal Site (WILSUD)

FIG. 4. - Disposal System for Example One

36

Page 41: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

specifies 15 periods for amortization of site acquisition costs; the discountrate of 7-5/8 percent per period is specified in field 3. Identification ofthe amortization period is required to allow proper computation of thepresent value of acquisition costs for comparison of alternative schemes. Aset of cards TI, TD, and TC cards (cards 5-10) is included for each of thetwo dredging techniques. These cards identify the dredging technique anddescribe the distance-cost function for each. The values of unit cost as afunction of distance are used with computed distance to estimate appropriateunit costs between irterconnected sites. Linear interpolation is used, sothe values specified must be selected accordingly. Cards 11-16 define thecharacteristics of the Ocean disposal site, cards 17-22 define thecharacteristics of the Williamson Harbor South disposal area, cards 23-28describe the Williamson Harbor disposal area, and cards 29-34 describe theEdgewood site. Fields 1 and 2 of the SL cards define the location of eachsite; the program uses these to compute distances. The off-river distancefor the ocean site (field 2 of card 12) is specified as an arbitrary, largevalue to yield a high cost, thus discouraging ocean disposal. Theacquisition status of each site is defined by the value in field 1 of the SXcards (cards 13, 19, 25, and 31). The ocean, Williamson Harbor, and Edgewoodsites are added to the system in 1981, as specified by the value in field 2of the SX cards. Acquisition costs ftr these sites are ignored in thisanalysis, so these are omitted from the SX cards. The ocean, and WilliamsonHarbor sites are available throughout the analysis, as specified in field 4of the SK cards. In the case of the Edgewood site, the lease is to berenegotiated in 1999, as specified by the value in field 4 of card 31. Thatsite is then available throughout the remainder of the analysis. TheWilliamson Harbor South site is added to the system in 1987 (field 2 of card19) and is available throughout the analysis. The Williamson Harbor dredgingsite is described by DI, DL, and DT cards (cards 35-39), and the volume ofmaterial dredged in each period is specified on DV cards (cards 40-45). Forthis example, the total volume is specified for each period, so six DV cardsare required with nine values specified on each. Cards 46-56 describe theWilliamson Harbor B site and define the volume dredged each period.

Each input error detected by the program is identified (item 3). Thesequence number of the card and the variable which is specified incorrectlyare shown. If a default value is used rather than the specified value, thedefault value is shown.

The basic data summary (item 4) shows the values specified by the useron the J1 card. Item 5 is the summary of dredge and transportation data.

The disposal site input reports summarize the data for each disposalsite in turn. The report for the Williamson Harbor South disposal areacomprises items 6-17. Similar reports are printed for each site but are notshown here. Item 6 is the specified location of the disposal site in termsof main-stem river distance and off-main-stem distance. Any origin formeasurement may be used, but all river distances must be specified relativeto the same origin. The off-main-stem distance may be specified as apositive or negative distance, depending on the location to the right or leftof the main river. The off-river transportation type also is shown. If thisfield is blank, the transportation type is assumed to be the same as thetransportation type used on the main-stem. Item 7 is the disposal sitestorage data, including the initial volume of material in the containmentsite, the wet-to-dry ratio (volume of wet material divided by volume of

37

Page 42: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

material after drying), the maximum allowable rate of addition of wetmaterial, and the unit cost for addition of material to the disposal site.For the Williamson Harbor South Disposal area, no maximum allowable rate isspecified (field 6 of card 19), so the site capacity is used as the defaultvalue. The site acquisition cost (in 1981 dollars), acquisition date, andthe expansion indicator (field 1 of card 19) are shown (item 8). The presentvalue of the acquisition cost is determined and is added to the systemoperation cost. If the site is leased and a lease-termination date isspecified, this is shown (item 9). Lease renegotiation costs are also shownhere. The present value of the renegotiation costs is determined and isadded to the sum of acquisition cost and operation cost. Data on reuse ofdried material from the disposal site are summarized (item 10), and transferdata are reported if provided (item 11). No transfer of material from thissite is possible, so no data are shown here. If transfer is possible, thepotential ultimate disposal sites and the transportation techniques areidentified. Finally the capacity-elevation-area function for the disposalsite is shown (item 12). Linear interpolation is used with these values, sothey should be specified accordingly.

The dredge-site input report for the Williamson Harbor dredging site(items 13, 14, and 15) shows the volumes of material dredged, by period, andthe techniques available to accomplish the dredging and transporting ofmaterial to the disposal sites. A similar report is prepared for each site,but these are not shown here. The dredging site location (item 13) isspecified in terms of main-stem river distance and off-main-stem distance,using a constant origin for main-stem locations and positive or negativedistances for off-main-stem distances. The material volume multiplier is aconvenience to allow scaling of all specified volumes for this disposal siteprior to analysis of system operation. If desired, this may be used toaccount for the difference of volume in situ and volume to be transported.The transportation link data summary (item 14) identifies disposal sites inwhich material from this dredging site may be disposed and the techniques forand unit cost of moving the material to the sites. Finally the materialvolumes are tabulated (item 15); these are the user-supplied values, scaledby the volume multiplier.

The volume summary report (item 16) shows the total volume by period,before drying and consolidating, that must be disposed within the specifiedsystem. The dimensions of the resulting network-flow programuing model areshown (item 17).

The capacity expansion iteration log serves as a cost summary in thisapplication of D2M2. Only a single execution on the model is required; thisis shown as iteration 0 (item 18). The disposal sites are identified andpertinent acquisition and lease dates are shown. The sum of present value ofsite acquisition, lease renegotiation, and operation, maintenance, andreplacement (OMR) costs for all sites is computed and shown (item 19). Theminimum-cost present value of system operation cost is shown, as determinedby solution of the network-flow programming problem (item 20). This costrepresents the cost of material transportation and disposal, less the revenuefrom reuse. The total net cost (item 21) is the total of acquisition, leaserenegotiation, ORR, and operation costs for all sites for the period ofanalysis.

38

Page 43: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

The results of optimal operation of the dredged-material disposal systemare presented as reports of the status of and changes to each disposal site.These reports include a tabulation of material added to the disposal site,either from dredging sites or from other disposal sites, a tabulation ofmaterial removed from the site for transfer or reuse, and a tabulation of thecontainment site storage, elevation, and surface area. An example, thereport for the Williamson Harbor South site, comprises items 22-25. Similarreports are presented for all sites, but are not included here.

The Williamson Harbor South disposal site may be used for containment ofmaterial from the Williamson Harbor dredging site and from the WilliamsonHarbor B dredging site. The volume of material transported from each isshown and the discounted transportation cost is tabulated (item 22). Thetotal for all dredging sites is shown (item 23), and the total for allperiods is computed and tabilated (Item 25). If the site fills, this isindicated (item 24). The disposal-site status report shows for each periodthe total volume of consolidated material added to the site (item 26), theresulting volume of material stored at the end of each period (item 27), andthe disposal cost (item 32). The elevation (item 29) and surface area (item30) corresponding to each storage are determined by reference to theuser-provided capacity-elevation-area function. The total volume ofconsolidated material added and the cost of the addition are presented (item31).

