Department of Transportation -...

13
Department of Transportation Office of Project Development 700 E Broadway Avenue Pierre, South Dakota 57501-2586 605/773-3268 FAX: 605/773-2614 October 17, 2017 ADDENDUM NO. 1 RE: Item #1, October 18, 2017 Letting - P 0231(12)80, PCN 02R5, Pennington County - Urban Grading, Roadway Lighting, Storm Sewer, Curb & Gutter, Sidewalk, Traffic Signals, Str. Repair, Pedestrian Crossing & PCC Surfacing TO WHOM IT MAY CONCERN: The following addenda to the plans shall be inserted and made a part of your proposal for the referenced project. SPECIAL PROVISIONS: NO CHANGE BID ITEM FILE: Bidders must log in to retrieve the addendum bid item file that must be loaded into the SDEBS to incorporate the revisions listed here. Bid Items were added: Bid Item 620E1030 “3 Post Panel” Quantities for Bid Items were changed: Bid Item 110E0300 “Remove Concrete Curb and/or Gutter” changed from 110 to 7,507 Ft Bid Item 110E1010 “Remove Asphalt Concrete Pavement” changed from 3,933.0 to 9,873.1 SqYd Bid Item 110E1100 “Remove Concrete Pavement” changed from 53,597.2 to 44,079.6 SqYd Bid Item 634E4050 “5 Section Vehicle Signal Head” from 8 to 10 Each Bid Items were removed: Bid Item 734E0170 “Temporary Sediment Barrier” PLANS: Please destroy sheets A1-A3, B2, B4, B5, D2, and L2 and replace with the enclosed sheets, dated 10/16/17 and 10/17/17. Sheets B117A and B117B were added. Sheet A1: Grading – Section B Bid Items were added: Bid Item 620E1030 “3 Post Panel” Quantities for Bid Items were changed: Bid Item 110E0300 “Remove Concrete Curb and/or Gutter” changed from 110 to 7,507 Ft Bid Item 110E1010 “Remove Asphalt Concrete Pavement” changed from 3,672.0 to 9,612.1 SqYd Bid Item 110E1100 “Remove Concrete Pavement” changed from 53,597.2 to 44,079.6 SqYd Connecting South Dakota and the Nation

Transcript of Department of Transportation -...

Page 1: Department of Transportation - apps.sd.govapps.sd.gov/HC65C2C/EBS/lettings/Addendums/02R5Addendum_1.pdf · Department of Transportation ... The existing 8.5 inch P.C.C. Pavement is

Department of Transportation Office of Project Development 700 E Broadway Avenue Pierre, South Dakota 57501-2586 605/773-3268 FAX: 605/773-2614

October 17, 2017 ADDENDUM NO. 1

RE: Item #1, October 18, 2017 Letting - P 0231(12)80, PCN 02R5, Pennington County - Urban Grading, Roadway Lighting, Storm Sewer, Curb & Gutter, Sidewalk, Traffic Signals, Str. Repair, Pedestrian Crossing & PCC Surfacing

TO WHOM IT MAY CONCERN: The following addenda to the plans shall be inserted and made a part of your proposal for the referenced project. SPECIAL PROVISIONS: NO CHANGE

BID ITEM FILE: Bidders must log in to retrieve the addendum bid item file that must be loaded into the SDEBS

to incorporate the revisions listed here. Bid Items were added:

Bid Item 620E1030 “3 Post Panel” Quantities for Bid Items were changed: Bid Item 110E0300 “Remove Concrete Curb and/or Gutter” changed from

110 to 7,507 Ft Bid Item 110E1010 “Remove Asphalt Concrete Pavement” changed from

3,933.0 to 9,873.1 SqYd Bid Item 110E1100 “Remove Concrete Pavement” changed from 53,597.2 to

44,079.6 SqYd Bid Item 634E4050 “5 Section Vehicle Signal Head” from 8 to 10 Each Bid Items were removed: Bid Item 734E0170 “Temporary Sediment Barrier”

PLANS: Please destroy sheets A1-A3, B2, B4, B5, D2, and L2 and replace with the enclosed

sheets, dated 10/16/17 and 10/17/17. Sheets B117A and B117B were added.

