Copyright © 2013 The Brattle Group, Inc. ISO-NE Offer Review Trigger Prices 2013 Study Final...
-
Upload
montana-swims -
Category
Documents
-
view
218 -
download
3
Transcript of Copyright © 2013 The Brattle Group, Inc. ISO-NE Offer Review Trigger Prices 2013 Study Final...
Copyright © 2013 The Brattle Group, Inc.
ISO-NE Offer Review Trigger Prices 2013 StudyFinal Results
NEPOOL Markets Committee
Sam Newell
September 10, 2013
PRESENTED TO
PRESENTED BY
| brattle.com2
Summary of ORTP Recommendations
Revised Onshore Wind ORTP Calculations
Revised Solar ORTP Calculations
Indices for Future Annual Updates
Next Steps
Agenda
| brattle.com3
Final Recommended ORTP Values
Summary of ORTPs (2018$)
Notes: 1.Overnight costs, fixed O&M, Gross CONE and revenue offsets are calculated based on installed capacities; Net CONE and ORTP values are calculated based on qualified capacities.2.DR categories evaluated at the asset level. Actual resources would be aggregations of at least 100 kW.3.Some values, esp. Onshore Wind, may appear high compared to current costs. These values are in 2018$ and include all cost components (e.g. Onshore Wind is $2,676/kW in 2013$ of which $349/kW is due to interconnection.) 4.FOM includes site leasing costs.5.Revenue Offsets values have been updated from draft results based on current electricity, gas and REC futures.6.Solar revenues are based on MA Class I REC price and not SREC price since SRECs are not available region-wide.7.Net CONE based on Qualified Capacity not applicable if Net CONE Installed is negative and Qualified Capacity is less than Installed Capacity.8.The auction starting price for FCA9 will be determined prior to the auction.
Reference Total Plant Installed Qualified Overnight After-Tax Fixed Gross Revenue Net Net 2018/19 2018/2019Technology Capital Cost Capacity2 Capacity Cost3 WACC O&M4 CONE Offsets5 CONE CONE Final ORTP Draft ORTP
($m) (MW) (MW) ($/kW) (%) ($/kW-mo) ($/kW-mo) ($/kW-mo) ($/kW-mo) ($/kW-mo) ($/kW-mo) ($/kW-mo)
denominator 1 Installed Installed Installed Installed Installed Qualified Qualified Qualified
Combustion Turbine $318 192 192 $1,583 7.2% $2.65 $16.13 $2.71 $13.42 $13.42 $13.42 $13.26
Combined Cycle $878 730 730 $1,108 7.2% $2.33 $12.61 $3.75 $8.87 $8.87 $8.87 $8.75
Onshore Wind $196 60 15 $3,063 7.2% $6.62 $23.89 $27.53 -$3.64 n.a.7 $0.00 $9.87
Solar PV6 $16 6.0 0.9 $2,593 7.2% $4.47 $16.77 $11.27 $5.50 $36.69 Starting Price8 ---
Energy Efficiency n.a. 1.0 1.0 $2,571 7.2% $0.00 $24.39 $25.37 -$0.97 -$0.97 $0.00 $0.00
Large DR n.a. 0.5 0.5 n.a. 7.2% n.a. $1.15 $0.00 $1.15 $1.15 $1.15 $1.15
Mass Market DR n.a. 0.001 0.001 n.a. 7.2% n.a. $7.09 $0.00 $7.09 $7.09 $7.09 $7.09
| brattle.com4
Stakeholders made the following comments:
▀ “Depreciation Schedule should be 5 Year MACRS”
▀ “Qualified Capacity is too low”
▀ “Interconnection costs are too high”
▀ “Capacity Factor is too low due to historically low wind resources and advances in wind turbine technology”
▀ “REC price is too low”
Summary of Feedback on Wind ORTP
| brattle.com5
Qualified Capacity increased based on Seasonal Claimed Capacity values and market rules for intermittent resources
Overnight capital costs reduced due to lower interconnection cost per mile along existing ROW, based on recent Maine 115 kV projects
Capacity factor increased due to efficiency of current turbine models being installed
Depreciation Schedule changed to 5 Year MACRS reflecting current IRS depreciation rules
Wind ORTP will be set at zero as the Net CONE is negative
Wind ORTP Calculation
Differences between Draft and Final explained further on next slide
Draft Final
Installed Capacity MW 60 60Qualified Capacity % 19% 25%Capital Costs (Overnight) $/kW 3,230 3,063Capital Costs (Installed) $/kW 3,441 3,263Capacity Factor % 31% 35%ATWACC % 7.2% 7.2%
Gross CONE $/kW-mo 26.51 23.89Levelized Capital Costs $/kW-mo 37.84 35.72Fixed O&M $/kW-mo 6.73 6.62Depreciation Tax Shield $/kW-mo -12.53 -12.22Tax Credits $/kW-mo -5.53 -6.22
Revenue Offsets $/kW-mo 24.63 27.53E&AS Margins $/kW-mo 13.35 14.94REC Revenue $/kW-mo 11.29 12.60
Net CONE (Installed) $/kW-mo 1.88 -3.64Net CONE (Qualified) $/kW-mo 9.87 n.a.
ORTP $/kW-mo 9.87 0.00
| brattle.com6
0
5
10
15
20
25
30
35
40
$/kW
-mo.
Wind ORTP Draft and Final Comparison
Gross CONEexcl. PTC
Gross CONEexcl. PTC
Non-Capacity Revenueincl. PTC
Non-Capacity Revenueincl. PTC
DRAFTNet CONE = 1.88 $/kW-mo.
FINALNet CONE = -3.64 $/kW-mo.
