Design Review Report for Bridges in Northern Uganda

download Design Review Report for Bridges in Northern Uganda

of 171

Transcript of Design Review Report for Bridges in Northern Uganda

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    1/171

    May 2011

    CCOONNSSUULLTTAANNCCYY SSEERRVVIICCEESS

    ffoorr

    CCOONNSSTTRRUUCCTTIIOONN OOFF BBRRIIDDGGEESSIINN NNOORRTTHH WWEESSTT UUGGAANNDDAA

    DDDEEESSSIIIGGGNNN RRREEEVVVIIIEEEWWW RRREEEPPPOOORRRTTT(((FFFIIINNNAAALLL)))

    Ethiopia

    Office

    (Head Office)

    P.O.Box 62668; Tel. 0114391065 /0114391499 /0114 391733 /0114393004; Fax 0114391230 /0114391617

    E-mail: [email protected] Web-site: www.saba-engineering.com

    Addis Ababa, Ethiopia

    Uganda

    Office

    P. O. Box 21321, Plot No. 1376, Block No. 244, Muyenga Diplomat Zone

    Tel. +25641267547; Fax. +25641268352; Mobile +256772712178, Email: saba-

    [email protected]

    Kampala, Uganda

    TTTHHHEEE RRREEEPPPUUUBBBLLLIIICCC OOOFFF UUUGGGAAANNNDDDAAA

    UUggaannddaa NNaattiioonnaall RRooaaddss AAuutthhoorriittyy

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    2/171

    Construction of Bridges in North West Uganda Design Review Report____________________________________________________________________________________________

    Uganda National Roads Authority i

    SABA Engineering P.L.C

    TABLE OF CONTENTSPage

    LIST OF FIGURES ....................................... ........................................ ................................. iv

    LIST OF TABLES ......................................... ............................................ .............................. v

    1 INTRODUCTION ........................................... ....................................... ................. 1-1

    1.1 General .......................................... ........................................... .................... 1-1

    1.2 Scope of the Design Review ......................................... ............................... 1-2

    1.3 Purpose and Content of the Report ........................................... .................... 1-3

    1.4 Approach of Design Review ......................................... ............................... 1-3

    2 FIELD INVESTIGATION BY THE DESIGN REVIEW CONSULTANT ....... 2-1

    2.1 Project Background ................................. ............................................ ......... 2-1

    2.2 Field Visit ...................................... ........................................... .................... 2-1

    2.3 Factual Findings ...................................... ........................................... .......... 2-1

    2.4 Recommendation ..................................... ........................................ ............. 2-2

    2.4.1 Supervision Team ............................................................................ 2-2

    2.4.2 Surveying Work ............................................................................... 2-2

    3 GEOTECHNICAL INVESTIGATION OF BRIDGE SITES AND

    CONSTRUCTION MATERIAL SOURCES ............................................... ......... 3-1

    3.1 General .......................................... ........................................... .................... 3-1

    3.2 Determination of Allowable Bearing Pressure for Bridge Foundations ....... 3-1

    3.3 Foundation Recommendation........................................ ............................... 3-2

    3.4 Investigation of Construction Material Sources .................................. ......... 3-7

    3.4.1 General ............................................................................................ 3-7

    3.4.2 Potential Quarry Stone Sources ...................................................... 3-7

    3.4.3 Potential Gravel (Muram) Sources ............................................... 3-17

    3.4.4 Potential Sand Sources .................................................................. 3-22

    4 HYDROLOGICAL and HYDRAULIC STUDY REVIEW ................................ 4-1

    4.1 Background ...................................... ........................................... ................. 4-1

    4.2 Objective ...................................... ............................................ .................... 4-1

    4.3 Hydrology..................................................................................................... 4-2

    4.4 Data Collection ........................................ ........................................... .......... 4-2

    4.4.1 DEM and Aerial Photographs ......................................................... 4-2

    4.5 Drainage Characteristics, Geology and Topography .................................. .. 4-2

    4.6 Climate ...................................... ........................................... ........................ 4-5

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    3/171

    Construction of Bridges in North West Uganda Design Review Report____________________________________________________________________________________________

    Uganda National Roads Authority ii

    SABA Engineering P.L.C

    4.7 Peak Discharge Estimation ..................................... ...................................... 4-5

    4.7.1 Rational Method .............................................................................. 4-5

    4.7.2 SCS Method ..................................................................................... 4-6

    4.7.3 Regression Equation........................................................................ 4-7

    4.7.4 Historic data Analysis ..................................................................... 4-7

    4.7.5 TRRL Flood Model ......................................................................... 4-7

    4.8 Hydrology Review Summery ........................................ ............................. 4-49

    4.9 Hydraulics ............................................ .............................................. ........ 4-49

    4.10 HEC Ras 4.0 Bridge Hydraulic Analysis ........................................ ........... 4-50

    4.11 HY-8.7 Culvert Hydraulic Analysis ......................................... .................. 4-62

    4.12 Culvert Hydraulic Design Review Output ......................................... ........ 4-70

    4.13 Hydraulic Design Review ...................................... .................................... 4-70

    4.14 Existing Structures Physical Assessment .................................. ................. 4-71

    4.15 Conclusion and Recommendations .......................................... .................. 4-76

    5 STRUCTURAL DESIGN REVIEW .......................................... ............................ 5-1

    5.1 General .......................................... ........................................... .................... 5-1

    5.2 Scope ...................................... ............................................. ......................... 5-1

    5.3 Structural System ............................................ ........................................... .. 5-1

    5.4 Design Codes ........................................... ........................................... .......... 5-2

    5.5 Materials Properties ..................................... ........................................... ...... 5-3

    5.5.1 Concrete Grade: .............................................................................. 5-3

    5.5.2 Reinforcement Steel ......................................................................... 5-35.5.3 Structural steel grade: ..................................................................... 5-3

    5.6 Design Limit States ........................................ ............................................ .. 5-3

    5.6.1 Strength Limit State ......................................................................... 5-3

    5.6.2 Serviceability Limit State ................................................................ 5-4

    5.7 Minimum Clear Cover to Reinforcement .................................... ................. 5-4

    5.8 Detailed Design Review of Bridges ......................................... .................... 5-4

    5.8.1 Superstructure ................................................................................. 5-4

    5.8.2 Substructure .................................................................................... 5-4

    5.8.3 Review Procedure ........................................................................... 5-5

    5.9 Geometric Design Review of Approach Road ....................................... ...... 5-6

    5.10 Conclusion and Recommendation .................................... ............................ 5-7

    5.10.1 Structural Analysis .......................................................................... 5-7

    5.10.2 Foundation ...................................................................................... 5-7

    6 KIA-KIA BRIDGE REVIEW ...................................................................... .......... 6-1

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    4/171

    Construction of Bridges in North West Uganda Design Review Report____________________________________________________________________________________________

    Uganda National Roads Authority ii i

    SABA Engineering P.L.C

    6.1 Background ...................................... ........................................... ................. 6-1

    6.2 Field Investigation ....................................... ........................................ ......... 6-2

    6.2.1 General ............................................................................................ 6-2

    6.2.2 Field Visit........................................................................................ 6-2

    6.2.3 Surveying Work.............................................................................. 6-3

    6.2.4 Geotechnical Investigations ............................................................ 6-5

    6.2.5 Investigation of Construction Material Sources .............................. 6-5

    6.2.6 Physical Hydrological Investigation ............................................... 6-7

    6.3 Preliminary Design .......................................... ........................................... .. 6-8

    6.3.1 General ............................................................................................ 6-8

    6.3.2 Hydrological and Hydraulic Analysis ............................................. 6-8

    6.3.3 Geometric Design.......................................................................... 6-13

    6.3.4 Structures....................................................................................... 6-13

    6.4 Conclusions and Recommendations ............................................ ............... 6-14

    7 NYAGAK-3 Culvert Hydraulic Design Adjustment .......................................... .. 7-1

    8 TENDER DOCUMENT REVIEW ......................................... ............................... 8-1

    8.1 Introduction ...................................... ........................................... ................. 8-1

    8.2 Section I: Invitation to Bid ............................................ ............................... 8-2

    8.3 Section II: Instructions to Bidders .................................... ............................ 8-2

    8.3.1 Contents of Bid Documents ............................................................. 8-2

    8.3.2 Documents Comprising the Bid ....................................................... 8-2

    8.4 Section III: Bidding Data ....................................... ...................................... 8-3

    8.5 Section IV: Part 1: General Conditions of Contract ..................................... 8-3

    8.6 Section V: Part 2: Conditions of Particular Application .............................. 8-3

    8.6.1 Contract Documents ........................................................................ 8-3

    8.6.2 Settlement of Disputes ..................................................................... 8-4

    8.6.3 Changes in Cost and Legislation..................................................... 8-4

    8.7 Section VI: Technical Specifications .................................... ....................... 8-7

    8.7.1 General Specifications .................................................................... 8-7

    8.7.2 Special Provisions for the Standard Technical Specifications ........ 8-7

    8.7.3 New Work Items .............................................................................. 8-7

    8.8 Section VII: Forms of Bid, Appendix to Bid and Bid Security .................. 8-118.8.1 Appendix to Form of Tender ......................................................... 8-11

