DBNGP Stage 5 Looping Expansion Project 2009 Annual Environmental Compliance Report (Statement No. 735) Prepared for DBNGP (WA) Nominees Pty Ltd by Strategen August 2010 DBP Document Control No.: DBPL00-501-0734-01

Transcript of DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance...

Page 1: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

DBNGP Stage 5 Looping

Expansion Project

2009 Annual Environmental

Compliance Report (Statement

No. 735)

Prepared for

DBNGP (WA) Nominees Pty Ltd

by Strategen

August 2010

DBP Document Control No.: DBPL00-501-0734-01

Page 2: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion
Page 3: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

DBNGP Stage 5 Looping

Expansion Project

2009 Annual Environmental Compliance

Report (Statement No. 735)

Strategen is a trading name of

Strategen Environmental Consultants Pty Ltd

Suite 7, 643 Newcastle Street Leederville WA

ACN: 056 190 419

August 2010

Page 4: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion
Page 5: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 1

DBNGP STAGE 5 LOOPING EXPANSION PROJECT

2009 ANNUAL ENVIRONMENTAL COMPLIANCE REPORT (STATEMENT NO. 735)

TABLE OF CONTENTS

1. INTRODUCTION 1

1.1 THE PROPOSAL 3

1.2 ENVIRONMENTAL APPROVAL 3

2. AUDIT METHODOLOGY 4

2.1 AUDIT PLAN 4

2.1.1 PURPOSE AND SCOPE 4

2.1.2 Methodology 5

2.1.3 Compliance with Statement No. 735 5

2.1.4 Conformance with Key Actions 6

2.1.5 Corrective and preventative actions 6

2.1.6 Evidence verification 6

2.2 AUDIT TERMINOLOGY 6

3. STATE OF PROPOSAL IMPLEMENTATION 8

4. AUDIT TABLES 9

4.1 MINISTERIAL STATEMENT 735 SUMMARY AUDIT TABLES 9

4.2 KEY ACTIONS SUMMARY AUDIT TABLE 9

5. AUDIT RESULTS 27

5.1 COMPLIANCE WITH STATEMENT NO. 735 CONDITIONS 27

5.2 CONFORMANCE WITH KEY ACTIONS 27

5.3 CORRECTIVE ACTIONS 27

6. STATEMENT REGARDING COMPLIANCE 37

7. REFERENCES 38

Page 6: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 2

LIST OF TABLES

Table 1.1 Key characteristics of the Stage 5 Looping Expansion 2

Table 2.1 Action implementation status 7

Table 3.1 Progress of DBNGP Stage 5 Looping Expansion Project 8

Table 4.1 Ministerial Statement 735 compliance summary (Generic conditions) 9

Table 4.2 Ministerial Statement 735 compliance summary (Loop specific conditions) 11

Table 4.3 Schedule 1 audit 19

Table 4.4 Disturbance areas within Easement 20

Table 4.5 Key Actions summary table 21

Table 5.1 Summary of potential non-compliances with Statement No. 735 29

Table 5.2 Summary of potential non-conformances with Key Actions 32

LIST OF APPENDICES

All appendices are contained on a CD–ROM attached to the inside cover of this report.

Appendix 1 Approval correspondence on change of reporting anniversary

Appendix 2 Stage 5B Loop 0 Compliance Audit

Appendix 3 Stage 5B Loop 1 Compliance Audit

Appendix 4 Stage 5B Loop 2 Compliance Audit

Appendix 5 Stage 5B Loop 3 Compliance Audit

Appendix 6 Stage 5B Loop 4 Compliance Audit

Appendix 7 Stage 5B Loop 5 Compliance Audit

Appendix 8 Stage 5B Loop 6 Compliance Audit

Appendix 9 Stage 5B Loop 7 Compliance Audit

Appendix 10 Stage 5B Loop 8 Compliance Audit

Appendix 11 Stage 5B Loop 9 Compliance Audit

Appendix 12 Stage 5B Loop 10 Compliance Audit

Page 7: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 1

DBNGP STAGE 5 LOOPING EXPANSION PROJECT

2009 ANNUAL ENVIRONMENTAL COMPLIANCE REPORT (STATEMENT NO. 735)

1. INTRODUCTION

The Dampier to Bunbury Natural Gas Pipeline (DBNGP) Stage 5 Looping Expansion project involves

the construction of eleven pipeline loops adjacent (and connected) to the existing DBNGP. Expansion

will result ultimately in completion of duplication of the pipeline from Dampier to Wagerup. The key

characteristics of the proposal are presented in Table 1.1. The Stage 5 Looping Expansion project,

which continues from Stage 4 (completed in 2006), involves a total length of approximately 1270 km

of pipeline.

The proposal for the Stage 5 Looping Expansion was approved for implementation under Part IV of

the Environmental Protection Act 1986 with issue of Statement No. 735 (the Statement) on

13 December 2009. DBNGP (WA) Nominees Pty Limited trading as Dampier Bunbury Pipeline

(DBP) is the Proponent of the DBNGP Stage 5 Expansion project. WestNet Energy (WestNet)

(previously Alinta Asset Management) has been contracted by DBP to provide project management

for the DBNGP expansion project.

The Statement requires the submission of an annual compliance report to address the status and

compliance of the DBNGP Stage 5 Looping Expansion project with Statement conditions and key

actions in accordance with the annual compliance reporting requirements of Conditions 4–1 to 4–4 of

the Statement.

Implementation of the project commenced in February 2007, and is being undertaken in three stages.

The first stage (5A) was completed in March 2008. Stage 5B commenced in January 2009 and was

effectively completed in early 2010. Planning for the third stage was in a preliminary phase at the

time of preparing this report.

The anniversary date for submission of compliance reports is 13 December each year. The

Department of Environment and Conservation (DEC) granted an extension for the submission of the

2007 compliance report to 31 May 2008. This extension enabled all construction activities involved in

completion of Stage 5A of the proposal (by end of March 2008) to be included in the 2007 report

(DBP 2008). In granting the extension, the DEC requested that the next annual (2008) report be based

on the original anniversary date (that is to December 13 2008). The 2008 report was prepared and

submitted accordingly (DBP 2009). No construction activity took place during the period covered by

the 2008 report.

Stage 5B of the project commenced in January 2009 and was effectively completed in April 2010,

although formal handover of the works from the WestNet Projects Division to the DBP Operations

Division had not been completed. An extension of the period to be reported on within the 2009 report

was requested from the DEC by letter dated (copy at Appendix 1) to enable the complete Stage 5B

construction program to be covered within the one report. At the time of preparing this report, no

response had been received from the DEC.

Page 8: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 2

Table 1.1 Key characteristics of the Stage 5 Looping Expansion

Aspect Proposal

Location There will be eleven loops. The first loop starts at about 2 km south of Dampier. The last loop is south of compressor station 10, which starts at about 17 km southeast of Rockingham, and ends at Wagerup West (Main Line Valve 144).

Proposed action Construct eleven pipeline looping lengths of 660 mm in diameter, buried adjacent to the existing DBNGP. These pipeline lengths will be looped to the existing DBNGP to increase flow of natural gas.

Total length of looping Approximately 1270 km

Characteristics of each loop No. Approx. length

Biogeographical region Shires

0 137.2 km Pilbara Shire of Roebourne

1 123.3 km Pilbara Shire of Ashburton

2 104.9 km Carnarvon, Gascoyne Shire of Ashburton

3 113.0 km Carnarvon, Gascoyne Shire of Carnarvon

4 112.9 km Carnarvon Shire of Carnarvon, Shire of Upper Gascoyne

5 119.0 km Carnarvon, Yalgoo

Shire of Shark Bay

6 131.0 km Yalgoo, Geraldton Sandplains

Shire of Northampton, Shire of Chapman Valley, Shire of Mullewa

7 142.4 km Geraldton Sandplains Shire of Mullewa, Shire of Irwin, Shire of Carnamah

8 96.8 km Geraldton Sandplains, Swan Coastal Plain

Shire of Coorow, Shire of Dandaragan, Shire of Gingin

9 127.7 km Swan Coastal Plain Shire of Gingin, Shire of Chittering, City of Swan, City of Belmont, Shire of Kalamunda, City of Gosnells, City of Armadale, City of Cockburn, Town of Kwinana

10 61.5 km Swan Coastal Plain Shire of Serpentine–Jarrahdale, Shire of Murray, Shire of Waroona

Proposed tenure The completed pipeline will be wholly within the existing DBNGP easement, which is gazetted under the Dampier to Bunbury Pipeline Act 1997.

DBNGP easement width The existing DBNGP easement is 30 m wide. The area to be cleared and graded in the northern loops (Dampier to Muchea) will be approximately 30 m and south of Muchea, the area cleared will be 20 to 30 m. Reduced working widths will be implemented as far as practicable in areas of conservation value.

Activities outside the DBNGP easement

Turnarounds, Campsites, Turkey nests*, Laydown areas, Water supply sources, Access roads, Works associated with watercourse and dune crossings

Temporary area of disturbance within DBNGP easement

Approximately 3175 ha, all to be rehabilitated in consultation with landowners.

Estimated area of vegetation clearing within DBNGP easement

Approximately 1264 ha, all to be rehabilitated in consultation with landowners.

Temporary area of disturbance outside the DBNGP easement

Approximately 139 ha, all to be rehabilitated in consultation with landowners.

Construction duration The Stage 5 Expansion will be constructed in stages, with Stage 5A commencing in February 2007. The subsequent stages will be constructed to match the increasing demand in fuel gas, and full looping is expected to be substantially completed within five years of approval.

Construction workforce Up to 900 people

* Turkey nests are artificially created water storages constructed by hollowing out an area of land and using the fill to build up its sides.

Page 9: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 3

This report has been prepared to demonstrate compliance with the Statement conditions for the period

from 1 January 2009 to 30 April 2010, covering the entirety of the Stage 5B construction program.

The report comprises the findings of an audit of compliance with the:

• conditions and procedures contained within the Statement as required by Condition 4-3-2 of the

Statement

• key actions contained within management plans or programs as required by Conditions 4-3-4 of

the Statement.

DBP engaged a Construction Contractor, McConnell Dowell Constructors Australia Pty Ltd

(MacDow), to undertake construction of the pipeline for Stage 5B with WestNet Energy managing the

MacDow contract on behalf of DBP.

1.1 THE PROPOSAL

The DBNGP Stage 5 Looping Expansion is being constructed in stages, the first of which was

Stage 5A, which commenced in February 2007 and was completed in March 2008. Stage 5B was

commenced in January 2009 and construction was effectively completed by the end of April 2010.

DBNGP (WA) Nominees Pty Limited trading as Dampier Bunbury Pipeline (DBP) remains the

Proponent of the DBNGP Stage 5 Looping Expansion project and there has been no change in

responsibility for proponency.

1.2 ENVIRONMENTAL APPROVAL

DBNGP (WA) Nominees Pty Ltd (DBP) was granted environmental approval for the DBNGP Stage 5

Looping Expansion proposal under Part IV of the Environmental Protection Act 1986 (EP Act). The

Minister for Environment approved the proposal on 13 December 2006 with the release of Statement

No. 735, which includes environmental conditions under which the proposal is to be implemented. Of

the 72 environmental conditions, the majority of conditions relate to the preparation and

implementation of management plans addressing areas of potential environmental risk identified

during the assessment.

The required management plans were prepared and consolidated as management protocols into a

Construction Environmental Management Plan (CEMP) that addressed a number of environmental

factors additional to those required under the Statement, in order to meet the requirements of all

environmental regulators.

Page 10: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 4

2. AUDIT METHODOLOGY

2.1 AUDIT PLAN

2.1.1 PURPOSE AND SCOPE

The purpose of this document is to enable compliance with Conditions 4–1 to 4–4 of Statement

No. 735:

4–1 The proponent shall submit to the CEO environmental compliance reports annually

reporting on the previous twelve–month period, unless required by the CEO to

report more frequently.

Note: Annual reporting shall continue until such time as the Minister for the

Environment determines on advice from the Environmental Protection Authority that

the proponent has fulfilled its responsibilities in relation to the conditions within this

Statement.

4–2 The environmental compliance reports shall address each element of an audit

program approved by the CEO and shall be prepared and submitted in a format

acceptable to the CEO.

4–3 The environmental compliance reports shall:

1. be endorsed by signature of the proponent's Chairman or a person, approved

in writing by the Chairman, delegated to sign on behalf of the proponent's

Chairman;

2. state whether the proponent has complied with each condition and procedure

contained in this statement;

3. provide verifiable evidence of compliance with each condition and procedure

contained in this statement;

4. state whether the proponent has complied with each key action contained in

any environmental management plan or program required by this statement;

5. provide verifiable evidence of conformance with each key action contained in

any environmental management plan or program required by this statement;

6. identify all non–compliances and non–conformances and describe the

corrective and preventative actions taken in relation to each non–compliance

or non–conformance;

7. provide an assessment of the effectiveness of all corrective and preventative

actions taken; and

8. describe the state of implementation of the proposal.

4–4 The proponent shall make the environmental compliance reports required by

condition 4–1 publicly available in a manner approved by the CEO.

Page 11: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 5

This report relates to Stage 5 of the DBNGP for the period 1 January 2009 to 30 April 2010.

The report has been prepared for submission by DBP to the Chief Executive Officer of the Department

of Environment and Conservation (DEC) to meet the requirements of Condition 4–1 of Statement

No. 735 for the submission of an annual compliance report.

The audit includes a determination as to whether a number of management plans are being

implemented (as they are conditions of the Statement) and for this purpose, a number of key actions

from the plans have been provided by DBP for the audit (Table 4.5). The Key Actions were adopted

by DBP for inclusion in annual compliance reports on Stage 5A, which were accepted by the DEC and

have been used for all subsequent compliance reporting.

It is also noted that where a previous Compliance Report has indicated a condition was ‘Cleared’,

‘Completed’ or ‘Satisfactory during this period’, and there has been no further requirement to

implement the action, the evidence associated with the previous audit determination has been accepted

without verification.

