Top Dewatering pumps India | Buy Dewatering Pumps Online - Pumpkart.com
Construction Dewatering Means and Methods Presentation
Click here to load reader
description
Transcript of Construction Dewatering Means and Methods Presentation
Construction Dewatering
Getting Your Project on Firm Ground……Before It Starts
Introduction
• David Giles– Co-Founder/Managing Partner: TerraFirma Earth
Technologies, Ltd.
• Overview of Construction Dewatering– Giving guidance to those directly or indirectly
involved in the planning, design, supervision, construction and operation of dewatering systems.
Topics of Discussion
• Construction Dewatering– What is it?– Why do it?
• The Consequences of Improper Dewatering• Design Considerations• Subsurface Investigations and Soil Borings• Methods of Groundwater Control• Case Studies
Topics of Discussion
• Construction Dewatering– What is it?– Why do it?
Dewatering: What is it?Intercepting/minimizing groundwater seepage from entering an
excavation.
Depressing the piezometric water surface to a point below the excavation.
Topics of Discussion
• Construction Dewatering– What is it?– Why do it?
Dewatering: Why do it?
Short Term Objectives(Temporary Systems)
• Intercept Seepage– Increase slope stability– Prevent loss of material
• Reduce lateral/uplift pressure
• Improve the excavation and the backfill characteristics of the excavation to allow construction to proceed in a safe and eficient manner
Long Term Objectives(Permanent Systems)
• Reduce or eliminate lateral and/or uplift pressures
• Achieve waterproofing objectives
Improper Dewatering
The Consequences• Blows, Rendering Excavation Subgrade
Unstable• Boils/Piping, the Creation of Voids Rendering
Slopes and Subgrades Unstable• Excavation Support Systems Rendered Unstable• Future Settling• Lost Time• Decreased Worksite Safety• Increased Cost
Improper Dewatering
The Consequences• Blows, Rendering Excavation Subgrade Unstable• Boils/Piping, the Creation of Voids Rendering
Slopes and Subgrades Unstable• Excavation Support Systems Rendered Unstable• Future Settling• Lost Time• Decreased Worksite Safety• Increased Cost
Improper Dewatering
The Consequences• Blows, Rendering Excavation Subgrade Unstable• Boils/Piping, the Creation of Voids Rendering
Slopes and Subgrades Unstable• Excavation Support Systems Rendered Unstable• Future Settling• Lost Time• Decreased Worksite Safety• Increased Cost
Improper Dewatering
The Consequences• Blows, Rendering Excavation Subgrade Unstable• Boils/Piping, the Creation of Voids Rendering
Slopes and Subgrades Unstable• Excavation Support Systems Rendered Unstable• Future Settling• Lost Time• Decreased Worksite Safety• Increased Cost
Improper Dewatering
The Consequences• Blows, Rendering Excavation Subgrade Unstable• Boils/Piping, the Creation of Voids Rendering
Slopes and Subgrades Unstable• Excavation Support Systems Rendered Unstable• Future Settling• Lost Time• Decreased Worksite Safety• Increased Cost
Improper Dewatering
Rio Grande River Crossing, Albuquerque, NM
Improper Dewatering Proper Dewatering
42” Gas Pipeline, Blythe, CA
Topics of Discussion
• The Origins of Dewatering• Construction Dewatering
– What is it?– Why do it?
• The Consequences of Improper Dewatering• Design Considerations• Subsurface Investigations and Soil Borings• Methods of Groundwater Control• Case Studies
Design Considerations
Dominant Considerations• Location and Geologic Environment• Size and Depth of Excavation• Groundwater (Piezometric) Level• Soil & Aquifer Characteristics (Hydraulic Conductivity)• Proposed Excavation Method and Excavation Support• Proposed Schedule• Proximity to Existing Structures, Potable and/or Irrigation
Wells, Potential Sources of Recharge• Nature of any On/Off-site Contamination
Design Considerations
Dominant Considerations• Location and Geologic Environment• Size and Depth of Excavation• Groundwater (Piezometric) Level• Soil & Aquifer Characteristics (Hydraulic Conductivity)• Proposed Excavation Method and Excavation Support• Proposed Schedule• Proximity to Existing Structures, Potable and/or Irrigation
Wells, Potential Sources of Recharge• Nature of any On/Off-site Contamination
Design Considerations
Dominant Considerations• Location and Geologic Environment• Size and Depth of Excavation• Groundwater (Piezometric) Level• Soil & Aquifer Characteristics (Hydraulic Conductivity)• Proposed Excavation Method and Excavation Support• Proposed Schedule• Proximity to Existing Structures, Potable and/or Irrigation
Wells, Potential Sources of Recharge• Nature of any On/Off-site Contamination
Depth to Water & the Piezometer
Design Considerations
Dominant Considerations• Location and Geologic Environment• Size and Depth of Excavation• Groundwater (Piezometric) Level• Soil & Aquifer Characteristics (Hydraulic Conductivity)• Proposed Excavation Method and Excavation Support• Proposed Schedule• Proximity to Existing Structures, Potable and/or Irrigation
Wells, Potential Sources of Recharge• Nature of any On/Off-site Contamination
Hydraulic Conductivity (K)
“K” can simply be defined as the ease at which water moves through soil.
