Est. cost
crores Agency LOI Sch comp Survey Foundation Erection Stringing
1400 kv s/s Gonda
(PPP I)
220 kv dc Gonda400-Gonda220 DC inter-
connector13.45 11.17
Trading Engineers
13.45 03/46 0/46 0/13.45 11.6
1. Stubs & Templates delivered at site. 2. 03 nos. FDN gang to be deployed shortly.
The proposed date of complition is 31.03.16.
2400kV Hardoi
Road(Lucknow)400kV Hardoi
Road(Lucknow) S/s- 220kV Hardoi Road DC Interconnector
9.25 7.4 18.07.14 22.07.14 26.07.14 5.18 Unitech Comp 0/35 0/35 0/9.25 10profile submitted for
approval.The proposed date of complition is 22.06.16.
1220 kv s/s Tanda
(RNNSAS)
220 kv DC Sohawal(400) -Tanda
TD-329
113.24 72.47 PNC 16.09.10 15.09.11 Comp 336/348 217/ 34812/
113.2469.3
FDN, ROW at 10 locs loc no- 11,12,23,29,157,183,190,248, 249,250 Er ROW at loc no 145,
Str ROW at loc no.-92, crop compensation cases paid. The
proposed date of complition is 31.10.15.
132 kv sc Tanda220-Tanda132
TD-348
11.8 2.42 Aster 06.04.11 05.04.12 Comp 50/54 45/54 7.92/ 11.8 86.6
As per local representative ROW at loc 8/0 & 6/1 for Erection and
at loc 8/0 to 13 for Stringing work and EE, ETD, Faizabad to meet DM today, 01 no Erection gang working at site at loc 12 & 13
WIP, 01 no Stringing gang working at Tanda Gantry & Dead End Tower WIP, Stringing work at
loc 3-4 completed, Foundation work could not be started due to standing sugarcane & paddy crop. Foundation work likely to start by next week. The proposed date of
complition 12.10.15.
2220 kv s/s Nighasan
(RNNSAS)
Work ProgressED
% Prog.
DETAILS OF ONGOING LINES UNDER TRANSMISSION CENTRAL
Sl. No.
Name of workTend. No.
Length Km.
TWC BOD ETFLoan
(in Cr.)Remarks
Est. cost
crores Agency LOI Sch comp Survey Foundation Erection Stringing
Work ProgressED
% Prog.
Sl. No.
Name of workTend. No.
Length Km.
TWC BOD ETFLoan
(in Cr.)Remarks
220 kv sc Sitapur-Nighasan
TD-329
110 55 15.19 SEW 23.03.10 22.09.11 Comp 335/336 317/ 33681.92/
11092.4
Row in Foundation at loc no. 84, under court case. River xing work to be taken up after receeding of
water.S/s Ready.The proposed date of complition 31.12.15.
220 kv sc Shahjahanpur-
Nighasan
TD-329
121 60.5 SEW 23.03.10 22.09.11 Comp 368/369 358/ 369104.18/
12195.9
ROW at 1location -32/2, matter in court ,River xing work to be
taken up after receeding of water..S/s Ready.The proposed
date of complition 31.12.15.
LILO of 132 kv Lakhimpur-Pallia line
@ Nighasan
TD-348
1.15 0.32 Aravali 06.04.11 05.01.12 WIP 04/8 0/8 0/1.15 18.5
No gang working at site since last one month,in the review meeting dt 23.09.15 firm assured to start the work earliest. The proposed
date of complition 30.09.15
132 kv sc Nighasan-Dhaurahra
TD-329
23.4 7.25 PNC 28.04.10 27.04.11 Comp 75/75 75/75 21/ 23.4 97.4
The work is held up due to crossing of LILO of Lakhimpur-
Palia at Nighasan being constructed by M/s Aravali who
have started the work. The proposed date of complition is
31.10.15.
132 kv sc Nanpara-Dhaurahra
TD-348
50.94 15.79 Aravali 06.04.11 05.04.12 Comp 139/153 89/153 0/50.94 64.4
Soil investigation report submitted, Rly proposal
submitted, Pile fdn to be built on River crossing, No gang working at site since last one month, in the review meeting dt 23.09.15 firm assured to start the work earliest. The proposed date of
complition 28.02.16
132 kv sc Nighasan-Gola
TD-348
50.11 15.54 Aravali 06.04.11 05.04.12 Comp 90/168 41/168 0/50.11 48.3
No gang working at site since last one month, in the review
meeting dt 23.09.15 firm assured to start the work earliest. The proposed date of complition
31.03.16
Est. cost
crores Agency LOI Sch comp Survey Foundation Erection Stringing
Work ProgressED
% Prog.