    8.8.2 Tender Security ............................................................................. 8-25

    8.9 Section VIII: Bill of Quantities ......................................... ......................... 8-26

    8.9.1 BOQ Specific Remark .................................................................... 8-26

    8.9.2 New Updated BOQ ........................................................................ 8-26

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    5/171

    Construction of Bridges in North West Uganda Design Review Report____________________________________________________________________________________________

    Uganda National Roads Authority iv

    SABA Engineering P.L.C

    8.10 Section IX: Form of Agreement, Forms of Performance Security, Bank

    Guarantee for Advance Payment & Letter of Acceptance ......................... 8-26

    8.10.1 Form of Agreement ........................................................................ 8-26

    8.10.2 Letter of Acceptance ...................................................................... 8-27

    8.11 Section X: Drawings ...................................... ............................................ 8-28

    8.12 Section XI: Dispute Resolutions Procedure ....................................... ........ 8-28

    9 CHANGES MADE ON THE TENDER DOCUMENT UNDER THE NEW

    SCOPE OF WORK .............................................................. ................................... 9-1

    LIST OF FIGURES

    PageFigure 2-1: Location of 21 Bridges ............................................................................ 2-3

    Figure 4-1: Areas for Calculation of 2 and 7 Day Antecedent Rainfall ................. 4-11

    Figure 4-2: Soil zones .............................................................................................. 4-12

    Figure 4-3: Rainfall Time (TP) Zones ...................................................................... 4-16

    Figure 4-4: 2yr 24hrs point storm rainfall................................................................ 4-18

    Figure 4-5: 10 year to 2 year ratio ........................................................................... 4-19

    Figure 4-6: Flood Factor .......................................................................................... 4-20

    Figure 4-7: Oluffe Bridge catchment area drainage description .............................. 4-22

    Figure4-8: Oluffebridge catchment area floworinetation ........................................ 4-23

    Figure 4-9: Ore culvert watershed area drainage pattern ......................................... 4-26

    Figure 4-10: Ore culvert drainage orientation with elevation labeling .................... 4-27

    Figure 4-11 Enve Bridge drainage pattern ............................................................... 4-31

    Figure 4-12: Enve bridge drainage orientation with elevation labeling .................. 4-32

    Figure 4-13: Goli bridge drainage pattern ............................................................... 4-35

    Figure 4-14: Goli bridge drainage orientation with elevation labeling.................... 4-36

    Figure4-15: Lebijo Culvert e drainage ..................................................................... 4-40

    Figure 4-16: Lebijo Culvert drainage orientation with elevation labeling .............. 4-41

    Figure 4-17: Enyau-3Bridge drainage pattern ......................................................... 4-46

    Figure 4-18: Enyau-3 bridge drainage orientation with elevation labeling ............. 4-47

    Figure 4-19: Oluffe proposed bridge U/S & D/S cross sectional view.................... 4-51

    Figure 4-20: Oluffe proposed bridge with 25 years design flood ............................ 4-52

    Figure 4-21: Enve proposed bridge U/S & D/S cross sectional view ...................... 4-54

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    6/171

    Construction of Bridges in North West Uganda Design Review Report____________________________________________________________________________________________

    Uganda National Roads Authority v

    SABA Engineering P.L.C

    Figure 4-22: Enve proposed bridge with 25 years design flood .............................. 4-55

    Figure 4-23: Goli proposed bridge U/S & D/S cross sectional view ....................... 4-57

    Figure 4-24: Goli proposed bridge with 25 years design flood ............................... 4-58

    Figure 4-25: Enyau-3 proposed bridge U/S & D/S cross sectional view ................ 4-60

    Figure 4-26: Enyau-3 proposed bridge with 25 years design flood ......................... 4-61

    Figure 4-27: Ore existing culvert cross sectional view ............................................ 4-64

    Figure 4-28: Ore new culvert cross sectional view .................................................. 4-66

    Figure 4-29: Lebijo existing culvert cross sectional view ....................................... 4-68

    Figure 4-30: Lebijo culvert (with additional culvert) cross sectional view. ............ 4-70

    Figure 6-1: Kia-Kia Stream catchment and cross section over view ......................... 6-8

    Figure 6-2: kia kia flood plain cross section along with water surface and proposed

    structures position ................................................................................. 6-13

    LIST OF TABLES

    Page

    Table 2-1: List of GPS Data for Bridges ................................................................... 2-4

    Table 3-1: Presumptive Allowable Pressures for Different Foundation Conditions . 3-2

    Table 3-2: Review of Bridge Site Foundation Investigation and Presumptive

    Allowable Pressures ............................................................................... 3-4

    Table 3-3: Review of Bridge Site Foundation Investigation and Presumptive

    Allowable Pressures as per the new scope of work

    (Lot 1,Lot 2 &Lot 3) ............................................................................... 3-6

    Table 3-4: Summary of Test Results on Rock Sources ............................................. 3-7

    Table 3-5: Summary of Laboratory test results of the potential gravel sources ...... 3-22

    Table 3-6: Summary of Laboratory test results of the potential Sand sources ........ 3-28

    Table 4-1: Bridge catchment area physiographic description

    (As per the new scope) ........................................................................... 4-4

    Table 4-2: Antecedent Moisture Conditions for Storms of Greater than 50mm ..... 4-10

    Table 4-3: Standard contributing area coefficients (Cs) .......................................... 4-13

    Table 4-4: Catchment Wetness Factor (CW) ........................................................... 4-14

    Table 4-5: Land Use Factor (CL) ............................................................................ 4-14

    Table 4-6: Catchment lag Times ............................................................................. 4-15

    Table 4-7: Rainfall time (Tp) for East African 10 year storms ............................... 4-17

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    7/171

    Construction of Bridges in North West Uganda Design Review Report____________________________________________________________________________________________

    Uganda National Roads Authority vi

    SABA Engineering P.L.C

    Table 4-8: Oluffe Bridge Catchment TRLL Model 25 Years Peak Discharge

    Determination ....................................................................................... 4-24

    Table 4-9: Ore Culvert Catchment TRLL Model 25 Years Peak Discharge

    Determination ....................................................................................... 4-28

    Table 4-10:Enve Bridge Catchment TRLL Model 25 Years Peak Discharge

    Determination ....................................................................................... 4-33

    Table 4-11:Goli Bridge Catchment TRLL Model 25 Years Peak Discharge

    Determination ....................................................................................... 4-37

    Table 4-12: Lebijo Culvert Catchment TRLL Model 25 Years Peak Discharge

    Determination ....................................................................................... 4-42

    Table 4-13:Enyau-3 bridge Catchment TRLL Model 25 Years Peak Discharge

    Determination ....................................................................................... 4-48

    Table 4-14: Ore existing culvert input data for HY-8.7 hydraulic analysis ............ 4-63

    Table 4-15: Ore existing culvert hydraulic analysis summery (scenario one) ........ 4-63

    Table 4-16: Ore existing culvert input data for HY-8.7 hydraulic analysis ............ 4-65

    Table 4-17: Ore new culvert hydraulic analysis summery (scenario two) ............. 4-65

    Table 4-18: Lebijo existing culvert input data for HY-8.7 hydraulic analysis ....... 4-67

    Table 4-19: Lebijo Existing culvert hydraulic analysis summery (scenario one) ... 4-67

    Table 4-20: Lebijo culvert (additional culvert) HY-8.7 input data .......................... 4-69

    Table 4-21: Lebijo culvert (with additional culvert) hydraulic analysis summery

    (scenario two) ....................................................................................... 4-69

    Table 4-22: bridge physical survey summery for the 6 bridges under the new

    scope of services. .................................................................................. 4-72

    Table 4-23: Lot 1 bridge physical survey summery ............................................... 4-73

    Table 4-24: Lot 2 bridge physical survey summery ............................................... 4-74

    Table 4-25: Lot 3 bridge physical survey summery ............................................... 4-75

    Table 5-1: List of Sample Bridges ............................................................................. 5-1

    Table 5-2: Slope ratio table (Vertical to Horizontal ratio) ......................................... 5-6

    Table 6-1:Kia-Kia Bridge Catchment TRLL Model 25 Years Peak DischargeDetermination ......................................................................................... 6-9

    Table 8-1: Bill 1000 General .................................................................................. 8-8

    Table 8-2: Bill 3000 Earth Works and Pavement Layers of Gravel or

    Crushed Stone ......................................................................................... 8-9

    Table 8-3: Bill 5000 Ancillary Road Works ........................................................... 8-9

    Table 8-4: Bill 6000 Structures ............................................................................... 8-9

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    8/171

    Construction of Bridges in North West Uganda Design Review Report____________________________________________________________________________________________

    Uganda National Roads Authority vi i

    SABA Engineering P.L.C

    Table 8-5: Bill No 8: Schedule of Day Works ......................................................... 8-10

    Table 8-6: Summary of currencies of the Bid .......................................................... 8-12

    Table 8-7: Interest Rates .......................................................................................... 8-12

    Table 8-8: Weightings for use with Local Currency (UGSH) ................................. 8-13

    Table 8-9: Weightings for use with Foreign Currency 1: ........................................ 8-13

    Table 8-10: Weightings for use with Foreign Currency 2: ...................................... 8-14

    Table 8-11: Weightings for use with Foreign Currency 3: ...................................... 8-15

    Table 8-12: Summary of Payment Currencies ......................................................... 8-16

    Table 8-13: Weightings Applicable for Bill No. 3: Earth Works &

    Pavement layers .................................................................................... 8-17

    Table 8-14: Weightings Applicable for Bill No. 2 & 6 Drainage & Structures ...... 8-17

    Table 8-15: Weightings Applicable for Bill No. 5 Ancillary Works ....................... 8-18

    Table 8-16: Local Currency ..................................................................................... 8-19

    Table 8-17: Foreign Currency 1 (FC1)(a) ................................................................ 8-19

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    9/171

    Construction of Bridges in North West Uganda Design Review Report____________________________________________________________________________________________

    Ministry of Works and Transport 1-1

    SABA Engineering P.L.C

    1 INTRODUCTION

    1.1 General

    Recognizing the vital role the road network plays in enabling national objectives to be

    achieved, the Government of Uganda, represented by the Ministry of Works andTransport (MoWT) recently Uganda National Roads Authority took the

    responsibility, is undertaking improvements to the countrys road network to a

    standard that can cope with the present and anticipated traffic growth.