More specifically defined by D’Arcy’s Law
Q=KA(h/L) Q = Quantity of Water Flow K = Permeability of Soil A = Cross-sectional Area h = Friction Loss in Distance L
Estimating PermeabilityVisual Classification (USCS)Soil Classification Hydraulic Conductivity(USCS) gpd/ft2 μ/secClay (CL) .02-.0002 .1-.0001Silt (ML) 1-2 .5-1Clayey Sand (SC) 2-20 1-10Silty Sand (SM) 20-100 10-50Well Graded Sand ( ) 20-2000 10-1000Uniform Sand (SP) 100-4000 50-2000Well Graded Gravel (GW) 1000-6000 500-3000Uniform Gravel (GP) 4000-20000 2000-10000Open Work Gravel 20000+ 10000+
J. Patrick Powers
Design Considerations
Dominant Considerations• Location and Geologic Environment• Size and Depth of Excavation• Groundwater (Piezometric) Level• Soil & Aquifer Characteristics (Hydraulic Conductivity)• Proposed Excavation Method and Excavation Support• Proposed Schedule• Avoiding Undesirable Side Effects
– Proximity to Existing Structures, Potable and/or Irrigation Wells– Nature of any On/Off-site Contamination
Design Considerations
Dominant Considerations• Location and Geologic Environment• Size and Depth of Excavation• Groundwater (Piezometric) Level• Soil & Aquifer Characteristics (Hydraulic Conductivity)• Proposed Excavation Method and Excavation Support• Proposed Schedule• Avoiding Undesirable Side Effects
– Proximity to Existing Structures, Potable and/or Irrigation Wells– Nature of any On/Off-site Contamination
Design Considerations
Dominant Considerations• Location and Geologic Environment• Size and Depth of Excavation• Groundwater (Piezometric) Level• Soil & Aquifer Characteristics (Hydraulic Conductivity)• Proposed Excavation Method and Excavation Support• Proposed Schedule• Avoiding Undesirable Side Effects
– Proximity to Existing Structures, Potable and/or Irrigation Wells, and potential sources of recharge
– Nature of any On/Off-site Contamination
Design Considerations
Dominant Considerations• Location and Geologic Environment• Size and Depth of Excavation• Groundwater (Piezometric) Level• Soil & Aquifer Characteristics (Hydraulic Conductivity)• Proposed Excavation Method and Excavation Support• Proposed Schedule• Avoiding Undesirable Side Effects
– Proximity to Existing Structures, Potable and/or Irrigation Wells, and potential sources of recharge
– Nature of any On/Off-site Contamination
Topics of Discussion
• Construction Dewatering– What is it?– Why do it?
• The Consequences of Improper Dewatering• Design Considerations• Subsurface Investigations and Soil Borings• Methods of Groundwater Control• Case Studies
Subsurface Investigations
Typical Bore Log for Pump House, Fulton, Arkansas
Topics of Discussion
• Construction Dewatering– What is it?– Why do it?