System operation for the entire period of analysis is summarized in thedredged-material source/disposal site report (item 32). Eachdredged-material source and disposal site is shown in this matrix. The totalvolume moved from each source to each disposal site is shown, and the firstand last periods of disposal site utilization are shown.

Item 33 is a graphic summary of disposal site use. Each period that anymaterial is deposited in a site is indicated by an "1X1 in the appropriatecolumn.

39

Page 44: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

6. u0%F- Min

4A0

-ý:s NU

'in N9,

=;PNN

NE NNz

cm cmKcm cm t

cm ccm cm c

KIKEKEcmcmc

NeNg

00040

Page 45: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

N 0B11iCcI an4 ann-fil

00~k Inn 000

0OMN 0 or Hoof

owan .111 5-

Nm 0~N 0, cm

~a~ -==nannwanna

N0~ -41

Page 46: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

4A 4A

tA- Lma-

LLSa

LLI LLP I&A a 4A

4c 41C. a

-a4b.

N 42

Page 47: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

0 40

840

8~CV

117!OI- ODOMI J

_ 00

viW 1- - -

88

LhJWWRW Lfl§

zzzsz

In

u) 85t)n~ 8st

8 "4

M- -iC" 0%.

z -CL

w jInn

IX 43

Page 48: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

,48

-VA

MNNaA8

98uCV)

*j I

I I04 8

A. aI I-

-j -a

w l 0 0 0

b-al WI

a: I. I -

In'n

#A 1.4

-Ji In0

I n

Omn

Page 49: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

88888

-Lntn UMz -U

-8888

-1 88888

1.- 88888I.- I

88 1-888WI.

LL) #A Ln 88

KU 0. . - Ln L L

* U 88~888

-i t-

0. IE I -W'-'L z, CL C-

I.- 101111Z ~ L 88888)a -)U

~l8

45

Page 50: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

§1 l o 1

cm - -

w CI I- - IN

IxI

uIn~

I LA.

II.

LU 0-4

cmCI

L u

ey~I.

a~!~ to

46

Page 51: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

I-

04

4Ic

uin

- --

-u NClCi000

LLS 0--4 9 -

4cit 49it4~~

LUwL0

ffi M

0 liC

cc

47

Page 52: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

000000000000000•0000000000000000 00000000

.. ..mmm

S...................................................

~ooo°°oooooooooroo l!!l!I!!I!I jooeooeooeoo°o

o~o.°oo~o!°..................li

004

+'++~..... ..+++++i+r +i+ ... .. ..!!!!!! .............. + ++++ itoo 004 o. to e o e e to ot *-o 4- 44.t o

0 000 ~U0O00000000C00

w~~~i fil k55n.181 --.111

48 A

48

Page 53: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

88888888888888888 8~8888Q88

ým il t i. 9i g4 .i gi K'

LUI

. . . . . . . . . .

41 4114411441144114411 Cov!900244114411444114 ................ 441144114411 144

(2 oo4-,oo

v1 8 %.0 i t 4 c i si g00i c4 90 i 1 4

is414it 414 it4141414 414 it41 it441444444 4141 4141414141441414'A 141441414R 41414411-41414144141 it4it

list 0~ t ARU RUI11111 111100 4C *00~0 0 4C0 * 1 *00 0 [*iit0 0 0000 0 0

In~n n~n I~n 49

Page 54: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

0~ 40 0i 0 0

- ' LA-

it ~ 0t 09 09i 9 4 9i 9 4 9i t

z

0L 0 0

wq

4'-4

0-1

****4t**

50 %

Page 55: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

X Iux -1

WIA ' I nxCI~' C x

'C~

XC 10In 'C IkA x

CL >- 'C

WI-I II 'C '

US RC ' In4n I Q0

ca )( x-

xI-n

x Q

51

Page 56: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

EXAMPLE TWO: ANALYSIS OF OPERATION WITH RESTART

This example illustrates the "restart" capability of program D2M2. Withthis capability, the program automatically can be executed recursively, withthe final status of disposal sites from one execution serving as the initialcondition for the next execution. The system considered in this example isthe same as that considered in example one, but instead of analyzing 50periods of operation, each one year in duration, two successive 25-periodoperations are analyzed. The first analysis determines the least-costlysystem operation of the system for 1981-2005. Program D2N2 then prepares aninput file for analysis of system operation for 2006-2030. The initialconditions specified in this input file are the final conditions for 2005, asdetermined from the first analysis. This is illustrated by Fig. 5.

The program user must issue appropriate job-control commands to executeprogram D2M2 with the program-prepared input file. The commands shouldaccomplish the following: (1) save the program-prepared restart input file,TAPEll, from the first execution; (2) rewind TAPEll; and (3) execute D2"2with input read from TAPEll.

Item 34 is the user-prepared input file for analysis of 1981-2005operation. This input file is essentially the same as the input file forexample one. However, the specified period of analysis is 25 periods (field1 of card 4). The value in field 10 of card 4 specifies that D2M2 is toprepare an input file to permit analysis of 25 additional periods withsubsequent execution of the program. Volumes are specified on DV cards foreach dredge site for only 25 periods (cards 40-42 and 48-50). The volumesspecified for each site on DV cards of the program-generated file correspondto the final value shown on the DV cards of this initial input file (550,000volume units per period for both sites). Field 3 is blank on the SX cardsfor the Ocean, Williamson Harbor South, and Williamson Harbor disposal areas(cards 13, 19, and 25). This indicates that these sites are availablethroughout the original 25-period analysis and the subsequent 25-periodanalysis performed when the program is restarted with the program-generatedfile. The lease for the Edgewood site is renegotiated in 1999, and that sitetoo is available throughout the remainder of the analysis.

Disposal-site input reports and dredge-site input reports similar tothose of example one are printed but are not included here. The volumesshown in the dredge site reports are those specified for 1981-2005.

Item 35 is the capacity expansion iteration log for analysis of thesystem operation for 1981-2005. As with example one, this serves as asummary of costs. This total net cost shown is the sum of acquisition, leaserenegotiation, OMR, and operation costs for 1981-2005 inclusive. The presentvalue calculations use the first period of analysis, 1981, as the base period.

System operation for the 25 periods, 1981-2005, is summarized by thetabular and graphical summaries identified as items 36 and 37.

A restart input file is prepared by D2M2 to allow analysis of operationfor 25 subsequent periods beginning with 2006. This file is shown as item38. Field 10 of the J1 card (card 4) indicates tL.at 1981 is to be used as

52

Page 57: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

User-Prepared Input

forPeriods 1981 - 20061

Output from Analysis

Program D2M2 of

Periods 1981 - 2006

Program-Prepared

Input for Periods

2006- 2030

S Program D2M2

Output from Analysis

of

Periods 2006 - 2031

FIG. 5. - Schematic of Restarting Execution of Program D2M2for Example Two

53

Page 58: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

the base year for cost amortization. The initial storage for each disposalsite is specified in field 3 of the SL card for each site (cards 18, 24, and30). The volume to be dredged at the Williamson Harbor dredging site anddisposed each period is 550,000 CY, and the volume to be dredged and disposedfrom the Williamson H~rbor B site is 550,000 CY. These values, specifiedoncards 40 and 46, respectively, correspond to the values previouslyspecified for each site for the final period of the initial analysis (2005).

