DECISION APPROVING SETTLEMENT AGREEMENT AS AMENDED … · 2015. 1. 27. · On April 2, 2014, six...

193
143336799 - 1 - ALJ/MD2/KD1/sbf Date of Issuance 11/25/2014 Decision 14-11-040 November 20, 2014 BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Investigation on the Commission’s Own Motion into the Rates, Operations, Practices, Services and Facilities of Southern California Edison Company and San Diego Gas and Electric Company Associated with the San Onofre Nuclear Generating Station Units 2 and 3. Investigation 12-10-013 (Filed October 25, 2012) And Related Matters. Application 13-01-016 Application 13-03-005 Application 13-03-013 Application 13-03-014 DECISION APPROVING SETTLEMENT AGREEMENT AS AMENDED AND RESTATED BY SETTLING PARTIES

Transcript of DECISION APPROVING SETTLEMENT AGREEMENT AS AMENDED … · 2015. 1. 27. · On April 2, 2014, six...

  • 143336799 - 1 -

    ALJ/MD2/KD1/sbf Date of Issuance 11/25/2014 Decision 14-11-040 November 20, 2014 BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

    Order Instituting Investigation on the Commission’s Own Motion into the Rates, Operations, Practices, Services and Facilities of Southern California Edison Company and San Diego Gas and Electric Company Associated with the San Onofre Nuclear Generating Station Units 2 and 3.

    Investigation 12-10-013 (Filed October 25, 2012)

    And Related Matters.

    Application 13-01-016 Application 13-03-005 Application 13-03-013 Application 13-03-014

    DECISION APPROVING SETTLEMENT AGREEMENT AS AMENDED AND RESTATED BY SETTLING PARTIES

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    Table of Contents

    Title Page

    - ii -

    DECISION APPROVING SETTLEMENT AGREEMENT AS AMENDED AND RESTATED BY SETTLING PARTIES ........................................................................... 1

    Summary .................................................................................................................. 2 1. Background ....................................................................................................... 7 2. Procedural History ......................................................................................... 12 3. Standard of Review ........................................................................................ 21 4. The Settlement Agreement ........................................................................... 22

    4.1. Joint Motion to Adopt Settlement Agreement .................................. 22 4.2. Terms of Settlement Agreement .......................................................... 23

    5. Parties’ Positions ............................................................................................ 30 5.1. Settling parties ........................................................................................ 30

    5.1.1. The Agreement is Reasonable in Light of the Whole Record............................................................................. 31

    5.1.2. The Agreement is Consistent with the Law .......................... 33 5.1.3. The Agreement is in the Public Interest ................................. 34

    5.2. Other parties ........................................................................................... 35 5.2.1. Parties Not Opposed to the Settlement Agreement ............. 35

    5.2.1.1. CLECA .............................................................................. 35 5.2.1.2. AReM/DACC .................................................................. 36 5.2.1.3. Joint Parties ....................................................................... 37 5.2.1.4. World Business Academy (WBA) ................................. 38

    5.2.2. Parties Opposed to the Settlement Agreement ..................... 39 5.2.2.1. Alliance for Nuclear Responsibility .............................. 39 5.2.2.2. Women’s Energy Matters (WEM) ................................. 43 5.2.2.3. Coalition to Decommission San Onofre ....................... 45 5.2.2.4. Ruth Henricks .................................................................. 49

    5.3. Settling Parties’ Reply Comments ....................................................... 51 5.3.1. Joint Settling Parties .................................................................. 51

    5.3.1.1. Agreement is Consistent With The Law ...................... 52 5.3.1.2. Agreement is Reasonable in Light of the Whole

    Record and in the Public Interest .................................. 54 5.3.1.3. The Commission Should Reject

    Alternative Terms ............................................................ 56 5.3.2. SCE .............................................................................................. 59 5.3.3. SDG&E ........................................................................................ 60

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    Table of Contents (Cont’d)

    Title Page

    - iii -

    6. Due Process Considerations ......................................................................... 61 6.1. The Settlement Conference ................................................................... 61 6.2. Timing of the Settlement Agreement .................................................. 64 6.3. The Hearing on the Settlement Agreement ....................................... 65

    6.3.1. No Prehearing Conference ....................................................... 65 6.3.2. Conduct of Hearing .................................................................. 66

    7. Discussion of Settlement Terms ................................................................... 69 7.1. Agreement is Consistent With the Law.............................................. 70

    7.1.1. Agreement Is Not Defective Pursuant to Rule 12.1 ............. 71 7.1.2. Resulting Rates Will Not Violate §451, §455.5,

    and §463(a) ................................................................................. 73 7.1.3. Settlement is Not Inconsistent With Prior Decisions ........... 76 7.1.4. NRC Notice of Violation to SCE is Not

    Determinative of SCE’s Imprudence ...................................... 79 7.1.5. ORA’s Participation Does Not Violate § 309.5 ...................... 81 7.1.6. Allegations of Collusion ........................................................... 82 7.1.7. Other Legal Claims ................................................................... 84

    7.2. Agreement is Reasonable in Light of the Whole Record ................ 85 7.2.1. Recovery of 2012-2013 Operations and

    Maintenance (O&M) and Non-O&M Costs .......................... 88 7.2.2. Recovery of CWIP ..................................................................... 91 7.2.3. Reduction of Current Inventories ........................................... 94 7.2.4. Materials and Supplies ............................................................. 96 7.2.5. Recovery of Net Investment and Reduced Return

    on Base Plant .............................................................................. 98 7.2.6. No Recovery for Post-Outage SGRP costs ........................... 100 7.2.7. Recovery of Replacement Power .......................................... 102 7.2.8. Sharing of Third Party Recoveries ........................................ 105 7.2.9. Other Terms ............................................................................. 107

    7.2.9.1. Community Education & Outreach ............................ 107 7.2.9.2. General Recitals and Findings of Fact in

    Joint Motion .................................................................... 108 7.2.10. Amended Agreement as a Whole is Reasonable

    in Light of the Whole Record ................................................ 109 7.3. Agreement in the Public Interest ....................................................... 109

    7.3.1. Termination of Investigation ................................................. 110

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    Table of Contents (Cont’d)

    Title Page

    - iv -

    7.3.2. Settlement Does Not Need to Be Perfect ............................. 115 7.3.3. Delayed refunds & remedies ................................................. 116 7.3.4. Increased Greenhouse Gas Emissions and Other

    Unrecognized Effects .............................................................. 119 7.3.5. Commission Oversight of Litigation and Refunds ............ 122 7.3.6. Third Party Litigation Recovery ........................................... 124 7.3.7. Filing of Revised Tariff Sheets ............................................... 127 7.3.8. Clarifications and Other Modifications to

    the Agreement ......................................................................... 128 8. Rate Adjustments for Direct Access Customers ...................................... 129 9. Oral Argument ............................................................................................. 130 10. Comments on Proposed Decision ............................................................. 130 11. Assignment of Proceeding .......................................................................... 131

    Findings of Fact ........................................................................................................... 131 Conclusions of Law ..................................................................................................... 134 ORDER ......................................................................................................................... 136

    Appendix A – Exhibit List Appendix B – Amended, Restated Settlement Agreement

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    -2 -

    DECISION APPROVING SETTLEMENT AGREEMENT AS AMENDED AND RESTATED BY SETTLING PARTIES

    Summary

    This decision approves a settlement agreement between Southern

    California Edison Company (SCE)and San Diego Gas & Electric Company

    (SDG&E) (collectively, the Utilities) and four other settling parties which

    provides resolution of rate recovery issues related to the premature shutdown of

    San Onofre Nuclear Generating Station (SONGS), following a steam generator

    tube leak on January 31, 2012. The original settlement agreement was amended

    and restated (Amended Agreement), inter alia, to provide that SCE and SDG&E

    shall each equally share net litigation proceeds from Mitsubishi Heavy Industries

    between their respective ratepayers and shareholders, and to improve

    Commission oversight of utility implementation of the settlement, particularly as

    to development of the revised rates.

    The primary result of the settlement is ratepayer refunds and credits of

    approximately $1.45 billion. The Utilities must also stop further collection of the

    Steam Generator Replacement Project (SGRP) costs in rates, return all SGRP costs

    collected after January 31, 2012 to ratepayers, and accept a substantially lower

    return on other prematurely retired SONGS assets.

    Ratepayers will still pay approximately $3.3 billion in costs over ten years

    (2012-2022), including costs of power the Utilities purchased for its customers

    after the outage, and recovery of the undepreciated net investment in SONGS

    assets (e.g., Base Plant), excluding the failed SGRP.

    However, instead of the usual authorized rate of return, the settlement

    reduces shareholders return on SONGS investments to less than 3%. The effect is

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 3 -

    ratepayers save approximately $420 million over the ten-year depreciation

    period.

    After a leak was detected in a new Unit 3 replacement steam generator

    (RSG) on January 31, 2012, neither SONGS reactor unit (Units 2 and 3) generated

    electricity for ratepayers.1 In June 2013, SCE decided to permanently shut down

    both units. The Utilities initially asked to keep several different categories of

    expenses, both unusual and routine, collected from ratepayers in 2012 and

    thereafter.

