Cost Engineering
www.costengineering.eu
Topics
> Who is Cost Engineering?
> What is Cleopatra Enterprise?
> Showcase Estimating an Industrial Plant: Class 4 to Class 2
> Questions & Answers
www.costengineering.eu
> Expertise
> Cost Data Development
> Education
> Professional Services
> Software solutions
Added value in Cost Engineering
www.costengineering.eu
> Preparing and validating estimates during the complete project life cycle
> Developing and supervising contract strategies
> Benchmarking
> Asset Validation / Verification
> Location factors surveys
> Planning, cost control, quantity surveying
> Risk Assessment
> Value management
Expertise
www.costengineering.eu
Cost Data Development
> Standard cost data for your estimates for onshore and offshore
> Multi-disciplinairy
> Various industries and geographical areas
> Based on DACE labour norms (Western Europe)
> Based on Vendor information, historical project data
> Well documented data qualifications
> Yearly maintenance updates possible
> 3rd Party sources:
> Richardson data
> DACE Price Booklet
> Reed business (Dutch civil)
> Van Leeuwen Buizen Pipe & Tube
www.costengineering.eu
> Based on knowledge and experience
> Individual attention in small groups
> Courses to suit managers as well as estimators
> From introducing terminology to estimating and cost management
> Company specific cost engineering programs
> Cost engineering software tools
Academy
www.costengineering.eu
> The cost engineering tool for fast and accurate estimates for the complete project life cycle
> Thorough needs analysis
> Optimized implementation
> Customized training
> Global support
Cleopatra Enterprise
www.costengineering.eu
> Bulk storage
> Construction industry
> EPC(M)
> Food and Nutrition
> Government
> Gas industry
> Heavy industry
> Pharmaceutical industry
> Petro-/chemical industry
> Power industry
> Mining & Minerals
References
www.costengineering.eu
Cleopatra Enterprise
www.costengineering.eu
Project
Analysis Cost
Estimation
Websharing
Interfacing
Workflow
Risk
Analyses
Modules
www.costengineering.eu
Characteristics
www.costengineering.eu
> Creating solid cost estimates for various elements of a project from feasibility up to construction
> Allocate all types of costs: direct, allowances, indirect, escalation and contingencies
> Creating cost objects e.g. Assemblies
> Monitor and control estimate revisions
> Perform “What-if” analysis
Cost Estimation Module
www.costengineering.eu
Cost types
www.costengineering.eu
Direct costs
Objects
Composites
Unit-Rates
Details
www.costengineering.eu
Breakdown structures
www.costengineering.eu
Breakdown structures
“What if” analysis
www.costengineering.eu
www.costengineering.eu
> Learn from your past projects
> Compare multiple projects and historical data
> Analyze scope development
> Perform health checks to be more confident
> Scheduling and cash flow trending
> Benchmark your organization
> Business intelligence through regression analysis, pivot tables, or other methods of data mining
Project Analysis
www.costengineering.eu
> Control your document routing
> Monitor progress on your projects
> Quickly draw your workflow
> Personalized dashboard
Workflow Module
Cleo
patra En
terprise
Softw
are Integratio
n
www.costengineering.eu
Show case:
Example Plant
www.costengineering.eu
> Scope> Distillate process: raw product to middle distillate> By products: top and bottom> 28 pieces of equipment (columns, heat exchangers,
tanks, pumps, vessels)> Executed in Western-Europe> Price level date 2010> Finish date: November 2011> Project life cycle: from feed to execution
> Plant design> 3D model> Process flow diagram> Equipment list
Show case: Example Plant
www.costengineering.eu
> Class 4 estimate (40% accuracy):
> Based on Factors> Parametric Equipment Models> Applying Hand methodology> Distribution of disciplines
> Class 3 estimate (20% accuracy):
> Object re-use (Engineering Standards)> Tuning for more accuracy> Include allowance, indirect, escalation and contingency> Disciplines: piping, mechanical, E&I, civil, etc.> Parts to be estimated
> Class 2 estimate (10% accuracy)
> Detailed Unit-Cost> Bill of Quantity / Material take off input> Equipment Parameters
Show case: Example Plant
www.costengineering.eu
> Benchmarking> Compare Class 4 with Class 3 Estimate> Compare Class 3 with Class 2 Estimate> Analyze using Metrics > View Key Quantities
> Scope Development> Create What-if scenario and compare alternatives > Show Comparison report
> Cash Flow Analysis> Show cash flow and schedule
Show case: Example Plant
Questions ?