Donner Case Study - MBA 621.pdf

download Donner Case Study - MBA 621.pdf

of 35

Transcript of Donner Case Study - MBA 621.pdf

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    1/35

    Medaille College

    MBA-621

    Operations Management

    Case Study #2

    Donner Company

    3/8/2006

    mr bbas

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    2/35

    Problem Definition

    The three-year old Donner Company has positioned itself well within both the

    small volume, customized (contract) printed circuit boards market as well as the

    large volume, generic (captive) printed circuit boards market. Large electronic

    firms (AT&T, IBM) produced their components in captive shops, while smaller

    sized companies, or when large and small quantities of simple technology or fast

    turn-around prototype boards were required, these requests usually are fulfilled

    by contract shops.

    With 750 competitors in the US alone, and a market that is volatile, Donners

    ability to anticipate and resolve design problems and prototype techniques

    enabled it to maintain its competitive edge. However, this competitive edge has

    been compromised by poor on-time delivery and high rate of product return, in

    addition to planning and manufacturing problems that caused bottlenecks,

    shifting bottlenecks and improper utilization of labor. These problems began to

    hamper the overall performance of the firm, and management started evaluating

    the companys position and different strategic policies.

    Following is detailed analysis and recommendations by evaluating the current

    conditions of the company, particularly the following areas:

    Operational and strategic implications of company direction

    Labor utilization

    Materials

    Capacity Information flow

    Evaluating the following performance criteria: Quality, Productivity and

    Delivery.

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    3/35

    Following detailed analysis of data, process flow and inventory strategies, my

    recommendations will be focused on the following opportunities:

    1. Changing strategy from current position to one which concentrates on

    producing only small quantities of fast turn-around SMOBCs.

    2. Changing strategy from current position to one which concentrates on

    producing only large quantities of simple technology boards.

    3. Changing strategy from current position to one which concentrates on

    producing large & small quantities of simple technology boards, through the

    use of two separate production lines.

    Company Objectives and Overview of Problems:

    With a company that is managed primarily by engineers, Donners core

    competency was, obviously, its engineering expertise, and it producedspecialized circuit boards known as soldermask over bare copper (SMOBC)

    boards. Donner positioned itself to manufacture these boards to small and large

    electronic firms and management envisioned it as one of the industry leaders.

    However, in order to achieve this objective, perhaps Donner needed a

    management that is more business oriented rather than being managed by

    engineers who dont necessarily possess the business sense to run a firm.

    Donner employed 22 production employees, managed by 4 senior executives.

    Please refer to exhibit 1 for Donners organizational chart. Operators were cross-

    trained and able to perform different functions in different departments. This is

    considered to be a major advantage for a company to have; the ability to deploy

    employees to perform different functions in different areas (as needed).

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    4/35

    However, it seemed that there was a lack of effective communication strategy

    within the organization, as information did not flow properly within the

    different departments and workers often interrupted their work to discuss issues

    with the supervisor, deliver completed panels or secure more work from other

    work stations (low hanging fruits).

    David Flaherty, shop supervisor, is responsible for all aspects of the

    manufacturing processes from the time he received the order and blueprint until

    the order has been completed and shipped. Flaherty is in charge of preparing

    work schedules, which occurred several days after the raw material has arrived

    from the vendor (most orders reached him 4 days after customers bids had been

    accepted, which included the time needed by purchasing to locate the raw

    material at a low price 1 2 days on average). Flaherty spent much of his time

    planning and determining how to move jobs ahead of others and how to shift

    workers from one operation to another (to meet unexpected customers changes

    to specifications and to meet the deadlines for rush orders). Please refer to the

    information flow chart (exhibit 2) and the order process flow chart (exhibit 3).

    Donner promised its customers 3 weeks delivery on orders of 1000 boards orless, and 5 weeks on orders larger than 1000 boards. Rush orders (orders of 8

    boards or less) were delivered after 4 days.

    Donner operated at a plant that was carefully chosen by management to

    minimize installation costs, preserved the life of expensive machinery and

    isolated the operations diverse environment. After being in the same location

    for a year and a half, neither the machines nor the graphic equipment exhibited

    any signs of corrosion. In fact, by October 1986, Donner began to expand their

    current location, which was fully utilized, by installing an 1800 sq ft addition.

    This addition was due to be completed by November, 1987.

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    5/35

    Donners management had to implement policies that, in addition to

    manufacturing, had to be cost effective, as Donner was not able to attract outside

    capital (cited earlier: managed primarily by engineers, not necessarily business

    oriented).

    Analyzing Donners current situations, it is evident that the company is suffering

    from several problems relating to its manufacturing, labor, quality and delivery.

    Following is a highlight and a brief analysis of each of Donners problems:

    1.

    Operating problems:

    Management could not manage the production bottlenecks effectively. Each

    order was different, as per each customers specifications. Since there is no set

    quality policy in place, some raw material may be defective. When operators are

    working on a specific project, they may require additional raw material (which

    takes about 1 2 days to locate, then additional days to be delivered to Donner).

    This causes interruptions to the production cycle at one operation, which in turn

    causes a production bottleneck at the next operation.

    Often times, some customers make modifications to the original specs and ask

    for changes in production. This means that the operators have to stop working

    on a certain project and await new instructions from management once they

    receive the new specs from the customers. Once again, this causes a production

    bottleneck and, more seriously, starts to shift the bottleneck to another operation

    process.