    With financial support of the Arab Bank and Economic Development in Africa

    (BADEA), economic and technical studies for rehabilitation of 66 bridges in the

    eastern and northern regions of the country were carried out in 2002. Following

    outcomes of the study, the bridges were rank ordered and placed in priorities 1 and 2

    according to traffic levels, existing structural condition and risk of flooding. Based on

    these criteria, 21 bridges were placed in priority I and the rest in priority II.

    Twenty one (21) priority I structures have been selected for inclusion in phase 1 of

    the implementation scheme. The Detailed Engineering Design and Tender

    Documents for the Project have been prepared by an International Consultant, ACE

    Consulting Engineers in the year 2002/ 2003.

    The consultancy contract agreement between the Ministry of Works and Transport

    and SABA Engineering Plc was signed on May 30th, 2007.

    Though the project has progressed through design review stage, recently Ugandan

    National Road Authority has agreed with BADEA to scale down the project scope to

    exclude all the bridges located along the Vurra-Arua-Koboko-Oraba road where the

    road is scheduled for upgrading under World Bank Financed Transport Sectordevelopment Program (TSDP).The very recent revised scope now comprises only 6

    bridges packaged to Enayao-3, Alla-1, Goli, Nyagak-3, Nyacara, Pakwala, bridges.

    The bridges are subdivided into three lots as shown on the table below

    LOT I LOT II LOT III

    Arua Nebbi Nebbi

    1 Alla Goli Nyacara

    2 Enyau 3 Nyagak 3 Packwala

    This Design Review report mainly emphasis 21 bridges in North West Ugandaincluding the recently agreed 10 bridges packaged but engineering estimates and

    tender documents are revised based on the new scope for subsequent retendering

    purpose. Kia-Kia bridge which took a special concern due to design insufficiency

    problem as discussed with UNRA on 19 July 2010 also included and elaborated as

    separate chapter though review report on Kia Kia bridge submitted to the client

    before this report.

    No

    Lot and District

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    10/171

    Construction of Bridges in North West Uganda Design Review Report____________________________________________________________________________________________

    Ministry of Works and Transport 1-2

    SABA Engineering P.L.C

    The high cost of the civil work as compared to the available budget has forced the

    client to seek alternative solution by abandoning Kia-Kia bridge which is considered

    to be very expensive, Cido Bridge which is replaced in 2003 and still in a good

    condition except its single lane configuration and Ora2 & Ora2.

    Objectives of the Project

    The project is divided into two distinct phases:

    Stage I: Pre Construction Services

    Stage II: Construction Supervision

    The objectives of the services as described in the Terms of Reference are:

    In Pre Construction phase, the Consultant familiarize himself with the

    designs, reports and tender documents relating to the project; inspect the

    respective bridge sites and propose any minor modifications deemed

    necessary on the designs and packaging of the works. Subsequently the

    consultant will assist the Client with procurement of Contractors.

    During the Construction Supervision phase, supervise construction of the

    Works (on behalf of the Employer) throughout the entire construction phase,

    including the defects liability (maintenance) period.

    1.2 Scope of the Design Review

    In accordance with the Contract Agreement, the main objectives of the Design

    Review are to carry out the following;

    To Review all documents of previous studies, designs, reports etc after

    acquainting himself with the location and structural condition of each bridgestructure included in the project, and compare these with the intervention measure

    proposed for the structure.

    To carry out field and laboratory tests where necessary to enable verification of

    essential aspects in the detailed engineering design. This will also include

    information on construction material sources.

    Based on the above, recommend minor modifications deemed necessary to the

    designs, bills of quantities, cost estimates and any other relevant aspects.

    Accordingly prepare any necessary drawings at appropriate scales, incorporating

    any modifications approved by the Client.

    To prepare a detailed time schedule for the project and for each structureassuming a practical sequence of activities under given climatic conditions and

    taking into account the time for procuring a contractor. The expected cash flow

    shall also be indicated.

    The consultant shall satisfy himself with suitability of the existing bidding

    documents (or propose any amendments thereof) prepared for national

    competitive bidding,

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    11/171

    Construction of Bridges in North West Uganda Design Review Report____________________________________________________________________________________________

    Ministry of Works and Transport 1-3

    SABA Engineering P.L.C

    1.3 Purpose and Content of the Report

    Tue purpose of this report is to provide a full and detailed description of the work

    undertaken by the consultant in carrying out the design review services of each

    respective review task. The report is dealing with all technical aspects of the projects

    review works, detailed information, investigations, results and recommendations.

    The following aspects of the Engineering Design Review have been addressed within

    the report:

    Section 1: General Introduction

    Section 2: Field Investigation by the Design Review Consultant

    Section 3: Geotechnical Investigation of Bridge sites and Construction

    Material Sources Geotechnical Investigation

    Section 4: Hydrological and Hydraulic Study Review

    Section 5: Structural Design Review

    Section 6: Tender Document Review

    1.4 Approach of Design Review

    Basically, the design review was carried out as per our technical proposal. Both field

    investigations and desktop studies were carried out in the respective disciplines.

    Details are presented in subsequent sections of this report.

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    12/171

    Construction of Bridges in North West Uganda Design Review Report____________________________________________________________________________________________

    Ministry of Works and Transport 2-1

    SABA Engineering P.L.C

    2 FIELD INVESTIGATION BY THE DESIGN REVIEW

    CONSULTANT

    2.1 Project Background

    The selected bridges are located along national and district roads in the north

    western region of Uganda in the districts of Arua and Nebbi and are categorized inthree Lots.

    The Detailed Engineering Design and Tender Documents for the Project have been

    prepared by an International Consultant, ACE Consulting Engineers in the year 2002/

    2003.

    The consultancy contract agreement between the Ministry of Works and Transport

    and SABA Engineering Plc was signed on May 30th, 2007.

    2.2 Field Visit

    The review consultant conducted the field investigation for the Project from

    September 27/2007 to October 1/2007. Kia-Kia and Pakwala bridge sites were notvisited due to their inaccessibility. The team composition is shown below;

    S.No Name Profession/ Assignment

    1

    2

    3

    4

    5

    Dereje Tilahun

    Kassa Dessie

    Michael Abebe

    Yared Amdie

    Samuel Girma

    Resident Engineer/ Team leader

    Material Engineer

    Structural Engineer

    Hydrologist

    Surveyor

    Two personnel that were assigned from the Ministry of Works have been with the

    team all the time.

    2.3 Factual Findings

    Of the 21 bridges considered under the review found in this project, all are proposed

    to be replaced by the design consultant. The following main reasons are given for

    replacement,

    The non-compliance of the design load of the existing structure with the

    required specifications.

    The existing bridge width is too narrow.

    The level of the existing bridge is lower than the flood water level.

    The present span length of the bridge increases the water velocity, which

    leads to the erosion of the substructure.

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    13/171

    Construction of Bridges in North West Uganda Design Review Report____________________________________________________________________________________________

    Ministry of Works and Transport 2-2

    SABA Engineering P.L.C

    The review consultant has visited all the sites except Kia Kia and Pakwala Bridge

    sites, which were inaccessible at the time of the visit. The location of the bridges/

    bridge sites under the new work scope is shown in Figure 2-1.

    2.4 Recommendation

    Following the completion of the field visit, the review consultant would like to bring

    the following general recommendations.

    2.4.1 Supervision Team

    The field investigation during the review period took five days to cover the nineteen

    sites. The proposed one team is in no way sufficient to efficiently conduct the

    supervision work, so the following personnel list is advisable;

    Full Time Staff

    Resident Engineer (1)

    Assistant Resident Engineer (3)

    Senior Surveyors (3)

    Inspector of Works (3)

    Intermittent Staff

    Material Engineer (1)

    Contract/ Claims Engineer (1)

    Environment Specialist (1)

    The Design Consultant has also included office, vehicle and housing for Assistant

    Resident Engineer for each lot. In addition, the Engineers house drawing prepared by

    the Design Consultant also shows a housing accommodation for the Assistant

    Resident Engineer. This shows that the Design Consultant has considered the

    necessity of Assistant Resident Engineer for each lot. But it will be advisable to

    assign resident engineer to address the revised neighboring lots and assistant resident

    engineer for the other lot according to the new consensus.

    2.4.2 Surveying Work

    The design consultant established bench marks using relative coordinates and did not

    connect it to the national grid. This has created problem in locating the bench marks.

    Even on the BMs found, the markings are no more there. If it was tied to the national

    grid, it would have been easier to identify each BM.

    During the construction stage, the consultant will tie the bench marks to the national

    grid.