2.1.2 Methodology

The audit was conducted in June 2010, and has been largely based on the findings of detailed audits of

compliance with Statement No. 735 conducted to meet the requirements of Condition 6 and as

reported in the compliance audit reports. Condition 6 requires compliance audit reports to be prepared

and submitted within 30 days of handover of each loop1

to DBP Operations. Copies of these audit

reports are presented in Appendix 2 through Appendix 12.

The required reporting includes “whether the proponent has complied with each condition and

procedure contained within the statement” and “conformed with each key action” (Conditions 4–3(2)

and 4–3(4) respectively). This section describes how compliance with each condition and

conformance with key actions has been audited and reported.

Audit results relating to the Statement conditions and key actions are presented in Sections 4 and 5.

Where potential non–compliances have been identified, the corrective and preventative actions taken

are described and an assessment of their effectiveness is provided in Section 5 as required by

Conditions 4–3(6) and 4–3(7).

2.1.3 Compliance with Statement No. 735

An audit of compliance with the conditions and procedures of the Statement was conducted and a

compliance rating was applied in accordance with terminology described in Section 2.2. The full audit

is presented in Section 4.1. The identified potential non–compliances are presented in Section 5.1.

1

A loop is a segment of pipeline constructed between compressor stations. Each sub-stage of the Stage 5 project comprised

a series of loops spread over the length of the pipeline.

Page 12: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 6

2.1.4 Conformance with Key Actions

Condition 4–3(4) requires DBP to report on conformance with each key action contained within any

management plan or program required by Statement No. 735.

Environmental management is primarily achieved through the implementation of the CEMP, which

contains a number of management protocols that directly relate to all the construction requirements of

the Ministerial Conditions and include a range of additional specific management actions reflecting

good management. A number of the management actions within the CEMP directly reflect specific

prescriptive conditions within the Statement.

Key actions from the CEMP have been identified as being:

• those management actions in the CEMP protocols implemented to manage a condition of the

Statement

• those management actions in CEMP protocols that reflect a key intent of a condition of the

Statement.

Using the above definition, key actions have been derived and audited. The results of the audit of key

actions are presented in Section 5.1 and details of identified potential non–conformances are presented

in Section 5.2.

2.1.5 Corrective and preventative actions

Statement Conditions 4–3(6) and 4–3(7) require descriptions of corrective and preventative actions

taken in relation to each non–compliance or non–conformance, together with assessments of their

effectiveness. These are presented in Section 5.3.

2.1.6 Evidence verification

Evidence to substantiate compliance with conditions contained within Statement No. 735 and key

actions contained within the management plans or programs as required by Conditions 4–3(3) and 4–

3(5) has been sourced from previous compliance reports submitted to the CEO and documentation

provided by the proponent.

2.2 AUDIT TERMINOLOGY

The ‘Status’ field of the audit tables (refer to Table 4.1 and Table 4.5) describes the implementation of

actions and compliance with the Statement. The status of each action is described using terminology

prescribed by the DEC (2007) (Table 2.1). DEC (2007) considers a non-compliance to be a failure to

meet requirements specified in the Statement, and a non-conformance to be any deviation from

procedures, programs and/or management actions detailed within an Environmental Management

Plan.

Page 13: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 7

Table 2.1 Action implementation status

‘Status’ Term Description Notes

Satisfactory during this period

The action has been satisfactorily implemented during the audited period.

Ensure the auditing period is specified either in the report or the audit table.

In process Action is in process of being implemented, but does not yet fully satisfy the requirements of the Ministerial Statement.

This can be used for those actions that, once completed, can be cleared (i.e. construction activities).

Potential non-compliance

Considered to be a potential failure to meet requirements of a condition in the Statement.

Potential non-conformance

Considered to be any potential deviation from the procedures, programs and/or management actions detailed within an Environmental Management Plan or similar document.

Not all potential non-conformances will automatically constitute a potential non-compliance.

Not required at this stage

The proponent was not required to implement the action during the audited stage of the project.

This should be consistent with the ‘Phase’ field of the audit table.

No longer relevant The action was not completed during the audited period, as the action is considered no longer relevant to the project.

The proponent should request approval for clearance of the audit element in order to remove its obligation to undertake the action.

Completed The action was satisfactorily completed during the audited period.

This term can only be used for audit elements with a finite period of application (i.e. construction activities; development of a document). Once completed the proponent should request clearance of the audit element.

Cleared Clearance for the action has been received from DEC.

The proponent is no longer legally obligated to implement the action.

Only proponent to audit

The action is only audited internally by the proponent.

Monitored by another agency

The action is audited by another agency. Prior approval for auditing by another agency must be obtained from the DEC. The agency must be specified (i.e. CALM, DEC licence).

Monitored under a DEC licence

This action is now monitored under Part V of the EP Act.

Source: Adapted from DEC (2007)

In addition to the ‘Status’ terminology prescribed by DEC, the term ‘Unable to assess’ is also used on

occasions where there was insufficient verifiable information/evidence available at the time of the

audit to determine compliance. The status of a number of conditions and key actions were recorded as

‘Unable to assess’ for a variety of reasons, the details of which are presented in the corresponding

detailed audit tables for the individual loops in Appendix 2 through Appendix 12. A common reason

related to a lack of verifiable evidence as the audits may not have occurred concurrently with a

specific activity, such that conformance with a specific action could be verified. This generally relates

to activities for which records are not made or kept, for practical reasons. An example, is the in ability

to assess whether or not fauna clearing on a specific loop was undertaken using the specified

equipment. Verification of this would usually require direct observation of the activity, or at least

photographic evidence, which may not have been available.

Page 14: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 8

3. STATE OF PROPOSAL IMPLEMENTATION

The state of implementation of the proposal as at 30 April 2010 is as follows. Stage 5A of the project

has been completed for all loops as summarised in Table 3.1 and as reported on in the 2007 annual

compliance report (DBP 2008). Stage 5B has been constructed to practical completion as summarised

in Table 3.1. Of the 1270 km of the Stage 5 proposal, 1011 km have now been constructed.

Table 3.1 Progress of DBNGP Stage 5 Looping Expansion Project

Loop Stage 5A Loop Lengths (km)*

Status of Loops for Stage 5A

Stage 5B Loop Lengths (km)*

Status of Loops for Stage 5B

Loop 0 0.0 No construction in Loop 0 undertaken in Stage 5A

114.9 Complete with exception of 600 m associated with Fortescue River crossing

Loop 1 74.0 Complete 32.9 Complete

Loop 2 57.8 Complete 31.9 Complete

Loop 3 60.3 Complete 34.6 Complete

Loop 4 61.9 Complete 33.6 Complete

Loop 5 63.7 Complete 34.0 Complete

Loop 6 70.5 Complete 35.8 Complete

Loop 7 60.4 Complete 44 Complete

Loop 8 55.3 Complete 21.8 Complete

Loop 9 52.0 Complete 23.4 Complete

Loop 10 15.1 Complete 33.3 Complete

TOTAL 571.1 440.2

Completion of Stage 5A was considered to be evidence of substantial commencement of the project as

required under Condition 3–2, as reported in the 2007 compliance report (DBP 2008).

As outlined in the 2007 compliance report, the above description satisfies the requirements of

Condition 4–3(8).

Page 15: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 9

4. AUDIT TABLES

4.1 MINISTERIAL STATEMENT 735 SUMMARY AUDIT TABLES

Table 4.1, Table 4.2 and Table 4.3 have been produced to meet condition 4–3(2) of Ministerial

Statement 735. Compliance reports have been provided to DEC on a loop by loop basis and provide

verifiable evidence as required by condition 4–3–3 and are presented in Appendix 2 through

Appendix 12. The tables include summaries of results of the completion–of–loop compliance audit

reports. Details can be found in the relevant appendix. These audits have been carried out in

accordance with a DEC approved audit program and presentation.

4.2 KEY ACTIONS SUMMARY AUDIT TABLE

The Audit confirmed that DBP, WestNet Energy and MacDow implemented a suite of environmental

management controls that facilitate implementation of management actions contained within

environmental management plans.

Table 4.5 has been produced to meet condition 4–3(4) of Ministerial Statement 735 related to

implementation of prescribed management plans. The table summarises of results of the completion–

of–loop compliance audit reports presented in Appendix 2 through Appendix 12. Details can be found

in the relevant appendix and provide reference to verifiable evidence as required by condition 4–3(5).

Table 4.1 Ministerial Statement 735 compliance summary (Generic conditions)

Audit code

Subject Action Status

735:M1.1 Implementation Implement the proposal as documented and described in schedule 1 of Statement 735 subject to the conditions and procedures of this statement.

Refer to Table 4.3, audit Schedule 1

735:M2.1 Nominated proponent

Implement the proposal until such time as the Minister for the Environment nominates another person as the proponent.

Not required at this stage

735:M2.2 Proponent contact details

Notify the Chief Executive Officer of the DEC (CEO) of any change of the contact name and address for the serving of a notice or other correspondence within 30 days of such change.

Not required at this stage

735:M3.1 Authorisation limit

Substantially commence the proposal before 13 December 2011 to avoid lapse of authorisation.

Completed

735:M3.2 Commencement Provide the CEO with written evidence which demonstrates that the proposal has substantially commenced on or before the 13 December 2011.

Completion of Stages 5A and 5B comprises substantial commencement.

735:M4.1 Compliance reporting - submitting

Submit to the CEO environmental compliance reports reporting on the previous twelve-month period. (Annual Environmental Compliance Report (AECR))

This report is presented to satisfy this condition with respect to the 2009 reporting period.

735:M4.2 Audit Program Prepare an audit program. Completed

Page 16: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 10

Audit code

Subject Action Status

735:M4.3 Annual environmental compliance reporting - preparation

The environmental compliance reports shall:

1. Be endorsed by signature of the proponent’s Chairman or a person, approved in writing by the Chairman, delegated to sign on behalf of the proponent’s Chairman.

2. State whether the proponent has complied with each condition and procedure contained in Statement 735.

3. Provide verifiable evidence of compliance with each condition and procedure contained in Statement 735.

4. State compliance with each key action contained in any environmental management plan or program required by Statement 735.

5. Provide verifiable evidence of conformance with each key action contained in any environmental management plan or program required by Statement 735.

6. Identify all non-compliances and non-conformances and describe the corrective and preventative actions taken in relation to each non-compliance or non-conformance.

7. Provide an assessment of the effectiveness of all corrective and preventative actions taken.

8. Describe the state of implementation of the proposal.

This report is presented to satisfy this condition with respect to the 2009 reporting period.

735:M4.4 Annual environmental compliance reporting – public availability

Make the environmental compliance reports (Acers) publicly available.

In process

735:M5.1 Performance review – prepare and submit

Submit a Performance Review report every five years after the start of construction to the EPA, which addresses:

Not required at this stage

735:M5.2 Performance review – public availability

Make the Performance Review reports publicly available. Not required at this stage

735:M9.1 Fauna Management Plan - preparation

Prepare a Fauna Management Plan, which includes a Fauna Interaction Protocol, in consultation with the DEC.

Cleared

Page 17: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 11

Table 4.2 Ministerial Statement 735 compliance summary (Loop specific conditions)

Audit code Subject Action Loop 0 Loop 1 Loop 2 Loop 3 Loop 4 Loop 5 Loop 6 Loop 7 Loop 8 Loop 9 Loop 10

735:M6.1 Compliance audit - submit

Submit a written compliance audit report to the CEO within 30 days of the conclusion of the construction of each loop section.

In process In process In process In process In process In process In process In process In process In process In process

735:M6.2 Compliance report - prepare

The compliance audit report shall outline identified non compliances against the conditions of Statement 735.

In process In process In process In process In process In process In process In process In process In process In process

735:M6.3 Compliance report - prepare

The report shall be endorsed by signature of the proponent’s Chairperson or a person approved in writing by the Chairperson, delegated to sign on behalf of the proponent’s Chairperson.

In process In process In process In process In process In process In process In process In process In process In process

735:M6.4 Compliance report - prepare

The report shall include the date, time and location of the non-compliances, the reason for the non-compliances, actions taken to remedy non-compliances and details of management measures implemented to reduce the risk of future non-compliances

In process In process In process In process In process In process In process In process In process In process In process

735:M7.1 Spring flora surveys

Submit a report to the CEO, which details the results of the spring flora, surveys undertaken in 2006.

Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared

735:M7.2 Flora and Vegetation Management Plan - preparation

Prepare a Flora and Vegetation Management Plan, in consultation with the DEC.

Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared

735:M7.3 Flora and Vegetation Management Plan - implementation

Implement the Flora and Vegetation Management Plan.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Unable to assess

Satisfactory during this period

Satisfactory during this period

Unable to assess

Satisfactory during this period

Refer to Table 4.5 – Key Management Actions - KAs 4 - 10

Satisfactory during this period

735:M7.4 Flora and Vegetation Management Plan – public availability

Make the Flora and Vegetation Management Plan publicly available.

Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed

735:M8.1 Vegetation disturbance – clear delineation

Clearly delineate on the ground the boundaries of the pipeline easement and the area of disturbance outside the easement.

Satisfactory during this period for delineation of pipeline easement

Unable to assess for delineation of areas of disturbance outside the easement

Satisfactory during this period for delineation of pipeline easement

Unable to assess for delineation of areas of disturbance outside the easement

Satisfactory during this period

Satisfactory during this period with respect to delineation of pipeline easement

Unable to assess with respect to areas of disturbance outside of the easement.

Unable to assess

Satisfactory during this period for delineation of pipeline easement

Unable to assess for delineation of areas of disturbance outside the easement

Satisfactory during this period with respect to delineation of pipeline easement

Unable to assess with respect to areas of disturbance outside of the pipeline easement

Satisfactory during this period with respect to delineation of pipeline easement

Unable to assess with respect to areas of disturbance outside of the pipeline easement

Satisfactory during this period for delineation of pipeline easement

Unable to assess for delineation of areas of disturbance outside the easement

Satisfactory during this period

Satisfactory during this period

Page 18: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 12

Audit code Subject Action Loop 0 Loop 1 Loop 2 Loop 3 Loop 4 Loop 5 Loop 6 Loop 7 Loop 8 Loop 9 Loop 10

735:M8.2 Vegetation disturbance – exceedance of boundaries

Do not cause disturbance of vegetation outside the delineated pipeline easement, or the delineated area of disturbance outside the easement, unless authorised by the Minister for the Environment.