    Furthermore, rush orders represented a problem to Donner. The companypromised 4 days delivery to customers. Looking at the bigger picture in this

    situation, we have a company that is being pressured by sudden interruptions (of

    production), not meeting its on-time delivery, suffers from bottlenecks at almost

    every stage of production yet continues to promise 4 days delivery on rush

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    6/35

    orders. This means that, no matter what, rush orders are a priority (Donner

    faced pressure from its competitors concerning the fulfillment of rush orders). If

    raw material is needed for rush orders, it is obtained from the existing inventory,

    which is originally bought to fulfill large orders. This causes possible shortages

    in inventory, which means that Donners purchasing has to locate and purchase

    additional material (a process that takes 2 days). The result is possibly stopping

    an operation process until new raw material is obtained, which also means down

    time for the operators (down time at one process, hence a bottleneck at a specific

    process). However, Donner experienced no problems with rush orders (these

    orders were completed by one senior employee) and had no reject rate. In fact,

    that was one area that did not suffer from any hemorrhage.

    2.

    Productivity problems:

    As a result of the operating problems, it is normal to predict, and expect,

    productivity problems. With frequent down times and order changes,

    management cited the fact that machines are idle for longer than expected. In

    addition, standard labor time for each process (as depicted in exhibit 4-A) did

    not reflect accurate time at Donner itself, rather it was based upon industrystandards and competitors. In addition, Donners operation is sequential in

    nature, however management is faced with a decision whether to use manual

    labor (for drilling and punch press) or to use the CNC machine for the same

    purpose. It is evident that management did not prepare a breakeven analysis to

    be able to objectively determine which method to use with which kind of order.

    Furthermore, the sequential process flow currently utilized at Donner can cause

    a significant idle time for workers. As my analysis will show, a parallel flow ofoperations, at certain points, may alleviate this problem and save time on

    production cycle time.

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    7/35

    3.

    Quality problems:

    Donner did not implement effective quality control measures to inspect the raw

    material or work in progress. Donner depended on the individual operators

    experience to perform informal examination as the operation shifted from one

    process to the next. The result was the increase rate of product return. The

    companys reject rate in September alone amounted to 7%, of which 1% was a

    total loss and 6% required re-works because the end products did not meet the

    customers specifications. Clearly, re-works resulted in pulling operators from

    their current jobs to begin re-works on the returned boards, which in turn caused

    lack of productivity and bottlenecks.

    4.

    Delivery problems:

    Similar to the current sequential manufacturing policy at Donner, it is no

    surprise to note the delivery problems. Because all these processes are

    interconnected, and especially because of the high rate of returns and re-works,

    Donner failed to meet is delivery dates (8 days late in September). Because re-

    works required pulling operators away from their current functions, deadlines

    were not met (due to delays in manufacturing and finishing work in progress);

    Donner continued to suffer from the inability to meet its delivery dates.

    However, rush orders were not affected and the company continued to promise

    4 days delivery for such orders (this also caused bottlenecks and shifting

    bottlenecks as rush orders were treated with special status, raw materials and

    workers were simmered to satisfy these orders).

    Finally, the new sales manager for Donner, Lloyd Searby, noted his concerns that

    Donners sales may not exceed $2M in sales (in 1988) if it continued to bleed

    from its quality (returns and re-works) and delivery problems. However, both

    Lloyd and the president believed that Donner should continue bidding for low

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    8/35

    volume orders and improve their quality standards, and believed this should

    stop the bleed and possibly push Donner towards $3M in sales.

    All these troubles resulted in financial problems that manifested itself in reduced

    sales in September and threatened Donners existence in the marketplace.

    Data Analysis:

    Donner provided several exhibits to demonstrate the following areas of its

    operation:

    Profit and Loss

    Standard Process Flow

    Inventory

    Following is an analysis of each area:

    Profit and Loss (exhibit 5):

    From the P&L report we can identify few key points:

    Donner is, despite the manufacturing problems, profitable. In fact, from January

    1987 to September 1987, Donners profit before tax exceeded the preceding two

    years. However, if we analyzed each month in 1987, it is obvious there is a

    negative trend from January till July, and another negative trend from August till

    September:

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    9/35

    !"#""

    !$#""

    !%#""

    !""

    !'#""

    !("#""

    !($#""

    !(%#""

    !(""

    !"#$% '(!)*

    )*+ - )./ (0'1 )./-'1 2.3-'1 456-'1

    +,-./%

    +,-./#0 !"#$% 12$-3 4 5678

    It is clear that there was a sharp drop in profits from August till September (total

    of $11.7 million loss /drop in net profit). From the information provided by

    Donner, most of the manufacturing and delivery problems occurred in

    September, 1987.

    Further analysis of the Profit and Loss sheet indicates that there was 21 working

    days in September, 1987. Donner employed 22 employees who worked 8 hrs /

    day shift. This amounted to a total of 3696 hours worked in that month. Direct

    labor amounted to $8.73 per employee ($32,300/3696 hrs). Total fixed cost was

    $34,100 and variable cost was $87,600. Added in exhibit 5is a column to depict

    the different costs per unit (based upon 5761 units manufactured in September).

