29585169 Projects Cost Management

162
Project Management Professional PMP Memo No (973) Projects Cost Management (Computer Software Oriented) لحاسب بأستخدام المشروعاتلتكاليف ل ادارة اby Dr. Abdalla El Daoushy March, 2009 Jan, 2010

Transcript of 29585169 Projects Cost Management

Page 1: 29585169 Projects Cost Management

Project Management ProfessionalPMP

Memo No (973)

Projects Cost Management(Computer Software Oriented)

ادارة التكاليف للمشروعات بأستخدام الحاسب

by

Dr. Abdalla El Daoushy

March, 2009Jan, 2010

Page 2: 29585169 Projects Cost Management

2

IndexPage

Theoretical PartProjects Cost Management . . . . . . .

51. Project’s Resources Planning . . . . . .

131.1 Inputs to Project’s Resource Planning . . . .151.2 Tools & Techniques for Project’s Resource Planning . .17

1.2.1 Applying Expert Judgment . . . . 171.2.2 Identifying Alternative Solutions . . . 181.2.3 Relying on Project Management Software . . 18

1.3 Outputs of Project’s Resource Planning . . . 19

1.3.1 Identifying Resource Requirements . . . 19

2. Project’s Cost Estimating . . . . . . .202.1 Inputs to Project’s Cost Estimating . . . .20

2.1.1 Using Work Breakdown Structure . . . 222.1.2 Relying on the Resource Requirements . . 222.1.3 Calculating Resource Rates . . . . 222.1.4 Estimating Activity Duration . . . . 242.1.5 Using Estimating Publications . . . 262.1.6 Using Historical Information . . . . 262.1.7 Referencing the Chart of Accounts . . . 272.1.8 Acknowledging the Cost of Risk . . . 27

2.2 Tools & Techniques for Project’s Cost Estimating . .28

2.2.1 Using Analogous Estimating . . . . 282.2.2 Using Parametric Modeling . . . . 282.2.3 Using Bottom-Up Estimating . . . . 302.2.4 Using Computer Software . . . . 30

2.3 Outputs of Project’s Cost Estimating . . . .31

2.3.1 Estimating Project Costs . . . . 312.3.2 Analyzing Cost Estimating Results . . . 312.3.3 Refining the Cost Estimates . . . . 322.3.4 Considering the Supporting Detail . . . 322.3.5 Developing the Cost Management Plan . . 32

3. Completing Project’s Cost Budgeting . . . . .33

Page 3: 29585169 Projects Cost Management

3

3.1 Inputs to Project’s Cost Budgeting . . . .34

3.1.1 Cost Estimates . . . . . . 343.1.2 Work breakdown Structure . . . . 343.1.3 Project Schedule . . . . . 343.1.4 Risk management Plan . . . . 34

3.2 Tools & Techniques of Project’s Cost Budgeting . .35

3.2.1 Analogous Budgeting . . . . .353.2.2 Parametric Modeling . . . . . 353.2.3 Bottom-Up Budgeting . . . . . 353.3.4 Computerized Tools . . . . . 35

3.3 Outputs of Project’s Cost Budgeting . . . .36

3.3.1 Creating the Cost Baseline . . . . 36Page

4. Implementing Project’s Cost Control . . . . .374.1 Inputs to Project’s Cost Control . . . . 38

4.1.1 Cost Baseline . . . . . . 384.1.2 Performance Reports . . . . . 384.1.3 Change Requests . . . . . 384.1.4 Cost Management Plan . . . . 38

4.2 Tools & Techniques of Project’s Cost Control .. 39

4.2.1 Creating a Cost Change Control System . . 394.2.2 Measuring Project Performance . . . 404.2.3 Planned Value (PV) . . . . . 414.2.4 Earned Value (EV). . . . . 414.2.5 Actual Cost (AC) . . . . . 414.2.6 Additional Planning . . . . . 414.2.7 Using Computers . . . . . 42

4.3 Outputs of Project’s Cost Control --- Cost Control Results. 43

4.3.1 Revising the Cost Estimates . . . . 434.3.2 Updating the Budget . . . . . 444.3.3 Applying Corrective Actions . . . . 454.3.4 Preparing for the Estimate at Completion . . 454.3.5 Calculating the Cost Performance Index (CPI) . 454.3.6 Calculating Estimate at Completion (EAC). .484.3.7 Experiencing Expected Condition . . 484.3.8 Accounting for Flawed Estimates . . 494.3.9 Accounting for Anomalies . . . . 504.3.10 Accounting for Permanent Variances . . 514.3.11 Closing Out the Project . . . . 524.3.12 Updating Lessons Learned . . . . 52

Page 4: 29585169 Projects Cost Management

4

Summary . . . . . . . . . 53

Key Terms . . . . . . . . . 55

Self Test . . . . . . . . . 61

Practical PartPage

Scenario 1: . . . . . . . . . 69 Defining Roles, Resources, & Costs . . . 70 Assigning Roles . . . . . . 71 Assigning Resources & Costs . . . . 72 Analyzing Resources . . . . . . 73

Scenario 2: . . . . . . . . . 74 Optimizing the Project Plan . . . . . 75 Baselining . . . . . . . 76 Project Execution & Control . . . . 77

Scenario 3: . . . . . . . . . 78 Reporting Performance . . . . . 79

Workshop (Case Study): Building 2nd Floor of a Villa . . .80

References . . . . . . . . .106

Page 5: 29585169 Projects Cost Management

5

Theoretical Part

Page 6: 29585169 Projects Cost Management

6

Page 7: 29585169 Projects Cost Management

7

1Resource Planning

1Resource Planning

3Cost Budgeting

3Cost Budgeting

4CostControlling

4CostControlling

2Cost Estimating

2Cost Estimating

Projects Cost Management

Planning

Execution &Controlling(Updating)

Cost Estimating is the process of calculating the Costs of Resources needed to complete the Project Work. Cost Budgeting is the process of assigning a cost to an individual work package.

Page 8: 29585169 Projects Cost Management

8

Projects Cost Management:

Most likely there is more negotiating, questioning, and evaluating for larger Projects than for smaller ones.

The relation between the Project’s Cost and the Project’s Scope should be direct: you get what you pay for.

A successful Project Manager must be able to plan, predict, budget, and control the costs of a Project.

Costs associated with Projects are not just the costs of goods procured to complete the Project.

The cost of Labor may be one of the biggest expenses of a Project.

The Project Manager must rely on time estimates to predict the cost of the labor to complete the Project Work.

In addition, the Cost of Equipments and Materials needed to complete the Project Work must be considered into the Project’s Expenses.

Page 9: 29585169 Projects Cost Management

In brief:

Projects Cost Management Processes:

1. Resource Planning

1.1 Inputs to Resource Planning

1.1.1 WBS

1.1.2 Historical Information

1.1.3 Scope Statement

1.1.4 Resource Pool Description

1.1.5 Organizational Policies

1.1.6 Activities Duration Estimates

1.2 Tools & Techniques of Resource Planning

1.2.1 Expert Judgment

1.2.2 Alternatives Identification

1.2.3 Project Management Software

1.3 Outputs of Resource Planning

1.3.1 Resource Requirements

Page 10: 29585169 Projects Cost Management

10

Hint: Refer to “Scenario1” of “Practical Part”

2. Cost Estimating

2.1 Inputs to Cost Estimating

2.1.1 Using WBS & RBS

2.1.2 Relying on Resource Requirements (output of previous process)

2.1.3 Calculating Resource Rates

2.1.4 Activities Duration Estimates

2.1.5 Using Cost Estimating Publications

2.1.6 Using Historical Information

2.1.7 Referencing the Chart of Accounts

(Chart of Accounts: A Coding System used by Performing Organization’s Accounting System to account for the Project Work)

2.1.8 Acknowledging the Cost Risk

2.2 Tools & Techniques for Cost Estimating

2.2.1 Using Analogous Estimating

2.2.2 Using Parametric Modeling

2.2.3 Using Bottom-Up Estimating

2.2.4 Using Computerized Tools

10

Page 11: 29585169 Projects Cost Management

11

2.3 Outputs of Cost Estimating

2.3.1 Estimating Project Costs

2.3.2 Analyzing Cost Estimating Results

2.3.3 Refining the Cost Estimates

2.3.4 Considering the Supporting Detail

(Supporting Detail: Any Information that supports Decisions, including the Project Plan as a whole. Supporting Detail can include Books, Articles, Web Sites, Vendor Information, Results of Testing, Historical Information, and many others Information Sources.)

2.3.5 Developing the Cost Management Plan

Hint: Refer to “Scenario1” of “Practical Part”

11

Page 12: 29585169 Projects Cost Management

12

3. Completing Cost Budgeting

3.1 Inputs to Cost Budgeting

3.1.1 Cost Estimates (from previous process)

3.1.2 WBS

3.1.3 Project Schedule

3.1.4 Risk Management Plan

3.2 Tools & Techniques of Cost Budgeting

3.2.1 Analogous Budgeting

3.2.2 Parametric Modeling

3.2.3 Bottom-Up Budgeting

3.2.4 Computerized Tools

3.3 Outputs of Cost Budgeting

3.3.1 Creating the Cost Baseline

Hint: Refer to “Scenario2” of “Practical Part”

12

Page 13: 29585169 Projects Cost Management

13

4. Implementing Cost Control

4.1 Inputs to Cost Control

4.1.1 Cost Baseline (from previous process)

4.1.2 Performance Reports

4.1.3 Change Requests

4.1.4 Cost Management Plan (from process 2)

4.2 Tools & Techniques of Cost Control

4.2.1 Creating a Cost Change Control System

4.2.2 Measuring Project Performance

4.2.3 Earned Value Management (EVM)

4.2.3.1 Planned Value (PV)

4.2.3.2 Earned Value (EV)

4.2.3.3 Actual Value (AV)

4.2.4 Additional Planning

4.2.5 Computerized Tools

13

Page 14: 29585169 Projects Cost Management

14

4.3 Outputs of Cost Control --- Cost Control Results

4.3.1 Revising the Cost Estimates

4.3.2 Updating the Budget

4.3.3 Applying Corrective Actions

4.3.4 Preparing for the Estimate at Completion

4.3.5 Calculating the Cost Performance Index(CPI)

4.3.6 Calculating Estimate At Completion (EAC)

4.3.7 Accounting for Anomalies

4.3.8 Accounting for Variances

4.3.9 Project Closeout

4.3.10 Updating Lessons Learned

Hint: Refer to “Scenario2” of “Practical Part”

14

Page 15: 29585169 Projects Cost Management

15

In details,

Project’s Resources Planning :

As part of the Planning Process, the Project Manager must determine what Resources are needed to complete the Project.

Resources include Labor (people), Nonlabor (Equipments), and Materials that will be utilized to complete the Project.

In addition, the Project Manager must identify how many & when of the Resources are needed for the Project.

The Identification of Resources, the Needed Quantity, and the Schedule of Resources are directly linked to the expected cost of the Project as shown:

15

Page 16: 29585169 Projects Cost Management

16

Example: Automate a “New Home” Project:

o The Lights, Air-Conditioning, Electrical Devices, and Home Security are all connected through a Central Computer Operating System.

o The Resources to complete the Project Work would include Technicians, HVAC Experts, Electricians, and other People with the knowledge to install and configure the components.

o The Resources in this case, however, would also include the Network Cabling to connect the components, Diagnostic Tools to monitor and test the installation, and the Equipments & Tools to physically install the components.

o In addition, Services are considered Resources as well. Your Project may require a Vendor's Service, such as a Printer, a Carpenter, or Other Service.

o If these services are not available for the Project as planned, the Project will suffer from delaying. Some Projects require you to lease space; the Leased Space is considered a Resource.

o In some instances, it is most cost effective to hire a Consultant or Subject Matter Expert (SME) to identify details unique to the Project Work, such as permissions, laws, and so on. The expense of relying on the SME may be far less than the cost of the time to research the unique details and requirements of the Project. The knowledge gained from the SME can balance the expenses that would otherwise result from not having specialized knowledge of the Project Work.

Exam

16

Page 17: 29585169 Projects Cost Management

17

1.1 Inputs to Project’s Resource Planning

Resource Planning is the process of examining the Project Work and determining what Resources (People, Equipments, and Materials) are needed to complete the Project.

Resource Planning also includes identifying the expected quantity of each Resource so the Predicted Cost can be calculated.

The following are some familiar Inputs to Resource Planning :

1.1.1 Work & Resource Breakdown Structure: The WBS & RBS help the Project Manager and the Project Team identifies the components requiring specific People, Equipments, and Materials.

1.1.2 Historical Information: Historical Information should be used if it is available, as it is Proven Information.

1.1.3 Project Scope: The scope statement serves as a key input to Resource Planning since the Scope Statement defines the Project Work. The required work, therefore, can help identify the Required Resources to Complete the Project.

1.1.4 Resource Pool Description:

o The Project Manager should identify the availability of Resources for the Project (People, Materials, and Equipments).

1.1.5 Performing Organization's Policies:

o The Performing Organization's Policies regarding Staff Achievements must be taken into consideration.

o In addition, any Procurement Policies to ascertain (determine) lease or rent equipment must be evaluated.

17

Page 18: 29585169 Projects Cost Management

18

o The Project Manager should be aware of these requirements before Resources Planning.

o Time invested identifying Resources may be lost if the process conflicts with the Organizational Policies.

1.1.6 Activities Duration Estimates:

o The duration of the Project’s Activities are needed so the Project Manager and the Project Team can consider the Resources & Costs and therefore the benefits of assigning more effort to reduce Activities’ Duration where feasible.

o The Activities Duration Estimates should be readily available from the “Time Management Processes” .

18

Page 19: 29585169 Projects Cost Management

19

1.2 Tools & Techniques for Project’s Resource Planning

1.2.1 Applying Expert Judgment

Preparing the Inputs to Resource Planning, the Project Manager and the Project Team should be ready to identify and plan the need for the Project Resources.

The Project Manager and Project Team will examine the Project Work and Resources Availability and then apply reason, logic, and experience in evaluating the Available Resources in relation to the Project’s Requirements.

A Person or Group can offer Expert Judgment on the Project Resource Needs. The Person or Group offering the Expert Judgment should have the expertise, experience, or training needed to evaluate and analyze the Resources that the Project needs.

Expert Judgment can come from several Sources:

Internal Subject Matter Experts (SME), such as Resources from other Departments

External Subject Matter Experts (SME), such as Consultants

Trade and Professional Associations

Industry Groups

19

Page 20: 29585169 Projects Cost Management

20

1.2.2 Identifying Alternative Solutions

Alternatives-Identification is any process that identifies other solutions to an Identified Problem. These Approaches typically use brainstorming and imaginative thinking. In this process, Alternatives-Identification may include Buy-versus-Build Scenarios, Outsourcing, Cross Training, and Other Activities.