Satisfactory during this period

Satisfactory during this period

Unable to assess

Unable to assess

Satisfactory during this period

Satisfactory during this period

Unable to assess

Satisfactory during this period with regards to the pipeline easement

Potential non-compliance with regards to areas of disturbance outside the easement

Satisfactory during this period

Unable to assess

Satisfactory during this period

735:M8.3 Vegetation disturbance – environmentally sensitive areas

Do not cause or allow disturbance of vegetation outside the 20 metre wide easement located within environmentally sensitive areas, unless authorised by the Minister for the Environment.

Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Not required at this stage

Satisfactory during this period

Not required at this stage

Not required at this stage

Refer to Table 4.5 Key Actions Summary Table , KA 5

Satisfactory during this period

735:M9.2 Fauna – trench clearing

The clearing of open trenches by the fauna-clearing persons is to be completed each day by no later than 4.5 hours after sunrise for Loops 0 to 7 and no later than 5 hours after sunrise for Loops 8 to 10 and at least half an hour prior to the backfilling of pipeline trenches.

Potential non-compliance regarding clearing by particular time after sunrise

Unable to assess regarding clearing of trenches occurring half an hour prior to backfilling

Satisfactory during this period regarding clearing by particular time after sunrise

Unable to assess regarding clearing of trenches occurring half an hour prior to backfilling

Satisfactory during this period with respect to trenches being cleared no later than 4.5 hours after sunrise

Unable to assess with respect to clearing of trenches occurring half an hour prior to backfilling

Satisfactory during this period with respect to trenches being cleared no later than 4.5 hours after sunrise

Unable to assess with respect to clearing of trenches occurring half an hour prior to backfilling

Satisfactory during this period regarding clearing by particular time after sunrise

Unable to assess regarding clearing of trenches occurring half an hour prior to backfilling

Satisfactory during this period regarding clearing by particular time after sunrise

Unable to assess regarding clearing of trenches occurring half an hour prior to backfilling

Satisfactory during this period with respect to trenches being cleared no later than 4.5 hours after sunrise

Unable to assess with respect to clearing of trenches occurring half an hour prior to backfilling

Satisfactory during this period with respect to trenches being cleared no later than 4.5 hours after sunrise

Unable to assess with respect to clearing of trenches occurring half an hour prior to backfilling

Satisfactory during this period regarding clearing by particular time after sunrise

Unable to assess regarding clearing of trenches occurring half an hour prior to backfilling

Satisfactory during this period regarding clearing by particular time after sunrise

Unable to assess regarding clearing of trenches occurring half an hour prior to backfilling

Satisfactory during this period with respect to the timing of clearing of trenches

Unable to assess with respect to clearing having been conducted half an hour prior to backfilling.

735:M9.3 Fauna – open trench length

Open trench lengths shall not exceed a length capable of being inspected and cleared by fauna clearing persons within the required times as set out in conditions 9-2, 10-2 and 10-4.

Potential non-compliance

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

735:M9.4 Fauna – identification of significant habitat trees

Significant habitat trees of sufficient age to form nesting hollows for hollow-nesting birds and mammals shall be marked, prior to construction, in consultation with the DEC.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Unable to assess

Unable to assess

Satisfactory during this period

Satisfactory during this period with regards to marking trees

Potential non-compliance with regards to consultation with DEC

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

735:M9.5 Fauna – retention of significant habitat trees

Marked significant habitat trees as referred to in condition 9-4 shall be retained, except in the case where habitat trees occur in the direct line of the proposed pipeline.

Unable to assess

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Unable to assess

Unable to assess

Satisfactory during this period

Unable to assess

Unable to assess

Satisfactory during this period

Satisfactory during this period

Page 19: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 13

Audit code Subject Action Loop 0 Loop 1 Loop 2 Loop 3 Loop 4 Loop 5 Loop 6 Loop 7 Loop 8 Loop 9 Loop 10

735:M9.6 Fauna – backfill of trench

Monitor weather forecasts through the Bureau of Meteorology and in the event of a weather forecast indicating rainfall sufficient to cause flooding of trenches or drowning of fauna trapped in trenches, in consultation with DEC, backfill all lengths of open trench with a potential to be flooded or cause drowning of fauna.

Satisfactory during this period in regards to monitoring weather forecasts

Unable to assess in regards to the use of weather forecasts

Satisfactory during this period in regards to monitoring weather forecasts

Unable to assess in regards to adverse weather forecasts and implementation of contingencies

Unable to assess

Satisfactory during this period with respect to monitoring of weather forecasts

Unable to assess regarding to use of weather forecasts in predicting likelihood of flooding.

Satisfactory during this period in regards to monitoring weather forecasts

Unable to assess in regards to adverse weather forecasts and implementation of contingencies

Satisfactory during this period in regards to monitoring weather forecasts

Unable to assess in regards to adverse weather forecasts and implementation of contingencies

Satisfactory during this period with respect to obtaining weather forecasts

Unable to assess with respect to adverse weather forecasts and backfilling of trenches

Satisfactory during this period in regards to monitoring weather forecasts

Unable to assess in regards to adverse weather forecasts and implementation of contingencies

Satisfactory during this period in regards to monitoring weather forecasts

Unable to assess in regards to adverse weather forecasts and implementation of contingencies

Satisfactory during this period

Unable to assess

735:M9.7 Fauna – period that trench is open

Where wet trenching is conducted, trenches shall not remain open for periods longer than 48 hours within wetlands and environmentally sensitive areas and 7 days for all other areas.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

735:M9.8 Fauna – qualifications of clearing persons

The fauna clearing persons shall operate in teams of two with at least one fauna clearing person experienced in the following, to the requirements of DEC:

• Fauna identification, capture and handling (including venomous snakes).

• Identification of tracks, scats, burrows and nests of conservation significant species.

• Fauna vouchering.

• Assessing injured fauna for suitability for release, rehabilitation or euthanasia.

• Familiarity with the ecology of the species that may be encountered in order to be able to appropriately translocate fauna encountered.

• Performing euthanasia.

Potential non-compliance

Potential non-compliance

Unable to assess during period 29/08/2009 to 02/09/2008 with respect to experience of fauna handlers

Satisfactory for the period 03/09/2009 to 24/09/2009

Satisfactory during remainder of period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Unable to assess

Unable to assess

735:M9.9:1 Fauna – clearing person training

Ensure that basic fauna handling training is provided to fauna clearing persons who do not possess the skills and experience outlined in condition 9-8 prior to the fauna clearing person commencing employment.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Page 20: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 14

Audit code Subject Action Loop 0 Loop 1 Loop 2 Loop 3 Loop 4 Loop 5 Loop 6 Loop 7 Loop 8 Loop 9 Loop 10

735:M9.9:2 Fauna clearing person-training

Ensure that basic fauna handling training is provided to fauna clearing persons who do not possess the skills and experience outlined in condition 9-8 prior to the fauna clearing person commencing employment.

Unable to assess

Unable to assess

Satisfactory during this period

Potential non-compliance

Satisfactory during this period

Not required at this stage

Not required at this stage

Not required at this stage

Satisfactory during this period

Unable to assess

Unable to assess

735:M9.10:1 Fauna – clearing person training

The fauna handling training as outlined in condition 9-9 shall be developed in consultation with the DEC.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

735:M9.10:2 Fauna – clearing person training

The fauna handling training as outlined in condition 9-9 shall be developed in consultation with the DEC.

Not required at this stage

Not required at this stage

Cleared Cleared Not required at this stage

Not required at this stage

Cleared Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period

735:M9.11 Fauna – period that trench is open

No part of the trench shall remain open for more than 14 days except ‘bell holes’, unless authorised by the CEO.

Potential non-compliance

Potential non-compliance

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Potential non-compliance

Satisfactory during this period

Satisfactory during this period

735:M9.12 Fauna – period that trench is open

In environmentally sensitive areas, no part of the trench shall remain open for more than seven days, unless authorised by the CEO.

Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Not required at this stage

Satisfactory during this period

Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period

735:M9.13 Fauna – period that trench is open

In order to comply with condition 9-11 and condition 9-12, record each day in a log and on the ground the kilometre points of the start point and finish point of the trench opened on each day.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period.

Satisfactory during this period.

Satisfactory during this period with regards to recording on a log

Unable to assess with regards to kilometre points on the ground

Satisfactory during this period

Satisfactory during this period.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period.

Satisfactory during this period

735:M9.14 Fauna Management Plan – review and revise

Review and revise, as required, the Fauna Management Plan required by condition 9-1.

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

735:M9.15 Fauna Management Plan - implementation

Implement the Fauna Management Plan and subsequent revisions.

Satisfactory during this period

Satisfactory during this period / Potential non-compliance

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Refer to Table 4.5 Key Actions summary table KA11 to KA27.

Satisfactory during this period

735:M9.16 Fauna Management Plan – public availability

Make the Fauna Management Plan and subsequent revisions publicly available.

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

Completed in regards to original Plan

Not required at this stage

Completed in regards to original Plan

Not required at this stage

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

Completed in regards to original Plan

Not required at this stage

Completed in regards to original Plan

Not required at this stage

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

Completed in regards to original Plan

Satisfactory during this period for subsequent revisions it

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

735:M9.17 Fauna management – performance monitoring reports

Produce weekly performance monitoring reports on fauna management for each loop.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Potential non -compliance

Satisfactory during this period

735:M9.18:1 Fauna management – performance monitoring reports

Produce monthly performance monitoring reports on fauna management for each Loop.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period.

Satisfactory during this period.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period.

Satisfactory during this period

Satisfactory during this period

Unable to assess

Satisfactory during this period

Page 21: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 15

Audit code Subject Action Loop 0 Loop 1 Loop 2 Loop 3 Loop 4 Loop 5 Loop 6 Loop 7 Loop 8 Loop 9 Loop 10

735:M9.18:2 Fauna management – performance monitoring reports

Make the monthly performance monitoring reports publicly available on completion of each loop.

In process In process In process In process In process In process In process In process In process In process In process

735:M10.1 Timing of construction works – Loops 0 to 2

Avoid open trench work on Loops 0 to 2 from November to March inclusive unless otherwise allowed for in condition 10-2.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not relevant to this stage

Not required at this stage

735:M10.2 Timing of construction works – Loops 0 to 2

In the event that open trench work on Loops 0 to 2 is conducted during November to March the following shall be undertaken:

• Provide a report to the DEC outlining the reasons why open trench work was necessary during the period November to March inclusive.

• Complete fauna clearing as described in condition 9-2 by 3 hours after sunrise or when daily temperatures are forecast by the Bureau of Meteorology to exceed 35˚C fauna clearing shall be completed by 2.5 hours after sunrise.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

735:M10.3 Timing of construction works – Loops 8 to 10

Avoid open trench work on Loops 8 to 10 from June to December (inclusive) unless otherwise allowed for in condition 10-4.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

735:M10.4 Timing of construction works – Loops 8 to 10

Where open trench work is undertaken during June to December inclusive the following shall be undertaken:

• Provide a report to the DEC outlining the reasons why open trench work was necessary during the period June to December inclusive.

• Implement the Wetlands Crossing Management Plan (condition 12-1) and the Dieback and Weed Management Plan (condition 13-2).

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Satisfactory during this period

Not required at this stage

735:M11.1:1 Watercourses – vegetation delineation

Delineate the riparian vegetation along watercourses which will be traversed.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

735:M11.1:2 Watercourses-vegetation delineation.

Delineate the riparian vegetation along watercourses which will be traversed

Satisfactory during this period

Not required at this stage

Not required at this stage

Satisfactory during this period

Unable to asses Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Satisfactory during this period

735:M11.2 Watercourse Crossing Management Plan -

Prepare in consultation with the DEC, a Watercourse Crossing Management Plan to minimise disturbance of riparian vegetation.

Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared

Page 22: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 16

Audit code Subject Action Loop 0 Loop 1 Loop 2 Loop 3 Loop 4 Loop 5 Loop 6 Loop 7 Loop 8 Loop 9 Loop 10

735:M11.3 Watercourse Crossing Management Plan - implementation

Implement the Watercourse Crossing Management Plan.

Satisfactory during this period

Unable to assess

Satisfactory during this period

Satisfactory during this period

Unable to asses Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Satisfactory during this period

735:M11.4 Watercourse Crossing Management Plan – public availability

Make the Watercourse Crossing Management Plan publicly available

Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed

735:M12.1 Wetland crossing Management Plan - prepare

Prepare, in consultation with the DEC, a Wetland Crossing Management Plan.

Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared

735:M12.2 Wetland crossing Management Plan - prepare

The Wetland Crossing Management Plan shall set out procedures to protect any wetland crossed by the trench in the event that trenching is proposed where there is standing water in the wetland.

Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared

735:M12.3 Wetland Crossing Management Plan - implementation

Implement the Wetland Crossing Management Plan.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Refer to Table 4.5 Key Actions summary table KA 32

Satisfactory during this period

735:M12.4 Wetland Crossing Management Plan – public availability

Make the Wetland Crossing Management Plan publicly available.

Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed

735:M13.1 Dieback – delineate risk areas

Delineate surveyed occurrences of high risk, medium risk and medium to low risk dieback areas.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period.

Satisfactory during this period

735:M13.2 Dieback and Weed Management Plan - prepare

Prepare a Dieback and Weed Management Plan.

Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared

735:M13.3 Dieback and Weed Management Plan – review and revise

In consultation with the DEC, review and revise, as required, the Dieback and Weed Management Plan.

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Not required at this stage

Satisfactory during this period

Not required at this stage

Not required at this stage

735:M13.4 Dieback and Weed Management Plan - implementation

Implement the Weed and Dieback Management Plan and any subsequent revisions of the Weed and Dieback Management Plan.

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Satisfactory during this period

Unable to assess

Satisfactory during this period

Not required at this stage

Unable to assess

Satisfactory during this period

Refer to Table 4.5 Key Actions summary table KA33 to KA35

Satisfactory during this period

735:M13.5 Dieback and Weed Management Plan – public availability

Make the Weed and Dieback Management Plan and any subsequent revisions required by condition 13-3 publicly available.

