Clyde Extension Wind Farm - SSE plc - The UK's...

23
Clyde Extension Wind Farm Environmental Statement Non-Technical Summary October 2011 Clyde Wind Farm Turbine T171 & Daer Reservoir July 2011 (Turbine scale not reflecve of Clyde Extension nominal turbine dimensions)

Transcript of Clyde Extension Wind Farm - SSE plc - The UK's...

Clyde Extension Wind FarmEnvironmental Statement

Non-Technical Summary

October 2011

Clyde Wind Farm Turbine T171 & Daer Reservoir July 2011 (Turbine scale not reflective of Clyde Extension nominal turbine dimensions)

Clyde Extension Wind Farm     Environmental Statement    Non‐Technical Summary 

October 2011    Page i 

Preface 

This document  forms  the non‐technical  summary  (NTS) of  the Environmental  Statement (ES) that accompanies an application made by Clyde Windfarm (Scotland) Ltd for consent under  Section  36  of  the  Electricity  Act  1989  for  the  construction  and  generation  of electricity from the Clyde Extension Wind Farm (herein referred to as the ‘Development’), and deemed planning permission  for  the  same development under Section 57(2), of  the Town  and  Country  Planning  (Scotland)  Act  1997  (as  amended  by  The  Planning  etc. (Scotland) Act 2006).  The ES comprises three volumes: 

Volume I: Text; 

Volume II: Figures; and 

Volume III A and B: Technical Appendices.  Additional documentation that will be submitted with the Section 36 application includes: 

Planning Statement; 

Design and Access Statement; 

Pre‐application Consultation Report; and 

Non‐Technical Summary.  The ES (Text, Figures and Technical Appendices) and associated documents will be available for viewing during normal business hours at the following locations: 

South Lanarkshire Council Enterprise Resources Planning & Building Standards Service HQ Montrose House 154 Montrose House Hamilton ML3 6LB 

South Lanarkshire Council Enterprise Resources Planning & Building Standards Service South Vennel Lanark ML11 7TJ 

Moffat Town Hall Customer Service Centre High Street Moffat Dumfries and Galloway DG10 9HF 

Scottish Borders Council Contact Centre High Street Peebles EH45 8AF 

Biggar Library Market Road Biggar South Lanarkshire ML12 6FX 

 

The  ES  will  also  be  available  for  purchase,  at  £200  for  paper  copies  and  £25  for  an electronic version on CD, from:  

Clyde Windfarm (Scotland) Ltd c/o SSE Renewables Developments (UK) Ltd 1 Waterloo Street 5th Floor Glasgow G2 6AY 

    Clyde Extension Wind Farm Non‐Technical Summary    Environmental Statement 

Page ii    October 2011 

Paper copies of the NTS are available free of charge.  The Application and ES will be advertised in the following newspapers: 

Moffat News; 

Peebleshire News; 

Hamilton Advertiser; 

Herald Newspaper; 

Lanark and Carluke Gazette; and 

Edinburgh Gazette. 

Clyde Extension Wind Farm     Environmental Statement    Non‐Technical Summary 

October 2011    Page 1 

1 Introduction 

This Non‐Technical Summary (NTS) forms part of the Environmental Statement (ES) which accompanies  an  application  by  Clyde Windfarm  (Scotland)  Ltd  (the  ‘Applicant’)  to  the Scottish  Government  for  consent  under  Section  36  of  the  Electricity  Act  1989  for  the construction  and operation of Clyde Extension Wind  Farm  (hereafter  referred  to as  ‘the Development’).    The  Development  will  comprise  57  wind  turbines  and  associated infrastructure with a total potential installed capacity of up to 171 MegaWatts (MW).  It is located in the Upper Clyde Valley, between Biggar, Abington and Moffat within both South Lanarkshire and Scottish Borders Council Areas as shown on Figure NTS 1.  The Development  forms  an  extension  to  the  nearby  consented  Clyde Wind  Farm.    The Clyde Wind Farm  lies directly  to  the west and south of  the Development, and comprises 152 wind turbines and associated  infrastructure with a total  installed capacity of 350MW.  Consent  for Clyde Wind Farm was granted by Scottish Ministers under Section 36 of  the Electricity Act 1989 (as amended) in July 2008 and construction activities are underway at the time of writing. 