Item 39 is the capacity expansion iteration log for analysis of systemoperation for 2006-2030. The acquisition, renegotiation, and ONR costs shownare the 1981 present-value equivalents of any such costs incurred in2006-2030. The operation cost shown is the 1981 present-value equivalent ofoperation in 2006-2030. Consequently, the total net cost shown is comrarableto total net cost computed for 1981-2005 in the initial analysis. Thetotal-net-cost values can be added directly to determine total cost for1981-2030 with the operation shown.

The operation for periods 2006-2030 is summarized by items 40 and 41.

Comparison of example one results with example two results shows thatthe disaggregated analysis may not yield the optimal operation scheme. Thecost of this optimal operation scheme for 50 consecutive periods is $31.7million while the sum of the cost for the two consecutive 25-periodoperations is $32.8 million. This is expected; in example two, analysis ofthe first 25-period operation cannot consider the disposal requir.•,•ents ofthe second 25 periods. In example one, the disposal requirementz of all 50periods are considered simultaneously, so disposal site capacity can beallocated more efficiently. However the restarting procedure may provide theonly means to analyze long-term operation of a system which includes a largenumber of dredge sites and disposal sites. Then the near-optimal solutionmay be acceptable.

54

Page 59: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

~Ilog III 0

N 0000

0U C; .

iol IIU.V NI.-

LI- 0 i222A I p Woy W d rC~l O'0- " - .

gngq0 -j4 PQ -

F- n _jjj_ - a_- 0j_

34 - -m " w- x N

-~l CY Caf 0 Cy~~ Q C M -- ý

55

Page 60: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

-w

4IA

w 1.4LM0

"a- -j -i

0-0

I-6

Page 61: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

49

I.--

Co 00 0 0 0

0j 0

1 9 *o *o cio *o

0 0 0

iIi 4*

I-.j

I-01-. b.4 c -j

~c c~O57

Page 62: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

LOI)

Lnuj I-a

4A6-

'-0

58

Page 63: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

CD,

A, A

cu"

Ln L -

-n IN -r

-NI ISO

i-I 0)I P4 I.

-m ý C.4

cm W

tA 9xx L&

en go a I

Ann

-- 000 wi wW- -.. e L-.-a-0i--fIII UIAnA)AUL u. A)IlfV C 0 0 C

ccN)I'U- -N)Ii

N~~~~~ n~~~~~~~ N N(J 0 )V000 .2 1ffj

CV) CL59

Page 64: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

tmB-Cc

0-IAS LA

*U ft~g

U.a- B

UjN

P4 -a .

w

I-t

~ ~I460

Page 65: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

Lhoc4Aqu-

- - Ni

*0 0 0

CA %1- .-o

Lo 6- 0 0i

w 39*0 * 0 *&A 9 w I oý

oi 0 0 0

InnI-m

S..- ~ ~ 4 w*0 * *0 0

'An 0 0. 0I-9

S 61

Page 66: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

-i LI 4

x x

x

uiu1-4 b-4-

1-4 -.

62

Page 67: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

Example Three: ANALYSIS OF OPERATION WITH DISPOSAL SITS RESTING.

In practice, dredged-materal disposal sites generally are not usedcontinuously. Instead sites are "rested" following use; the sites areallowed to dry and maintenance is performed as necessary. This operationpractice is simulated in program D2M2 with cycles of availability andnon-availability of sites. This example illustrates analysis of systemoperation with site resting. The system analyzed is the same systemconsidered in example one, but the Edgewoode site is rested for two periodsof each five.

Item 42 is the user-prepared input for example three. This input fileis essentially the same as the input file for example one. The resting ofthe Edgewood disposal area is specified in field 2 of the SX card for thatsite (card 31). The value in columns 9 and 10 indicates the site isavailable for three periods prior to resting, and the value in columns 11 and12 indicates the site is rested for two periods. This cycle is repeatedwhile the site is available (1981-2030).

As with example one, disposal-site and dredge-site input reports areprinted; these are not included here. Likewise, disposal-site status reportsare printed for each site; these are also omitted.

Items 43, 44, and 45 sunimarize system operation for example three. Thesame volume of material is disposed in each site as in example one (see item44), but the timing of the disposing is different due to the resting of theEdgewood site (see item 45). The total system net cost is $37.8 million(item 43), which exceeds the cost of optimal operation in example one.

63

Page 68: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

"111l!

1 101kn-!, " I i X= ýj- ° >r - I Hi 111 11111

ti 1 • • ".•!"--•l0. °lllll 01==11

:i; alp",~I too 'M

,. 1,.- 0 ! ! -i - og1 11 . 1 1

j~~8~g~oi IOO? ~

! -i-------°. ... N, -Nt -1-- t - -

64

Page 69: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

I-- j

-JL

I.-

,..4.

1w ;c01

w * ---w0'L

C-j I.-.

L .8 - i- - -

-i Ln LnI.- 0 ~

000

8 6 -

i R5

Page 70: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

I.- .- %

LLJ C~o 0 0~ *0CD

tnn

-i4A

I I-

In dL 1 0 6 0 C~ ciw I

LL0 0- 0

-l 8

b-ii N

-J~~~n CI - 0 0

"'33

4A % 'sWEýn 0 0 C

6-4 -4--j -

L" 4c11 44444441111111 444

*0 ~ 4 it*0 *

W In 0 0 0 06

Page 71: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

C,

zx-4l

5 -

'CV

W x

V) 'C

'C x

LnI.- IU. -4 -I

LC I tx

'C ' I'C I LM

x "5

67

Page 72: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

Example Four: ANALYSIS OF OPERATION WITH PARTIAL SOLUTION SPECIFIED.

Due to non-economic factors, operation policies that are not theleast-costly policies are sometimes necessary. These policies can besimulated with program D2M2 by specifying the volume of material that is tobe transported in a specified period from a dredging site to a disposalsite. Example four illustrates this.

The disposal system modeled in example four is the same system modeledin example one, and cards 1-56 of the input (item 46) are identical to cards1-56 of the input for example 1. The required system operation is shown inTable 2. This operation is specified on cards 57-62. Each card specifies adredged-material source, disposal site, period, and volume. In this example,no alternative transporation types exist between pairs of dredging sites anddisposal sites, so transportation types need not be specified (field 5 of FScard). When a partial solution is specified, the user must specify asolution that is feasible: the disposal site and dredge site must beavailable and must be linked, and the transportation link and the disposalsite capacities must not be exceeded by the volume specified.

Disposal site input reports and dredge site input reports similar tothose of example one are printed but are not included here. Likewise asystem volume report is printed, but is not included here.

Item 47 is the capacity expansion iteration log, which serves here as asummary of system costs. The present value of the operation cost shown hererepresents the least cost for operation of the system, given the requiredoperation specified on the FS cards.