    SCE and SDG&E both have an ownership interest in SONGS.2 The

    Commission filed this Order Instituting Investigation (OII) on October 25, 2012,

    commencing an investigation into the SONGS shut down. The OII was

    consolidated with our deferred general rate reviews of 2012 SONGS-related

    expenses for each utility3 and the reasonableness review of each utility’s

    recorded costs for replacing four steam generators at SONGS.4 The Utilities and

    other parties provided substantial testimony, evidence, and argument during the

    proceedings to date, including claims by some that SCE bore fault in the design

    of the RSGs.

    Although hearings were held for early phases of the OII, no final decisions

    have been adopted by the Commission in the consolidated proceedings.

    1 Unit 2 was non-operational in January 2012 due to a scheduled refueling outage.

    2 Edison is the majority owner and the operator of the SONGS facility; The City of Riverside also holds a fractional ownership share.

    3 Application (A.) 13-01-016 (Edison);

    4 A.13-03-015; The replacement of the four steam generators was approved by the Commission in D.05-12-040 which ordered a reasonableness review of the Utilities’ expenses related to the replacement project after completion.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 4 -

    Furthermore, hearings have not been held on issues related to review of expenses

    for the Commission-approved SGRP.5 As part of that cost review in Phase 3, we

    would have looked at whether SCE acted reasonably as a plant operator, and

    how the SGRP expenses should be divided between utility customers and utility

    shareholders.

    On April 2, 2014, six parties: SCE, SDG&E, Office of Ratepayer

    Advocates, The Utility Reform Network, Friends of the Earth), and Coalition of

    California Utility Employees (collectively, Settling Parties) served a Joint Motion

    for Adoption of Settlement Agreement to resolve all issues in the consolidated

    proceedings. The Settling Parties fairly reflect a diverse array of affected

    interests in this proceeding.

    Alliance for Nuclear Responsibility, Women’s Energy Matters, Coalition to

    Decommission San Onofre, and Ruth Henricks (collectively, Opposing Parties)

    filed comments challenging various elements of the proposed settlement.

    Opposing Parties primarily reject the settlement because the Commission has not

    completed its investigation into whether SCE shares culpability with Mitsubishi

    Heavy Industries (Mitsubishi), the designer and manufacturer, for “design

    errors” in the RSGs. Opposing Parties are optimistic the evidence will show SCE

    has whole or partial fault related to the defective RSG design, shifting liability for

    some costs.

    On September 5, 2014, the assigned Commissioner and Administrative

    Law Judges issued a ruling requesting the Settling Parties make certain

    modifications to the proposed settlement agreement in support of the public

    5 Decision (D.) 05-12-040 (A.04-02-026).

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 5 -

    interest. The ruling identified our public interest concerns with some provisions,

    including a failure to address “external” consequences of the shutdown, i. e.,

    increases to greenhouse gases due to power purchases from non-nuclear sources.

    The Settling Parties accepted the changes and submitted the Amended

    Agreement.6

    Based on the entirety of the record established to date, and after thorough

    consideration of the Settling Parties' arguments, the opposition by Opposing

    Parties, and other parties’ comments, we determine that the modified settlement,

    is a reasonable, efficient and timely resolution of this investigation. Although

    more parties have since voiced support, it is not an all-party settlement.

    The settlement establishes ratemaking treatment for the different expense

    categories, primarily by establishing February 1, 2012 as the key date for

    reducing ratepayer costs and calculation of refunds.

    Significant features of the settlement include the following:

    As of February 1, 2012: (1) ratepayers stop paying for the Utilities’ investment in the shutdown RSGs; (2) SGRP capital-related revenue collected thereafter is refunded to ratepayers; and (3) depreciation of approximately $100 million previously collected, when the RSGs produced electricity, is retained by the utilities;

    As of February 1, 2012, approximately $1 billion of SCE’s non-SGRP investment in SONGS is removed from rate base and recovered at a reduced rate of return (less than 3% through 2014) and over an extended (10-year) amortization period; the net difference is estimated to be a reduction to the Utilities of approximately $419 million, present value revenue requirement;

    6 Joint Submission of Amended Settlement Agreement September 24, 2014.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 6 -

    For 2012, SCE will keep $389 million for Operations and Maintenance expenses and will not recover in rates approximately $99 million spent in excess of the amount provisionally authorized in its 2012 General Rate Case;

    The Utilities recover all costs for power purchased from January 1, 2012 until after the settlement is adopted.

    A sharing formula allocates between ratepayers and shareholders any recovery from insurance7 or claims against Mitsubishi. After deducting litigation costs, as modified, the ratepayers and shareholders will share 50%/50% in all recovery from the pending multi-billion arbitration claim by the Utilities against Mitsubishi.

    Refunds due to ratepayers will be credited to each utility’s under-collected Energy Resource Recovery Account balance upon adoption of the settlement by the Commission to reduce otherwise approved rate increases.

    Directs the Utilities to develop a multi-year project associated with the University of California (UC) or UC-affiliated entities, funded by shareholder dollars, to spur immediate, practical, technical development of devices, methodologies, and processes to reduce emissions at existing and future California power plants tasked to replace the lost SONGS generation.

    In this decision we address, and are unpersuaded by the arguments by

    Opposing Parties urging the Commission not to adopt the settlement. Several

    other parties, namely California Large Energy Consumers Association, Alliance

    for Retail Markets/Direct Access Coalition, Joint Minority Parties, and World

    Business Academy have subsequently voiced general or conditional support

    (e.g., with implementation advice) for the proposal.

    7 Nuclear Energy Insurance Limited.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 7 -

    In sum, the Commission is satisfied that the amended and restated

    settlement will result in just and reasonable rates, is consistent with the law,

    reasonable in light of the whole record, and in the public interest.

    1. Background

    In Decision (D.) 05-12-040, the Commission authorized replacement of the

    four steam generators at the San Onofre Nuclear Generating Station (SONGS)

    Units 2 (U2) and 3 (U3), to be followed by a reasonableness review of the project

    costs after completion. The Commission provided a conditional presumption of

    reasonableness for the Steam Generator Replacement Project (SGRP) expenses, if

    actual total costs did not exceed the adopted estimate of $680 million (in 2004$).8

    However, the Commission reserved the option to undertake a reasonableness

    review of costs, even if within the accepted cost cap.9 To what extent ratepayers

    are responsible for the costs of the SGRP is at issue in this proceeding.

    Southern California Edison Company (SCE) contracted with Mitsubishi

    Heavy Industries (Mitsubishi) for the design and manufacture of the

    Replacement Steam Generators (RSG). U2 went online in January 2010 with its

    new RSGs, and U3 followed in January 2011. On January 10, 2012, U2 was taken

    out of service for a scheduled Refueling Outage (RFO) and expected to return to

    service on March 5, 2012. U3 was taken offline on January 31, 2012, after station

    operators detected a radiation leak in a steam generator tube. Evidence of

    similar types of excess vibration wear were found in the tubes of both the U2 and

    8 In D.11-05-035, we reduced the $680 million approved by D.05-12-040 to $670.8 million to reflect changes in the project’s scope.

    9 D.05-12-040 at Ordering Paragraph (OP) 11, as modified by D.11-05-035.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 8 -

    U3 RSGs, although less advanced in U2. The Utilities began recovering

    associated RSG costs in rates after each unit went online.

    In February 2012, the United States Nuclear Regulatory Commission

    (NRC)10 sent an inspection team to examine the RSG tube damage and SCE’s

    response. The NRC then issued a Confirmatory Action Letter, confirming SCE’s

    agreement not to restart the units until SCE had obtained NRC permission to

    restart.11 The team found SCE’s plant operators responded to the January 31

    tube leak “in accordance with procedures and in a manner that protected public

    health and safety. Plant safety systems also worked as expected during the

    event.”12 Nonetheless, SCE was faced with a set of decisions including how

    much time and money to spend figuring out what went wrong, whether it was

    feasible to fix the RSGs to NRC specifications, and how to manage reliability of

    electrical service during the extended outages.

    During and after 2012, SCE recorded expenses for various SONGS-related

    actions including inspection, analysis, and repair activities related to the RSGs, as

    well as for continuing operations and some previously planned capital projects.

    In June 2012, SCE began preliminary work to put U3 into Preservation Mode.13

    10 Arizona v. United States, 132 S. Ct. 2492, 2501 (Radiological safety represents an arena of preemption that "Congress, acting within its proper authority, has determined must be regulated by its exclusive governance.")

    11 NRC Confirmatory Action Letter (March 27, 2012); Order Instituting Investigation (OII) Attachment A.

    12 SONGS--NRC Augmented Inspection Team Report 05000361/20122007 and 05000362/20122007 (June 18, 2012) (AIT Report) at Executive Summary; available at

    http://pbadupws.nrc.gov/docs/ML1218/ML12188A748.pdf

    13 SCE-10 at Q4 (Preservation Mode is a temporary state of non-operation where the nuclear fuel is removed).

    http://pbadupws.nrc.gov/docs/ML1218/ML12188A748.pdf

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 9 -

    San Diego Gas & Electric Company (SDG&E), as a minority owner, was billed by

    SCE for its share of SONGS-related expenses. SCE and SDG&E (collectively

    Utilities) have also had to purchase power to replace power lost due to the

    SONGS outages. To the extent these purchases have been more costly than the

    price of the lost power, ratepayers have borne the consequential expense.