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    14/171

    Construction of Bridges in North West Uganda Des

    Ministry of Works and Transport

    SABA Engineering P.L.C

    Figure 2-1: Location of 21 Bridges

    Figure 2-1: Location of 21 Bridges Legend: Location: selected 6 bridges

    7

    14

    Bridge Lege

    Lot II

    Lot I

    Lot III

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    15/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 2-4

    SABA Engineering P.L.C

    Table 2-1: List of GPS Data for Bridges

    No Description East North Elevation

    1 Alla 285641 321381 873

    2 Enyo-3 267062 333770 1192

    3 Enayu-1 267125 342069 1140

    4 Enve 267147 348930 1152

    5 Oluffe 270332 352993 1119

    6 Ayi 271353 360296 1106

    7 Yoyo 271976 368197 1128

    8 Oru 272522 369028 1106

    9 Apa-1 272909 375995 1184

    10 Ore 272892 373464 1165

    11 Kochi 273325 381108 1194

    12 Debara 265890 390867 1137

    13 Lebijo 279881 380785 1064

    14 ORA 1 321246 300833 636

    15 ORA 2 321235 300861 628

    16 Nyagak 3 266974 270220 1514

    17 Goli 280863 263203 1375

    18 Cido 262039 284418 1297

    19 Nyacara 274042 287827 1003

    Note: The highlighted including Pakwala bridges in table 2.1 above are the one

    considered under the newly revised scope of work.

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    16/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-1

    SABA Engineering P.L.C

    3 GEOTECHNICAL INVESTIGATION OF BRIDGE SITES

    AND CONSTRUCTION MATERIAL SOURCES

    3.1 General

    Preliminary foundation investigations were conducted by the Design Consultant,Arab Consulting engineers (ACE), on the major river crossing sites to identify

    possible bearing layers and make recommendations on bearing capacity and

    determine the required depth of foundation for safely conveying the superstructure

    loads to the supporting strata. The field investigation and laboratory testing were

    conducted by the Central Materials Laboratory in 2003.

    The drilling investigations involved Standard Penetration Tests (SPT) and recovery of

    undisturbed and disturbed soil/silty sand samples for laboratory tests. However, depth

    of drilling was limited to top of hard stratum; no drilling was made in hard

    formations/rock strata. Thus, the strength and extent of hard formations were not

    adequately investigated. It seems that due to these uncertainties, a very low bearing

    capacity of 300KPa has been assumed for all hard formations including those where

    rock outcrops are evident.

    The design consultant recommended placing the foundation on replaced soil/selected

    granular fill material over river beds were exposed rock are encountered on the

    surface, for example Ayi, Yoyo, Apa and Lebijo crossing sites. This has a potential

    risk of scouring of the foundation soil; hence the review consultant recommends

    placing the footings on the rock strata where sound rock is encountered at shallow

    depths.

    3.2 Determination of Allowable Bearing Pressure for Bridge Foundations

    Most of the river crossings are constituted of alluvium deposit which is mainly clayey

    silty/sandy loam on top of weathered gneiss. Rocky outcrops are visible at some

    rivers.

    Allowable (presumptive) bearing pressure values are commonly assigned for the

    foundation bearing layers for foundation design purposes, taking their geology,

    compactness of alluvial deposits, and degree of weathering and consistency of rock

    outcrops, if any, into consideration as classified during the site investigation.

    The presumptive bearing pressure values recommended by different codes of

    practice, design manuals and reference texts for different type of foundation materialsand consistency are presented in Table 3.1 below.

    The presumptive bearing pressure values for various foundation materials have been

    adopted from the following code of standards, design manuals and reference texts:

    Foundation Analysis and Design, 5th Edition, McGraw-Hill Companies,

    Inc., 1996, by J. E. Bowles;

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    17/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-2

    SABA Engineering P.L.C

    Naval Facilities Engineering Command Design Manual (NAVFAC DM -

    7.02, sec.4, table1: on Foundations & Earth Structures, 1986);

    Overseas Road Note No. 9, Transport Research Laboratory (TRL), Design

    of Small Bridges; 2nd Edition, 2000.

    Table 3-1: Presumptive Allowable Pressures for Different Foundation Conditions

    *Depth of ground water is assumed to be not less than B below the

    base of foundation.

    The presumptive bearing pressures should be used with caution to allow for the

    uncertainties as determination of the actual extent and jointing requires drilling and

    coring.

    3.3 Foundation Recommendation

    The minimum depth below riverbed at which the bottom of abutment / pier will beplaced is governed by the maximum scour depth and the presence of a good bearing

    layer. An average depth of 2 meters below the lowest level of the river bed, is

    recommended for those crossing foundations composed of alluvial deposits, is

    recommended. For riverbanks and riverbeds composed of rock outcrops, a minimum

    depth of 0.5m in sound rock for keying (anchorage) purpose is recommended. The

    presumptive bearing pressures are used with caution assuming soft rock to allow for

    the uncertainties.

    Type of Bearing MaterialConsistency in

    place

    Recommended Allowable

    Bearing Pressure (KPa)

    ORN 9 NAVFAC Bowles

    Massive igneous and

    metamorphic rock (basalt,

    granite, gneiss)

    Hard and sound 10,000 7,600 9,600

    Foliated metamorphic rock

    and sedimentary rocks (un-

    weathered)

    Medium hard and

    sound4,000 3,300 -

    Weathered or broken bed rock

    of any kindSoft rock 1,500 1,000 1,400

    Gravel, gravel-sand mixtures,

    boulder gravel mixtures , and

    Sand with little gravel

    [Non-cohesive Soils]

    -Dense/very

    compact

    -Medium dense

    - Loose

    600

    500

    150

    600

    480

    280

    400*

    380*

    200

    Clay [Cohesive Soils]

    Silt

    -Hard

    -Stiff

    -Hard

    -Stiff

    200

    150

    200

    150

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    18/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-3

    SABA Engineering P.L.C

    The bearing pressure values recommended by the Design Consultant are generally

    conservative and need to be amended during construction. Investigation by core

    drilling (ASTM D2113) is neither feasible nor scope of this assignment; it is foreseen

    that verification/confirmatory investigations would be scheduled during construction,

    by means of rotary core drilling to a depth of at least 10m in soft /loose formation and

    at least 3 meters into solid rock. If the foundation conditions encountered during

    excavation are different from what has been revealed or assumed at design stage, the

    necessary modifications on the foundation design shall be made by the engineer.

    Pile load test shall also be conducted for bridges to be founded on pile foundations.

    Static Load Tests are performed to determine the ultimate failure load of a foundation

    pile and to determine the piles capability of supporting a load without excessive or

    continuous displacement. The purpose of such tests is to verify that the allowable

    loads used for the design of a pile are appropriate and that the installation procedure

    is satisfactory. The Pile Load Test shall be conducted in accordance with the

    procedures given in ASTM D1143.

    Hence pay items for the structures shall include the estimated costs for confirmatoryinvestigations by core drilling and for pile load testing in the BOQ.

    Tables 3.2 and 3.4 present the summary of Geotechnical Investigations conducted by

    the Design Consultant.

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    19/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-4

    SABA Engineering P.L.C

    Table 3-2: Review of Bridge Site Foundation Investigation and Presumptive Allowable

    Sr.

    No.

    River

    Name

    Route & DistrictGPS

    Coordinates

    Foundation Material Description

    1 Enayu-1Arua-Koboko-Orba

    (Arua)

    267125 E,

    342069 N

    Arua side: Sandy clay withfew gravels 0.7m 5.0m,

    SPT values: 7,8,9 at 3.0m

    -Hard pan/rock below 5.0m

    (refusal to penetration)

    Koboko side: Stiff Sandy c0.7m 5.0m,

    -Hard pan/rock below 5.0m

    2 Enve Arua-Koboko-Oraba(Arua)

    267147 E,

    348930 NDark brown silty clay on both abutments and the river bed

    3 Oluffe

    Arua-Koboko-Oraba(Arua)

    270332 E,

    352993 N

    Arua side: Firm Sandy clay ,SPT values: 3,2,4 at 1.5m and

    7,9,9 at 3.0m and Hard

    pan/weathered rock below5.0m

    Koboko side:Sandy clay 2.0 6.0m,

    Hard pan/rock below 6.0m

    4 AyiArua-Koboko-

    Orba(Arua)

    271353 E,

    360296 NRocky outcrops at both abutments and the river bed

    5 Kia-KiaArua-Wandi-Invep-Rhino-Camp

    Odupi Side: Grayish brownfirm clay up to 3.0m below

    which is a hard pan/rock

    Rhino Camp side: LooseBrown sand up to 9.0

    medium dense below 9.0m:

    N-values at 6.0m and 9.0m

    and 24, respectively.

    6Yoyo

    Arua-Koboko-Oraba

    (Arua)

    271976 E,

    368197 N

    Rock outcrops at both abutments, silty clay/sand

    7 Oru

    Arua-Koboko-Oraba

    (Arua)

    272522 E,

    369028 N 0.0 -4.0m: Loose Clayey sand and hard formation below 4.0

    8 Apa-1Arua-Koboko-Oraba

    (Arua)

    272909 E,

    375995 N

    0 4.0m Silty Sand on downstream

    and exposed rock on up stream,

    hard formation below 4.0m

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    20/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-5

    SABA Engineering P.L.C

    Sr.

    No.