Items 48 and 49 are the components of the operation report for theWilliamson Harbor South disposal site. Similar reports are printed for theother disposal sites, but these are not reproduced here. The volumestransported to this site from the Williamson Harbor dredging site in 1987,1989, 1990, 2029 and 2030 are volumes specified on the FS cards. The statusof the disposal site with this operation can be compared with the status ofthe same site without the forced operation by referring to items 22-31 ofexample one. In example one, the site filled in 2018 and thus was notavailable for use from 2019 to 2030. However in example four, therequirement that 550,000 be transported from the Williamson Harbor dredgingsite and disposed at the Williamson Harbor South site in both 2029 and 2030precludes this. The disposal site must have space available to store thematerial. This is accomplished by adding material to the site until 2017,reserving capacity to store the material deposited in 2019 and 2030. Thesite is filled then in 2030.

System operation for example four is sunnarized in the dredged-materialsource/disposal site summary report and the disposal site usage chart,included as items 50 and 51.

68

09 -

Page 73: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

TABLE 2. - Required Operation for Example Four

Volume, in

Period Dredsed-material source Disposal site cubic yards(1) (2) (3) (4)

1987 Williamson Harbor Williamson Harbor South 550,0001989 Williamson Harbor Williamson Harbor South 1,100,0001990 Williamson Harbor Williamson Harbor South 1,100,0002029 Williamson Harbor Williamson Harbor South 550,0002030 Williamson Harbor Williamson harbor South 550,000

69

Page 74: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

COE~

10i i C, 101 H l

In o: oo

N= 0ow In In I

o n wt In -- nSuJ - A

I (mlcc~

§n~ ~~ a o.c o ~oo~~o0 ~ 50wl c"

- - - - . H ill.

70

Page 75: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

U-

U.0

Lai

1 >

_jI LeS IS-

1.-b- P-4 j _

1 ccn'3949 lw

iij

71

Page 76: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

a.

000000 ~~S ARE~ a.~3000

- - -------- I

0 66666046 0cc a 0ac 0 OOOQCCOeOO 0ocoaco CC10ooooo 0 0 0 00 0

on X

c~odo-N@. -000000000

-C 0

LAS N , W U, 0,

U, ,~4- 414.i 4 4 .4 4 -4 -$- 4.4 94 1 .4 V4 N t4 94 9 -4 14 9 1 i ,o . A' -4 - 14 .4 ' .4 A0

*::::::****:::::t:*:* *:** ***.............: **- 000 go OOQOO

A 0yA!1a

4- - t I 4 'A014111 1 1 04949 9 1 t * * : : : * : * * * * : : : * : i:4*p04 . 4 .4 . ti 14 g4 1i t414 14 t i .4 .

72

Page 77: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

enc nmE~m CCcyJ 0 coo co- mmmv D00'f.

-. . ..00 .80 ..80000 ..

CYu U R,

000000

0 00

73

Page 78: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

Co a~ ca a a

a 4g * 4g

LL0 *i 0 *0o *e

oC~ 0 0 0

P- N N

4c 4g0

0j

*0LL,0 *

0 0 0 0

ini cLI 0 0 0

N - 0 0 0A

4~V) 1-4 P-4 0 *0

~ - 0 0 74

Page 79: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

LI-

-i

Lm I.-

ai

&A I.-

0'-4

Wx

""4- P-I -

.~Jan 75

Page 80: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

x•ample Five: APPLICATION OF CAPACITY MANSIOU CAPABILITY

This example illustrates application of program D2M2 to select aneconomically efficient capacity-expansion schedule for a disposal system.The system, illustrated in Fig 5, includes two dredging sites, two existingdisposal sites, three disposal sites that will be acquired in period 2000 forcapacity expansion, and the Williamson Harbor South site, which may beacquired if economically justified. System operation for the period1981-2030 is to be analyzed, but acquisition of the Williamson Harbor Southsite is considered only between 1981 and 2000 inclusive. Material from thetwo dredging sites is removed and transported to the disposal sites with a16-inch or 27-inch pipeline dredge or a government-owned hopper dredge. Therates of required removal from the dredging site are the same as specified inexample one.

Items 52 through 58 are reproductions of selected portions of the D2M2output. Item 52 is a list of the program input. The input required toexercise the capacity-expansion capability of D212 is essentially the same asrequired to use D212 for evaluation of system operation; the exception is themanner in which the potential capacity expansion site is described. As withexample one, title cards (cards 1-3) and a J1 card (card 4) are provided. Onthis J1 card, the total number of disposal sites (field 4) is the number ofexisting sites plus sites with specified future acquisition periods pluspotential capacity expansion sites. A set of TI, TD, and TC cards isincluded for each dredging and transporting technique. If techniques notcurrently used may be used for expansion sites, these techniques must bespecified here with TI, TD and TC cards. A set of SI, SL, SX, SS, SE, and SAcards are provided for each disposal site. Cards 20-25 and 26-31 are thedisposal-site description cards for Williamson Harbor and Edgewood, theexisting sites. The three sites for which future acquisition is specifiedand the potential expansion site likewise are described by data provided onSI, SL, SX, SS, SE, and SA cards (cards 14-19, 32-37, 38-43, and 44-49). Forthe capacity expansion site, the parameter IEXP (field 1 of the SX card) isthree, indicating that the site may be acquired anytime between IPERA andIPERG, the specified earliest and latest possible period for acquisition.For this example, these periods are specified as 1981 and 2000, respectively.

The capacity-expansion iteration log shows the expansion plans that areselected and evaluated by the program and the results of each evaluation.For each iteration, the trial acqusition period for the site is shown (item53). For the potential expansion site, this acquisition period changes fromiteration to iteration. The lease termination period is identified for allsites (item 54). This is the period in which the lease terminates; the sitethen is no longer available for use unless the lease is renegotiated. Forsites that are not leased, this is shown as the period following the study.After the termination period shown (item 55), the designated disposal site isno longer considered for use. For existing or possible capacity-expansionsites this is the last period of the study. For leased sites, this is thelast period of the study if lease renegotiation is considered in theiteration; otherwise the site is unavailable after the lease terminationperiod. Item 56 is the approximate total net cost of each alternativecapacity-expansion plan evaluated. The estimated present value ofacquisition cost, lease-renegotiation cost, ONR cost, and operation cost isincluded in this calculation. Acquisition cost is estimated as a function ofsystem operation in all cases in which a specific acquisition period is notdefined for all capacity expansion sites, so no cost breakdown is possible.

76

Page 81: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

Lucky Strike Expansion

Site (LUCKYS)

Interstate ExpansionSite (INTER)

Williamson HarborDredging Site(WILMHA)

Williamson Harbor

Disposal Site (WILHAR)

Edgewood Disposal Site(EDGEWD)

Williamson Harbor BDredging Site(WILMBO)

Williamson Harbor SouthExpansion Site (WILSUD)

Belvedere ExpansionSite (BELVED)

FIG. 6. - Disposal System for Example Five

77

Page 82: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

For the example problem, the minimum-cost expansion scheme found callsfor acquisition of the Williamson Harbor South site in 1990. The actualpresent value of total cost for this plan is $23786139, which includesacquisition cost and ORR cost of $892846 and operation cost of $22893294.These true costs are shown in the final row of the iteration log (item 57),which recapitulates the optimal solution. Identification of the optimal planrequired 12 iterations as follows:

Iteration 0: Acquisition of the Williamson Harbor South site isconsidered at any time following the earliest specified date (1981).This includes not acquiring the site at all within the time horizon ofthis analysis. A network is formulated with the site available for allperiods following 1981, and the acquisition cost is approximated as afunction of the utilization of the site each period.