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    10/35

    Standard Process Flow (exhibits 4-A and 4-B):

    Perhaps the most important exhibit provided by Donner to enable us to

    identify problems and suggest solutions. From the information provided in

    exhibit 4-A, the following can be identified and calculated:

    Breakeven point to decide when to use the automated CNC drill vs.

    manual drill (based upon number of orders)

    Breakeven point to decide when to use the automated CNC router vs.

    manual punch press (based upon number of orders)

    Identify bottlenecks within all areas of manufacturing with special focus

    on the Dry Film Photoresist process (to perform capacity analysis of the

    DFPR area by assuming order size of 8, 80 and 800 boards)

    Standard labor time for an order size of 1, 8 and 200 boards

    Following is an analysis of each area:

    Since Donner purchased a CNC machine at $80,000 to perform the drilling and

    router functions, and also since these processes can be performed manually, it is

    important to decide which orders can be scheduled on the CNC machine and

    manually. This is achieved by performing a breakeven analysis of each function.

    It is important to note that the set up time for each process is fixed no matter the

    order size. The run time is variable and changes per order size.

    Calculations of the breakeven points (please refer to exhibit 6 for complete

    calculation of breakeven points), for CNC or manual drill and for CNC or

    manual profile processes show the following results:

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    11/35

    Drill process:

    For orders of 6units or less, manual drill should be utilized as it will incur fewer

    costs (and less overall time to process) and for orders over 6 units the CNC drill

    should be utilized because the cost will be less than if manual is used, as well as

    time to process.

    Profile process:

    For orders below 200boards, manual punch press should be utilized as it will

    take less time and incur fewer costs, and for orders above 200 boards the CNC

    router should be utilized for the same reasons.

    Exhibit 4-A can also be used to identify bottlenecks within Donners standard

    process, particularly surrounding the capacity of the dry Film Photoresist area. It

    is critical to realize the true capacity to prevent bottlenecks and work-overload.

    If, for example, the maximum number of boards that the DFPR area can handle

    (due to the set up and run time involved in the process) is 100, then Donner

    should realize that order size that passes through the drilling process should not

    exceed 100 units (to match the DFPR capacity). If the order sized is more than

    100 (hence, more than the maximum capacity that the DFPR area can handle), a

    bottleneck is created and possibly shifted throughout the entire manufacturing

    process. In addition, since the DFPR area consists of several functions, it is

    important to be aware of the maximum capacity (as per order size) to prevent

    bottlenecks within the DFPR area. Exceeding maximum capacity will have a

    direct negative impact on quality and on-time delivery (two problems that

    Donner was already suffering from in September). Of course, the bottleneck will

    change from one area of the DFPR to the other, depending on the order size and

    the time involved in each process.

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    12/35

    Following is a table illustrating the results of an analysis of the DFPR area to

    determine the maximum daily capacity for order sizes of 8, 80 and 800 units

    (assuming normal 8 hours working days 480 minutes):

    Order size

    DFPR area

    8 80 800

    Panel Prep 738.4 5485.6 15360

    Laminate &

    Expose

    174.4 960 1744

    Develop 190.08 1744.8 9600

    Please refer to exhibit 7 for complete calculation methods used to determine

    DFPR daily capacities.

    To translate these numbers into facts, it is clear that in order to avoid bottlenecks

    for an order size of 8 boards, the number of boards that can be processed per day

    can not exceed 174.4 boards (by taking the least number of boards for each of the

    three stages of DFPR, as it reflects the maximum daily capacity of orders

    processed). If total boards did not exceed 174.4, this is, at least, a guarantee that

    Donner should not experience bottlenecks at the DFPR area, as well as at other

    areas of manufacturing, for an order size of 8 boards.

    The same is applied to the daily capacity for an order size of 80 boards. The

    maximum daily capacity for the DFPR area is 960 boards, based upon an order

    size of 80. Any increase in order size will result in a bottleneck. For an order of

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    13/35

    800 units, the maximum daily capacity for the DFPR area is 1744 boards without

    bottlenecks.

    It is clear then that based upon the order size, the daily capacity for the DFPR

    area changes. The larger the order size, the more capacity the area can handle,

    however that capacity should not exceed the highlighted figures. Bottlenecks

    can cause work to pile at another stage of the process, which will impact the

    entire manufacturing process as a whole, which is a major factor in creating on-

    time delivery and quality problems.

    In addition, the larger the order size, the less expensive unit price is. This is a

    simple application of economies of scale, which should enable Donner to

    continue to compete in this volatile market and maintain its competitive edge for

    the long term.

    Donner suffered from a productivity problem, as noted by the President of the

    firm, as well as the new sales manager. Both indicated that the labor time in the

    standard process flow chart (exhibit 4-A) did not reflect the true labor time at

    Donner.

    In September 1987, there was a total of 3696 hours worked (exhibit 5), however

    the standard process flow for September (exhibit 4-A) showed a total actual

    hours worked of 1531 hours. This means that there was a total of 2165 hours that

    were considered either as down time or idle (non-revenue producing), hence:

    unproductive (59% of idle time), yet paid for by Donner. This also means thefollowing:

    2165 hrs / 21 days in September = 103 total hours wasted every working day

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    14/35

    103 hours / 22 employee = 5 hours that are wasted by each employee every day,

    which is !of the working day. This simply means that each employee worked

    an actual 3 hours on a normal 8 hours working day. Not only does this affect

    productivity, but Donner paid $8.73 per employee for 8 hours a day (each

    employee cost Donner $69.84 / day), yet they only worked for 3 hours (revenue

    generating production). This amounts to a loss of $43.65 per day, per employee

    ($69.84 - $26.19). Calculate this loss by 22 employees, and it is clear that Donner

    wasted money on wages for hours either not worked or worked without

    generating revenue, that amounted to $960.3 every working day, and $20,166.3 a

    month!