 The Applicant is a company incorporated under the laws of Scotland and is a 100% owned subsidiary of the publically quoted company Scottish and Southern Energy plc (SSE).  SSE is a FTSE‐100 company,  formed  in 1998  from  the merger of Scottish Hydro Electric plc and Southern Electric plc.  The company is headquartered in Perth, Scotland and employs more than 20,000 people.  Core activities include electricity generation, transmission distribution and  supply;  gas  storage,  distribution  and  supply;  the  operation  of  a  telecoms  network; utility contracting; and electrical and gas appliance  retailing.   The company has a market capitalisation  of  around  £10  billion,  and  supplies  over  9.59 million  customers  in  Great Britain and Ireland under the Scottish Hydro‐Electric, Southern Electric, Swalec and Atlantic and Airtricity brands.   The company  is co‐owner of Scotia Gas Networks, which owns and operates the ‘Scotland’ and ‘South of England’ regional gas distribution networks.  The gas network business employs around a further 5,000 staff.  SSE’s power generation assets  total around 11,410MW, comprising 4,590MW of gas and oil‐fired  capacity;  4,370MW  coal‐fired  capacity  and  2,450MW  of  renewable  (including pumped storage, hydro, wind and biomass) capacity.  SSE Renewables Developments (UK) Ltd is the renewable energy development division of SSE (Scottish and Southern Energy plc).  SSE has over 20 onshore wind farms in operation in Scotland and Ireland totalling over 915MW.  Wind farms totalling over 705MW are under construction and a further 275MW with consent for development.  

2 EIA Process and Methodology 

Environmental Impact Assessment (EIA)  is a process aimed to ensure that permissions for developments with  potentially  significant  effects  on  the  environment  are  granted  only after assessment of the likely significant environmental effects has been undertaken.  The assessment must  be  carried  out  following  consultation with  statutory  consultees,  other interested  bodies  and  members  of  the  public.    The  information  that  an  applicant  is required  to  submit  as  part  of  the  EIA  process  (as  specified  in  Schedule  4  of  the  EIA Regulations) is presented in the ES.  Consultation  has  formed  an  integral  role  throughout  the  EIA  process,  including  at  the following key stages: 

    Clyde Extension Wind Farm Non‐Technical Summary    Environmental Statement 

Page 2    October 2011 

Pre‐Scoping ‐ obtaining initial feedback on the Development; 

Scoping ‐ identification of key issues; 

Technical  Assessments  ‐  collecting  baseline  information  and  confirming  survey methodologies;  

Informing site design ‐ communication with local communities; and 

Discussing opportunities for mitigation and enhancement.  As part of the wider consultation process, public exhibitions were held in June 2010 and in February 2011.   The exhibitions provided members of the public the opportunity to  learn more about the Development, feed in to the design process and to ask any questions.    Following the  initial public exhibitions a scoping opinion request was  issued on 15th June 2010 with the accompanying Scoping Report.   This was submitted to the Energy Consents Unit alongside other consultees and interested bodies.  All responses to the scoping report have  been  compiled  and  distributed  to  the  relevant  technical  disciplines  for  inclusion within the appropriate assessment.  Further detail on the community consultation process is provided in a separate Pre‐Application Consultation Report submitted to accompany the application. 

3 Renewable Energy Policy Context and Alternative Technologies 

In 2008 the European Commission published proposals  for reducing the EU’s greenhouse gas  emissions  by  20%  and  increasing  the  proportion  of  final  energy  consumption  from renewable  sources  to  20%.   Both  targets  are  to  be  achieved  by  2020.    For  the UK,  the European Commission’s proposals  include 16% reduction  in UK greenhouse gas emissions by 2020 and for 15% of all energy consumed in the UK to come from renewable sources by 20201.  The UK Renewable Energy Strategy (UKRES) sets out the means by which the UK can meet the legally binding target of 15% of energy consumption from renewable sources by 2020.  This will mean a very substantial  increase  in  the share of  renewables  in about a decade.  The majority of  this  is expected  to  come  from wind power, both on  and offshore.   The document makes it clear that the UKRES is an integral part of the Government’s overall UK Low Carbon Transition Plan and that the Devolved Administrations have a  leadership role to undertake.    The  Scottish  Government  is  committed  to  promoting  the  increased  use  of  renewable energy sources to help tackle climate change and to support economic growth in Scotland.   In  July 2011  the Scottish Government published  the “Routemap  for Renewable Energy  in Scotland”  (’the Routemap’).   This document outlines Scotland’s renewables ambition and paths  to  delivery  and  provides  an  increase  in  Scottish Government’s  renewable  energy generation target to 100% by 2020. This  is a significant  increase  in targets set  in previous years.  The Routemap specifically recognises the scale of the challenge that requires to be addressed  to  meet  the  revised  2020  targets  and  provides  a  summary  of  the  main challenges that require to be addressed to meet the 2020 renewables targets, one of which is ‘consents and planning’.  