$32.04$30.16 $30.11
$33.75
$1.93 lower, 75% due to
interconnection and 25% due to Dep. Schedule
$3.59 higher, due to capacity
factor
| brattle.com7
Capacity of 6 MW was chosen based on largest capacity that has been built in MA SREC program and through consultation with a regional solar developer (whose projects in development are 2 – 10 MW)
Capacity factor of 14% was determined from NREL Solar Advisor Model (SAM) data for New England
Qualified capacity of 15% was calculated from values in ISO-NE Seasonal Claimed Capacity database for 8 operating facilities (Summer = 44%, Winter = 0%)
Interconnection voltage of 13 kV is based on recent projects
Solar Technical Specifications
Unit Specifications Solar PV
PV Module Type Polysilicon PV panels, Fixed Tilt, Ground Mounted
Primary Fuel SolarConfiguration 20,000 x 300 WNet Plant Capacity (MW) 6 (DC)Capacity Factor 14%Qualified Capacity 15%Interconnection 13 kVPlot Size (acres) 40Location Massachusetts
| brattle.com8
2013 Overnight Capital Cost of $3,139/kW was developed based on 6 projects beginning operation in 2012 – 2015 with an average capacity of 12 MW and is comparable to publicly available values▀ MA SREC average installed costs for 2012 – 2013 installations >5 MW is $2,940/kW▀ LBNL Tracking the Sun VI 20th Percentile of installed cost for 1-5 MW Fixed-Tilt
Commercial and Utility-Scale Systems is $3,095/kW (in 2013$)
We assume overnight capital costs decline by 6% per year in real terms through 2018▀ LBNL Tracking the Sun VI: Installed Costs have fallen historically by 6 – 7% per year
in real terms▀ NREL/Black and Veatch Study: Installed Costs projected to decline by 3% per year
in real terms
We assume no sales tax due to MA exemption from sales tax for the purchase of solar equipment
Solar Capital Costs
| brattle.com9
Capacity = 6 MW (DC)
Solar Capital Cost Components
Capital Costs2013 Overnight
Costs2013 Overnight
Costs2018 Overnight
Costs(2013 $) (2013 $/kW) (2018 $/kW)
EPC CostsEquipment
Solar PV Modules $8,100,000 $1,350 - Other Equipment $0 $0 -
Construction Labor $2,520,000 $420 - Other Labor $1,020,000 $170 - Materials $2,160,000 $360 - Sales Tax $0 $0 - EPC Contractor Fee $1,380,000 $230 - EPC Contingency $1,518,000 $253 -
Total EPC Costs $16,698,000 $2,783 -
Non-EPC CostsOwner's Costs (Services) $1,169,000 $195 - Electrical Interconnection $300,000 $50 - Gas Interconnection $0 $0 - Emission Reduction Credits $0 $0 - Land $0 $0 - Working Capital and Inventories $167,000 $28 - Owner's Contingency $131,000 $22 - Financing Fees $369,000 $62 -
Total Non-EPC Costs $2,136,000 $356 -
Overnight Capital Costs ($) $18,834,000 $3,139 $2,593
| brattle.com10
Projected E&AS margins were estimated using hourly NREL SAM data for New England (with a capacity factor of 14%) and hourly Mass Hub prices for 2010 – 2012▀ 2010–2012 Average E&AS Margin was $4.97 / kW-mo▀ 2018/2019 Projected E&AS Margin is $6.23 / kW-mo
Assumed contract REC price is the same as for Onshore Wind▀ Assumed 2018/2019 contract REC price is $49/MWh, based on 2016
forwards (updated value based on current futures)▀ Although the MA SREC price (currently $249/MWh) is significantly higher,
we are unable to use SRECs in the ORTP calculation since they are not available region-wide
Solar Revenue Offsets
| brattle.com11
The starting price for FCA9 will be determined prior to the auction
Solar ORTP Calculation (2018$)
Installed Capacity MW 6Qualified Capacity % 15%Capital Costs (Overnight) $/kW 2,593Capital Costs (Installed) $/kW 2,705ATWACC % 7.2%
Gross CONE $/kW-mo 16.77Levelized Capital Costs $/kW-mo 29.61Fixed O&M $/kW-mo 4.47Depreciation Tax Shield $/kW-mo -8.73Tax Credits $/kW-mo -8.58
Revenue Offsets $/kW-mo 11.27E&AS Margins $/kW-mo 6.23REC Revenue $/kW-mo 5.04
Net CONE (Installed) $/kW-mo 5.50Net CONE (Qualified) $/kW-mo 36.69
ORTP $/kW-mo Starting Price
| brattle.com12
Gas Turbines will be indexed to publicly available Bureau of Labor Statistics (BLS) Producer Price Index (PPI)
Construction and Other Labor will be indexed using non-composite indices from BLS Quarterly Census of Employment and Wages (QCEW)
Fuel inventories will be indexed based on GDP Deflator
E&AS revenue will be updated based on futures values for Henry Hub, Algonquin City Gates and Mass Hub On-Peak
Changes to Annual Updates
Cost Component Index
Gas Turbines BLS-PPI "Turbines and Turbine Generator Sets"Steam Turbines BLS-PPI "Turbines and Turbine Generator Sets"Wind Turbines Bloomberg Wind Turbine Price IndexOther Equipment BLS-PPI "General Purpose Machinery and Equipment"Construction Labor BLS-QCEW "Utililty System Construction"Other Labor BLS-QCEW "Power Generation and Supply"Materials BLS-PPI "Materials and Components for Construction"Electric Interconnection BLS-PPI "Electric Power Transmission, Control, and Distribution"Gas Interconnection BLS-PPI "Natural Gas Distribution"Fuel Inventories Gross Domestic Product Deflator
| brattle.com13
End of September ORTP report submitted to ISO-NE
Next Steps