    Furthermore, the standard labor time increases with the order size. Please refer

    to exhibits 8, 9 and 10 (standard process flow area)for complete calculations of

    labor time for 1, 8 and 200 orders respectively:

    Order size

    Labor time

    1 board

    (exhibit 7)

    8 boards

    (exhibit 8)

    200 boards

    (exhibit 9)

    Manual 6.39 hrs 11.57 hrs 153.59 hrs

    CNC 11.16 hrs 11.85 hrs 30.67

    It is clear that the labor time increases with the order size. As previously noted,

    the breakeven point for the drilling process is 6 boards, and the breakeven point

    for the profile process is 200 boards. Reviewing the table above, for an order size

    of 1 board, it is more cost effective for Donner to utilize an entirely manual

    procedure, as it takes about 6.40 hrs to finish an order and have it ready to be

    shipped. As the order size increases (for example, 200 boards), it is clear that it is

    past the breakeven point and therefore takes less time to be processed utilizing

    CNC drill and router rather than manual processing.

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    15/35

    In addition, Donner is now faced with several options to better utilize its labor.

    For example: for order size of 8 boards, Donner may choose to utilize manual

    drill combined with CNC router, or CNC drill with manual punch press. To

    illustrate, please refer to exhibits 8, 9 and 10- proposed strategies areas:

    It is clear from the calculations that if the order size is 1 board, it is still cost and

    time effective to utilize an entirely manual process (standard labor time for an

    entire manual processing is 6.39 hrs), however once the order size increases to 8

    boards (exhibit 9 proposed strategy), it is less time consuming for Donner to

    utilize CNC drill + manual punch press, rather than an entirely manual or

    automated process (labor time for the proposed strategy CNC drill + punch

    press - is reduced to 10.25 hrs).

    For order size of exactly 200 boards, Donner should utilize CNC drill and may

    choose between punch press or CNC router (as 200 boards is the breakeven point

    at which CNC drill must be utilized for time and cost effectiveness, and both

    punch press and CNC router take the same amount of time 250 minutes).

    Labor time is reduced to 30.67 hrs with the proposed strategy (exhibit 10

    proposed strategy). For orders above 200 units, it is more efficient for Donner toimplement a process than utilizes both CNC drill and router to ensure less labor

    time, less manufacturing lead time and better utilization of their resources. The

    following table illustrates the proposed strategy and labor times savings for

    orders of 8 and 200 boards:

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    16/35

    Strategy

    Order size

    CNC drill +

    Punch Press

    Manual drill +

    CNC RouterEntirelymanual

    Entirely CNC

    8 boards

    (exhibit 9

    standard &

    proposed)

    10.25 hrs 13.17 hrs 11.57 hrs 11.85 hrs

    200 boards

    (exhibit 10

    standard &proposed)

    30.67 hrs 153.59 hrs 153.59 hrs 30.67 hrs

    If the order size is above 200 (for example, 250 boards), then the labor time is

    35.57 hours when CNC is used for drilling and profiling (entirely automated

    process), which is less than the time taken when manual processes are utilized.

    The breakeven points play a big role in these situations. This poses a suggestion

    that if Donner decided to focus on large volume orders (over 200 boards); it may

    be beneficial to buy a second CNC machine, particularly if they followed a

    parallel manufacturing process (detail explanation of this process will follow in

    the recommendation section).

    As mentioned earlier, when Donner received an order and the bid had been

    accepted by the customer, it took about 2 days for purchasing to locate the rawmaterial at a low price. It also took about 4 days from that moment until

    Flaherty (shop Supervisor) received the order and prepared the blueprints,

    scheduled work orders and allocated proper resources. Exhibit 11demonstrates

    the actual order sizes for the month of September, 1987. Further analysis of the

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    17/35

    inventory strategy followed by Donner is depicted in exhibit 12, which is the

    stock of each raw material ordered by Donner throughout September. It is

    suggested that Donner should carry some inventory to minimize the lead time

    from the moment the bid is accepted until it reaches Flaherty. To determine

    which raw material Donner should carry depends on the strategy followed. If

    Donner followed a strategy that focuses on small orders only, it makes sense to

    carry over a percentage of the commonly used raw material for such orders

    (suggested 20%, which follows the 80/20 rule). To illustrate: in September,

    Donner received a total of 60 orders from customers, where 80% of these orders

    were below 100 boards. Only 20% of these orders were for orders above 100

    boards. If Donner decided to focus on small orders (i.e. orders of less than 100

    boards), then it would make sense to carry about 20% the following raw

    materials: stock codes A, B, C, D, E, F and possibly K as well. If Donner decided

    to focus on orders of 100 boards and above, then the following stock codes

    should be carried by the firm: A, D and possibly M. As mentioned earlier,

    stocking some of these raw materials should minimize manufacturing lead time

    as the firm will not be at the mercy of locating the entire amount once an order is

    received. In addition, Flaherty will not have to wait for 4 days to begin planning

    for each project.

    It is worth mentioning that despite the fact that 80% of orders received from

    customers in September were for small volume boards, 90% of the total number

    of circuit boards manufactured was for orders of 100 boards or more. This

    means that large volume orders represented the largest portion of total number

    of boards made by Donner for September. This may play a role when Donner

    decides whether to focus on large or small volume orders, and whether it can

    afford to lose the customer base for each type of orders if they decided to drop

    one.

