Construction Dewatering Means and Methods Presentation

172

Click here to load reader

description

This presentation was given by David Giles at the University of Houston Cullen College of Engineering.

Transcript of Construction Dewatering Means and Methods Presentation

Page 1: Construction Dewatering Means and Methods Presentation

Construction Dewatering

Getting Your Project on Firm Ground……Before It Starts

Page 2: Construction Dewatering Means and Methods Presentation

Introduction

• David Giles– Co-Founder/Managing Partner: TerraFirma Earth

Technologies, Ltd.

• Overview of Construction Dewatering– Giving guidance to those directly or indirectly

involved in the planning, design, supervision, construction and operation of dewatering systems.

Page 3: Construction Dewatering Means and Methods Presentation

Topics of Discussion

• Construction Dewatering– What is it?– Why do it?

• The Consequences of Improper Dewatering• Design Considerations• Subsurface Investigations and Soil Borings• Methods of Groundwater Control• Case Studies

Page 4: Construction Dewatering Means and Methods Presentation

Topics of Discussion

• Construction Dewatering– What is it?– Why do it?

Page 5: Construction Dewatering Means and Methods Presentation

Dewatering: What is it?Intercepting/minimizing groundwater seepage from entering an

excavation.

Depressing the piezometric water surface to a point below the excavation.

Page 6: Construction Dewatering Means and Methods Presentation

Topics of Discussion

• Construction Dewatering– What is it?– Why do it?

Page 7: Construction Dewatering Means and Methods Presentation

Dewatering: Why do it?

Short Term Objectives(Temporary Systems)

• Intercept Seepage– Increase slope stability– Prevent loss of material

• Reduce lateral/uplift pressure

• Improve the excavation and the backfill characteristics of the excavation to allow construction to proceed in a safe and eficient manner

Long Term Objectives(Permanent Systems)

• Reduce or eliminate lateral and/or uplift pressures

• Achieve waterproofing objectives

Page 8: Construction Dewatering Means and Methods Presentation

Improper Dewatering

The Consequences• Blows, Rendering Excavation Subgrade

Unstable• Boils/Piping, the Creation of Voids Rendering

Slopes and Subgrades Unstable• Excavation Support Systems Rendered Unstable• Future Settling• Lost Time• Decreased Worksite Safety• Increased Cost

Page 9: Construction Dewatering Means and Methods Presentation

Improper Dewatering

The Consequences• Blows, Rendering Excavation Subgrade Unstable• Boils/Piping, the Creation of Voids Rendering

Slopes and Subgrades Unstable• Excavation Support Systems Rendered Unstable• Future Settling• Lost Time• Decreased Worksite Safety• Increased Cost

Page 10: Construction Dewatering Means and Methods Presentation

Improper Dewatering

The Consequences• Blows, Rendering Excavation Subgrade Unstable• Boils/Piping, the Creation of Voids Rendering

Slopes and Subgrades Unstable• Excavation Support Systems Rendered Unstable• Future Settling• Lost Time• Decreased Worksite Safety• Increased Cost

Page 11: Construction Dewatering Means and Methods Presentation

Improper Dewatering

The Consequences• Blows, Rendering Excavation Subgrade Unstable• Boils/Piping, the Creation of Voids Rendering

Slopes and Subgrades Unstable• Excavation Support Systems Rendered Unstable• Future Settling• Lost Time• Decreased Worksite Safety• Increased Cost

Page 12: Construction Dewatering Means and Methods Presentation

Improper Dewatering

The Consequences• Blows, Rendering Excavation Subgrade Unstable• Boils/Piping, the Creation of Voids Rendering

Slopes and Subgrades Unstable• Excavation Support Systems Rendered Unstable• Future Settling• Lost Time• Decreased Worksite Safety• Increased Cost

Page 13: Construction Dewatering Means and Methods Presentation

Improper Dewatering

Page 14: Construction Dewatering Means and Methods Presentation

Rio Grande River Crossing, Albuquerque, NM

Page 15: Construction Dewatering Means and Methods Presentation

Improper Dewatering Proper Dewatering

42” Gas Pipeline, Blythe, CA

Page 16: Construction Dewatering Means and Methods Presentation

Topics of Discussion

• The Origins of Dewatering• Construction Dewatering

– What is it?– Why do it?

