Design and Implementation of Large Wood Structures at Twelvemile Creek Prince of Wales Island...
-
Upload
jacob-owen -
Category
Documents
-
view
217 -
download
0
description
Transcript of Design and Implementation of Large Wood Structures at Twelvemile Creek Prince of Wales Island...
Design and Implementation of
Large Wood Structures at
Twelvemile Creek
Prince of Wales Island
Tongass National ForestThe Nature ConservancyTEAMS Enterprise Unit
Prepared By:Sean ClaffeyNovember 2013
recap…
Habitat Attribute Percentile FP3 FP4 FP5*
Process Group
FP CCAFP5
LowerFP5
Upper FP4 Rating
WD
25 10.9 18.5 23.1 16.5 23 Fair _low
25-50 Good 50 14.9 20.2 27.2 19.3
50-75 33 Fair_high 75 19 32.8 43.6 26.7 35 Poor
TKWD/m
25 0.10 0.06 0.02 0.04 0.02 0.02 0.02 Poor 25-50 Fair
50 0.17 0.11 0.03 0.10 50-75 Good
75 0.25 0.15 0.08 0.15 Excellent
Pools/km
25 30 30 10 30 Poor 25-50 11 11 Fair 50 40 40 20 45 50-75 43 Good
75 70 60 25 70 Excellent * low sample size (n<10)
Pool Size (rpd/avbfd)
25 0.67 0.68 0.58 0.65 Poor 25-50 Fair
50 1.14 0.84 0.65 0.84 50-75 0.93 0.91 Good
75 1.58 0.94 0.95 0.95 2.06 Excellent
RPD/CBW
25 0.06 0.04 0.03 0.04 0.04 Poor 25-50 Fair
50 0.07 0.04 0.03 0.05 50-75 Good
75 0.09 0.05 0.03 0.06 0.06 0.08 Excellent
Priority Watershed
Habitat Surveys and Data collection
Data guided our efforts
to evaluate condition of watershed
Treatment Reach
Twelvemile vs. Unmanaged Reference StreamsData comparison defined our restoration objectives.
Objectives• Objectives based on reference unmanaged floodplain channels.
Design Concepts• Concepts based on the parameters provided by the Twelvemile
references.
For Example: Reference pools were formed by LWD creating a constriction at the pool head. Either spanning or on one or both sides of the channel.Pool head width (31’-38’) and bankfull width (70’-80’).
Using LWD structures to restore Hydrological Function.
Used Data to define our objectives
Objective Design Concept (How can we use wood)
A) Increase large wood & key wood Add wood. Use to meet other objectives
B) Maintain or increase pool frequency
• Use wood to constrict pool head, • stabilize outside bank of an accelerated meander, • supplement existing pool forming woody debris.
C) Decrease width/depth ratio • Reduce rapid bank erosion by adding structure to
unstable banks,• Encourage or increase lateral/point bar development
D) Improve pool quality • Add complexity and cover to pools, • Increase scour potential.
E) Improve side water habitat connections and/or quality.
• Use wood to maintain or improve inflow,• Use wood to backwater outflow.
Energy!
Rapidly eroding bankExisting pool
Design Concept Site Selection
Shallow, clean pool
Objective
Flow
Flow
Energy!Outside Meander Bend
Low bar, wide cross section with uniform shallow depth
Intense Focus of Energy dissipation caused by the wood.
riffle
Site selection
• Site selection was determined by the channel.o Was not new channel construction or realignment
o Multiple objectives could be met at each site and each structure has multiple objectives.
o This was by design. Each LWD structure was strategically placed according to the existing scour and deposition features, intervals and cross sectional area.
Didn’t force anything.
Diversity, mobile debris source
Enhance scourOverall channel stability, riparian health
Enhance depositional feature to constrict local channel widths
Bank Stabilization, Habitat
• Sites Selected
Design for Site Specific Objectives• What type of structure will accomplish objective/s– Formidable Multi-Faceted (FMF)– Bar buddy– Spanning member – Floodplain– Single piece or small cluster
Often a combination of the above. One structure may be in response to another.
Design Concept Site Selection
Site Design
Objective Design Concept Site Design (Structure type)
A) Increase large wood & key wood
Add wood. Use to meet other objectives ALL
B) Maintain or increase pool frequency
• Use wood to constrict pool head, • stabilize outside bank of an
accelerated meander, • supplement existing pool forming
woody debris.
FMF, Bar buddy, Spanning
C) Decrease width/depth ratio
• Reduce rapid bank erosion by adding structure to unstable banks,
• Encourage or increase lateral/point bar development
FMF, Bar Buddy
D) Improve pool quality
• Add complexity and cover to pools, • Increase scour potential.
Convenient by product of all structures. Spanning
E) Improve side water habitat connections and/or quality.
• Use wood to maintain or improve inflow,
• Use wood to backwater outflow.Can be incorporated into all of the
above.
Site Selection
Site Design
Permitting
Contracting
Implementation
Title 16
404
Wood Collection About 85% of project used ~50 yr old young
growth. Spread collection out in “gaps”.
Rootwad harvest against existing roads.
Getting the wood to the creek...
Flying Trees
Helicopter decked trees on bars and adjacent floodplain in creek.
Equipment to the creek• Six points of access. • All off of old roads adjacent to creek. Some required
a short trail from the road surface to the creek.From Phase 1
• Equipment was power washed before entering the stream• Vegetable based hydraulic fluid replaced petroleum products.• Oil absorbent booms were deployed downstream of worksite in event of a spill.
• Work Completed at low flow• Travel concentrated to riffles and bars • Fish and game provided the timing window of July 5th - August 5th
• Duration in channel- For example Phase II - there were ~300 trees placed with two excavators in about a mile reach. Only 4 days in the channel.
•
Objective Design Concept
A) Increase large wood & key wood
Add wood. Use to meet other objectives
B) Maintain or increase pool frequency
• Use wood to constrict pool head, • stabilize outside bank of meander, • supplement existing pool forming
woody debris.
C) Decrease width/depth ratio
• Reduce rapid bank erosion by adding structure to unstable banks,
• Encourage or increase lateral/point bar development
D) Improve pool quality
• Add complexity and cover to pools, • Increase scour potential.
E) Improve side water habitat connections and/or quality.
• Use wood to maintain or improve inflow,
• Use wood to backwater outflow.
Instream Placement
HOW
Example Site #XX
Low bar. Wide uniform shallow cross section
Poorly developed shallow pool
Pool head 50+ feet
Site Design (Structure type)
ALL
FMF, Bar buddy, Spanning
FMF, Bar Buddy
Convenient by product of all structures. Spanning
Can be incorporated into all of the above.
We are going to build• FMF, • Bar Buddy, • and Spanning member.
WITH
Placement
• FMF first• Set the base
Rootwad
Spanning member
Bar Buddy
Formidable Multi-Faceted Structure
Spanner
Flow
Flow
Before, June 1013
After, July 2013
Example Site #XX
Site #XX after its first good flow event…
FMF
Improved Scour
Flow
September 2013
Notes on implementation…
• Notice there was no cable or large rock used. • Structures are meant to stay dynamic.
• They will shift and individual pieces may move between structures.
• Design also had to be dynamic• Built to field conditions at each site
• 100% on-site supervision• Great operators
Site Design
PermittingContracting
Implementation
Design Concept Site SelectionObjectives(Parameters)(DATA)
Monitor
Notes on implementation…
Thank you to: Southeast Roadbuilders,S&S General Contractors,
Columbia Helicopters
&
The Nature ConservancyAlaska Sustainable Salmon Fund
National Forest FoundationNational Fish & Wildlife Foundation
END