Commissioning System(ex)

12
8/10/2019 Commissioning System(ex) http://slidepdf.com/reader/full/commissioning-systemex 1/12 Commissioning Air Systems By Chris Parsloe BG 49/2013 A BSRIA Guide  www.bsria.co.uk    p  f  

Transcript of Commissioning System(ex)

Page 1: Commissioning System(ex)

8/10/2019 Commissioning System(ex)

http://slidepdf.com/reader/full/commissioning-systemex 1/12

Commissioning Air Systems

By Chris Parsloe

BG 49/2013

A BSRIA Guide    www.bsria.co.uk 

I   n  c  l   u  d   e  s   d   o  w  n  l   o  a  d   a  b  l   e  

 p r  o  -  f   o  r  m  a   

c  h  e  c  k  l   i   s  t  s  

Page 2: Commissioning System(ex)

8/10/2019 Commissioning System(ex)

http://slidepdf.com/reader/full/commissioning-systemex 2/12

Page 3: Commissioning System(ex)

8/10/2019 Commissioning System(ex)

http://slidepdf.com/reader/full/commissioning-systemex 3/12

  1

COMMISSIONING AIR SYSTEMS

© BSRIA BG 49/2013

 

ACKNOWLEDGEMENTS

The first edition of Commissioning Air Systems was produced by BSRIA

(AG 3/89) as part of a research project in 1989, under the sponsorship of the

Department of Trade and Industry, and under the direction of an industry

steering group.

This new fully-revised edition has been compiled with the help of an industry

steering group. BSRIA would like to thank the following people, without

whom this revised guidance would not have been possible:

Roger Carlin Ashford Environmental Services Ltd.

Luke Collier Belimo Automation UK Ltd.

Ross Nield Belimo Automation UK Ltd.

Alan Gilbert BSRIA Instrument Solutions

Paul Blower Building Technology Systems Ltd.

Daniel Davies Cardiff Commissioning Ltd.

Neil White Commissioning Specialists Association

Iain Kinghorn Fläkt Woods UK Ltd.

Chris Parsloe Parsloe Consulting

Nick Ward Prime (ES) Ltd.

Rob Lambert Skanska Rashleigh Weatherfoil

Chris Johnston Sutton Services International Ltd.

Gary Nicholls Swiftclean UK Ltd.

Ian Thomas Trox UK Ltd.

Chris Davey JPS Commissioning Services Ltd.

BSRIA acknowledges the very significant contribution made by all the

steering group members, and especially the chair and author, Chris Parsloe of

Parsloe Consulting. The final editorial responsibility for this publication restedwith BSRIA. It was designed and produced by Joanna Smith of BSRIA.

BSRIA would like to thank DP Measurement, KIMO Instruments UK,

Swema AB, Testo Ltd.,Trox UK Ltd., and TSI Incorporated who kindly

provided photographs.

BSRIA acknowledges with thanks Ashford Environmental Services ltd.,

Balcomm Ltd., Crosscount Ltd., HVAC Plant Proving Ltd., Sutton Services

International Ltd. and Swegon Ltd., who provided financial support to this

publication by placing an advertisement.

The advertisements in this publication do not necessarily reflect the views of

BSRIA. BSRIA does not endorse the products and services of advertisers and

the technical content has not been influenced by the presence of advertising.

The guidance given in this publication is correct to the best of BSRIA’s knowledge. However BSRIAcannot guarantee that it is free of errors. Material in this publication does not constitute any warranty,endorsement or guarantee by BSRIA. Risk associated with the use of material from this publication isassumed entirely by the user.

All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or

transmitted in any form or by any means electronic or mechanical including photocopying, recording orotherwise without prior written permission of the publisher.