Sheet A1: Grading – Section B Bid Items were added:

Bid Item 620E1030 “3 Post Panel” Quantities for Bid Items were changed:

Bid Item 110E0300 “Remove Concrete Curb and/or Gutter” changed from 110 to 7,507 Ft

Bid Item 110E1010 “Remove Asphalt Concrete Pavement” changed from 3,672.0 to 9,612.1 SqYd

Bid Item 110E1100 “Remove Concrete Pavement” changed from 53,597.2 to 44,079.6 SqYd

Connecting South Dakota and the Nation

Page 2: Department of Transportation - apps.sd.govapps.sd.gov/HC65C2C/EBS/lettings/Addendums/02R5Addendum_1.pdf · Department of Transportation ... The existing 8.5 inch P.C.C. Pavement is

Sheet A2: Erosion and Sediment Control – Section D

Bid Items were removed: Bid Item 734E0170 “Temporary Sediment Barrier”

Sheet A3: Signals and Lighting – Section L

Quantities for Bid Items were changed: Bid Item 634E4050 “5 Section Vehicle Signal Head” from 8 to 10 Each

Sheet B2: Grading – Section B

Bid Items were added: Bid Item 620E1030 “3 Post Panel” Quantities for Bid Items were changed:

Bid Item 110E0300 “Remove Concrete Curb and/or Gutter” changed from 110 to 7,507 Ft

Bid Item 110E1010 “Remove Asphalt Concrete Pavement” changed from 3,672.0 to 9,612.1 SqYd

Bid Item 110E1100 “Remove Concrete Pavement” changed from 53,597.2 to 44,079.6 SqYd

Sheet B4: TABLE OF CONCRETE PAVEMENT REMOVAL and TABLE OF

ASPHALT CONCRETE REMOVAL were revised. TABLE OF CONCRETE MEDIAN PAVEMENT REMOVAL was moved to

Sheet B5.

Sheet B5: TABLE OF ASPHALT CONCRETE CURB REMOVAL and TABLE OF CONCRETE CURB REMOVAL were moved to Sheet B4.

TABLE OF CONCRETE CURB AND GUTTER REMOVAL was revised. Sheet B30: A 3 Post Panel was added in the plan view at 25+26.07 L and at

27+09.58 L. Sheets B117A & B117B: Standard Plate 620.03 was added. Sheet D2: Erosion and Sediment Control – Section D

Bid Items were removed: Bid Item 734E0170 “Temporary Sediment Barrier”

Sheet L2: Signals and Lighting – Section L

Quantities for Bid Items were changed: Bid Item 634E4050 “5 Section Vehicle Signal Head” from 8 to 10 Each

Sincerely, Sam Weisgram Engineering Supervisor SW/cj CC: Todd Seaman, Rapid City Region Engineer Mike Carlson, Rapid City Area Engineer

Page 3: Department of Transportation - apps.sd.govapps.sd.gov/HC65C2C/EBS/lettings/Addendums/02R5Addendum_1.pdf · Department of Transportation ... The existing 8.5 inch P.C.C. Pavement is

ESTIMATE OF QUANTITIES AND ENVIRONMENTAL COMMITMENTS PROJECT STATE OF SOUTH

DAKOTA P 0231(12)80 SHEET

A1 A5

TOTAL SHEETS

Grading – Section B

Revised By: RS 10/16/2017

INDEX OF SHEETS A1 to A3 Estimate of Quantities for Sections B,C,D,E, F, M,

and S A4 to A5 Environmental Commitments

Page 4: Department of Transportation - apps.sd.govapps.sd.gov/HC65C2C/EBS/lettings/Addendums/02R5Addendum_1.pdf · Department of Transportation ... The existing 8.5 inch P.C.C. Pavement is

ESTIMATE OF QUANTITIES AND ENVIRONMENTAL COMMITMENTS PROJECT STATE OF SOUTH

DAKOTA P 0231(12)80 SHEET

A2 A5

TOTAL SHEETS

Traffic Control – Section C

Erosion and Sediment Control – Section D

Structure – Section E

Revised 10/16/2017

Surfacing – Section F

Page 5: Department of Transportation - apps.sd.govapps.sd.gov/HC65C2C/EBS/lettings/Addendums/02R5Addendum_1.pdf · Department of Transportation ... The existing 8.5 inch P.C.C. Pavement is