    River

    NameRoute & District

    GPS

    CoordinatesFoundation Material Description

    9

    Ore

    Arua-Koboko-Oraba

    (Arua)

    272892 E,

    373464 NSilty Sand at both abutments

    10 KochiArua-Koboko-Oraba

    (Arua)

    273325 E,

    301108 NSilty sand and sandy Clay, up to

    11Debara

    Arua-Koboko-Oraba

    (Arua)

    265890 E,

    390867 NClayey silt alluvium, with some boulders exposed on down

    12Lebijo

    Arua Koboko-

    Yumbe (Arua)

    279881E,

    380785NExposed rock at abutments and pier position

    13 Ora-1(Lot 3)

    Nebbi-Akaba-Kucwiny-Wadela

    (Nebbi)

    321246E,300833N

    Arua side:Sandy clay : 0 3.0m,Below 3.0m hard pan

    Pakwach side:Stiff, black clay 0-2.0mGranular fill material,

    2.0 6.0m black sandy clay (N-v

    6.0m -14m (N-value=15) Black to gray

    14Cido(Lot 2)

    Nebbi-Goli-

    Japanziri-Erussi(Nebbi)

    262039E,284418N

    Goli side: Dense Sandyclay with gravel(0.0 3.0m),

    Hard pan below 3.0m

    Errusi side: Sandy clay with quartz(0.0 4.0m),Hard pan below 4.0m; i.e. refu

    penetration,

    N-value=45

    15

    Ora-2(Lot 3)

    Nebbi-Akaba-Kucwiny-

    Wadela(Nebbi)

    321235E,

    300861NDense Silty Sand at both abutments

    Note:All the bridges on table 3-2 are excluded under the revised work scope.

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    21/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-6

    SABA Engineering P.L.C

    Table 3-3: Review of Bridge Site Foundation Investigation and Presumptive Allowable Pressures as per t

    1,Lot 2 &Lot 3)

    Sr.

    No.

    River

    NameRoute & District

    GPS

    CoordinatesFoundation Material Description

    1Alla-1

    Arua-Inde-packwach

    (Arua)

    285641 E,

    321381 N

    Arua side:Brown to red silty

    clay/alluvium, with gravel.

    Hard pan at 2.0m

    Inde side:Light brown silty clay/allu

    2 Enayu-3 Arua-Ediofe (Arua)267062 E,

    333770 NReddish brown clayey Sand at both abutments

    3Nyagak-3

    Jqang-Okoro-

    Alyenda(Nebbi)

    266974E,

    270220NSilty Clay with few gravel at both abutments

    4Goli

    Nebbi-Goli

    Custom-Mahagi

    (Nebbi)

    280863E,

    263203N

    Goli customs side:Stiff to very stiff sandy clay with

    gravel,

    SPT-values: 5,6,7 at 3.0m and 12,11,9 at 6.0m,

    Hard pan (refusal to pen.) at 8.0m

    Mahagi side:Sandy clay with gravel,

    SPT-values: 3,4,5 at 3.0m

    Hard pan below 5.0m

    5Nyacara

    Nebbi-Erussi(Nebbi)

    274042E,287827N

    Sandy gravel with boulders

    6Pakwala

    Nebbi-Erussi

    (Nebbi)

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    22/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-7

    SABA Engineering P.L.C

    3.4 Investigation of Construction Material Sources

    3.4.1 General

    As part of the assignments in the Design Review Contract, the Consultant (SABA

    Eng.) has conducted field investigations and laboratory tests on Potential

    Construction Material sources; i.e. to enable verification of the findings during

    detailed engineering design. These included assessment of the Geotechnical

    Investigations report, and identification of construction material sources which were

    conducted by the Design Consultant (ACE).

    Based on the physical inspection of the potential construction material sources and

    results of laboratory tests conducted on some representative samples, the Design

    Review Consultant has evaluated the available design documents with regards to

    adequacy of the investigations and compliance of the values obtained with relevant

    standard specification requirements.

    A total of twelve (12) locations; i.e. 7 were potential stone sources, 4 sand sources,

    and 1 gravel source have been investigated by the Design Consultant. However, 5(five) of these sources are located near Lira and Soroti district HQs, which are very

    far from the project sites. The gravel source is located on the Lira Aloi road, 6.4Km

    from Lira town.

    3.4.2 Potential Quarry Stone Sources

    Coarse aggregate for concrete has to be strong, durable and must have a particle size

    distribution and particle shape which provide high mechanical stability.

    Potential sources of hard rock for production of crushed aggregate for concrete works

    were identified by the Design Consultant. Based on the test results report, conducted

    by the Central Materials Laboratory in June 2003, four (4) of the stone quarrysamples tested meet all the specification requirements for concrete aggregates. The

    following table has been taken directly from the Materials Investigation Report

    prepared by the Design Consultant:

    Table 3-4: Summary of Test Results on Rock Sources

    Sr.No.

    Rock SourceSpecificgravity(g/cc)

    WaterAbs.(%)

    Acv(%)

    Aiv(%)

    Tfv(KN)

    Laa(%)

    SSS(%)

    Bitumen Affinity

    1 Oparra (Arua) 2.5 0.1 29 30 150 28 0.3 Good

    2

    Over Senia

    River 2.6 0.8 19 23 180 16 0.5 Good3 Ngweny 2.6 0.2 16 11 200 18 0.3 Good

    4 Akia 2.7 0.1 19 19 170 22 0.4 Fair

    5 Ngetta 2.6 0.3 27 23 160 23 0.2 Good

    Spec. Limits >2.5 -25

    Max.

    26

    Max

    160

    Min.

    28

    Max

    12

    MaxGood

    ACV Aggregate Crushing Value, AIV-Aggregate Impact Value, TFV-10% Fines

    Value LAA Los Angeles Abrasion, SSS Sodium Sulfate Soundness

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    23/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-8

    SABA Engineering P.L.C

    From the test results, it can be concluded that with the exception of the rock source at

    Oparra (Arua) which has marginally weaker values, all the investigated rock sources

    fulfill the specification requirements.

    The Design Review Consultant has inspected these sources and identified additional

    potential sources. Photographs of the sites showing selected features of the source and

    location of each quarry stone from the bridge sites is also given. Under the newlyrevised scope of work all construction material indicated under lot 2 below can be

    considered for Lot 1 bridges. Similarly the material sites under lot 3 could be

    shared by lot 2 and lot 3 bridges.

    3.4.2.1 Stone Quarry Sites Proposed For Lot 1

    Priority 1 Lot 1

    Description

    Quarry Name Orawa

    Location 3.5 km from Arua TownRoad Name Arua Air field Road

    GPS Coordinates Elevation 1198

    Easting 36N 269053

    Northing 337155

    Estimated Quantity (Cum) >11,000 m3

    Overburden Varies from 0 -1.5m

    Access Existing and in good Condition

    Rock type Gneiss

    Degree of weathering Un weathered

    Distance from: Enyau 3 bridge 5 kmEnyau 1 bridge 7 km

    Enve bridge 14 km

    Oluffe bridge 21 k m

    Ayi bridge 31 km

    Alai-1 bridge 30.5 km

    Kia Kia bridge 70 km

    photos Orawa-Photo 1 through 6

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    24/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-9

    SABA Engineering P.L.C

    Orawa Site- Photo 3Orawa

    Orawa Site Photo 1 Orawa Site- Photo 2

    Orawa Site Photo 3 Orawa Site Photo 4

    Orawa Site Photo 5 Orawa Site Photo 6

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    25/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-10

    SABA Engineering P.L.C

    Description

    Quarry Name Arivu

    Location 14 km from Arua Town

    Road Name Arua Nebbi Road

    GPS Coordinates Elevation 1027

    Easting 36N 274510Northing 319462

    Estimated Quantity( Cum)

    >100,000 m3

    Overburden None

    Access Existing and in good Condition

    Rock type Gneiss

    Degree of weathering Minor surface disintegrations

    Distance from: Enyau 3 bridge 18.1km

    Enyau 1 bridge 23.5 km

    Enve bridge 31 kmOluffe bridge 37.2 k m

    Ayi bridge 47.7 km

    Alai-1 bridge 23 km

    Kia Kia bridge 88 km

    photos Arivu Site Photo 1 through 4

    Priority 2 Lot 1

    Arivu Site Photo 1 Arivu Site Photo 2

    Arivu Site Photo 3 Arivu Site Photo 4

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    26/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-11

    SABA Engineering P.L.C

    Priority 3 Lot 1

    DescriptionQuarry Name Ovisoni , adjacent to Ovisoni trading centre, LHSLocation 14 km from Arua TownRoad Name Arua Odiya -Vurra customs RoadGPS Coordinates Elevation 1337

    Easting 36N 264731Northing 321521

    Estimated Quantity(Cum)

    >1,000 m3

    Overburden 0.1-0.5mAccess Existing and in good ConditionRock type GneissDegree of weathering Un weathered

    Distance from; Enyau-3 bridge 18.1kmEnyau-1 bridge 23.5 km

    Enve bridge 31 km

    Oluffe bridge 37.2 k m

    Ayi bridge 47.7 km

    Alai-1 bridge 27km

    Kia Kia bridge 88 km

    photos Ovisoni Site- Photo 1 through 4

    Ovisoni Site- Photo 1 Ovisoni Site- Photo 2

    Ovisoni Site- Photo 3 Ovisoni Site- Photo 4

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    27/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-12

