Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case...
Transcript of Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case...
![Page 1: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/1.jpg)
Construction Risks at Stampede DamThird Workshop on Case Histories in Dam Safety Risk-Informed Decision Making
3 May 2018
![Page 2: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/2.jpg)
“For the strength of the Pack is the Wolf, and strength of Wolf is the Pack” – Rudyard Kipling
The Law of the Jungle – The Jungle Book
![Page 3: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/3.jpg)
ACKNOWLEDGEMENTS
•Steve Dominic•Frank Dworak•Kathleen Holman•Kyle Hughes•Jeanne Major•Elizabeth Ouellette•Miguel Rocha •Scott Schoenfeld•Chris Slaven
![Page 4: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/4.jpg)
PRESENTATION OVERVIEW
1. Purpose, Context and Scope2. Baseline Risk Assessment3. Risk Reduction Assessment4. Limitations, Decisions, Risk Communication
and Lessons Learned
![Page 5: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/5.jpg)
1. PURPOSE, CONTEXT ANDSCOPE
![Page 6: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/6.jpg)
Dam(Completed 1970)
Dike
Spillway and Outlet Works
Primary Borrow Area
1.1 PURPOSE OF THE RISK ASSESSMENT
![Page 7: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/7.jpg)
1.1 PURPOSE OF THE RISK ASSESSMENT
Independence Creek Independence Camp Independence Lake Elevation 6436 feet Elevation 6980 feet Elevation 8338 feet
Water Year Max March SWE
Water Year Max March SWE
Water Year Max March SWE
2011 30 1983 45.3 2017 74.71993 25.6 1995 36.9 1995 70.11983 25.5 2011 35 2011 681995 24.4 1993 34.8 1983 66.31986 23.5 1986 30 1982 60.31999 22.4 1998 29.3 1999 59.51998 21.9 1999 27.2 1993 592005 21.3 1982 25.7 1986 54.92017 20.7 1980 25.1 1997 54.71985 19.8 2017 25.1 1998 53.4
88.73% Basin 5.63% Basin
Elev. < 6000 ft – d 5.64% Basin
Snotel (Snowpack Telemetry)
![Page 8: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/8.jpg)
1.1 PURPOSE OF THE RISK ASSESSMENT
2004
Risk Assessment:Increasing Justification to Reduce Risks
2010
Corrective Action Study
2012
Final Design for Dam Safety Modifications
2016
Contract Awarded
2016/2017
Record Snowpack
2017
Decision
![Page 9: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/9.jpg)
1.2 CONTEXT FOR THE RISK ASSESSMENT
•Reclamation Dam Safety Triad• Dam Safety Office• Region Office• Area Office
•Reclamation Public Protection Guidelines• Annualized Failure Probability: 1E-04• Annualized Life Loss: 1E-03
•Dam safety case claim
![Page 10: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/10.jpg)
1.2 CONTEXT FOR THE RISK ASSESSMENT
CR
Comprehensive Review:Screening-Level RA
IE
Issue Evaluation: Refinement of Risks
CAS
Corrective Action Study:Alternative Evaluation
FD
Final Designs of Dam Safety Modification
DesignSpecificationsConstruction RA
Construction EAPCountermeasures
Simplified Dam Safety Process
![Page 11: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/11.jpg)
1.2 CONTEXT FOR THE RISK ASSESSMENT
• Temporarily increased risks result from the construction activities; however, construction activities are necessary to achieve long term risk reduction
• We will accept the temporary increase in risks
![Page 12: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/12.jpg)
1.3 SCOPE OF THE RISK ANALYSIS
•Outcome desired: approval from the Triad•Potential Failure Mode: Overtopping during a flood event
• Initiating event: Large floods caused by atmospheric Rivers under construction conditions
• Uncertainty: relationship between large floods and seasonal floods
![Page 13: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/13.jpg)
1.3 SCOPE OF THE RISK ANALYSIS
100-year events Final Design
![Page 14: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/14.jpg)
1.3 SCOPE OF THE RISK ANALYSIS
•Purpose: Reduce risks associated with hydrologic overtopping PFM
•Modification components:• Embankment raises to increase flood storage capacity
• Dam• Dike• Construction of freeboard dikes
• Spillway crest structure modification
![Page 15: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/15.jpg)
2. BASELINE RISKASSESSMENT
![Page 16: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/16.jpg)
2.1 POTENTIAL FAILURE MODESIDENTIFICATION
•Single PFM impacted by construction activities: increased risks of overtopping temporarily.
![Page 17: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/17.jpg)
MSE Crest Raise
Existing Dam/Dike
Existing Dam Crest
• Constructing dam and dike crest raise by mechanically stabilized earth (MSE) constr. methods.