• The Consequences of Improper Dewatering• Design Considerations• Subsurface Investigations and Soil Borings• Methods of Groundwater Control• Case Studies

Page 17: Construction Dewatering Means and Methods Presentation

Design Considerations

Dominant Considerations• Location and Geologic Environment• Size and Depth of Excavation• Groundwater (Piezometric) Level• Soil & Aquifer Characteristics (Hydraulic Conductivity)• Proposed Excavation Method and Excavation Support• Proposed Schedule• Proximity to Existing Structures, Potable and/or Irrigation

Wells, Potential Sources of Recharge• Nature of any On/Off-site Contamination

Page 18: Construction Dewatering Means and Methods Presentation

Design Considerations

Dominant Considerations• Location and Geologic Environment• Size and Depth of Excavation• Groundwater (Piezometric) Level• Soil & Aquifer Characteristics (Hydraulic Conductivity)• Proposed Excavation Method and Excavation Support• Proposed Schedule• Proximity to Existing Structures, Potable and/or Irrigation

Wells, Potential Sources of Recharge• Nature of any On/Off-site Contamination

Page 19: Construction Dewatering Means and Methods Presentation

Design Considerations

Dominant Considerations• Location and Geologic Environment• Size and Depth of Excavation• Groundwater (Piezometric) Level• Soil & Aquifer Characteristics (Hydraulic Conductivity)• Proposed Excavation Method and Excavation Support• Proposed Schedule• Proximity to Existing Structures, Potable and/or Irrigation

Wells, Potential Sources of Recharge• Nature of any On/Off-site Contamination

Page 20: Construction Dewatering Means and Methods Presentation

Depth to Water & the Piezometer

Page 21: Construction Dewatering Means and Methods Presentation

Design Considerations

Dominant Considerations• Location and Geologic Environment• Size and Depth of Excavation• Groundwater (Piezometric) Level• Soil & Aquifer Characteristics (Hydraulic Conductivity)• Proposed Excavation Method and Excavation Support• Proposed Schedule• Proximity to Existing Structures, Potable and/or Irrigation

Wells, Potential Sources of Recharge• Nature of any On/Off-site Contamination

Page 22: Construction Dewatering Means and Methods Presentation

Hydraulic Conductivity (K)

“K” can simply be defined as the ease at which water moves through soil.

More specifically defined by D’Arcy’s Law

Q=KA(h/L) Q = Quantity of Water Flow K = Permeability of Soil A = Cross-sectional Area h = Friction Loss in Distance L

Page 23: Construction Dewatering Means and Methods Presentation

Estimating PermeabilityVisual Classification (USCS)Soil Classification Hydraulic Conductivity(USCS) gpd/ft2 μ/secClay (CL) .02-.0002 .1-.0001Silt (ML) 1-2 .5-1Clayey Sand (SC) 2-20 1-10Silty Sand (SM) 20-100 10-50Well Graded Sand ( ) 20-2000 10-1000Uniform Sand (SP) 100-4000 50-2000Well Graded Gravel (GW) 1000-6000 500-3000Uniform Gravel (GP) 4000-20000 2000-10000Open Work Gravel 20000+ 10000+

J. Patrick Powers

Page 24: Construction Dewatering Means and Methods Presentation

Design Considerations

Dominant Considerations• Location and Geologic Environment• Size and Depth of Excavation• Groundwater (Piezometric) Level• Soil & Aquifer Characteristics (Hydraulic Conductivity)• Proposed Excavation Method and Excavation Support• Proposed Schedule• Avoiding Undesirable Side Effects

– Proximity to Existing Structures, Potable and/or Irrigation Wells– Nature of any On/Off-site Contamination

Page 25: Construction Dewatering Means and Methods Presentation

Design Considerations

Dominant Considerations• Location and Geologic Environment• Size and Depth of Excavation• Groundwater (Piezometric) Level• Soil & Aquifer Characteristics (Hydraulic Conductivity)• Proposed Excavation Method and Excavation Support• Proposed Schedule• Avoiding Undesirable Side Effects

– Proximity to Existing Structures, Potable and/or Irrigation Wells– Nature of any On/Off-site Contamination

Page 26: Construction Dewatering Means and Methods Presentation

Design Considerations

Dominant Considerations• Location and Geologic Environment• Size and Depth of Excavation• Groundwater (Piezometric) Level• Soil & Aquifer Characteristics (Hydraulic Conductivity)• Proposed Excavation Method and Excavation Support• Proposed Schedule• Avoiding Undesirable Side Effects

– Proximity to Existing Structures, Potable and/or Irrigation Wells, and potential sources of recharge

– Nature of any On/Off-site Contamination

Page 27: Construction Dewatering Means and Methods Presentation

Design Considerations

Dominant Considerations• Location and Geologic Environment• Size and Depth of Excavation• Groundwater (Piezometric) Level• Soil & Aquifer Characteristics (Hydraulic Conductivity)• Proposed Excavation Method and Excavation Support• Proposed Schedule• Avoiding Undesirable Side Effects

– Proximity to Existing Structures, Potable and/or Irrigation Wells, and potential sources of recharge

– Nature of any On/Off-site Contamination

Page 28: Construction Dewatering Means and Methods Presentation

Topics of Discussion

• Construction Dewatering– What is it?– Why do it?