    Although SCE submitted a plan to NRC in October 2012 to restart the

    units, neither U2 nor U3 generated electricity again. Instead, the NRC eventually

    referred SCE’s proposed restart plan14 to the Atomic Safety Licensing Board

    (ASLB) which concluded SCE would need to obtain a license amendment, a

    potentially lengthy process.15 On June 7, 2013, SCE announced it would not seek

    to restart either SONGS unit.

    During 2012, both SCE and SDG&E had pending general rate cases (GRC)

    wherein each utility included forecasts for test year 2012 SONGS-related

    expenses which assumed a fully operational generation facility. The

    Commission declined to give final approval to either utility’s estimated

    SONGS-related expenses in the GRCs, due to the non-operation of both units

    after January 2012. Instead, the Commission deferred final reasonableness

    review of that portion of revenue requirement to this investigation, to be instead

    based on actual 2012 expenses in light of the changed circumstances.16 The

    14 SCE Response to NRC Confirmatory Action Letter (October 3, 2012), available at http://pbadupws.nrc.gov/docs/ML1335/ML13357A058.pdf

    15 ASLB Memorandum and order (May 13, 2013), The September 11, 2014 Administrative Law Judges’ Ruling Taking Official Notice of Documents and Addressing Various Motions took official notice of this document, available at http://pbadupws.nrc.gov/docs/ML1313/ML13133A323.pdf

    16 Each utility was permitted to collect an amount up to the preliminarily approved amounts, pending review in applications to be filed and consolidated with the OII.

    http://pbadupws.nrc.gov/docs/ML1335/ML13357A058.pdfhttp://pbadupws.nrc.gov/docs/ML1313/ML13133A323.pdf

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 10 -

    Utilities have already collected the majority of their 2012 and 2013

    SONGS-related expenses in rates, subject to refund. Rate recovery of these

    expenses and for excess power purchases is at issue here.

    In addition, Public Utilities Code17 Section (§) 455.5(a) grants the

    Commission discretion to remove from rates the value of any portion of an

    electric generation facility which remains out of service for nine or more

    consecutive months, along with “related” expenses. This proceeding concerns

    what portion of the SONGS plant the Commission could remove from rate base

    and when. Parties differed as to whether all plant value and costs at SONGS

    should be removed from rates as no longer “used and useful,”18 or whether some

    portions of the plant (e.g., cooling systems, toxic control-related structures and

    systems, storage of spent nuclear fuel) and related expenses (e.g., security,

    personnel) are still necessary and, therefore, recoverable from ratepayers.

    Some parties contend that if SCE acted imprudently in managing the

    design of the RSGs, then ratepayers have no responsibility to pay for any costs at

    SONGS after January 31, 2012 (and perhaps before).

    SCE,19 the NRC,20 and Mitsubishi21 have all undertaken studies to

    determine the cause of the excess tube-to-tube wear (TTW) in the RSGs.

    Although responsibility for the problem is disputed, there is apparent agreement

    17 Unless otherwise indicated, all references to code sections refer to the Pub. Util. Code.

    18 § 454.8

    19 SCE-04 at 82 (On April 23, 2012, SCE issued U2 tube wear Root Cause Analysis (RCA) which identified the cause of TTW as Fluid Elastic Instability (FEI)).

    20 Investigation (I.) 12-10-013 OII Attachment A, AIT Report.

    21 Mitsubishi Root Cause Analysis (October 12, 2012) at http://pbadupws.nrc.gov/docs/ML1306/ML13065A097.pdf.

    http://pbadupws.nrc.gov/docs/ML1306/ML13065A097.pdf

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 11 -

    that the cause of the unexpected TTW was due to FEI. The AIT Report found

    that both the U2 and U3 SGs were susceptible:

    “…the NRC team concluded that both units’ steam generators were of similar design with similar thermal hydraulic conditions and configurations. Therefore, SONGS Unit 2 steam generators are also susceptible to this phenomenon (emphasis added).”22

    The RSGs include some differences from the design of the original steam

    generators (OSGs). These differences have sparked questions about the nature

    and purpose of the design changes, and what SCE knew or should have known

    about the safety implications of the changes. Responsibility for failure to

    discover the potential for the excess wear, and consequential damages therefrom,

    are subjects of a pending arbitration claim filed by SCE, since joined by the

    SONGS co-owners, against Mitsubishi.23

    Additionally, SCE and SDG&E state they have submitted claims and

    proofs of loss to Nuclear Electric Insurance Limited (NEIL) to recover a portion

    of the costs to purchase power to replace that lost from SONGS.24 It is unclear

    whether the Utilities are pursuing additional claims under the accidental

    property damage coverage, arising from facility damage related to the eventual

    shut down of the SONGS plant.

    22 I.12-10-013 OII Attachment A, AIT Report.

    23 International Chamber of Commerce Arbitration (October 16, 2013); available at http://songscommunity.com/docs/101613_SCE_RFA_Redacted_Final.pdf.

    24 Joint Motion at 7.

    http://songscommunity.com/docs/101613_SCE_RFA_Redacted_Final.pdf

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 12 -

    On November 27, 2013, the NRC issued a Notice of Non-Conformance25 to

    Mitsubishi based on finding the company did not establish measures for design

    control interfaces: the output of the thermal-hydraulic code and input to the

    flow induced vibration analysis software vibration code “were not verified to be

    in accordance with {Mitsubishi} design requirements.”26

    The NRC also issued a Notice of Violation27 to SCE which found design

    control measures were not established to provide for verifying or checking the

    adequacy of the output of the thermal-hydraulic code and input to the vibration

    code to be in accordance with NRC requirements.

    These Notices have been admitted to the record by ALJ ruling.28

    2. Procedural History

    Pursuant to § 455.5, the Commission issued an OII on October 25, 2012,

    initiating a multi-part investigation into the actions and expenses of Utilities

    associated with the extended outage at SONGS:

    This investigation will consider the causes of the outages, the utilities’ responses, the future of the SONGS units, and the resulting effects on the provision of safe and reliable electric service at just and reasonable rates.29

    25 Administrative Law Judges’ Ruling Taking Official Notice of Documents and Addressing Various Motions (September 11, 2014) at 4.

    26 October 17, 2013 Mitsubishi reply to NRC (incorporated by reference in November 27, 2013 NNC to Mitsubishi) at 2.

    27 Ibid.

    28 Ibid., Notice of Non-Conformance to Mitsubishi (November 27, 2013) and Notice of Violation to SCE (December 23, 2013).

    29 OII at 21.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 13 -

    The OII identified rate recovery issues including: (1) review of all post

    2011 Operations & Maintenance (O&M) costs and capital spending; (2) costs of

    scheduled RFO and emergent activities; (3) removal of non-useful generation

    assets from rate base; and (4) various questions around the costs, viability, and

    prudency of the SGRP approved in D.05-12-040.

    SCE and SDG&E were ordered to separately record all SONGS-related

    expenses, beginning as of January 1, 2012, into a SONGS outage memorandum

    account (SONGSOMA),30 subject to refund, and report the expenses to the

    Commission on a regular basis.31 The Commission later confirmed the order in

    the decision on each utility’s GRC application.32

    Within the OII, the Commission stated its intention to consolidate other

    future proceedings to encompass review of the full range of post-outage costs

    and activities.33 Subsequently, SCE and SDG&E each filed applications for

    reasonableness review of 2012 recorded O&M, non-O&M costs, and capital

    spending,34 for approval of the totality of the SGRP costs,35 and for power

    30 I.12-10-013 at 10-13 and OP 4. The SONGSOMA is different than SCE’s SONGS Memorandum Account (SONGSMA) authorized by D.12-11-051 and SDG&E’s SONGS Balancing Account (SONGSBA) created by D.06-11-026 and most recently reauthorized by D.13-05-010.

    31 SCE reports to the Commission monthly on its SONGSOMA and SDG&E reports on its SONGSOMA quarterly.

    32 D.12-11-051 at Findings of Fact (FOF) 366, Conclusions of Law (COL) 21-22, OP 9, 10 (SCE); D.13-05-010 at FOF 19, COL 7, 8 (SDG&E).

    33 OII at 8-9.

    34 A.13-01-016 (SCE), A.13-03-013 (SDG&E).

    35 A.13-03-005 (SCE), A.13-03-014 (SDG&E).

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 14 -

    purchased during 2012, including replacement of power lost due to the outages.36

    In these applications, the Utilities sought full recovery in rates for all of the

    identified expenses.