Sl. No.
Name of workTend. No.
Length Km.
TWC BOD ETFLoan
(in Cr.)Remarks
3220 kv s/s Kanpur
Road(GIS)
LILO of 22o kV DC Sarojini Nagar (400kV)- Unnao Line at 220 kV
GIS Kanpur Road
5
REC-047-2011-4811
(7153.7)
Turn Key UPRNN
2.10.11 702 Km cable laying work
completed out of 5 Kms.
4 220 kv s/s Bahraich
220 kv dc Gonda400-Bahraich
74.29 24.61 09.07.08 03.02.09 Varrsana 04.02.14 03.02.15 Comp224/ 234
148/ 234
0/74.29 66.6
Erection WIP at loc 94 & 12, Fdn WIP at loc 109. The proposed date of complition
29.02.16.
132 kv dc Bahraich220-Nanpara
40.58 13.44 09.07.08 03.02.09REC 047-
2009-3058
ECI 15.02.14 14.02.15 Comp 21/130 0/130 0/40.58 20Fondation WIP. The proposed date of complition 31.03.16.
132 kv LILO Gonda-Bahraich @ 220Kv
Bahraich17.56 3.67 09.07.08 03.02.09
REC 047-2009-3058
ECI 15.02.14 14.02.15 Comp 22/58 0/58 0/17.56 35.5
Re-survey done between location 50-60, profile submitted in the
division not approved so for. The proposed date of complition
31.12.15.
5220 kv s/s Kursi Road
(RNN III)
220 kV dc Lko PGCIL(400)-Kursi Rd
TD-348
12.89 8.12 Hythro/
Jyoti23.12.11 23.12.12 Comp 66/66 13/66 0/12.89 58.9
Erection work in progress, 01 no Erection gang working at
site..The proposed date of complition 31.12.15.
6 220 kv s/s Pilibhit
220 kv sc Baikunthpur (Bareilly)(400) - Pilibhit
(on dc tower) 58 20.62 21.5.12 18.7.12 12.12.12 Accord 03.07.16 0/180 0/180 0/58
Route alignment approved, Profile submitted, under
checking, firm debared for a period of one year.
7 220kV S/s Barabanki220 kV DC
Sohawal(400) PGCIL -Barabanki(220) Line at
Barabanki S/s
69 45 18.07.14 22.07.14 26.07.14 31.5 Unitech Comp 8/225 0/225 0/69 10Fdn WIP at 2 loc. The proposed date of complition is 22.12.16
1 132 kv s/s Jalalpur
Est. cost
crores Agency LOI Sch comp Survey Foundation Erection Stringing
Work ProgressED
% Prog.
Sl. No.
Name of workTend. No.
Length Km.
TWC BOD ETFLoan
(in Cr.)Remarks
132 kv sc Kadipur-Jalalpur
TD-348
46.4 8.82 Aster 24.12.11 23.12.12 comp 60/151 0/151 0/46.4 39.9Work to be taken after Tanda-
Tanda line.The proposed date of complition 31.03.16.
2 132 kv s/s Bhinga
132 kv sc Nanpara-Bhinga
TD-348
50.05 9.51 Aster 06.04.11 05.04.12 Comp 79/165 33/165 0/50.05 46
Firm has submitted work schedule to complete the line by
Feb, 2016, 03 no Foundation gang working Fdn at loc-91,92,93 &158. WIP. The proposed date of
complition 28.02.16.
3132 kv s/s
Utraula(Dept)
132 kv sc Dumariaganj-Utraula
TD-329
39.95 12.38 PNC 09.11.10 31.07.11 Comp 108/114 107/ 114 32/ 39.95 92.5
FdnWIP,Fdn ROW at Loc-32 shall be resolved by month end, under
court case, anchor tower excavation work will start on
15.10.15. The proposed date of complition is 31.10.15.
4 132 kv s/s Nindura
132 kV SC Kursi Road LKO(220)-
Piparsand(Nindura)
TD-348
26.49 8.21Hythro/
Jyoti23.12.11 23.12.12 Comp 79/103 18/103 0/26.49 52.7
Tower material reached at site.Work to start shortly.The proposed date of complition
15.01.16.