• The Consequences of Improper Dewatering• Design Considerations• Subsurface Investigations and Soil Borings• Methods of Groundwater Control• Case Studies

Page 29: Construction Dewatering Means and Methods Presentation

Subsurface Investigations

Page 30: Construction Dewatering Means and Methods Presentation

Typical Bore Log for Pump House, Fulton, Arkansas

Page 31: Construction Dewatering Means and Methods Presentation

Topics of Discussion

• Construction Dewatering– What is it?– Why do it?

• The Consequences of Improper Dewatering• Design Considerations• Subsurface Investigations and Soil Borings• Methods of Groundwater Control• Case Studies

Page 32: Construction Dewatering Means and Methods Presentation

Dewatering Methods

• Open Pumping• Pre-Drainage

– Wellpoints– Deepwells– Eductors

• Methods of Cutoff– Soil Bentonite– Interlocking Steel Sheet Pile– Concrete Caisson

Page 33: Construction Dewatering Means and Methods Presentation

Open Pumping

Favorable Conditions:• Dense, Well Graded Soils, Some Cementation/Cohesiveness• Firm Clays, Few Sand/Silt Lenses Unconnected Hydraulically• Hard Fissured Rock• Low Dewatering Head• Remote Source of Recharge• Open Cut, Relatively Flat Slopes, Minimal Depth Below GW

Table• Steel Interlocking Sheet Pile, Concrete Caisson

Page 34: Construction Dewatering Means and Methods Presentation

Dewatering Methods• Open Pumping• Pre-Drainage

– Wellpoints– Deepwells– Eductors

• Methods of Cutoff– Soil Bentonite– Interlocking Steel Sheet

Pile– Concrete Caisson

Page 35: Construction Dewatering Means and Methods Presentation

Vacuum Wellpoints

Key System Components:• Vacuum Pump• Suction Header• Wellpoint• Swingjoint• Discharge Pipe

Traditional Rotary Lode Vacuum Wellpoint Pump 8”, Diesel Driven

Accessories: wellpoint, swingjoint, header pipe

Page 36: Construction Dewatering Means and Methods Presentation

Vacuum Wellpoints

Page 37: Construction Dewatering Means and Methods Presentation

Vacuum WellpointsFavorable Conditions:• Wide Ranging Soil Types• Impervious Clay/Rock At or Near Subgrade• Highly Stratified Soil• Wide Ranging Permeability• Remote or Proximate Sources of Recharge• Excavations <= 20’; Greater than 20’ requires the use of multiple stages• Rapid Drawdown Required

Page 38: Construction Dewatering Means and Methods Presentation

Dewatering Methods

• Open Pumping• Pre-Drainage

– Wellpoints– Deepwells– Eductors

• Methods of Cutoff– Soil Bentonite– Interlocking Steel Sheet Pile– Concrete Caisson

Page 39: Construction Dewatering Means and Methods Presentation

Deepwells

Key System Components:• Well Assembly

– Well Screen\Casing– Filter Media

• Pump Assembly– Submersible Pump\Motor– Discharge Column Pipe

• Pump Control Panel• Electrical Distribution• Discharge Pipe

Page 40: Construction Dewatering Means and Methods Presentation

Deepwells

12” SDR 26 Well Screen

24” Sch 40 Stainless Steel Well Screen/Casing

Page 41: Construction Dewatering Means and Methods Presentation

Deepwells

20 HP Submersible Pump and Motor

Page 42: Construction Dewatering Means and Methods Presentation

Deepwells

Page 43: Construction Dewatering Means and Methods Presentation

DeepwellsFavorable Conditions:• Sands and Gravels Extending

Well Below Subgrade• Uniform Soil• Moderate to High

Permeability• Open Cut or Vertical/Shored,

Excavations of Any Depth• Long Draw Down Times

Acceptable

Page 44: Construction Dewatering Means and Methods Presentation

Dewatering Methods

• Open Pumping• Pre-Drainage

– Wellpoints– Deepwells– Eductors

• Methods of Cutoff– Soil Bentonite– Interlocking Steel Sheet Pile– Concrete Caisson

Page 45: Construction Dewatering Means and Methods Presentation

Eductor SystemKey System Components:• Well Assembly

– Well Screen/Casing– Filter Media

• Eductor Assembly• High Pressure

Recirculation Pump• Supply/Return Headers• Recirculation Tank• Discharge Pipe

Page 46: Construction Dewatering Means and Methods Presentation

Eductor System

Eductor Body

Page 47: Construction Dewatering Means and Methods Presentation

Eductor System

Eductor Wellhead and Headers

Page 48: Construction Dewatering Means and Methods Presentation

Eductor SystemFavorable Conditions:• Silty and Clayey Sand• Highly Stratified Soil• Impervious Clay/Rock At or

Near Subgrade• Low Permeability Soils• Excavation Depths Not

Limited• Rapid Draw Down Times

Required

Page 49: Construction Dewatering Means and Methods Presentation

Dewatering Methods

• Open Pumping• Pre-Drainage

– Wellpoints– Deepwells– Eductors

• Methods of Cutoff– Soil Bentonite– Interlocking Steel Sheet Pile– Concrete Caisson

Page 50: Construction Dewatering Means and Methods Presentation

Cut-Off WallFavorable Conditions:• Impervious Clay/Rock At or

Near Subgrade• Proximate Sources of

Recharge• Close Proximity to Existing

Structures• Close Proximity to

Contamination Plume• Properly Designed Cut-off

Wall can Function as Ground Support

Materials Utilized…– Soil Bentonite– Cement/Bentonite– Concrete Caisson– Interlocking Steel Sheet Piling

Stop seepage into an excavation, where excavation encroaches upon or penetrates an impervious stratum

Page 51: Construction Dewatering Means and Methods Presentation

Cut-Off Wall

Soil Bentonite Mixing Station and Trenching Activities

Page 52: Construction Dewatering Means and Methods Presentation

Topics of Discussion

• The Origins of Dewatering• Construction Dewatering

– What is it?– Why do it?

• The Consequences of Improper Dewatering• Design Considerations• Subsurface Investigations and Soil Borings• Methods of Groundwater Control• Case Studies

Page 53: Construction Dewatering Means and Methods Presentation

Case Studies• San Juan Chama Drinking Water Project (SJCDWP)

– Install (2) two 54” Pipelines under the Rio Grande River• Bayport Terminal Complex – Port of Houston

– Container Loading/Off Loading Facility– Cruise Ship Terminal

• Denver Justice Center, Down Town Denver• Environmental Retrofit Program – Luminant Generation• US 93 Wickenburg Bypass• Beaver Dam Road Reconstruction Project• Trinity Rural WSC Water Treatment Plant

Page 54: Construction Dewatering Means and Methods Presentation

Dimensions– Length 1100 ft– Width 110 ft– Depth 26 ft

Excavation Type: Open CutGeology: Typical River Deposits (Well Graded Sands, gravel, cobbles, boulders)Depth to Water: at surface

Design Considerations

(Installing Dual 54” WL Beneath the Rio Grande River)

San Juan Chama Drinking Water Project

General Contractor: AUI, Inc.

Page 55: Construction Dewatering Means and Methods Presentation

San Juan Chama Drinking Water Project

System Description

Deep Wells: 12” (30” BH), Spaced Approximately 50 – 75 ft apart, extending 75 ft bgs

62 Deep Total

Powered by 20 hp, 600 GPM Each

Initial Flow Rate: Measured at approx 12,000 GPM (10 – 12 running at any one time

Results: Dropped Water 5 ft Below Pipe Subgrade

Page 56: Construction Dewatering Means and Methods Presentation

San Juan Chama Drinking Water Project

Portable Coffer Dam Construction

Page 57: Construction Dewatering Means and Methods Presentation

San Juan Chama Drinking Water Project

Portable Coffer Dam Construction

Page 58: Construction Dewatering Means and Methods Presentation

San Juan Chama Drinking Water Project

Completed Portable Coffer Dam Construction

Page 59: Construction Dewatering Means and Methods Presentation

San Juan Chama Drinking Water Project

Drilling Operation

Page 60: Construction Dewatering Means and Methods Presentation

San Juan Chama Drinking Water Project

Drilling Operation

Page 61: Construction Dewatering Means and Methods Presentation

San Juan Chama Drinking Water Project

Drilling Spoils

Page 62: Construction Dewatering Means and Methods Presentation

San Juan Chama Drinking Water Project

Setting of the 12” Well Materials

Page 63: Construction Dewatering Means and Methods Presentation

San Juan Chama Drinking Water Project

Gravel Packing the Well

Page 64: Construction Dewatering Means and Methods Presentation

San Juan Chama Drinking Water Project

Filter Media

Page 65: Construction Dewatering Means and Methods Presentation

San Juan Chama Drinking Water Project

Well Development

Page 66: Construction Dewatering Means and Methods Presentation

Pump Setting

San Juan Chama Drinking Water Project

Page 67: Construction Dewatering Means and Methods Presentation

San Juan Chama Drinking Water Project

Common Discharge Piping/Manifold

Page 68: Construction Dewatering Means and Methods Presentation

San Juan Chama Drinking Water Project

Lateral Seepage AlongCemented Cobble Layer

Pipe Installation – Successfully Dewatered Excavation

Page 69: Construction Dewatering Means and Methods Presentation

Pipe Laying Activities – Ideal Conditions

San Juan Chama Drinking Water Project

Page 70: Construction Dewatering Means and Methods Presentation

San Juan Chama Drinking Water Project

Finished Excavation

Page 71: Construction Dewatering Means and Methods Presentation

Well Removal/Abandonment

San Juan Chama Drinking Water Project

Page 72: Construction Dewatering Means and Methods Presentation

San Juan Chama Drinking Water Project

Breach of Portable cofferdam

Page 73: Construction Dewatering Means and Methods Presentation

Breach of Portable Coffer Dam

San Juan Chama Drinking Water Project

Page 74: Construction Dewatering Means and Methods Presentation

Case Studies• San Juan Chama Drinking Water Project (SJCDWP)