    The Utilities served Opening Testimony on December 5, 2012, in response

    to the broad scope of the OII. On December 12, 2012, the ALJ ordered the

    utilities to provide supplemental testimony, inter alia, regarding SONGS: outage

    history, historic forecast and actual expenses, 2012 treatment of fuel contracts,

    reasonableness support for 2012 recorded expenses, calculation of replacement

    power costs, support for meeting a reasonable or prudent manager standard

    post-outage, and for production of reports from NRC and others addressing the

    cause of the outage. Other parties had an opportunity to serve reply testimony,

    and the Utilities were permitted to serve rebuttal.

    A prehearing conference (PHC) was held on January 12, 2013. Due to the

    potentially wide scope and quantity of information necessary for review, the

    assigned Commissioner and ALJ determined that to promote efficient

    administration of the OII, it would be divided into several phases, each with its

    own PHC and Scoping Memo. Among the expected benefits of this approach

    were: (i) resolving the hold-over 2012-2014 revenue requirement first;

    (ii) building a chronological record of 2012 activities to inform the second phase

    determination of whether to remove some or all of SONGS plant from rate base;

    (iii) pacing for certain information not yet known (e.g., pending NRC actions,

    Mitsubishi arbitration, insurance claims); and (iv) consistent decisions between

    phases.

    36 A.13-04-001 (SCE), A.13-03-013 (SDG&E).

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 15 -

    On January 28, 2013 assigned Commissioner Michel Peter Florio and

    ALJ Melanie M. Darling37 issued a Phase 1 scoping memo that set dates for

    parties to serve testimony, established dates for evidentiary hearings, and

    defined the scope of inquiry. In Phase 1, the Commission focused on the

    Utilities’ applications38 for review of 2012 expenses recorded in the SONGS

    memorandum accounts, including an assessment of the reasonableness of SCE’s

    actions and expenditures following the U3 steam generator leak. On May 3,

    2013, the ALJs created a sub-phase, Phase 1A, to develop a method for

    calculating 2012 costs of replacement power.

    In response to the OII, the Utilities argued the Commission lacked

    authority to (1) review and refund 2012 estimates of O&M and capital spending,

    as deferred by the GRC decision; and (2) remove any SONGS assets and

    associated O&M from rate base pursuant to § 455.5, prior to SCE’s 2015 GRC.

    After parties briefed these legal issues, the Assigned Commissioner and

    Administrative Law Judge issued a ruling resolving the questions:39

    (1) Regarding Phase 1, the Commission has legal authority to conduct the deferred final reasonableness review of SONGS-related expenses (100%) sought in SCE’s 2012 GRC and immediately order refunds, if warranted.

    (2) Regarding Phase 2, the Commission has authority pursuant to § 455.5 to remove SONGS assets and associated expenses from rate base in this consolidated proceeding which has been categorized as ratesetting.

    37 On May 1, 2013, ALJ Kevin Dudney was co-assigned to the OII.

    38 These proceedings were consolidated with the OII in an April 19, 2013 ALJ ruling.

    39 Assigned Commissioner and Administrative Law Judge Ruling on Legal Matters (April 30, 2013)

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 16 -

    Several parties participated in Phase 1 and Phase 1A by submitting

    testimony, conducting cross-examination of witnesses, and/or filing post-

    hearing briefs. In addition to SCE and SDG&E, these parties are Office of

    Ratepayer Advocates40 (ORA), The Utility Reform Network (TURN), Alliance for

    Nuclear Responsibility (A4NR), World Business Academy (WBA), Women’s

    Energy Matters (WEM), Joint Parties (comprised of National Asian American

    Coalition, Ecumenical Center for Black Church Studies, Latino Business Chamber

    of Greater Los Angeles and Chinese American Institute for Empowerment), and

    the Coalition to Decommission San Onofre (CDSO).41

    Ruth Henricks (Henricks) and other parties filed several, primarily

    procedural, motions during the Phase 1 period. Motions to alter the Scoping

    Memo, to immediately order refunds, strike testimony, etc. have been filed and

    ruled upon, none of which altered the course of the OII set forth in the Scoping

    Memo, except to clarify that ordinary review of power purchases by both

    Utilities would continue to occur in their respective Energy Resource Recovery

    Account (ERRA) proceedings.

    On February 21, 2013, the ALJ ordered SCE to file its SGRP application by

    March 15, 2013, and to provide supplemental testimony regarding interim

    collection of SGRP costs in rates, calculation of the SGRP revenue requirement,

    and to explain some aspects of SCE’s first SONGSMA report. Other parties had

    40 Formerly known as Division of Ratepayer Advocates (ORA) and filed as such during these proceedings.

    41 Other entities which were granted party status in the OII and participated at some point are : Friends of the Earth (FOE), (CLECA)Direct Access Customer Coalition jointly with the Alliance for Retail Energy Markets (DACC/AReM). Several other parties did not participate in these proceedings.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 17 -

    an opportunity to serve reply testimony, and the Utilities were permitted to

    serve rebuttal. On April 30, 2013, the ALJs ordered SCE to collect and

    summarize relevant cost data which appeared throughout their testimony, and

    to create a chronology of key operational facts and decisions related to the

    outage. Even though no new information was to be included in the reorganized

    SCE exhibit, other parties had an opportunity to submit rebuttal exhibits.42

    Evidentiary hearings in Phase 1 were held from May 13 to 17, 2013.

    Opening and Reply Briefs were filed by SCE, SDG&E, DRA, TURN, A4NR,

    WBA, CDSO, Joint Parties and WEM on June 28, 2013 and July 9, 2013,

    respectively. Evidentiary hearings in Phase 1A were held on August 5 and 6,

    2013. Opening Briefs were filed on August 29, 2013 by SCE, SDG&E, DRA, and

    A4NR. Phase 1A Reply Briefs were filed by SCE, SDG&E, TURN, A4NR, DRA,

    and WEM.

    In addition, the ALJs sought input about the OII issues from the public

    during 2013. They held four public participation hearings regarding the SONGS

    outages: two in Costa Mesa on February 21, 2013 and two in San Diego on

    October 1, 2013.

    A proposed decision (PD) for Phase 1 was published for comment on

    November 19, 2013. Opening Comments were filed on December 9, 2013 by

    WEM, CDSO, Joint Parties, SCE, TURN, CCUE, SDG&E, WBA, and A4NR.

    Reply Comments were filed on December 16, 2013 by SCE, SDG&E, TURN, DRA,

    42 The ruling merely ordered a more coherent presentation of previously served, and revised, cost data, not any new information. However, some corrections were made on the record to the proffered exhibit, SCE-10.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 18 -

    Joint Parties, WBA, and A4NR. However, the Commission has not acted on the

    PD. 43

    Regarding Phase 2, the ALJs ordered the Utilities to provide testimony by

    July 22, 2013 that provided an accounting of the assets and amounts currently in

    rate base for the entire SONGS facility.44 The ruling also required each utility to

    make a proposal for which assets should be removed from rate base, and related

    monthly O&M costs, as of November 1, 2012, and other dates as preferred.

    A PHC for Phase 2 occurred on July 12, 2013. Based on § 455.5, the Phase 2

    Scoping Memo focused on the value of SONGS assets in rate base at different

    points in time, which of these assets and associated costs should be removed

    from rate base, and the ratemaking treatment for removed assets and costs.45

    Phase 2 evidentiary hearings were held October 7 to 11, 2013. Phase 2

    Opening Briefs were filed and served on November 22, 2013 by SCE, SDG&E,

    ORA, TURN, A4NR, WBA, CDSO, WEM, and Henricks.46 Reply Briefs were

    filed and served on December 13, 2013 by SCE, SDG&E, DRA, TURN, ANR,

    WBA, CDSO, and DACC/AReM. No PD for phase 2 has yet been published for

    comment. A list of the exhibits admitted into the record during Phases 1, 1A,

    and 2 is attached hereto as Appendix A.

    43 On January 14, 2014, four Commissioners (Peevey, Florio, Sandoval, Peterman) participated in a noticed all-party meeting to discuss the PD.

    44 ALJ Ruling on Miscellaneous Issues and Setting Phase 2 prehearing Conference (July 1, 2013).

    45 Assigned Commissioner and Administrative Law Judges’ Ruling Determining Phase 2 Scope and Schedule (July 31, 2013).

    46 WBA (on November 22) and CDSO (on November 27) filed and served “corrected” Phase 2 opening briefs; all references to WBA’s and CDSO’s opening briefs in this decision refer to these corrected briefs.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 19 -

    Through many weeks of evidentiary hearings, and review of a substantial

    amount of testimony and other evidence, the parties have had an opportunity to

    weigh the claimed facts associated with: (1) the deferred review of 2012 General

    Rate Case SONGS-related expenses; (2) replacement power costs; and (3) the

    values of SONGS assets in rate base; and (4) which of these assets should be

    removed from rate base pursuant to Public Utilities Code § 455.5.