    SABA Engineering P.L.C

    3.4.2.2 Stone Quarry Sites Proposed For Lot 2

    Priority 1- Lot 2

    DescriptionQuarry Name Liru New proposal

    Location 14 km from koboko Town

    Road Name Koboko- liru RoadGPS Coordinates Elevation 1198

    Easting 36N 269053

    Northing 337155

    Estimated Quantity ( Cum) > 11,000 m3

    Overburden Varies from 0 -1.5m

    Access Existing and in good Condition

    Rock type Gneiss

    Degree of weathering Un weatheredDistance from: Yoyo bridge 26 km

    Oru bridge 25 km

    Ore bridge 20.3 km

    Apa bridge 18 k mKochi bridge 16 km

    Lebijo bridge 20.3 km

    Debara bridge 30 km

    photos Liru Site Photo 1 through 4

    Liru Site Photo 1 Liru Site Photo 2

    Liru Site Photo 3 Liru Site Photo 4

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    28/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-13

    SABA Engineering P.L.C

    3.4.2.3 Stone Quarry Sites Proposed For Lot 3

    Priority 1 Lot 3

    DescriptionQuarry Name Acwera Chinese QuarryLocation 12.3 km from NebbiTownRoad Name Nebbi- Pakwach Road

    GPS Coordinates Elevation 985Easting 36N 295868

    Northing 273361

    Estimated Quantity ( Cum) >10,000 m3Overburden Varies from 0 -1.5 mAccess Existing and in good ConditionRock type Granite

    Degree of weathering Un weathered

    Distance from: Nyacara bridge 13.3 kmPakwala bridge 15.3 km

    Goli bridge 26.3 km

    Cido bridge 29.3 k m

    Nyagak 3 bridge 51.3 kmOra-1 bridge 37 km

    Ora-2 bridge 37 km

    photos Acwera Chinese Qs Photo 1 through 4

    Acwera Chinese Qs Photo 1 Acwera Chinese Qs Photo 2

    Acwera Chinese Qs Photo 3 Acwera Chinese Qs Photo 4

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    29/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-14

    SABA Engineering P.L.C

    Priority 2 Lot 3

    DescriptionQuarry Name Ngweny kumiLocation 3.6 km from NebbiTownRoad Name Nebbi- Goli Road ( New road in angir village)GPS Coordinates Elevation 1097

    Easting 36N 285917Northing 271332

    Estimated Quantity ( Cum) >15,000 m3Overburden Varies -1m approxAccess Existing and in good ConditionRock type Gneiss

    Degree of weathering Un weathered bouldersDistance from; Nyacara bridge 2.6 km

    Pakwala bridge 0.7 km

    Goli bridge 12 km

    Cido bridge 15 k m

    Nyagak 3 bridge 42.6 km

    Ora-1 bridge 49.6 km

    Ora-2 bridge 49.6 km

    photos Ngweny k- Photo 1 through 4

    Ngweny kumi - Photo 1 Ngweny k - Photo 2

    Ngweny k - Photo 3 Ngweny k - Photo 4

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    30/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-15

    SABA Engineering P.L.C

    Priority 3 Lot 3

    Description

    Quarry Name Cananyira rock New proposal

    Location 1.2 km from NebbiTown

    Road Name Nebbi- cananyira RoadGPS Coordinates Elevation 986

    Easting 36N 288156

    Northing 273405

    Estimated Quantity ( Cum) >10,000 m3

    Overburden None

    Access Existing and in good Condition

    Rock type Gneiss

    Degree of weathering Un weathered

    Distance from; Nyacara bridge 1.5 km

    Pakwala bridge 4 kmGoli bridge 15 km

    Cido bridge 18k m

    Nyagak 3 bridge 40 km

    Ora-1 bridge 47.5 km

    Ora-2 bridge 47.5 km

    photos Cananyira Photo 1 through 2

    Cananyira Photo 1 Cananyira Photo 2

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    31/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-16

    SABA Engineering P.L.C

    Priority 4 Lot 3

    Description

    Quarry Name Angir rocks New proposal

    Location 1.6 km from NebbiTown

    Road Name Nebbi- Goli Road ( near Angir primary school)GPS Coordinates Elevation 1061

    Easting 36N 286537

    Northing 272491

    Estimated Quantity ( Cum) >5,000 m3

    Overburden None

    Access Available and in good Condition

    Rock type Gneiss

    Degree of weathering Un weathered

    Distance from: Nyacara bridge 0.6 km

    Pakwala bridge 2.4 km

    Goli bridge 12.4 km

    Cido bridge 15.4 k m

    Nyagak 3 bridge 40.6 km

    Ora-1 bridge 47.6 km

    Ora-2 bridge 47.6 km

    photos Angir Photo 1 through 2

    Angir Photo 1 Angir Photo 2

    3.4.2.4 Conclusions and Recommendations on Potential Stone Sources:

    Following the investigations conducted on the stone quarry sites proposed by the

    design consultant, the following is recommendable:

    For Lot 1: Stone aggregates from Orawa, Arivu or Ovisoni quarries are

    recommended.

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    32/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-17

    SABA Engineering P.L.C

    For Lot 2: The virgin rock at Liru (new proposal) is recommended as source

    of stone aggregates ( as per the revised scope of work this material site

    should be considered for lot 1 if the need arise)

    For Lot 3: Stone Quarries Acwera Chinese Quarry, Ngweny Kumi,

    Cananyira rock (new proposal) and Angir rock (new proposal) are

    recommended. ( as per the revised scope of work these material site shall beconsidered for both Lot 2 and Lot 3)

    Ngetta Hill Quarry (5.3 Km from Lira town, on Lira kitgum road), Akia Hill Quarry

    (5.9 km from Lira Town, on Lira Aloi road) and Ochuloi Quarry (19Km from

    Soroti town, on Soroti Lira road), are all located at distances that are not

    economically viable (more than 300Km far) relative to the project sites and are

    therefore not recommendable for use as aggregate sources.

    3.4.3 Potential Gravel (Muram) Sources

    Gravel sources were not identified by the Design Consultant, for all the three lots.

    Granular borrow materials are required for construction of embankments in approach

    roads and for backfilling behind abutments. The Design Review Consultant has

    identified a total of eleven (11) potential sources of gravel and collected

    representative samples for laboratory tests.

    It should, however, be noted that the construction material sources identified during

    this phase are by no means exhaustive. Additional sources should be further located

    and investigated by the contractors during construction.

    I. Location of Gravel Sources for Lot 1:

    Sample ID Location/nearest town Estimated Qty (m3)

    G1/Lot (1)11 Km from Arua town,

    Arua District, Kijomoro Subcounty,

    Near Loliragoro town

    85,000

    (200mx340mX1.3m)

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    33/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-18

    SABA Engineering P.L.C

    Gravel G1/Lot 1 (1) Gravel G1/Lot 1 (2)

    Sample ID Location/nearest town Estimated Qty (m3)

    G2/Lot (1)

    19 Km from Arua town,

    Arua District, Oleba Subcounty, 2Kmfrom Oleba Trading Center (ExistingPit)

    10,000

    (165mx70mX1.0m)

    G2/Lot 1 (1) Borrow area used by MoWT G2/Lot 1 (2) Borrow area used by MoWT

    Sample ID Location/nearest town Estimated Qty (m3)

    G3/Lot (1)29 Km from Arua town,

    Arua District, Oluffe Subcounty,

    near Ombere town ( Existing Pit)

    17,000

    (150mx100mX1.2m)

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    34/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-19

    SABA Engineering P.L.C

    G3/Lot 1 (1) G3/Lot 1 (2)

    SampleID

    Location/nearest town Estimated Qty (m3)

    GravelAruaTC

    8Km from Arua town, along Arua-AjonoRoad, Vura Subcounty, near Gil-gil

    Existing Borrow pit, 200m away fromCongo/Uganda Boarder (at Ajono village)

    100,000 (200mx500mx1m)

    Sample ID Location/nearest town Estimated Qty (m3)

    Gravel at Ala 1Bridge

    5Km from Arua town, along Arua Pakwach Road, Ajiya Subcounty,near Ajiya

    8,600

    (120mx60mx1.2m)

    II.Location of Gravel Sources for Lot 2:

    Sample ID Location/nearest town Estimated Qty (m3)

    G1/Lot 2

    5.5Km from Koboko town, along

    Arua Koboko Road, MidiaSubcounty, near Danya TC

    28,800(120mx240mx1.0m)

    Sample ID Location/nearest town Estimated Qty (m3)

    G2/Lot 2 8.0Km from Koboko town, alongArua Koboko Road, MidiaSubcounty, near Koboko

    74,880

    (320mx180mx1.3m)

    Note:The Bridges under lot 2 are discarded under the new scope of work. Thus

    these material locations can be considered for lot 1 bridges if the need arise,

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    35/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-20

    SABA Engineering P.L.C

    G2/Lot 2

    Sample ID Location/nearest town Estimated Qty (m3)

    G3/Lot 28.0Km from Koboko town, along

    Arua Koboko Road, MidiaSubcounty, near Koboko

    74,880

    (320mx180mx1.3m)

    G3/Lot 2 (a) G3/Lot 2 (b)

    G3/Lot 2 (a) G3/Lot 2 (b)

    G3/Lot 2 (1) G3/Lot 2 (2)

    Sample ID Location/nearest town Estimated Qty (m3)

