Delivering Cost Effective Public Works Projects
through Cost-based Procurement
Ir. John Kwong
Head of Project Cost Management Office
Development Bureau, HKSAR Government
![Page 2: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/2.jpg)
*
• Improve people’s living environment
• Promote economic growth
• Enhance Hong Kong’s long term competitiveness
Construction Industry
is TASKED to …
2
Your Contributions
2
![Page 3: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/3.jpg)
Real GDP
CWP Expenditure
Establishment of CWRF
Rose Garden Project
Asian Economic Crisis
SARS Epidemics
Ten Major Infrastructure Projects
3
How much should be allocated for public works?
![Page 4: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/4.jpg)
How much should be allocated for public works?
Real GDP
CWP Expenditure
Establishment of CWRF
Rose Garden Project
Asian Economic Crisis
SARS Epidemics
Ten Major Infrastructure Projects
3.4% of Real GDP
4
![Page 5: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/5.jpg)
2018-19 GDP $2,800B
Govt. Revenue $605B
Govt. Expenditure $558B
Infrastructure $86B
Infrastructure to GDP: 3.2%
Considerable Investment in Infrastructure
2018-19 Budget
5
![Page 6: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/6.jpg)
Challenges
Construction Industry in Hong Kong
![Page 7: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/7.jpg)
Significant future construction volumes
High costs
Unsatisfactory mega-project performance
Unsatisfactory site safety performance
Declining productivity
Lack of creativity and innovation
Core challenges facing the industry
Core challenges facing the Industry
7
![Page 8: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/8.jpg)
$240 B
$350 B
Significant future construction volume
8
![Page 9: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/9.jpg)
• Housing and land supply ( Lantau, NDA )
• Transportation ( 3rd Runway )
• Health care (Hospital Development Plan)
• Education (Hostel Development Fund)
• Sports and recreation facilities (5-Yr Plan)
• Other livelihood-related projects
Overall Expenditure
➢$1,000B in next 10 years!
i.e. > $100B @ year9
Major projects in the pipeline
![Page 10: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/10.jpg)
Significant future construction volumes
High costs
Unsatisfactory mega-project performance
Unsatisfactory site safety performance
Declining productivity
Lack of creativity and innovation
Core challenges facing the industry
Core challenges facing the Industry
10
![Page 11: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/11.jpg)
High construction cost
Hong Kong -3rd most expensive place to build!
11
![Page 12: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/12.jpg)
~100%
Tender Price Indices
12
![Page 13: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/13.jpg)
Important
industry milestones
Building challenges inPublic housing
Ten MajorInfrastructureProjects
Financial SecretaryTF on ManagingCost of Public Works
f
Project CostManagement Office
Construction coststaking off
Construction IndustryReview Committee
AirportCore ProgrammeOur pathway
13
![Page 14: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/14.jpg)
• Established PCMO in June 2016
• Direct command of Perm Secretary for Development (Works)
• Report to the Financial Secretary regularly
• Oversee cost management for all public works projects
• Promote cost management in private sector projects
14
Project Cost Management Office (PCMO)
![Page 15: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/15.jpg)
15
⚫ Objectives:
- Contain risks of budget overrun
- Ensure cost-effectiveness of public works projects
⚫ Achievements:
- Cost saving of $27 billion or ~10% (out of $260 billion in 130 projects)
- Increasing cost awareness in Project Offices
Project Cost Management Office (PCMO)
![Page 16: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/16.jpg)
Why do we need to pay so much?
Conventional Wisdom
The designer is often content
to leave the matter entirely to
the contractor, and while the
latter will undoubtedly
overcome the problems
imposed by the design, this
often means that the cost is
higher than it need be.
16
![Page 17: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/17.jpg)
17
⚫ Need to have an encompassing design to avoid impossibility
e.g. conservative pile design, higher CFA/NOFA ratio, trenchless, etc.
⚫ Need to allow for unforeseen situations
e.g. uncharted utilities
⚫ Need to pay premium for transferring risks to contractors
e.g. cost fluctuations risks, interfacing risks, temporary works risks, etc.
High Cost + High Premium = High Price !!!!
Why do we need to pay so much!
Segregation between Design and Construction
![Page 18: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/18.jpg)
Price Index vs Cost Index
100%
12007
4 3 2 12010
4 3 2 12013
4 3 2 12016
4 3
HyDCCI & CEWICEWTPI
CEWTPI HyDCCICEWI
18
![Page 19: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/19.jpg)
19
⚫ Don’t want to exploit contractors or take advantage out of their difficulties
⚫ Only pay for something executed
⚫ Ensure the cost-effectiveness of public projects
What Government as a public project owner wants?
![Page 20: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/20.jpg)
20
⚫ Payment to the contractor on the basis of cost
⚫ pay for something executed, cost incurred (e.g. labour/materials cost)
⚫ Government can enjoy cost saving during works execution
Cost-based Procurement instead of Price-based Procurement
Cost-based Procurement
![Page 21: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/21.jpg)
21
⚫ cost-based
⚫ incentivize cost saving (pain-gain share)
⚫ collaborative, not adversarial
⚫ a well established international contract form
Why NEC Open Book Target Cost?