Iteration 1: At the beginning of each iteration, a capacity expansionsite is selected as the candidate for acquisition period revision. Inthis case, only one potential site is defined, so its acquisition periodis altered from 1981-2031 to 1981-2000. The latest acceptable periodfor acquisition of this site is 2000, so in this iteration, theefficiency of site acquisition within the specified allowable timewindow is evaluated.

Iteration 2: The utilization of the Williamson Harbor South site isevaluated. The site is not used extensively, so acquisition ispostponed until it is 10% filled, in 1997. However acquisition in 1197fails to provide capacity needed earlier, so this alternative isinfeasible.

Iteration 3: The algorithn oack racks and considers acquisition between1981 and 1996 after determiring that acquisition after 1996 isinfeasible. The approximate cost of this is $23500275.

Iteration 4: Utilization of the site in the previous iteration isconsidered. In 1990, the site was 10% filled, so acquisition ispostponed until then, yielding an approximate cost of $23515395.

Iteration 5: In iteration 4, the site never filled to 10% of capacitybetween 1990 and 1996, so acquisition is postponed to at least period1994. This is 67% of the time from 1990 to 1996, a percentagedetermined from experience. Unfortunately, such postponement is notfeasible in this case.

Iteration 6: The procedure backtracks and considers acquisition between1990 and 1993. This is feasible, and the approximate cost is $23661674.

Iteration 7: The site does not fill to 10% between 1990 and 1993, soacquisition is postponed using the 671-criteria again. Again this isinfeasible.

Iteration 8: The algorithm backtracks and evaluates the cos:.- ofacquisition between 1990 and 1991. The approximate cost is $23786634.

Iteration 9: Again the site does not fill to 10%, so again acquisitionis postponed to 1991 with the 671-criteria. This is infeasible. Notethat this iteration yields a potential solution: acquire the site in1991. However that solution is infeasible.

78

Page 83: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

Iteration 10: Backtracking now requires evaluation of acquisition in1990. This is feasible, and the cost is approximately $23786139. Thisis then a feasible acquisition plan: acquire the Williamson Harbor Southsite in 1990. However, without further evaluation, this cannot bedeclared the optimal solution.

Iteriation 11: The procedure requires backtracking to evaluate all as-yet unconsidered alternative solutions. Acquisition between 1981 and1989 is one such solution. However the approximate cost excewds thecost of the solution found in interation 10, so this solution, and anysolution requiring acquisition between 1981 and 1989, can be eliminatedfrom further consideration.

Iteration 12: The algorithm backtracks finally and considersnon-acquisition, which is infeasible.

Following the capacity expansion iteration log, the usual disposal sitereports and operation summaries (item 58 for example) are printed for thesystem with the optimal acquisition of expansion sites.

79

Page 84: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

tyn mniniS~

t4n

V 3 5- 8 co

- N01I01115 fo0fRIINQ UOO, a, 'n 1. Q QnS0 0

A WN NA oil~

~-10 510S000X 0n -~151 0, 9 % ,1 1 ; 1

0~~- - 9--n ~ ~ N S~~

8G0

Page 85: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

3 9

I z IN 0j %nSf

I.- zN~ cmN

-nIIxLug

)I- 0%. I.-- -- OS-000 00 00 020 0%00 0 0 0 009

1. 0 L a OR00 0 02

kA 1. 04 04w C4 ( MCN M " Y N 4 e4C4 VCMI 4 IN O I i O

4t J-~s4t t i t4 t*4 t4 t4 t 4 t i it it-J - 2W-J 4c&Lit.it i 4c

Nt Vj Urm81 Mm 2g22 -2-

Page 86: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

N VC

0 91 0 1N .04 g * i . 04 9 t 00 0 *$

it1441141 4 1444114 441t .4t 14141A0 t4-141 41 414 4141 4 t41 it14114 414441 4 it414141*114 41 41 i t 410 1 4t1t t 4 1041 ti.it491s4141 4 14 4141 t t41 4141 4 t1i 41 i tt4141414141 41 is41 it4141 it141 41414414141 414141it141141 it41 is i

* i*6 0* iti tf 4 t00 0 -9 N9 ** 4* * i *i f 0 * * *1:4141A14141I 411441144 41111444 414114114 4141414111 41i111i 1 44441111 4444444

9-- -- - - ----- ii A !82

Page 87: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

1-4~

*0 .0 N0. *

oe e 0it0 0

I LU~ a 00 6 CD a06

Po 0

LLUI-jI

i t 0 60 60 60 0 60 0

-4~~CV LU CY. % ~ . %. %

LU&.11.-0

P>- --

**4

w 0 0 0 0 0 83

Page 88: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

APPENDIX W

D2N2 INPUT DESCRIPTION

INPUT DESCRIPTION

This appendix provides a detailed description of program D2M2 inputrequirements, by card and by variable. The requirements are sumarized inFig. 7. The field number shown for each variable designates the location ofthat variable on the input card. Of the 80 columns available, columns 1-2are reserved for the card identifier and are referred to as field 0 (zero).Field 1 includes card columns 3-8. Fields 2-10 contain eight columns each.When necessary, an abbreviated field location description is used to identifyvariables; the card name is followed by a decimal point and the fieldnumber. For example, SL.8 refers to the eighth field on the SL card.

All variables with names beginning with I, J, K, L, K, or N are integersand must be right-justified without decimal points. In general, inputvalues, both numerical and alphanumeric, should be right-justified in theirfields, except for multiple field alphanumeric information.

Appropriate values for each variable are shown in the column headedVALUE. A "+" in the column indicates a non-negative value should beprovided. A "-" indicates a negative value should be provided. In somecases, either non-negative or negative values are acceptable; the variabledescription specifies the interpretation of the values. The abbreviation"AN" identifies variables for which alphanumeric characters are to bespecified.

84

Page 89: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

Ti, T2, T3

TITLE

These required cards provide three lines of information at the top of eachpage of output.

Ti, T2, T3, CARDS - TITLES

FIELD VARIABLE VALUE DESCRIPTION

0 KODE Tl,T2, Card identification.T3

1-10 TITLE AN Title information (center of title in cardcolumn 41).

85

Page 90: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

J1JOB CONTROL

Values on this required card define the period of analysis, economicanalysis parameters, the dimensions of the disposal system, and the outputdesired.

Ji CARD - JOB CARD

FIELD VARIABLE VALUE DESCRIPTION

0 KODE Ji Card identification.

1 NPER + Number of uniform time periods for whichanalysis is to be performed. These time periodsmay be of any duration. Maximum allowable valueis 100.

2 IPER1 + Identifier of first time period of analysis (forexample, 1982). All benefits and costs arediscounted to the beginning of this time period.

3 DRATE + Effective discount rate per period, expressed asa percentage. This is used to determine thepresent value of all benefits and costs. Anonzero value must be used because siteacquisition costs and operation costs areamortized in the analysis. Default value is 1%

4 NDISP + Total number of existing and potential disposalsites. This includes disposal sites to whichmaterial is moved directly from a dredge siteand disposal sites to which material isrehandled from other disposal sites. See noteon next page.