    G4/Lot 2 8.0Km from Koboko town, alongArua Koboko Road, MidiaSubcounty, near Koboko

    74,880

    (320mx180mx1.3m)

    G4/Lot 2 (a) G4/Lot 2 (a)

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    36/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-21

    SABA Engineering P.L.C

    III. Location of Gravel Sources for Lot 3:

    Sample ID Location/nearest town Estimated Qty (m3)

    G1/Lot 35.0Km from Nebbi town, near Okeya Village,

    Used by MoWT

    > 10,000

    (150mx50mx1.5m)

    G1/Lot 3(a) G1/Lot 3(b)

    Sample ID Location/nearest town Estimated Qty (m3)

    G2/Lot 35.0Km from Nebbi town, near Okeya Village,

    Used by MoWT

    > 100,000

    (210mx300mx1.5m)

    G2/Lot 3 (a) G2/Lot 3 (b)

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    37/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-22

    SABA Engineering P.L.C

    Table 3-5: Summary of Laboratory test results of the potential gravel sources

    Sr. ID Location

    Grading, % passingSieves

    Laboratory Test Results

    2.0mm

    0.425mm

    0.075mm

    LL(%)

    PI(%)

    OMC(%)

    MDD(g/cc)

    BS Light

    CBR@ 95%MDD

    G1-Lot1

    11 Km from Arua town, Arua

    District, Kijomoro Subcounty,

    Near Loliragoro town

    39 30 20 46 25 11 2.02 26

    G2-Lot1

    19 Km from Arua town, Arua

    District, Oleba Subcounty,

    2Km from Oleba T C

    40 30 23 47 24 11 2.06 20

    G3-Lot129 Km from Arua town, AruaDistrict, Oluffe Subcounty,

    near Ombere town

    52 39 25 46 24 14 1.82 10

    ALA 1

    Bridge

    5Km from Arua town, along

    Arua Pakwach Road 38 30 22 50 25 12 1.86 22

    Arua TC

    8Km from Arua town, along

    Arua-Ajono Road, VuraSubcounty, near Gil-gil

    42 32 25 45 21 11 1.84 27

    G1-Lot25.5Km from Koboko town,

    along Arua Koboko Road43 33 25 44 24 10 1.96 20

    G2-Lot28.0Km from Koboko town,

    along Arua Koboko Road32 25 13 36 17 10 12.10 45

    G3-Lot28.0Km from Koboko town,along Arua Koboko Road

    50 34 21 45 22 10 1.90 18

    G4-Lot28.0Km from Koboko town,

    along Arua Koboko Road36 27 16 37 23 11 1.98 27

    G1-Lot35.0Km from Nebbi town, near

    Okeya Village44 33 22 40 22 10 2.03 15

    G2 - Lot3 5.0Km from Nebbi town 45 33 25 42 21 11 2.02 37

    Spec. requirements for Subbase to be usedfor approach road & backfill

    20%) strength but all have higher plasticity to be directly used as

    subbase. Thus, it is recommended stabilized the materials with lime (usually 3% to

    5% with the red clayey sandy lateritic gravels in Uganda), in order to improve both

    on their plasticity and CBR values to within the specification limits.

    Those sources with CBR values more than 10% and less than 20% can be used for

    improved subgrade layers and embankments for approach roads.

    3.4.4 Potential Sand Sources

    The Design Consultants have identified and tested three sources of sand. The sources

    were from Oreku on the Arua-Koboko Road, Ayi 1 on the Arua-Koboko Road, and

    Akaba which is 6.6Km from Nebbi town. The test results showed that had high clay

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    38/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-23

    SABA Engineering P.L.C

    contents and only the sand from Akaba fulfilled the specification limits for gradation.

    As a result, only the sand from Akaba was recommended to be used as a filter media

    (drainage layer) under high embankments and crushed fine was recommended

    instead.

    Efforts have been made by the Design Review consultant to exhaustively search for

    possible sources of sand in the project area. As a result, the following sand sourceshave been identified and laboratory tests conducted on them to assess their suitability

    for concrete and mortar works.

    I. Potential Sand Sources for Lot 1

    Sample ID Location/nearest town Estimated Qty (m3)

    S1/Lot 16.2Km from Arua town, from

    Enyayu River bridge, on Arua

    Koboko - Oraba Road

    3,000

    S1/Lot1 (1) S1/Lot1 (2)

    S1/Lot1 (3) S1/Lot1 (4)

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    39/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-24

    SABA Engineering P.L.C

    Sample ID Location/nearest town Estimated Qty (m3)

    S2/Lot 117Km from Arua town, near Kijomoro

    town, from Enve river bridge, on Arua

    Koboko - Oraba Road

    2,000

    S2/Lot 1(1) S2/Lot 1(2)

    Sample ID Location/nearest town Estimated Qty (m3)

    S3/Lot 133.7Km from Arua town, near

    Nyoro town, from Ayi river

    bridge, on Arua Koboko - Oraba

    Road

    2,000

    S3/Lot 1 (1) S3/Lot 1 (2)

    Sample ID Location/nearest town Estimated Qty (m3)

    ALA River Sand17Km from Arua town, Arivu

    Subcounty, from ALA river

    bridge

    2,000

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    40/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-25

    SABA Engineering P.L.C

    II.Potential Sand Sources for Lot 2

    Sample ID Location/nearest town Estimated Qty (m3)

    S1/Lot2Near Oleba town, from Oru 1

    river bridge, on Arua Koboko

    Oraba Road

    1,000

    S1/Lot2 (1) S1/Lot2 (2)

    Sample ID Location/nearest town Estimated Qty (m3)

    S2/Lot2

    8.2Km from Koboko town, from

    Lebijo river bridge, on Koboko

    Yumbe Road, Appx. 2.1Km from

    the Road

    4,000

    S2/Lot2 (1) S2/Lot2 (2)

    Sample ID Location/nearest town Estimated Qty (m3)S3/Lot 2 Otumbari Subcounty, from Oru

    river bridge,

    3,000

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    41/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-26

    SABA Engineering P.L.C

    S3/Lot 2 (1) S3/Lot 2 (2)

    III. Potential Sand Sources for Lot 3

    Sample ID Location/nearest town Estimated Qty (m3)

    S1/Lot 3

    9.0Km from Nebbi town, from

    Acwera river bridge, along NebbiWadi Lai district rural road,

    2Km off the highway

    2,500

    S1/Lot 3 (1) S1/Lot 3 (2)

    S1/Lot 3 (C)

    S1/Lot 3 (3) S1/Lot 3 (4)

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    42/171

    Construction of Bridges in North West Uganda Design Review Report

    Uganda National Roads Authority 3-27

    SABA Engineering P.L.C

    Sample ID Location/nearest town Estimated Qty (m3)

    S2/Lot 35.0Km from Nebbi town, from

    Akaba river bridge, along Nebbi

    Pakwach Road

    2,500

    S2/Lot 3 (1) S2/Lot 3 (2)

    S2/Lot 3 (3) S2/Lot 3 (4)

    Sample ID Location/nearest town Estimated Qty (m3)

    S3/Lot 330Km from Nebbi town, from

    Nam-Rwadho river bridge, along

    Nebbi Pakwach Road

    4,000

    S3/Lot 3 (1) S3/Lot 3 (2)

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    43/171

    Construction of Bridges in North West Uganda Design Revie

    Uganda National Roads Authority 3-28

    SABA Engineering P.L.C

    Table 3-6: Summary of Laboratory test results of the potential Sand sources

    From the laboratory test results, it can be seen that most of the identified sources can be used with some treatm

    grading requirements or by washing to remove clay lumps and minor organics contents.

    Sr.No.

    LocationOf Sand

    Sieve Analysis, % passing, mmSilt and

    ClayContent

    (%)

    Compress

    Strength Cement Mo

    (7 days, MP10.0 5.0 2.36 1.18 0.60 0.30 0.15

    1 S1/Lot 1 100 99 94 83 51 8 2 1.8 30

    2 S2/Lot 1 100 99 92 38 28 3.8 32

    3 S3/Lot 1 97 94 89 73 34 6 4 3.4 28

    4 Lot 1- C 99 98 97 90 69 10 4 3.2 30

    5 S1/Lot 2 100 98 94 70 13 5 4.2 29

    6 S2/Lot 2 100 98 90 65 13 3 2.0 35

    7 S3/Lot 2 100 99 97 87 51 14 4 1.6 31

    8 S1/Lot 3 100 99 95 79 38 8 3 2.0 30 9 S2/Lot 3 100 97 88 66 34 6 2 1.6 29

    10 S3/Lot 3 98 95 84 65 39 16 11 9.6 35

    11 ALA River Sand 96 94 91 81 56 14 3 2.4 32

    Ugandan Grading

    Spec. I100 90-100 60-95 30-70 15-34 5-20 0-10 6% Max. 28 Min

    II 100 90-100 75-100 55-90 35-59 8-30 0-10

    III 100 90-100 85-100 75-100 60-79 12-40 0-10

    IV 100 95-100 95-100 90-100 80-100 15-50 0-15

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    44/171

    Construction of Bridges in North West Uganda

    Design Review Report

    Uganda National Roads Authority 4-1

    SABA Engineering P.L.C

    4 HYDROLOGICAL and HYDRAULIC STUDY REVIEW

    4.1 Background

    Highway drainage is an important consideration in the design of many projects. The

    term drainage is defined in several different ways, including the process of removing

    surplus groundwater or surface waters by artificial means, the manner in which the

    waters of an area are removed, and the area from which waters are drained. A project

    may alter the existing drainage. When this occurs, drainage features should be

    provided which protect the highway, adjacent landowners, and the traveling public

    from water, while maintaining water quality and protecting other environmental

    resources.