The idea of using Alternatives-Identification is to ensure that the Identified Resources are complete and that the Cost of Resources is the best fit for the Project Work.

Value Analysis is an Approach to find more affordable (reasonable) and less costly Methods of accomplishing the same work. For example, a Project Manager may change Activities-Sequencing to shorten the Project’s Duration, while saving Labor Costs by assigning high-cost Resources only to the Activities that demand them.

1.2.3 Relying on Project Management Software

o Project Management Software can assist in Resource Panning.

o Project Management Software can help the Project Manager identify and organize the Resources Pool.

o Project Management Software can be configured to organize Common Resources, Talents, Skill Sets, Resources Calendars, Rates, Contract Information, and more.

20

Page 21: 29585169 Projects Cost Management

21

1.3 Outputs of Project’s Resource Planning

1.3.1 Identifying Resource Requirements:

Once the Project Manager and Project Team have completed Resource Planning, the required Resources to complete the Project will have been identified.

The Resource Identification is specific to the lowest level of the WBS (i.e., Project Activities).

The Identified-Resources will need to be obtained through Staff-Acquisition or through Procurement.

Resource Planning identifies all of the Required-Resources.

21

Page 22: 29585169 Projects Cost Management

22

Project’s Cost Estimating

Cost Estimating is the process of calculating the Costs of Resources needed to complete the Project Work.

The Person or Group doing the Cost Estimating must consider the possible fluctuations, inflation, conditions, and other causes of Variances that could affect the total Cost Estimating.

Cost Estimating and Pricing:

o There is a difference between Cost Estimating and Pricing.

o A Cost Estimate is the cost of Resources required to complete the Project Work.

o Pricing , however, includes a profit margin . In other words, a Company performing Projects for other Organizations may do a cost estimate to see how much the Project is going to cost to complete. Then, with this Cost Information, they will factor a profit into the Project Work, as shown:

22

Page 23: 29585169 Projects Cost Management

23

The costs for Scheduled Activities are:

o Labor (People)

o NonLabor (Equipments)

o Materials

o Expenses:

Services

Facilities

Inflation Allowance

Contingency (emergency) Cost

23

Page 24: 29585169 Projects Cost Management

24

2.1 Inputs to Project’s Cost Estimating

Cost Estimating relies on Historical Information and Policies from the Performing Organization.

2.1.1 Using the Work Breakdown Structure:

Of course, the WBS is included. It is an input to five major Planning Processes: 1- Activity Definition, 2- Resource Planning, 3- Cost Estimating, 4- Cost Budgeting, and 5- Risk Management Planning.

2.1.2 Relying on Resource Requirements:

The output of Resource Planning serves as a key input to Cost Estimating.

The Project will have some Resources Requirement. The Skills of the Labor, the Availability of Materials, or the Function of Equipments, must all be accounted for Cost Estimating.

24

Page 25: 29585169 Projects Cost Management

25

2.1.3 Calculating Resource Rates:

The Estimator has to know how much each Resource costs. The Cost should be in some Unit of Time or Unit of Measure --- such as:

$/hr, $/ton, $/lf (long feet), or $/use.

There are four Categories of Cost:

1. Direct Costs: These costs are accredited directly to the Project Work and cannot be shared among Projects (airfare, hotels, long distance phone charges, and so on).

2. Indirect Costs: These costs are representative of more than one Project (Utilities-of-Performing-Organization, Access-to-Training-Room, Project-Management-Software-License, and so on).

3. Variable Costs: These costs vary depending on the conditions applied in the Project (number of Meetings for Participants, Supply and Demand of Materials, and so on).

4. Fixed Costs: These costs remain constant throughout the Project (the Cost-of-Rented-Equipment for the Project, the Cost-of-Consultant brought onto the Project, and so on).

25

Page 26: 29585169 Projects Cost Management

26

2.1.4 Estimating Activity Durations:

Activities’ Durations Estimating (which predicts the length of the Project as a whole) are needed for decisions on Project’s Financing.

Recall the formula for Present Value. It is:

FV= PV * (1+R)n

; PV is the present value,

FV is the future value,

R is the interest rate, and

n is the number of time periods.

The Future Value of the Money the Project will earn may need to be measured against the Present Value to determine if the Project is worth financing, as shown here:

26

Page 27: 29585169 Projects Cost Management

27

Determining of the Activities’ Durations are needed in order to estimate the Total Cost of the Project. For example, if an Activity is estimated to last 14 hours and Suzanne’s Cost is $80/h, then the Cost of this Activity will be $1,120.

The Duration shows Management how long the Project is expected to last and which Activities will cost the most and provides the opportunity to re-sequence Activities to shorten the Project’s Duration---which consequently shortens the finance period for the Project.

There are three Approaches to estimate the Product’s Cost:

1. Straight-Line Depreciation : allows the Organization to write off the same amount each year. The formula for straight-line depreciation is:

Yearly Deduction =(Purchase Value - Salvage Value) / Number of Years in Use.

الخصممم (تكلفممة الهلك) السممنوي = (سممعر الشممراء - قيمممةالخردة ) ÷ العمر النتاجي للصل

See Question no 19 page 65……

27

Page 28: 29585169 Projects Cost Management

28

For example, if the purchase price of a photocopier is $7,000 and the salvage value of the photocopier in five years is $2,000, the formula would read:

Yearly Deduction = (7,000 - 2,000)/5 = $1,000

2. Double-Declining Balance: is considered accelerated depreciation. This method allows the organization to double the percentage written off in the first year.

In our preceding example, a single deduction was $1,000 per year, which is 20% of the total deduction across the five years.

With double-declining, the customer would subtract 40% the first year, and then 40% of the remaining value each subsequent year. In our example, the deducted amount for year one would be $2,000. For year two, it would be $1,200, and year three it would be $720.

This is a great method for Equipment that you don’t anticipate to have around for a very long time---such as Computer Equipment.

3. Sum of the Year’s Depreciation is like a magic trick. It works by writing out the number of years the equipment is in production and adding each year to the year before.

In our example: it was five years, so we do this: 5+4+3+2+1=15 (note the largest to smallest).

The sum of the years (15) becomes our denominator; the five, for the first year, is our numerator.

So for the first year, we’d deduct 5/15 (or one third) of the Photocopier Cost after the Salvage Amount, which would be $1,650.

The second year, the four would be the numerator and we deduct $1,250, and so on. Each year we’d deduct a slightly smaller percentage than the year before.

2.1.5 Using Cost Estimating Publications:

There are (for different Industries) Commercial Cost Estimating Publications. These references can help the Project Estimator confirm

28

Page 29: 29585169 Projects Cost Management

29

and predict the accuracy of estimates. If a Project Manager elects to use one of these Commercial Databases, the Cost Estimate should include a pointer to this document for future reference and verification.

2.1.6 Using Historical Information:

Historical Information is Proven Information and can come from several places:

Project Files: Past Projects within the Performing Organization can be used as a reference to predict Costs and Time. Caution must be taken that the records referenced are accurate, somewhat current, and reflective of what was actually experienced in the Historical Project.

Commercial Cost-Estimating Database: These databases provide estimates of what the Project should cost based on the variables of the Project, Resources, and other Conditions.

Team Member’s Knowledge: Team Members may have specific experience with the Project Cost Estimate. Recollections may be useful, but are highly unreliable when compared to documented results.

Lessons Learned: Lessons Learned could include Cost Estimates obtained from previous Projects that are similar in Scope and Size.

Exam Watch

2.1.7 Referencing the Chart of Accounts:

This is a Coding System used by the Performing Organization’s Accounting System to account for the Project Work.

Estimates within the Project must be mapped to the correct code of accounts so that the Organization’s Ledger reflects the Actual Work Performed, the Cost of the Work Performed, and any billing (internal or external) that was charged to the Customer for the Completed Work.

2.1.8 Acknowledging the Cost of Risk:

29

Page 30: 29585169 Projects Cost Management

30

The impact of Risks, for positive or negative effect, must be evaluated and considered in the Cost Estimates.

2.2 Tools & Techniques for Project’s Cost Estimating

2.2.1 Using Similar Estimating:

Similar Estimating relies on Historical Information to predict the Cost of the current Project. It is also known as Top-Down Estimating.

The process of Similar Estimating takes the Actual Cost of a Historical Project as a basis for the current Project. The Cost of the Historical Project is applied to the Cost of the Current Project, taking into account the Scope and Size of the Current Project as well as other known Variables.

Similar Estimating is a form of Expert Judgment. This Estimating Approach takes less time to complete than other Estimating Models, but is also less accurate. This Top-Down Approach is good for fast estimates to get a general idea of what the Project may cost.

Example of Similar Estimating:

30

Page 31: 29585169 Projects Cost Management

31

The “Carlton Park Project” was to grade and pave a sidewalk around a Swimming Pool in the Community-Park. The sidewalk of Carlton Park was 1,048 feet by 6 feet, and cost $25,287 to complete.

The current Project, “King Park Project”, will have a similar surface and will cover 4,500 feet by 6 feet. The Analogous Estimate for this Project, based on the work in Carlton-Park, is $108,500. This is based on the price/foot of Material at $4.02.

2.2.2 Using Parametric Modeling:

Parametric Modeling uses a Mathematical Model based on known parameters to predict the Cost of a Project. The parameters in the Model can vary based on the type of work being completed.

A parameter can be cost/long foot, cost/cubic yard, cost/unit, and so on.

A complex parameter can be cost per unit with adjustment factors based on the conditions of the Project. In addition, the adjustment factors may have additional modifying factors depending on additional conditions.

To use Parametric Modeling, the factors the model is based on must be accurate. The factors within the Model are quantifiable and do not vary much based on the effort applied to the Activity. And finally, the Model must be scalable between Project-Sizes.

The Parametric Model using a scalable Cost/Unit Approach is depicted here:

31

Page 32: 29585169 Projects Cost Management

32

There are two types of Parametric Cost Estimating:

1. Regression Analysis:

This is a Statistical Approach to predict what Future Values may be based on Historical Values.

2. Learning Curve:

This Approach is simple. The cost/unit decreases the more units Workers complete; this is because Workers learn as they complete the required Work. The more an Individual completes an Activity, the easier it is to complete. The estimate is considered parametric, as the formula is based on repetitive Activities such as wiring Telephone-Jacks, Painting-Hotel-Rooms, or other Activities that are completed over and over within a Project. The cost/unit decreases as the experience increases because the time to complete the Work is shortened.

2.2.3 Using Bottom-Up Cost Estimating:

32

Page 33: 29585169 Projects Cost Management

33

Bottom-Up Estimating starts from zero, accounts for each component of the WBS, and arrives at a sum for the Project. It is completed with the Project Team and can be one of the most time-consuming Methods to predict Project Costs.

While this method is more expensive (because of the time invested to create the estimate) it is also one of the most accurate.

Exam Watch

2.2.4 Using Computer Software:

Computer Software can assist the Project Manager. There are several different Computer Programs that can make Accurate Estimates for the Project Work.

2.3 Output of Project’s Cost Estimating

2.3.1 Estimating Project Costs:

Management, Customers, and other interested Stakeholders are all going to be interested in what the Project is going to cost to complete.

The Estimates are reflective of the Accuracy of the Information the Estimate is based upon. The more Accurate the Information, the better the Cost Estimate will be.

2.3.2 Analyzing Cost Estimating Results:

The output of Cost Estimating is the Cost Estimates of the Resources required to the complete the Project Work.

The Estimate is typically quantitative and can be presented in detail against the WBS Components or summarized in terms of a Grand Total, by phases of the Project, or by Major Deliverables (like Sub-Contractors).

33

Page 34: 29585169 Projects Cost Management

34

Each Resource in the Project must be accounted for and assigned to a Cost Category.

Cost Categories include:

Labor Costs Material Costs Travel Costs Supplies Hardware Costs Software Costs

The Cost of the Project is expressed in Monetary Terms, such as dollar, euro, or yen, so Management can compare Projects based on Costs.

It may be acceptable, depending on the demands of the Performing Organization, to provide estimates in Staffing Hours or Days of Work to complete the Project along with the Estimated Costs.

2.3.3 Refining the Cost Estimates:

Through the Project Progresses, the Estimates are refined. Industry Guidelines and Organizational Policies may define how the Estimates are refined, but there are generally three accepted Categories of Estimating Accuracy:

1. Rough Order of Magnitude: This Estimate is ‘rough’ and is used during the Initiating Processes and in Top-Down Estimates. The range of variance for the estimate can be -25% to +75%.

2. Budget Estimate: This Estimate is also somewhat broad and is used early in the Planning Processes and also in Top-Down Estimates. The range of variance for the estimate can be -10% to +25%.

3. Definitive Estimates This estimate type is one of the Most Accurate. It is used late in the Planning Processes and is associated with Bottom-Up Estimating. The range of variance for the estimate can be -5% to +10%.

2.3.4 Considering Supporting Detail:

34

Page 35: 29585169 Projects Cost Management

35

Once the Estimates have been completed, Supporting Detail must be organized and documented to show how the Estimates were created.

The Supporting Detail includes the following:

o Information on the Project Scope Work This may be provided by referencing the WBS.

o Information on the Approach used in Developing the Cost Estimates This can include how the estimate was accomplished and the parties involved with the Estimate.

o Information on the Range of Variance in the Estimate For example, based on the estimating method used, the Project Cost may be $220,000 ± $15,000. This Project Cost may be as low as $205,000 or as high as $235,000.

2.3.5 Developing the Cost Management Plan:

The Cost Management Plan details how Project Costs Variances will be managed.

3. Completing Project’s Cost Budgeting

Cost Budgeting: Cost Budgeting is the process of assigning a cost to an Individual Work Package. The goal of this process is to assign costs to the Work in the Project so that the Work may be measured for performance.

Cost Budgeting involves aggregating the estimated Costs of Individual Activities or Work Packages to establish a Total Cost Baseline for measuring Project Performance.

This is the creation of the Cost Baseline, as shown:

35

Page 36: 29585169 Projects Cost Management

36

Cost Budgeting and Cost Estimates may go hand-in-hand, but Estimating should be completed before a Budget is requested or assigned.

The difference between Cost Estimates and Cost Budgeting is that Cost Estimates show Costs by Category, whereas a Cost Budget shows Costs across Time according to Project’s Schedule.

3.1 Inputs to Project’s Cost Budgeting

Because Cost Budgeting and Cost Estimating are so closely related, you can expect many of the same inputs for both.

Here are the inputs to Cost Budgeting:

3.1.1 Cost Estimates: These serve as key inputs; they are the predicted cost for the Project Work.

36

Page 37: 29585169 Projects Cost Management

37

3.1.2 Work Breakdown Structure: It is a key input to this process, as it is the Deliverables of the Project.

3.1.3 Project Schedule: The Project Schedule is needed to determine when the money in the Budget will be spent.

3.1.4 Risk Management Plan: The Risk Management Plan is considered because of information it provides of the probability of Identified Risks and their associated Costs. In addition, the Risks may have an expected Risk Value that contributes to the Contingency Reserve for the Project.