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

Completed in regards to original Plan

Not required at this stage for subsequent revisions of Plan

Completed in regards to original Plan

Not required at this stage for subsequent revisions of Plan

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

Completed in regards to original Plan

Not required at this stage for subsequent revisions of Plan

Completed in regards to original Plan

Not required at this stage for subsequent revisions of Plan

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

Completed Completed

735:M14.1 Rehabilitation Management Plan - prepare

Prepare a Rehabilitation Management Plan.

Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared

Page 23: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 17

Audit code Subject Action Loop 0 Loop 1 Loop 2 Loop 3 Loop 4 Loop 5 Loop 6 Loop 7 Loop 8 Loop 9 Loop 10

735:M14.2 Rehabilitation – management period

Manage rehabilitation of the pipeline route until the rehabilitation completion criteria, referred to in condition 14-1, have been achieved (Note: obligations under DoIR legislation mean the vehicular access track must be maintained and thus certain completion criteria may not be achievable within the access track).

In process In process Not required at this stage

Not required at this stage

In process In process Not required at this stage

In process In process Not required at this stage

In process

735:M14.3:1 Rehabilitation Management Plan – review and revision

In consultation with the DEC, review and revise, as required, the Rehabilitation Management Plan.

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Not required at this stage

Satisfactory during this period

Not required at this stage

Not required at this stage

735:M14.3:2 Rehabilitation Management Plan – review and revision

In consultation with the DEC, review and revise, as required, the Rehabilitation Management Plan.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

735:M14.4:1 Rehabilitation Management Plan - implementation

Implement the Rehabilitation Management Plan and subsequent revisions until such time as the completion criteria are met.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Unable to assess

Satisfactory during this period

Satisfactory during this period

In process Unable to assess

Refer to Table 4.5 Key Actions summary table KA38 to KA41

Satisfactory during this period

735:M14.4:2 Rehabilitation Management Plan - implementation

Implement the Rehabilitation Management Plan and subsequent revisions until such time as the completion criteria are met.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

735:M14.5 Rehabilitation Management Plan – public availability

Make the Rehabilitation Management Plan and subsequent revisions publicly available.

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

Completed in regards to original Plan

Not required at this stage for subsequent revisions of Plan

Completed in regards to original Plan

Not required at this stage for subsequent revisions of Plan

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

Completed in regards to original Plan

Not required at this stage for subsequent revisions of Plan

Completed in regards to original Plan

Not required at this stage for subsequent revisions of Plan

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

Completed in regards to original Plan

Not required at this stage for subsequent revisions of Plan

Completed in regards to original Plan

Not required at this stage for subsequent revisions of Plan

735:M15.1 Acid Sulphate Soils - investigations

Prior to the commencement of soil disturbance or dewatering in an area, undertake field investigations within that area to clearly delineate areas of high, high to medium, medium to low risk acid sulphate soils.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Satisfactory during this period

735:M15.2 Acid Sulphate Soils - Management

Ensure that within high, high to medium and medium to low acid sulphate soil risk areas, trenches will be excavated in lengths that permit trenches to be opened and closed within a 48 hour period.

Unable to assess

Not required at this stage

Not required at this stage

Unable to assess

Not required at this stage

Not required at this stage

Not required at this stage

Unable to assess

Not required at this stage

Satisfactory during this period

Satisfactory during this period

735:M15.3 Acid Sulphate Soils and Dewatering Management Plan - prepare

Prepare an Acid Sulphate Soils and Dewatering Management Plan, in consultation with the DEC to the requirements of the Minister for the Environment on advice of the EPA.

Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared

735:M15.4 Acid Sulphate Soils and Dewatering Management Plan – review and revise

Review and revise, as required, the Acid Sulphate Soils and Dewatering Management Plan.

Satisfactory during this period

Satisfactory during this period

Completed in regards to original Plan

Not required at this stage for subsequent revisions of Plan

Completed in regards to original Plan

Not required at this stage for subsequent revisions of Plan

Satisfactory during this period

Satisfactory during this period

Completed in regards to original Plan

Not required at this stage for subsequent revisions of Plan

Completed in regards to original Plan

Not required at this stage for subsequent revisions of Plan

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Page 24: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 18

Audit code Subject Action Loop 0 Loop 1 Loop 2 Loop 3 Loop 4 Loop 5 Loop 6 Loop 7 Loop 8 Loop 9 Loop 10

735:M15.5 Acid Sulphate Soils and Dewatering Management Plan - implementation

Implement and comply with the Acid Sulphate Soils and Dewatering Management Plan and subsequent revisions.

Not required at this stage

Not required at this stage

Not required at this stage

Satisfactory during this period

Not required at this stage

Not required at this stage

Not required at this stage

In process Not required at this stage

Refer to Table 4.5 Key Actions summary table KA36 and KA37

Unable to assess

735:M15.6 Acid Sulphate Soils and Dewatering Management Plan – public availability

Make the Acid Sulphate Soils and Dewatering Management Plan and subsequent revisions publicly available.

Completed in regards to original Plan

Satisfactory during this period with respect to subsequent revisions

Completed in regards to original Plan

Satisfactory during this period with respect to subsequent revisions

Completed in regards to original plan and revised plan dated 22/10/2008

Not required at this stage for subsequent revisions

Completed in regards to original plan and revised plan dated 22/10/2008

Not required at this stage for subsequent revisions

Completed in regards to original Plan

Satisfactory during this period with respect to subsequent revisions

Completed in regards to original Plan

Satisfactory during this period with respect to subsequent revisions

Completed in regards to original plan and revised plan dated 22/10/2008

Not required at this stage for subsequent revisions

Completed in regards to original plan and revised plan dated 22/10/2008

Not required at this stage for subsequent revisions

Completed in regards to original Plan

Satisfactory during this period with respect to subsequent revisions

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

Completed in regards to original Plan

Satisfactory during this period with respect to revised plans

735:M16.1 Preliminary Decommissioning Plan - prepare

Prepare a Preliminary Decommissioning Plan for approval by the CEO.

Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared Cleared

735:M16.2 Final Decommissioning Plan – prepare and submit

At least 12 months prior to the anticipated date of closure, or at a time approved by the EPA, submit a Final Decommissioning Plan designed to ensure that the site is left in an environmentally acceptable condition prepared on advice of the EPA, for approval of the CEO.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

735:M16.3 Final Decommissioning Plan - implementation

Implement the Final Decommissioning Plan until such time as the Minister for the Environment determines, on advice of the CEO, that decommissioning responsibilities have been fulfilled.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

735:M16.4 Final Decommissioning Plan – public availability

Make the Final Decommissioning Plan publicly available.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Page 25: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 19

Table 4.3 Schedule 1 audit

Element Description Audit criteria (Stage 5B) Evidence Finding

Location Eleven loops, the first one starts approx. 2 km south of Dampier, the last loop is south of compressor station 10, which starts at about 17 km south-east of Rockingham, and ends at Wagerup West (Main Line Valve 144).

Stage 5B constructed in area as shown in Figure 1 Schedule 1.

DBNGP Stage 5 Expansion Looping Project, Construction Environmental Management Plan (CEMP) Figure 1.2 and Appendix Maps 1-63 [DBPL00-501-0722-01, Controlled Version 2, Revision B, 22/12/2008]

Environmental Line Lists (ELL) Stage 5B

Trench construction logs

The CEMP includes maps showing the location of the pipeline which appear to be consistent with Figure 1 of Schedule 1. The ELLs and Open Trench Charts confirm the extent of works for Stage 5B.

Proposed action Construct eleven pipeline looping lengths of 660 mm diameter, buried adjacent to the existing DBNGP and looped to the existing DBNGP to increase flow of natural gas.

Pipeline of 660 mm diameter buried next to existing DBNGP

DBNGP Stage 5 Expansion Project – Looping, ERA Line Pipe Specification, Appendix C – Schedule of Specific Requirements, Document no. 400/D0030 : Rev A : 24-Aug-06

Site inspections

DBNGP Stage 5B Alignment Sheets

Trench construction logs

Schedule of Specific Requirements specifies the outside diameter of the pipe to be 660 mm, which was confirmed during site inspections.

The site inspections also confirmed that the pipeline is buried adjacent to the existing DBNGP.

Alignment sheets indicate Stage 5B is located adjacent to the existing DBNGP and within the DBNGP corridor.

Total length of looping Not more than 1300 kilometres, varying from 60 to 140 kilometres per loop (approximately).

Pipeline length laid in Stage 5B up to 440 km. Trench construction logs No potential for the total length of 1300 km to be exceeded, verified by Stage 5A and 5B trench construction logs. Stage 5A is 571 km long and Stage 5B is 440 km long.

Biogeographical regions Pilbara, Carnarvon, Gascoyne, Yalgoo, Geraldton Sand Plains, Swan Coastal Plain

Construction within the Geraldton Sandplains biogeographical region.

DBNGP Stage 5 Expansion Looping Project, Construction Environmental Management Plan (CEMP) Figure 1.2 and Appendix Maps 1-63 [DBPL00-501-0722-01, Controlled Version 2, Revision B, 22/12/2008]

The CEMP (contains management plans approved by the DEC) includes maps showing the location of the pipeline that appear to be consistent with Figure 1 of Schedule 1 and indicates that the various Loops of Stage 5A and 5B are located within the appropriate biogeographical regions.

The Auditors noted that there has been no section 45C amendment to the project and also observed photographs that show the location of the pipeline adjacent to the existing pipeline demonstrating no change to the location of the pipeline easement for the project.

Local Government Authorities

Roebourne, Ashburton, Carnarvon, Upper Gascoyne, Shark Bay, Northampton, Chapman Valley, Mullewa, Irwin, Carnamah, Coorow, Dandaragan, Gingin, Chittering, City of Swan, City of Belmont, Kalamunda, Gosnells, City of Armadale, City of Cockburn, Town of Kwinana, Serpentine-Jarrahdale, Murray, Waroona

Stage 5B was constructed within the range of shires, with the exception of City of Belmont, Kalamunda, Gosnells, City of Armadale, City of Cockburn, and Town of Kwinana.

N/A The Auditors noted that there has been no section 45C amendment to the project and also observed photographs that show the location of the pipeline adjacent to the existing pipeline demonstrating no change to the location of the pipeline easement for the project.

Tenure The pipeline will be constructed wholly within the existing DBNGP easement which is gazetted under the Dampier to Bunbury Pipeline Act 1997.

New pipeline within DBNGP easement. DBNGP Contract 5B650L5075 / Part 17 – Safety and Environmental Management_Rev A

DBNGP Stage 5 Expansion Looping Project, Construction Environmental Management Plan (CEMP) (Appendix 7 – Typical drawings) [DBPL00-501-0722-01, Controlled Version 2, Revision B, 22/12/2008]

DBNGP Stage 5 Expansion Project – Looping, ERW Line Pipe Specification, Appendix C – Schedule of Specific Requirements, Document no. 400/D0030 : Rev A : 24-Aug-06

DBNGP Stage 5B Alignment Sheets

DBNGP Stage 5B Expansion Internal Audit reports

DBNGP Stage 5B Looping Expansion Rehabilitation Inspection Reports

Appendix 7 of the CEMP includes typical drawings indicating construction within the 30 m wide easement. Section 17.2 of the contract requires the Contractor to meet all requirements determined within the draft CEMP, as issued to the Contractors in conjunction with the invitation to bid.

It is understood that the pipeline has been constructed within the DBNGP easement, and that Contractors hold the survey data. The Alignment sheets, Internal Audit Report and Rehabilitation Inspection Report indicate Stage 5A and 5B is located adjacent to the existing DBNGP and within the DBNGP corridor.

Easement width The existing easement is 30 wide. The area to be cleared and graded in the northern loops (Dampier to Muchea) will be approximately 30 m and south of Muchea, the area cleared will be 20 to 30 m. In environmentally sensitive areas, working widths will be 20 m.

Construction width between 20 and 30 m except through environmentally sensitive areas, where it should be 20 m:

• Wetland and 50 m wetland buffers

• Areas within 50 m of rare flora

• TEC areas

• Bush Forever sites

• EPP lakes and wetlands.

DBP Contract No. 5B650L5076, Stage 5B Expansion Project between DBNGP (WA) Nominees Pty Ltd & DBNGP Transmission Pty Ltd & MacDow

Environmental Line Lists (ELL) Stage 5B

Easement disturbance widths over the extent of Stage 5A and 5B have varied between 20 and 23.5 m, with 20 m being applied in areas of conservation value, and are in accordance with the Statement.

Page 26: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 20

Element Description Audit criteria (Stage 5B) Evidence Finding

Activities outside the easement

Turnaround bays, campsites, turkey nests, lay down areas, water supply sources, access roads (approximately 139 ha, all to be rehabilitated)

Estimated area for turnaround bays, campsites, turkey nests, lay down areas, water supply sources, access roads is less than 139 ha.

Register of Landowners and EWS Agreements (18/12/2009) The Minister for Environment has approved clearing of approximately 139 ha of native vegetation outside of the pipeline easement for the Stage 5 expansion project, all of which is to be rehabilitated.

The clearing register for Stage 5A indicate that the total ex-easement clearing for activities outside of the easement was conducted for access roads, turning bays, camp site etc., was 49.332 ha.

The clearing register for Stage 5B indicates the total vegetation cleared outside the easement to be 40.116 ha.

The total clearing on Stage 5 to this time is 89.448 ha, being less than the limit of approximately 139 ha.

Rehabilitation is reported separately, in accordance with the requirements of the management plan.

The totals fall within the limits set and are considered compliant.

Temporary area of disturbance within easement

Not more than 3200 hectares (including not more than 1300 hectares of vegetation.

Estimated area of disturbance within easement for Stage 5.

Environmental Line Lists (ELL) Stage 5A and 5B

Trench construction logs

Easement disturbance widths over the extent of Stage 5A and 5B have varied between 20 and 23.5 m, with 20 m being applied in areas of conservation value. The total area of disturbance of both Stages 5 A and 5B is approximately 2375 ha, with approximately 414 ha of vegetation disturbance in areas of conservation value (conservation areas, wetland buffers, etc.) and 110 ha of vegetation disturbance outside conservation value areas. The details of the areas of disturbance over each of the stages is presented in Table 4.4

All areas of vegetation disturbance have been rehabilitated. Rehabilitation is reported separately, in accordance with the requirements of the management plan.