– Install (2) two 54” Pipelines under the Rio Grande River• Bayport Terminal Complex – Port of Houston

– Container Loading/Off Loading Facility– Cruise Ship Terminal

• Denver Justice Center, Down Town Denver• Environmental Retrofit Program – Luminant Generation• US 93 Wickenburg Bypass• Beaver Dam Road Reconstruction Project• Trinity Rural WSC Water Treatment Plant

Page 75: Construction Dewatering Means and Methods Presentation

Bayport Terminal – Port of Houston

• Dimensions– Length 2100ft– Width 200ft– Depth 62ft (-) 56 msl

Excavation Type: Open CutGeology: Beaumont Formation (Clays, Sands, Silts)

Depth to Water: 13’ BGS (+) 3 msl

Design Considerations

General Contractor: Zachry Construction Corporation

Page 76: Construction Dewatering Means and Methods Presentation

Bayport Terminal – Port of Houston

Page 77: Construction Dewatering Means and Methods Presentation

System Description Deep Wells: 8” (30”

BH), Spaced Approx. 75 ft apart, extending 80 ft bgs

Sand Drains: 2” (6” BH) – 2 between ea. pumping well

65 Deep Wells Total 130 Sand Drains Powered by 5 hp, 60

GPM EA Initial Flow Rate:

Estimated at approx 3600 GPM (10 – 12 running at any one time

Results: Dropped Water 45 ft from its original level

Bayport Terminal – Port of Houston

Page 78: Construction Dewatering Means and Methods Presentation

Bayport Terminal – Port of Houston

Deepwell and Sand Drain Detail

Page 79: Construction Dewatering Means and Methods Presentation

Bayport Terminal – Port of Houston

Drilling of Sand Drains – Mud Rotary Method

Page 80: Construction Dewatering Means and Methods Presentation

Bayport Terminal – Port of Houston

Drilling of Deepwells – Bucket Auger Method

Page 81: Construction Dewatering Means and Methods Presentation

Bayport Terminal – Port of Houston

Night Time Drilling and Well Placement

Page 82: Construction Dewatering Means and Methods Presentation

Bayport Terminal – Port of Houston

Gravel Packing the Deepwell

Page 83: Construction Dewatering Means and Methods Presentation

Bayport Terminal – Port of Houston

Pump Assembly, Pre-Wiring

Page 84: Construction Dewatering Means and Methods Presentation

Bayport Terminal – Port of Houston

Pumping Setting

Page 85: Construction Dewatering Means and Methods Presentation

Bayport Terminal – Port of Houston

Pump Setting Discharge Installation

Page 86: Construction Dewatering Means and Methods Presentation

Bayport Terminal – Port of Houston

Completed Well Heads (rigid/flexible)

Page 87: Construction Dewatering Means and Methods Presentation

Bayport Terminal – Port of Houston

Completed – Dewatering System

Page 88: Construction Dewatering Means and Methods Presentation

Bayport Terminal – Port of Houston

Excavation Beneath Deck, Between Drilled Piers

Page 89: Construction Dewatering Means and Methods Presentation

Bayport Terminal – Port of Houston

Discharge

Page 90: Construction Dewatering Means and Methods Presentation

Bayport Terminal – Port of Houston

Discharge

Page 91: Construction Dewatering Means and Methods Presentation

Case Studies• San Juan Chama Drinking Water Project (SJCDWP)

– Install (2) two 54” Pipelines under the Rio Grande River• Bayport Terminal Complex – Port of Houston

– Container Loading/Off Loading Facility– Cruise Ship Terminal

• Denver Justice Center, Down Town Denver• Environmental Retrofit Program – Luminant Generation• US 93 Wickenburg Bypass• Beaver Dam Road Reconstruction Project• Trinity Rural WSC Water Treatment Plant

Page 92: Construction Dewatering Means and Methods Presentation

Design Considerations:Dimensions

– Length 250 ft– Width 250 ft– Depth 28 ft

Excavation Type: H-Pile and Wood Lagging

Geology: well graded sands, gravel, cobbles, boulders over lying a steeply sloped “Blue Shale”

Depth to Water: 20 ft bgs

General Contractor: Hensel Phelps Construction Company

Case Study: Denver Justice Center, Down Town Denver, Colorado

Page 93: Construction Dewatering Means and Methods Presentation

General Contractor: Hensel Phelps Construction Company

Case Study: Denver Justice Center, Down Town Denver, Colorado

Page 94: Construction Dewatering Means and Methods Presentation

General Contractor: Hensel Phelps Construction

Case Study: Denver Justice Center, Down Town Denver, Colorado

• Deep Wells: 12” dia. (30” BH), spaced approximately 75 ft apart, extending 60 ft bgs

• 10 Deep Wells Total• Powered by 10 hp, 250 GPM

Each• Initial Flow Rate: Estimated

at approx 2500 GPM• Results: Dropped water

several feet below subgrade in the deep alluvium.