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    18/35

    It is clear however that Donner needs to carry some inventory (regardless of their

    strategy). Assuming a monthly cost of 2% (cost of carrying inventory), and

    assuming that Donner carried over some inventory from August (to show total

    impact on total cost and cost per unit), we note the following:

    Re-reviewing exhibit 5(P&L summary), the cost of materials in September was

    $42,600. If Donner carried inventory from August, then we add an additional 2%

    to Septembers materials cost: $42,600 x 2% = $852, which means that the new

    cost of materials for September will be equal to $43,452. The new calculations

    are depicted on exhibit 13. It is apparent that by adding the additional cost of

    carrying inventory, total cost of materials becomes higher, which also means that

    the cost of materials per unit is increased from $7.39 to $7.54. This also has a

    direct effect on total variable cost (increased from $87.60 to $88.45), as well as

    total net profit before tax, which is reduced from $3.1M to $2.25M. Certainly,

    adding another cost, as the cost of carrying inventory, will have an effect on the

    bottom line; however it may be a strategy Donner prefers to implement to reduce

    lead times and enable the manufacturing process to begin sooner, given that

    there are no bottlenecks or any other problems within the manufacturing

    process. You have to spend money to make money, especially if you are planning for

    long term existence. The appropriate volume of inventory Donner needs to carry

    can be determined by utilizing the 80/20 rule, which means that (by looking into

    Septembers orders) Donner may choose to carry 20% inventory of the most

    commonly ordered raw materials (80% of total volume of each core raw

    material).

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    19/35

    Recommendations

    Based upon my analysis of Donners current situation and problems, the

    following are recommendations that I deem as appropriate for the companys

    survival:

    Recommendation #1:

    Change strategy from current position to one which concentrates on

    producing only small quantities of fast turn-around SMOBCs.

    Currently, Donner is fulfilling low-volume (100 or less), high-volume (more than

    100) and expedited (8 or less) SMOBC orders. Although diversification of a

    product line is sometimes a desirable business strategy to pursue, there are

    several compelling reasons for Donner to concentrate on fulfilling one type of

    order, namely those that are low-volume and fast turn-around:

    First, excelling at its core competency as a manufacturer of SMOBCs is the

    primary reason Donner has managed to not only survive, but to flourish in this

    highly competitive and volatile industry (consisting of approximately 750 firms

    in the U.S. alone). Donner has successfully maintained its competitive edge by

    asserting itself as a leader and enhancing various manufacturing processes and

    equipment.

    Second, by continuing to serve the specific market segment of small quantities of

    fast turn-around SMOBCs, the firm will not be required to seek out new

    customers or to develop a new core competency (either activity is burdened with

    uncertainty, time-consuming and additional costs). In short, the firm could

    continue to supply large and prestigious firms such as IBM, AT&T or Digital

    Equipment in addition to the smaller electronics firms; thus allowing Donner to

    target all manufacturers in the electronics industry (for low-order volumes).

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    20/35

    Third, senior management has cited the firms ability to anticipate and resolve

    problems encountered during the design and production of small volumes of

    SMOBCs as one of its strengths and distinguishing features when compared to

    the competition. Coupled with managements desire to continue fulfilling low-

    volume orders (where they experienced no problems with rejects or on-time

    delivery), the firm should pursue a policy of serving this market segment with

    vigour since it possesses both the experience and confidence to assure a high

    degree of success.

    Finally, although only a three-year old firm, its profits have grown consistently

    year-on-year, as shown in following graph:

    !"#$

    %&'("))

    !"#'

    &*(!))

    !"#+

    &,,($))

    %!))))

    %$)))

    )

    $)))

    !))))

    !$)))

    *))))

    *$)))

    ,))))

    ,$)))

    !"#$% '( )!*

    +$",

    *-(($, .-/0"(1 2$3 4,-5'3 6$5-,$ 7"8

    -./0

    1/2.3

    -./0 !"#$ !"#' !"#+

    1/2.3 %&'(")) &*(!)) &,,($))

    ! * ,

    It is interesting to note that they have already exceeded last years earnings in

    the first nine months of this year (1987). Such financial facts are further evidence

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    21/35

    that the firm is clearly well positioned in the industry of producing small

    quantities of fast turn-around SMOBCs, while avoiding the possible problems

    that are associated with large-volume orders (i.e. bottlenecks, sudden changes to

    the designs by customers, which may result in long idle time).

    Operational and Strategic Implications

    If the firm decides to pursue a policy of producing only small volumes of quick

    turn-around boards, it will enjoy productivity gains, better labor utilization and

    improved quality assurance, which will make Donner a more competitive and

    efficient firm. Below are listed the impacts, positive and negative, which will beexperienced in specific areas of the firms operations in the pursuit of this

    strategy:

    Materials

    Currently, raw materials are being simmered by those who are fulfilling

    expedited orders, namely by Arthur Dief. Such a practice may consistently lead

    to an order remaining as a Work in Progress (WIP) order, in the firmsmanufacturing stream for longer than necessary. WIP are further delayed as it

    awaits another shipment of raw materials that were originally acquired for its

    use but now consumed by the rush orders. Fulfilling only small-volume, quick

    turn-around orders would require the firm to either hold larger inventories of

    raw materials or to acquire materials in a more timely fashion, but would

    decrease the probability of this inefficient process from continuing to hamper the

    entire manufacturing process.

    Labor utilization:

    The simmering of materials also has the added disadvantage of increasing the

    amount of labor required to produce a board. When a WIP is interrupted by an

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    22/35

    expedited order, it may incur additional set-up costs. In addition, workers then

    remain idle until the machine he/she was using is made available again (after the

    rush order has been completed). Therefore, small quantity orders should

    alleviate such a problem since all orders being filled by the firm will be of similar

    size and have similar delivery dates, thus eliminating the special status given

    to rush orders and reducing the idle time, which amplifies workers productivity.

    Capacity:

    The ability of the firm to increase its production capacity is being hampered by

    the shifting bottleneck, which appears throughout various stages of the

    manufacturing process without any particular pattern. This phenomenon mainly

    occurs due to the variation in the order sizes and the unremitting interruption of

    current work flow (work in progress) in favor of rush orders. Thus, by adapting

    a small order volume only policy, which will eliminate both the great difference

    in order size and the concept of the rush order, the firms manufacturing

    throughput will improve significantly.

    Information Flow:

    As shown in exhibit 2, David Flaherty, the shop supervisor, has the greatest

    number of informational in and out flows. A high proportion of information,

    both inter-departmental and inter-firm, has to pass through Flaherty. Allowing

    him to operate effectively and efficiently will have tremendous impact on

    Donners overall performance. Flaherty had indicated that due to the sizeable

    variations in order types, work in progress remain in the manufacturing stream

    for longer than necessary. By making the order-types as uniform as possible,

    Flaherty should find it easier to plan resources and share information.

    Furthermore, carrying inventory of necessary raw materials should alleviate the

    need for long lead time to plan for work.

    Effect of suggested strategy on performance criteria:

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    23/35

    Donners management is concerned with the firms performance in the following

    areas:

    Quality

    Productivity

    Financial

    Deliveries

    Since all these items are inter-linked, an improvement in one area will lead to an

    improvement in all. Should the firm decide to produce only small quantities of

    fast turn-around SMOBCs, it will be able to fix the flaws in all of these areas.Since new employees typically take only approximately 3 "months to become

    proficient in their assigned areas and if the order size is small, managing the

    orders would be easier. Staff could work either individually or in teams to

    ensure their orders are of high quality and free of errors, from the moment the

    order is received till the moment it is shipped to the customer. The productivity

    and morale of workers should also benefit from this as the floor staff are given

    more responsibility for assuring their orders efficiently move along themanufacturing process.

    On-time delivery will improve as a result and will be more uniform throughout

    the month, rather than the current unorganized shipping strategy (as illustrated

    in the chart below):

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    24/35

    Also favourably affected will be the financial health of the firm since it will be

    able to bill its customers sooner and will carry smaller inventory of work in

    progress.

    Recommendation #2:

    Change strategy from current position to one which concentrates on

    producing only large quantities of simple technology boards.

    Currently, Donner holds a position in both the contract and captive

    manufacturing markets. While initially focusing on small quantity specialized

    circuit boards for experimental devices and for pilot production runs (proto-

    types), the experience Donner has gained over the last three years would

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    25/35

    facilitate the firm to concentrate on the large quantities of Simple Technology

    boards. This will enable Donner to utilize their current core competency and

    resources, and focus on gaining new strengths, yielding improved quality and on

    time delivery.

    Focusing on the captive market will mean that Donner will be in a position to

    further support its larger customers (i.e. IBM, AT&T, etc) with orders larger than

    200 boards (90% of total orders received in September)

    Operational & Strategic Implications

    Labor Utilization:

    Donners current labor use will require changes. As the chart below shows,

    significant time is saved per board when using the CNC Drill and Router (for

    orders over 200 boards); hence no requirements for manual drill or punch press.

    Employment could be reduced or workers could be re-deployed to work in other

    areas in the firm (Donners management cited the fact that workers are well

    cross-trained and able to perform different functions throughout the

    manufacturing process).

    Septembers Production Data September Total Std Production

    Operation Setup(min) Run

    (min)

    Orders Boards Setup

    (min)

    Runs

    (min)

    Total

    Hours

    Manual

    Drill

    15 0.080 51 936 765 37,440 636.8

    CNC Drill 240 0.004 9 4,825 2,160 9,650 196.8

    The increase in batch size will reduce the time per average board for

    manufacture and subsequently reduce labor time. In addition, previous

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    26/35

    calculations of breakeven points depicted the very fact: the larger the order size,

    the less time the process flow looked using the CNC machine, as opposed to

    manual processes. Perhaps Donner should purchase a second CNC machine to

    accommodate this new strategy (advantageous for large-volume orders).

    Capacity:

    As previously mentioned, capacity is dependent on the order size, product mix

    and technology choices. By choosing to manufacture just the large quantity

    simple technology boards, product mix is no longer an issue, the technology is

    set and order size will always be high, hence producing at a lower average time

    per board (and low cost by utilizing economies of scale). The bottlenecks

    inherent in the current process would be easier to identify and solve, without

    further reoccurrences.

    Materials:

    The need to source raw material on a regular urgent basis should decrease in

    number substantially. In effect, there should be more control over the raw

    material stock levels as more time is available to source and locate raw material (

    as delivery time for large orders is typically less restrictive). Furthermore, raw

    material required for large orders should be freed from the continuous

    simmering by rush orders. This being said, a new strategic policy should be

    applied with relation to the stocking levels of raw materials to satisfy large

    orders (i.e. carry certain percentage of inventory as previously explained).

    Information Flow:

    Analyzing all processes within the company, by far the most fractured and

    complex (and confusing) is the information flow (exhibit 2). The majority of the

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    27/35

    returned boards were a result of the firm missing or failing to complete one or

    two required design specification. Currently, until an order is shipped, Flaherty

    keeps the factory order and blueprint at all times throughout the process. This

    indicates that possibly, vital information is not being disseminated throughout

    the production line. September 1987s pre-shipment rejection rate amounted to

    7%, causing a large amount of rework. This information flow policy must

    change from being centered on Flaherty. Flahertys role should be redefined and

    restructured to improve the flow of information and communication. In

    addition, the current process of expediting rush orders through the

    manufacturing process is adversely affecting the rest of the production process

    and increasing the information over load. Focusing on only large volume boards

    should allow for enhancements within information flow.

    Effect of suggested strategy on performance criteria:

    A new Quality strategy should be adopted. Arthur Dief (senior worker) could be

    used in this role due to his knowledge of the entire manufacturing process and

    the fact that he had a zero return rate. There are various quality control

    strategies that could be implemented throughout the entire manufacturing

    process to detect (early) and prevent product defects, and to monitor the entire

    manufacturing process (i.e. six sigma, SPC or TQM). Workers should be trained

    to utilize such methods and to utilize new technologies. Productivity should be

    increased due to the decrease in bottlenecks throughout the manufacturing

    process. Regarding the financial performance of Donner, if the sales manager

    (Searby) can generate the desired sales and focus on the large quantity simple

    technology boards, there should be a marked improvement in Donners financial

    health. The on-time delivery should be enhanced significantly due to the

    companys new strategic policy of concentrating on the large quantity boards, as

    well as the reduction in product returns and re-works.

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    28/35

    In summary, by adopting this strategy and focusing on this segment of the

    market, Donner should be able to compete with those current producers in the

    Captive Market. It is critical that consistent sales numbers can be achieved. If

    Donner lost one or two large customers in this specialized and highly

    competitive market, revenue will seriously be compromised. Furthermore,

    Donner must be prepared to turn down a significant number of small orders.

    These small orders represent a large portion of the established customer base

    (80%); and those customers have been the backbone of Donners business.

    Management and workers will need to adjust their mentality to focus on larger

    orders and be willing to avoid those smaller orders.

    Recommendation# 3:

    Change strategy from current position to one which concentrates on

    producing large & small quantities of simple technology boards,

    through the use of two separate production lines.

    Currently, Donner is already operating and manufacturing for both segments of

    the market with considerable success and a solid customer base. However, in

    serving both the low & high volume markets, it is becoming increasing evident

    that the production processes and facilities are under significant stress. It is also

    clear that the present production facilities have been designed primarily around

    small order size production (since Donner originally started as a producer for

    contract markets). At the same time, Donner is trying to adapt itself, workers

    and facility to cope with the diversification in product lines (the penetration of

    captive markets). Lloyd Searbys sales forecast looks very promising for the

    company, yet this will only be realized if the company can achieve faster delivery

    time, coupled with fewer work in progress and re-works. A large part of the

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    29/35

    problem in meeting these faster delivery times and the increased number of re-

    works and work in progress appears to be the effects that rush orders have on

    the entire production process. Work in progress (WIP) is usually delayed in

    order to expedite these rush orders in a delivery time of four days. With the

    additional 1800-sq. feet of factory space available in the near future, it may be the

    best time make a strategic move to develop two separate production facilities,

    with two separate product lines. This extra production line should be designed to

    meet small volume & rush orders. The existing production line can then be fully

    devoted for large volume production purposes and Donner should purchase a

    second CNC machine and run two separate production lines to accommodate

    this new strategy (advantageous for large-volume orders).

    If two production lines are established, it will simplify the production process

    and make it more efficient, increase the workers productivity, improve delivery

    dates and increase volume of work secured in both the contract and captive

    markets, thus increasing the overall customer base.

    Operational & Strategic Implications

    Labor Utilization:

    At the present time, Donners workers are only working productively for only 3

    hours of their working day and idle (unproductive) for 5 hours (3696 total hours

    in September, however only 1531 hours are actually worked for the month of

    September). This issue stems from three main problems:

    First: there is considerable time wasted through the frequent stop & start

    manufacturing process directly resulting from rush orders.

    Second: inadequate operational organization of current production

    facilities.

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    30/35

    Third: ineffective communication and flow of vital information from

    Flaherty.

    Through the strategic move of introducing a second production line, it will be

    feasible to improve productivity from each work, as work should be able to flow

    continuously through each production line without interruption. Furthermore,

    adopting a parallel manufacturing process will result in less manufacturing lead

    time and faster completion of orders, which will enhance on-time delivery. In

    addition, workers can be deployed more effectively in each production line, as

    job functions will become more defined leading to less confusion and less time

    wasted as the case in the current manufacturing process.

    Also, it is clear that the current manufacturing process results in having too

    many responsibilities lie on the shoulders of very few people (namely: Flaherty).

    With two production lines in operation simultaneously, David Flaherty could be

    made responsible for the large volume production line, with Arthur Dief (as a

    senior and experienced worker) managing the smaller production line. Arthur

    Dief is, clearly, valuable to Donner. Also, new workers could receive their

    training from Arthur. This strategy will allow Donner to better utilize all

    available resources and focus on improving productivity, quality, information

    flow, delivery and, in essence, the bottom line.

    Furthermore, if Donner adopted this strategy, I would also recommend applying

    a parallel process flow as it will result in reduced manufacturing lead time.