ESTIMATE OF QUANTITIES AND ENVIRONMENTAL COMMITMENTS PROJECT STATE OF SOUTH

DAKOTA P 0231(12)80 SHEET

A3 A5

TOTAL SHEETS

Signals and Lighting – Section L

Pavement Marking – Section M

Permanent Signing – Section S

Revised By: RS 10/16/2017

Page 6: Department of Transportation - apps.sd.govapps.sd.gov/HC65C2C/EBS/lettings/Addendums/02R5Addendum_1.pdf · Department of Transportation ... The existing 8.5 inch P.C.C. Pavement is

Revised By RS: 10/172017 PROJECT STATE OF

SOUTH DAKOTA P 0231(12)80

SHEET

B2 B117

TOTAL SHEETS

SECTION B ESTIMATE OF QUANTITIES

GRADING OPERATIONS Water for Embankment is estimated at the rate of 10 gallons of water per cubic yard of Embankment minus Waste. The estimated cubic yards of excavation and/or embankment required to construct outlet ditches, side streets, and driveways are included in the earthwork balance notes on the profile sheets. Special ditch grades and other sections of the roadway different than the typical section(s) shall be constructed to the limits shown on the cross sections. If significant changes to the cross sections are necessary during construction, the Engineer shall contact the Designer for the proposed change. Generally, all shallow inlet and outlet ditches as noted on the plan sheets shall be cut with a 40-foot wide bottom with 5:1 backslopes. However, the Engineer may direct the Contractor to adjust the ditch width for proper alignment with the downstream drainage. A copy of the soils profile is available for review at the Rapid City Region and Rapid City Area offices. Temporary fence and/or permanent fence shall be placed ahead of the grading operation unless directed by the Engineer.

Page 7: Department of Transportation - apps.sd.govapps.sd.gov/HC65C2C/EBS/lettings/Addendums/02R5Addendum_1.pdf · Department of Transportation ... The existing 8.5 inch P.C.C. Pavement is

Revised By RS: 10/172017 PROJECT STATE OF

SOUTH DAKOTA P 0231(12)80

SHEET

B4 B117

TOTAL SHEETS

TABLE OF PIPE CULVERT UNDERCUTTING

Pipe Diameter

(In)

Round Pipe Undercut Rate

for 1’ Depth (CuYd/Ft)

Arch Pipe Undercut Rate

for 1’ Depth (CuYd/Ft)

24 0.2407 0.2577 30 0.2623 0.2847 36 0.2840 0.3110 42 0.3056 0.3337 48 0.3272 0.3596 54 0.3488 0.3827 60 0.3704 0.4105 66 0.3920 --- 72 0.4136 0.4630 78 0.4352 --- 84 0.4568 0.5123 90 0.4784 ---

INCIDENTAL WORK, GRADING Station to Station L/R Remarks 6+50 6+50 Take Out 18”-61’ RCP 6+52 7+37 L Take Out 18”-85’ RCP 6+56 8+94 R Take Out 18”-238’ RCP 7+15 L Temp. Connection between new and

existing storm sewer. 7+38 8+15 L Take Out 18”-120’ RCP 8+21 L Install Berm around Type C Inlet 8+97 9+68 R Take Out 18”-72’ RCP 9+71 10+99 R Take Out 18”-128’ RCP 10+37 R Temp. Connection between new and

existing storm sewer. 11+00 10+98 Take Out 18”-56’ RCP 11+01 12+17 R Take Out 18”-116’ RCP 12+03 12+59 R Take Out Rock Retaining Wall 12+20 13+73 R Take Out 18”-153’ RCP 13+74 13+74 L Take Out 18”-5’ RCP 13+74 13+74 L Take Out 18”-33’ RCP 13+74 13+75 Take Out 18”-60’ RCP 13+75 CL Temp. Connection between new and

existing storm sewer. 13+75 R Temp. Connection between new

storm sewer and existing drop inlet. 19+23 19+23 L Take Out Block Retaining Wall 23+70 23+70 Take Out 18”-95’ RCP

INCIDENTAL WORK, GRADING (CONTINUED) Station to Station L/R Remarks 23+70 CL Temp. connection between new storm

sewer and existing drop inlet. 23+72 27+00 R Take Out 18”-328’ RCP 24+40 R Temporary Connection between

existing and new storm sewer. 27+00 L Temp. connection between new and

existing storm sewer. 27+02 27+02 Take Out 18”-96’ RCP 27+03 32+18 Take Out 18”-513’ RCP 32+19 32+20 Take Out 18”-60’ RCP 32+21 35+14 L Take Out 18”-297’ RCP 32+35 L Temp. connection between existing

storm sewer and back side of new drop inlet.