© BSRIA 56653 July 2013

Page 4: Commissioning System(ex)

8/10/2019 Commissioning System(ex)

http://slidepdf.com/reader/full/commissioning-systemex 4/12

 

© BSRIA BG 49/2013

COMMISSIONING AIR SYSTEMS

 PREFACE

It has been almost 12 years since BSRIA’s guidance on Commissioning

Air Systems was last updated (AG 3/89.3 in November 2001).Amendments to Part F and Part L of the Building Regulations combined

with Soft Landings and the recently issued BSRIA Guide to Seasonal

Commissioning (BG 44/2013) have elevated the importance of

commissioning.

Environmental assessment methods such as BREEAM, LEED and

DREAM have focused the minds of building owners, operators, developers

and designers on the benefits of a proficient, professional commissioning

process. Technological advances in plant and equipment and in particular

the measurement instrumentation utilised by the commissioning specialist

have also played their part in necessitating a full revision of the guide.CIBSE Commissioning Code A Air Distribution Systems sets out the

normal standards of good practice which are generally accepted within

the building services industry. This BSRIA guide explains how to carry

out the commissioning procedure in a way that ensures these standards are

achieved.

This revised guide has been compiled with the assistance of an industry

steering group and it is heartening to see that the Commissioning

Specialists Association (CSA) has been so well represented by both

corporate and individual members. It is the ultimate aim of the CSA to

promote proficient, professional commissioning to the built environment

and to support this with training and career development.

Neil F. White

Chairman, Commissioning Specialists Association – April 2011 to April

2013

Managing Director, Crosscount Ltd.

 June 2013

Page 5: Commissioning System(ex)

8/10/2019 Commissioning System(ex)

http://slidepdf.com/reader/full/commissioning-systemex 5/12

 

COMMISSIONING AIR SYSTEMS

© BSRIA BG 49/2013

 CONTENTS

DEFINITIONS 1

1 INTRODUCTION

1.1 Building regulations 3

  1.2 Guide content 3

2. DESIGN FOR COMMISSIONABILITY 5

  2.1 Commissioning specification 5

  2.2 Duct system layout 6

  2.3 Fan selection 7

  2.4 Access space 8

  2.5 Variable air volume (vav) systems 8

  2.6 Specifying flow rates and tolerances 10

3. COMMISSIONING FACILITIES 16

  3.1 Flow regulating dampers 16

  3.2 Flow measurement 18

4. THE INSTALLATION OF COMMISSIONABLE SYSTEMS 23

  4.1 General 23

  4.2 Organisation and planning 23

  4.3 Installation issues affecting commissionability 24

  4.4 Housekeeping 24

  4.5 Duct system cleanliness 24  4.6 Duct workmanship 25

  4.7 Duct air leakage testing 25

  4.8 Installation inspections 25  4.9 Preparation for commissioning 26

5. SITE TEST INSTRUMENTS 27

  5.1 Rotational speed measurement 27

  5.2 Voltage and current measurement 28

  5.3 Static pressure measurement 29

  5.4 Air velocity and flow rate measurement 29

6 ON SITE FLOW MEASUREMENT TECHNIQUES 40

  6.1 Air flow and velocity flow measurements in ducts 41

  6.2 Measuring air velocity at supply and extract terminals 44

  6.3 Use of flow capture hoods for supply diffusers 45

  6.4 Flow measurements at other terminals 46

Page 6: Commissioning System(ex)

8/10/2019 Commissioning System(ex)

http://slidepdf.com/reader/full/commissioning-systemex 6/12

 

© BSRIA BG 49/2013

COMMISSIONING AIR SYSTEMS

 CONTENTS

7. COMMISSIONING PROCEDURES 47

  7.1 Organisation and planning 47  7.2 Setting to work 48

  7.3 Regulation method and system type 49

  7.4 Proportional balancing 50

8. EXAMPLE METHOD STATEMENTS 52

  8.1 Proportion balancing with volume control dampers 52

  8.2 Systems with constant volume dampers (CVD) 56  8.3 Commissioning of variable air volume systems (VAVs) 59

9. DOCUMENTATION 64

  9.1 Example proformas 64

REFERENCES 73

Page 7: Commissioning System(ex)

8/10/2019 Commissioning System(ex)

http://slidepdf.com/reader/full/commissioning-systemex 7/12

 

COMMISSIONING AIR SYSTEMS

© BSRIA BG 49/2013

1

For the purpose of this guide the following definitions apply:

Cleanliness quality class

A quantifiable level of duct cleanliness that should be achieved prior to

handover. It should be specified as high, medium or low prior to contract

commencement based on a British & European Standard.