3.2 Tools & Techniques of Project’s CostBudgeting --- Developing the Project

Budget

The Tools and Techniques used to create the Project Cost Estimates are also used to create the Project Budget. Here is a quick reminder of the four components:

3.2.1 Similar Budgeting: This is a form of Expert Judgment that uses a Top-Down Approach to predict Costs. It is generally less accurate than other Budgeting Techniques.

37

Page 38: 29585169 Projects Cost Management

38

3.2.2 Parametric Modeling: This Approach uses a Parametric Model to extrapolate what Costs will be for a Project (for example, cost/hr and cost/unit).

3.2.3 Bottom-Up Budgeting: This Approach is the most reliable, though it takes the longest time to create. It starts at zero and requires each Work Package to be accounted for.

3.2.4 Computerized Tools: The same Software Programs used in Estimating can help predict the Project Budget with some accuracy.

3.3 Output of Project’s Cost Budgeting

3.3.1 Creating the Cost Baseline

o A Project’s Cost Baseline shows what is expected to be spent on the Project. It is usually shown in an S-curve as follows:

38

Page 39: 29585169 Projects Cost Management

39

o The idea of the Cost Baseline allows the Project Manager and Management to predict when the Project will be spending money and over what time period. The purpose of the Cost Baseline is to measure and predict Project Performance.

o The figure above “Cost Baselines” shows predicted Project Cost and Phase Cost Performance.

o Large Projects that have multiple Deliverables may have multiple Cost Baselines to illustrate the Costs within each Phase. Additionally, larger Projects may have Cost Baselines to predict Spending Plans, Cash Flows of the Project, and overall Project Performance.

o The purpose of a Cost Baseline is to measure Performance, and a Baseline will predict the expenses over the life of the Project.

o Any inconsistency early in the predicted Baseline and the Actual Costs serve as a signal that the Project is slipping.

4. Implementing Project’s Cost Control

Cost Control focuses on the Ability of Costs to Change and on the ways of allowing or preventing Cost Change from happening.

39

Page 40: 29585169 Projects Cost Management

40

When a Cost Change does occur, the Project Manager must document the change and the reason why the change has occurred and, if necessary, create a Cost Variance Report.

Cost Control is concerned with understanding why the Cost Variances (both good and bad) have occurred. The “why” behind the variances allows the Project Manager to make appropriate decisions on future Project Actions. Ignoring the Project Cost Variances may cause the Project to suffer from Budget Shortages, Additional Risks, or Scheduling Problems.

Cost Control allows the Project Manager to deal with the problem, find a solution, and then act accordingly.

Specifically, Cost Control includes:

o Controlling Causes of Cost Change to ensure the changes are actually needed

o Controlling and Documenting Cost Changes to the Cost Baseline as they happen

o Controlling Cost Changes in the Project and their influence on Cost

o Recording Appropriate Cost Changes in the Cost Baseline

o Preventing Unauthorized Changes to the Cost Baseline

o Communicating the Cost Changes to the Proper Stakeholders

o Working to Bring and Maintain Costs within an Acceptable Range

4.1 Inputs to Project’s Cost Control

4.1.1 Cost Baseline:

40

Page 41: 29585169 Projects Cost Management

41

The Cost Baseline is the Expected Cost the Project will incur (deserve). The Cost Baseline is a tool used to measure Project Performance.

4.1.2 Performance Reports:

These Reports focus on Project Cost Performance, Project Scope, and Planned Performance versus Actual Performance. The Reports may vary according to Stakeholder Needs.

4.1.3 Change Requests:

When Changes to the Project Scope are requested, an analysis of the Associated Costs to complete the Proposed Change is required. In some instances, such as removing a portion of the Project Deliverable, a Change Request may reduce the Project Cost.

4.1.4 Cost Management Plan:

The Cost Management Plan dictates how Cost Variances will be managed.

4.2 Tools & Techniques of Project’s Cost Control

4.2.1 Creating a Cost Change Control System:

41

Page 42: 29585169 Projects Cost Management

42

Sometimes a Project Manager must add (or remove) Costs from a Project.

The Cost Change Control System is a part of the Integrated Cost Change Control System which documents the procedures to Request, Approve, and incorporate Changes to Project Costs.

When a Cost Change enters the System, there is appropriate Paperwork, a Tracking System, and Procedures the Project Manager must follow to obtain Approval on the Proposed Change.

The following figure demonstrates a Typical Workflow for Cost Change Approval. If a Change gets Approved, the Cost Baseline is updated to reflect the Approved Changes. If a Request gets denied, the denial must be documented for future Potential Reference.

Three Phases of Change Management(from Primavera Expedition)

Phase 1.InvestigationIdentify Change Tools to

InitiateChange

2.Change Impact($ & Time)

ToolsCollect

3.Resolve Change

DOCType

CICRFI/AnswerSketchBulletinMeeting MinutesPhone Record

ESTRFPPCOCOR

COPRO

DONE BY

ProjectEngineer

ProjectManager

Approving Authority

A “Cost Change Control System” tracks and documents Cost Change Issues. The following represents some of Cost Change Documents:

CIC = Change in ConditionRFI = Request for InformationEST = ESTimateRFP = Request For ProposalPCO = Proposed Change OrderCOR = Change Order RequestCO = Change OrderPRO = Proceed Order

4.2.2 Measuring Project Performance:

42

Page 43: 29585169 Projects Cost Management

43

Earned Value Management (EVM) is the process of measuring performance of Project Work against Plan to identify Variances. It can also be useful in predicting future variances and the final Costs At Completion. It is a System of Mathematical Formulas that compares Work Performed against Work Planned and measures the Actual Cost of the Work Performed.

EVM is an important part of Cost Control as it allows a Project Manager to predict future variances from the expenses to date within the Project.

EVM, in regard to Cost Management, is concerned with the relationships between three formulas that reflect Project Performance.

The following figure demonstrates the relation between these EVM Values:

Earned Value Management measures Project Performance.

4.2.3 Planned Value (PV):

43

Page 44: 29585169 Projects Cost Management

44

Planned Value is the Work scheduled and the Budget authorized to accomplish that Work.

Example:

If a Project has a Budget of $100,000 and month 6 represents 50% of the Project Work, the PV for month 6 is $50,000. Planned Value used to be known as the Budget Cost of Work Scheduled ( BCWS ) .

4.2.4 Earned Value (EV):

Earned Value is the Physical Work Completed to Date and the authorized Budget for that Work.

Example:

If a Project has a Budget of $100,000 and the Work Completed to Date represents 25% of the Entire Project Work, its EV is $25,000. Earned Value used to be known as the Budgeted Cost of Work Performed ( BCWP ) .

4.2.5 Actual Cost (AC):

Actual Cost is the actual amount of money the Project has required to date.

Example:

If a Project has a Budget of $100,000 and $35,000 has been spent on the Project to Date, the AC of the Project would be $35,000. Actual Cost used to be known as Actual Cost of Work Performed ( ACWP ) .

These three values are key information about the Worth of the Project to Date:

These values will be revisited later. 4.2.6 Additional Planning:

44

Page 45: 29585169 Projects Cost Management

45

Planning is an Iterative Process. Throughout the Project, there will be demands for Additional Planning and an output of Cost Control is one of those demands.

Consider a Project that must complete by a given date and that also has a Budget. The balance between the Schedule and the Cost must be kept.

The Project Manager can not assign a large crew to complete the Project Work if the Budget would not allow it.

The Project Manager must (through planning) get as creative as possible to figure out an Approach to accomplish the Project without exceeding the Budget.

The Balance between Cost and Schedule is an ongoing battle (fight). While it is usually easier to get more time than money, this is not always the case. Consider deadlines that can not move, or the Company may face penalties, or a deadline that centers on a tradeshow, or the start of the school year.

4.2.7 Using Computers:

Project Managers can rely on Project Management Software (Primavera, MS Project, etc…) and Spreadsheet Programs to assist them in calculating Actual Costs, Earned Value, and Planned Value.

45

Page 46: 29585169 Projects Cost Management

46

4.3 Outputs of Project’s Cost Control --- Cost Control Results

The Project Manager always does the following:

o Monitor Cost Variances and then understand why Variances have occurred.

o Update the Cost Baseline as needed based on Approved Changes.

o Work with the conditions and Stakeholders to prevent unnecessary Changes to the Cost Baseline.

o Communicate to the Appropriate Stakeholders to discuss Cost Changes as they occur.

o Maintain Costs within an Acceptable and Agreed Range.

4.3.1 Revising Cost Estimates:

As the Project progresses and more detail come available, there may be a need to update the Cost Estimates.

A revision to the Cost Estimates requires communication with the key Stakeholders to share why the Costs were revised.

46

Page 47: 29585169 Projects Cost Management

47

4.3.2 Updating the Cost Budget:

Updating the Cost Budget is slightly different than revising a Cost Estimate.

Cost Budget Updates allow the Cost Baseline to be changed.

The Cost Baseline is the “before Project Snapshot” of what the Total Project Scope and the Individual WBS Components should cost.

Should the Project Scope grow, as shown here, the Cost will also likely change to be able to fulfill the new Scope.

If a Project has a drastic (radical) changes due to large changes to the Project Scope (false assumptions, or new demands from the Customer), it may be necessary to re-baseline the Project Cost.

Re-baselining is done only in drastic changes. All Historical Information up to the re-baseline is cleared, and the Project starts fresh.

47

Page 48: 29585169 Projects Cost Management

48

4.3.3 Applying Corrective Actions:

Throughout a Project, the Project Manager will apply Corrective Actions.

Corrective Actions are any actions applied to Project Performance to bring the Project back into position with the Project Plan.

Corrective A ctions can be Scheduling Changes, a Shift in Resources, a Different Approach to completing the Project Work, Any Action to bring the Project back to its expected level of Performance.

4.3.4 Preparing for the Estimate at Completion:

The Estimate at Completion (EAC) is a hypothesis of What the Total Cost of the Project will be. Before the Project begins, the Project Manager completes an Estimate for the Project Deliverables based on the WBS.

As the Project progresses, there will be in most Projects some variances between what the Cost Estimate was and what the Actual Cost is. The difference between these Estimates is the Variance for the Deliverable.

EAC is part of the Earned Value Management Approach (EVM). We have talked about Earned Value, Planned Value, and Actual Costs earlier.

To complete this discussion on EAC, we well need another formula from the EVM family. It is the CPI (Cost Performance Index) as follows.

48

Page 49: 29585169 Projects Cost Management

49

4.3.5 Calculating the Cost Performance Index (CPI):

CPI is a value that demonstrates how the Project Costs are performing.

CPI is a value that reveals How Much Money the Project is Losing. Or, if you are an optimist, How Much Money the Project is Making.

Example:

A Project with a CPI of .93 is losing seven cents on the Dollar (assuming US dollars). Or, for the Optimist, it is making .93 cents on the Dollar.

The fact of the matter is, a Project with this CPI Value is likely to be Over Budget because for every Dollar spent, 7 cents evaporates (vanishes). The following shows the CPI in action:

CPI relates the Work you have accomplished to the amount you have spent to accomplish it.

A Project with a CPI of .93 means you are spending 1.00 for every .93 Worth of Work Accomplished.

Therefore, a CPI under 1.00 means the Project is Performing Poorly against the Plan.

49

Page 50: 29585169 Projects Cost Management

50

However, a CPI over 1.00 does not necessarily mean that the Project is Performing Well. It could mean that Estimates were inflated or that expenditure for equipment is late or sitting in accounts payable and has not yet been entered into the Project Accounting Cycle.

In summary,

If you do not want to think of the CPI Value as making or losing money, that is fine too. Just know the CPI Value should be as close to 1.00 as possible and do not celebrate too loudly if the CPI is greater than 1.00. A CPI greater than 1.00 may just reflect Poor Estimates rather than an Over-Performing Project.

50

Page 51: 29585169 Projects Cost Management

51

4.3.6 Calculating Estimate at Completion (EAC):

There are many approaches to calculating the EAC:

4.3.7 Experiencing Expected Conditions:

Estimate At Completion = Budget at Completion /Cost Performance Index

EAC=BAC/CPI

Example:

If the Project’s BAC is $575,000 and the CPI is .91, the EAC for this Project is $631,868. Those 9 cents on every dollar sure do add up!

4.3.8 Accounting for Flawed (faulty) Estimates:

51

Page 52: 29585169 Projects Cost Management

52

Imagine a Project to Install a New Operating System on 1,000 Workstations.

One of the assumptions the Project Team made was that each Workstation had the correct hardware to install the Operating System automatically.

As it turns out, this assumption was wrong, and now the Project Team must change their approach to installing the Operating System.

Exam WatchBecause the assumption to install the Operating System was flawed (defective), a new Estimate To Complete the Project is needed.

This new Estimate to Complete the Work is known as the “Estimate to Complete (ETC)”.

The ETC represents how much more money is needed to complete the Project Work, and its formula is:

ETC=EAC-AC.

In this scenario of a flawed (imperfect) assumption, the Project Manager will use a slightly different formula to predict the EAC:

EAC = AC +ETC

Example:

If the Project’s Original BAC was $100,000 and the Project Team had spent $20,000 before realizing the Project Assumption was flawed (faulty), they have to create a new ETC the remaining work.

Let’s pretend (imagine) the ETC the Project Team arrived at was $175,000.

The formula EAC = AC+ETC EAC = $20,000+$175,000

= $195,000.

This is because the Project had spent $20,000, and $175,000 more is needed to complete the Work.

52

Page 53: 29585169 Projects Cost Management

53

4.3.9 Accounting for Anomalies:

Sometimes a Project suffers from Anomalies.

Example:

o Consider a Project to construct a “Wooden Fence Around a Large Building”.

o One of the Project Team Members made a mistake while installing the Wooden Fence and reverses the face of the Fencing Material. In other words, the Material for the outside of the Fence faces the wrong direction.

o The Project Manager now has to consume Additional Time to remove the Fence Material, correct the problem, and replace any Wood that may have been damaged in the incorrect Installation.

o This anomaly likely would not happen again, but it will add Costs to the Project.

o For these instances, when events happen but the Project Manager doesn’t expect similar events to happen again, the EAC Formula should be used:

EAC=AC+BAC-EV. See page 48

o Let’s try this out with our “Fencing Project”:

The Project’s AC so far was $7,000

The BAC was $24,500

The EV is only $2,450, as the Project has barely (just) started. (EV = %Comp * BAC)

Therefore, EAC=$7,000+$24,500-$2,450 = $29,050 ---- a costly mistake.

53

Page 54: 29585169 Projects Cost Management

54

4.3.10 Closing Out the Project:

As part of Project Closeout, Phase Closeout, or even Project Cancellation, there must be Identified Processes and Procedures on how to shut down the Project.

A formal Auditor may be called for to review the Time, Costs, Materials, and Budget of the Project.

In some instances, a review may happen with Management or the Project Sponsor to account for the Project Budget and how well Cost Control was managed within the Project.

54

Page 55: 29585169 Projects Cost Management

55

4.3.11 Updating Lessons Learned:

As part of Cost Control, the Project Manager should update the Lessons Learned document to reflect the decisions behind the actions taken.

For example, the Project Manager should identify:

o Changes to Cost Baseline and why they were Approved

o Corrective Actions and why they were Implemented

o Cost Control Challenges and Issues and how they were Resolved

o Other Cost Control Information that may be beneficial for other Projects

Summary

55

Page 56: 29585169 Projects Cost Management

56

• There are several factors that affect the Project’s Cost:

o The Expense of Labor to complete the Project,

o The Expense of Materials needed to complete the Project, and

o The Expense of the Equipments needed to complete a Project.

• These expenses must be estimated, planned for, and monitored for a Project to finish on Budget.

• Management and Customers want to know how much a Project is going to cost so they can determine if the Project is worth doing, if the Project Deliverable (outputs) will be worth the Cost, and if the Project will be Profitable.

• The Estimates for Project Costs can come in several forms:

o Similar Estimating : Uses similar historical information to predict the cost of the current project.

o Parametric Modeling : Uses a parameter, such as cost per metric ton, to predict project costs.

o Bottom-Up Estimating : Starts from zero and adds the expenses from bottom-up.

o Top-Down Estimating : Uses a similar Project as a Cost Baseline and factors in current project conditions to predict costs.

o The Resources needed to complete a Project may be one of the biggest expenses in the Project’s Budget. The Activities the Resources complete must be worthy of the Resource’s Time. In other words, the Project Manager does not want to assign a $125/hr Engineer to filing Activity that a $15/hr Administrative Assistant is qualified to do.

o Accurate Assignment of Project Resources to Project Activities helps prevent waste.

o Projects also have four different kinds of Cost:

56

Page 57: 29585169 Projects Cost Management

57

Direct Costs: These are costs that consumed directly in the project and cannot be shared with operations or other Projects.

Variable Costs: Costs that vary depending on the conditions within the Project.

Fixed Costs: Costs that remain the same throughout the Project.

Indirect Costs These costs can be shared across multiple projects that use the same Resources ---such as Training Room or Equipments.

Key Terms

57

Page 58: 29585169 Projects Cost Management

58

Earned Value (EV): A method of measuring project performance by comparing the amount of work planned with that actually accomplished, in order to determine if cost and schedule performance are as planned.

Planned Value (PV)

Actual Cost (AC)

Budget At Completion (BAC)

Estimate At Completion (EAC)

Schedule Variance (SV)

Cost Variance (CV)

Variance At Completion (VAC)

Responsibility Assignment Matrix (RAM)

o RAM --- The integration of the WBS and the OBS (Organizational Breakdown Structure).

o Proper creation of the RAM results from locating the intersection of the OBS unit that is assigned responsibility for the work and the specific WBS element that defines the work to be performed.

o Example :

WBS Element : 1.1 Frame OBS Element:Frame Shop RAM: Mr. I. M. Smart Budget: $125,000 Schedule: Jan – Jun 08

58

Page 59: 29585169 Projects Cost Management

59

Performance Measurement Baseline (PMB)

Schedule Variance (SV)

o Comparing the EV (the amount originally budgeted for the work that has been completed or in-progress) to the PV (the amount budgeted for the work that was planned to have been accomplished)

o SV = EV – PV

o A –ve result means less work has been performed than was planned.

o SV Example :

PV = $42,000

EV = $38,000

AC = $48,000

SV = EV – PV = $38,000 - $42,000 = - $4,000

SV% = SV / PV = -$4,000 / $42,000 = -0.095 = - 9.5%

59

Page 60: 29585169 Projects Cost Management

60

Cost Variance (CV) :

o Comparing the amount originally budgeted for the work completed or in progress (EV) to the actual costs of that work (AV). That is:

CV = EV – AC

o A –ve CV means more dollars were spent to accomplish the work than was planned.

o Cost Variance Example :

PV = $42,000

EV = $38,000

AC = $48,000

CV = EV – AC = $38.000 - $48,000 = -$10,000

CV% = CV / EV = -$10,000 / $38,000 = -26%

60

Page 61: 29585169 Projects Cost Management

61

Cost Performance Indices :

o Cost Performance Index (CPI) = EV / AC

o CPI Example :

PV = $42,000 EV = $38,000 AC = $48,000 CPI = EV / AC = $38,000 / $48,000 = 0.79

That is $0.79 worth of work was actually done for each

$1.00 spent.

o Schedule Performance Index (SPI) = EV / PV

o SPI Example :

PV = $42,000 EV = $38,000 AC = $48,000 SPI = EV / PV = $38,000 / $42,000 = 0.90

That is $0.90 worth of work has been done for each $1.00 worth of work that was planned to be done.

Estimate At Completion (EAC) :

o After Variance Analysis, the estimated cost at completion is determined

o EAC Example :

61

Page 62: 29585169 Projects Cost Management

62

BAC = $80,000 CPI = 0.79 EAC = BAC / CPI = $80,000 / 0.79 =

$201,265

Variance At Completion (VAC) :

o VAC Example :

BAC = $80,000

EAC = $201,265

VAC = BAC – EAC = $80,000 - $101,265 = $21,265

Based on past performance, project planned budget will exceed by $21,265.

To Complete Performance Index (TCPI) :

o Work Remaining / Cost Remaining

o TCPI = (BAC – EV) / (EAC – AC)

= ($80,000 - $38,000) / ($101,000 - $48,000)= $42,000 / $53,000= 1.4

Example :

PV EV AC EAC BAC100 125 75 600 560125 100 100 850 800

62

Page 63: 29585169 Projects Cost Management

63

75 75 75 700 560100 75 100 570 600

Problem :

o Given: BAC = $40K EV = $20K PV = $28K AC = $26K

o Calculate: % of Work Scheduled % of Budget Spent % of Work Accomplished Cost Variance Schedule Variance

Solution :

% of Work Scheduled = PV / BAC = $28K / $40K

= 70%

% of Budget Spent = AC / BAC = $26K / $40K

= 65

% of Work Accomplished = EV / BAC = $20K / $40K

63

Page 64: 29585169 Projects Cost Management

64

= 0.50

Cost Variance = EV – AC = $20K - $26K

= -$6K

Schedule Variance = EV – PV = $20K - $28K

= - $8K

Self Test (Reference 2)

1. Which one of the following best describes analogous estimating?

A. Regression analysisB. Bottom-up estimatingC. Less accurateD. More accurate

2. You are the project manager for GHG Project. You are about to create the cost estimates for the project. Which input to this process will help you the most?

A. Parametric modelingB. WBSC. Project scopeD. Requirements document

3. You are the project manager for the JKH Project. You have elected to use parametric modeling in your cost estimating for the project. Which one of the following is an example of parametric modeling?

64

Page 65: 29585169 Projects Cost Management

65

A. $750 per tonB. Historical information from a similar projectC. Estimates built bottom-up based on the WBSD. Estimates based on top-down budgeting

4. You are the project manager for a new technology implementation project. Management has requested that your estimates be as exact as possible. Which one of the following methods of estimating will provide the most accurate estimate?

A. Top-down estimatingB. Top-down budgetingC. Bottom-up estimatingD. Parametric modeling

5. Your company has been hired to install the tile in 1,000 hotel rooms. All rooms will be identical in nature and will require the same amount of materials. You calculate the time to install the tile in each hotel room as six hours. The cost for labor for each room is calculated at $700. Your Project Sponsor disagrees with your labor estimate. Why?

A. You haven’t completed one hotel room yet so you don’t know how long the work will actually take.

B. You have not factored in all of the effort applied to the work.C. You have not considered the law of diminishing returns.D. You have not considered the learning curve.

6. You are the project manager for a construction project to build 17 cabins. All of the cabins will be identical in nature. The contract for the project is set at a fixed cost, the incentive being the faster the project work is completed, the more the profitable the job. Management has requested that you study the work method to determine a faster, less costly, and better method to complete the project. This is an example of which one of the following?

A. Time constraintB. Schedule constraintC. Value analysisD. Learning curve

65

Page 66: 29585169 Projects Cost Management

66

7. You are the project manager for a technical implementation project. The customer has requested that you factor in the after-the-project costs, such as maintenance and service. This is an example of which one of the following?

A. Life cycle costsB. Scope creepC. Project spin offD. Operations

(The after-the-project costs are known as the life cycle cost)

8. Which one of the following provides the least accurate in estimating?

A. Rough order of magnitudeB. Budget estimateC. Definitive estimateD. WBS estimate

(The rough order of magnitude is the least accurate approach, as it may vary from -25% to +75%.)9. Which one of the following is true?

A. The cost management plan controls how change management affects the BAC.

B. The cost management plan controls how cost variances will be managed.

C. The cost management plan controls how the project manager may update the cost estimates.

D. The cost management plan controls how the BAC may be adjusted

10.You have just started a project for a manufacturer. Project team members report they are 30 percent done with the project. You agree with their completion status but do not change any of the progress in your report to the customer. This is an example of which one of the following?

A. 50/50 ruleB. 0/100 ruleC. Percent Complete RuleD. Poor project management

(This completion method allows for 0%credit on an activity until it is 100% complete)

11.You and your project team are about to enter a meeting to determine project costs. You have elected to use bottom-up estimating and will base

66

Page 67: 29585169 Projects Cost Management

67

your estimates on the WBS. Which one of the following is not an attribute of bottom-up estimating?

A. People doing the work create the estimates.B. Creates a more accurate estimate.C. More expensive to do than other methods.D. Less expensive to do than other methods.

12.What is the present value if the organization expects to make $100,000 four years from now and the annual interest rate is 6%?

A. $100,000B. $58,000C. $25,000D. Zero

{PV = FV/(1+R)n [FV=future value; R=interest rate; n=number of time periods]}

13.You are the project manager for the construction of a new hotel. Before you begin the cost budgeting process, what is needed?

A. Costs estimates and project scheduleB. Cost estimates and supporting detailC. EAC and BACD. Parametric model used to arrive at the costs submitted

(B, C, & D are all not inputs to cost budgeting)

14.You are the project manager of the MNJ Project. Your project is falling behind schedule and you have already spent $130,000 of your $150,000 budget. What do you call the $130,000?

A. Planned valueB. Present valueC. Sunk costsD. Capital expenditure

(Sunk Costs are monies that have been spent)

15.You are the project manager of the JHD Project. Your project will cost your organization $250,000 to complete over the next eight months. Once the project is completed, the deliverables will begin earning the company $3,500 per month. The time to recover the costs of the project is which one of the following?

67

Page 68: 29585169 Projects Cost Management

68

A. Not enough information to knowB. Eight monthsC. 72 monthsD. 5 years

(This is calculated by dividing the ROI of $3,500 per month into the project cost)

16.You are the project manager for the consulting company. Your company has two possible projects to manage, but they can only choose one. Project KJH is worth $17,000, while Project ADS is worth $22,000. Management elects to choose Project ADS. The opportunity cost of this choice is which one of the following?

A. $5,000B. $17,000C. $22,000D. Zero, as project ADS is worth more than Project KJH

(The opportunity cost is the amount of the project that was not chosen)

17.You are the project manager for the CSR Training Project, and 21,000 customer service reps (sales representatives) are invited to attend the training session. Attendance is optional. You have calculated the costs of the training facility, but the workbook expense depends on how many students register to the class. For every 5,000 workbooks created the cost is reduced a percentage of the original printing cost. The workbook expense is an example of which one of the following?

A. Fixed costsB. Parametric costsC. Variable costsD. Indirect costs

(The more students that register to take the class the more the cost of the books will be)

18.You are the project manager of a construction project scheduled to last 24 months. You have elected to rent a piece of equipment for the duration of a project, even though you will need the equipment only periodically throughout the project. The costs of the equipment rental per month are $890. This is an example of ________________.

A. Fixed costsB. Parametric costsC. Variable costsD. Indirect costs

68

Page 69: 29585169 Projects Cost Management

69

19.You are the project manager for the Hardware Inventory Project. You have a piece of equipment that was purchased recently for $10,000 and is expected to last five years in production. At the end of the five years the expected worth of the equipment is $1,000. Using straight-line deprecation, what is the amount that can be written off each year?

A. ZeroB. $1,000C. $1,800D. $2,000

[The straight-line depreciation takes the purchase value of the item, minus the salvage price of the item, divided by the number of time periods. That is ($10,000 - $1,000)/5 = $1,800 per year.]

20.You are the project manager of the LKG Project. The project has a budget of $290,000 and is expected to last 3 years. The project is now 10% complete and is on schedule. What is the BAC?

A. $29,000B. $290,000C. $96,666D. $9,666

(The BAC is the budget at completion, which is $290,000)

21.Your project has a budget of $130,000 and is expected to last 10 months, with the work and budget spread evenly across all months. The project is now in month 3, the work is on schedule, but you have spent $65,000 of the project budget. What is your variance?

A. $65,000B. $39,000C. $26,000D. $64,999

(This is calculated by subtracting the actual costs of $65,000 from the earned value of $39,000. EV is calculated by taking the 30% completion of the project against the BAC. The project is considered to be 30% complete because it is slated (scheduled) for 10 months, is currently in month 3, and is on schedule.)

22.You are the project manager of the Carpet Installation Project for new building. Your BAC is $600,000. You are now 40% done with the

69

Page 70: 29585169 Projects Cost Management

70

project, though your plan called for you to be 45% done with the work at this time. What is your earned value?

A. $240,000B. $270,000C. $30,000D. ?$30,000

(The earned value is calculated by multiplying the % of completion, 40%, by the BAC, which is %600,000, for a value of $240,000.)

23.You are the project manager of the Carpet Installation Project for new building. Your BAC is $600,000. You have spent $270,000 of your budget. You are now 40% done with the project, though your plan called for you to be 45% done with the work at this time. What is your CPI?

A. 100B. 89C. .89D. .79

(The EV of $240,000 is divided by the AC of $270,000 for a value of .89.)

24.You are the project manager for the Facility Installation Project. The project calls for 1500 units to be installed into a new baseball stadium. Your team wants to know why you have not assigned the same amount of time for the last 800 units as you had for the first 500 units. You tell them it is because of the learning curve. Which one of the following best describes this theory?

A. Production increases as workers become more efficient with the installation procedure.

B. Efficiency increases as workers become more familiar with the installation procedure.

C. Costs decrease as workers complete more of the installation procedure.

70

Page 71: 29585169 Projects Cost Management

71

D. Time decreases as workers complete more of the installation procedure in the final phases of a project.

25. Of the following, which one is the most reliable source of information for estimating project costs?

A. Historical information from a recently completed projectB. An SME’s opinionC. Recollections of team members that have worked on similar

projectsD. Vendor’s white papers

Practical Part

71

Page 72: 29585169 Projects Cost Management

72

Scenario 1:

The Project Team has determined the Types of Skills (Roles) required for completing the Project Activities. The Project Team has also estimated the effort needed to accomplish the work.

Specific Resources have not yet been assigned to the Project. Roles can be used as temporary placeholders for future Resource Assignments. A Role represents a Skill or Job defined in the Application. View the Roles Dictionary to become familiar with the Skill Sets that have been defined.

Resource Management is divided into 3 distinctive parts:

1. Defining Resources in the Resource Pool :Defining Resources has already been completed by the Project Office. Only specific information about specific Resources that have been defined has to review at the Corporation.

2. Assigning Resources to Activities :

72

Page 73: 29585169 Projects Cost Management

73

Before Assigning Resources, the Project Manager must negotiate with the Resource Manager about the Resources Availability. Once the negotiation has occurred, it is the time to assign the Resources to the appropriate Activities.

3. Analyzing Resource Allocation :

After Resource Assignment, we can start analyzing Resource Allocation. In this case, the Resources Over-Allocation (Resources that are assigned to more work than they can perform) must be resolved. During Resource Allocation Analysis, a review of the Projects’ Cost has to make to ensure that the Project is within Budgetary Constraints.

Defining Roles & Resources:

Lesson 13, Training Material, Course 102PRIMAVERA

73

Page 74: 29585169 Projects Cost Management

74

Assigning Roles:

Lesson 14, Training Material, Course 102PRIMAVERA

74

Page 75: 29585169 Projects Cost Management

75

Assigning Resources & Costs:

Lesson 15, Training Material, Course 102PRIMAVERA

75

Page 76: 29585169 Projects Cost Management

76

Analyzing Resources:

Lesson 16, Training Material, Course 102PRIMAVERA

76

Page 77: 29585169 Projects Cost Management

77

Scenario 2:

Project Manager is responsible for evaluating the Project against the triple constraints:

1. Schedule, 2. Resources, and 3. Cost.

He is also responsible to ensure that the Project Requirements as outlined in the Scope Document are being met.

Initially, the Project Manager should verify that the Project is scheduled to finish on time. If the Project delays, he has to make adjustments to the Project Plan by analyzing the Resources and resolve the over-allocation.

Once the Schedule & Resources Adjustments have been made, validate the Project’s Cost. The Project’s Cost may have changes due to the Adjustments of Resources.

Once the Project is optimized, baseline the Project. Baseline is a copy of a Project that can be used to compare against the Current Project to evaluate progress.

77

Page 78: 29585169 Projects Cost Management

78

Once the Baseline has been created, move to the Execution & Control Process.

Information must be distributed to the Teem Members performing the work on the Project. Then the Work Accomplished must be reported back to the Project Manager. The Project Manager gathers information from the Teem Members and enters the data directly into Primavera to reflect the progress in the Project up to the Data Date.

Optimizing the Project Plan:

Lesson 17, Training Material, Course 102PRIMAVERA

78

Page 79: 29585169 Projects Cost Management

79

Baselining the Project Plan:

Lesson 18, Training Material, Course 102PRIMAVERA

79

Page 80: 29585169 Projects Cost Management

80

Project Execution & Control:

Lesson 19, Training Material, Course 102PRIMAVERA

80

Page 81: 29585169 Projects Cost Management

81

Scenario 3:

As a Project Manager, you must prepare for a monthly Project Status Meeting, where Project Engineers report out on the progress of their works.

The Project Manager needs to create a number of reports to distribute at the meeting to the Project Executive Committee.

81

Page 82: 29585169 Projects Cost Management

82

Reporting Performance:

Lesson 20, Training Material, Course 102PRIMAVERA

82

Page 83: 29585169 Projects Cost Management

83

CASE STUDY

Building A 2nd Floor Of A Villa

Background:

1. You have been assigned the responsibility for scheduling and monitoring the progress of building the 2nd floor of a villa.

2. Major Engineering Design tasks have been completed.

3. The project consists of 29 major activities. The following list of project activities includes the basic information which you need to schedule and track the principle activities in the project.

4. While you are in charge of the scheduling and implementing of the overall project, you will receive monthly reports of project implementation progress from the construction site supervisors.

5. On the basis of monthly reports from the project site, you will monitor the progress of project execution.

83

Page 84: 29585169 Projects Cost Management

84

6. In carrying out your assignment, you are aware that the OWNER is anxious to open the project as early as possible.

This Case Study will cover the following points:

1. Creating Project Calendar(s),

2. Creating Work Breakdown Structure (WBS) with Responsible Managers Assignment.

3. Entering project Activities with their Duration and Relationships.

4. Scheduling & Assigning Constraints.

5. Establishing Project & Activity Codes which may determineProject #, Project Manager, Responsibilities, Locations, Area, Phases, Milestones, etc….

6. Establishing Roles & Resources Dictionaries and Assign them to Activities as needed to execute the Project which may be Labor, Material, Nonlabor (Equipments), and Money (Expenses).

7. Use the Cost Accounts feature to determine every item cost in the Project.

8. Analyze Project Resources , Optimize the Project Plan, Baselining the Project Plan, Execute, and Control (Update).

9. Producing different set of Reports, for example:

84

Page 85: 29585169 Projects Cost Management

85

. Tabular Schedules,

. Bar Charts,

. Time-Scaled Logic Diagrams,

. Project Network Diagrams,

. Resource and Cost Reports:

.. Project Labor, Nonlabor(Equipments), Material, and Expenses Costs,

.. Project Cash-Flow, etc….

1. Project’s Calendar(s) :

Create a Project called Case_01 --- Creating Calendar called “Case Cal”

Planning Unit: Day

Workdays/week: 5

Week Start on: Sunday

Project Start: 01-JAN-11

Holidays:

o 07-JAN-11o 25-JAN-11, (28-JAN..31-JAN & Exception 30-JAN..31-JAN-11) o 04-APR .. 09-APR & Exception 07-APR..09-APR-11)o 01-MAY-11o 18-JUN-11o 23-JUL-11o 06-OCT-11

Hint:

Calendar is a Global or Project Data.

Create a New Global Calendar named for example, Case Cal ------ 5 D/W [SUN] with Holidays.

85

Page 86: 29585169 Projects Cost Management

86

There are no Repeated Holidays.

Exception affects only on the Weekends days or the holidays from an “Inherited Holidays & Exceptions from Global Calendar”.

To assign the created calendar to the project:

o Highlight the Project in the “Projects” window.

o In the Project Details, click “Default” tab.

o Assign the created Calendar from the “Calendar” field.

2. Creating WBS of the Project :

Background:

The Project Structure has been defined for this Project. We now need to add the WBS elements and assign Responsible Managers.

The Project will be named Case_02 – Creating WBS.From “Projects” window, use “Edit -- Copy/Paste” & change the name of the new Project….

WBS Code WBS Name Responsible Manager (OBS)

Case_02.Admin Project Administrator

INP_OBS

Case _02.Prep Preparation for the Project & Analysis

Case _02.Concrete Concrete WorksCase _02.Concrete.Columns ColumnsCase _02.Concrete.SlabStairs Slab and StairsCase _02.BlockWorking Block WorkingCase _02.WoodenWorks Wooden WorksCase _02.Electrical Electrical WorksCase _02.Sanitary Sanitary WorksCase _02.Isolation Isolation WorksCase _02.IntPlastering Interior Plastering

86

Page 87: 29585169 Projects Cost Management

87

Case _02.Painting Painting WorksCase _02.FrontPlastering Frontal Plastering

(Facades)Case _02.Flooring Flooring WorksCase _02.Ceramic Ceramic WorksCase _02.HO Hand Over

Hint:

To make “Indent/Outdent” Active:o Click “Layout Option Bar/Group and Sort By/WBS”o Check the “ID/Code” box.

87

Page 88: 29585169 Projects Cost Management

88

88

Page 89: 29585169 Projects Cost Management

89

3. Creating Project’s Codes : (Enterprise / Project Codes…)

The Project will be named Case_03 – Creating Project Codes.Use “Edit--Copy/Paste” & change the name of the new Project….

Project Code Code Value Code Description

Project # Case Building 2nd Floor of a House

Project Location AR Air Port Road

Project Manager Hesham Hesham Mostafa

Project Region Heliopolis Heliopolis, Cairo

A Project Code Value can be associated with one User.

To Create Project Codes :

Project Codes is a Global Data.

Create New Project Codes Hierarchy & Globally from “Enterprise/Project Codes”, or

Assign Project Code Values to the existing Project Codes (our case).

o So, Assign Project Codes to the Project (Click “Projects” & use “Codes” tab from “Project Details”).

89

Page 90: 29585169 Projects Cost Management

90

90

Page 91: 29585169 Projects Cost Management

91

4. Adding Activities

The WBS and Project’s Calendar have been defined and approved for the Building of 2nd Floor in a Villa.

The next step is to finish adding Activities to the Project. You will also add a Notebook topic and Steps to perform System Requirements Analysis.

Project will be named Case_04 – Adding Activities.Use “Copy/Paste” & change the name of the new Project….

Hint: All of the following Activities are of Duration Type “Fixed Duration

& Units” and “Activity Type: Task Dependent” except for the 1st

Activity (ADM2) which is of Activity Type “Level of Effort”

PD = Planned Duration ** = Level of Effort Type

WBSCode

ActivityID

Activity Name PD S.No.

Case_04.Admn ADM2 Project Administration ** 1

Case_04.Prep PRP2 Preparing Project Requirements & Analysis التجهيز لبدء العمل

10d 2

Case_04.Concrete.Columns

CO22C100 FormWork (Columns) .اعمال شد النجارة للعمدة

7d 3

CO22C200 R.F.T (Columns) رص الحديد للعمده

4d 4

CO22C300 Cast-in-place Concrete (Columns) صب الخرسانة المسلحة للعمدة

3d 5

CO22C400 Curing Time for Columns اعمال المعالجة للعمدة

5d 6

Case_04.Concrete.SlabStairs

CO22S100 FormWork (Slab/ٍStairs) لسقفل شد النجارة المسلحة

والسللم

10d 7

CO22S200 R.F.T (Slab/Stairs) رص الحديد للسقف والسللم

7d 8

CO22S300 Cast-in-Place (Slab/Stairs) صب الخرسانة المسلحة للسقف والسللم

3d 9

91

Page 92: 29585169 Projects Cost Management

92

CO22S400 Curing Time & Removal of FormWork for Slab/Stairs اعمال المعالجة + فك الشدة الخشبية

10d 10

Case_04.BlockWorking

BLO2 100 Block Working thick 25 cm سم25أعمال مباني سمك

12d 11

BLO2 200 Block Working thick 12 cm سم12أعمال مباني سمك

4d 12

Case_-04.WoodenWorks

WOD2 100 Windows & Doors Sub-Frames Installation

تركيب حلوق البواب والشبابيك

7d 13

WOD2 200 Windows & Doors Installation تركيب البواب والشبابيك

10d 14

Case_04. Electrical

ELE2 100 Electrical Conduits تركيب مواسير الكهرباء في

الحوائط

7d 15

ELE2 200 Electrical Wires ادخال السلك في المواسير الكهربية

14d 16

ELE2 300 Electrical Switches Lighting Fix. تركيبات كهربية نهائية

14d 17

Case_04.Sanitary

SAN2 100 Sanitary Pipes تركيب مواسير الزهر

20d 18

SAN2 200 Potable Water Piping Circuits تركيب مواسير الشرب .. .. سباكة

9d 19

SAN2 300 Install of Sanitary Fixtures تركيب الحواض والحنفيات .. .. سباكة

6d 20

Case_04.Isolation

ISO2 100 Bathrooms Proofing اعمال العزل للحمامات

2d 21

Case_04.IntPlastering

INP2 100 Internal Plastering for Walls & Slabs البياض الداخلي للحوائط

سقفالو

20d 22

INP2 200 TRATZO Plastering height 2m م ..عادة ما2سفل بارتفاع يكون بالممرات

8d 23

Case_04.PaintingPAI2 100 Painting Preparation Layers

اعمال البطانة للدهانات6d 24

PAI2 200 Painting Layers اعمال

الدهانات النهائية

12d 25

Case_04.FRP2 100

Frontal Plastering بياض الواجهات 21d 26

92

Page 93: 29585169 Projects Cost Management

93

FrontPlastering

Case_04.Flooring FLO2 100 Mosaic Tiles dim 40*40 cm 40*40تركيب بلط

سم

10d 27

Case_04.Ceramic CER2 100 Ceramic Working تركيب السراميك للحوائط

والسقف

4d 28

Case_04.HO END2 Hand Over تسليم الدور الثاني

10d 29

Add a Purpose Notebook topic to Activity “PRP2” as follows:

o ِAssign “Customer Problem” and add the following Notebook: “Participate in Analyzing User Input provided by the Acquirer to gain an understanding of User Needs. This input may take the form of Need Statements, Surveys, Interviews, or other User Feedback.”

Add the following Steps to Activity PRP2 :

o Identify Required States and Modes

o Define System Requirements

o Perform Requirements Tracing

o Document Requirements

5. Creating Activities Relationship *

93

Page 94: 29585169 Projects Cost Management

94

Background:

Now that the Activities have been entered, Relationships need to be established.Use the information from the table below to create relationships between the Activities.

The Project will be named Case _05 – Creating Relationships.

ActivityID

Activity Name Successor RelationType

Lag

ADM2* END2 FF 0

BLO2 100 WOD2 100 SS 8BLO2 200 WOD2 100 FS 0

CER2 100 PAI2 100 FS 0

CO22C100 CO22C200 SS 4CO22C200 CO22C300 FS 0CO22C300 CO22C400 FS 0CO22C400 CO22S100 SS 3

CO22S100 CO22S200 FF 2CO22S200 CO22S300 FS 0CO22S300 CO22S400 FS 0CO22S400 BLO2 100 FS 0CO22S400 BLO2 200 FS 0

ELE2 100 INP2 100 FS 0ELE2 100 SAN2 100 FS 0ELE2 200 PAI2 100 FS 0ELE2 300 END2 FS 0

FLO2 100 PAI2 100 FS 0

FRP2 100 SAN2 300 FS 0

94

Page 95: 29585169 Projects Cost Management

95

INP2 100 INP2 200 FS 0INP2 200 ELE2 200 FS 0INP2 200 FLO2 100 FS 0

ISO2 100 CER2 100 FS 0

PAI2 100 FRP2 100 FS 0PAI2 200 ELE2 300 FS 0

PRP2 CO22C100 FS 0

SAN2 100 SAN2 200 FS 0SAN2 200 ISO2 100 FS 0SAN2 300 WOD2 200 FS 0

WOD2 100 ELE2 100 FS 0WOD2 200 PAI2 200 FS 0

• The “Level of Effort” Activity (ADM2*) requires both a Predecessor and a Successor.

o Predecessor: Start-to-Start relationship with PRP2 Activity with 1 day of Lag.

o Successor: Finish-to-Finish relationship with END2 Activity.

6. Project Scheduling

95

Page 96: 29585169 Projects Cost Management

96

Background:

Having entered Activities, Duration, and Relationships for the Project, You are now ready to schedule the Project. Open the Project Case-06 – Scheduling and schedule the Project and view the “Schedule Log” of the Project’s Statistics.

The Project will be named Case_06 – Scheduling.Use “Copy/Paste” & change the name of the new Project….

Question:

Use the “Schedule Log” to answer the following questions:

7. How many activities are in the Project? ________________

8. How many relationships are in the Project? _____________

9. How many activities do not have Predecessors and/or Successors (Open Ends) in the Project? ______ _______

10. What is the Latest Early Finish Date for the Project? _____

11. How many Critical Activities in the Project? ____________

Hint:

Press “Schedule” icon

Press “View Log” to see Schedule Report.

96

Page 97: 29585169 Projects Cost Management

97

97

Page 98: 29585169 Projects Cost Management

98

2. Creating Activity Codes Dictionary :

The Project will be named CASE_07 – Creating Activity Codes Dictionary.

No Act. Code Name/Description

CodeValue

Code Title

1 Case_RespResponsibility

AHMED

AMR

NOHA

Resp of Reinforcement Works & Others

Resp of Electrical Works & Others

Resp of Finishing Works & Others2 Case_Area

Area/LocationAR Air Port Road, Heliopolis, Cairo

3 Case_MileMileStone

ECPS

MileStone for Electrical WorksMileStone for ConcreteMileStone for Painting WorksMileStone for Sanitary Works

4 Case_Type1Type of Work 1

ADMBLOCERCO2ELEENDFLOFRPINPISOPAISANPRPWOD

Project Administration Block WorksCeramic TilesReinforcement Concrete(RFT)Electrical WorksHand OverFlooring WorksFrontal PlasteringInternal PlasteringIsolation WorksPainting WorksSanitary WorksPreparation for the ProjectWooden Works

5 Case_Floor#Floor Number

12

First FloorSecond Floor

6 Case_ColSlabColumns/Slab&Stairs

CS

7 Case_Type2Type of Work 2

100200300400

Activity Codes here will be created on the Global-Level. !!!!! Open the Project. Click “Enterprise/Activity Codes…”, a “Primavera” Alarm window displays. Click “OK” Choose “Global”. Click “Modify” Click “Add” Continue…

98

Page 99: 29585169 Projects Cost Management

99

3. Assigning Activity Codes : (Activities Sorted Alphabetically)

The Project will be named Case_08 – Assigning Activity Codes.

Case_

No ActivityID

Activity Name PD RespArea

Mile

Typ1

ColSlab

01 ADM2 Project Administration --- AHMED AR02 BLO2 100 Block Work thick 25 cm 12 NOHA AR03 BLO2 200 Block Work thick 12 cm 4 NOHA AR04 CER2 100 Ceramic Work (Walls &

Slabs)4 NOHA AR

05 CO22C100 Form Work Columns 7 AHMED AR C CO2 C06 CO22C200 R.F.T Columns 4 AHMED AR C CO2 C07 CO22C300 Cast-in-Place Concrete

Columns3 AHMED AR C CO2 C

08 CO22C400 Curing Time for Columns 5 AHMED AR C CO2 C09 CO22S100 Form Work (Slabs &

Stairs) 11 AHMED AR C CO2 S

10 CO22S200 R.F.T (Slabs & Stairs) 7 AHMED AR C CO2 S11 CO22S300 Cast-in-Place (Slabs &

Stairs) 3 AHMED AR C CO2 S

12 CO22S400 Curing Time & Removal of FormWork for Slab/Stairs

10 AHMED AR C CO2 S

13 END2 Hand Over 10 NOHA AR14 ELE2 100 Electrical Conduits 7 AMR AR E15 ELE2 200 Electrical Wires 14 AMR AR E16 ELE2 300 Electrical Switches

Lighting Fix.14 AMR AR E

17 FLO2 100 Mosaic Tiles Dim 40*40 cm

10 NOHA AR

18 FRP2 100 Frontal Plastering 21 NOHA AR 19 INP2 100 Internal Plastering for

Walls & Stairs20 NOHA AR

20 INP2 200 TRATZO Plastering Height 2m

8 NOHA AR

21 ISO2 100 Bathrooms Proofing 2 AHMED AR 22 PAI2 100 Painting Preparation

Layers6 NOHA AR P

23 PAI2 200 Final Painting Layers 12 NOHA AR P24 SAN2 100 Sanitary Pipes 20 NOHA AR S25 SAN2 200 Potable Water Piping

Circuits9 NOHA AR S

99

Page 100: 29585169 Projects Cost Management

100

26 SAN2 300 Installation of Sanitary Fixtures

6 NOHA AR S

27 PRP2 Preparing Project Requirements & Analysis

10 AHMED AR

28 WOD2 100 Windows & Doors Sub-Frames Installation

7 NOHA AR

29 WOD2 200 Doors & Windows Installation

10 NOHA AR

* Activities here are sorted alphabetically. ** Note: You can sort them by ES and TF.*** MileStone here does not mean Activity MileStome. It is used for example to group Activities.

Questions Related to Activity Codes:

1. Display all activities of RFT. Check that the Code Case_Type1 is assigned to the activities: CO22C100 ..

CO22S400. Create and execute a Filter: Where “Case_Type1 = CO2”

2. Display all Activities related to Eng Ahmed & Columns Only. Do not forget to assign the Activity Code “Case_ColSlab” to the corresponding

Activities.

3. Display all Activities of Columns.

4. Display all Activities of Slab & Stairs.

5. Display any Activities of Eng. Ahmed or Amr.

6. Display all Activities of Eng. Ahmed and Amr.

7. Display all Activities in 2nd Floor & RFT (i.e., CO2…activities)

8. Create Schedule Report with ES < 01-MAR-09 and Eng. Ahmed

9. …etc

Hint: The following Layout comes from:o “Layout Option Bar/Group and Sort/Group By ---- Case_Respo Click “ID/Code” box

100

Page 101: 29585169 Projects Cost Management

101

101

Page 102: 29585169 Projects Cost Management

102

4. Resources Management

The Project will be named CASE_09 – Resource Breakdown Structure.

Resources Breakdown Structure (RBS)Root: Case_RBS

LaborCase ------ Labor of Case_RBSo Carpentero Steel.Men o Con.Laboro Ord.Laboro Bric.Layo Door.Carpo Plas.Meno Plumbero Tile.Men Resourceso Iso.Meno Cer.Meno Paint.Men o Plumber-1o Front.Plaster o Light.Fixturero Removalo TRAT.Plaster.Meno . . .

EquipmentsCase ------ Equipments of Case_RBSo Conc.Mixo Up.Crane Resourceso . . .

MaterialsCase ------ Materials of Case_RBSo R.F.To Cemento Sando Gravelo Water.Priceo Brick.Mato Gypsumo Paint.Mato San.Pipeo WhiteCem Resourceso Iron.Pipo Mosaico Isolationo San.Fixo Mos.Door

102

Page 103: 29585169 Projects Cost Management

103

o Light.Fixationo Ord.Tiles

Now,

Click “Enterprise/Resources”.

Click the “Display Option” bar.

Choose “Group and Sort By/Default”.

Press “Add” in the “Command” bar

o Add the Root of the RBS:Resource ID: Case_RBS Name: Case Study Resources

o Under the Root Resource ID (Case_RBS), “Add” the 2nd Levels. For example:

Case_RBS. LaborCaseCase_RBS.EqupmentsCaseCase_RBS.MaterialsCase

103

Page 104: 29585169 Projects Cost Management

104

Hint : Creating Resources’ Units of Measure

You can establish the Resource’s Units of Measure (to be used with Materials Resources) as follows:

o Click “Admin/Admin Categories…”

o Click “Units of Measure” button, the “Admin Categories” displays.

o Click “Add”.

o Write the “Unit Abbreviation” & “Unit Name” for the required Units of Measure.

o For our Case Study, we have the following Units of Measures:

SN Unit Abbreviation

Unit Name

01 Ton Ton02 Day Day03 CM Cubic Meter 04 SM Square Meter 05 LM Long Meter06 Part Part07 Each Each

104

Page 105: 29585169 Projects Cost Management

105

After establishing Units of Measure, You can select the Unit of Measure when assigning the Resources to Activities in the Activities window.

105

Page 106: 29585169 Projects Cost Management

106

5. Creating Resources Dictionary

The Project will be named Case_10 – Resource Dictionary.

“Add” the coming Resources for each corresponding RBS Items…

A) LaborCase (People) *

Hint: Do not forget to assign the Default Project Calendar (It should be better to be Global Calendar. It is called in our case: Case Cal- 5 D/W [SUN] with Holidays) to the different Resources except when there are Resource Calendars…

NO RESOURCE/DISCRIPTION

Def.Units/Time(h/d)

Max. Units/Time(h/d)

Price/Unit ($)

($/d)01 Administer 1h/d 1h/d 50/h02 Plumber سباك -- طقم

Crew(1 Blumber+ 1 Assistant)8/d 24/d 23/d

03 Bric.Lay بنآCrew(8 B.L +2 Mortar + 2 Handling)

8/d 32/d 75/d

04 Carpentr النجارين Crew(Carpenter + Assistant)

8/d 80/d 25/d

05 Cer.Men متخصص تركيب سيراميكCrew(1 Chief + 1 Assistant)

8/d 16/d 28/d

06 Con.Labor الطبلية Crew(20 Workers)

8/d 16/d 300/d

07 Door.Carp نجار باب و شباك Crew(1 Carpenter + 1 Assistant)

8/d 56/d 28/d

08 Front.Plaster بياض المحارة --- واجهات Crew(2 Palstmen + 2 Assistant + 1 Worker)

8/d 32/d 60/d

09 Iso.MenCrew(1 Chief + 2 Assistant)

8/d 16/d 25/d

10 Ord.LaborOrdinary Labor

8/d 136/d 20/d

11 Paint.Men النقاشين Crew(4 Painters + 2 Assistants)

8/d 16/d 100/d

12 Plas.Men متخصص بياض Crew(1 Plaster Man + 1 Mortar)

8/d 40/d 25/d

13 RemovalRemoval of FormWork to Upper Level

8/d 40/d 20/d

14 Steel.Men الحدادين Crew(2 St. Cut. + 2 St. Erection + 3 Assist.)

8/d 32/d 70/d

15 Tile.Men 8 المبلطين/d 16/d 130/d

106

Page 107: 29585169 Projects Cost Management

107

Tile Men for Mosaic Flooring)16 TRAT.Plaster.Men المبيضين

Crew(2 Plastermen + 2 Mortar) TRATZO Plaster Men.8/d 16d 50/d

17 PMProject Manager

8/d 16d 300/d

Data to be entered in the “Resource Dictionary”

B) EquipmentsCase - NonLabor

NO RESOURCE/ Def. Max. Price/

107

Page 108: 29585169 Projects Cost Management

108

DISCRIPTION Units/Time(h/d)

Units/Time(h/d)

Unit of Time($/d)

1 Conc.Mix الخلطة الخرسانية Concrete Mixer used for R.F.T , P.C * * (P.C = Plain concrete)

8/d 16/d 400/d

2 Up.Crane ونش لرفع الطوب Up. Lift Crane used for Bricks

8/d 8/d 50/d

C) MaterialsCase

NO RESOURCE/DISCRIPTION

Unit of Measure

Def.Units/Time

Max.Units/Time

Price/Unit($/U)

01 Brick.Mat الطوبBrick material thickness 12 cm

SM 180/d 6

01d Brick.Mat الطوبBrick material thickness 25 cm

SM 180/d 12

02 Cement Cement

Ton 10/d 8/d 380

03 CeramicCeramic Dim 20*20 cm

SM 50/d 25

04 Gravel زلط Gravel for Different Tasks

CM 60/d 22

05 Gypsum جيبس Gypsum for different Tasks

Ton 1/d 108

06 Insulation المادة العازلة Insulation Material for Water Proofing

SM 50/d 5

07 Iron.Pip مواسير الحديد Iron Pipe diameter .5”

LM 100/d 5

08 Light.Fixation تركيبات كهربية Electric Switches and Lighting Fixtures

Part 10/d 200

9 Mos.Door البواب والشبابيك الموسكيMoskey Materials (Door + Window)

Part 12/d 150

10 Mosaic الموزايك Mosaic Tiles dim 40*40 cm

SM 60/d 20

11 Ord.Tile بلط عادي Ordinary Tiles for Roof dim 20*20 cm

SM 40/d 5

12 Paint.MatPainting Materials

SM 300/d 3

13 R.F.T حديد التسليح Reinforcement Steel

Ton 3/d 3600

14 San.Fixt أجهزة صحي Sanitary Fixtures

Part 10/d 1200

15 SAN.PIPE مواسير الصرف الصحي Pipe Material for Sanitary Pipes

LM 30/d 20

16 Sand CM 12/d 5

108

Page 109: 29585169 Projects Cost Management

109

Sand for Different Tasks

17 Water.Price مياهWater

CM 10/d 10

18 WhiteCemWhite Cement

Ton 1/d 500

Hint:

Click “Edit/User Preferences…/Time Units tab” to customize the Units of Time as follows:

Units Format:o Unit of Time: hour

Duration Format:o Unit Time: day

Units/Time Format:o Choose “Show as units/duration”

No need for writing values in the “Default Units/Time” of Materials except when needed…

Close

109

Page 110: 29585169 Projects Cost Management

110

110

Page 111: 29585169 Projects Cost Management

111

111

Page 112: 29585169 Projects Cost Management

112

6. Assigning Resources and Costs

Project Manager has identified the specific Resources that will be work on this Project.

Project will be named Case_11 – Assigning Resources & Costs.

Assign Resources based on the table below. If an activity has multiple resource assignments, the 1st resource listed is the Primary Resource.

(Activities are sorted by Act. ID)

No Act. ID TitleOD

Resource ID

Res.Type

UnitofMeasure

DefaultUnits/Time

BudgetedUnits/Time

01 ADM2 Project Administration --- Administer L 1h/d 1h/d

02 PRP2 Preparing Project Requirements & Analysis

10d PM 8/d

03-1 BLO2 100 Block Work thick 25 cm 12d Bric.Lay L 1/d 24/d03-2 BLO2 100 Block Work thick 25 cm 12d Cement M TON 10/d 20/d03-3 BLO2 100 Block Work thick 25 cm 12d Brick.Mat M CM 180/d

04-1 BLO2 200 Block Work thick 12 cm 04d Bric.Lay L 1/d 16/d04-2 BLO2 200 Block Work thick 12 cm 04d Brick.Mat M SM 80/d04-3 BLO2 200 Block Work thick 12 cm 04d Cement M TON 10/d

P3eCaseStudy - 112

Page 113: 29585169 Projects Cost Management

113

05-1 CER2 100 Ceramic Work (Wall&Slabs) 04d Ceramic M SM 50/d05-2 CER2 100 Ceramic Work (Wall&Slabs) 04d Cer.Men L 1/d 16/d05-3 CER2 100 Ceramic Work (Wall&Slabs) 04d Sand M CM 3/d

06 CO22C100 Form Work Columns 07d Carpenter L 1/d 48/d

07-1 CO22C200 R.F.T Columns 04d R.F.T M TON 3/d07-2 CO22C200 R.F.T Columns 04d Steel.Men L 1/d 24/d

08-1 CO22C300 Cast-in-Place Concrete Columns 03d Conc.Mix E 1/d 2/d08-2 CO22C300 Cast-in-Place Concrete Columns 03d Con.Labor L 1/d 32/d08-3 CO22C300 Cast-in-Place Concrete Columns 03d Cement M TON 10/d08-4 CO22C300 Cast-in-Place Concrete Columns 03d Sand M CM 20/d08-5 CO22C300 Cast-in-Place Concrete Columns 03d Gravel M CM 25/d

09-1 CO22C400 Curing time for Columns 05d Water.Price M CM 10/d09-2 CO22C400 Curing time for Columns 05d Ord.Labor L 1/d 8/d

10 CO22S100 Form Work (Slabs/Stairs) 11d Carpenter L 1/d 80/d

11-1 CO22S200 R.F.T (Slabs/Stairs) 07d Steel.Men L 1/d 24/d11-2 CO22S200 R.F.T (Slabs/Stairs) 07d R.F.T M TON 4/d

12-1 CO22S300 Cast-in-Place (Slab/Stairs) 03d Con.Labor L 1/d 16/d12-2 CO22S300 Cast-in-Place (Slab/Stairs) 03d Conc.Mix E 1/d 2/d12-3 CO22S300 Cast-in-Place (Slab/Stairs) 03d Cement M TON 25/d12-4 CO22S300 Cast-in-Place (Slab/Stairs) 03d Sand M CM 30/d12-5 CO22S300 Cast-in-Place (Slab/Stairs) 03d Gravel M CM 60/d

P3eCaseStudy - 113

Page 114: 29585169 Projects Cost Management

114

13-1 CO22S400 Curing Time & Removal of FormWork for Slab/Stairs

10d Ord.Labor L 1/d 8/d

13-2 CO22S400 Curing time & Removal of FormWork for Slab/Stairs

10d Water.Price M CM 16/d

14-1 ELE2 100 Electrical Conduits 07d14-2 ELE2 100 Electrical Conduits 07d

15-1 ELE2 200 Electrical Wires 14d15-2 ELE2 200 Electrical Wires 14d

16-1 ELE2 300 Electrical Switches Lighting Fix 14d Light.Fixation M PART 18/d16-2 ELE2 300 Electrical Switches Lighting Fix 14d

17 END2 Hand Over 10d

18-1 FLO2 100 Mosaic Tiles dim 40*40 cm 10d Mosaic M SM 125/d18-2 FLO2 100 Mosaic Tiles dim 40*40 cm 10d Tile.Men L 1/d 16/d18-3 FLO2 100 Mosaic Tiles dim 40*40 cm 10d Sand M CM 5/d18-4 FLO2 100 Mosaic Tiles dim 40*40 cm 10d Cement M TON 10/d 1/d

19-1 FRP2 100 Frontal Plastering 21d Front.Plaster L 1/d 40/d19-2 FRP2 100 Frontal Plastering 21d Cement M TON 10/d 2/d19-3 FRP2 100 Frontal Plastering 21d Sand M CM 4/d19-4 FRP2 100 Frontal Plastering 21d Gypsum M TON 1/d19-5 FRP2 100 Frontal Plastering 21d WhiteCem M TON 1/d

P3eCaseStudy - 114

Page 115: 29585169 Projects Cost Management

115

20-1 INP2 100 Internal Plastering for Walls & Slabs 20d Front.Plaster L 1/d 32/d20-2 INP2 100 Internal Plastering for Walls & Slabs 20d Cement M TON 10/d 2/d20-3 INP2 100 Internal Plastering for Walls & Slabs 20d Sand M CM 6/d20-4 INP2 100 Internal Plastering for Walls & Slabs 20d Gypsum M TON 1/d

21-1 INP2 200 TRATZO Plastering 08d Plas.Men L 1/d 24/d21-2 INP2 200 TRATZO Plastering 08d Cement M TON 10/d 2/d21-3 INP2 200 TRATZO Plastering 08d Sand M CM 30/d21-4 INP2 200 TRATZO Plastering 08d Gypsum M TON 1/d21-5 INP2 200 TRATZO Plastering 08d WhiteCem M TON 1/d

22-1 ISO2 100 Bathrooms Proofing 02d Isolation.Men L 1/d 8/d22-2 ISO2 100 Bathrooms Proofing 02d Insulation M SM 100/d

23-1 PAI2 100 Painting Preparation Layers 06d Paint.Men L 1/d 16/d23-2 PAI2 100 Painting Preparation Layers 06d Paint.Mat M SM 308/d

24-1 PAI2 200 Final Painting Layers 12d Paint.Mat M SM 308/d24-2 PAI2 200 Final Painting Layers 12d Paint.Men L 1/d 16/d

25-1 SAN2 100 Sanitary Pipes 20d Plumber-1 L 1/d 24/d25-2 SAN2 100 Sanitary Pipes 20d San.Pipe M LM 60/d

26-1 SAN2 200 Potable Water Piping Circuits 09d Plumber-1 L 1/d 24/d26-2 SAN2 200 Potable Water Piping Circuits 09d Iron.Pip M LM 20/d

P3eCaseStudy - 115

Page 116: 29585169 Projects Cost Management

116

27-1 SAN2 300 Install of Sanitary Fixtures 06d Plumber-1 L 1d 16/d27-2 SAN2 300 Install of Sanitary Fixtures 06d San.Fixt M PART 2/d

28 WOD2 100 Windows & Doors Sub-Frames Installation

07d Door.Carp L 1/d 32/d

29-1 WOD2 200 Windows & Doors Installation 10d Door.Carp L 1/d 56/d29-2 WOD2 200 Windows & Doors Installation 10d Mos.Door M PART 8/d

P3eCaseStudy - 116

Page 117: 29585169 Projects Cost Management

117

7. Cost Accounts Dictionary

Project will be named Case_12 – Coat Account Dictionary.

Cost Accounts Structure:

Root: Case_CA Cost Categories:

Cost Category Code Category Title -------------------------- ----------------------------

L Labor

E Nonlabor (Equipment)

M Material

S Expenses

Hint:

Use “Enterprise/Cost Accounts…” to build Cost Account Dictionary..

P3eCaseStudy - 117

Page 118: 29585169 Projects Cost Management

118

Cost Account:

Hint: Each Activity has its own Cost Account. So, most of Cost Accounts take the names of Activities IDs

NoCost

AccountPrefix

Cost Account ID Cost Account Name Cost Account Category

Suffix01

Case_CA.

ADM2 Project Administration

Each Cost Account have all of the Cost Categories: L, E, M, and S

02 BLO2 100 Block Work thick 25 cm 03 BLO2 200 Block Work thick 12 cm04 CER2 100 Ceramic Work (Walls & Slabs)05 CO22C100 Form Work Columns06 CO22C200 R.F.T Columns07 CO22C300 Cast-in-Place Concrete Columns08 CO22C400 Curing time for Columns09 CO22S100 Form Work (Slabs & Stairs) 10 CO22S200 R.F.T (Slabs & Stairs) 11 CO22S300 Cast-in-Place (Slabs & Stairs) 12 CO22S400 Curing time & Removal of

FormWork for Slab/Stairs13 END2 Hand Over 14 ELE2 100 Electrical Conduits15 ELE2 200 Electrical Wires16 ELE2 300 Electrical Switches Lighting Fix.17 FLO2 100 Mosaic Tiles Dim 40*40 cm18 FRP2 100 Frontal Plastering19 INP2 100 Internal Plastering for Walls & Stairs20 INP2 200 TRATZO Plastering Height 2m21 ISO2 100 Bathrooms Proofing

P3eCaseStudy - 118

Page 119: 29585169 Projects Cost Management

119

22 PAI2 100 Painting Preparation Layers23 PAI2 200 Final Painting Layers24 SAN2 100 Sanitary Pipes25 SAN2 200 Potable Water Piping Circuits26 SAN2 300 Installation of Sanitary Fixtures27 PRP2 Preparing Project Requirements &

Analysis28 WOD2 100 Windows & Doors Sub-Frames

Installation29 WOD2 200 Doors & Windows Installation

P3eCaseStudy - 119

Page 120: 29585169 Projects Cost Management

120

P3eCaseStudy - 120

Page 121: 29585169 Projects Cost Management

121

P3eCaseStudy - 121

Page 122: 29585169 Projects Cost Management

122

8. Assigning Cost Accounts

Project will be named Case_13 – Assigning Coat Accounts

Note: There is only one Cost-Account (with different categories) for each Activity Cost Accounts exist where there are Resources….

No Act. ID TitleOD

Resource Name

Res.Type

CostAccount

01 ADM2 Project Administration --- L ADM2.L

02 PRP2 Preparing Project Requirements & Analysis

10d PRP2.L

03-1 BLO2 100 Block Work thick 25 cm 12d BRIC.LAY L BLO2 100.L03-2 BLO2 100 Block Work thick 25 cm 12d CEMENT M BLO2 100.M03-3 BLO2 100 Block Work thick 25 cm 12d BRICKMAT M BLO2 100.M

04-1 BLO2 200 Block Work thick 12 cm 04d BRIC.LAY L BLO2 200.L04-2 BLO2 200 Block Work thick 12 cm 04d BRICKMAT M BLO2 200.M04-3 BLO2 200 Block Work thick 12 cm 04d CEMENT M BLO2 200.M

05-1 CER2 100 Ceramic Work (Wall&Slabs) 04d CERAMIC M CER2 100.M05-2 CER2 100 Ceramic Work (Wall&Slabs) 04d CER.MEN L CER2 100.L05-3 CER2 100 Ceramic Work (Wall&Slabs) 04d SAND M CER2 100.M

06 CO22C100 Form Work Columns 07d CARPENTR L CO22C100.L

P3eCaseStudy - 122

Page 123: 29585169 Projects Cost Management

123

07-1 CO22C200 R.F.T Columns 04d R.F.T M CO22C200.M07-2 CO22C200 R.F.T Columns 04d STEELMEN L CO22C200.L

08-1 CO22C300 Cast-in-Place Concrete Columns 03d CONC.MIX E CO22C300.E08-2 CO22C300 Cast-in-Place Concrete Columns 03d CON.LABR L CO22C300.L08-3 CO22C300 Cast-in-Place Concrete Columns 03d CEMENT M CO22C300.M08-4 CO22C300 Cast-in-Place Concrete Columns 03d SAND M CO22C300.M08-5 CO22C300 Cast-in-Place Concrete Columns 03d GRAVEL M CO22C300.M

09-1 CO22C400 Curing Time for Columns 05d WATERPRI M CO22C400.M09-2 CO22C400 Curing Time for Columns 05d LABOUR L CO22C400.L

10 CO22S100 Form Work (Slabs/Stairs) 11d CARPENTR L CO22S100.L

11-1 CO22S200 R.F.T (Slabs/Stairs) 07d STEELMEN L CO22S200.L11-2 CO22S200 R.F.T (Slabs/Stairs) 07d R.F.T M CO22S200.M

12-1 CO22S300 Cast-in-Place (Slab/Stairs) 03d CON.LABR L CO22S300.L12-2 CO22S300 Cast-in-Place (Slab/Stairs) 03d CONC.MIX E CO22S300.E12-3 CO22S300 Cast-in-Place (Slab/Stairs) 03d CEMENT M CO22S300.M12-4 CO22S300 Cast-in-Place (Slab/Stairs) 03d SAND M CO22S300.M12-5 CO22S300 Cast-in-Place (Slab/Stairs) 03d GRAVEL M CO22S300.M

13-1 CO22S400 Curing time & Removal of Form Work for Slab/Stairs

10d LABOUR L CO22S400.L

13-2 CO22S400 Curing time & Removal of Form Work for Slab/Stairs

10d WATERPRI M CO22S400.M

14-1 ELE2 100 Electrical Conduits 07d ELE2 100.L14-2 ELE2 100 Electrical Conduits 07d ELE2 100.M

15-1 ELE2 200 Electrical Wires 14d ELE2 200.L

P3eCaseStudy - 123

Page 124: 29585169 Projects Cost Management

124

15-2 ELE2 200 Electrical Wires 14d ELE2 200.M

16-1 ELE2 300 Electrical Switches Lighting Fix 14d LIG.FIXT M ELE2 300.M16-2 ELE2 300 Electrical Switches Lighting Fix 14d L ELE2 300.L

17 END2 Hand Over 10d END2.L

18-1 FLO2 100 Mosaic Tiles dim 40*40 cm 10d MOSAIC M FLO2 100.M18-2 FLO2 100 Mosaic Tiles dim 40*40 cm 10d TILE.MEN L FLO2 100.L18-3 FLO2 100 Mosaic Tiles dim 40*40 cm 10d SAND M FLO2 100.M18-4 FLO2 100 Mosaic Tiles dim 40*40 cm 10d CEMENT M FLO2 100.M

19-1 FRP2 100 Frontal Plastering 21d FRON.PLA L FRP2 100.L19-2 FRP2 100 Frontal Plastering 21d CEMENT M FRP2 100.M19-3 FRP2 100 Frontal Plastering 21d SAND M FRP2 100.M19-4 FRP2 100 Frontal Plastering 21d GUYPSUM M FRP2 100.M19-5 FRP2 100 Frontal Plastering 21d WHITECEN M FRP2 100.M