                                                            1 This 15% figure compares to only 3% in 2009, as confirmed in the National Renewable Energy Action Plan for the UK, page 5, July 2010. 

Clyde Extension Wind Farm     Environmental Statement    Non‐Technical Summary 

October 2011    Page 3 

The  mechanism  introduced  to  achieve  the  UK  and  Scottish  renewables  targets  is  the Renewables Obligation, which aims to incentivise the further development of renewables.  The  Renewables  Obligation  obliges  electricity  supply  companies  to  source  prescribed proportions of their total supply from eligible renewable resources, or pay a ‘buy out’ fee per MWh of shortfall.  In order to meet its obligation, the Applicant must develop eligible renewable energy sources on a large scale.  The Applicant’s renewable energy strategy to meet its Renewable Obligation is diverse and a  wide  range  of  alternative  technologies  has  been  considered.    In  all,  SSE  now  has 3,780MW  of  renewable  energy  capacity  (onshore  wind,  offshore  wind,  hydro  and dedicated biomass)  in operation, under construction or with consent  for development  in the UK and the Republic of  Ireland.   The Development therefore  forms part of a broader renewable  energy  strategy  being  implemented  by  the  Applicant  in  response  to UK  and Scottish Government policy. 

4 Design Evolution 

The Applicant’s approach to site selection is an ongoing process where candidate sites are identified  in  accordance  with  national  and  local  planning  policy,  government  targets, Renewable UK guidance and a range of environmental and technical parameters.  It is the Applicant’s opinion  that  the  site  selection process and  the detailed work undertaken  for the  EIA  has  confirmed  the  Clyde  Extension  site  is  an  acceptable  site  for  wind  farm development.  The  design  process  is  a  balance  between  minimising  negative  environmental  effects, achieving a  technically viable site and maximising energy yield, and the wind  farm  layout has evolved throughout  the duration of the EIA.   This  iterative approach has allowed the findings of  the public  consultation exercise along with  results  from  the EIA  to guide  the evolution of  the wind  farm design  and has  allowed  the Development  to be modified  in order  to  avoid,  reduce  or  mitigate  potential  effects  as  far  as  reasonably  practicable.  Specific environmental drivers have been: 

Landscape and visual; 

Ornithology; 

Ecology; 

Hydrology; 

Cultural heritage; 

Noise; and 

Peat stability.  The design process commenced with a preliminary layout which optimised wind yield and took  account  of  topographical  constraints  and  characteristics  such  as  slope  and watercourses.    This  layout  comprised  67  turbines  and  formed  the  submitted  ‘Scoping’ layout.    Following  consideration  of  the  EIA  the  layout was  refined  to  result  in  the  final design of 57 turbines and associated infrastructure. 

5 Description of Development 

The operational Development would comprise: 

57 wind  turbines up  to 142m  (to  tip) height and associated  infrastructure  including, foundations and crane hardstanding areas; 

Site entrances and access tracks from the public road; 

    Clyde Extension Wind Farm Non‐Technical Summary    Environmental Statement 

Page 4    October 2011 

On‐site  access  tracks  between  turbines,  including  passing  bays  and  four  new watercourse crossings; 

Three permanent meteorological masts nominal height 90m; 

On‐site power collection  system  including  turbine  transformers, underground cables, electrical control building and satellite office/welfare building;  

Permanent signage; and 

Permission  to  extend  the  operational  consent  period  of  the  consented  Clyde  north substation and Clyde south substation infrastructure.   