5 132 kv S/S Bikapur
132 kv sc Bikapur-Sohawal
TD-348
23.15 4.74 Aster 06.04.11 05.04.12 Comp 0/89 0/89 0/23.15 0
Survey Work complited and to be submitted to concerned divison
by month end, S/s ready & charged by LILO of Sultanpur-Darshan nagar. The proposed date of complition 31.03.16.
6132 kv S/S Shahabad
(RNN)
132 kv sc Shahjahanpur-
Shahabad
TD-329
51.18 15.86 PNC 28.04.10 27.04.11 Comp 135/135 131/ 13533.50/ 51.18
90.8
Er & stringing work under progress, 01 no. gang for each
activity is deployed, Er ROW at 05 locs:- loc no.1,2,3,4 & 5 Str ROW at 4 locs:- loc no. 47,52,53& 65.
7 132 kv s/s Baghauli
132 kv LILO Hardoi-Shahabad@ Baghauli
TD-329
22.5 8.78Aravali/
Jyoti15.10.11 14.10.12 Comp 72/72 33/72 0/ 22.50 64.2
Erection work under progress, 01 no. gang working at site.
Est. cost
crores Agency LOI Sch comp Survey Foundation Erection Stringing
Work ProgressED
% Prog.
Sl. No.
Name of workTend. No.
Length Km.
TWC BOD ETFLoan
(in Cr.)Remarks
8132 kv s/s Biswan
(TKSAS)CM
132 kv 2 Ph. 220 Kv S/s Sitapur-Hempur Rly
TSS24.99 7.7 RS INFRA 20.07.12 19.07.13 Comp 93/93 93/93
24.99/ 24.99
100Line completed gantry at Rly end
not ready.
9132 kv s/s Laharpur
(TK NKG)
132 kV SC Lakhimpur-Laharpur
TD-348
32.23 9.99Hythro/
Jyoti23.12.11 23.12.12 Comp 86/95 27/95 0/ 32.23 58.3
Approval of 1no. of rly xing is awaited. No work at present.The
proposed date of complition 23.12.15.
10132 kv s/s
Goshaisinghpur (Dept)
132 kv sc Tanda220-Goshaisghpr
TD-348
29.4 5.95 Aster 06.04.11 05.04.12 Comp 94/99 76/99 0/29.4 69.1Work to be taken up shortly & 1 stringing gang to be deployed by
month end.
11 132 kv s/s TilharLILO of
Shahanjahanpur-Badau at Tilhar
8.76 3.42Aravali/
JyotiComp 19/30 0/30 0/ 8.76 45.8
Survey work under progress.The proposed date of complition
31.12.15.
12132 kv s/s
Chakalbanshi (Dept)
132 kv sc Sonik-Chakalvanshi
TD-313
29.75 9.22 Jyoti 04.09.08 03.09.09 Comp 98/104 90/10429.07/ 29.75
95.3
2 rly xing one already approved & one under approval.2 loc forest clearence required, on line NOC applied to forest department for approval.The proposed date for
the complition is 31.10.15.
13 132 kV Neri (Sitapur)
132 kv LILO of Sitapur-Shahjahanpur@Neri
4 1.95 06.07.12 18.07.12 12.12.12
REC 047-2012-6596 1.75
Local 12th Plan
14 132 kV s/s Bandaa
Est. cost
crores Agency LOI Sch comp Survey Foundation Erection Stringing
Work ProgressED
% Prog.
Sl. No.
Name of workTend. No.
Length Km.
TWC BOD ETFLoan
(in Cr.)Remarks
132 kV SC Puwanyan - Bandaa
20 6.202 Aravali
Land finalized, no work yet started, in the review meeting dt 23.09.15 firm assured to start the work earliest. The proposed date
of complition is 31.03.2016.
133 kV SC Gola - Bandaa
45 13.955 Aravali
Land finalized, no work yet started, in the review meeting dt 23.09.15 firm assured to start the work earliest. The proposed date
of complition is 31.03.2016.
15 132 kv s/s Haidargarh
132 kv LILO of sc jagdishpur-Haidergarh
Sugar Mill @ Haidergarh
20 6.59 30.4.11 18.7.12
REC 047-2012-6631 05.93
Accord 03.07.16 0/62 0/62 0/20
Route survey completed, profile approved, no gang present at
site, firm debared for a period of one year.
