Crenshaw/LAX Transit Project Construction Update Meeting July 28, 2015 1

Transcript of Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015...

Page 1: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

Crenshaw/LAX Transit Project Construction Update Meeting

July 28, 2015

1

Page 2: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

2

Project Overview

„ Design-Build Contract - Walsh Shea Corridor Constructors (WSCC)

„ 8.5 mile Light Rail Line

„ Eight (8) new stations

„ Three (3) underground

„ Four (4) at-grade

„ One (1) aerial

„ Southwestern Yard Maintenance Facility ‟ Separate Contract

„ $2.058 billion Budget

„ Planned opening: 2019

2

Page 3: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

3

Project Elevation/Alignment

3

Page 4: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

4

Project Labor Agreement

4

Project Labor Agreement (PLA) / Construction Careers Policy (CCP) Update

Crenshaw/LAX Transit Corridor Project

Report Data Through June 20, 2015 Reporting Period

Page 5: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

No. of Work Hours*

Targeted Economically Disadvantaged Worker Utilization (%)

Goal: 40%

Apprentice Utilization (%)

Goal: 20%

Disadvantaged Worker Utilization (%)

Goal: 10%

730,874.74 58.98% 17.91% Based on Total

Apprenticeable Work Hours

10.85%

Crenshaw/LAX Transit Corridor Project PLA Targeted Worker Attainment: Prime: Walsh/Shea

Report Data Through June 20, 2015

Executive Order 11246 Demographic Summary

No. of Work Hours*

African American Utilization

Asian/Pacific Islander Utilization

Caucasian Utilization

Hispanic Utilization

Native American Utilization

Other/Declined to state

Minority Utilization

Goal: 28.3%

(rounded)

Female

Utilization

Goal: 6.9%

730,874.74 16.64% 0.96% 22.82% 54.80% 1.26% 3.52% 73.66% 2.54%

*Cumulative Hours Through End of Noted Reporting Period – as Reported by Prime Contractor. Data subject to change to reflect updates or audits.

Percentage Project Complete Based on Worker Hours: 24.36% (rounded)

Page 6: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

Crenshaw/LAX Transit Corridor Project PLA Targeted Worker Attainment: Prime: Walsh/Shea

*As Reported by Walsh/Shea. Data subject to change to reflect updates or audits. Data reflects a 20 month period

Page 7: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

7 7

Metro Construction Mitigation Programs

„ Construction Relations Program

„ Community Leadership Council

„ Eat, Shop, Play Crenshaw/Inglewood

„ Metro Business Interruption Fund (BIF)

„ Metro Business Solutions Center (BSC)

7 7

Page 8: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

Business Interruption Fund

Program Overview

„ Financial assistance to small “mom and pop” businesses

„ 25 employees or less - For-profit business or non-religious, non-profit

„ Located immediately adjacent to the rail corridor and directly affected by construction

8 8

• Continuous operation for min. of two years • Ability to provide relevant financial records,

solvent and in good standing with all local, state and federal authorities

• Can file multiple requests for financial assistance

• Maximum grant of $50,000 per business, per year

Grants as of July 2015: • 110 applications • 42 approved applications (2 denied) • $748,789 in approved grant requests

Page 9: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

Business Solutions Center

„ Provides hands-on case management services and business assistance to small businesses between 48th St and 60th St

„ Small businesses not in the immediate area have access for business and technical assistance

„ BSC Services

‟ Expert business advice and technical assistance

‟ Hands-on Case Management

‟ Business outreach, partner outreach and referral services (e.g. referrals to BSC Business Partners, financial services providers, business resource providers)

„ Partnership with Del Richardson & Associates, Inc. (DRA) and collaborative with Vermont Slauson Economic Development Corporation, Los Angeles Urban League, Urban Design Center and Turning Point Communication

9 9

Page 10: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

10 10

Eat, Shop, Play Crenshaw Eat, Shop, Play Inglewood

„ Metro sponsored campaign to bring attention to local businesses impacted by construction

„ Benefits for businesses:

‟ Metro.net Website Page and Promotion

‟ Participation in ESP events

‟ Email Promotion

‟ Social Media Alerts

‟ Print, Radio, Online Ads

‟ Quarterly Raffle

10 10

Page 11: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

„ You can help support local businesses!