 The proposed layout of the Development is shown in Figure NTS 2.    Construction would  take  place  over  a  24 month  period  and may  involve  the  following associated components: 

Up to three temporary construction compounds adjacent to site access points; 

Up to ten on‐site borrow pits; 

On‐site concrete batching; 

Three temporary meteorological assessment masts;  

Forestry operations; and 

Site signage.  The  core  development  area  covers  approximately  2760ha,  however  the  Development infrastructure will  only  occupy  an    approximate  area  of  38.5  hectares  (ha)  or  less  than 1.5%.   During  the  construction phase,  further  land on‐site will be  required and  restored mainly for construction compounds, lay‐down areas and borrow pits.    Further  detailed  surveys  will  be  undertaken  during  the  pre‐construction  phase  and turbines, associated  infrastructure and associated access tracks may be sited up to 50m – in  any  direction  –  with  the  approval  of  on‐site  archaeologists,  ecologists  or  any  other relevant  specialist  supervising  the  works,  or  by  up  to  100m  with  the  approval  of  the Planning  Authority  and  appropriate  consultees  such  as  Scottish  Environment  Protection Agency (SEPA) and Scottish Natural Heritage (SNH).  Two  access  points  from  the  consented  Clyde Wind  Farm will  be  utilised  and  upgraded (where necessary) to provide access to the Development.   These  include routes from the M74 from the south and west.  An additional length of track of approximately 1.2km will be required  in  order  to  utilise  the  existing  Clyde  Wind  Farm  Access  B.    In  addition,  the formation of  a new  access  route  from  the A701  in  the east will be  required with  a  site entrance  at  grid  reference  305403  619806.    This  utilises  an  existing  forestry  track  and entrance which will be upgraded as part of the construction works for the Development.    The total length of new access tracks required within the core development area would be approximately 33.5km.   New access  tracks will have a  typical running width of 6m.   Peat depths measured on site are generally  less than 1.5m suggesting that the majority,  if not all, of the tracks will be  ‘cut track’ design.   The access tracks will be retained  throughout the  operational  life  of  the  Development  to  enable  maintenance  of  the  turbines  and replacement  of  any  turbine  components.   Access  tracks may  also  be  retained  following decommissioning for use by landowners.  It is estimated that approximately 276,000m3 of stone will be required for construction of the  Development  and  it  is  anticipated  that  the  majority  will  be  sourced  from  on‐site borrow pits in order to minimise haulage distances.  However, where aggregate of suitable 

Clyde Extension Wind Farm     Environmental Statement    Non‐Technical Summary 

October 2011    Page 5 

quality  is not available  from on‐site borrow pits, material may be  imported  from offsite commercial  quarries.    A  total  of  ten  locations  for  potential  borrow  pits  have  been identified,  with  the  potential  volume  of  rock  available  estimated  to  be  approximately 421,500 m³, sufficient to supply the required quantities.  It  is  planned  to  connect  the  Development  into  the  Clyde  North  Substation  (CNS)  and possibly also the Clyde South Substation (CSS) at NGR 298745 620207 and 298278 613415, respectively,  and  integrate  the Development  in  the  consented Clyde Wind  Farm making use of existing grid connection  infrastructure.   No external extension works are proposed as part of this application to the CNS and CSS buildings or compounds however the Section 36 application for the Development seeks to extend the operational life of the CNS and CSS infrastructure  to  coincide  with  the  operational  consent  period  of  the  Development.  Cabling will  be  underground  and will  follow  infrastructure  such  as  on‐site  access  tracks where possible.   The Development will also involve changes to the forestry on‐site which is described within the  ES.    Of  the  245ha  of  felling,  all  but  22ha  would  be  replanted.    The  assessment concludes that there will be no necessity for compensatory planting given that there will be no net deforestation as a  result of  the Development.   The outline Habitat Management Plan  (HMP)  for  the  Development  (Technical  Appendix  9.4)  includes  commitments  to restore bog habitat around the forestry edges and to create approximately twelve hectares of high quality native woodland (including native birch, rowan, alder and hazel) located in a series of copses throughout the site.   This planting constitutes wider biodiversity benefits and  is  proposed  to  off‐set  residual  ecological  effects  but  will  also  provide  additional benefits  in  terms  of  achieving  objectives  for  Government  Policy  on  woodland enhancement/creation. 

 A  draft  Site  Environmental  Management  Plan  (SEMP)  has  been  provided  as  Technical Appendix 5.4.   This will be refined, developed and streamlined as the project proceeds  in consultation with  relevant  statutory consultees and would be monitored by  the  relevant site project manager for compliance. 