    On March 20, 2014, SCE, SDG&E, TURN, and ORA served a notice of

    settlement conference to be held on March 27, 2014. On April 3, 2014, SCE,

    SDG&E, TURN, ORA, FOE, and California Coalition of Utility Employees

    (CCUE) (collectively, Settling Parties) filed and served a Joint Motion for

    Adoption of Settlement (Joint Motion). Settling Parties assert the proposed

    Settlement Agreement (Agreement), if approved, “would resolve all issues in the

    OII and consolidated proceedings.”47 It is not an all-party settlement, and is

    strongly opposed by some.

    On April 24, 2014, the ALJs issued a ruling that: (1) ordered Settling

    Parties to post documents supporting or clarifying the Agreement on SCE’s

    SONGS discovery website; (2) ordered Settling Parties to serve supporting

    testimony by May 1, 2014 to provide clarifying information, and support for

    certain numbers referenced in the Agreement in response to questions posed by

    the ALJs in the ruling; (3) scheduled and set the agenda for an evidentiary

    hearing pursuant to Rule 12.3 to hear material contested issues of fact asserted in

    the Agreement; and (4) scheduled and set the agenda for a community

    47 Joint Motion at 1.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 20 -

    information meeting near SONGS on June 16, 2014.48 Settling Parties, jointly and

    separately, timely served the supplemental testimony.

    On May 7, 2014 (or earlier), comments on the Joint Motion were filed by

    WBA, CDSO, Joint Parties, A4NR, CCUE, CLECA, DACC/AReM, WEM, and

    Henricks.49 On May 14, 2014, the ALJs conducted the evidentiary hearing, took

    submission of the supplemental testimony, heard sworn oral testimony from

    Settling Parties and permitted cross-examination of the Settling Parties’ witnesses

    by non-settling parties.50 A list of the exhibits admitted into the record at the

    hearing on the Agreement is included in Appendix A. On May 22, 2014, Reply

    Comments on the Joint Motion were filed by Henricks, Joint Parties, Settling

    Parties, SCE, CDSO, SDG&E, A4NR, and WEM.

    As part of her Reply Comments, Henricks included a request that ALJ

    Darling be reassigned pursuant to Rule 9.4 based on ”demonstrated bias in favor

    of SCE and prejudice against ratepayers in this case.” Henricks objected to

    introductory statements made by ALJ Darling at the evidentiary hearing for the

    benefit of webcast viewers. The Chief ALJ, in consultation with the President of

    the Commission, denied the motion based on Rule 9.5 which expressly finds it is

    not bias for an ALJ to express views on a legal, factual, or policy issue presented

    in the proceeding.51

    48 Commissioners Peevey, Florio, and Picker attended the scheduled Community Information Meeting on June 16, 2014 as observers.

    49 Henricks filed an “Objection” which Docket Office characterized as “comments.”

    50 Commissioners Peevey and Florio attended the hearing as observers.

    51 Chief Administrative Law Judge’s Ruling denying request for Reassignment for Cause (June 26, 2014).

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 21 -

    On September 5, 2014, the assigned Commissioner and the ALJs issued a

    Ruling Requesting the Settling Parties to Adopt Modifications (Modification

    Ruling) to the proposed Settlement Agreement. The request was based on a

    preliminary assessment which identified a few provisions that needed to be

    clarified or modified to meet the public interest even when considered as part of

    the whole settlement package. The Settling Parties dispute the view that the

    identified provisions are not in the public interest, however, they voluntarily

    accepted the requests and amended and restated the Agreement to accomplish

    our public interest objective.52 Several non-settling Parties filed comments ten

    days later confirming their continued opposition. On September 24, 2014, the

    Settling Parties filed and served an “Amended and Restated Settlement

    Agreement” (Amended Agreement) which included the requested modifications.

    This proceeding was submitted on September 24, 2014

    3. Standard of Review

    The Commission’s standard of review for this contested settlement

    pursuant to Rule 12.1(d) is that the Commission must find a settlement

    “reasonable in light of the whole record, consistent with the law, and in the

    public interest.” The standard of proof is a preponderance of the evidence.53

    In determining whether a settlement is fair, adequate, and reasonable, the

    Commission reviews a number of factors. These factors include whether the

    settlement reflects the risks, expense, complexity, and likely duration of further

    litigation; whether it fairly and reasonably resolves the disputed issues and

    52 Joint Settling Parties Comments on Modification Ruling.

    53 D.13-04-012 at 3.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 22 -

    conserves public and private resources; and whether the agreed-upon terms fall

    clearly within the range of possible outcomes had the parties fully litigated the

    dispute.54 The Commission also has considered factors such as whether the

    settlement negotiations were at arm's length, whether the parties were

    adequately represented, and how far the proceedings had progressed when the

    parties settled.55

    Below we review the settlement provisions, and the parties’ arguments in

    support and in opposition.

    4. The Settlement Agreement

    4.1. Joint Motion to Adopt Settlement Agreement

    Settling Parties present the Agreement as a fair compromise of contested

    issues which resolves all issues in the consolidated proceedings, duly authorized

    by Article 12 of the Commission’s Rules of Practice and Procedure.56 The Joint

    Motion includes the general positions advocated by the parties in the OII, the

    terms of the Agreement, argument that the Agreement meets the Commission’s

    standards for review of settlements, proposes a process for consideration of the

    Agreement, including possible Commission-proposed modifications, and

    requests the Commission expedite consideration, stay the OII and make specific

    findings with respect to the Agreement.

    The Settling Parties assert the Agreement is the result of “hard-fought”

    negotiations over many months by SCE, SDG&E, DRA and TURN where each

    party “compromised substantially” from positions taken in testimony and

    54 D.96-05-070, 66 C.P.U.C. 2d 314, 317 (1996).

    55 D.00-11-041 at 6.

    56 Joint Motion at 1-2.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 23 -

    briefs.57 Although CCUE, which represents utility employees, and FOE, an

    environmental organization, did not participate in the negotiations prior to the

    Settlement Conference, each joined in the Agreement, contending it is a “fair

    compromise of the disputed issues.”58 The Settling Parties state the combination

    of Utilities, DRA, TURN, FOE and CCUE represents a broad coalition of interests

    represented in the OII.

    However, Rule 12.1(a) provides that settlements need not be joined by all

    parties. This is not an all-party settlement. As discussed below, some parties ask

    the Commission to deny the motion and reject the Agreement.

    4.2. Terms of Settlement Agreement

    Generally, the Agreement divides costs from certain categories (e.g. O&M,

    capital cost of RSGs) into different categories for payment (e.g. refunds to

    ratepayers, allowed past or current rate recoveries, future rate recoveries). The

    Settling Parties responded to the September 5, 2014 Ruling Requesting

    Modifications by preparing and serving an Amended and Restated Settlement

    Agreement (Amended Agreement) incorporating the requested changes. The

    Amended Agreement is attached hereto as Appendix B.

    a. Steam Generator Replacement Project

    ¶4.2 specifies that the “Capital-Related Revenue Requirement for the

    SGRP will be terminated as of February 1, 2012.” The Utilities will refund all

    Capital-Related Revenue Requirement59 of the SGRP collected after that date, but

    will retain all amounts collected in rates prior to that date. The Utilities will not

    57 Id. at 8.

    58 Ibid.

    59 Defined in Agreement ¶2.9.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 24 -

    recover the Net Book Value60 of the SGRP as of that date, which is $597 million

    for SCE and $160.4 million for SDG&E according to ¶3.36.

    b. Base Plant

    ¶4.3 specifies that the Utilities share of Base Plant61 will be removed from

    rate base as of February 1, 2012, and this amount will be recovered at a reduced

    rate of return over ten years (February 1, 2012 to February 1, 2022). As of

    February 1, 2012 SCE’s share of Base Plant was $622 million and SDG&E’s share

    was $165.6 million, excluding Construction Work in Progress (CWIP).62 The

    Utilities will retain all Capital-Related Revenue Requirement for Base Plant

    collected before February 1, 2012; amounts collected after that date that exceed

    what would be allowed by the Agreement will be returned.63 The rate of return

    for Base Plant after February 1, 2012 will be calculated as “the Utility’s

    Authorized Cost of Debt plus 50% of the Utility’s Authorized Cost of Preferred

    Stock, weighted by the amount of debt and preferred stock in the Utility’s

    authorized ratemaking capital structure.”64 The rate of return for SCE for 2012 is

    2.95% and 2.62% for 2013-2014. For SDG&E, the rate of return for 2012 is 2.75%

    and 2.35% for 2013-2014.65 Finally, ¶4.4 provides that each Utility would be

    60 Agreement ¶2.24.

    61 Agreement ¶2.6.

    62 Agreement ¶3.37.

    63 Agreement ¶4.12.

    64 These Authorized Cost terms are defined in Agreement ¶¶2.4 and 2.5. This rate of return is adjusted for deferred taxes. The rate of return on common equity is excluded from the calculation.