![Page 22: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/22.jpg)
Open Book Target Cost vs Price-based
Cost-based (e.g. NEC Options C/D) Price-based (e.g. GCC)
Saving from contract prices
⚫ Government pays less than the target costif final actual costs < contractor’s estimate
⚫ Government cannot enjoy cost saving evenif final actual costs < contractor’s estimate
Extra risk premium ⚫ Contractor needs not to price in extra riskpremium for risks shared by Government
⚫ Government is willing to take up more riskin return of a lower tender premium andpays only when risks are materialised
⚫ Contractor speculates extra risk premiumfor unknown risks
⚫ Government pays for the extra riskallowance which may not have materialised
Further cost saving ⚫ Contractor has more incentive to adoptinnovative and cost effective alternativedesigns or construction methods toachieve cost savings
⚫ Contractor has less incentive to proposeinnovative and cost-effective alternativedesigns or construction methods
Project Performance
⚫ Contractor has incentive to enhance project management , productivity, safety, environmental and quality – better time and cost performance
⚫ Contractor has less incentive to drive better project delivery performance
22
![Page 23: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/23.jpg)
Open Book Target Cost vs Price-based
Cost-based (e.g. NEC Options C/D) Price-based (e.g. GCC)
Saving from contract prices
⚫ Government pays less than the target costif final actual costs < contractor’s estimate
⚫ Government cannot enjoy cost saving evenif final actual costs < contractor’s estimate
Extra risk premium ⚫ Contractor needs not to price in extra riskpremium for risks shared by Government
⚫ Government is willing to take up more riskin return of a lower tender premium andpays only when risks are materialised
⚫ Contractor speculates extra risk premiumfor unknown risks
⚫ Government pays for the extra riskallowance which may not have materialised
Further cost saving ⚫ Contractor has more incentive to adoptinnovative and cost effective alternativedesigns or construction methods toachieve cost savings
⚫ Contractor has less incentive to proposeinnovative and cost-effective alternativedesigns or construction methods
Project Performance
⚫ Contractor has incentive to enhance project management , productivity, safety, environmental and quality – better time and cost performance
⚫ Contractor has less incentive to drive better project delivery performance
23
![Page 24: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/24.jpg)
Major Large Scale Projects in Target Cost Options
… many more to come!
24
![Page 25: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/25.jpg)
• Option selection• Specifications
• Fitness-for-Purpose• No-Frills• Cost Estimation
• Variations• Cashflow • Cost-based procurement
• AM/FM• Life cycle cost
Budget / Cost
Time
Budget Management
Planning & Design Construction
Expenditure Management
PCMO Cost Management Model
25
![Page 26: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/26.jpg)
Wider Collaboration
26
![Page 27: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/27.jpg)
V 1.0 July 2015 © NEC Contracts 2015 27
International Collaboration
![Page 28: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/28.jpg)
Project Cost Management Office
• Enhancing Project Governance - Promote cost-based procurement (and early contractor involvement!!)- Encourage adoption of innovation and advance technology- Monitoring project finance throughout planning, design, construction stage- Establishing cost information database and enhance ERA- International collaboration
• Uplifting Project Delivery Capability- Major Project Leaders Academy- Project Capability Building for construction professionals- System re-engineering for maximising delivery performance - Professionalism, commercial mindset and efficient execution
28
![Page 29: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/29.jpg)
29
NEC Journey in Hong Kong
![Page 30: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/30.jpg)
NEC Journey in Hong Kong
✓ 1st Government NEC ECC
✓ Option C was selected
✓ Awarded in 2009 and completed in 2012
✓ 15% time saving (6 month ahead)
✓ 5% cost saving ($4.1M shared gain)
NEC Consultant - EC Harris (now Arcadis?)
NEC Legal Adviser - Lovells (now Hogan Lovells)
DSD Contract Adviser - John Kwong (still John Kwong)
DSD project - Improvement of Fuk Man Road Nullah in Sai Kung (HK$76M)
30
![Page 31: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/31.jpg)
NEC Journey in Hong Kong
✓ 1st Government NEC ECC
✓ Option C was selected
✓ Awarded in 2009 and completed in 2012
✓ 15% time saving (6 month ahead)
✓ 5% cost saving ($4.1M shared gain)
NEC Consultant - EC Harris (now Arcadis?)
NEC Legal Adviser - Lovells (now Hogan Lovells)
DSD Contract Adviser - John Kwong (still John Kwong)
DSD project - Improvement of Fuk Man Road Nullah in Sai Kung (HK$76M)
31
![Page 32: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/32.jpg)
NEC vs GCC
• Government directive • World trend of collaborative contracting• Keep up to date with technology and
supply chain development• Drive for better project performance
• Fading out • No maintenance• Cannot cope with rapid changes in
construction industry
32
![Page 33: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/33.jpg)
33
-Hong Kong SAR Government will strive to delivering cost effective public works projects through NEC Target Cost Contracts
NEC in Hong Kong
33
![Page 34: Delivering Cost Effective Public Works Projects through Cost-based Procurement · 2019-04-08 · Cost-based Procurement instead of Price-based Procurement Cost-based Procurement.](https://reader033.fdocuments.net/reader033/viewer/2022042622/5fa1ddb909d120453c17449c/html5/thumbnails/34.jpg)
Delivering Cost Effective Public Works Projects
through Cost-based Procurement
-Thank You
34