2.1 POTENTIAL FAILURE MODESIDENTIFICATION
![Page 18: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/18.jpg)
• Replacing spillway crest structure; headwall to limit peak spillway discharges during the IDF to 3,000 ft3/s.
Existing ModifiedOrifice Opening
Headwall
Existing Crest Structure (to be replaced)
2.1 POTENTIAL FAILURE MODESIDENTIFICATION
![Page 19: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/19.jpg)
2.2 EVALUATION AGAINST DAM SAFETYSTANDARDS
• It is difficult to evaluate construction risks within the standard annualized framework
• Conditions are temporary• Loading ranges can vary
• Atmospheric river season is not construction season
•Tracking risk with construction schedule
![Page 20: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/20.jpg)
2.3 RISK MODEL FORM
•Event trees to estimate annual failure probability• 2012 trees used full range of starting RWS elevations• 2017 trees needed to account for the forecast RWS
elevations• Impacts to downstream reservoirs were assessed
• System flood routings
![Page 21: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/21.jpg)
2.4 ESTIMATION OF LOAD PROBABILITIES
• Overtopping by more frequent floods• No spillway operation during 2017 construction season• Crest Excavation to an elevation 5 feet below existing
Initial RWS El. ToJUInitial RWS El. ToA
Existing Dam/Dike Crest El.
Excavated Dam/Dike Crest El.
![Page 22: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/22.jpg)
2.5 ESTIMATION OF SYSTEM RESPONSEPROBABILITIES
•Flood hydrographs and routings accounted for the reservoir downstream and the intervening area
• Risk estimates were not made for the downstream reservoir
• Designers considered flood routing results to guard against overtopping
![Page 23: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/23.jpg)
2.6 ESTIMATION OF CONSEQUENCES
•Consequences: life loss•Factors taken into account
• Breach outflow• Inundation area• Flood severity• Warning times
![Page 24: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/24.jpg)
2.7 EXISTING DAM RISK ESTIMATES ANDTOLERABLE RISK EVALUATION
•Time history of risk with construction schedules• 2012: Strict Annualized Life Loss• 2017: Updated annualized life loss accounting for
anticipated reservoir operations
![Page 25: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/25.jpg)
2.7 EXISTING DAM RISK ESTIMATES ANDTOLERABLE RISK EVALUATION
Pre Project Crest El.
Required Ex.
Actual RWS El.
Projected RWS El.
CofferdamConstruction
Cofferdam
Spillway CrestRemove Cofferdam
Embankment Section Lowered
Min Crest El.
Projected Max. 2,000-yr.
Emba
nkm
ent a
nd R
WS
Elev
atio
ns
Project Schedule
![Page 26: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/26.jpg)
2.7 EXISTING DAM RISK ESTIMATES ANDTOLERABLE RISK EVALUATION
Pre Project Crest El.
Required Ex.
Actual RWS El.
Projected RWS El.
CofferdamConstruction
Cofferdam
Spillway CrestRemove Cofferdam
Embankment Section Lowered
Min Crest El.
Projected Max. 2,000-yr.
![Page 27: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/27.jpg)
2.7 EXISTING DAM RISK ESTIMATES ANDTOLERABLE RISK EVALUATION
Baseline ALL
Post-Construction ALL
Winter Shutdown MSE Dam - Completed
MSE Dike - Excavated
MSE Dike -Res. Exist.
2012 Construction Risk Estimates
MSE Dam - Excavated
MSE Dam - Res. Exist.
HJE35
![Page 28: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/28.jpg)
Slide 27
HJE35 baseline flood protection? 2012 flood protection? no need to plot, but discuss.Huggins, Jennifer E, 4/5/2018
![Page 29: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/29.jpg)
2.7 EXISTING DAM RISK ESTIMATES ANDTOLERABLE RISK EVALUATION
Baseline ALL
Post-Construction ALL
Spillway Demo
Winter ShutdownMSE Dam - CompletedSeasonal
Hydrograph Estimate
Seasonal HydrographEstimate
MSE Dike - Excavated
MSE Dike -Res. Exist.
MSE Dike -Completed
2012 Construction Risk EstimatesMSE Dam - Excavated
2017 Construction Risk Estimates
MSE Dam - Res. Exist.