35+16 35+16 Take Out 18”-48’ RCP 35+16 36+10 R Take Out 18”-136’ RCP 35+17 39+69 L Take Out 24”-452’ RCP 35+25 CL Temp. connection between existing

and new storm sewer. 36+11 36+45 R Take Out 18”-37’ RCP 39+71 39+70 Take Out 18”-60’ RCP 39+72 42+67 L Take Out 30”-288’ RCP 42+69 42+68 Take Out 18”-60’ RCP 42+70 45+90 L Take Out 30”-312’ RCP 45+92 45+91 Take Out 18”-59’ RCP 45+92 45+92 L Take Out 30”-85’ CMP 45+92 CL Temp. connection between existing

and new storm sewer. 45+93 48+91 L Take Out 18”-298’ RCP 48+93 49+21 Take Out 18”-99’ RCP 49+00 CL Temp. connection between existing

and new storm sewer. 57+70 57+70 Take Out 18”-96’ RCP 57+71 61+68 L Take Out 18”-397’ RCP Sturgis Rd. 95+92 97+78 L Take Out 18”-186’ RCP 97+79 97+79 Take Out 18”-61’ RCP 97+79 97+89 R Take Out 18”-36’ RCP 97+80 R Temp. connection between existing

and new storm sewer. 100+23 103+15 R Take Out 18”-293’ RCP 103+15 R Temp. connection between existing

and new storm sewer. 103+16 ( 103+16 Take Out 18”-61’ RCP

REMOVAL OF EXISTING CONCRETE PAVEMENT STA. 6+45.11 to STA. 63+34.00 STA. 96+00.00 to STA. 103+30.62 (STURGIS RD.) Existing asphalt concrete and/or existing asphalt concrete patch work that was placed above the existing concrete pavement is included in the quantity for “Remove Concrete Pavement”. The Contractor shall dispose of the concrete pavement and asphalt concrete at a site approved by the Engineer. The existing 8.5 inch P.C.C. Pavement is typically 94 feet wide and is reinforced with dowel bars at the joints. The existing contraction joint spacing typically is between 15 and 20 feet.

TABLE OF CONCRETE PAVEMENT REMOVAL

Station to

Station

Description

Quantity (SqYd)

5+40 12+00 West Chicago Mainline 5388.4 12+00 18+00 West Chicago Mainline 5208.9 13+05 13+41 Parking Lot on South Side of

West Chicago St. 55.3

18+00 24+00 West Chicago Mainline 4848.1 24+00 30+00 West Chicago Mainline 4670.3 30+00 36+00 West Chicago Mainline 4086.1 36+00 42+00 West Chicago Mainline 4156.3 42+00 48+00 West Chicago Mainline 3548.6 48+00 49+24 West Chicago Mainline 955.7 53+24 54+00 West Chicago Mainline 519.9 54+00 60+00 West Chicago Mainline 4220.7 60+00 65+00 West Chicago Mainline 1365.2 97+03 99+36 North Sturgis Rd. 2090.7 100+60 103+31 South Sturgis Rd. 2241.9 0+25 0+82 North St. Onge St. 266.7 1+56 2+56 South St. Onge St. 456.8

Total: 44079.6

TABLE OF ASPHALT CONCRETE PAVEMENT REMOVAL Station to

Station

L/R

Quantity (SqYd)

10+00 13+57 L 680.8 13+72 16+83 R 278.2 13+72 16+75 L 269.3 17+15 17+51 L 30.1 17+15 17+51 R 118.9 17+90 20+37 L 217.9 17+94 20+41 R 219.7 20+63 21+06 L 56.6 20+70 21+02 R 9.7 21+36 27+03 L 506.0 21+39 26+96 R 495.1 27+35 27+76 R 138.7 28+15 24+89 L 599.1 34+41 48+13 L 1219.6 36+87 48+13 R 1000.9 53+64 60+04 L 568.0 54+39 58+12 R 331.6 58+42 58+74 R 28.7 59+03 61+67 R 234.7 95+50 (Sturgis Rd.) 97+03 1009.5 96+19 (Sturgis Rd.) 99+49 L 991.0 100+56 (Sturgis Rd.) 103+35 R 869.0* 9873.1

