Decommissioning of offshore installations in the ... . Ramboll. Decom in...
date post
13-Apr-2018Category
Documents
view
216download
0
Embed Size (px)
Transcript of Decommissioning of offshore installations in the ... . Ramboll. Decom in...
Decommissioning of
offshore installations in
the operational phase
Kristian Lund Jepsen
Ramboll Oil & Gas
2SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Two types of installations two types decom
3SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Reasons for decom at fixed installations
Equipment redundant from day one
Equipment/system process wise outdated
Demolition
Equipment/system technological outdated
Equipment failed / worn-out
Replace with equipment / systems that fits changedprocess conditions
Replace with modernequipment / systems withnew technology
Refurbish / Repair
Replace (1 : 1)
4SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Redundant from day one - example
Gas fired heater back-upfor turbine WHRUs
Other examples:
Mud tanks
Well kill system
Runway beams
Trolleys/chain hoists
5SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Process wise outdated equipment
Increased amount of produced water
Change from HP separation to LP Mode
Change in gas composition / mole weight
Change in gas composition increase of H2S + CO2
Increased amount of oil/gas
Debottlenecking of complete process train
Debottlenecking of produced water system
Larger pipe dia, larger volume in separators
Re-bundling of centrifugal compressors and larger driver
Change piping matr. class from CS to duplex
6SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Technological outdated equipment - examples
Pneumatic analog instruments
F&G Detectors / systems
Control / ESD Systems
Control panels for gas compressors
7SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Examples worn-out equipment
8SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Heat exchangers for cleaning/refurbisment
9SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Decommissioned stay in place
Runway beams aredecommissioned to avoid periodicinspections / tests.
10SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Experiences from operational decom
Dangerous lifting operations (unknown weight+COG)
Handling of NORM (NaturalOccuring Radioactive Matr)
Handling of chemical/oil waste
No asbestos in insulation(however: Flange Insulationkits, Carbon-Asbestos filledgaskets)
Scale may be barium orstrontium sulphate which is NORM material.
11SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Estimates tons metal scrap per year
Detailed data from one platform backload to shore during one year.
Assumed a model partly based on above data from one platform for calculating the amount of equipment operational decommissioned yearly.
Assessed the Customs Authorities to obtain information about import from offshore installations.
Assessed the oil Companies (DUC/Mrsk Oil, Hess, DONG E&P)
12SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Backload Logistics and Handling
Return Goods
/ Supply Boat
Well Service
Company
Equipment
Waste skips
Chemical Tote
Tanks
Backload
Containers /
Baskets
Large scrap
items
To Service company
Not dangerous
waste
Chemicals/oil
waste
Empty - send
to Kommune
Kemi
Empty -
normal
renovation
Waste to Kommune Kemi
Tank Cleaning
Waste to Kommune Kemi
Refill Tote
Tank
Sorting /
Evaluation
To Service /
Repair
company
To be Stocked for
later use
(OIL COMPANY'S
STORE)
To be sold for
re-use
Repair /
scrap
Repaired/
To stock
Supply Goods
/ Supply Boat
Scrap Yard
Scrap
Repaird - directly return to offshore
Costums area
13SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Estimate Model. All Danish offshore fields installedpiping / decomissioned piping and totally decommissioned
Estimated piping (incl. valves) from Danish offshore platforms decommissioned yearly
Installation
year 1987 and before 1987 - 1997 1997 - 2007 Totally
Age 20 years and more 10 - 20 years 0 - 10 years
Piping (tons) 6923 4825 3400 15148Scrap/change-
out % yearly 10 5 2,5Scrapped piping
- tons yearly 692 241 85 1018
Totally decommissioned from Danish offshore platforms yearly - estimated tons:
Piping 1000
Mech. Equipm. 500
Structures 250
Elect/Instrum 200
Other 50
Totally 2000
The model is based on a life time of 20 -25 years of an installation.
14SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Estimates from the 3 operators in Danish sector
DUC/Mrsk Oil
Hess Denmark Aps
DONG E&P
Totally: 3100 tons 3400 tons yearly
Variations: 2500 4000 tons yearly
15SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Jack-up rig conversion / decom
Maersk Giant:
Converted to oil/gas production 1996.
Production package owned by Schlumberger.
Produced on Yme Field 1996 2001, operated by Maersk Contractors.
Decommissioned production packagedemolished in Esbjerg Port 2001. Packagetaken over by Hannover Company
The rig converted back to drilling.
16SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Statoil preparations to decom. HSE / NORM
Study of consequences (Konsekvensutredning Ymeavslutningsplan).
Included evaluations regarding HSE impacts.
Included evaluations regarding NORM it was concluded there was no NORM as seawater had only been injected for a short period in the initial stage of the project.
Samples of scale in the production equipment was taken.
Concluded that scale was not radioactive and that it was calciumcarbonate.
17SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Maersk Giant towing in 2001
18SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Maersk Giant at the port side
19SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Maersk Giant production package onboard
20SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Maersk Giant equipment being lifted off
21SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Maersk Giant 2001 Decom/Conversion
Noise / Fire Walls around package removed
Flare tower removed
Production package removed from deck
All interconnecting piping and cabling removed
Totally: 1200 tons removed
Production package, 800 tons, sold from Schlumberger to Hannover Company for possible re-use
22SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Yme production package. Summer 2007
23SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Mobile offshore units. Decom status.
Yearly 2 units in the harbour.
Equipment decommissioned/scapped yearly: 500 tons 2000 tons
24SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Total status. Decom. Tonnes handled yearly
From fixed installations 2500 - 4000From mobile offshore units 500 - 2000
Total 3000 - 6000
25SlideOctober 15, 2007Basic Ramboll Oil & Gas PPT
Conclusion
The amount (tonnes) of equipment decomissioned/scraped and then handled in the harbour of Esbjerg yearly corresponds to the weight of one medium size topside.
The experience exists and the companies to handle the waste and scrap are used to handle these items.
Large heavy lift cranes (Thialf) cannot go into the harbour.
Need for companies who can handle and clean scrapped piping and equipment for NORM.
Need for long-term storage facilities for NORM.