6 Planning 

The  Development,  due  to  the  electricity  generation  capacity  exceeding  50  MW,  is submitted under the terms of Section 36 of the Electricity Act 1989 and Section 57 of the Town  and  Country  Planning  (Scotland)  Act  1997.    In  considering  the  application  under Section  36  of  the  Electricity  Act  1989  the  Scottish  Ministers  must  also  fulfil  the requirements of Paragraph 3 of Schedule 9 to that Act.  If Section 36 consent is granted the Scottish Ministers may also direct that planning permission for the Development is deemed to be granted.  The  Structure  and  Local  Plans,  national  policy  and  guidance  (material  considerations) provide the relevant planning policy context against which to assess the Development.  The Local and Structure Plans that form the statutory Development Plans for the Development are as follows: 

The Glasgow and Clyde Valley Joint Structure Plan 2000 (as altered); 

The South Lanarkshire Local Plan (adopted 2009);  

The South Lanarkshire Minerals Local Plan 2002; 

The Scottish Borders Structure Plan (2001 – 2011)(approved 2002 and as   altered  in 2005 and 2009); and 

The Scottish Borders Local Plan (adopted 2008 and altered 2010). 

    Clyde Extension Wind Farm Non‐Technical Summary    Environmental Statement 

Page 6    October 2011 

 The Development Plan policies of potential relevance to the Development are referred to within Chapter 6 of the ES  ‘Planning Policy Context’ and are quoted within Appendix 6.1: Development Plan Policies.  There is also a suite of national planning policy, Planning Advice Notes (PANs), an emerging Strategic Development Plan and Supplementary Planning Guidance  that are also of some relevance to the Development.  These include: 

The National Planning Framework 2; 

Scottish Planning Policy; 

The Glasgow and the Clyde Valley Strategic Development Plan ‐ Proposed Plan; 

The Scottish Government’s Web Based Renewables Guidance; 

Scottish Historic Environment Policy; 

South Lanarkshire Council SPG ‘Renewable Energy’; and 

Scottish Borders Council SPG ‘Wind Energy’.  The Applicant has submitted a separate Planning Statement which assesses,  in detail, the Development  in the context of the relevant Development Plan policies, national planning policy and advice, renewable energy policy, SPG and other material considerations.   

7 Landscape and Visual Assessment 

The Landscape and Visual Assessment aims to  identify significant effects that would arise as  a  result of  the Development.    The  assessment  considers  the  effect on  the  landscape resource  (both directly and on how  the  landscape  is perceived) and  the effect on visual amenity.   Cumulative effects, arising  from  the effect of  the Development  in  conjunction with other wind farms, are also considered.  SNH has prepared  landscape character assessments  for Scotland however  in 2010 South Lanarkshire Council updated  the original 1999 SNH character assessment  for  those areas within  its authority boundary. The  study area  in  the assessments  is divided  into distinct Landscape Types, Sub Types and Units.  The main changes to landscape character resulting from  the Development would arise  in  the Southern Uplands: Lowther Hills and Southern Upland and the Southern Upland with Scattered Forest: Broadlaw Group landscape units as the wind  farm would be physically  located with  these  landscape units.   Both units have similar  characteristics  and  the  baseline  conditions  of  the  landscape  have  and  are  being further  changed by wind  farms, most notably  the  consented Clyde Wind  Farm, which  is currently  under  construction.    This  wind  farm,  which  lies  immediately  adjacent  to  the Development will contribute strongly to the baseline landscape character.   The  level  of  effect  of  the  Development  on  these  landscape  units  is  assessed  as  not significant,  because  they  would  continue  to  be  defined  principally  by  their  baseline characteristics, which include wind farms.  Although the landscape is essentially remote the underlying  upland  character  has  been  substantially  altered  by  commercial  forestry,  and wind turbines are becoming a prevailing influence, forming a ‘Southern Upland, Windfarm’ landscape sub type adjacent to the Development.    It  is considered that the Development would  not  constitute  a material  change  from  the  baseline  conditions  and  that while  it would  extend  the  influence  of  turbines  within  the  landscape,  the  effect  on  landscape character is assessed as being not significant.  Similarly, it is considered that there would be no significant effects on the landscape character of designated landscapes within the study area, which include the Upper Tweeddale National Scenic Area (NSA), the Upper Clyde and 