    Bridge is a structure which provides passage facilities over an obstacle without

    closing the water way underneath. In a highway project the obstacle is usually of

    valley water way that will be passed by the provision of a structure which can safely

    pass both motorized and non motorized transport facilities without causing any

    natural flow system disturbance on its underside zone.

    The design of a bridge across a stream demands a special attention towards route

    location, potential traffic flow and structural and foundation details, but also to the

    characteristics of the stream beneath the structure. Collecting information and data

    regarding to stream channel stability, anticipated flood, and sediment discharge and

    scour potential is a basic and primary task prior to a detailed hydraulic design work of

    a bridge.

    A bridge must not only be hydraulically efficient, but also be consistent with the

    importance of the road, safety, initial cost, aesthetics, environmental considerations,

    maintenance and legal responsibilities. Highway bridge hydraulic design comprisestwo major components:

    1. Hydrological study

    2. Hydraulic Analysis

    Hydrology/Hydraulics design review of 21 bridges where the recently selected 10

    bridges contained on it is conducted by undertaking a detailed hydrological and

    hydraulic investigation at sample bridges and/or culverts representing the overall

    design approach together with physical hydrologic survey data of the existing

    structures.

    4.2 Objective

    The review has the following objectives:

    Undertaking a detailed hydrological and hydraulic investigation at selected

    sample bridges and culverts to examine and to compare the overall bridge/culvert

    hydrological and hydraulic design of the consultant.

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    45/171

    Construction of Bridges in North West Uganda

    Design Review Report

    Uganda National Roads Authority 4-2

    SABA Engineering P.L.C

    Estimating maximum probable flood through flood mark physical identification

    and local people consultation and compare it with the design consultant remarks.

    Examining the existing structure flood accommodation capacity or hydraulic

    sufficiency or insufficiency in relation to the proposed once.

    River bank condition assessment to visualize the extent of erosion in and around

    the bridge sites and to identify the necessity of protection works

    To check the design consultant remedial recommendations in relation to existing

    and proposed structure.

    4.3 Hydrology

    Hydrology in a highway development deals with estimating flood magnitudes as the

    result of precipitation (usually the peak discharge) .The necessity and extent of the

    hydrologic analysis to be performed is based on the type of project, road design

    standard and type of structure that will be laid in a highway.

    An overview of the process of performing a hydrologic analysis, including criteria

    (design flood frequency) and methodologies for determining the peak discharge. The

    overall process which should be used to conduct the hydrologic analysis for a given

    project is listed below:

    Conduct preliminary assessment at the office level.

    Take an initial field trip to the project site.

    Select a methodology and design flood frequency, and calculate the design

    discharge with some methods.

    Take a final field trip to verify the analysis/design and to recheck flood damage

    potential.

    4.4 Data Collection

    The hydrological analysis has been made using available digital elevation models

    (DEM) and aerial photographs together with keen physical hydrologic survey made at

    each bridge/culvert site. Additional hydrological and geological information have

    been gathered by consulting local residents and from concerned bodies around the

    project area.

    4.4.1 DEM and Aerial Photographs

    Available 90m resolution digital elevation model (DEM) showing all the drainage

    pattern to the required level is used as an input to delineate bridge catchment area at

    road. Widely used public domain GIS softwares (ARC View 3.3, WMS 8.1 and

    ILWIS) are used for DEM hydro processing purpose at selected bridges watershedareas thereby determining catchment characteristics such as area, slope, stream length

    etc.

    4.5 Drainage Characteristics, Geology and Topography

    The overall watershed areas draining towards each bridge outlet point comprises a

    number of minor and major tributaries originating from most remote and/or nearby

    hillsides or dividing lines depending upon the nature of the stream and topographic

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    46/171

    Construction of Bridges in North West Uganda

    Design Review Report

    Uganda National Roads Authority 4-3

    SABA Engineering P.L.C

    conditions. Dissected plateau with a number of narrow valleys and active flow nature

    is the dominant surface drainage pattern on the area. Most streams are perennial in its

    very nature but others are intermittent streams flowing only during rainy seasons of

    the year. Dense vegetation cover (Dry combretum and grass) with some cultivation is

    the major land use cover forms where most watershed areas are characterized. Sandy

    loam, lithosols and sandy clay loam are the main soil types covering the catchment

    area. The catchment area is also dominated by quartzo-feldspathic genesis,

    magmatites of Aruan Complex, charnockites, enderbites, hypersthenes genesis and

    basic granulites geological forms.

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    47/171

    Construction of Bridges in North West Uganda Design Revie

    Uganda National Roads Authority 4-4

    SABA Engineering P.L.C

    Table 4-1: Bridge catchment area physiographic description (As per the new scope)

    S/NBridge

    Name

    Route & District Flow directionStream

    nature

    Topography Catchm

    1 Alla

    Arua-Inde-

    packwach(Arua)

    R to L (from Arua

    to Inde) perennial Relatively Rolling terrain

    Originates fro

    neighborhood

    highlands

    2 Enayu-3 Arua-Ediofe (Arua)

    L to R (from Arua

    to Ediofe) perennial Relatively steep terrain

    Originates fro

    neighborhood

    highlands

    3 Nyagak-3

    Jqang-Okoro-

    Alyenda(Nebbi)

    L to R (from

    Okoro to

    Alyenda) perennial

    Slightly steep

    topographic condition

    Originates fro

    neighborhood

    highlands

    4 Goli

    Nebbi-Goli

    Custom(Nebbi)

    R to L (from

    Nebbi to Goli)

    perennial Moderately rolling Originates fro

    neighborhood

    highlands

    5 Nyacara

    Nebbi-

    Erussi(Nebbi)

    L to R (from

    Nebbi town to

    Pakwala) perennial Rolling terrain

    Originates fro

    nearby highla

    6 Pakwala

    Nebbi-

    Erussi(Nebbi) - perennial

    Relatively rolling to hilly

    terrain

    Originates fro

    nearby highla

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    48/171

    Construction of Bridges in North West Uganda

    Design Review Report

    Uganda National Roads Authority 4-5

    SABA Engineering P.L.C

    4.6 Climate

    The distinction in climate characteristics mainly caused by altitude differences and its

    location where rainfall on the area is highly influenced by Inter Tropical Convergence

    Zone (ITCZ).

    Watershed areas of twenty one bridges mainly falls under the same climatic

    zonation with an expected mean annual rainfall ranging from 1000-1500mm and

    mean annual temperature in between 25 and 30 0C .

    4.7 Peak Discharge Estimation

    There are several methods to compute peak discharge, among these methods the most

    commonly used once are stated below:

    1. Rational Method.

    2. Modified Soil Cover Complex Method, SCS (plotting a hydrograph).

    3. Regression Equations

    4. Historical Data statistical analysis.

    5. TRRL Model (East African Flood Model)

    4.7.1 Rational Method

    Rational method is recommended to determine the peak discharge, or runoff rate,

    from drainage areas up to 80 ha and its application requires appropriate intensity data.

    Assumptions under Rational Method are:

    Peak discharge occurs when all of the drainage area is contributing,

    A storm that has duration equal to the time of concentration (Tc) produces the highest

    peak discharge for the selected frequency,

    Intensity is uniform over a duration of time equal to or greater than the Tc, and

    The frequency of the peak flow is equal to the frequency of the intensity.

    The rational method formula is:

    Q = kCiA, where:

    Q = peak discharge or rate of runoff (m3/s)

    k = 0.00278 (m 3/s) hr / (ha C mm)

    C = runoff coefficient

    i = intensity (mm/hr)

    A = drainage area (ha)

  • 7/30/2019 Design Review Report for Bridges in Northern Uganda

    49/171

    Construction of Bridges in North West Uganda

    Design Review Report

    Uganda National Roads Authority 4-6

    SABA Engineering P.L.C

    4.7.2 SCS Method

    A relationship between accumulated rainfall and accumulated runoff was derived by

    SCS from experimental plots for numerous hydrologic and vegetative cover

    conditions. Data for land-treatment measures, such as contouring and terracing, from

    experimental catchment areas were included. The equation was developed mainly for

    small catchment areas for which daily rainfall and catchment area data are ordinarily

    available. It was developed from recorded storm data that included total amount of

    rainfall in a calendar day but not its distribution with respect to time. The SCS runoff

    equation is therefore a method of estimating direct runoff from 24-hour or 1-day

    storm rainfall. The equation is:

    SPforSP

    SPQ 2.0

    8.0

    )2.0( 2

    -------------------------------eq. (4.1)

    Where:Q Effective accumulated rainfall depth (mm)

    P Gross accumulated rainfall depth (mm)

    S Potential maximum retention (mm)

    The potential maximum retention S has been expressed in terms of the Curve Number

    CN in order to make the operations of interpolating, and weighting more nearly

    linear. This relationship is:

    25425400

    CN

    S ---------------------------------------eq. (4.2)

    CN refers the runoff response characteristics of the watershed area.

    Using the equation of the area of the triangle and expressing the volume in m3, the

    peak discharge qp of the triangular unit hydrograph is given by the equation shown

    below: