MJEX Gate 1 WEEKLY SITE
PROGRESS
PICTORIAL
REPORT
Feb.07 to 13
2017
DEVELOPMENT
DEPARTMENT
BIRD’S EYE VIEW : February 13, 2017
VIEW near GATE 3 : VIEW FROM Gate 1 : VIEW near Gate 2 :
VIEW LOOKING SOUTH ; VIEW LOOKING NORTH :
VIEW FROM MSCP first floor to mjex gate 1 :
February 07, 2017 February 13, 2017.
Building FAÇADE VIEW FROM KING ROAD:
February 07, 2017
February 13, 2017
SKYLIGHTS :
A.1 CIVIL & STRUCTURAL :
Zone 1= Pouring of stamped concrete
walkways @ Mall Entrance. Remove part of existing concrete road @
Gate 3.
Zone 2= Concrete art form for decorative
fountain. Site work for car parking area.
Zone 3=: Pouring of stamped concrete ramp/
walkway.. Site layout & preparation prior pouring of
stamped concrete driveway, Gate 2.
B.1 ARCHITECTURAL :
Zone 1= Gypsum board ceiling & fascia. Cement plastering of external walls.
Zone 2 =Gypsum board false ceiling @ 1
st
Floor. Floor tiles work @ 1
st Floor, Gate 1.
Zone 3= Sealing of curtain wall glazing
joints. Floor tiles work @ Ground Floor, Gate 3...
C.1 MEP / ELECTRO- MECHANICAL:
Zone 1= Existing/ old lighting pole pedestal. Electrical wires for branches distribution.
Zone 2 = Fixing of Fire Hose Cabinet... Fixing of ductwork insulations..
Zone 3 = Survey of As- Built location of
machines… Electrical cable pulling…
Electrical cables & cable trays. Insulation for ductwork...
Power Ventilator for Smoke Control System. Power Ventilator Specifications.
Grease trap interceptors @ Gate 2... Grease trap interceptor @ Gate 3.
Prepared by : Noted by :
Engr. DANIEL L. RAZO RSM Site Superintendent
Engr. JAWEED O. ALHINDI RSM Development Manager