* 261 SqYd is Non-Participating to account for extra pavement to be removed for the combination project water main. TABLE OF ASPHALT CONCRETE CURB REMOVAL

Station to

Station

L/R

Quantity (Ft)

17+15 17+16 L 7.6 Total: 7.6

TABLE OF CONCRETE CURB REMOVAL

Station to

Station

L/R

Quantity (Ft)

100+55 (Sturgis Rd.)

100+64 R 21.2

Total: 21.2

Page 8: Department of Transportation - apps.sd.govapps.sd.gov/HC65C2C/EBS/lettings/Addendums/02R5Addendum_1.pdf · Department of Transportation ... The existing 8.5 inch P.C.C. Pavement is

Revised By RS: 10/172017 PROJECT STATE OF

SOUTH DAKOTA P 0231(12)80

SHEET

B5 B117

TOTAL SHEETS

TABLE OF CONCRETE MEDIAN PAVEMENT REMOVAL

Station to

Station

L/R

Quantity (SqYd)

5+40 6+64 229.9 7+21 9+42 386.1 8+89 9+16 31.2 10+58 13+12 423.5 10+86 11+11 R 32.4 16+08 16+90 130.0 17+75 20+43 420.7 21+29 22+13 132.9 26+36 27+18 130.6 27+96 28+84 132.6 33+28 35+33 281.3 36+59 38+46 R 258.0 58+98 59+81 131.8 63+10 65+00 266.3

Total: 2987.3 TABLE OF CONCRETE CURB AND GUTTER REMOVAL

Station to

Station

L/R

Quantity (Ft)

13+72 16+83 R 311.2 13+72 16+75 L 303.4 17+90 20+37 L 246.8 17+94 20+41 R 247.2 20+63 20+67 L 16.0 20+70 20+70 R 3.2 21+02 21+02 R 2.5 21+04 21+06 L 7.6 21+36 27+03 L 569.2 21+39 26+96 R 557.0 27+35 27+37 R 32.4 27+74 27+76 R 32.7 28+15 34+89 L 674.0 28+15 35+27 R 712.2 34+41 48+13 L 1372.3 36+87 48+13 R 1126.2 53+64 60+04 L 639.6 54+39 58+12 R 373.8 58+42 58+43 R 7.9 58+74 58+74 R 8.0 59+03 61+67 R 264.2

Total: 7507.4 TABLE OF CONCRETE APPROACH PAVEMENT REMOVAL

Station to

Station

L/R

Quantity (SqYd)

7+14 7+53 R 21.2 8+46 8+93 R 23.8 11+46 11+94 L 24.9 13+09 13+61 R 27.0 13+11 13+61 L 25.1 27+77 27+78 R 5.3 58+33 58+83 L 69.4 96+14 (Sturgis Rd.) 96+51 R 17.6 96+78 (Sturgis Rd.) 97+06 L 24.8 98+25 (Sturgis Rd.) 98+73 L 24.1 100+63 (Sturgis Rd.) 101+01 R 18.7 101+20 (Sturgis Rd.) 101+67 R 24.0 101+77 (Sturgis Rd.) 102+25 R 24.2 102+48 (Sturgis Rd.) 102+80 R 15.4

Total: 345.5

TABLE OF SIDEWALK REMOVAL Station to

Station

L/R

Quantity (SqYd)

6+45 7+14 R 43.5 7+53 8+46 R 52.6 8+93 10+15 R 72.5 11+84 13+11 R 124.9 13+41 16+98 R 153.0 17+67 20+68 R 139.1 21+05 27+34 R 333.3

Total: 918.9 TABLE OF MANHOLE REMOVAL All costs for removal of the frame and grate assembly shall be incidental to the contract unit price per each for “Remove Manhole”. Station

L/R

Quantity (Each)

9+70 R 1 11+00 R 1

Total: 2 TABLE OF DROP INLET REMOVAL All costs for removal of the frame and grate assembly shall be incidental to the contract unit price per each for “Remove Drop Inlet”.