5 NDREG + Total number of dredge sites. See note on nextpage.

6 NTRAN + Total number of possible dredged-materialtransportation methods. This includes dredgingplants (such as hopper dredges) and rehandlingtransportation types (such as dump trucks). Seenote on next page.

7 IPRNT 0 Transportation link input report, disposal siteinput report, and dredge site input report areprinted in addition to list of input.

1 Transportation link input report, disposal siteinput report, and dredge site input report areomitted.

86

Page 91: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

jl

Jl CARD (Continued)

FIELD VARIABLE VALUE DESCRIPTION

8 ITKAX + Maximum number of iterations allowed forcapacity-expansion problem solution. Ignored ifsystem capacity expansion is not to beconsidered. Default value is 25.

9 NPERAM + Number of periods required for amortization ofsite acquisition or lease costs. Must notexceed NPER.

10 NPREST + The restart capability of the program is to beused. A file is prepared for analysis of NPRESTperiods following the last period of analysisperformed in this execution of D2M2. This fileis a new input file for the same disposalsystem. The initial conditions specified inthis new file are final conditions determinedfrom the current analysis. The file isidentified as TAPEll. The program user mustissue appropriate job control comnands tore-execute D2M2 with this input file.

0 File for restart execution of program is notprepared.

NOTE: The available computer memory is allocated automatically by thisprogram based on the requirements for storage of disposal site, dredge site,and transportation data. Thus maximum values for NDISP, NDREG, and NTRAN arenot set explicitly. Instead the following restrictions apply for thedistributed Harris version of the program:

a. (NTRAN*34) + (NDISP*78) + (NDREG*I8) + (NDREG*NPER) + ((NPER+I)*12) +(NDREG*7*MXNIMKS) + (NPER+3)*l0O must not exceed 40000. MXILNKS is themaximum number of disposal sites to which any one of the dredge sitesmay transport material (maximum of all values of NTLINK (DL.3)).

b. (((NDISP*2) + NDREG)*NPER) + 2 must not exceed 5000.

c. ((NDISP*(2+N)) + NDREG)*NPER must not exceed 10000. N is the maximumnumber of transportation links that originate and terminate at anydisposal site, including links for reuse and for transfer.

87

Page 92: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

TI

TRANSPORTATION D&SCRIPTION

Data on the required TI, TD, and TC cards describe each possible method

for moving dredged material within the system, including shipment from sources

to disposal sites and shipment between disposal sites in the case of

rehandling. NTRAN (Jl.6) sets of TI, TD, and TC cards are required.

TI CARD - TRANSPORTATION IDENTIFICATION

The transportation type identification and description are provided on

this required card.

FIELD VARIABLE VALUE DESCRIPTION

0 KODE TI Card identification.

1 ITID AN Right-justified 6-character transportation type

identifier. This identifier is used later to

define system linkages.

2-7 ITNAME AN Transportation type description.

88

Page 93: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

TD

TD CARD - DISTANCES FOR TRANSPORTATION-COST FUNCTION

The unit cost of moving material within the disposal system is representedin D2M2 as a function of distance. The values on the required TD card are thedistances of the distance vs. unit cost function. The values must bespecified in increasing order or execution will terminate. A maximum of 10values may be provided. Linear interpolation without extrapolation is used,so the values should be selected accordingly. Any desired units of distancemay be used (miles, feet, kilometers, meters), however, the units of distancesspecified on the TD card and the units of all other distances specified mustbe consistent.

FIELD VARIABLE VALUE DESCRIPTION

0 KODE TD Card identification.

1 TDIST(l) + First distance value. This value must be lessthan the minimum required transportation linkagedistance.

2 TDIST(2) + Second distance value.

3-10 TDIST(3)- + Repeat as above for values 3-10 If less thanTDIST(10) 10 values are specified, the fields remaining

after the last value must be blank. The lastvalue specified is the maximum value and mustexceed the length of any transportation link inthe system.

89

Page 94: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

TC

TC CARD - COSTS FOR TRANSPORTATION-COST FUNCTION

The values specified with the required TC card are the unit costs (costper unit volume shipped) corresponding to the distances specified in thecorresponding fields of the TD card. Any desired units of cost and volume maybe used, but all costs and volumes must be specified with consistent units ofmeasurement.

FIELD VARIABLE VALUE DESCRIPTION

0 KODE TC Card identification.

1 TCOST(1) + First unit cost value. This value is the unitcost associated with TDIST(1) (TD.1).

2 TCOST(2) + Second unit cost value. This value isassociated with TDIST(2) (TD.2).

3-10 TCOST(3)- + Unit cost values corresponding to TDIST(3),TCOST(10) TDIST(4),....TDIST(10).

90

Page 95: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

SI

DISPOSAL-SITE DESCRIPTION CARDS

Data on these cards describe each material disposal site in turn. NDISP(J1.4) sets of SI, SL, SX, SS, SE, and SA cards are required. An SR card isrequired for each disposal site from which material can be rehandled, asidentified by a nonzero value for NREHND (SX.9).

SI CARD - DISPOSAL-SITE IDENTIFICATION

The dredged-material disposal site identification and description areprovided on this required card.

FIELD VARIABLE VALUE DESCRIPTION

0 RODE SI Card identification.

1 IDISP AN 6-character disposal-site identifier.

2-7 IDNAME AN Disposal-site description.

91

Page 96: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

SL

SL CARD - DISPOSAL-SITE LOCATION

The values on the required SL card specify the disposal-site location, thetransportation type used to move material from the river to the site, sitestorage data, and fixed operation, maintenance, and replacement (OMR) costs.

FIELD VARIABLE VALUE DESCRIPTION

0 KODE SL Card identification.

1 SRVDST + River distance to location associated withdisposal site (see Fig. 2). Any origin formeasurement may be used, but all river distancesmust be specified relative to the same origin.

2 SOFFMN + Distance from river to disposal site (see Fig.2).

3 IDTRAN AN Right-justified 6-character identification ofthe transportation facility used to movematerial from the river to the disposal site.This value must correspond exactly to one of thetransportation-type identifiers on TI cards. Ifthis field is blank, IDTRAN is assumed to be thesame as the transportation type used on theriver (specified on DT cards), and SOFFMN isadded to the river distance for unit costdetermination. Otherwise the unit cost is thesum of on-river and off-river unit costs.

4 STOR1 + Volume of material stored in disposal site atbeginning of IPERI (J1.2). Must not exceedcapacity of disposal site.

5 WDRAT + Average ratio of volume of "wet" materialdeposited in site to volume of material afterdrying. This drying is accomplished within onetime step.

6 ADDMAX + Maximum allowable addition of unconsolidatedmaterial to disposal site per period (volume perperiod).

The absolute value of ADDMAX is the maximumelevation increase due to addition ofunconsolidated material per time step. Linearinterpolation of the elevation-volumerelationship is used to convert this elevationchange to volume change for the network.

0 The maximum allowable volume addition per time

step equals site capacity.

92

Page 97: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

SL

SL CARD (continued)

FIELD VARIABLE VALUE DESCRIPTION

7 STRCST + Cost per unit volume of wet material added todisposal site. This cost includes operationcosts that are a function of the volumedeposited in the site, including mitigationcosts.