• The Consequences of Improper Dewatering• Design Considerations• Subsurface Investigations and Soil Borings• Methods of Groundwater Control• Case Studies
Dewatering Methods
• Open Pumping• Pre-Drainage
– Wellpoints– Deepwells– Eductors
• Methods of Cutoff– Soil Bentonite– Interlocking Steel Sheet Pile– Concrete Caisson
Open Pumping
Favorable Conditions:• Dense, Well Graded Soils, Some Cementation/Cohesiveness• Firm Clays, Few Sand/Silt Lenses Unconnected Hydraulically• Hard Fissured Rock• Low Dewatering Head• Remote Source of Recharge• Open Cut, Relatively Flat Slopes, Minimal Depth Below GW
Table• Steel Interlocking Sheet Pile, Concrete Caisson
Dewatering Methods• Open Pumping• Pre-Drainage
– Wellpoints– Deepwells– Eductors
• Methods of Cutoff– Soil Bentonite– Interlocking Steel Sheet
Pile– Concrete Caisson
Vacuum Wellpoints
Key System Components:• Vacuum Pump• Suction Header• Wellpoint• Swingjoint• Discharge Pipe
Traditional Rotary Lode Vacuum Wellpoint Pump 8”, Diesel Driven
Accessories: wellpoint, swingjoint, header pipe
Vacuum Wellpoints
Vacuum WellpointsFavorable Conditions:• Wide Ranging Soil Types• Impervious Clay/Rock At or Near Subgrade• Highly Stratified Soil• Wide Ranging Permeability• Remote or Proximate Sources of Recharge• Excavations <= 20’; Greater than 20’ requires the use of multiple stages• Rapid Drawdown Required
Dewatering Methods
• Open Pumping• Pre-Drainage
– Wellpoints– Deepwells– Eductors
• Methods of Cutoff– Soil Bentonite– Interlocking Steel Sheet Pile– Concrete Caisson
Deepwells
Key System Components:• Well Assembly
– Well Screen\Casing– Filter Media
• Pump Assembly– Submersible Pump\Motor– Discharge Column Pipe
• Pump Control Panel• Electrical Distribution• Discharge Pipe
Deepwells
12” SDR 26 Well Screen
24” Sch 40 Stainless Steel Well Screen/Casing
Deepwells
20 HP Submersible Pump and Motor
Deepwells
DeepwellsFavorable Conditions:• Sands and Gravels Extending
Well Below Subgrade• Uniform Soil• Moderate to High
Permeability• Open Cut or Vertical/Shored,
Excavations of Any Depth• Long Draw Down Times
Acceptable
Dewatering Methods
• Open Pumping• Pre-Drainage
– Wellpoints– Deepwells– Eductors
• Methods of Cutoff– Soil Bentonite– Interlocking Steel Sheet Pile– Concrete Caisson
Eductor SystemKey System Components:• Well Assembly
– Well Screen/Casing– Filter Media
• Eductor Assembly• High Pressure
Recirculation Pump• Supply/Return Headers• Recirculation Tank• Discharge Pipe
Eductor System
Eductor Body
Eductor System
Eductor Wellhead and Headers
Eductor SystemFavorable Conditions:• Silty and Clayey Sand• Highly Stratified Soil• Impervious Clay/Rock At or
Near Subgrade• Low Permeability Soils• Excavation Depths Not
Limited• Rapid Draw Down Times
Required
Dewatering Methods
• Open Pumping• Pre-Drainage
– Wellpoints– Deepwells– Eductors
• Methods of Cutoff– Soil Bentonite– Interlocking Steel Sheet Pile– Concrete Caisson
Cut-Off WallFavorable Conditions:• Impervious Clay/Rock At or
Near Subgrade• Proximate Sources of
Recharge• Close Proximity to Existing
Structures• Close Proximity to
Contamination Plume• Properly Designed Cut-off
Wall can Function as Ground Support
Materials Utilized…– Soil Bentonite– Cement/Bentonite– Concrete Caisson– Interlocking Steel Sheet Piling
Stop seepage into an excavation, where excavation encroaches upon or penetrates an impervious stratum
Cut-Off Wall
Soil Bentonite Mixing Station and Trenching Activities
Topics of Discussion
• The Origins of Dewatering• Construction Dewatering
– What is it?– Why do it?
• The Consequences of Improper Dewatering• Design Considerations• Subsurface Investigations and Soil Borings• Methods of Groundwater Control• Case Studies
Case Studies• San Juan Chama Drinking Water Project (SJCDWP)
– Install (2) two 54” Pipelines under the Rio Grande River• Bayport Terminal Complex – Port of Houston
– Container Loading/Off Loading Facility– Cruise Ship Terminal
• Denver Justice Center, Down Town Denver• Environmental Retrofit Program – Luminant Generation• US 93 Wickenburg Bypass• Beaver Dam Road Reconstruction Project• Trinity Rural WSC Water Treatment Plant
Dimensions– Length 1100 ft– Width 110 ft– Depth 26 ft
Excavation Type: Open CutGeology: Typical River Deposits (Well Graded Sands, gravel, cobbles, boulders)Depth to Water: at surface
Design Considerations
(Installing Dual 54” WL Beneath the Rio Grande River)
San Juan Chama Drinking Water Project
General Contractor: AUI, Inc.