The totals fall within the limits set and are considered compliant.

Table 4.4 Disturbance areas within Easement

Stage Areas of Conservation Value Disturbed

(ha)

Areas of Vegetation Outside Areas of Conservation Value

(ha)

Other Areas of Disturbance (ha)

Totals (ha)

Stage 5A 210.846 53.823 1025.915 1290.5841

Stage 5B 203.096 56.250 824.829 1084.1745

Totals (ha) 413.942 110.07259 1850.7439 2374.7585

Page 27: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 21

Table 4.5 Key Actions summary table

Action No. MS Area Management Action Loop 0 Loop 1 Loop 2 Loop 3 Loop 4 Loop 5 Loop 6 Loop 7 Loop 8 Loop 9 Loop 10

KA 1 Results of Spring Flora Surveys

Areas of conservation value shall be entered onto the ELL.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Unable to assess

Not required at this stage

Satisfactory during this period

Satisfactory during this period

KA 2 Results of Spring Flora Surveys

No construction operations shall commence on any section until the pre–construction Threatened Flora field survey for that section is complete.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

KA 3 Results of Spring Flora Surveys

All vegetated and bushland areas shall be surveyed for Threatened Flora prior to any construction activities commencing and locations of all Threatened Flora to be protected entered onto the Environmental Line List (ELL). Threatened Flora to be protected shall be identified by a protection zone that shall include a 20 m buffer either side of the occurrence.

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

KA 4 Vegetation Disturbance

Areas of conservation value shall be clearly marked on–the–ground.

Not required at this stage

Satisfactory during this period

Not required at this stage

Satisfactory during this period

Not required at this stage

Satisfactory during this period

Not required at this stage

Unable to assess

Not required at this stage

Satisfactory during this period

Satisfactory during this period

KA 5 Vegetation Disturbance

The construction corridor width shall be reduced to 20 m within all areas of conservation value.

Not required at this stage

Satisfactory during this period

Not required at this stage

Satisfactory during this period

Not required at this stage

Potential non-conformance

Not required at this stage

Unable to assess

Not required at this stage

Unable to asses

Satisfactory during this period

KA 6 Vegetation Disturbance

A construction survey will be undertaken immediately prior to construction commencing, with pegs to clearly delineate the construction corridor and areas of disturbance outside the easement.

Satisfactory during this period in regards to the construction corridor

Unable to assess in regards to areas outside the easement

Satisfactory during this period with regards to delineation of the construction corridor

Unable to assess with regards to the areas of disturbance outside the easement

Satisfactory during this period

Satisfactory during this period

Unable to assess

Satisfactory during this period with regards to delineation of the construction corridor

Unable to assess with regards to the areas of disturbance outside the easement

Satisfactory during this period

Satisfactory during this period with respect to delineation of pipeline easement

Unable to assess with respect to areas of disturbance outside of the pipeline easement

Satisfactory during this period for delineation of pipeline easement

Unable to assess for delineation of areas of disturbance outside the easement

Satisfactory during this period

Satisfactory during this period

KA 7 Vegetation Disturbance

No construction activities shall be undertaken outside the delineated construction corridor and area of disturbance unless specifically approved.

Satisfactory during this period

Satisfactory during this period

Unable to assess

Unable to assess

Satisfactory during this period

Satisfactory during this period

Unable to assess

Satisfactory during this period with regards to the pipeline easement

Potential non-conformance with regards to areas of disturbance outside the easement

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Page 28: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 22

Action No. MS Area Management Action Loop 0 Loop 1 Loop 2 Loop 3 Loop 4 Loop 5 Loop 6 Loop 7 Loop 8 Loop 9 Loop 10

KA 8 Vegetation Disturbance

In the event that Threatened Flora cannot be avoided and destruction of some plants is necessary to implement the project, the following management steps shall be taken:

1. The impact of removal of the plants on the conservation status of the species shall be assessed at a local and regional scale by a qualified botanical consultant.

2. Options for transplanting of individual plants or salvage of biological material for later propagation shall be assessed by a qualified botanical consultant.

3. An application to take DRF shall be prepared and submitted to DEC for approval by the Minister for the Environment in accordance with the Wildlife Act. All conditions of permits shall be followed.

Not required at this stage

Not required at this stage

Not required at this stage

Not required during this period

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Satisfactory during this period

KA 9 Vegetation Disturbance

Cleared vegetation and log debris shall be stockpiled along the construction corridor separately from topsoil.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Unable to assess

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

KA 10 Vegetation Disturbance

Stockpiles shall be located adjacent to where vegetation has been cleared.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Unable to assess

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Refer to KA9 Satisfactory during this period

KA 11 Fauna Welded pipeline sections shall be capped at end of shifts to prevent fauna entry.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

KA 12 Fauna Fauna shelters/refuges (eg: cardboard boxes, hessian bags, commercial egg cartons) shall be placed in open trenches at intervals not exceeding 100 m unless alternative arrangements are agreed with DoIR in consultation with DEC on a loop by loop basis.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Unable to assess

Unable to assess

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Unable to assess

KA 13 Fauna Trench plugs and fauna exit ramps shall be installed at both ends of trenches at intervals not exceeding 1200 m and ramp slopes are not to exceed 45° unless alternative arrangements are agreed to with DoIR in consultation with DEC, on a loop by loop basis.

Satisfactory during this period

Potential non-conformance with regards to trench plugs distances

Unable to assess with regards to ramp slopes

Satisfactory during this period as at the date of the site inspection on 01/09/2009

Potential non conformance during the periods 03/09/2009 and 17/09/2009 to 22/09/2009 inclusive

Unable to assess with respect to exit ramps not exceeding 45º at several locations

Unable to assess

Potential non-conformance with regards to trench plugs distances

Unable to assess with regards to ramp slopes

Potential non-conformance with regards to trench plugs distances

Satisfactory during this period with regards to ramp slopes

Satisfactory during this period

Potential non-conformance with regards to trench plugs

Satisfactory during this period with regards to ramp slopes

Potential non-conformance with regards to trench plugs distances

Satisfactory during this period with regards to ramp slopes

Unable to assess

Satisfactory during this period

KA 14 Fauna Open trenches shall be inspected and cleared by fauna handling teams by:

• Loops 0 – 7: 4.5 hours after sunrise

• Loops 8 – 10: 5.0 hrs after sunrise

• or by times to be agreed to by DoIR in consultation with DEC.

Potential non-conformance

Satisfactory during this period

Satisfactory during this period with respect to trenches being cleared no later than 4.5 hours after sunrise

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period with respect to trenches being cleared no later than 4.5 hours after sunrise

Satisfactory during this period

Satisfactory during this period

Refer to Condition 9.2

Satisfactory during this period

Page 29: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 23

Action No. MS Area Management Action Loop 0 Loop 1 Loop 2 Loop 3 Loop 4 Loop 5 Loop 6 Loop 7 Loop 8 Loop 9 Loop 10

KA 15 Fauna Trench shall be inspected by construction contractor and cleared by a fauna handler half an hour prior to backfilling.

Unable to assess

Unable to assess

Unable to assess

Unable to assess

Unable to assess

Unable to assess

Unable to assess

Unable to assess

Unable to assess

Refer to Condition 9.2

Satisfactory during this period

KA 16 Fauna Open trench lengths shall not exceed lengths capable of being practically inspected and cleared in accordance with this protocol by the available fauna teams at any time.

Potential non-conformance

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Refer to Condition 9.3

Satisfactory during this period

KA 17 Fauna Significant habitat trees of sufficient age to form nesting hollows for hollow–nesting birds and mammals shall be marked by the fauna handling team in accordance with advice to be obtained from DEC regional staff, prior to clearing. Marked trees shall not be felled except where they materially interfere with construction of the pipeline, or are a safety concern. All habitat trees identified for felling within DEC managed estate will require signoff by the local DEC district representative.

Satisfactory during this period with regards to marking trees and liaison with DEC

Unable to assess with regards to retention of marked trees

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Unable to assess

Unable to assess

Satisfactory during this period

Potential non-conformance with regards to marking trees in accordance with advice from DEC

Unable to assess in regards to retention of habitat trees

Satisfactory during this period with regards to marking trees

Unable to assess with regards to retention of trees

Refer to Condition 9.4

Satisfactory during this period

KA 18 Fauna Prune habitat trees that overhang construction areas, rather than remove them, where practical.

Unable to assess

Satisfactory during this period

Not required at this stage.

Satisfactory during this period

Unable to assess

Satisfactory during this period

Not required at this stage

Satisfactory during this period

Unable to assess

Satisfactory during this period

Satisfactory during this period

KA 19 Fauna Daily checks of Bureau of Meteorology weather forecasts shall be undertaken. In the advent of an adverse weather forecast, the contingency action shall be implemented.

Satisfactory during this period in regards to monitoring weather forecasts

Unable to assess in regards to adverse weather forecasts and implementation of contingencies

Satisfactory during this period in regards to monitoring weather forecasts

Unable to assess in regards to adverse weather forecasts and implementation of contingencies

Unable to assess

Satisfactory during this period

Satisfactory during this period in regards to monitoring weather forecasts

Unable to assess in regards to adverse weather forecasts and implementation of contingencies

Satisfactory during this period in regards to monitoring weather forecasts

Unable to assess in regards to adverse weather forecasts and implementation of contingencies

Satisfactory during this period with respect to obtaining weather forecasts

Unable to assess with respect to contingency action

Satisfactory during this period in regards to monitoring weather forecasts

Unable to assess in regards to adverse weather forecasts and implementation of contingencies

Satisfactory during this period in regards to monitoring weather forecasts

Unable to assess in regards to adverse weather forecasts and implementation of contingencies

Refer to condition 9.6

Satisfactory during this period

KA 20 Fauna Where a trench contains water and is not dewatered, the trench shall not remain open for longer than 7 days, except within wetlands and environmentally sensitive areas where it shall not remain open for longer than 48 hours.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Satisfactory during this period

Page 30: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 24

Action No. MS Area Management Action Loop 0 Loop 1 Loop 2 Loop 3 Loop 4 Loop 5 Loop 6 Loop 7 Loop 8 Loop 9 Loop 10

KA 21 Fauna Fauna inspection and handling shall only be undertaken by teams of a minimum of two people. At least one person in each team must be able to demonstrate experience in:

• fauna identification, capture and handling (including venomous snakes)

• identification of tracks, scats, burrows and nests of conservation significant species (i.e. mulgara or malleefowl)

• fauna vouchering

• assessing injured fauna for suitability for release, rehabilitation or euthanasia

• familiarity with the ecology of the species that may be encountered in order to be able to appropriately translocation fauna encountered

• performing euthanasia

• interacting with venomous snakes.

Basic fauna handling training is to be provided to all other members of the fauna handling team who do not possess the above experience. This training is to be provided before the team members are employed in fauna inspection or clearing activities.

Fauna handlers shall be equipped with a hoop–bag for capturing animals, a snake jigger, and means of inspecting fauna shelters without the need to enter the trench.

Fauna handling shall only be undertaken by an experienced member of any fauna team, or under the direct supervision of an experienced fauna handler.

An experienced zoologist or veterinarian shall be available for consultation on fauna handling matters as required. The zoologist need not be located on site.

Potential non-conformance

Potential non-conformance

Unable to assess during period 29/08/2009 to 02/09/2008 with respect to the experience of fauna handlers

Satisfactory during the period 03/09/2009 to 24/09/2009 with respect to the number and experience of fauna handlers

Satisfactory during this period with respect to basic fauna handler training being provided prior to commencement of fauna inspections or fauna clearing activities

Satisfactory during this period with respect fauna handler equipment

Satisfactory during this period with respect to a zoologist being available to consult on fauna handling matters.

Satisfactory during this period with regards to fauna handler requirements

Potential non-conformance with respect to provision of fauna handling training

Satisfactory during this period with respect fauna handler equipment and zoologist

Satisfactory during this period with regards to experience, fauna handling by an experienced member, basic fauna hander training and availability of zoologist

Unable to assess with regards to fauna handler equipment

Satisfactory during this period with regards to fauna handler teams, experience and availability of a zoologist

Not required at this stage with regards to provision of basic fauna handler training

Unable to assess with regards to fauna handling team equipment

Satisfactory during this period with respect to the fauna handler’s experience

Satisfactory during this period with respect to basic fauna handler training being provided prior to commencement of fauna inspections or fauna clearing activities

Satisfactory during this period with respect fauna handler equipment

Satisfactory during this period with respect to fauna handler experience.

Satisfactory during this period with respect to a zoologist being available to consult on fauna handling matters.

Not required at this stage with regards to fauna handling training

Satisfactory during this period with respect to all other elements of this action

Satisfactory during this period

Refer to Condition 9.8

Satisfactory during this period

KA 22 Fauna In all conservation areas and in vegetated bushland areas in Loops 8 – 10, trenches shall not to be left open during construction breaks that exceed three days duration.

Not required at this stage

Satisfactory during this period

Not required at this stage

Not required at this stage

Not required at this stage

Satisfactory during this period

Not required at this stage

Unable to assess

Not required at this stage

Satisfactory during this period

Satisfactory during this period

KA 23 Fauna No part of the trench, other than “bell holes”, shall remain open for more than 14 days unless such an exceedance can be demonstrated as being unavoidable under the prevailing circumstances and approval is obtained from the CEO of the DEC[2].

Potential non-conformance

Potential non-conformance

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Potential non-conformance

Refer to condition 9.11

Satisfactory during this period

Page 31: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 25

Action No. MS Area Management Action Loop 0 Loop 1 Loop 2 Loop 3 Loop 4 Loop 5 Loop 6 Loop 7 Loop 8 Loop 9 Loop 10

KA 24 Fauna In environmentally sensitive areas, no part of the trench shall remain open for more than 7 days unless such an exceedance can be demonstrated as being unavoidable under the prevailing circumstances and approval is obtained from the CEO of the DEC.

Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Not required at this stage

Satisfactory during this period

Not required at this stage

Not required at this stage

Refer to condition 9.12

Satisfactory during this period

KA 25 Fauna Trench open lengths and locations (trench start and end locations by KP points)

Unable to assess

Unable to assess

Satisfactory during this period.