HJE22
![Page 30: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/30.jpg)
Slide 28
HJE22 work through this, talking thru black, then blue, then red.Huggins, Jennifer E, 4/5/2018
![Page 31: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/31.jpg)
2.7 EXISTING DAM RISK ESTIMATES ANDTOLERABLE RISK EVALUATION
![Page 32: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/32.jpg)
2.8 INSIGHTS AND RECOMMENDATIONS
•Risks increase from 2012 to 2017: higher starting RWS elevations
•Routing results are conservative• Annual Rain on snow storms• Large events driven by atmospheric rivers
•Risk refinement: season construction hydrographs
![Page 33: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/33.jpg)
3. RISK REDUCTIONASSESSMENT
![Page 34: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/34.jpg)
3.1 IDENTIFICATION OF RISK REDUCTIONALTERNATIVES
•Factors that Reduce risk• Increased Presence at the dam• Construction Emergency Action Plan (CEAP)
• Interventions• Emergency
• Backfill any excavated embankments• Cofferdam Breach for spillway releases
• Non-Emergency• Management of RWS elevation through outlet works operations
![Page 35: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/35.jpg)
3.1 IDENTIFICATION OF RISK REDUCTIONALTERNATIVES
•Developed by team in 2012 (updated 2017)• Region & Area office• Construction office• TSC • DSO
• Identifies RWS elevations for• More frequent monitoring
• Cofferdam• Reservoir operations
• Notification of officials
![Page 36: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/36.jpg)
3.2 REPRESENTATION OF RISK REDUCTIONALTERNATIVES IN RISK MODEL
• Increase freeboard• Increase release capacity
![Page 37: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/37.jpg)
3.2 REPRESENTATION OF RISK REDUCTIONALTERNATIVES IN RISK MODEL
•Non-Emergency Intervention: Managing reservoir for increased storage
• Hydraulic modeling• Advanced Draw-down
![Page 38: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/38.jpg)
3.2 REPRESENTATION OF RISK REDUCTIONALTERNATIVES IN RISK MODEL
Emergency intervention to increase freeboardSuperSacks to Backfill excavated areas
http://www.bigbagsusa.com/cofferdam/index.asphttp://www.bigbagsusa.com/construction-barriers/FIBC/bulk-bags/index.asp
![Page 39: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/39.jpg)
3.2 REPRESENTATION OF RISK REDUCTIONALTERNATIVES IN RISK MODEL
![Page 40: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/40.jpg)
3.2 REPRESENTATION OF RISK REDUCTIONALTERNATIVES IN RISK MODEL
![Page 41: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/41.jpg)
3.2 REPRESENTATION OF RISK REDUCTIONALTERNATIVES IN RISK MODELEmergency Intervention: Breach of Cofferdam for Increased release capacity
Field Condition Factors for Consideration• Cofferdam crest < des.
El., Existing Spillway Functional
• Existing spillway discharge• Outflows from Stampede Dam could
combine with intervening inflows to Boca and exceed Boca’s release capacity.
• Cofferdam at des. elevation, Existing Spillway demolished
• Releases would not be controlled by a spillway crest
• Flows would pass directly over the tuff breccia bedrock.
• Cofferdam at des. Elevation, New Crest Structure Partially Complete
• Erosion of embankment or bedrock materials could Initiate
• Release capacity at Boca could be exceeded
![Page 42: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/42.jpg)
3.3 RISK ESTIMATES AND TOLERABLE RISKEVALUATION FOR ALTERNATIVES
Without any intervention, we have 2,000-year storm protection
![Page 43: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/43.jpg)
4. LIMITATIONS, DECISIONS, RISK COMMUNICATION ANDLESSONS LEARNED
![Page 44: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/44.jpg)
4.1 LIMITATIONS
•Fruit Salad• Typical RIDM: Annualized• Construction: Seasonal
![Page 45: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/45.jpg)
4.2 DECISION AND RISK MANAGEMENTRECOMMENDATIONS
•Accept temporarily increased construction risks to achieve long-term risk reduction
![Page 46: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/46.jpg)
4.3 RISK COMMUNICATION
•Within Reclamation• Decision makers
• DSAT• DD/TROF (approval from Triad)
• Field office Design office•With Contractor
• CEAP• COR
![Page 47: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/47.jpg)
4.4 LESSONS LEARNED
•Would we estimate construction risks differently in retrospect?
• No• Sensitivity Studies
•Reassessing construction risks of value to Dam Safety Office
![Page 48: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/48.jpg)
“Wash daily from nose tip to tail tip; drink deeply, but never too deep;And remember the night is for hunting and forget not the day is for sleep.” – Rudyard Kipling
The Law of the Jungle – The Jungle Book
![Page 49: Construction Risks at Stampede Dam - USSDConstruction Risks at Stampede Dam Third Workshop on Case Histories in Dam Safety Risk-Informed Decision Making ... 2011 30 1983 45.3 2017](https://reader036.fdocuments.net/reader036/viewer/2022070812/5f0b39bd7e708231d42f772d/html5/thumbnails/49.jpg)
Jen Huggins, P.E.Jen Huggins, P.E.