Commissionable system

A system designed, installed and prepared to specified requirements in such

a manner as to enable commissioning to be carried out.

Commissionability 

The ability of a system to be commissioned satisfactorily.

Commissioning 

The advancement of an installation from the state of static completion to

full working order to specified requirements. For air systems, it includes

the setting to work of an installation and the regulation of flow rates.

Commissioning Management

The planning, organisation, co-ordination and control of commissioning

activities.

Commissioning Management Organisation

The firm (or person) appointed to manage the commissioning process,being responsible for overall planning, supervision and witnessing of the

results of the integrated commissioning of all installed building services

systems.

Commissioning specialist

The firm (or person) appointed to carry out specified duties in connection

with the commissioning of the engineering services.

Note: The appointed person should have an appropriate level of

competence. One way of demonstrating competence is by individual

membership at an appropriate grade of the Commissioning Specialists

Association.

Commissioning specification

The document (or sub-section of the design specification) that prescribes

the detailed objectives and requirements for commissioning.

Note: the specification must refer to drawings, schedules and relevant parts

of the codes, manuals, guides and other standards.

Designer 

The organisation (firm or persons) responsible for the design of the

air systems that are to be commissioned. Depending on the method ofprocurement this may be one or more organisation. In many instances the

design intent of the air systems may be set out by one organisation, with

DEFINITIONS

Page 8: Commissioning System(ex)

8/10/2019 Commissioning System(ex)

http://slidepdf.com/reader/full/commissioning-systemex 8/12

 

© BSRIA BG 49/2013

COMMISSIONING AIR SYSTEMS2

the final selection of some, or all, of the individual components (main

plant, fans, terminal equipment, control and regulating dampers etc.) by

another organisation. Where this is the case the final system flow rates

should be provided by the organisation that has selected the components,

however this responsibility should be clearly set out in the contractdocuments.

Design criteria

The specified performance of the system expressed as a numerical quantity

together with allowable tolerances.

Installation

A system placed in position as required by the design or specification.

Pre-commissioning

The systematic checking of a completed installation to confirm its state of

readiness for commissioning.

Note: Pre-commissioning is a post-installation completion activity.

Pressure and leakage testing 

The measurement and recording of a specified pressure retention or loss

within a system or system component.

Proportional balancing 

The process of bringing the fluid flow rates throughout a distribution

system into balance with one another, in their correct proportions and

within tolerances specified by the designer.

Regulating

The process of adjusting the flow rates of a fluid in a distribution system

to achieve the design flow rates within the tolerances specified by the

designer.

Setting to work 

The process of setting a static system into operation.

Static completion

The state of a system when it is installed in accordance with the drawings

and specification, clean and ready for setting to work.

System

A set of connected components for heating, cooling, ventilation or air

conditioning consisting of plant, distribution ducting, piping and terminal

units and arrangements to control their operation.

Tolerance

The permissible range of variation from the specified design value.

Witnessing authority 

The firm or person that may sometimes be appointed to witness the resultsof commissioning, and to verify that results obtained comply with the

requirements of the design criteria and commissioning specification.

 DEFINITIONS

Page 9: Commissioning System(ex)

8/10/2019 Commissioning System(ex)

http://slidepdf.com/reader/full/commissioning-systemex 9/12

 INTRODUCTION 1

COMMISSIONING AIR SYSTEMS

© BSRIA BG 49/2013

3

This Guide explains how to commission ducted air distr ibution systems

in buildings. The commissioning process mainly comprises the setting towork of the system fans and the regulation (or proportional balancing) of

system flow rates.