20-1 INP2 100 Internal Plastering for Walls & Slabs

20d PLAS.MEN L INP2 100.L

20-2 INP2 100 Internal Plastering for Walls & Slabs

20d CEMENT M INP2 100.M

20-3 INP2 100 Internal Plastering for Walls & Slabs

20d SAND M INP2 100.M

20-4 INP2 100 Internal Plastering for Walls & Slabs

20d GUYPSUM M INP2 100.M

21-1 INP2 200 TRATZO Plastering 08d PLAS.MEN L INP2 200.L21-2 INP2 200 TRATZO Plastering 08d CEMENT M INP2 200.M21-3 INP2 200 TRATZO Plastering 08d SAND M INP2 200.M21-4 INP2 200 TRATZO Plastering 08d GUYPSUM M INP2 200.M21-5 INP2 200 TRATZO Plastering 08d WHITECEN M INP2 200.M

P3eCaseStudy - 124

Page 125: 29585169 Projects Cost Management

125

22-1 ISO2 100 Bathrooms Proofing 02d ISO.MEN L ISO2 100.L22-2 ISO2 100 Bathrooms Proofing 02d INSULATI M ISO2 100.M

23-1 PAI2 100 Painting Preparation Layers 06d PAINTMEN L PAI2 100.L23-2 PAI2 100 Painting Preparation Layers 06d PAINTMAT M PAI2 100.M

24-1 PAI2 200 Final Painting Layers 12d PAINTMAT M PAI2 200.M24-2 PAI2 200 Final Painting Layers 12d PAINT L PAI2 200.L

25-1 SAN2 100 Sanitary Pipes 20d BLUMBER L SAN2 100.L25-2 SAN2 100 Sanitary Pipes 20d SAN.PIPE L SAN2 100.L

26-1 SAN2 200 Potable Water Piping Circuits 09d BLUMBER L SAN2 200.L26-2 SAN2 200 Potable Water Piping Circuits 09d IRON.PIP L SAN2 200.L

27-1 SAN2 300 Install of Sanitary Fixtures 06d BLUMBER L SAN2 300.L27-2 SAN2 300 Install of Sanitary Fixtures 06d SAN.FIXT M SAN2 300.M

28 WOD2 100 Windows & Doors Sub-Frames Installation

07d DOORCARP L WOD2 100.L

29-1 WOD2 200 Windows & Doors Installation 10d DOORCARP L WOD2 200.L29-2 WOD2 200 Windows & Doors Installation 10d MOS.DOOR M WOD2 200.M

P3eCaseStudy - 125

Page 126: 29585169 Projects Cost Management

126

P3eCaseStudy - 126

Page 127: 29585169 Projects Cost Management

127

9. Analyzing Resources & Costs

Objectives:

Verify a “Gantt Chart” is displayed in the top Layout window.

Display a “Resource Usage Profile” in the bottom Layout window.

Format the Timescale to display a Date Interval once of “Year/Month” and once of “Month/Week” or “Week/Day”.

Adjust the Timescale to view the Date Range of the entire Project.

Verify that only the Resources assigned to the Case Study are displayed in the “Resource/Role” Hierarchy.

Hide the Legend in the Resource Profile.

Display the resource called “Cement” Profile.

Rsolve the “Over-Allocation” of all Over-Allocated Resources.

P3eCaseStudy - 127

Page 128: 29585169 Projects Cost Management

128

P3eCaseStudy - 128

Page 129: 29585169 Projects Cost Management

129

Resolve Resource Over-Allocation:

All of the following Resources are over-allocated and the over-allocation resolved ( for simplicity ) by the suggested “ Max. Units /Time ” :

ResourceUnit of Measure

Suggested Max. Units /Time

1 BrickMat SM 1200 SM/d2 Cement Ton 70 Ton/d3 Light.Fixation Part 90Part/d

4 Mosaic SM 600 SM/d5 Sand CM 150 CM/d6 R.F.T Ton 18 Ton/d

By this manner, the project becomes optimized.

Hint: Many waysto resolve Resource-overallocation

o There is what we call Resource-Leveling, and

o Activities Relationships

P3eCaseStudy - 129

Page 130: 29585169 Projects Cost Management

130

10. Optimizing the Project Plan

Verify that the Projeect Plan meets the Project Stakeholders’s Dates, Resource, and Cost Requirements.

Shorten a Project Schedule

o The most important date in the schedule is the calculated Project Finish Date.

o If the calculated Finish Date of the Project is behind the required Project Finish Date, the Project must be shortend. In addition, each deliverable in the Project should be scheduled to finish by the dates imposed by the Project stakeholders.

It is required for our case that the Project must finished by 01-Sep-11. However, the scheduled indicates that the Project will not finish until 29-Sep-11.

P3eCaseStudy - 130

Page 131: 29585169 Projects Cost Management

131

Focusing on Critical Activities :

o Click the “Setting” tab in the “Projects” window.

o In the “Critical Activities” section, select “Logest Path”.

o Go to “Activities” window.

o Choose “Filter…” from the “Layout Option Bar”.

o Check “Critical” and press OK as shown:

P3eCaseStudy - 131

Page 132: 29585169 Projects Cost Management

132

P3eCaseStudy - 132

Page 133: 29585169 Projects Cost Management

133

o Decrease the Duration of Activity “FRP2 100” from 21 days to 14 days , the Project Schedule Finish Date becmes 08-Sep-11.

o Add a Successor Actvity “ELE2 300” to “ELE2 200” with Relationship type “SS” and “Lag time = 1”, the Project Schedule Finish Date becmes 20-Sep-11.

o Decrease the Duration of Activity “ELE2 300” from 14 days to 13 days , the Project Schedule Finish Date becmes 14-Sep-11.

o Decrease the Duration of Activity “INP2 100” from 20 days to 14 days , the Project Schedule Finish Date becmes 06-Sep-11.

o Decrease the Duration of Activity “PAI 200” from 12 days to 10 days , and

o Decrease the Duration of Activity “WOD2 200” from 10 days to 7 days , the Project Schedule Finish Date becmes

P3eCaseStudy - 133

Page 134: 29585169 Projects Cost Management

134

01-Sep-1 as shown:

P3eCaseStudy - 134

Page 135: 29585169 Projects Cost Management

135

Cost Report Using Cost Account:

Click “Tools/Report Wizard”

Choose “New Report”

Select Subject Area: Cost Accounts

Select Additional Subject Area: Activity Resource and Role Assignments

Columns:

o Cost Account ID

o Cost Account Name

o Cost Account Description

o Labor Cost

o Nonlabor (Equipment) Cost

o Material Cost

o Total Cost

Continue…

For Cost Accounts: Use “Tools/Reports” to run the ready made report:

o Report Group: Cost

P3eCaseStudy - 135

Page 136: 29585169 Projects Cost Management

136

Report Group: ControlCC-01 Budgeted Cost by Cost Account

11. Baselining the Project Plan

Creating BaseLine:

o Open the Project “Case_15 --- BaseLining the Project Plan”

o In the “Project” menu, click “Maintain Baselines”.

o Verify the Project to which you are associating the Baseline “Case_15 BaseLining the Project Plan” is selected.

o Click OK.

o Select the Baseline “BaseLining the Project Plan - B1”

o Type a new Baseline name “Base 1: Case_Target”

o In the “Baseline Type” drop-down-list, select “Initial Plan”

P3eCaseStudy - 136

Page 137: 29585169 Projects Cost Management

137

Assigning a BaseLine:

o Click “Project/Assign Baselines…”

o In the opened dialog box, select “Base 1: Case_Target” in both “Project Baseline” & “User Baselines – Primary” fields.

o Click OK.

P3eCaseStudy - 137

Page 138: 29585169 Projects Cost Management

138

Viewing Baseline Bars & Bar Style:

o In the “Layout Option Bar”, click “Bars”.

o Mark the check boxes next to “Primary Baseline” & “Baseline Milestone”

o Click OK.

o Notice the Baseline Bars appears in the “Gantt Chart”.

o Save this Layout with the name “Current vs. Baseline Bars”

Bar labels :

o In the “Layout options Bar”, click “Bars”.

o Highlight a bar, “Current Bar Labels”.

o Click the “Bar Labels” tab.

o In the “Label” column, replace “Activity Name” with “Finish”

o Click “Add”.

o In the “Label” column, select “Total Float”.

o Click OK.

P3eCaseStudy - 138

Page 139: 29585169 Projects Cost Management

139

P3eCaseStudy - 139

Page 140: 29585169 Projects Cost Management

140

P3eCaseStudy - 140

Page 141: 29585169 Projects Cost Management

141

P3eCaseStudy - 141

Page 142: 29585169 Projects Cost Management

142

12. Project Execution & Control

Once the Project Information has been distributed, the next step is to update the Project with Actuals.

Information has been distributed about the Project. The Project has started. You have gathered information from the Team Members. You can now manually update the Activities and apply the progress to the Project.

Updating the Project:

You may need to update daily, weekly, or monthly, depending on the length of the Project and how frequently you want to adjust your forecasts.

How Data is Collected?

o Project Managers manually enter the Actual Date, Resource, and Cost Information.

Record Actual Dates and Progress, Actual Resource Usage and Costs.

o Approve and Apply Timesheets:

Team Members use the Timesheets Module to update Activities.

Project Managers review and approve timesheets.

Project Managers apply timesheets to the Project.

Data Date :

o The Data Date is the date up to which Acual Performance Data is reported and the Date from which future work is scheduled.

P3eCaseStudy - 142

Page 143: 29585169 Projects Cost Management

143

Updating Process:

o Create a Baseline Plan.

o Enter Activity Progress.

o Use Suspend & Resume Dates as necessary.

o Apply Actuals to the Project

o Perform Target Analysis:

Compare the Current Plan to the Target Plan to analyze variances.

o Determine whether Project Objectives are being met:

Will the Project finish on time?

Are Project Resources being used effectively?

Use the following Activity Progress:

o Actual Data is usually different from Planned Data. It is the real Time/Cost associated with an Activity.

o Record Actual Information for the Project using the Actual Data coming from the Site,

P3eCaseStudy - 143

Page 144: 29585169 Projects Cost Management

144

P3eCaseStudy - 144

Page 145: 29585169 Projects Cost Management

145

Act ID Act Name Dur AS AF Expected Finish

PCT

ADM2 Project Administration 170 1/1/11

PRP2 Preparing Project Requirements & Analysis

10 3/1/11 17/1/11

CO22C100 FormWork (Columns) 7 4/1/11 11/1/11

CO22C200 RFT (Columns) 4 8/1/11 12/1/11

CO22C300 Cast-in-Place Concrete (Columns) 3 13/1/11 16/1/11

CO22C400 Curing Time for Columns 5 19/1/11 25/1/11

CO22S100 FormWork (Slab/Stairs) 10 24/1/11 10/2/11

CO22S200 RFT (Slab/Stairs) 7 30/1/11 … 80.0

P3eCaseStudy - 145

Page 146: 29585169 Projects Cost Management

146

Remember that The Earlist Completion Date of the Projerct was 01-Sep-2010.

Drag the “Data Date” to the morning of 01-Feb-11 as shown:

P3eCaseStudy - 146

Page 147: 29585169 Projects Cost Management

147

P3eCaseStudy - 147

Page 148: 29585169 Projects Cost Management

148

Entering Actuals:

For Completed Activities :

o Actual Start & Actual Finish Dates

o Actual regular Units/Costs

o Actual Expense Costs

For Activities In-Progress :

o Actual Start Date

o Suspend and/or Resume Dates

o Percent Complete and/or Remaining Duration

o Expected Finish Dates

o Actual regular Units/Costs and Remaining Units/Costs

o Actual and Remaining Expense Costs

P3eCaseStudy - 148

Page 149: 29585169 Projects Cost Management

149

P3eCaseStudy - 149

Page 150: 29585169 Projects Cost Management

150

Resheduling Project & Viewing the Results:

P3eCaseStudy - 150

Page 151: 29585169 Projects Cost Management

151

P3eCaseStudy - 151

Page 152: 29585169 Projects Cost Management

152

Controlling the Project:

o It seems that the Project is behid the target by 7 days.

o Repeat the process of solving this problem as mentioned before.

P3eCaseStudy - 152

Page 153: 29585169 Projects Cost Management

153

13. Reporting Performance

In this section, We demonstrate how to run & create Tabular Reports as a means of reporting performance information.

Describe Reporting Methods

Run a Schedule Report

Create a Resource Report with the Report Wizard

Create a Report using the Current Layout

Methods for Performance Reporting:

There are many methods to distribute Schedule, Resource, and Cost Performance Information to Project Team.

1. Open the Project, Case_15.

2. From the “Directory” bar, click “Reports”

3. Locate a Report Group Title Band, “Schedule”.

4. Highlight the report “SR-03 Schedule Report with Activity Budget”

5. In the “Command” bar, click “Run Report”.

Hint: When you see the report, right-click and choose “Save As --- image.jpg”

P3eCaseStudy - 153

Page 154: 29585169 Projects Cost Management

154

P3eCaseStudy - 154

Page 155: 29585169 Projects Cost Management

155

Report Wizard

You can report “Resource Assignment” by creating and printing a “Resource Report” in the “Report Wizard”.

1. Click “Reports” from “Direcory” bar.

2. On the “Command” bar, click “Add”, the “Report Wizard” displays.

3. Click “Next”

P3eCaseStudy - 155

Page 156: 29585169 Projects Cost Management

156

4. Select a subject area, Resources.

5. Click “Next”

6. Select an additional subject area, Activity Notebook.

7. Click “Next”

P3eCaseStudy - 156

Page 157: 29585169 Projects Cost Management

157

8. Select “Resources”

9. Click “Columns”. Choose Resource ID & Resource Name.

10. Add a Filter to the Report:

1. Click “Filter…” and choose as shown

P3eCaseStudy - 157

Page 158: 29585169 Projects Cost Management

158

2. Click Ok, the following window appears:

3. Type a descriptive report title: Case_15: Assigning

Resources to Activities

P3eCaseStudy - 158

Page 159: 29585169 Projects Cost Management

159

4. Click “Next”, the following window appears:

5. Click “Run Report”.

P3eCaseStudy - 159

Page 160: 29585169 Projects Cost Management

160

P3eCaseStudy - 160

Page 161: 29585169 Projects Cost Management

161

Creating a Report Using Current Screen:

The “Report Wizard” can also be used to create reports based on the screen that is currently visible in Primavera.

This enables the User to easily create a wide variety of reports by basing them on the layout of the current screen.

1. Navigate to the “Activities” window.

2. Select & Modify the Current “Layout”.

3. Click “Tools/Report Wizard”

4. In the “Create or Modify Report” window, select “Use Current Screen”.

5. Continue as usual….

P3eCaseStudy - 161

Page 162: 29585169 Projects Cost Management

162

References

Project Management Institute,A Guide to the Project Management Body of KnowledgePMPOK Guide, 2000 Edition

Joseph Phillips,Project Management Professional (PMP)Study Guide

Premavera P6 Project ManagementReference Manual

Abdalla ElDaoushyProjects Time Management & Controlling using Project Management Software, Dec. 2008,Institute of National Planning, Cairo, Egypt

P3eCaseStudy - 162