‟ Click “Take the Pledge” at metro.net/eatshopplay for deals and events

‟ Click “Follow” and “Share” on Facebook alerts from #espCrenshaw

‟ Attend Lunch Meet Ups, #espCrenshaw and #espInglewood (this Saturday!)

„ Quarterly Drawing is October 1st, 2015

‟ Visit metro.net/eatshopplay for a list of participating businesses

‟ Submit receipts for a chance to win cash prizes

‟ $1,000 Grand Prize, $500, 2nd Prize and $250 3rd Prize

„ Question, Comments, Suggestions?

‟ JC Lacey, Business Liaison, [email protected], 213.922.7264

Eat, Shop, Play Crenshaw Eat, Shop, Play Inglewood

Page 12: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

12 12

Community Leadership Council (CLC)

„ The mission of the Crenshaw/LAX Community Leadership Council (CLC) is to promote community-based dialogue around opportunities arising from the Crenshaw/LAX Line development and engage a wide base of community stakeholders with ongoing project activities throughout communities located along the Project alignment in a way that’s equitable, beneficial, resourceful and meets the needs of the community.

„ These actions will be carried out through topic-specific working groups, quarterly community meetings, bi-monthly construction meetings and special project collaborations with Metro staff and other community groups.

Page 13: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

13

Community Leadership Council (CLC)

Working Groups:

„ Community Engagement- Solicit input and encourage dialogue in the community on topics surrounding the Project.

„ Economic Development- Establish opportunities for job creation, commercial development, capital investment, jobs and small business development within the project area.

„ Quality of Life- Identify opportunities to improve quality of life for the community within the areas of mobility, safety and environmental health.

„ Special Projects- Additional areas of community interest

Page 14: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

14 14

Tunnel Boring Machine Art & Naming Contest

Pre-kindergarten through 12th grade students are invited to compete in a naming and art illustration contest for the new Tunnel Boring Machine (TBM) that will dig twin tunnels to connect three underground stations on the Crenshaw/LAX Transit Project. Students from pre-k through 5th grade are invited to submit art illustrations depicting their ideal community with the Crenshaw/LAX Transit Project as a central theme. Students from 6th through 12th grade are invited to submit videos or essays with recommended names for the TBM. Winners will be announced at the TBM lowering ceremony in Fall 2015. For more information on the naming and illustration contest, visit www.metro.net/crenshaw. The contest runs through Sept 1, 2015.

Page 15: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

Tunnel Boring Machine Art & Naming Contest

Page 16: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

Tunnel Boring Machine Fun Facts

Page 17: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

Southern Segment Update

(105 Fwy to West Bl)

Crenshaw/LAX Transit Project

17

Page 18: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

• Four New Stations • (3 At-Grade, 1 Aerial)

Southern Segment Construction Area

18

Page 19: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

19

Crenshaw/LAX Transit Project The Century/Aviation Bridge

A conceptual rendering of the Century/Aviation Station

Page 20: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

20

Crenshaw/LAX Transit Project Southern Segment Bridge Progress

• Pile installation (Manchester bridge) • Completed in June

• Falsework installation (Century bridge)

• Completed in July

20

Page 21: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

21

Activity Projected Start

Date

Estimated Length of

Activity

Concrete Crushing (La Brea Yard) Redondo Blvd Parking Lot Closure Pile Installation for La Brea Bridge

February, 2015 February, 2015 April, 2015

Complete Duration of project Complete

Redondo Blvd at Florence Ave. Closure

April, 2015 Duration of project

Southern Segment Completed Activities:

21

Page 22: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

22

Activity Projected Start

Date

Estimated Length of

Activity Clear and Grub along Metro ROW Rough Subgrade/Initial Excavation Guideway Storm Drain Installation Rail Welding at ROW and Redondo Bl Erect Century Bridge Falsework

March, 2015 March, 2015 June, 2015 June, 2015 July, 2015

May, 2015 May, 2015 June, 2015 July, 2015 July, 2015

Southern Segment Completed Activities:

22

Page 23: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

23

Activity Projected Start

Date*

Estimated Length of

Activity

Manchester Bridge Abutment Construction I-405 Bridge CIDH Drilling Erect Century Bridge Super Structure Green Line Bridge Falsework 111th St Waterline Relocation

August, 2015 July, 2015 July, 2015 September, 2015 August, 2015

September, 2015 August, 2015 December, 2015 September, 2015 August, 2015

Southern Segment Upcoming Bridge Construction:

Page 24: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

Activity Projected Start

Date

Estimated Length of

Activity Continued Install of Inglewood Storm Drain Continued Southwestern Yard Excavation Stockpile Maintenance

July, 2015 June, 2015

November, 2015 August, 2015

Southern Segment Upcoming Construction:

24

Page 25: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

25 25 25 25 25 25 25 25

Crenshaw/LAX Transit Project

Northern Segment Construction Update

(Crenshaw Bl between Exposition Bl and 67th St/West Bl)

Page 26: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

26 26 26 26 26

26

26 26

Northern Segment Crenshaw Bl Area Construction • Four New Stations

(3 Underground, 1 At-Grade)

• Tunnel boring from Expo to Leimert Park Station

• At-Grade construction (48th St to 59th St)

• Cut & Cover tunnel between Vernon Av to 48th St 59th St to 67th St

Page 27: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27 27 27 27

27

27

Underground Station Construction Exposition Station

27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27 27 27 27 27 27

27

27 27

Page 28: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28 28 28 28

28

28

Underground Station Construction Vernon Station

28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28 28 28 28 28 28

28

28 28

Page 29: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

Leimert Park Station Area Construction (43rd St to 48th St)

29 29 29 29 29

29

29 29 29 29 29 29 29

29

29 29 29 29 29 29 29

29

29 29 29 29 29 29 29

29

29 29 29 29 29 29 29

29

29 29 29 29 29 29 29

29

29 29 29 29 29 29 29

29

29 29 29 29 29 29 29

29

29 29 29 29 29 29 29

29

29 29 29 29 29 29 29

29

29 29 29 29 29 29 29

29

29 29 29 29 29 29 29

29 29 29 29

29

• Leimert Park will be moving to Stage C - with staging in the middle of Crenshaw Bl, south of Vernon.

• On-going utility relocation work

• Pedestrian and business access maintained during construction

• Full Crenshaw Bl closures anticipated 15 between 43rd St/Homeland and 48th St.

• 10-Day Closure Vernon Ave (Leimert Bl ‟ Crenshaw Bl) • 4-Weekend Closures Crenshaw Bl (43rd St ‟ 48th St) • 40-Day Closure Crenshaw Bl (43rd St ‟ 48th St)

22

Page 31: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

31 31

Underground Tunnel: • From Exposition to 43rd Pl

• Earth pressure balance tunnel

boring machine TBM) maintains ground pressure

• Little surface activity and vibration

• Tunnel boring machine slated to begin tunneling work in late 2015

Page 32: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

32

Park Mesa Heights Area Construction (48th St to 59th St)

• Tree removal and replacement on-going • At-Grade construction and street widening 48th St to 59th St in

late Summer or Early Fall of 2015

• Upcoming utility relocation work activities

• Worked will be performed in stages, working on alternating blocks at a time to reduce the construction impact.

Page 33: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

33

Park Mesa Heights (59thSt to 67thSt/Brynhurst)

Cut & Cover Tunnel Construction

• Traffic reconfiguration scheduled for late summer 2015 Crenshaw Bl - Two lanes in each direction Crenshaw Bl (59th St to 60th St) ‟ mid-street work zone

• Multiple stages of construction activities: Pile installation ‟ one side and one block at a time Excavation and decking at center of the street Tunnel construction at center of street Utility relocations at various locations

• Anticipated 3 ½ year construction duration with traffic reconfiguration through duration of construction

Page 34: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

34

Park Mesa Heights (59thSt to 67thSt/Brynhurst)

Cut & Cover Tunnel Construction

• Removal of street parking, temporary parking lots provided

• Left-Turn restrictions on Crenshaw Bl 63rd St (both directions) 67th St (southbound) 59th Pl (permanently to and from 59th Pl)

• Occasional weekend lane closures of Crenshaw Bl

• Pedestrian and driveway access maintained

• Daytime heavy construction

Page 36: Crenshaw/LAX Transit Projectmedia.metro.net/.../presentation_crenshawlax_2015-0728.pdfJuly 28, 2015 - Presentation - Crenshaw/LAX Transit Project Construction Update Meeting Author

Crenshaw/LAX Transit Project

36

Connect with us:

Telephone: 213-922-2736

Email: [email protected]

Web site: metro.net/crenshaw

Facebook.com/crenshawrail

Twitter.com/crenshawrail

http://www.walsh-shea-corridorconstructors.com/