8 OMRCST + Fixed annual operation, maintenance, andreplacement cost for disposal site. This costis incurred at the end of each period a site isavailable, regardless of the volume of materialstored in the site.

9 ISTPRT 0 Disposal-site operation report includestabulation of material added to and materialremoved from site each period, disposal-sitestatus each period, and total volumes added andremoved during period of analysis.

Disposal-site operation report includestabulation of material added and removed anddisposal-site status for period that siteinitially fills, tabulation of final sitestatus, and tabulation of total volumes added

and removed.

+ Disposal-site operation report includestabulation of material added and removed anddisposal-site status for period that siteinitially fills and for period ISTPRT,tabulation of final site status, and tabulationof total volumes added and removed.

93

Page 98: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

Is

SI CARD - MIPANSION SPECIFICATION

The values on the required SX card include site-acquisition data, leasedata, reuse data, and rehandling data.

FIELD VARIABLE VALUE DESCRIPTION

0 KODE Sx Card identification.

I IEXP 0 This disposal site is added to system atbeginning of period IPERA (SX.3) and isavailable until lease expires at end of periodLLEASE (SX.4). The site is then deleted fromthe system

1 This disposal site is added to system atbeginning of period IPERA (SX.3). The lease isrenegotiated at end of period LLEASE (SX.4) at acost of RENCST (SX.5), and the site is availablethroughout the analysis.

2 This disposal site is added to system atbeginning of period IPERA (SX.2). Leaserenegotiation at end of period LLEASE at a costof RENCST is considered as a capacity expansionoption. This option cannot be exercised withthe program "restart" capability.

3 Acquisition of this site is a capacity expansionoption. The site may be acquired between IPERAand IPERG (SX.3), inclusive, at a cost of ACQCST(SX.l0) and will then be available for theremainder of this of analysis. This optioncannot be exercised with the program "restart"capability.

2 IPUSE ÷ Columns 9-10 contain a 2-digit number definingthe number of periods a site is available priorto "resting". The site is added to the systemin IPERA (SX.2) as specified by the user (or asselected by the capacity expansion algorithm).The site is then alternately included for IPUSEperiods and omitted for IPREST periods.

0 Site is not rested.

IPREST 4 Columns 11-12 contain a 2-digit number definingthe number of periods a site is rested in thealternating using-resting cycles.

O Site is not rested.

94

Page 99: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

2Z

SK CARD (Continued)

FIELD VARIABLE VALUE DESCRIPTION

IPERA + Columns 13-16 contain a 4-digit number. If ISWP= 0, 1, or 2, this is the period of siteacquisition. If IEXP = 3, site acquisition is acapacity expansion option, and acquisition willbe considered only during or after IPERA. Ifomitted, IPERA is set equal to IPERI (0.12).

3 IPERG Last period within which :apacity expansion byacquisition of this site will be considered.This value must not exceed IPERI . NPER - NPERAMto insure that the site acquisition cost tifully amortized within the period of analysis.Ignored if IEXP is not equal 3.

4 LLEASE Period of lease termination. If IEXP = 0, thedisposal site is deleted from the system at theend of this period. If IEXP = 1, the leaserenegotiation cost is incurred at the end ofthis period, and the site remains in the systemthroughout the analysis. If IEXP = 3, LLEASE isignored. Omit if site is available throughoutanalysis.

0 Lease does not terminate. Disposal site remainsin system throughout analysis (includingsubsequent "restart" analysis, if that option isused).

5 RENCST + Lease renegotiation cost. Required if IEXP = 1or 2. This cost is incurred at the beginning ofperiod LLEASE+l if the lease is renegotiated.

6 IPERR 4 First period reuse is possible. This appliesonly to sites with known acquisition period(IEXP = 0,1) and with positive value for REMAX(SX.7). If reuse from a potential site(identified by IEXP = 3) is possible, it isassumed to begin when site is acquired. In thatcase, this field is ignored.

7 REMAX + Maximum volume that may be removed per periodfor reuse. REMAX must not exceed site capacity.Omit if no reuse from this disposal site.

8 REBEN + Unit benefit of reuse of material from this site.

9 NREHND 0 Material from this site cannot be transferred toother sites within the system.

95

Page 100: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

3x

SI CARD (Continued)

FIELD VARIABLE VALUE DESCRIPTION

+ Number of sites to which material from this sitemay be transferred. Maximum value is 2. Datadescribing the transportation links to thesesites are provided on the SR card.

10 ACQCST Total site acquisition cost. This cost mayinclude cost of facilities, of real estate, andof mitigation of adverse environmental orcultural impacts.

96

Page 101: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

SR

SR CARD - TRANSFER DESCRIPTION

The data on this optional card describe the potential facilities fortransferring material from the disposal site identified on the SI card. TheSR card is required if NREHND (SX.9) is positive.

FIELD VARIABLE VALUE DESCRIPTION

0 KODE SR Card identification.

1 IRESIT(l) AN Right-justified 6-character identification ofthe first disposal site to which material may betranslerred. This site must be described alsoby data on SI, SL, SX, SR, SS, SE, and SA cards.

2 IREPER(l) + First period that transferring from siteIDISP(SI.I) to site IRESIT (SR.I) is possible.This applies only to sites with knownacquisition period. Otherwise transfer isassumed to begin when both sites IDISP andIRESIT have been acquired.

3 REDIST(l) + Distance to site IRESIT.

4 IRETYP(l) AN Right-justified 6-character identification ofthe transportation method for transferringmaterial. This value must correspond to one ofthe transportation types specified previously onTI cards.

5 REHMAX(l) + Maximum volume per period that may betransferred to site IRESIT. If no value isspecified, maximum site capacity is used.

6 IRESIT(2) AN Same as IRESIT(l), but for second transfer site,if one is available..

7 IREPER(2) + Same as IREPER(l), but for second transfer site,if one is available.

8 REDIST(2) + Same as REDIST(1), but for second transfer site,if one is available.

9 IRETYP(2) AN Same as IRETYP(l), but for second transfer site,if one is available.

10 REHMAX(2) + Same as REHMAX(1), but for second transfer site,if one is available.

97

Page 102: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

5S, s5

SS CARD - DISPOSAL-SITE CAPACITY

The data on the required SS, SE, and SA cards describe the capacity,surface elevation, surface area relationship of the disposal site. Anyconsistent system of measurement may be used. The values are specified suchthat CAPCTY(1) is the capacity corresponding to ELEV(1), which corresponds toAREA(l). The storage values specified must increase or execution willterminate. The same number of values must be specified on each of the cards.A maximum of 9 values may be provided. Linear interpolation withoutextrapolation is used, so the values specified should be selectedaccordingly. The last nonzero value of the SS card is assumed to be themaximum allowable volume of material deposited in the site.

FIELD VARIABLE VALUE DESCRIPTION

0 KODE SS Card identification.

1 Not used.

2 CAPCTY(1) + First storage value

3-10 CAPCTY(2)- + Storage values 2-9.CAPCTY(9)

SE CARD - DISPOSAL-SITE ELEVATION

The required SE card identifies the elevations corresponding to thecapacity values of the SS card.