Satisfactory during this period.

Unable to assess

Unable to assess

Satisfactory during this period.

Unable to assess

Unable to assess

Refer to condition 9.13

Satisfactory during this period

KA 26 Fauna Weekly reports on fauna interactions shall be provided to the Environmental Management Branch DEC.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Refer to Condition 9.17

Satisfactory during this period

KA 27 Fauna Performance monitoring reports on fauna management. Monthly reporting, to be made publicly available on completion of each Loop

In process Satisfactory during this period

Not required at this stage

In process Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Refer to Condition 9.18

Satisfactory during this period

KA 28 Timing of Construction Works

Where practicable to do so, open trenching in Loops 0 to 2 shall be avoided between the months of November to March to minimise fauna stress or deaths during the summer months.

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

KA 29 Timing of Construction Works

If open trenching is undertaken in Loops 0 to 2 during November to March, trenches shall be inspected and cleared by 3 hours after sunrise, except if the maximum daily temperature is forecast to exceed 35°C, then trenches shall be inspected and cleared by 2.5 hours after sunrise.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

KA 30 Timing of Construction Works

If open trenching is undertaken in Loops 0 to 2 during November to March, local weather forecasts will be monitored on a daily basis. In the event of a forecast of rainfall likely to cause partial or complete flooding of an open trench, all lengths of trench with potential to be flooded will be backfilled, with trench inspections and fauna clearing undertaken immediately prior to backfilling. The decision on whether the trench should be backfilled shall be undertaken in consultation with the local regional office of the DEC.

Note required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

KA 31 River crossings Riparian vegetation along watercourses which will be traversed will be delineated on the ground on advice of DEC.

Satisfactory during this period with regards to flagging

Unable to assess with regards to DEC consultation

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Unable to assess with respect to advice from DEC

Unable to asses

Not required at this stage

Not required at this stage

Satisfactory during this period with regards to delineation

Unable to assess with regards to DEC advice

Satisfactory during this period

Not required at this stage

Satisfactory during this period

KA 32 Wetlands Where vegetation within a wetland or its associated buffer area is required to be disturbed to enable construction, the width of the construction corridor shall be reduced to 20 m to minimise the disturbance.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Unable to assess

Satisfactory during this period

KA 33 Dieback and Weed Management

Field surveys of dieback risk areas shall be completed to identify medium to low, medium and high risk areas in Loops 8–10 and the Environmental Line List (ELL) updated with results.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

KA 34 Dieback and Weed Management

Entry to areas identified as ‘high risk’, ‘disease/weed free’ and areas of conservation value in the ELL will only be through hygiene stations.

Not required at this stage

Satisfactory during this period

Not required at this stage

Satisfactory during this period

Not required at this stage

Satisfactory during this period

Not required at this stage

Unable to assess

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

KA 35 Dieback and Weed Management

Weed, pest and dieback (Loops 8 – 10 only) hygiene stations shall be located at:

1. Entry points for areas of conservation value.

2. Entry and exit points for areas identified as ‘high risk’ for dieback (Loops 8 – 10 only).

3. Entry and exit points for areas identified as ‘high risk’ for weeds.

Not required at this stage

Satisfactory during this period

Not required at this stage

Not required at this stage

Not required at this stage

Satisfactory during this period

Not required at this stage

Unable to assess

Satisfactory during this period

Refer to KA34

Satisfactory during this period

Page 32: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 26

Action No. MS Area Management Action Loop 0 Loop 1 Loop 2 Loop 3 Loop 4 Loop 5 Loop 6 Loop 7 Loop 8 Loop 9 Loop 10

KA 36 Acid Sulphate Soils and Dewatering

Pre–construction acid sulphate soil surveys shall be undertaken in areas where there is a HIGH, MEDIUM or MED–LOW risk of the presence of acid sulphate soils. Results shall be included in the Environmental Line List (ELL) and specific management plans developed for handling soils in these areas.

Satisfactory during this period

Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period

Refer to condition 15.1

Satisfactory during this period

KA 37 Acid Sulphate Soils and Dewatering

Soils within the MEDIUM and HIGH risk areas that are confirmed to be potentially acid generating as evidenced by a sulphide content: for coarse sandy soils (clay content <5%) of 0.03%S, for sandy loam to light clay (clay content <40%) of 0.06%S and for clayey soils with clay content >40% of 0.1%S shall, in the case of dry soils be uniformly treated with sufficient neutralising agent using a method approved by the DEC. The amount of neutralising agent at any location shall be based on the laboratory defined %S concentration with a 1.5 safety factor. Approved treatment methods include either of the following:

Prior to excavation of the trench, a layer of neutralising agent (aglime or lime sands) shall be laid along the trench line, within the width of the expected excavation. The thickness of the neutralising layer shall be based on the laboratory defined %S concentration with a 1.5 safety factor. Excavation of the trench will result in a blended stockpile. The blended stockpile should then all be placed into the trench during backfilling.

The excavated soil stockpile shall be uniformly covered with the neutralising agent (aglime or lime sands) immediately upon excavation from the trench. The thickness of the neutralising layer shall be based on the laboratory defined %S concentration with a 1.5 safety factor. The stockpile and covering layer should then all be placed into the trench during backfilling to result in a blended backfill.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Satisfactory during this period

Satisfactory during this period

KA 38 Rehabilitation Weed and disease management shall be managed in accordance with the Weed and Dieback Management Protocol (Section 4) and with the completion criteria set out in Section 18.6.

Unable to assess

Unable to assess

Not required at this stage.

Satisfactory during this period

Unable to assess

Unable to assess

Not required at this stage

In process Unable to assess

Refer to KAs 33 to 35

Satisfactory during this period

KA 39 Rehabilitation Erosion shall be managed in accordance with the Soil Management Protocol (Section 16) and with the completion criteria set out in Section 18.6.

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Unable to assess

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

Satisfactory during this period

KA 40 Rehabilitation A watercourse crossing rehabilitation and wet crossing plan shall be prepared and submitted to DoW for approval. The plan should set out the rehabilitation procedure for all major watercourse crossings and should include geotechnical survey data, stabilisation techniques and revegetation plans. The plan should also set out the detailed procedures to be applied where crossing watercourses that contain water is to be prepared for the approval of the DoW (wet crossing procedure). The procedures are to ensure that there is no adverse effect on the flow available to downstream users in terms of either quantity or quality. The procedures will set out the methods to be employed, including flow bypass methods, i.e.: trenches, pumps etc. Detailed requirements for the procedures are set out in Section 9.4.1 below.

Completed Completed Cleared Cleared Completed Completed Cleared Cleared Completed Refer to condition 11.2

Satisfactory during this period

KA 41 Rehabilitation Wetlands shall be managed in accordance with the Wetland Management Protocol (Section 5).

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Refer to KA32

Satisfactory during this period

KA 42 No campsites or laydown areas shall be located within the boundaries of the Allanooka–Dongara, Gnangara and Jandakot Water Reserves unless approved by the DoW.

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Not required at this stage

Unable to assess

Not required at this stage

Not required at this stage

Satisfactory during this period

Page 33: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 27

5. AUDIT RESULTS

This report has been prepared to address the status and compliance of the proposal with the conditions

in the Statement in accordance with the annual compliance reporting requirements of Conditions 4–1

to 4–4 of the Statement. The report considers the extent of compliance with each of the 72 conditions,

and the extent of conformance with the 42 actions within approved management plans required under

various conditions and determined to be Key Actions.

5.1 COMPLIANCE WITH STATEMENT NO. 735 CONDITIONS

The results of the audit of Statement 735 are shown in Table 4.1 and Table 4.2. Condition 1-1 of

Statement 735 requires implementation of the proposal as documented in Schedule 1 of the Statement.

The results of the audit of implementation of the key characteristics contained in Schedule 1 are

outlined in Table 4.3. Statement 735 also requires the preparation and implementation of a number of

Environmental Management Plans. Conformance with these plans is addressed in Section 5.2.

Eleven potential non-compliances with Statement No. 735 were identified by the auditors. These are

presented in summary in Table 5.1, and each is detailed in the relevant loop audit report in Appendix 2

through Appendix 12. It should be noted that DBP does not consider several of the potential non-

compliances identified by the auditors to be non-compliances.

There is no evidence that any measurable or identifiable environmental harm resulted from any of the

potential non-compliances.

5.2 CONFORMANCE WITH KEY ACTIONS

An audit of selected key management actions contained within the Environmental Management Plans

was also conducted and is outlined in Table 4.5. Twelve potential non-conformances with Key

Actions were identified by the auditors and each is detailed in the relevant loop audit report in

Appendix 2 through Appendix 12. These are presented in summary in Table 5.1. As a number of the

Key Actions directly reflect conditions of Statement No. 735, the majority of the potential non-

conformances reflect the potential non-compliances identified in Section 5.1.

It should be noted that DBP does not consider several of the potential non-conformances identified by

the auditors to be non-conformances.

There is no evidence that any measurable or identifiable environmental harm resulted from any of the

potential non-conformances.

5.3 CORRECTIVE ACTIONS

The corrective actions taken with respect to the identified potential non-compliances and potential

non-conformances are outlined in the relevant summary tables (Table 5.1 and Table 5.2 respectively).

In some cases, the proponent did not consider corrective actions to be necessary as the situations were

unusual, and/or practically unavoidable, and/or the event had passed and a remedy was not

appropriate.

Page 34: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 28

This page is deliberately blank

Page 35: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 29

Table 5.1 Summary of potential non-compliances with Statement No. 735

Statement Condition Subject to Potential Non-compliance

Loop No and Nature of Potential Non-compliance Reason Remedy Management Measures Implemented to Reduce Risk of Future Potential Non-Compliances

Condition 8.2:

The proponent shall not cause disturbance of vegetation outside the delineated pipeline easement, or the delineated area of disturbance outside the easement, as referred to in condition 8-1, unless authorised by the Minister for the Environment.

Loop 7

The potential non-compliance with this condition specifically relates to clearing beyond the delineated area of disturbance outside the pipeline easement, associated with a firebreak around the camp site.

Clearing external to the previously delineated camp site boundary was undertaken without Ministerial approval to provide an emergency firebreak. The firebreak clearing was approximately 0.75 ha in size, and its inclusion did not result in any exceedance of the total area approved for clearing under Statement No. 735.

Additional firebreak cleared after a major bushfire headed towards the camp which had to be evacuated as advised by FESA.

WestNet has advised that the clearing was undertaken in an emergency situation to protect property, at the request of FESA, and as such was an unusual occurrence. The area was fully rehabilitated in accordance with the requirements of the Rehabilitation Management Plan.

Future clearing plans for camps in fire risk areas will include a requirement for initial delineation of the proposed clearing area to make provision for fire breaks, which would not be cleared unless required.

Condition 8.3:

The proponent shall not cause or allow disturbance of vegetation outside the 20 metre wide easement located within environmentally sensitive areas, unless authorised by the Minister for the Environment.

Loop 9

Three locations along the construction right of way within an environmentally sensitive area were measured as having a width greater than 20 m.

The anomaly was due to the CROW having been constructed immediately adjacent to an historical pre-cleared pipeline track which was approximately 3 – 4 m in width.

Full width of disturbed area was fully rehabilitated in accordance with the DEC approved Rehabilitation Management Protocol requirements.

CROW widths are to be limited to 20 m in all environmentally sensitive areas irrespective of the presence of any pre-existing cleared areas such as tracks.

Condition 9.2:

The clearing of open trenches by the fauna clearing persons is to be completed each day by no later than 4.5 hours after sunrise for Loop 0 to 7 and no later than 5 hours after sunrise for Loops 8 to 10 and at least half an hour prior to the backfilling of pipeline trenches.

Loop 0

Thirteen weekly fauna reports were available for the Loop 0 audit, indicating 90 days for which trench was open and fauna clearing was required. On eight occasions, the trenches were not cleared within 4.5 hrs of sunrise (up to 2 hrs and 5 minutes overtime); including one occasion where trench clearing did not commence even though trench was open.

The incident reports outline that in most cases the exceedance was a result of heavy rains preventing or limiting access to the easement. On one occasion vehicle difficulties resulted in delayed fauna clearing. On another occasion, the relocation of a kangaroo within the trench which was caught beneath pipe required additional attention (including machinery to lift the pipe), resulting in an exceedance of the required time. Logistical delays and the numbers of fauna required to be cleared from trenches were also causes of exceedances.

Two exceedances of time (14/06/2009 by 2 minutes, 24/06/2009 by 1 hr and 8 minutes) did not have an associated incident report outlining the cause of the exceedance. The Trench Fauna Clearance Log associated with the exceedance on 24/06/2009 indicates heavy rain resulted in an approximate 1 hr and 20 minute postponement of clearing activity, resulting in the late finish to the inspection.

Reported to DEC in weekly fauna reports.

No other remedies implemented as occasions had passed, no environmental harm occurred as a result and issue could not be retrospectively rectified.

Three follow-up actions, specifically to minimise the time trench with un-shaded pipe is left exposed overnight, review of staffing resources and preparation and implementation of an Emergency Plan for unforseen events. Completion of these actions was signed-off on 1/08/2009.

Condition 9.3:

Open trench lengths shall not exceed a length capable of being inspected and cleared by fauna clearing persons within the required times as set out in conditions 9-2, 10-2 and 10-4.

Loop 0

As for 735:M9.2. There were three occasions where fauna inspections and clearing of open trench was not completed within the required times as a consequence of trench lengths exceeding a length capable of being inspected and cleared within the required times. This did not apply to those occasions when clearing was not undertaken or a limited length of trench was inspected, because of boggy or unsafe conditions or vehicle breakdown.

Condition 9.4:

Significant habitat trees of sufficient age to form nesting hollows for hollow-nesting birds and mammals shall be marked, prior to construction, in consultation with the Department of Environment and Conservation.

Loop 7

The Pre-construction Environmental Survey identified 34 trees of habitat value for Loop 7, specifically 7 trees were considered mature (potential habitat value or likely to form hollows) and 27 were considered to already be habitat trees (i.e. approximately 50 years old or older and/or contained hollows). One of these trees was considered to have significant value, with hollows observed being utilised by fauna at the time of the survey.

During the audit site inspection, the Auditors observed a number of marked (with paint) and flagged habitat trees.