Clyde Extension Wind Farm     Environmental Statement    Non‐Technical Summary 

October 2011    Page 7 

Tinto Special Landscape Areas  (SLA) and  the Tweedsmuir Area of Great Landscape Value (AGLV).  Twenty  five  representative viewpoints and a number of  transport  routes  chosen  for  the assessment  of  visual  effects  were  selected  in  consultation  with  SNH,  Scottish  Borders Council and South Lanarkshire Council.   The assessment of effects on views  indicates that the  Development  would  have  relatively  few  significant  effects  on  views  and  visual receptors.   Seven viewpoints were considered to be significantly affected during the operation of the Development.  Six of these lie within a 5km radius of the outermost turbine, and of these, four are to the east of the site along the A701.   These six viewpoints would gain views of the Development  turbines  at  closer  proximity  than  those  of  the  consented  Clyde Wind Farm, which would  also  be  visible  but  less  prominent.    The  viewpoint  at Grains  beside Camps Reservoir lies closest to the Development with turbines prominent in views.  Culter Fell overlooks  the Development site, and while  the consented Clyde Wind Farm  turbines will  be  clearly  visible  from  this  location,  the  new  turbines  would  be  more  visually prominent in front of them.  The seventh viewpoint considered to be significantly affected is  situated  at  the  summit  of  Trahenna  Hill  to  the  north‐east  of  the  Development  at  a distance of approximately 15.3km, and would be significantly affected due to the increase in the visual prominence of wind turbines on the skyline in views to the south‐west.  For the majority of the remaining 18 representative viewpoints the consented Clyde Wind Farm will be a prevailing element  in views  so  the nature of  the views would not change significantly and the Development would appear as a logical extension of the existing wind farm.  To the west of the Development, the extent of effects on views is very limited as the Development  would  generally  be  seen  behind  the  consented  Clyde Wind  Farm.    This ensures that the influence of the consented wind farm is prevalent, and the Development would have a  limited additional effect when  seen at distance and behind  the consented Clyde Wind Farm turbines, and no significant effects are predicted.  The  assessment  of  the  effects  of  the  Development  on  views  from  route  corridors  and settlements has  found  that new  turbines would be prominent  features  in a  sequence of views from approximately 13km of the A701 to the north of Moffat.  The consented Clyde Wind Farm will also be visible from many of the same sections of the route, with screening provided by forestry along the route corridor, however, the effect of the Development on this  route  would  be  significant  due  to  the  scenic  nature  of  available  view.    The Development has been assessed as having no significant effects upon the route corridors of the M74/A74(M), A702, A721,  Southern Upland Way and National Cycle Route 74.   The Development  is  also  considered  to  have  no  significant  effects  on  settlements  including Tweedsmuir and Crawford, which are the two closest villages.     As well as assessing  the effects of  the Development  in  its own  right,  the  landscape and visual  assessment  also  assessed  the  cumulative  effect  that  the  addition  of  the Development  may  have  in  conjunction  with  other  operational/under  construction, consented  or  application  stage  wind  farms.    The  landscape  and  visual  amenity  in  the vicinity of the Development site and the wider study area have been altered by wind farms, most  notably  the  consented  Clyde  Wind  Farm,  which  will  contribute  strongly  to  the baseline  landscape character and views.   The Development  is not considered material  to the creation of a  ‘wind farm  landscape’ and would represent a relatively small change to the cumulative scenarios considered. 