    65 In both cases, these rates of return do not reflect income taxes associated with the return on preferred equity, property taxes, or franchise fees and uncollectibles; each Utility would gross-up its revenue requirement accordingly.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 25 -

    allowed to exclude the Base Plant regulatory asset from future measurements of

    its ratemaking capital structure.

    c. Materials and Supplies (M&S), Construction Work In Progress (CWIP), and Nuclear Fuel

    M&S, CWIP, and Nuclear Fuel are all recovered in a manner similar to

    Base Plant, with some variations. For M&S and Nuclear Fuel, the Utilities

    receive an incentive (5%) to salvage the value of the asset as best as possible. For

    CWIP, the recovery period depends on whether or not the project is completed

    and goes into service. Details are summarized in the following table.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 26 -

    Item Amortization Period

    Rate of Return

    Dollar Amount (12/31/2013) 5% Incentive Notes

    References (Agreement Section)

    M&S Same as base plant

    Same as base plant

    SCE: $99 million; SDG&E: $10.4 million Yes

    4.5, 4.13, 2.21, 3.39

    Nuclear Fuel

    Same as base plant

    Commercial paper

    SCE: $477 million; SDG&E: $115.8 million inventory (excludes cancellation and sales)

    Yes, of net proceeds (proceeds less cost of storage, sale, and making fuel saleable), AND of purchase obligations minus cancellation costs

    Amount recovered will be existing investment plus cancellation cost, less proceeds from sales

    4.6, 4.7, 4.13, 2.17, 2.18, 2.30, 3.38

    CWIP - Cancelled

    Same as base plant

    AFUDC until 1/31/2012then same as base plant

    SCE: $153 million; SDG&E: unstated no

    4.8, 4.13, 2.13(a), 3.40

    CWIP - Completed

    Starting the earlier of project completion or the end of the month of the effective date of this decision, and ending 2/1/2022

    AFUDC until amoritization begins. AFUDC rate as authorized until 1/31/2012then same as base plant. During amortization, same return as base plant.

    SCE: $302 million; SDG&E unstated no

    4.8, 4.13, 2.13(b), 3.41

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 27 -

    d. O&M and Non-O&M Expenses

    Under the agreement, the Utilities will generally recover the lower of their

    recorded or preliminarily authorized66 expenses. Costs for inspections and

    repair of the RSGs are included in recorded O&M, distinguished from “Base” or

    routine O&M. Excess recoveries, or amounts later recovered from the Nuclear

    Decommissioning Trusts will be refunded to ratepayers. 2014 costs are subject to

    review by this Commission in the future. ¶4.9 (k) specifies that the “Utilities

    shall utilize a formula agreeable to all Settling Parties for allocating

    company-wide expenses to SONGS” for purposes of Non-O&M Expenses.

    Details are provided in the following table.

    Item Year Recovery

    O&M 2012 Retain revenue provisionally authorized; revenue can be applied to recorded O&M (Base and SGIR) and severance; SDG&E to refund any revenues beyond recorded O&M

    O&M 2013 Recover recorded costs up to the provisionally authorized amounts; any excess recoveries or amounts recovered from the decommissioning trusts to be refunded

    Non-O&M 2012 Retain all revenue, except that SCE will refund to ratepayers any revenues that exceed the provisional authorization by more than $10 million; SDG&E will retain revenue for all recorded Non-O&M Expenses

    Non-O&M 2013 All recorded expenses recovered; Utilities shall seek recovery from decommissioning trusts, and refund such recoveries

    O&M and Non-O&M

    2014 Recover recorded, refund excess recoveries and any recoveries from decommissioning trusts

    e. Replacement Power

    ¶4.10 allows the Utilities to recover all “replacement power costs”

    associated with the non-operation of SONGS and amortize these costs in rates by

    December 31, 2015.

    f. Third Party Recoveries

    66 By the previous GRC decisions: D.12-11-051 and D.13-05-010.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 28 -

    As modified by the Amended Agreement, ¶4.11 orders each utility to

    establish two memorandum accounts (or sub-accounts) to track SONGS litigation

    costs and recoveries67 from NEIL and Mitsubishi. The accounts will track all

    costs recorded since January 31, 2012. Any negative balance of these accounts

    (i.e. Recoveries in Excess of Costs) will be shared between ratepayers and the

    Utilities according to ¶4.11 (c). For NEIL recovery: the Utilities’ share is 5% and

    95% to rate payers in the Outage account; the Utilities’ share is 17.5%, with 82.5%

    to ratepayers in the Other Recoveries account. Ratepayers will receive their

    share via a credit to each Utility’s ERRA account.

    The original Agreement provided for a three-tiered allocation of recoveries

    from Mitsubishi with the Utilities getting a significant majority of the first

    $1.1 billion. As modified, the ratepayers and Utilities share the net Mitsubishi

    recoveries equally (50/50).

    The first portion of Mitsubishi recoveries will be distributed to balancing

    accounts of the Utilities: SCE ratepayers’ first $282 million will be credited to

    SCE’s Base Revenue Requirement Balancing Account and SDG&E ratepayers’

    first $71 million will be credited to SDG&E’s Non-Fuel Generation Balancing

    Account. Any further ratepayer recoveries will be distributed by reducing the

    regulatory assets described above.

    The Utilities will have full discretion to settle or otherwise resolve claims

    against NEIL and Mitsubishi, and will notify the Commission promptly of such

    resolution, subject to two conditions: the confidentiality of the resolution and

    that the Commission will not review the reasonableness of the resolution; except

    67 See: Agreement ¶2.43-2.44 for definitions.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 29 -

    that, the Amended Agreement requires the Utilities to provide documentation of

    any final resolution of third-party litigation and of SONGS Litigation Costs. The

    Commission may review the documentation to ensure Litigation Costs are not

    out of proportion to the recovery obtained and that ratepayer credits are

    accurately calculated. SONGS Litigation Costs shall not be considered in the

    recorded costs used to develop future general rate case forecasts.

    Close Proceeding and Proposed Findings of Fact

    ¶4.16 and ¶4.17 state the intent of the Agreement to resolve all

    proceedings consolidated with this Investigation, enumerate several factual

    findings for the CPUC to make, and request the withdrawal of the PD on Phase 1

    and Phase 1A. The proposed findings are summarized below:

    Proceeding(s) Findings

    A.13-03-005, A.13-03-014

    Total cost of SGRP was $612.1 million in 2004 dollars (100% share). SCE used appropriate inflation indexes to deflate these costs to 2004 dollars. No further reasonableness review of SGRP costs is required, and each Utility may retain all revenues for the SGRP prior to February 1, 2012.

    A.13-01-016, A.13-03-013

    No further reasonableness review of the 2012 costs recorded in SCE’s SONGSMA and SDG&E’s SONGSBA is required.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 30 -

    5. Parties’ Positions

    5.1. Settling parties

    Settling Parties contend the proposed Agreement meets the Commission’s

    requirements for approval: it is consistent with the law, reasonable in light of the

    whole record, and in the public interest. The Joint Motion also identifies four

    factors the Commission has included when previously reviewing settlements:

    (1) the risk, expense, complexity and likely duration of further litigation;

    (2) whether the settlement negotiations were at arms-length; (3) whether major

    issues were addressed; and (4) whether the parties were adequately

    represented.68

    In support of approval, Settling Parties assert “[T]he Utilities, TURN, and

    ORA---represented by experienced CPUC practitioners---negotiated in good

    faith, bargained aggressively, and, ultimately, compromised.69” Furthermore,

    they argue, the result is a comprehensive resolution of all major issues, which

    reduces ratepayer costs for protracted litigation, conserves scarce Commission

    resources, and reduces the risk of unacceptable results.

    Additionally, the Settling Parties assert it is “critical” to consider the

    Agreement as a whole, not just the individual provisions.70

    68 Joint Motion at 36 [citing e.g., 40 CPUC 2nd 301, 326].

    69 Ibid.

    70 Id. at 36-37 [citing, D.11-05-018 at 16 (…we do not base our conclusion on whether any single provision is the optimal result. Rather, we determine whether the settlement as a whole produces a just and reasonable outcome.”)].

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 31 -

    5.1.1. The Agreement is Reasonable in Light of the Whole Record

    The Agreement is reasonable in light of the whole record, Settling Parties

    argue, because on “a basic level” ratepayers pay for power they received and

    don’t pay for the SGRP after the outages.71 The result is presented as a fair and

    reasonable solution, reached as a result of substantial negotiations, and is within

    the range of potential outcomes proposed by the Settling Parties during the OII.

    Settling Parties assert the record contains sufficient information for the

    Commission to make this finding, given the thousands of pages of written

    testimony on a wide range of issues, from many different witnesses, covered by

    three phases of hearings over 12 days, with lengthy post-hearing briefs filed by

    the Settling Parties. The Utilities separately note they have already responded to

    over a thousand data requests from the parties.72 Settling Parties claim the

    magnitude of information and depth of analysis in the record underpinned the

    success of the substantial negotiations undertaken by the Utilities, TURN and

    ORA.

    Settling Parties claim the negotiated outcomes of various provisions in the

    Agreement, including recoveries and disallowances, demonstrate that

    compromises were reached for thoroughly litigated positions.73 On the other

    hand, they claim that potential Phase 3 findings on the causes of tube wear and

    SCE’s prudence in managing the SGRP are unnecessary to find the Agreement is

    reasonable in light of the whole record. Instead, they argue the primary purpose

    71 Joint Motion at 39.

    72 Id. at 37.

    73 Ibid.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 32 -

    of this settlement is to avoid the costs, time, and burden on all parties to get to

    the cause of the damage and reasonableness of consequential costs.