The procedures set out in this guide, if undertaken, should achieve

compliance with the requirements of CIBSE Code A Air Distribution

Systems. In general, CIBSE Code A sets out the normal standards of good

practice which are generally accepted within the building services industry.

This guide explains how to carry out the commissioning procedure in a

way that ensures these standards are achieved.

This guide is equally applicable to new-build and retrofit large scalecommercial applications. The procedures are not generally applicable

to ventilation systems in dwellings. For domestic applications, reference

should be made to BSRIA publication BG46/2013 Domestic ventilation

systems – a guide to measuring air flow rates[1].

Throughout this guide, references are made to England & Wales Building

Regulations and Approved Documents. Separate Building Regulations

apply in Scotland and Northern Ireland. The Welsh government has

powers to enact separate Building Regulations but at the time of writing

has not yet done so.

Newly installed ventilation systems must comply with the requirements of

the relevant Building Regulations. Approved Guidance for England and

Wales can be found in Approved Document F, Ventilation, 2010.

Furthermore, Part L of the Building Regulations for England and Wales

requires that, “Reasonable provision shall be made for the conservation

of fuel and power in buildings by… providing fixed building services

which… are commissioned by testing and adjusting as necessary to ensure

they use no more fuel and power than is reasonable in the circumstances.”

The approved procedure by which compliance with Part L can

be demonstrated is that set out in CIBSE Code M CommissioningManagement [2], and, for ductwork distribution systems, its sub-referenced

document CIBSE Code A Air Distribution Systems[3].

The technical guidance in this guide is divided into the following section

headings:

Section 2: Design for commissionability

Section 3: Commissioning facilities

Section 4: The installation of commissionable systems

Section 5: Site test instrumentsSection 6: On-site flow measurement techniques

1 INTRODUCTION

1.1 BUILDING REGULATIONS

1.2 GUIDE CONTENT

Page 10: Commissioning System(ex)

8/10/2019 Commissioning System(ex)

http://slidepdf.com/reader/full/commissioning-systemex 10/12

  INTRODUCTION1

© BSRIA BG 49/2013

COMMISSIONING AIR SYSTEMS4

Section 7: Commissioning procedures

Section 8: Example method statements

Section 9: Documentation

 

Sections 2, 3 and 4 of the guide are aimed at system designers andinstallers. Unless commissioning is properly considered during both the

design and installation stages of a project, it may not be possible to meet

the requirements of CIBSE Code A[3].

Section 3 provides a summary of the main commissioning facilities.

Sections 5-9 are intended as guidance for commissioning specialists

employed to undertake commissioning activities.

The pro-forma checklists in section 9 are available as an editable Excel

workbook. These can be used on projects, and can be edited or altered bythe user to suit the needs of their projects.

The workbook is attached to the pdf of this publication and can also be

downloaded from www.bsria.co.uk.

Page 11: Commissioning System(ex)

8/10/2019 Commissioning System(ex)

http://slidepdf.com/reader/full/commissioning-systemex 11/12

Page 12: Commissioning System(ex)

8/10/2019 Commissioning System(ex)

http://slidepdf.com/reader/full/commissioning-systemex 12/12

Old Bracknell Lane West,Bracknell, Berkshire,

RG12 7AH, UKOffices in Bracknell, Beijing, Dunfermline,Dusseldorf, Kuala Lumpur, St Helens, NorthAmerica, Toulouse, Madrid, Brazil andAssociates in Armagh

BSRIA

the builtenvironment experts

BSRIA gives you confidence in design, added value inmanufacture, competitive advantage in marketing,profitable construction, and efficient buildings

¢ Testing

¢ Modelling

¢ Research

¢ Consultancy

¢ Instrument hire,

sales and calibration

¢ Troubleshooting

¢ Information

¢ Training

¢ Publications

¢ Market research and

intelligence

Membership is the foundation of BSRIA’s expertise and independence 

Whatever your buildingservices requirement

contact BSRIA:

T: +44 (0)1344 465600F: +44 (0)1344 465626E: [email protected]: www.bsria.co.uk