Station

L/R

Quantity (Each)

6+50 L 1 7+38 L 1 8+95 R 1 10+98 L 1 12+18 R 1 13+74 L 2 13+75 R 1 23+70 L 1 23+70 R 1 27+02 L 1 27+02 R 1 32+20 L 1 32+20 R 1 35+16 L 1 35+16 R 1 36+09 R 1 36+47 R 1 39+70 L 1 39+71 R 1 42+68 L 1 42+69 R 1 45+92 L 1 45+92 R 1 48+93 L 1 49+21 R 1 57+70 L 1 57+70 R 1 97+79 (Sturgis Rd) L 1 97+79 (Sturgis Rd) R 1 97+89 (Sturgis Rd) R 1 103+16 (Sturgis Rd) L 1 103+16 (Sturgis Rd) R 1

Total: 33

CORRUGATED METAL PIPE Corrugated metal pipes shall have 2 ⅔-inch X ½-inch corrugations for 42-inch and smaller round pipe and 48-inch and smaller arch pipe unless otherwise stated in the plans. Corrugated metal pipes shall have 3-inch X 1-inch or 5-inch X 1-inch corrugations for 48-inch and larger round pipe and 54-inch and larger arch pipe unless otherwise stated in the plans. The gauge of the corrugated metal elbows shall match the thickest gauge of corrugated metal pipe it is connected to. PIPE FOR DOWNSPOUTS If corrugated metal pipes are provided, the pipes shall be as specified in the CORRUGATED METAL PIPE note. High density polyethylene pipe may be substituted for 36 inch and smaller pipe downspouts at no additional cost to the State. All necessary connections, transitions, and anchoring methods shall be in accordance with the manufacturer’s recommendations and be approved by the Engineer. Bedding and backfill material and installation procedures shall conform to the manufacturer’s design requirements. REINFORCED CONCRETE PIPE High sulfate levels are likely to be encountered on this project. The type of cement used for the reinforced concrete pipes shall be either a type II with 20% class F modified fly ash substituted for cement in accordance with Specifications Section 605 or a type V. The water/cementitious material ratio shall not exceed 0.45 as defined in Specifications Section 460.3 A. The mix shall be as per the fabricator's design; however, minimum compressive strength shall not be less than 4500 psi at 28 days. The pipe must be marked in an acceptable way to designate meeting requirements for sulfate resistance. CONCRETE PIPE CONNECTIONS Pipe connections to existing pipes, manholes, junction boxes, and drop inlets shall be done by breaking a hole into the existing structure and inserting the pipe. A concrete collar shall then be poured around the pipe in the area of the connection. When it is not possible to use a normal pipe joint (male-female ends), connections to existing pipe shall be made by placing a 2’ wide by 6" thick M6 concrete collar around the outside of the connection. The concrete collar shall be reinforced with 6x6 W2.9 x W2.9 wire mesh. All costs for constructing the concrete collars including materials and labor shall be incidental to the contract unit price per foot for the corresponding pipe bid item. RCP FLARED END SECTIONS The storm sewer pipe outlet near station 45+92 L shall have flared ends placed at the ends. These flared ends shall have 3’ Concrete Cutoff Walls attached to the bottom of the flared end in accordance with the details. Cost for 3’ concrete cutoff walls will be considered incidental to the contract unit price for each type of RC Flared End Section.

Page 9: Department of Transportation - apps.sd.govapps.sd.gov/HC65C2C/EBS/lettings/Addendums/02R5Addendum_1.pdf · Department of Transportation ... The existing 8.5 inch P.C.C. Pavement is
Page 10: Department of Transportation - apps.sd.govapps.sd.gov/HC65C2C/EBS/lettings/Addendums/02R5Addendum_1.pdf · Department of Transportation ... The existing 8.5 inch P.C.C. Pavement is
Page 11: Department of Transportation - apps.sd.govapps.sd.gov/HC65C2C/EBS/lettings/Addendums/02R5Addendum_1.pdf · Department of Transportation ... The existing 8.5 inch P.C.C. Pavement is
Page 12: Department of Transportation - apps.sd.govapps.sd.gov/HC65C2C/EBS/lettings/Addendums/02R5Addendum_1.pdf · Department of Transportation ... The existing 8.5 inch P.C.C. Pavement is