System Description

Page 95: Construction Dewatering Means and Methods Presentation

Drilling Activities

Case Study: Denver Justice Center, Down Town Denver, Colorado

Page 96: Construction Dewatering Means and Methods Presentation

Pump Setting and Wiring Activities

Case Study: Denver Justice Center, Down Town Denver, Colorado

Page 97: Construction Dewatering Means and Methods Presentation

Well Head Completion and Discharge Assembly Operations

Case Study: Denver Justice Center, Down Town Denver, Colorado

Page 98: Construction Dewatering Means and Methods Presentation

Completed Well Head and Discharge

Case Study: Denver Justice Center, Down Town Denver, Colorado

Page 99: Construction Dewatering Means and Methods Presentation

Completed Well Heads and Discharge Manifold

Case Study: Denver Justice Center, Down Town Denver, Colorado

Page 100: Construction Dewatering Means and Methods Presentation

Discharge Water & Baffled Settling Tank

Case Study: Denver Justice Center, Down Town Denver, Colorado

Page 101: Construction Dewatering Means and Methods Presentation

Baffled Settling Tank & Final Discharge Point

Case Study: Denver Justice Center, Down Town Denver, Colorado

Page 102: Construction Dewatering Means and Methods Presentation

Excavation During Demo Phase, Prior to Dewatering

Case Study: Denver Justice Center, Down Town Denver, Colorado

Page 103: Construction Dewatering Means and Methods Presentation

Completed Excavation Following Successful Dewatering

Case Study: Denver Justice Center, Down Town Denver, Colorado

Page 104: Construction Dewatering Means and Methods Presentation

Excavation Subgrade & Excavation Support Wall

Case Study: Denver Justice Center, Down Town Denver, Colorado

Page 105: Construction Dewatering Means and Methods Presentation

Case Studies• San Juan Chama Drinking Water Project (SJCDWP)

– Install (2) two 54” Pipelines under the Rio Grande River• Bayport Terminal Complex – Port of Houston

– Container Loading/Off Loading Facility– Cruise Ship Terminal

• Denver Justice Center, Down Town Denver• Environmental Retrofit Program – Luminant Generation• US 93 Wickenburg Bypass• Beaver Dam Road Reconstruction Project• Trinity Rural WSC Water Treatment Plant

Page 106: Construction Dewatering Means and Methods Presentation

Design Considerations:

Dimensions– Length 400 ft– Width 225 ft– Depth 10 ft

Excavation Type: Combination Vertical Shoring, Open Cut

Geology: Man placed fill (fine sand, dense) to 18ft bgs. Intermediate concrete “mud” slab from previous construction 10 ft bgs

Depth to Water: 6 ft bgs

General Contractor: Fluor Enterprises, Inc

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Page 107: Construction Dewatering Means and Methods Presentation

General Contractor: Fluor Enterprise, Inc

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Page 108: Construction Dewatering Means and Methods Presentation

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

• Vacuum Wellpoints• Approx. 1200 ft perimeter• Approx. 180 wellpoints

extending to 18 ft bgs (top of natural clay)

• 2 primary wellpoint pumps, electrically driven

• 2 stand by wellpoint pumps, diesel driven

• Anticipated initial flow of 1800 gpm; anticipated steady state flow of 900 gpm

System Description

Page 109: Construction Dewatering Means and Methods Presentation

Existing Conditions – Prior to Dewatering/Excavation.

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Page 110: Construction Dewatering Means and Methods Presentation

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Slab Removal– Prior to Dewatering/Excavation.

Page 111: Construction Dewatering Means and Methods Presentation

Specialty Drilling Rig – Designed/Built by TerraFirma and Duramast

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Page 112: Construction Dewatering Means and Methods Presentation

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Specialty Drilling Rig – Designed/Built by TerraFirma and Duramast

Page 113: Construction Dewatering Means and Methods Presentation

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Specialty Drilling Rig – Designed/Built by TerraFirma and Duramast

Page 114: Construction Dewatering Means and Methods Presentation

Water Supply and Custom Designed and Built Self Jetting Head.

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Page 115: Construction Dewatering Means and Methods Presentation

Wellpoint and Flexible Riser Pipe (2” HDPE).