132 kv dc Sultanpur Rd. Lko (400)-
Haidergarh 30 9.89 30.4.12 18.7.12
REC 047-2012-6631 08.90
Accord 03.07.16 0/93 0/93 0/30On hold,firm debared for a
period of one year.
16132 kv s/s
Mahmudabad
132 kv sc (on dc towers) Sidhauli-
Mahmudabad 32 19.87 6.7.12 18.7.12 12.12.12 Accord 03.07.16 0/99 0/99 0/32
Route survey completed, profile approved, no gang present at
site, firm debared for a period of one year.
132 kv bay @ Sidhauli
17 132KV Sareni S/s
132KV Dalmau(Raebareilly)-
Sareni30 10.05 13.02.14 10.05.14 Accord 03.07.16 0/93 0/93 0/30
Route survey defective re-route survey in progress, firm debared
for a period of one year.
132KV Bighapur (Unnao)-Sareni
40 13.34 13.02.14 10.05.14 Accord 03.07.16 0/124 0/124 0/40Route survey defective re-route survey in progress, firm debared
for a period of one year.
18 132 kv s/s Bisalpur
Est. cost
crores Agency LOI Sch comp Survey Foundation Erection Stringing
Work ProgressED
% Prog.
Sl. No.
Name of workTend. No.
Length Km.
TWC BOD ETFLoan
(in Cr.)Remarks
132 kv sc Pilibhit-Bisalpur
35 8.03 09.07.08 Accord 03.07.16 0/109 0/109 0/35
Profile approved, 01 excuation done after that no gang at site,
firm debared for a period of one year.
132 kv sc Barreily II-Bisalpur
40 9.17 09.07.08 Accord 03.07.16 0/124 0/124 0/40Route survey in progress,firm
debared for a period of one year.
4*132kv bays
132 kv sc Aonala-Bisauli
25 8.33Archon/
EMC4.03.15/3
1.07.1530.06.16
Route survey to start form 01.11.15. The proposed date of
competion is 30.06.16
19 132 kv s/s Alapur
132 kv sc New Tanda(Akbarpur 220KV) -Alapur
35 8.03 21.11.11 18.7.12 Accord 03.07.16 0/109 0/109 0/35Due to wrong survey re-survey
started by firm,firm debared for a period of one year.
132 kv sc Koilsa (Azamgarh) -Alapur
15 3.44 21.11.11 18.7.12 Accord 0/47 0/47 0/15On hold,firm debared for a
period of one year.
20 132 kv S/s Colonelganj
132kV DC Gonda (400) - Colonelganj Line at
132kV S/s Colonelganj30.36 8.76 18.07.14 22.07.14 26.07.14
Trading Engineers
30.36 0/101 0/101 0/30.36 10
1. Stubs & Templates delivered at site. 2. 03 nos. FDN gang to be deployed shortly.
The proposed date of complition is 30.04.16.
21 132 kV S/s Salon132kV DC Amawan (Raebareilly) - Salon
Line at 132kV S/s Salon
40.84 21 18.07.14 22.07.14 26.07.14 14.7 Unitech Comp 0/149 0/149 0/40.84 10
Profile approved on 18.09.15, work will start shortly.The
proposed date of complition is 22.09.16.
22132 kV S/s
Begampur(Sohrwa)
LILO of Cons 132kV SC Bahraich(220kV) -
Nanpara Line at 220kV S/s Begampur
0.4 4.6 18.07.14 22.07.14 26.07.14 3.22 Unitech Comp 0/3 0/3 0/0.4 10
Only 3 tower required in this line. The proposed
date of complition is 22.06.16.
23132KV Maurawan
(Unnao) S/s2x20
Est. cost
crores Agency LOI Sch comp Survey Foundation Erection Stringing
Work ProgressED
% Prog.
Sl. No.
Name of workTend. No.
Length Km.
TWC BOD ETFLoan
(in Cr.)Remarks
132KV Bighapur-Maurawan
35 11.718 10.12.13 10.05.14
24 132 kv s/s Jalalabad
LILO of 132 kv Shahjanpur- Usawan
line @ Jalalabad18 7.57 21.11.11 18.7.12
REC 047-2012-6591 6.81
Accord 03.07.16 0/56 0/56 0/18On hold,firm debared for a
period of one year.