San Juan Chama Drinking Water Project
System Description
Deep Wells: 12” (30” BH), Spaced Approximately 50 – 75 ft apart, extending 75 ft bgs
62 Deep Total
Powered by 20 hp, 600 GPM Each
Initial Flow Rate: Measured at approx 12,000 GPM (10 – 12 running at any one time
Results: Dropped Water 5 ft Below Pipe Subgrade
San Juan Chama Drinking Water Project
Portable Coffer Dam Construction
San Juan Chama Drinking Water Project
Portable Coffer Dam Construction
San Juan Chama Drinking Water Project
Completed Portable Coffer Dam Construction
San Juan Chama Drinking Water Project
Drilling Operation
San Juan Chama Drinking Water Project
Drilling Operation
San Juan Chama Drinking Water Project
Drilling Spoils
San Juan Chama Drinking Water Project
Setting of the 12” Well Materials
San Juan Chama Drinking Water Project
Gravel Packing the Well
San Juan Chama Drinking Water Project
Filter Media
San Juan Chama Drinking Water Project
Well Development
Pump Setting
San Juan Chama Drinking Water Project
San Juan Chama Drinking Water Project
Common Discharge Piping/Manifold
San Juan Chama Drinking Water Project
Lateral Seepage AlongCemented Cobble Layer
Pipe Installation – Successfully Dewatered Excavation
Pipe Laying Activities – Ideal Conditions
San Juan Chama Drinking Water Project
San Juan Chama Drinking Water Project
Finished Excavation
Well Removal/Abandonment
San Juan Chama Drinking Water Project
San Juan Chama Drinking Water Project
Breach of Portable cofferdam
Breach of Portable Coffer Dam
San Juan Chama Drinking Water Project
Case Studies• San Juan Chama Drinking Water Project (SJCDWP)
– Install (2) two 54” Pipelines under the Rio Grande River• Bayport Terminal Complex – Port of Houston
– Container Loading/Off Loading Facility– Cruise Ship Terminal
• Denver Justice Center, Down Town Denver• Environmental Retrofit Program – Luminant Generation• US 93 Wickenburg Bypass• Beaver Dam Road Reconstruction Project• Trinity Rural WSC Water Treatment Plant
Bayport Terminal – Port of Houston
• Dimensions– Length 2100ft– Width 200ft– Depth 62ft (-) 56 msl
Excavation Type: Open CutGeology: Beaumont Formation (Clays, Sands, Silts)
Depth to Water: 13’ BGS (+) 3 msl
Design Considerations
General Contractor: Zachry Construction Corporation
Bayport Terminal – Port of Houston
System Description Deep Wells: 8” (30”
BH), Spaced Approx. 75 ft apart, extending 80 ft bgs
Sand Drains: 2” (6” BH) – 2 between ea. pumping well
65 Deep Wells Total 130 Sand Drains Powered by 5 hp, 60
GPM EA Initial Flow Rate:
Estimated at approx 3600 GPM (10 – 12 running at any one time
Results: Dropped Water 45 ft from its original level
Bayport Terminal – Port of Houston
Bayport Terminal – Port of Houston
Deepwell and Sand Drain Detail
Bayport Terminal – Port of Houston
Drilling of Sand Drains – Mud Rotary Method
Bayport Terminal – Port of Houston
Drilling of Deepwells – Bucket Auger Method
Bayport Terminal – Port of Houston
Night Time Drilling and Well Placement
Bayport Terminal – Port of Houston
Gravel Packing the Deepwell
Bayport Terminal – Port of Houston
Pump Assembly, Pre-Wiring
Bayport Terminal – Port of Houston
Pumping Setting
Bayport Terminal – Port of Houston
Pump Setting Discharge Installation
Bayport Terminal – Port of Houston
Completed Well Heads (rigid/flexible)
Bayport Terminal – Port of Houston
Completed – Dewatering System
Bayport Terminal – Port of Houston
Excavation Beneath Deck, Between Drilled Piers
Bayport Terminal – Port of Houston
Discharge
Bayport Terminal – Port of Houston
Discharge
Case Studies• San Juan Chama Drinking Water Project (SJCDWP)
– Install (2) two 54” Pipelines under the Rio Grande River• Bayport Terminal Complex – Port of Houston
– Container Loading/Off Loading Facility– Cruise Ship Terminal
• Denver Justice Center, Down Town Denver• Environmental Retrofit Program – Luminant Generation• US 93 Wickenburg Bypass• Beaver Dam Road Reconstruction Project• Trinity Rural WSC Water Treatment Plant
Design Considerations:Dimensions
– Length 250 ft– Width 250 ft– Depth 28 ft
Excavation Type: H-Pile and Wood Lagging
Geology: well graded sands, gravel, cobbles, boulders over lying a steeply sloped “Blue Shale”
Depth to Water: 20 ft bgs
General Contractor: Hensel Phelps Construction Company
Case Study: Denver Justice Center, Down Town Denver, Colorado
General Contractor: Hensel Phelps Construction Company
Case Study: Denver Justice Center, Down Town Denver, Colorado
General Contractor: Hensel Phelps Construction
Case Study: Denver Justice Center, Down Town Denver, Colorado
• Deep Wells: 12” dia. (30” BH), spaced approximately 75 ft apart, extending 60 ft bgs
• 10 Deep Wells Total• Powered by 10 hp, 250 GPM
Each• Initial Flow Rate: Estimated
at approx 2500 GPM• Results: Dropped water
several feet below subgrade in the deep alluvium.
System Description
Drilling Activities
Case Study: Denver Justice Center, Down Town Denver, Colorado
Pump Setting and Wiring Activities
Case Study: Denver Justice Center, Down Town Denver, Colorado
Well Head Completion and Discharge Assembly Operations
Case Study: Denver Justice Center, Down Town Denver, Colorado
Completed Well Head and Discharge
Case Study: Denver Justice Center, Down Town Denver, Colorado
Completed Well Heads and Discharge Manifold
Case Study: Denver Justice Center, Down Town Denver, Colorado
Discharge Water & Baffled Settling Tank
Case Study: Denver Justice Center, Down Town Denver, Colorado
Baffled Settling Tank & Final Discharge Point
Case Study: Denver Justice Center, Down Town Denver, Colorado
Excavation During Demo Phase, Prior to Dewatering
Case Study: Denver Justice Center, Down Town Denver, Colorado
Completed Excavation Following Successful Dewatering
Case Study: Denver Justice Center, Down Town Denver, Colorado
Excavation Subgrade & Excavation Support Wall
Case Study: Denver Justice Center, Down Town Denver, Colorado
Case Studies• San Juan Chama Drinking Water Project (SJCDWP)
– Install (2) two 54” Pipelines under the Rio Grande River• Bayport Terminal Complex – Port of Houston
– Container Loading/Off Loading Facility– Cruise Ship Terminal
• Denver Justice Center, Down Town Denver• Environmental Retrofit Program – Luminant Generation• US 93 Wickenburg Bypass• Beaver Dam Road Reconstruction Project• Trinity Rural WSC Water Treatment Plant
Design Considerations:
Dimensions– Length 400 ft– Width 225 ft– Depth 10 ft
Excavation Type: Combination Vertical Shoring, Open Cut
Geology: Man placed fill (fine sand, dense) to 18ft bgs. Intermediate concrete “mud” slab from previous construction 10 ft bgs
Depth to Water: 6 ft bgs
General Contractor: Fluor Enterprises, Inc
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
General Contractor: Fluor Enterprise, Inc
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
• Vacuum Wellpoints• Approx. 1200 ft perimeter• Approx. 180 wellpoints
extending to 18 ft bgs (top of natural clay)
• 2 primary wellpoint pumps, electrically driven
• 2 stand by wellpoint pumps, diesel driven
• Anticipated initial flow of 1800 gpm; anticipated steady state flow of 900 gpm
System Description
Existing Conditions – Prior to Dewatering/Excavation.
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Slab Removal– Prior to Dewatering/Excavation.
Specialty Drilling Rig – Designed/Built by TerraFirma and Duramast
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Specialty Drilling Rig – Designed/Built by TerraFirma and Duramast
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Specialty Drilling Rig – Designed/Built by TerraFirma and Duramast
Water Supply and Custom Designed and Built Self Jetting Head.
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Wellpoint and Flexible Riser Pipe (2” HDPE).