    Current process flow is sequential in nature. Assume an order size of 200 boards

    (where CNC drill will be utilized), the sequence of the process flow is as follows:

    Artwork generation 29 minutes to

    set up

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    31/35

    Analyzing the current process, it is evident that it takes a total of 324 minutes

    from the time an artwork is generated until CNC drilling commences. During

    such time it is also evident that there is a total of 55 minutes of idle time that

    occurs at the CNC drilling station. The worker who is responsible for the CNC

    drilling is, literally, idle and waiting for the artwork generation, then for the

    inspect and sheer process, then for the punch tooling hole processes to be

    completed then he or she would begin the CNC set up (which takes 240

    minutes).

    By applying a parallel process flow, this idle time can be reduced significantly.

    The new process may look as follows:

    Inspect and sheer 32.5 minutes

    Punch tooling hole 22.5 minutes

    CNC drill set up time 240 minutes

    Art work generation 29 minutes

    Inspect andSheer

    32.5minutes

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    32/35

    The moment artwork generation is completed, two copies are passed onto both

    stations: inspect and sheer as well as the CNC drill, so that the worker

    responsible for setting up the CNC machine may begin his set up process

    without waiting (being idle / unproductive) for 55 minutes (the time spent on

    inspect & sheer and punch tooling processes). This amounts to a total of 55

    minutes saved on production cycle time (324 min. vs. 269 min. proposed under

    the parallel process flow). Reduced cycle time will translate into better efficiency

    and productivity, which will add to Donners bottom line and improve the on-

    time delivery process.

    The parallel process flow can be utilized at any stage of the production cycle,

    regardless of the order size. It is another method to improve productivity. In

    addition, eliminating any non-value-added processes from the manufacturing

    process will improve productivity (i.e. un-necessary time spent to transfer

    completed boards to the tanks back and forth and other low hanging fruits

    that hamper the overall productivity).

    Capacity:

    The capacity of Donners current production facility is not being fully realized, as

    it is not fully optimized for low or high volume circuit board manufacturing. By

    utilizing two production lines, each can be optimized for their respective

    production purposes, and potential bottlenecks will be easier to identify and

    resolve. This strategic move should allow Donner to achieve the potential sales

    volume of $3 million by 1988 as, predicted by the sales manager.

    Punchtooling

    hole 22.5minutes

    CNC drill 185

    minutes toset up

    CNC run 640

    minutes

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    33/35

    Materials:

    Donners current delivery problems stem from several reasons, including re-

    works, rush orders and the effect they have on WIPs, and also the inadequate

    inventory policy existing within the company. David Flaherty had

    acknowledged that he often delayed his scheduling for several days until the raw

    materials arrived from the vendor. As previously analyzed, it is understandable

    that it would not be possible to stock all raw materials, but a certain core raw

    materials should be stocked to avoid valuable days being lost in the present

    order processing system, as well as to avoid vendors volatilities. The costs

    incurred by carrying inventory should be realized with sales figures increase,

    improved quality and on-time delivery.

    Information Flow:

    The current information flow within Donner can be described as incredibly

    inadequate! Adopting this strategy will succeed only if information flows faster

    and becomes more readily available. Just as there are bottlenecks in the

    production process, there are also bottlenecks in the current information system.

    Orders are taking up to four days to reach Flaherty, after the bid has been

    accepted. This excessive time period is adding to the existing delivery problem.

    As previously described, Donner will hold certain levels of inventory of specific

    raw materials; which will lead to a shorter lead-time of manufacturing and

    information to Flaherty, as well as to his workers. The amount of inventory

    carried can be determined by the 80/20 rule, which means that Donner could

    hold 20% inventory of core raw materials based upon 80% of their individual

    order sizes in September (Donner could determine a monthly baseline or, should

    they elect to, quarterly baseline to determine appropriate level of inventory).

    Also, by improving information flow and simplifying the process, Donner could

    become a market leader in the delivery time of its products, as well as in quality

    and fewer product return rates.

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    34/35

    Quality and on-time delivery:

    Once the new strategic move is adopted by Donner, a new quality strategy

    should also be adopted. Currently, there is not one specific person responsible

    for ensuring quality standards are met. However, by implementing highly

    effective quality control measures (six-sigma, SPC or TQM), this should improve

    quality standards and reduce product returns. Productivity will also be increased

    for the same reasons outlined above. Concerning Donners financial status, the

    firm can generate more sales figures, as a result of improved productivity and

    quality, and possibly attain the sales figure planned by Searby ($3M). Expenses

    incurred during this strategic move should be recouped with increased sales.

    The on-time delivery should be increased significantly due to the companys new

    strategic policy of having two separate production lines, each independent, with

    each optimized for their respective production processes. This will help alleviate

    the delay and confusion inherent in the current system.

    Conclusion

    After reviewing Donners current strategic plans, it is evident that certain

    operations of the company are no longer compatible with Donners objectives.

    There is a need to change while concentrating on the companys core

    competency.

    By attempting to serve both captive and contract markets, Donner has the

    opportunity to expand its market and customer base, as well as improve

    productivity, quality, financial health, labor utilization and capacity. Donner

    could remain one of the market leaders and maintain its competitive edge. All

    these factors will lead to increased sales. It is therefore my conclusion that

  • 7/25/2019 Donner Case Study - MBA 621.pdf

    35/35

    recommendation # 3is the most appropriate and effective solution to Donners

    current problems.