The Pre-construction Environmental Survey report was provided to DEC after the commencement of construction on this loop, therefore, the action was not undertaken in consultation with DEC and the Auditor considers that this is a potential non-compliance with the requirements of the condition.

The Auditor considers that the condition does not stipulate DEC consultation is required only if significant habitat trees are to be cleared, therefore it is considered a potential non-compliance.

DBP believes that while the survey reports identified potential habitat trees in proximity to the easement, and all were marked, no trees of habitat value were found to be within the area actually proposed for clearing following survey of the easement boundaries. As it is understood that the intent of the condition relates to trees proposed to be removed, DBP believes there was no requirement to advise DEC prior to construction in this case. The survey report was provided to DEC as a courtesy only.

DBP consequently does not consider this to be a non-conformance.

No significant habitat trees were removed. None considered necessary.

Page 36: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 30

Statement Condition Subject to Potential Non-compliance

Loop No and Nature of Potential Non-compliance Reason Remedy Management Measures Implemented to Reduce Risk of Future Potential Non-Compliances

Condition 9.8:

The fauna clearing persons shall operate in teams of two with at least one fauna clearing person experienced in the following, to the requirements of DEC:

• Fauna identification, capture and handling (including venomous snakes).

• Identification of tracks, scats, burrows and nests of conservation significant species.

• Fauna vouchering.

• Assessing injured fauna for suitability for release, rehabilitation or euthanasia.

• Familiarity with the ecology of the species that may be encountered in order to be able to appropriately translocate fauna encountered.

• Performing euthanasia.

Loop 0

There are 29 occurrences when that the auditors considered that there was no Senior Fauna Handler (i.e. with sufficient experience in the matters outlined by the condition) part of a team, as required by the condition.

Additional fauna handlers were employed in response to construction schedule requiring substantial lengths of trench to be open at one time. Paucity of sufficiently experienced handlers in the market required potential engagement of people with experience less than necessary to specifically meet requirements, but were judged by MacDow as being capable of undertaking the required tasks to a satisfactory standard.

Situation was temporary and not expected to occur again. There was no evidence of environmental harm having resulted.

Fauna handler list updated more frequently and forwarded to DEC for endorsement prior to engagement of fauna handlers in undertaking trench inspections and clearing tasks.

Loop 1

Teams of two people were recorded as inspecting and clearing open trenches on all days except between the period 3/09/2009-11/09/2009 inclusive, where one person was recorded as conducting the work. The one person conducting the fauna inspections and clearing during that period was identified as a safety person or a person considered to be an assistant fauna handler, and therefore not the experience required by this condition.

The Trench Fauna Clearance Logs note that the trench on the days of concern was “Half trench and pipe trench” only.

The open trench indicated on the summaries was mostly backfilled to near ground level (final subgrade and backfill delayed due to sudden laying off of crews), with a short section of 'true' half trench and pipe trench at the very end of the loop (treated effectively as a bell hole, though the part trench was also inspected).

It was considered that provided the trench was sufficiently backfilled so as not to cause entrapment, it was not considered to be a trench with respect to the requirements of the Statement. The fact that no fauna were recovered is an indication that this requirement of a sufficient level of backfill for it not to be considered a trench was satisfied. The overall average fauna interaction rate on this loop was 10.425 animals/km of trench inspected.

DBP consequently does not consider this to be a non-conformance.

None required. There was no evidence of environmental harm having resulted.

None required.

Condition 9.9:

The proponent shall be responsible for ensuring that basic fauna handling training is provided to fauna clearing persons who do not possess the skills and experience outlined in condition 9-8 prior to the fauna clearing person commencing employment.

Loop 3:

An Assistant Fauna Handler was not recorded as having been trained by a Senior Fauna Handler prior to employment in undertaking the fauna inspection and clearing task (having been trained by an Assistant Fauna Handler).

The contractor overlooked the need for a Senior Fauna Handler to provide the required training, on the basis that the Assistant Fauna Handler was professionally qualified, and had been both trained and had previous experience in undertaking the tasks required of an Assistant Fauna Handler. The person being trained as an Assistant Fauna Handler has a tertiary qualification (Bachelor of Science [Environmental Science] [hons]).

No remedy is applicable to this situation as the time has passed. There was no evidence of environmental harm having resulted.

Future contractors will be reminded of the requirement for training to be provided by a suitably experienced fauna handler, in accordance with the requirements of the approved training package.

Condition 9.11:

No part of the trench shall remain open for more than 14 days except ‘bell holes’, unless authorised by the CEO.

Loop 0

One short portion of trench remained open for longer than the prescribed period.

Pipe laid in trench had to be removed, and trench widened after it was realised that construction specifications had not been met with respect to saddle weighting of the pipe to prevent floating when groundwater levels rise in association with flows in the Fortescue River. Additionally, the equipment permitted to work in the area was limited to reduce vibration effects on trench walls. Time taken to remove pipe, widen trench, and re-lay and backfill trench resulted in exceedance of prescribed time limit.

Pipe removal, relaying and trench backfilling was expedited to limit length of exceedance to as small a period as possible. There was no evidence of environmental harm having resulted.

Incident was considered by MacDow and WestNet to be extraordinary and the time exceedance is consequently unavoidable.

Page 37: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 31

Statement Condition Subject to Potential Non-compliance

Loop No and Nature of Potential Non-compliance Reason Remedy Management Measures Implemented to Reduce Risk of Future Potential Non-Compliances

Loop 1

One short portion of open and half filled trench remained open for longer than the prescribed period.

The open trench indicated on the summaries was mostly backfilled to near ground level (final subgrade and backfill delayed due to sudden laying off of crews), with a short section of 'true' half trench and pipe trench at the very end of the loop (treated effectively as a bell hole, though the part trench was also inspected). The recordings in the 'total open trench' in the weekly summary don't reflect this distinction, and a note was made to this effect.

It was considered that provided the trench was sufficiently backfilled so as not to cause entrapment, it was not considered to be a trench with respect to the requirements of the Statement. The fact that no fauna were recovered at times when half trench and pipe trench only were present is an indication that this requirement of a sufficient level of backfill for it not to be considered a trench was satisfied. The overall average fauna interaction rate on this loop was 10.425 animals/km of trench inspected (see fauna summary report).

DBP consequently does not consider this to be a non-compliance.

None considered necessary. There was no evidence of environmental harm having resulted.

None considered necessary.

Loop 8

Three short portions of the trench remained open for longer than the prescribed period.

Work restrictions due to bushfires burning in the region delayed crews being able to access open trench.

Once work restrictions lifted, open trench inspected for fauna and then trench backfilled. There was no evidence of environmental harm having resulted.

As work restrictions were not predictable and imposed without warning by a third party, it is not possible to avoid future reoccurrences with practicable measures. The likelihood of such occurrences is low

Condition 9.17:

The proponent shall produce weekly performance monitoring reports on fauna management for each Loop. The Reports shall include but not necessarily limited to details of all fauna inspections, the number of fauna cleared from trenches, fauna interactions, fauna mortalities and all actions taken. These reports are to be provided to the CEO each week.

Loop 9

On several occasions during the early stages of construction of Loop 9, the following details were not recorded on the fauna reports provided to the CEO:

• start and finish times of clearing of trenches

• no KP points or start and finish times were not recorded.

Some of the systems relating to fauna clearing were not completely in place at the time of commencement of construction of Loop 9, resulting some of the information relating to fauna inspections not being recorded.

Fauna report proformas were modified to include provision for entry of the required information. The Auditors noted that this non compliance was addressed so that these details were recorded in all reports prepared for later periods during the construction of Loop 9.

There was no evidence of environmental harm having resulted.

See Remedy.

Page 38: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 32

Table 5.2 Summary of potential non-conformances with Key Actions

Key Action Subject to Potential Non-conformance

Loop No and Nature of Potential Non-conformance

Reason Remedy Management Measures Implemented to Reduce Risk of Future Potential Non-Conformances

KA 5:

The construction corridor width shall be reduced to 20 m within all areas of conservation value.

Key Action partially relates to Statement Condition No. 8.3.

Loop 5

DEC advised that the construction right of way was confined to between 20 m and 20.5 m within the Toolonga Nature reserve, which indicates it was not 20 m within all areas of conservation value.

The DEC measurements were made by pacing, and not with an accurate measure, and DBP does not consider that the level of accuracy of such means is sufficient to identify a potential non-conformance.

Area was rehabilitated following construction, in accordance with the approved Rehabilitation Management Protocol. There was no evidence of residual environmental harm having resulted.

None considered necessary, other than ensuring accurate distance measuring equipment is available for use by DEC.

Loop 9

Three locations along the construction right of way within an environmentally sensitive area were measured as having a width greater than 20 m.

The anomaly was due to the CROW having been constructed immediately adjacent to an historical pre-cleared pipeline track which was approximately 3 – 4 m in width.

Full width of disturbed area was fully rehabilitated in accordance with the DEC approved Rehabilitation Management Protocol requirements.

There was no evidence of environmental harm having resulted.

CROW widths are to be limited to 20 m in all environmentally sensitive areas irrespective of the presence of any pre-existing cleared areas such as tracks.

KA 7:

No construction activities shall be undertaken outside the delineated construction corridor and area of disturbance unless specifically approved.

Key Action partially relates to Statement Condition No. 8.2.

Loop 7

The potential non-conformance specifically relates to clearing beyond the delineated area of disturbance outside the pipeline easement, associated with a firebreak around the camp site.

Clearing external to the previously delineated camp site boundary was undertaken without Ministerial approval to provide an emergency firebreak. The firebreak clearing was approximately 0.75 ha in size, and its inclusion did not result in any exceedance of the total area approved for clearing under Statement No. 735.

Additional firebreak cleared after a major bushfire headed towards the camp which had to be evacuated as advised by FESA.

WestNet has advised that the clearing was undertaken in an emergency situation to protect property, at the request of FESA, and as such was an unusual occurrence. The area was fully rehabilitated in accordance with the requirements of the Rehabilitation Management Plan.

There was no evidence of residual environmental harm having resulted.

Future clearing plans for camps in fire risk areas will include a requirement for initial delineation of the proposed clearing area to make provision for fire breaks, which would not be actually cleared unless required.

KA 13:

Trench plugs and fauna exit ramps shall be installed at both ends of trenches at intervals not exceeding 1200 m and ramp slopes are not to exceed 45° unless alternative arrangements are agreed to with DoIR in consultation with DEC, on a loop by loop basis.

Loop 1

The Loop 1 Open Trench Chart identifies the location of trench plugs, with a number of occasions identified where trench plug locations did not meet the distance requirements:

Several occasions of exceedance of the 1200 m interval distance requirements were minor (less than 300 m). On eight occasions the exceedances were substantial (being from 1.6 km to 3.7 km).

The issue was not investigated at the time of discovery of the issue, being after backfilling of the trench, and the reasons are not clear, and in some cases may have been a failure to record the trench plugs being in place.

Normal practice has been to weld the pipe above ground prior to laying, in ‘strings’ usually no longer than 1200 m in length, and to install a trench plug to allow access at the end of each string.

Issue was not discovered until after the pipe had been laid, backfilled and final trench logs prepared and submitted.

There was no evidence of environmental harm having resulted.

Regular and frequent checking of trench logs and inspection of pipeline during construction.

Loop 4

The Loop 4 Open Trench Chart identifies the location of trench plugs, with a number of occasions identified where trench plug locations did not meet the distance requirements:

Several occasions of exceedance of the 1200 m interval distance requirements were minor (less than 400 m). On three occasions the exceedances were substantial (being from 1.6 km to 3.7 km).

The issue was not investigated at the time of discovery of the issue, being after backfilling of the trench, and the reasons are not clear, and in some cases may have been a failure to record the trench plugs being in place.

Normal practice has been to weld the pipe above ground prior to laying, in ‘strings’ usually no longer than 1200 m in length, and to install a trench plug to allow access at the end of each string.

Issue was not discovered until after the pipe had been laid, backfilled and final trench logs prepared and submitted.

There was no evidence of environmental harm having resulted.

Regular and frequent checking of trench logs and inspection of pipeline during construction.

Page 39: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 33

Key Action Subject to Potential Non-conformance

Loop No and Nature of Potential Non-conformance

Reason Remedy Management Measures Implemented to Reduce Risk of Future Potential Non-Conformances

Loop 5

The Loop 5 Open Trench Chart identifies the location of trench plugs, with a number of occasions identified where trench plug locations did not meet the distance requirements:

Several occasions of exceedance of the 1200 m interval distance requirements were minor (less than 200 m). On eight occasions the exceedances were substantial (being from 1.8 km to 3.7 km).

The issue was not investigated at the time of discovery of the issue, being after backfilling of the trench, and the reasons are not clear, and in some cases may have been a failure to record the trench plugs being in place.

Normal practice has been to weld the pipe above ground prior to laying, in ‘strings’ usually no longer than 1200 m in length, and to install a trench plug to allow access at the end of each string.

Issue was not discovered until after the pipe had been laid, backfilled and final trench logs prepared and submitted.

There was no evidence of environmental harm having resulted.

Regular and frequent checking of trench logs and inspection of pipeline during construction.

Loop 7

The Loop 7 Open Trench Chart identifies the location of trench plugs, with a number of occasions identified where trench plug locations did not meet the distance requirements:

Four occasions of exceedance of the 1200 m interval distance requirements occurred, ranging from 100 to 900 m.

The issue was not investigated at the time of discovery of the issue, being after backfilling of the trench, and the reasons are not, clear, and in some cases may have been a failure to record the trench plugs being in place.

Normal practice has been to weld the pipe above ground prior to laying, in ‘strings’ usually no longer than 1200 m in length, and to install a trench plug to allow access at the end of each string.

Issue was not discovered until after the pipe had been laid and backfilled.

There was no evidence of environmental harm having resulted.

Regular and frequent checking of trench logs and inspection of pipeline during construction.

Loop 8

The Loop 8 Open Trench Chart identifies the location of trench plugs, with a number of occasions identified where trench plug locations did not meet the distance requirements:

Two occasions of exceedance of the 1200 m interval distance requirements were minor (100 m).