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Page 116: Construction Dewatering Means and Methods Presentation

Self Jetting and Sanding Activities

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Page 117: Construction Dewatering Means and Methods Presentation

Self Jetting and Sanding Activities

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Page 118: Construction Dewatering Means and Methods Presentation

Pump Testing and Completed Wellpoint Installation

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Page 119: Construction Dewatering Means and Methods Presentation

Completed Wellpoint and Header Pipe Installation

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Page 120: Construction Dewatering Means and Methods Presentation

Completed Wellpoint, Header Pipe, and Wellpoint Pump Installation

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Page 121: Construction Dewatering Means and Methods Presentation

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Completed Wellpoint, Header Pipe, and Wellpoint Pump Installation

Page 122: Construction Dewatering Means and Methods Presentation

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Completed Excavation Following Successful Dewatering

Page 123: Construction Dewatering Means and Methods Presentation

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Completed Excavation Following Successful Dewatering

Page 124: Construction Dewatering Means and Methods Presentation

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Completed Excavation Following Successful Dewatering

Page 125: Construction Dewatering Means and Methods Presentation

Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX

Completed Excavation Following Successful Dewatering

Page 126: Construction Dewatering Means and Methods Presentation

Case Studies• San Juan Chama Drinking Water Project (SJCDWP)

– Install (2) two 54” Pipelines under the Rio Grande River• Bayport Terminal Complex – Port of Houston

– Container Loading/Off Loading Facility– Cruise Ship Terminal

• Denver Justice Center, Down Town Denver• Environmental Retrofit Program – Luminant Generation• US 93 Wickenburg Bypass• Beaver Dam Road Reconstruction Project• Trinity Rural WSC Water Treatment Plant

Page 127: Construction Dewatering Means and Methods Presentation

Design Considerations:

Dimensions– Length 300 ft– Width 60 ft– Depth 15 ft

Excavation Type: Sloped, Open Cut

Geology: Alluvium material, primarily unconsolidated silt, sand, and gravel: underlain by a confining layer of conglomerate sandstone.

Depth to Water: 5ft Below River Bed

General Contractor: Markham Contracting, Inc

Case Study: US 93 Wickenburg Bypass (Soil Cement Scour Protection)Wickenburg, AZ

Page 128: Construction Dewatering Means and Methods Presentation

General Contractor: Markham Contracting, Inc

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Page 129: Construction Dewatering Means and Methods Presentation

General Contractor: Markham Contracting, Inc

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Page 130: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

• Deep Wells: 12” dia. (34” BH), spaced approximately 60 ft apart, extending 60 ft bgs

• 33 Deep Wells Total• Powered by 20 hp, 600 GPM

Each• Initial Flow Rate: Estimated

at approx 6000 GPM• Results: Dropped water

several feet below subgrade in the deep alluvium.

System Description

Page 131: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Hassayampa River Bed – Existing Bridge

Page 132: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Drilling Operations

42” x 10’ Surface Casing

Page 133: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Biopolymer Mixing Station – Borehole Stability and Fluid Loss

Page 134: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Drilling OperationsBiopolymer Slurry / Surface Casing

Page 135: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Well Setting Activities (glue and screw)

Page 136: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Borehole Development – Fresh Water Injection

Drilling Operations (thru biopolymer)

Page 137: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Gravel Packing Operation

Water Displacement During Gravel Placement

Page 138: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Well Development – Reverse Air

Page 139: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Pump Setting Activities – 20 hp Pumps, 800 GPM

Page 140: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Completed Well Head

Connection at HDPE Manifold

Page 141: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Discharge Manifold Assembly

Page 142: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Completed Installation – East Abutment

Page 143: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Discharge – East Abutment (est. 6500 gpm)

Page 144: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

The New Local Watering Hole

Page 145: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

The Other Local Watering Hole

Page 146: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Excavation Following Successful Dewatering

Page 147: Construction Dewatering Means and Methods Presentation

Case Study: US 93 Wickenburg BypassWickenburg, AZ

Excavation Following Successful Dewatering

Page 148: Construction Dewatering Means and Methods Presentation

Case Studies• San Juan Chama Drinking Water Project (SJCDWP)

– Install (2) two 54” Pipelines under the Rio Grande River• Bayport Terminal Complex – Port of Houston

– Container Loading/Off Loading Facility– Cruise Ship Terminal

• Denver Justice Center, Down Town Denver• Environmental Retrofit Program – Luminant Generation• US 93 Wickenburg Bypass• Beaver Dam Road Reconstruction Project• Trinity Rural WSC Water Treatment Plant

Page 149: Construction Dewatering Means and Methods Presentation

Design Considerations:

Dimensions– Length 1200 ft– Depth 12 ft

Excavation Type: Open Cut

Geology: Erratic silt, clay, sands and gravels.