    Lastly, Settling Parties state the Agreement reflects a fair resolution of their

    respective litigation positions. In support, they provide an illustrative

    comparison of the present value of the SONGS revenue requirement for each

    settling party’s litigation position with the results of the proposed Agreement.74

    The reduction to the Utilities’ original revenue requirements indicates significant

    concessions which, according to Settling Parties, reflects write-offs of more than

    $800 million ($nominal) in SGRP-related costs after January 31, 2012.75

    CCUE offered additional comments in which it stated its support for the

    Agreement was primarily based on treatment of 2012-2013 O&M costs,

    particularly severance costs because they argue staff retention was necessary to

    operate plant equipment when restart was still a possibility.76

    In an attachment to the original agreement, Settling Parties included an

    estimate of the Present Value Revenue Requirement (PVRR) for each Utility

    based on the litigation positions of the Utilities, DRA, and TURN, in comparison

    to the outcome under the Agreement. The table below shows an excerpt of this

    PVRR, as updated in exhibits SCE-56 and SDGE-23, with the combined revenue

    requirements of the two Utilities. Note that the PVRR is calculated at a discount

    rate of 10%.

    74 Id., Attachment 2.

    75 Id. at 39.

    76 CCUE Opening Comments (OC) at 2-3.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 33 -

    SCE and SDG&E All values in $ millions

    TURN Litigation DRA Litigation Settlement

    Utilities Litigation

    PVRR @ 10% $ 2,692.5 $ 2,542.9 $ 3,284.5 $ 4,732.9

    RSG $ - $ 100.9 $ - $ 917.7

    Base Plant $ 1,127.3 $ 908.9 $ 1,319.4 $ 1,738.5

    O&M $ 900.5 $ 868.5 $ 970.6 $ 1,039.6

    Nuclear Fuel $ 520.0 $ 519.9 $ 477.3 $ 519.9

    Replacement Power $ 144.7 $ 144.7 $ 517.2 $ 517.2

    5.1.2. The Agreement is Consistent with the Law

    Settling Parties state the terms of the Agreement comply with all

    applicable statutes and prior Commission decisions, and assert they considered

    these statutes and decisions during the settlement process.77 In particular,

    Settling Parties claim the Agreement is consistent with § 451 and § 455.5.

    Section 455.5, authorizes the Commission to remove from rate base the

    value of portions of a generating facility that has been out of service for nine or

    more months, along with related expenses. Settling Parties believe the

    Agreement is consistent with applicable law because the SGRP and SONGS Base

    Plant are removed from rate base as of February 1, 2012, and $99 million in post-

    outage RSG inspection and repair costs are disallowed.78

    Section 451 requires that rates be just and reasonable. Settling Parties,

    referencing the revenue requirement comparison chart attached to the Joint

    Motion, claim the terms are just and reasonable because the parties have

    compromised their positions.

    77 Joint Motion at 39.

    78 Id. at 39-40.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 34 -

    5.1.3. The Agreement is in the Public Interest

    The Commission has previously determined that a settlement meets the

    “public interest” criterion if it “commands broad support among participants

    fairly reflective of the affected interests” and “does not contain terms which

    contravene statutory provisions or prior Commission decisions.”79 Settling

    Parties cite the fact they are comprised of both utilities, two “prominent

    ratepayer advocate groups in Commission practice, a global network of

    environmental activists, and a labor group representing hundreds of affected

    SONGS employees;” these parties all participated in the OII prior to the

    Agreement. 80 ORA and TURN were especially active in all phases of the

    consolidated proceedings to date. Settling Parties emphasize that all signatories

    to the Agreement have stated it is a reasonable compromise of their respective

    positions.

    Settling Parties argue the public interest is also served by settlement of the

    entire OII because, if adopted, it avoids the cost of further litigation and frees up

    Commission resources for other proceedings.81 They view the potential Phase 3

    as extremely time-consuming and complex litigation, potentially taking a year or

    two, delaying refunds, and generating discovery relating to a ten year period and

    thousands more pages of largely technical testimony. Instead, Settling Parties

    contend the Agreement provides “substantial relief to ratepayers” by eliminating

    the need for more litigation and freeing the Commission and other parties to

    79 Joint Motion at 40 [citing e.g., D.10-06-015 at 11-12].

    80 Id. at 40.

    81 Id. at 41.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 35 -

    concentrate limited resources on other pressing energy-related matters, including

    meeting Southern California’s energy needs in the near future.82

    5.2. Other parties

    With one exception (CLECA), parties who did not join the Agreement, are

    basically divided between: (1) those who do not generally oppose the settlement,

    but prefer some modifications, and (2) those who oppose the Agreement and

    prefer the Commission undertake Phase 3 to confirm SCE’s fault for approval of

    the RSG design, as well as explore a variety of other questions each seeks to have

    answered. One party, Henricks, alleges there must be “collusion” among the

    Utilities, Settling Parties, Commissioners, and the ALJs for a settlement to occur at

    this time which would obviate the need for a Phase 3 inquiry into the RSG design

    decisions.

    5.2.1. Parties Not Opposed to the Settlement Agreement

    5.2.1.1. CLECA

    CLECA, who became a party in time to weigh in on the Agreement, offers

    essentially unqualified support, finding it “reasonable and balanced between

    ratepayer and shareholder interests” including a reasonable “bottom line.”83

    They agree with Settling Parties that the Commission has historically supported

    qualifying settlements in order to reduce the litigation burden on parties and the

    Commission.84

    In addition, CLECA appreciates the diversity of Settling Parties, including

    utilities, ratepayer advocates, environmental, and labor parties. Of significance

    82 Id. at 41-42.

    83 CLECA OC at 1.

    84 Id. at 2.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 36 -

    to CLECA, the overall result is closer to TURN’s litigation position than that of

    the Utilities.

    5.2.1.2. AReM/DACC

    AReM and DACC find the Agreement to be a reasonable resolution of this

    proceeding and do not oppose its adoption by the Commission. These parties

    filed joint comments stating their primary interest is the fair and equitable

    treatment of direct access (DA) ratepayers in light of the closure, especially as to

    how the costs and refunds authorized by an adopted settlement will be

    implemented in rates, and in particular, the Power Charge Indifference Amount

    (PCIA).85

    AReM and DACC claim the inclusion of the ongoing full SONGS revenue

    requirement in the calculation of the PCIA rate, without accounting for the lost

    SONGS generation, results in extraordinary increases to the 2014 PCIA. They

    wish to ensure that these increases do not continue and that the implementation

    of the Agreement does not cause an unfair burden to fall on DA ratepayers.86

    Their second concern is the rate treatment of the Replacement Power costs.

    According to AReM and DACC, these amounts were for short-term purchases

    made only on behalf of bundled customers--–not on behalf of DA customers.

    Thus, these replacement purchases cannot and should not be included in the

    Total Portfolio Amount used to calculate the PCIA.87

    Therefore, they recommend the Commission specifically direct the Utilities

    to: 1) utilize the provisions of the Consensus Protocol when implementing the

    85 AReM/DACC OC at 2.

    86 Ibid.

    87 Id.at 3.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 37 -

    rate adjustments associated with the Settlement; and 2) omit the short-term

    SONGS replacement costs from any Total Portfolio Costs.

    5.2.1.3. Joint Parties

    Joint Parties were generally supportive of the Agreement, finding it

    “reasonable and fair” and the result of “protracted and difficult negotiations.”88

    Joint Parties are very supportive of the Commission’s modifications and believe

    they are in the public interest and are consistent with long-standing precedents

    favoring settlements, including settlements where the hearings have not been

    completed.89 However, they seek a modification related to community outreach

    and education efforts in service areas near SONGS, an issue advanced by Joint

    Parties throughout Phase 1 of the consolidated OII proceedings.

    Joint Parties reiterate their request that SCE be required to expand its

    public education about SONGS and the future decommissioning, beyond the

    20-mile designated public education zone to 50 miles.90 In addition, they ask the

    Commission to “be particularly sensitive to pockets of alternative language users

    and coordinate with community based organizations to ensure wide distribution

    of public information and availability of emergency planning information.”91

    Second, Joint Parties were initially concerned that current third-party

    recovery provisions were not structured to properly incentivize the recovery of

    88 Joint Parties OC at 2.

    89 Joint Parties’ Comments on Modification Ruling at 1.

    90 Joint Parties OC at 2-3.

    91 Id. at 3.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 38 -

    funds from Mitsubishi and NEIL. However, the modifications to ratepayer share

    of the recoveries seems to abate that objection.92

    5.2.1.4. World Business Academy (WBA)

    WBA generally supports the Agreement, but voices a few concerns. WBA

    initiated settlement discussions with SCE in February 2012 when its President93

    requested a meeting with SCE representatives to present WBA’s “Settlement

    Principles,” a set of nine concepts which WBA viewed as the basis for a fair and

    equitable settlement. According to WBA, the proposed Agreement in large part

    reflects these settlement principles.94

    These principles include:

    SCE should not collect money for power not delivered by SONGS;

    SCE should be able to recover the actual costs of power purchased to replace lost SONGS output;

    Ratepayers should not pay the costs of amortizing undepreciated value of SONGS base plant after June 7, 2013;

    SCE should be allowed to keep SGRP costs recovered in rates through January 31, 2012;

    SCE should be allowed to retain recorded labor costs through June 7, 2013, and associated with gradual lay-off for 90 days thereafter; and

    Ratepayers should pay for CWIP plant upgrades to extent equipment or systems were put into service before January 31, 2102 and incurred by June 7, 2013.