REVISED 10/16/17 PROJECT STATE OF SOUTH

DAKOTA P 0231(12)80 SHEET

D2 D30

TOTAL SHEETS

SECTION D ESTIMATE OF QUANTITIES

STREET SWEEPING Vehicle tracking of sediment from the construction site shall be minimized. Street sweeping shall be used if erosion and sediment control best management practices are not adequate to prevent sediment from being tracked onto the street. The Contractor shall use a pickup broom having integral self-contained storage to clean the roadway. The pickup broom used shall be a minimum of 6 feet wide and have working gutter brooms. At a minimum, sweeping will be required: 1. Prior to opening any segment or roadway to traffic. 2. Following pavement grooving operations and prior to the application of

the pavement marking tape. 3. When sawing operations are underway in the inside driving lanes, the

outside driving lanes and gutter may need to be swept to control dust. 4. Whenever sediment is tracked onto the roadway being used by traffic. All costs for cleaning the roadway with a pickup broom shall be incidental to the contract unit price per hour for “Sweeping”.

DEWATERING AND SEDIMENT COLLECTING The Contractor has the option to treat sediment laden water trapped within the project limits with the DEWATERING AND SEDIMENT COLLECTION SYSTEM as described in the detail drawings, or the Contractor may elect to transport sediment laden water off the project. Water transported off the project limits shall not be disposed of in an area where it can enter a waterway. The disposal site must be approved by the Engineer. CONSTRUCTION ENTRANCE The Contractor shall install a Construction Entrance at locations where there is a potential for mud tracking and sediment flow from the construction site and work area onto a paved public roadway. It is the Contractor’s option to use the SDDOT Construction Entrance (See SDDOT Construction Entrance notes and details), a product from the list provided in these notes, or other products or processes as approved by the Engineer during construction. If the Contractor elects to use one of the products listed in the table, then the Contractor shall install the construction entrance product in accordance with the manufacturer’s installation instructions or as directed by the Engineer. The Contractor shall maintain the construction entrance such that mud tracking and sediment flow will not enter the roadway or adjacent drainage areas. The construction entrance shall be routinely inspected and the Contractor shall repair or replace material as deemed necessary by the Engineer. All costs for furnishing, installing, maintaining, and removal of the construction entrance including equipment, labor, materials, and incidentals shall be included in the contract unit price per each for “Construction Entrance”. The following table is a list of known construction entrance products available for use:

Product Manufacturer

Grizzly Rumble Grate (10’ width and 24’ length required)

Trackout Control, LLC Tempe, AZ Phone: 1-800-761-0056 www.trackoutcontrol.com

Rumble Grid (12’ width and 24’ length including combination of grids and ramps

required)

Pro-Tec Equipment, Inc. Charlotte, MI Phone: 1-800-292-1225 www.pro-tecequipment.com

SDDOT CONSTRUCTION ENTRANCE If the SDDOT Construction Entrance is utilized, then the Contractor shall install the SDDOT Construction Entrance in accordance with these notes and the detail drawings. Pit run material shall be obtained from a granular source and shall conform to the following gradation:

Sieve Size Percent Passing 6” 100% #4 0-60%

#200 0-20% The pit run material shall be compacted to the satisfaction of the Engineer. The aggregate for the granular material shall conform to the following gradation requirements:

Sieve Size Percent Passing 3” 100%

2 ½” 90-100% 1 ½” 25-60% ¾” 0-10% ½” 0-5%

The granular material shall be placed in 6” maximum lifts. It is anticipated that the granular material will need to be periodically removed and replaced as it becomes inundated with mud and sediment. The reinforcement fabric (MSE) shall conform to Section 831 of the Specifications. The MSE geotextile shall be on the Approved Products List for this material or will be certified by the supplier to meet this specification prior to installation. The reinforcement fabric (MSE) should be kept as taut as possible prior to placing. Equipment shall not be allowed on the reinforcement fabric (MSE) until the first lift of granular material is in place. All seams in the reinforcement fabric (MSE) shall be overlapped at least 2’ and shingled.