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Self Jetting and Sanding Activities
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Self Jetting and Sanding Activities
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Pump Testing and Completed Wellpoint Installation
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Completed Wellpoint and Header Pipe Installation
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Completed Wellpoint, Header Pipe, and Wellpoint Pump Installation
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Completed Wellpoint, Header Pipe, and Wellpoint Pump Installation
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Completed Excavation Following Successful Dewatering
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Completed Excavation Following Successful Dewatering
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Completed Excavation Following Successful Dewatering
Case Study: Environmental Retrofit Program, Luminant Generation Facility, Rockdale, TX
Completed Excavation Following Successful Dewatering
Case Studies• San Juan Chama Drinking Water Project (SJCDWP)
– Install (2) two 54” Pipelines under the Rio Grande River• Bayport Terminal Complex – Port of Houston
– Container Loading/Off Loading Facility– Cruise Ship Terminal
• Denver Justice Center, Down Town Denver• Environmental Retrofit Program – Luminant Generation• US 93 Wickenburg Bypass• Beaver Dam Road Reconstruction Project• Trinity Rural WSC Water Treatment Plant
Design Considerations:
Dimensions– Length 300 ft– Width 60 ft– Depth 15 ft
Excavation Type: Sloped, Open Cut
Geology: Alluvium material, primarily unconsolidated silt, sand, and gravel: underlain by a confining layer of conglomerate sandstone.
Depth to Water: 5ft Below River Bed
General Contractor: Markham Contracting, Inc
Case Study: US 93 Wickenburg Bypass (Soil Cement Scour Protection)Wickenburg, AZ
General Contractor: Markham Contracting, Inc
Case Study: US 93 Wickenburg BypassWickenburg, AZ
General Contractor: Markham Contracting, Inc
Case Study: US 93 Wickenburg BypassWickenburg, AZ
Case Study: US 93 Wickenburg BypassWickenburg, AZ
• Deep Wells: 12” dia. (34” BH), spaced approximately 60 ft apart, extending 60 ft bgs
• 33 Deep Wells Total• Powered by 20 hp, 600 GPM
Each• Initial Flow Rate: Estimated
at approx 6000 GPM• Results: Dropped water
several feet below subgrade in the deep alluvium.
System Description
Case Study: US 93 Wickenburg BypassWickenburg, AZ
Hassayampa River Bed – Existing Bridge
Case Study: US 93 Wickenburg BypassWickenburg, AZ
Drilling Operations
42” x 10’ Surface Casing
Case Study: US 93 Wickenburg BypassWickenburg, AZ
Biopolymer Mixing Station – Borehole Stability and Fluid Loss
Case Study: US 93 Wickenburg BypassWickenburg, AZ
Drilling OperationsBiopolymer Slurry / Surface Casing
Case Study: US 93 Wickenburg BypassWickenburg, AZ
Well Setting Activities (glue and screw)
Case Study: US 93 Wickenburg BypassWickenburg, AZ
Borehole Development – Fresh Water Injection
Drilling Operations (thru biopolymer)
Case Study: US 93 Wickenburg BypassWickenburg, AZ
Gravel Packing Operation
Water Displacement During Gravel Placement
Case Study: US 93 Wickenburg BypassWickenburg, AZ
Well Development – Reverse Air
Case Study: US 93 Wickenburg BypassWickenburg, AZ
Pump Setting Activities – 20 hp Pumps, 800 GPM
Case Study: US 93 Wickenburg BypassWickenburg, AZ
Completed Well Head
Connection at HDPE Manifold
Case Study: US 93 Wickenburg BypassWickenburg, AZ
Discharge Manifold Assembly
Case Study: US 93 Wickenburg BypassWickenburg, AZ
Completed Installation – East Abutment
Case Study: US 93 Wickenburg BypassWickenburg, AZ
Discharge – East Abutment (est. 6500 gpm)
Case Study: US 93 Wickenburg BypassWickenburg, AZ
The New Local Watering Hole
Case Study: US 93 Wickenburg BypassWickenburg, AZ
The Other Local Watering Hole
Case Study: US 93 Wickenburg BypassWickenburg, AZ
Excavation Following Successful Dewatering
Case Study: US 93 Wickenburg BypassWickenburg, AZ
Excavation Following Successful Dewatering
Case Studies• San Juan Chama Drinking Water Project (SJCDWP)
– Install (2) two 54” Pipelines under the Rio Grande River• Bayport Terminal Complex – Port of Houston
– Container Loading/Off Loading Facility– Cruise Ship Terminal
• Denver Justice Center, Down Town Denver• Environmental Retrofit Program – Luminant Generation• US 93 Wickenburg Bypass• Beaver Dam Road Reconstruction Project• Trinity Rural WSC Water Treatment Plant
Design Considerations:
Dimensions– Length 1200 ft– Depth 12 ft
Excavation Type: Open Cut
Geology: Erratic silt, clay, sands and gravels.