    92 Joint Parties’ Comments on Modification Ruling at 3.

    93 WBA’s President is Rinaldo S. Brutoco.

    94 WBA OC at 3.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 39 -

    Although the Agreement does not achieve all of WBA’s objectives in the

    OII, WBA believes the Agreement will resolve key issues of dispute between

    parties and bring a “much needed resolution of the contested claims” when

    adopted in a final form.95 Nonetheless, WBA asks the Commission to carefully

    consider issues raised by non-settling parties. To improve transparency, WBA

    also suggests it would be in the best interests of ratepayers to provide a table in

    this decision which clearly illustrates the components of the proposed refund to

    ratepayers.96

    Additionally, WBA identifies what it calls “overly-broad or unnecessary

    language” which it suggests be deleted from the Agreement because such

    language may not be fully supported by the record. Three examples are

    provided: (1) delete the word “unexpected” from ¶3.8, which states, in part, that

    the tube wear (discovered in February 2012) “caused unexpected and extensive

    property damage to” RSGs; (2) delete ¶3.9 which refers to inspections in

    February and March 2012 of U3 RSGs and similarly states the tube-to-tube wear

    “caused unexpected and extensive property damage….;” and (3) delete all but

    the first sentence of ¶3.23 (describes SCE’s grievances with Mitsubishi’s

    performance.)97

    5.2.2. Parties Opposed to the Settlement Agreement

    5.2.2.1. Alliance for Nuclear Responsibility

    The modifications adopted by the Settling Parties did not alter A4NR’s

    95 Id. at 1.

    96 WBA OC at 2.

    97 Id. at 2-3.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 40 -

    Objections to the settlement. A4NR’s Comments were primarily a restatement of

    its views opposing the proposed settlement. Although the modifications

    included a program response to A4NR’s criticism that the settlement did not

    address “externalities,” A4NR expresses “disappointment with the Ruling’s

    timid consideration of the shutdown’s impact on CO2 emissions and electricity

    prices.”98

    A4NR urges the Commission to reject the Joint Motion, not adopt the

    proposed settlement, and to make a counter proposal to resolve the OII.

    Although A4NR says it supports the core framework of the Agreement as it

    relates to removal of assets from rate base, and reduced return for Base Plant

    assets only, it argues for conduct of Phase 3 based on a conclusion that SCE was

    imprudent in managing the SGRP and is liable for all consequential damages.

    As a result, A4NR states Phase 3 should consist only of fashioning remedies for

    SCE’s imprudence.

    During the proceedings, A4NR has consistently rejected rate recovery for

    any post-outage SONGS-related expenses. As soon as SCE became aware of the

    extent of vibratory damage to the steam generator tubes in both units, A4NR

    argues that SCE should have decided to shut down permanently. Therefore,

    A4NR concluded that all post-outage facility-related rates should be refunded.99

    Furthermore, A4NR argued that all SONGS assets, including CWIP not in

    service, should be removed from rate base no later than November 1, 2012, if not

    February 1, 2012, and zero return on investment authorized.100

    98 A4NR Comments on Modification Ruling at 8.

    99 A4NR Phase 1 Opening Brief (OB) at 2.

    100 A4NR Phase 2 OB at 24.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 41 -

    Particular to the proposed settlement, A4NR argues it is untimely and

    does not meet the criteria necessary for Commission approval.101 A4NR’s

    premise is that the NRC citation issued to SCE for failure to properly supervise

    Mitsubishi’s design of the RSGs “places Edison at the head of the chain of

    causation.”102 A4NR characterizes SCE’s decision to not contest the NRC citation

    as an admission of imprudence of its regulatory duty as the operator to “retain

    responsibility for the quality assurance program.”103 Thus, A4NR concludes that

    SCE is factually unable to meet the reasonable manager standard for an operator.

    A4NR contends the Agreement is unduly expansive and pre-emptive of

    issues the Commission should consider as “core priorities” (e.g., review of

    purchased power costs, SCE violations of NRC regulations, increased

    emissions).104 Instead, the Agreement ignores these issues, “absolves Edison

    management of culpability for its admitted violation of NRC regulations

    concerning design control, and ignores the large majority of multi-billion dollar

    consequences that flowed from that violation.”105 Moreover, A4NR is troubled

    by statements made by some at SCE or its parent company, Edison International,

    which imply the terms of the settlement will have nominal impact on SCE’s

    earnings.106

    101 A4NR Opening Comments (OC) at 1.

    102 Id. at 2; See, Ruling Taking official Notice of Documents and Ruling on Various Motions (September 11, 2014) at 4.

    103 A4NR OC at 3.

    104 Id. at 7-12.

    105 Id at 15.

    106 Id. at 17-21.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 42 -

    Terms of the Agreement which authorize recovery of nearly all

    preliminarily authorized O&M, a different result from a proposed decision in

    Phase 1, must be unreasonable in light of the record, argues A4NR. Similarly, it

    claims the treatment of CWIP unreasonably fails to account for the

    “extraordinary and continuing growth in CWIP” since the SONGS closure.107

    The calculation of replacement power costs, including ratepayer credits for lost

    energy sales revenue, omission of expanded community education, and the third

    party recovery incentives are also rejected by A4NR as being neither consistent

    with, nor reasonable in light of, the record.

    A4NR criticizes the original proposed sharing formula for third party

    recoveries as unsupported, and lacking any independent assessment of the

    merits of SCE’s claims. The formula is inverse to the public interest, states

    A4NR, because it incentivizes SCE to settle as soon as it has been made whole.

    The formula should be reversed or eliminated, and the Commission’s ability to

    review any such recovery for reasonableness should be restored, states A4NR.

    Furthermore, A4NR disputes that the utility recovery authorized in the

    Agreement, particularly for 2012-2013 O&M and CWIP that didn’t enter service,

    is consistent with § 451.108 A4NR contends that the terms authorizing the utilities

    to retain all SGRP costs prior to the outage, are improperly calculated by SCE

    and not in the public interest.109 Similarly, A4NR is unconvinced the 5% sales

    incentives for M&S and NFI will actually benefit ratepayers, and render the

    refund amounts unknown for now.

    107 Id. at 27.

    108 Id. at 39-41.

    109 Id. at 43-44.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 43 -

    Lastly, A4NR views the implied use of nuclear decommissioning trust

    funds for certain CWIP and 2014 expenses to be misguided, premature, and

    likely in violation of California’s Nuclear Facility Decommissioning Act of

    1985.110

    5.2.2.2. Women’s Energy Matters (WEM)

    WEM opposes the Agreement and asserts it does not meet the criteria for

    Commission approval. Instead, WEM recommends the Commission order large

    refunds of funds collected in 2012-2013, and continue with Phase 3.111 The

    modifications adopted by the Settling Parties did not alter WEM’s disapproval of

    the Agreement.112

    First, WEM argues the Agreement is not reasonable in light of the whole

    record because it does not reflect the entire record, as evidenced by omission of

    any reference to expanded community outreach addressed in Phase 1. In

    addition, because the Agreement settles the contested OII, WEM contends it

    “diminishes” the contributions of other, non-settling parties, which WEM

    concludes is per se unreasonable.113

    WEM’s contention the Agreement is inconsistent with the law is primarily

    based on its view that when ORA became a settling party, it violated its duty to

    ratepayers under § 309.5. Section 309.5 establishes the Office of Ratepayer

    Advocates (ORA) “to represent and advocate on behalf of the interests of public

    utility customers….The goal of the office shall be to obtain the lowest possible

    110 Id. at 53-58.

    111 WEM OC at 6.

    112 WEM Comments on Modification Ruling.

    113 WEM OC at 5.

  • I.12-10-013 et al. ALJ/MD2/KD1/sbf

    - 44 -

    rate for service consistent with reliable and safe service levels.” In WEM’s view,

    ORA moved too far from its litigation position of rejecting

    cost-of-service ratemaking for SONGS, including seeking disallowance of all

    SGRP inspection and repair costs, reduced recovery with zero rate of return on

    Base Plant, reduced 2012-2013 O&M, and capping replacement power costs in

    June 2013.114

    Lastly, WEM argues the Agreement is not in the public interest because it

    stops the investigation before review of the SGRP. The Commission “promised”

    the public an investigation when it opened the OII, claims WEM, and the

    resulting Agreement prevents the public from knowing whether SCE was