Page 13: Department of Transportation - apps.sd.govapps.sd.gov/HC65C2C/EBS/lettings/Addendums/02R5Addendum_1.pdf · Department of Transportation ... The existing 8.5 inch P.C.C. Pavement is

PROJECT STATE OF

SOUTH

DAKOTA

P 0231(12)80

SHEET

L2 L36

TOTAL SHEETS

SECTION L ESTIMATE OF QUANTITIES – PCN 02R5

SUPPLYING AS BUILT PLANS

If the traffic signal systems or roadway lighting systems are constructed differently than what is stated in the plans, the Contractor shall supply as built plans to the Engineer and a copy shall be sent to the Traffic Design Engineer. The as built plans may include conduit layouts, wiring diagrams, or other drawings depicting the changes from the original plans.

SHOP DRAWING AND CATALOG CUTS SUBMITTALS

The Contractor shall submit shop drawings and catalog cuts in accordance with Section 985 of the Specifications. Adobe PDF submittals shall be sent to the following email addresses:

[email protected] [email protected] [email protected]

ON-SITE INSPECTION

An on-site inspection of the traffic signal shall be conducted before acceptance of the project, once the traffic signal is completed and operational. The on-site inspection shall be conducted by the Project Engineer or Region Traffic Engineer with the Contractor, City Traffic Engineer, and the Traffic Design Engineer present.

REMOVE SIGNAL EQUIPMENT

Signal equipment removed shall become the property of the Contractor. All costs for work involved in the removal of existing signal equipment shall be incidental to the contract lump sum price for “Remove Signal Equipment”.

SALVAGE SIGNAL EQUIPMENT

Traffic signal controller cabinet and roadway luminaires shall be salvaged and delivered to the City of Rapid City by the Contractor. The Contractor shall notify the City 5 days before the delivery of the salvaged signal equipment. The City contact is Traffic Operations at (605)394-4118. All costs for work involved in the salvage and delivery of the existing signal equipment shall be incidental to the contract lump sum price for “Salvage Signal Equipment”.

REMOVE SIGNAL POLE FOOTING

The footings of existing signal poles shall be removed by the Contractor to a minimum of 2’ below the ground surface. Restoration of the disturbed area shall be to the satisfaction of the Engineer. All costs for removing the footings of the existing luminaire poles shall be incidental to the contract unit price per each for “Remove Signal Pole Footing”.

REVISED DATE: 16-OCTOBER-2017 REMOVE LUMINAIRE POLE

Existing luminaire poles EL1-EL26 shall be removed by the Contractor. The Contractor shall coordinate the removal of the existing luminaire poles with the installation of the new luminaire poles. All costs involved with coordinating the installation of the new luminaire poles shall be incidental to the contract unit price per each for “Remove Luminaire Pole”.

REMOVE LUMINAIRE POLE FOOTING

The footings of existing luminaire poles EL1-EL26 shall be removed by the Contractor to a minimum of 2’ below the ground surface. Restoration of the disturbed area shall be to the satisfaction of the Engineer. All costs for removing the footings of the existing luminaire poles shall be incidental to the contract unit price per each for “Remove Luminaire Pole Footing”.

TABLE OF FOOTING DATA

Site Designation

Footing Diameter

* Footing Depth

**Spiral Diameter

**Spiral Length

Vertical Reinforcement

S1, S9 2’ - 0” 9’ - 0” 1’ - 8” 60’ - 0” 8-#7 x 8’ - 6”

S2, S8 3’ - 0” 12’ - 0” 2’ - 8” 120’ - 9” 14-#8 x 11’ -6”

S3 3’ - 0” 14’ - 0” 2’ - 8” 137’ - 6” 14-#8 x 13’ -6”

S6 3’ - 0” 15’ - 0” 2’ - 8” 145’ - 9” 14-#8 x 14’ -6”

L1-L39 2’ - 0” 8’ - 0” 1’ - 8” 54’ - 9” 8-#7 x 7’ - 6”

* Footing depth shall be below ground level. ** The size of all spirals shall be #3.

FOOTING DATA

The subsurface conditions from the beginning of the project to approximately station 42+00 consist of reddish brown silt-clay up to 5’ in depth overlying red sandy clay-silt (Spearfish Formation) to 15’ below the surface. Occasional gypsum layers up to 1.5’ thick were encountered at various depths throughout this section of the project. No groundwater was encountered during the investigation in this section of the project. The borings caved between 11.9’ and 13.3’ below the surface.

MattV
Stamp