COON CREEK WATERSHED DISTRICT5C6B0F6F-9658... · 2017-11-08 · Item 16: Request to Award Work...
Transcript of COON CREEK WATERSHED DISTRICT5C6B0F6F-9658... · 2017-11-08 · Item 16: Request to Award Work...
Item 16: Request to Award Work Wehmoff Bank Stabilization Project Page 1 of 9
COON CREEK WATERSHED DISTRICT
Request for Board Action
MEETING DATE: November 13, 2017
AGENDA NUMBER: 16
ITEM: Request to Award Work -Wehmoff Bank Stab Project
FISCAL IMPACT: $40,750
POLICY IMPACT: Policy
REQUEST
Review Quotes and Award contract for Wehmoff Bank Stabilization Project
BACKGROUND
On June 25, 2007 the resident at 309 117th Ave NW Coon Rapids (Wehmoff) contacted
the District concerning bank erosion on the property. Staff observed an approximately
250 linear foot eroded bank along four properties (including Wehmoff) of a shaded
outside bend of Sand Creek. Staff recommended the resident attempt vegetating the slope
to encourage deep roots to prevent or at least slow future erosion. Staff also
recommended the resident stop dumping lawn clippings onto the bank. The bank was
surveyed and photographed to monitor the rate of erosion. The site was added to the
Districts list of potential bank stabilization projects in the event vegetation alone did not
stabilize the bank.
As part of the Comprehensive and Capital Improvement planning process, the Wehmoff
Bank Stabilization project was prioritized and budgeted $40,750 for work in 2017 as part
of the District Bank Stabilization Program.
On September 12, 2016 the Board approved the 2017 budget. Including $40,750 for the
Wehmoff Bank Stabilization Project.
At the January 23, 2017 Board meeting the board received an itemization of projects
commencing in 2017 including the Wehmoff Bank Stabilization.
In June 2017 Staff met with the four adjacent properties to discuss the project details. All
residents were willing and excited about a project to address the erosion.
On September 28, 2017 Staff surveyed the site for design. A preliminary design of a
boulder toe bank stabilization project was created. The engineers estimate for the design
is $37,030.00 ($32,200.00 without 15% contingency).
At the October 9, 2017 Board meeting the board authorized staff to seek quotes from pre-
qualified contractors for the project.
Item 16: Request to Award Work Wehmoff Bank Stabilization Project Page 2 of 9
On October 11, 2017 a final design was established including an additional line item for
site grading. All 4 residents executed cooperators agreements with the District. A request
for quotes was sent to 7 prequalified contractors that the District has successfully
contracted with in the past for similar work. The City of Coon Rapids and Wenck were
copied on the request for quotes.
On October 25, 2017 a non-mandatory pre-quote meeting was held onsite. 4 contractors
attended. A representative from the City of Coon Rapids attended. Staff delivered a copy
of the cooperators agreement, final design and request to seek quotes staff report to the 4
residence adjacent to the project for their records.
On November 2, 2017 a quotes were due at noon to the District office. 7 contractors’
submitted quotes.
ISSUES/CONCERNS
Trees removal for site access: The District forester (YTS) will prepare the site access
for the bank stabilization project by removing trees as necessary along the top of slope.
Quote Completeness: Staff reviewed quotes for completeness.
Plan Holder Quote
Signed
Quote Schedule
Filled Out
Information
Required of Quoters
Blackstone Contractors Yes Yes Yes
GF Jedlicki Yes Yes Yes
MN Native Landscapes Yes Yes Yes
Northland Excavating Yes Yes Yes
Peterson Contracting Yes Yes Yes
Rachel Contracting Yes Yes Yes
Sunram Construction Yes Yes Yes
Costs:
Company Quote Rank
Blackstone Contractors $36,220.00 3
GF Jedlicki $43,840.00 6
MN Native Landscapes $36,400.00 4
Northland Excavating $30,275.00 1
Peterson Contracting $52,000.00 7
Rachel Contracting $33,785.00 2
Sunram Construction $36,490.00 5
Engineers Estimate* $32,200.00
Budget $40,750.00
*Excludes site grading and 15% contingency
PRIOR DECISIONS
• September 2016 Project included and approved as part of adopted 2017 budget
Item 16: Request to Award Work Wehmoff Bank Stabilization Project Page 3 of 9
OPTIONS
1. Award contract to lowest responsible bidder
2. Table action until next meeting with statement of reason and need
3. Reject all quotes
RECOMMENDATION
Award contract to Northland Excavating
Item 16: Request to Seek Quotes on Wehmoff Bank Stabilization Project Page 4 of 9
Quote Summary
Estimated
Quantity
Unit Price Unit Price Unit Price Unit Price Unit Price Unit Price Unit Price Unit Price
Item Unit Engineer Blackstone
Contractors
GF
Jedlicki
MN Native
Landscapes
Northland
Excavating
Peterson
Contracting
Rachel
Contracting
Sunram
Construction
Mobilization –
Demobilization (MN
DOT 2021)
LS 1 $2,000.00 $2,500.00 $3,150.00 $1,500.00 $1,280.00 $2,010.00 $5,000.00 $4,750.00
Type V Non-woven
Geotextile Fabric
(MN DOT 3733)
SY 340 $5.00 $3.00 $3.50 $5.00 $3.00 $3.09 $4.00 $2.25
36” Fieldstone
Boulders TON 200 $120.00 $130.00 $134.00 $135.00 $113.00 $103.30 $115.00 $90.00
Erosion Control
Blanket Type 2S, No
Poly Netting (MN
DOT 3876 & 3885)
SY 150 $5.00 $5.00 $4.00 $3.00 $8.00 $6.60 $4.00 $2.50
Seed-MN 34-261
(Amended) SY 150 $5.00 $5.00 $5.00 $3.00 $2.50 $7.70 $3.50 $2.00
Site Grading LS 1 $1,200.00 $5,500.00 $3,800.00 $1,500.00 $20,559.40 $1,650.00 $5,700.00
Site Access
Restoration LS 1 $3,000.00 $4,000.00 $5,850.00 $1,500.00 $2,300.00 $5,575.00 $1,650.00 $6,600.00
$32,200.00 $36,220.00 $43,840.00 $36,400.00 $30,275.00 $52,000.00 $33,785.00 $36,490.00
Item 16: Request to Seek Quotes on Wehmoff Bank Stabilization Project Page 5 of 9
Item 16: Request to Seek Quotes on Wehmoff Bank Stabilization Project Page 6 of 9
2010
2015
Item 16: Request to Seek Quotes on Wehmoff Bank Stabilization Project Page 7 of 9
Item 16: Request to Seek Quotes on Wehmoff Bank Stabilization Project Page 8 of 9
Item 16: Request to Seek Quotes on Wehmoff Bank Stabilization Project Page 9 of 9