1 220 kv dc Roza-DohnaTD-329
108.07 74.52 SEW23.03.10
/ 19.10.10
22.09.1118.04.11
Comp 340/340 340/ 340107.87/ 108.07
100Line completed OPGW work
under progress.
2220 kv dc Dohna-CB
ganj secTD-329
24 12 SEW 23.03.11 22.03.12 Comp 92/92 82/92 14.55/ 24 88
Rly xing approval pending for loc 26-27, Crop compensation cases pending, work stop at loc. No. 61 &25 due to crop compensation
not paid.
3132 kv sc SGPGI-
Utrathiya Rly LineTD-304
10.62 2.09 Pioneer Apr-08 Oct-08 Comp 44/44 32/44 5/ 10.44 81.2
ROW at 11 loc(14-21,24,42 & 43) 9 loc at kali pashim & 2 loc at
SGPGI), matter being taken up at higher level with Distt admin.
Held up.
4132 kv sc 2ph
Ramsanehighat-Budwal
TD-313
44.27 13.72 Unitech 20.1.08 20.01.09 Comp 139/146 139/ 14639.48/ 44.27
95.1
Letter written by EE to DM,Joint survey with Rly. done on 18.08.15,
meeting was held with Rly & estimate of cable has been sent to Railways
5132 kv dc Shyam Fert-
Shahjahanpur15.3 Kribhco Comp 68/68 68/68
15.31/ 15.31
Work being carried out by M/S Kribhco Shyam Fertilizers
themselves.
6132 kv Maqsoodpur
Sugar Mill-Shahajanpr220
TD-350
46.05 20.09 Hythro 31.12.10 30.06.11 Comp 138/139 127/ 13913.67/ 46.05
80.5
Notice has been surve to M/s Hythro & SE, ETC Bareilly taking
action to get the work done through a debitable agency.
7
132kV Loc-12 of Maqsoodpur -
Shahjahanpur (220kV) Line - Shahjahanpur
(132kV)
8.62 7.56 Hythro 8.62 30/33 28/33 0/8.62 69.7
Notice has been surve to M/s Hythro & SE, ETC Bareilly taking
action to get the work done through a debitable agency.
Est. cost
crores Agency LOI Sch comp Survey Foundation Erection Stringing
Work ProgressED
% Prog.
Sl. No.
Name of workTend. No.
Length Km.
TWC BOD ETFLoan
(in Cr.)Remarks
8
LILO of 132 kV Sonik(unnao) -
Bighapur @ Maurawan S/s
22.69 4.74 Varrsana 03.09.14 02.09.15 Comp 74/78 1/78 0/22.69 40
Fdn-casting in progress at loc no 14 B, Er under progress at loc 19 A, 20 C+0 (material shifted). The
Target date of completion 15.11.15
9220 Kv Hardoi rd.-132 kv Hanuman setu (GIS)
U/G Cable107.8
14815.87 (In Lac)
11.11.11REC-047-
2011-5719
UPRNN 88
New site for S/s identified but couldn't handed over yet. The
proposed date of completion is 31.12.15.
10
220 KV dc Sohawal (220 KV)-
Muzzafrapur,Faizabad(400 KV PGCIL)
30 21.99 10.09.12 11.12.12 ECI 15.04.15 14.04.16 1/82 0/82 0/30 10
Foundation WIP, firm to immediately take action for starting erection work. The propsed date of complition
31.03.16.
11
Replacement of HTLS conductor & other
works of following SC lines:-
i)132kv Chinhat-
Gomtinagar SC line13.9 29.08.14 Apar 14.08.15 13.08.16 NA NA
LOI issued on 14.08.15. The proposed date of
complition is 13.08.16.
ii)132kv Chinhat-
Barabanki SC line19.05 29.08.14 Apar 14.08.15 13.08.16 NA NA
LOI issued on 14.08.15. The proposed date of
complition is 13.08.16.
iii)132kv Hardoi Rd.-NKN
SC line10.05 29.08.14 Apar 14.08.15 13.08.16 NA NA
LOI issued on 14.08.15. The proposed date of
complition is 13.08.16.
iv)132kv Gonda-Bahriach
SC line65 29.08.14 Apar 14.08.15 13.08.16 NA NA
LOI issued on 14.08.15. The proposed date of
complition is 13.08.16.
v)132kv Dohna-
Bareilly(I) SC line21 29.08.14 Apar 14.08.15 13.08.16 NA NA
LOI issued on 14.08.15. The proposed date of
complition is 13.08.16.
50.5