FIELD VARIABLE VALUE DESCRIPTION

0 KODE SE Card identification.

1 Not used.

2 ELEV(1) + First elevation value. This is the elevationthat corresponds to CAPCTY(1).

3-10 ELEV(2)- + Elevation values 2-9, corresponding to storageELEV(9) values 2-9 on SS card.

98

Page 103: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

SA

SA CAR - DISPOSAL-SITUC ARIA

The surface area values of the capacity-elevation-area relationship arespecified on this required card.

FIELD VARIABLE VALUE DESCRIPTION

0 KODE SA Card identification.

1 Not used.

2 AREAI) + First surface area value. This is the surfacearea that corresponds to CAPCTY(1).

3-10 AREA(2)- + Area values 2-9, corresponding to storage valuesAREA(9) 2-9 on SS card.

99

Page 104: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

DI

DREDGE-SITZ DESCRIPTION CARDS

Data on these required cards describe each dredge site in turn. NDREG(Jl.5) sets of DI, DL, DT, and DV cards must be included. Within each set,one DT card is included for each possible linkage of the dredge site with anydisposal site.

DI CARD - DREDGE-SITE IDENTIFICATION

The dredge-site identification and description are specified on thisrequired card.

FIELD VARIABLE VALUE DESCRIPTION

0 KODE DI Card identification.

1 IDREG AN Right-justified 6-character dredge-siteidentifier.

2-7 IDRNAN AN Dredge site description.

100

Page 105: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

DL

DL CARD - DRIDGE-SITE LOCATION

The data on the required DL card specify the dredged-material sourcelocation, the number of links of the source with disposal sites, and themultiplier that may be used to scale all the specified material volumes forthis source.

FIELD VARIABLE VALUE DESCRIPTION

0 KODE DL Card identification.

1 DRVDST + River distance to dredged-material sourcelocation. The origin of measurement must beconstant and the same used for specification ofdisposal-site location.

2 DOFFMN + Distance from river to dredge site. If dredgesite is on a tributary, this is the distancefrom the point of intersection of the tributaryand the main channel.

3 NTLINK + Number of possible links of this dredgedmaterial source with existing or potentialdisposal sites. These links are defined by DTcards that follow.

4 VKULT + Material-volume multiplier. All materialvolumes specified on DV cards for this dredgesite are multiplied by VKULT prior to analysis.

0 VMJLT is assumed equal to 1.0.

101

Page 106: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

DT

DT CARD - DREDGE SITE TO DISPOSAL SITE TRANSPORTATION DESCRIPTION

One DT card is required to describe each possible link of this dredged-material source to existing or potential disposal sites. A total of NTLINK(DL.3) cards are required.

FIELD VARIABLE VALUE DESCRIPTION

0 KODE DT Card identification.

1 LDID AN Right-justified 6-character identifier of siteto which material may be transported fordisposal. This identifier must match exactlyone previously specified on SI cards.

2 LMTYP AN Right-justified 6-character identifier of methodused for transportation of material on river.This identifier must match exactly onepreviously specified on TI cards.

3 LOFTYP AN Right-justified 6-character identifier of methodused to transport dredged material from sourceto river. This identifier must match exactlyone previously specified on TI cards. Omit ifDOFFMN (DL.2) is zero. If this field is blank,LOFTYP is assumed to be the same as LXTYP(DT.2). In that case, DOFFMN (DL.2) is added tothe river distance for unit cost determination.

4 VLMAX + Maximum allowable volume per period that may betransported via this transportation link. If novalue is specified, the entire volume removedfrom this site each period is used as the limit.

102

Page 107: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

DV

DV CARD - DRZDGID-ATZRIAL VOUlMS

The volume to be transported from the dredge site each period, beforedrying, is specified with the required DV card. Ten values are specified percard. NPER (J1.1) values must be specified, unless a constant volume is to beused. In that case the value specified for the first period is used in allsubsequent periods. This is controlled by the presence of -1 in field 3. IfVMULT (DL.4) is nonzero, all volumes specified or implied are multiplied byVKULT.

FIELD VARIABLE VALUE DESCRIPTION

0 KODE DV Card identification.

1 Not used.

2 VOLNAT(l) e Volume of "wet" material to be transported fromthis dredge site, period IPERl.

3 VOLMAT(2) + Volume of "wet" material to be disposed, periodIPERl-1.

-1 The volume of material for period IPERl+÷ andfor all subsequent periods is VOLMAT(1)UVMULT.No additional values are required on this cardand additional DV cards for this site are notrequired.

4 VOLMAT(3) + Volume of "wet" material to be disposed, periodIPERl+2. Omit this value and subsequent valuesif VOLHAT(2) = -1.

5- VOLMAT(4)- + Volume of "wet" material to be disposed inNPER VOLMAT remaining periods. If NPER exceeds 9, use

(NPER) addition cards as needed, with 9 values percard, beginning with Field 2 of each card.

103

Page 108: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

FS

USER-SPECIFIID SOLUTION

Data on these optional cards force transportation of a specified volume ofdredged-material from a specified source to a specified disposal siteregardless of the cost. If multiple transportation linkages exist, thetransportation type must also be specified. The user muat realize that fixinga portion of the solution in this manner may yield a network-flow programmingproblem to which no solution exists, especially in the case of capacityexpansion sites. Furthermore, the user must define a feasible solution; thelinkage must exist, the volume to be transported must not exceed the capacityof the disposal site, and transporting and disposing the material must notcause overfilling of the disposal site in a single period.

FS CARD - FIXED SOLUTION SPECIFICATION

FIELD VARIABLE VALUE DESCRIPTION

0 KODE FS Card identification.

1 JDREG AN Right-justified 6-character identifier of thedredged-material source. This value mustcorrespond exactly to one of the sourcesidentified on DI cards.

2 JDISP AN Right-justified 6-character identifier of thedisposal site to which material is to betransported. This value must correspond exactlyto one of the disposal sites identified on SIcards.

3 JPR + Period in which specified value is to betransported. Both IDREG and IDISP must beavailable in period IPER or execution willterminate.

4 VOL + Volume to be transported. Must not exceedvolume specified on DV card for source IDREG,period IPER.

5 JTRTYP AN Right-justified 6-character identifier of thetransportation method used, if more than onetype of linkage exists. This value mustcorrespond exactly to one of the transportationtypes identified on DT cards.

104

Page 109: Dredged-Material Disposal · SUMARY The Dredged-Material Disposal Management Model, D2M2, is a simulation-optimization model designed to provide information required to answer the

SA ADREA .. CRRSPONINGR VOL CAPTY

DV CACT ... MAXIU ... 0PE VALUES

SR REIT IRPE RE IS IRTRE A IRE IREE REIS IREY REMAI

DT IEXD IER LLEASE REIS IPERRP REAXREENNEINDC

DL SRDSTOFMVDYRAFFN STOLIN WDRATADMXTCTMCTTR

Si PR IREI RPERi DRAEDISP NDREGY NREHA IPRNST ITMAENERA NPIS RESTY EM

FIG 7. I Sumr of Prga D2M Inu

SX IEP PUE PEG LESERECS IER RMA RBE NEH105OST