Depth to Water: 4 ft bgs
General Contractor: WSU, Inc
Case Study: Beaver Dam Road ReconstructionVail, CO
General Contractor: WSU, Inc
Case Study: Beaver Dam Road ReconstructrionVail, CO
• Sump Wells: 12” dia. (30” BH), spaced approximately 200ft apart, extending 15-25 ft bgs
• 9 Sump Wells Total• Powered by 2 hp, 40 GPM
Each• Initial Flow Rate: Estimated
at approx 250 GPM
Case Study: Beaver Dam Road ReconstructionVail, CO
System Description
Case Study: Beaver Dam Road ReconstructionVail, CO
Beaver Dam Road – Prior to Excavation/Dewatering
Case Study: Beaver Dam Road ReconstructionVail, CO
Well Drilling at Base of Beaver Dam Road
Case Study: Beaver Dam Road ReconstructrionVail, CO
Drilling Activities
Boulder Removal
Case Study: Beaver Dam Road ReconstructrionVail, CO
Drilling Operations
Placement of Well Materials
Case Study: Beaver Dam Road ReconstructrionVail, CO
Gravel Packing Activities
Case Study: Beaver Dam Road ReconstructionVail, CO
Well Development – Traditional Airlift
Case Study: Beaver Dam Road ReconstructionVail, CO
Drilling Activities – Boulder Removal
Case Study: Beaver Dam Road ReconstructionVail, CO
Well Placement Gravel Packing the Well
Case Study: Beaver Dam Road ReconstructionVail, CO
Excavation Following Successful Dewatering
Discharge Settlement Tank
Final Discharge Point – Adjacent Beaver Creek
Case Study: Beaver Dam Road ReconstructionVail, CO
Scenery – Main Lift, Vail Ski Resort
Case Studies• San Juan Chama Drinking Water Project (SJCDWP)
– Install (2) two 54” Pipelines under the Rio Grande River• Bayport Terminal Complex – Port of Houston
– Container Loading/Off Loading Facility– Cruise Ship Terminal
• Denver Justice Center, Down Town Denver• Environmental Retrofit Program – Luminant Generation• US 93 Wickenburg Bypass• Beaver Dam Road Reconstruction Project• Trinity Rural WSC Water Treatment Plant
Design Considerations:
Dimensions– Length 165 ft– Width 120 ft– Depth 12 ft (16 ft @
Decant Pump Station)
Excavation Type: Open CutGeology: Upper clayey soils,
fine to silty sands, confining clay layer 20 ft bgs.
Depth to Water: 8 ft bgs
General Contractor: RM Dudley Construction
Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX
• Vacuum Wellpoints
• 60 Wellpoints: 1 ½”, Spaced approximately 10 ft c. to c. extending 18-22 ft BGS
• Powered by Vacuum Wellpoint pump, electric primary, diesel backup
• Flow Rates: Measured at approx 150 GPM
• Results: Ongoing
Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX
System Description
Dewatering Layout – Plan View
Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX
Pre-Drilling Activities
Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX
Jetting Activities
Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX
Jetting and Gravel Packing Activities
Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX
Header Pipe Completion
Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX
Primary and Stand By Wellpoint Pumps - Discharge to The River
Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX
Discharge
Case Study: Trinity Rural Water Supply Co. – Water Treatment Plant, Trinity, TX
Thank You
Reference Material:• Driscoll, Fletcher G. Groundwater and Wells, Second Edition. St. Paul: US
Filter/Johnson Screens, 1986
• Powers, J Patrick. Dewatering – Avoiding Its Unwanted Side Effects. New York: American Society of Civil Engineers, 1985
• Powers, J Patrick. Construction Dewatering: New Methods and Applications, Second Edition. New York: John Wiley & Sons, Inc., 1992
• Todd, David Keith. Groundwater Hydrology, Second Edition. New York: John Wiley & Sons, Inc., 1980