The issue was not investigated at the time of discovery of the issue, being after backfilling of the trench, and the reasons are not, clear, and in some cases may have been a failure to record the trench plugs being in place.

Normal practice has been to weld the pipe above ground prior to laying, in ‘strings’ usually no longer than 1200 m in length, and to install a trench plug to allow access at the end of each string.

Issue was not discovered until after the pipe had been laid and backfilled.

There was no evidence of environmental harm having resulted.

Regular and frequent checking of trench logs and inspection of pipeline during construction.

KA 14:

Open trenches shall be inspected and cleared by fauna handling teams by:

• Loops 0 – 7: 4.5 hours after sunrise

• Loops 8 – 10: 5.0 hrs after sunrise

• or by times to be agreed to by DoIR in consultation with DEC.

Key Action partially relates to Statement Condition No. 9.2.

Loop 0

Thirteen weekly fauna reports were available for the Loop 0 audit, indicating 90 days for which trench was open and fauna clearing was required. On eight occasions, the trenches were not cleared within 4.5 hrs of sunrise (up to 2 hrs and 5 minutes overtime); including one occasion where trench clearing did not commence even though trench was open.

The incident reports outline that in most cases the exceedance was a result of heavy rains preventing or limiting access to the easement. On one occasion vehicle difficulties resulted in delayed fauna clearing. On another occasion, the relocation of a kangaroo within the trench which was caught beneath pipe required additional attention (including machinery to lift the pipe), resulting in an exceedance of the required time. Logistical delays and the numbers of fauna required to be cleared from trenches were also causes of exceedances.

Two exceedances of time (14/06/2009 by 2 minutes, 24/06/2009 by 1 hr and 8 minutes) did not have an associated incident report outlining the cause of the exceedance. The Trench Fauna Clearance Log associated with the exceedance on 24/06/2009 indicates heavy rain resulted in an approximate 1 hr and 20 minute postponement of clearing activity, resulting in the late finish to the inspection.

Reported to DEC in weekly fauna reports.

No other remedies implemented as occasions had passed, no environmental harm occurred as a result and issue could not be retrospectively rectified.

Three follow-up actions, specifically to minimise the time trench with un-shaded pipe is left exposed overnight, review of staffing resources and Emergency Plan for unforseen events. Completion of these actions was signed-off on 1/08/2009.

KA 16:

Open trench lengths shall not exceed lengths capable of being practically inspected and cleared in accordance with this protocol by the available fauna teams at any time.

Key Action relates to Statement Condition No. 9.3.

Loop 0

As for KA 14. There were three occasions where fauna inspections and clearing of open trench was not completed within the required times, and therefore the lengths exceeded a length capable of being inspected and cleared within the required times. This did not apply to those occasions when clearing was not undertaken or a limited length of trench was inspected, because of boggy or unsafe conditions or vehicle breakdown.

Page 40: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 34

Key Action Subject to Potential Non-conformance

Loop No and Nature of Potential Non-conformance

Reason Remedy Management Measures Implemented to Reduce Risk of Future Potential Non-Conformances

KA 17:

Significant habitat trees of sufficient age to form nesting hollows for hollow–nesting birds and mammals shall be marked by the fauna handling team in accordance with advice to be obtained from DEC regional staff, prior to clearing. Marked trees shall not be felled except where they materially interfere with construction of the pipeline, or are a safety concern. All habitat trees identified for felling within DEC managed estate will require signoff by the local DEC district representative.

Key Action partially relates to Statement Condition No. 9.4.

Loop 7

The Pre-construction Environmental Survey identified 34 trees of habitat value for Loop 7, specifically 7 trees were considered mature (potential habitat value or likely to form hollows) and 27 were considered to already be habitat trees (i.e. approximately 50 years old or older and/or contained hollows). One of these trees was considered to have significant value, with hollows observed being utilised by fauna at the time of the survey.

During the audit site inspection, the Auditors observed a number of marked (with paint) and flagged habitat trees.

The Pre-construction Environmental Survey report was provided to DEC after the commencement of construction on this loop, therefore, the action was not undertaken in consultation with DEC and the Auditor considers that this is a potential non-compliance with the requirements of the condition.

The Auditors considered that the condition does not stipulate DEC consultation is required only if significant habitat trees are to be cleared, therefore, it is considered a potential non-compliance.

DBP believes that while the survey reports identified potential habitat trees in proximity to the easement, and all were marked, no trees of habitat value were found to be within the area actually proposed for clearing following survey of the easement boundaries. As it is understood that the intent of the condition relates to trees proposed to be removed, DBP believes there was no requirement to advise DEC prior to construction in this case. The survey report was provided to DEC as a courtesy only.

DBP consequently does not consider this to be a non-conformance.

No significant habitat trees were removed and no remedy is considered necessary.

There was no evidence of environmental harm having resulted.

None considered necessary as no significant habitat trees were proposed for removal.

KA 21:

Fauna inspection and handling shall only be undertaken by teams of a minimum of two people. At least one person in each team must be able to demonstrate experience in:

• fauna identification, capture and handling (including venomous snakes)

• identification of tracks, scats, burrows and nests of conservation significant species (i.e. mulgara or malleefowl)

• fauna vouchering

• assessing injured fauna for suitability for release, rehabilitation or euthanasia

• familiarity with the ecology of the species that may be encountered in order to be able to appropriately translocation fauna encountered

• performing euthanasia

• interacting with venomous snakes.

Basic fauna handling training is to be provided to all other members of the fauna handling team who do not possess the above experience. This training is to be provided before the team members are employed in fauna inspection or clearing activities.

Fauna handlers shall be equipped with a hoop–bag for capturing animals, a snake jigger, and means of inspecting fauna shelters without the need to enter the trench.

Fauna handling shall only be undertaken by an experienced member of any fauna team, or under the direct supervision of an experienced fauna handler.

An experienced zoologist or veterinarian shall be available for consultation on fauna handling matters as required. The zoologist need not be located on site.

Key Action partially relates to Statement Condition No. 9.8.

Loop 0

There are 29 occurrences when that the auditors considered that there was no Senior Fauna Handler (i.e. with sufficient experience in the matters outlined by the condition) part of a team, as required by the condition.

Additional fauna handlers were employed in response to issues associated with Key Actions KA 14 and KA 16. Paucity of sufficiently experienced handlers in the market required potential engagement of people with experience less than necessary to specifically meet requirements, but were judged by MacDow as being capable of undertaking the required tasks to a satisfactory standard.

No remedies implemented as occasions had passed, no environmental harm occurred as a result and issue could not be retrospectively rectified.

Fauna handler list updated more frequently and forwarded to DEC for endorsement.

Loop 1

Teams of two people were recorded as inspecting and clearing open trenches on all days except between the period 3/09/2009-11/09/2009 inclusive, where one person was recorded as conducting the work. The one person conducting the fauna inspections and clearing during that period was identified as a safety person or a person considered to be an assistant fauna handler, and therefore not the experience required by this condition.

The Trench Fauna Clearance Logs note that the trench on the days of concern was “Half trench and pipe trench” only.

The open trench indicated on the summaries was mostly backfilled to near ground level (final subgrade and backfill delayed due to sudden laying off of crews), with a short section of 'true' half trench and pipe trench at the very end of the loop (treated effectively as a bell hole, though the part trench was also inspected).

It was considered that provided the trench was sufficiently backfilled so as not to cause entrapment, it was not considered to be a trench with respect to the requirements of the Statement. The fact that no fauna were recovered is an indication that this requirement of a sufficient level of backfill for it not to be considered a trench was satisfied. The overall average fauna interaction rate on this loop was 10.425 animals/km of trench inspected.

DBP consequently does not consider this to be a non-conformance.

None considered to be required by DBP.

There was no evidence of environmental harm having resulted.

None considered to be required by DBP.

Loop 3:

An Assistant Fauna Handler was not recorded as having been trained by a Senior Fauna Handler prior to employment in undertaking the fauna inspection and clearing task (having been trained by an Assistant Fauna Handler).

The contractor overlooked the need for a Senior Fauna Handler to provide the required training, on the basis that the Assistant Fauna Handler was professionally qualified, and had been both trained and had previous experience in undertaking the tasks required of an Assistant Fauna Handler. The person being trained as an Assistant Fauna Handler has a tertiary qualification (Bachelor of Science [Environmental Science] [hons]).

No remedy is applicable to this situation as the time has passed.

There was no evidence of environmental harm having resulted.

Future contractors will be reminded of the requirement for training to be provided by a suitably experienced fauna handler, in accordance with the requirements of the approved training package.

Page 41: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 35

Key Action Subject to Potential Non-conformance

Loop No and Nature of Potential Non-conformance

Reason Remedy Management Measures Implemented to Reduce Risk of Future Potential Non-Conformances

KA 23:

No part of the trench, other than “bell holes”, shall remain open for more than 14 days unless such an exceedance can be demonstrated as being unavoidable under the prevailing circumstances and approval is obtained from the CEO of the DEC.

Key Action relates to Statement Condition No. 9.11.

Loop 0

One short portion of trench remained open for longer than the prescribed period.

Pipe laid in trench had to be removed, and trench widened after it was realised that construction specifications had not been met with respect to saddle weighting of the pipe to prevent floating when groundwater levels rise in association with flows in the Fortescue River. Additionally, the equipment permitted to work in the area was limited to reduce vibration effects on trench walls. Time taken to remove pipe, widen trench, and re-lay and backfill trench resulted in exceedance of prescribed time limit.

Pipe removal, relaying and trench backfilling was expedited to limit length of exceedance to as small a period as possible.

There was no evidence of environmental harm having resulted.

Incident was considered by MacDow and WestNet to be extraordinary and the time exceedance is consequently unavoidable.

Loop 1

One short portion of open and half filled trench remained open for longer than the prescribed period.

The open trench indicated on the summaries was mostly backfilled to near ground level (final subgrade and backfill delayed due to sudden laying off of crews), with a short section of 'true' half trench and pipe trench at the very end of the loop (treated effectively as a bell hole, though the part trench was also inspected). The recordings in the 'total open trench' in the weekly summary don't reflect this distinction, and a note was made to this effect.

It was considered that provided the trench was sufficiently backfilled so as not to cause entrapment, it was not considered to be a trench with respect to the requirements of the Statement. The fact that no fauna were recovered at times when half trench and pipe trench only were present is an indication that this requirement of a sufficient level of backfill for it not to be considered a trench was satisfied. The overall average fauna interaction rate on this loop was 10.425 animals/km of trench inspected (see fauna summary report).

DBP consequently does not consider this to be a non-compliance.

None considered necessary.

There was no evidence of environmental harm having resulted.

None considered necessary.

Loop 8

Three short portions of the trench remained open for several days longer than the prescribed period.

Work restrictions due to bushfires burning in the region delayed crews being able to access open trench.

Once work restrictions lifted, open trench inspected for fauna and then trench backfilled.

There was no evidence of environmental harm having resulted.

As work restrictions were not predictable and imposed without warning by a third party, it is not possible to avoid future reoccurrences with practicable measures. The likelihood of such occurrences is low.

Page 42: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 36

This page is deliberately blank

Page 43: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion
Page 44: DBNGP Stage 5 Looping Expansion · PDF fileThe anniversary date for submission of compliance reports is 13 December each year. ... Proponent of the DBNGP Stage 5 Looping Expansion

st rategen DBNGP Stage 5 Looping Expansion Project

DBP08048 DBNGP Stage 5B 2009 Annual Report Rev 0.doc 38

7. REFERENCES

DBP 2008, DBNGP Stage 5 Looping Expansion Project – DBPL00-506-0504-01 2007 Annual

Environmental Compliance Report (Ministerial Statement No. 735), report prepared for DBNGP

(WA) Nominees Pty Ltd by Strategen, Perth, Western Australia.

Strategen 2010a, DBNGP Stage 5 Looping Expansion Project, Stage 5B Loop 0 Compliance Audit,

report prepared for DBNGP (WA) Nominees Pty Ltd by Strategen, Perth, Western Australia.

Strategen 2010b, DBNGP Stage 5 Looping Expansion Project, Stage 5B Loop 1 Compliance Audit,

report prepared for DBNGP (WA) Nominees Pty Ltd by Strategen, Perth, Western Australia.

Strategen 2010c, DBNGP Stage 5 Looping Expansion Project, Stage 5B Loop 2 Compliance Audit,

report prepared for DBNGP (WA) Nominees Pty Ltd by Strategen, Perth, Western Australia.

Strategen 2010d, DBNGP Stage 5 Looping Expansion Project, Stage 5B Loop 3 Compliance Audit,

report prepared for DBNGP (WA) Nominees Pty Ltd by Strategen, Perth, Western Australia.

Strategen 2010e, DBNGP Stage 5 Looping Expansion Project, Stage 5B Loop 4 Compliance Audit,

report prepared for DBNGP (WA) Nominees Pty Ltd by Strategen, Perth, Western Australia.

Strategen 2010f, DBNGP Stage 5 Looping Expansion Project, Stage 5B Loop 5 Compliance Audit,

report prepared for DBNGP (WA) Nominees Pty Ltd by Strategen, Perth, Western Australia.

Strategen 2010g, DBNGP Stage 5 Looping Expansion Project, Stage 5B Loop 6 Compliance Audit,

report prepared for DBNGP (WA) Nominees Pty Ltd by Strategen, Perth, Western Australia.

Strategen 2010h, DBNGP Stage 5 Looping Expansion Project, Stage 5B Loop 7 Compliance Audit,

report prepared for DBNGP (WA) Nominees Pty Ltd by Strategen, Perth, Western Australia.

Strategen 2010i, DBNGP Stage 5 Looping Expansion Project, Stage 5B Loop 8 Compliance Audit,

report prepared for DBNGP (WA) Nominees Pty Ltd by Strategen, Perth, Western Australia.

Strategen 2010j, DBNGP Stage 5 Looping Expansion Project, Stage 5B Loop 9 Compliance Audit,

report prepared for DBNGP (WA) Nominees Pty Ltd by Strategen, Perth, Western Australia.

Strategen 2010k, DBNGP Stage 5 Looping Expansion Project, Stage 5B Loop 10 Compliance Audit,

report prepared for DBNGP (WA) Nominees Pty Ltd by Strategen, Perth, Western Australia.