Depth to Water: 4 ft bgs

General Contractor: WSU, Inc

Case Study: Beaver Dam Road ReconstructionVail, CO

Page 150: Construction Dewatering Means and Methods Presentation

General Contractor: WSU, Inc

Case Study: Beaver Dam Road ReconstructrionVail, CO

Page 151: Construction Dewatering Means and Methods Presentation

• Sump Wells: 12” dia. (30” BH), spaced approximately 200ft apart, extending 15-25 ft bgs

• 9 Sump Wells Total• Powered by 2 hp, 40 GPM

Each• Initial Flow Rate: Estimated

at approx 250 GPM

Case Study: Beaver Dam Road ReconstructionVail, CO

System Description

Page 152: Construction Dewatering Means and Methods Presentation

Case Study: Beaver Dam Road ReconstructionVail, CO

Beaver Dam Road – Prior to Excavation/Dewatering

Page 153: Construction Dewatering Means and Methods Presentation

Case Study: Beaver Dam Road ReconstructionVail, CO

Well Drilling at Base of Beaver Dam Road

Page 154: Construction Dewatering Means and Methods Presentation

Case Study: Beaver Dam Road ReconstructrionVail, CO

Drilling Activities

Boulder Removal

Page 155: Construction Dewatering Means and Methods Presentation

Case Study: Beaver Dam Road ReconstructrionVail, CO

Drilling Operations

Placement of Well Materials

Page 156: Construction Dewatering Means and Methods Presentation

Case Study: Beaver Dam Road ReconstructrionVail, CO

Gravel Packing Activities

Page 157: Construction Dewatering Means and Methods Presentation

Case Study: Beaver Dam Road ReconstructionVail, CO

Well Development – Traditional Airlift

Page 158: Construction Dewatering Means and Methods Presentation

Case Study: Beaver Dam Road ReconstructionVail, CO

Drilling Activities – Boulder Removal

Page 159: Construction Dewatering Means and Methods Presentation

Case Study: Beaver Dam Road ReconstructionVail, CO

Well Placement Gravel Packing the Well

Page 160: Construction Dewatering Means and Methods Presentation

Case Study: Beaver Dam Road ReconstructionVail, CO

Excavation Following Successful Dewatering

Discharge Settlement Tank

Final Discharge Point – Adjacent Beaver Creek

Page 161: Construction Dewatering Means and Methods Presentation

Case Study: Beaver Dam Road ReconstructionVail, CO

Scenery – Main Lift, Vail Ski Resort

Page 162: Construction Dewatering Means and Methods Presentation

Case Studies• San Juan Chama Drinking Water Project (SJCDWP)

– Install (2) two 54” Pipelines under the Rio Grande River• Bayport Terminal Complex – Port of Houston

– Container Loading/Off Loading Facility– Cruise Ship Terminal

• Denver Justice Center, Down Town Denver• Environmental Retrofit Program – Luminant Generation• US 93 Wickenburg Bypass• Beaver Dam Road Reconstruction Project• Trinity Rural WSC Water Treatment Plant

Page 163: Construction Dewatering Means and Methods Presentation

Design Considerations:

Dimensions– Length 165 ft– Width 120 ft– Depth 12 ft (16 ft @

Decant Pump Station)

Excavation Type: Open CutGeology: Upper clayey soils,

fine to silty sands, confining clay layer 20 ft bgs.

Depth to Water: 8 ft bgs

General Contractor: RM Dudley Construction

Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX

Page 164: Construction Dewatering Means and Methods Presentation

• Vacuum Wellpoints

• 60 Wellpoints: 1 ½”, Spaced approximately 10 ft c. to c. extending 18-22 ft BGS

• Powered by Vacuum Wellpoint pump, electric primary, diesel backup

• Flow Rates: Measured at approx 150 GPM

• Results: Ongoing

Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX

System Description

Page 165: Construction Dewatering Means and Methods Presentation

Dewatering Layout – Plan View

Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX

Page 166: Construction Dewatering Means and Methods Presentation

Pre-Drilling Activities

Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX

Page 167: Construction Dewatering Means and Methods Presentation

Jetting Activities

Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX

Page 168: Construction Dewatering Means and Methods Presentation

Jetting and Gravel Packing Activities

Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX

Page 169: Construction Dewatering Means and Methods Presentation

Header Pipe Completion

Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX

Page 170: Construction Dewatering Means and Methods Presentation

Primary and Stand By Wellpoint Pumps - Discharge to The River

Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX

Page 171: Construction Dewatering Means and Methods Presentation

Discharge

Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX

Page 172: Construction Dewatering Means and Methods Presentation

Thank You

Reference Material:• Driscoll, Fletcher G. Groundwater and Wells, Second Edition. St. Paul: US

Filter/Johnson Screens, 1986

• Powers, J Patrick. Dewatering – Avoiding Its Unwanted Side Effects. New York: American Society of Civil Engineers, 1985

• Powers, J Patrick. Construction Dewatering: New Methods and Applications, Second Edition. New York: John Wiley & Sons, Inc., 1992

• Todd, David Keith. Groundwater Hydrology, Second Edition. New York: John Wiley & Sons, Inc., 1980