    Clyde Extension Wind Farm Non‐Technical Summary    Environmental Statement 

Page 8    October 2011 

 The  assessment  of  cumulative  effects  of  the  Development  on  landscape  character concluded  that  although  the Development would  have  cumulative  effects  on  landscape character and designations,  for  the majority of  landscape  types and all  the designations, these would not be significant in relation to the operational/under construction, consented or application wind farms.  In nearly all instances when the Development would affect the landscape character,  it would generally appear  in combination with  the consented Clyde Wind Farm and would not cause additional effects for the affected areas.  Only the Upper Glen: Culter Water & Cow Gill  landscape unit would experience a  significant  cumulative effect  from  the Development  in combination with  the consented Clyde Wind Farm.   This area  is relatively unaffected by the visual  influence of surrounding wind farms,  is situated in an SLA and is considered to be of medium to high sensitivity.  Although the development would not physically encroach upon this  landscape unit, the addition of the Development would  cause  a medium magnitude  of  change.    The  large  number  of  other  wind  farm developments  that  are  proposed  will  result  in  turbines  becoming  common  landscape features within the study area, with the Glenkerie wind farm (currently under construction) and Earlshaugh (application stage) wind farm (if consented), likely to increase the influence of turbines on the character of the affected  landscape units and designated areas, which would  also  help  to  limit  the  significance  of  the  effects  of  the  Development  on  the landscape.   The  Development  would  be  located  immediately  adjacent  to  the  considerably  larger consented  Clyde Wind  Farm  and  it  would  be  largely  viewed  in  combination  with  the existing  turbines,  giving  cumulative  visual  effects  for  the  majority  of  viewpoints.    In consequence there are only relatively small parts of the study area from which views of the Development would be  available without  the  consented Clyde Wind  Farm  turbines  also being  visible.    The  assessment  of  cumulative  effects  on  views  has  found  that  the Development would have significant visual effects on five of the twenty five representative viewpoints assessed, all of which are within 5km of the Development, and would be seen in combination with  the  consented  Clyde Wind  Farm.    These  include  Camps  Reservoir  at Grains, viewpoints along the A701 and the summit of Culter Fell.  Cumulative  effects  would  not  be  significant  from  the  other  twenty  viewpoints  as  the Development would generally be seen within the same section of views as the consented Clyde Wind  Farm  and  several  other  schemes, with  numerous  other wind  farms  visible across  the  surrounding  area within  the  available  panoramic  views,  so would  not  cause notable cumulative effects on the visual amenity.  The assessment of cumulative effects on settlements and  route corridors has  found  that the development would not have a significant cumulative effect on settlements or  route corridors within  the  study  area.   Views of  the Development would be notable  from  the A701 as  it passes along the scenic route through  the River Tweed valley, but  it would be seen as one of a  sequence of wind  farms  that would  include  the  consented Clyde Wind Farm  and  the  cumulative  effects  of  the Development  on  this  route  are  considered  not significant.  Based on the  findings of the  landscape and visual assessment,  it  is considered that while the Development would  increase  the  influence of  turbines within  the  Southern Uplands and Southern Uplands with Scattered Forest  landscape types, would have significant  local effects on views within 5km to the east and north of the Development, from a hilltop 15km to  the  north‐east  and  from  the  A701  corridor  during  construction  and  operation,  the 

Clyde Extension Wind Farm     Environmental Statement    Non‐Technical Summary 

October 2011    Page 9 

landscape  has  the  capacity  to  accommodate  development  of  the  scale  proposed.    The operational effects would be  long term (for the  life of the wind farm) but reversible, such that following decommissioning these effects would not exist. 

8 Ornithology 

The  possible  key  ornithological  effects  relating  to  the Development  are  its  potential  to adversely affect  the  conservation  status of bird populations  (particularly  those given  the highest levels of statutory protection through inclusion in Annex I of the EU Birds Directive and/or Schedule 1 of the Wildlife and Countryside Act 1981  (as amended)) through  land‐take, disturbance, displacement, collisions with the turbines and/or barrier effects.   Some or all of these effects may occur as a result of construction activities, operation of the wind farm and decommissioning activities.  The baseline‐gathering process  involved a combination of desk studies and  field surveys, carried out  in 2009‐10.   Surveys ensured that all months were covered, and  included two breeding seasons as well as the intervening winter and spring/autumn migratory periods.  A  total of 62  species were  recorded during breeding bird  surveys.   The  key bird  species found breeding within  the  study  area were moorland‐breeding  raptors  (hen harrier  and merlin), osprey, waders  (in particular golden plover and curlew) and black grouse.   Most activity was recorded during summer months before birds migrated from the site, although some passerine and raptor species make use of forestry habitats, and are present all year round.  The site is crossed regularly by pink‐footed goose on migration between roost and staging  sites.    Other  key  species  recorded  (e.g.  peregrine,  goshawk,  skylark)  were  not considered likely to be subject to any significant effects due to scarcity on‐site or relatively small numbers compared to regional populations.  Direct habitat loss through wind farm construction was considered to be not significant for birds,  as  construction  usually  only  involves  small  losses  of  land  associated with  turbine bases, access tracks and other infrastructure.  An exception to this was where the felling of a tree used for nest‐building activities by a young non‐breeding osprey pair in 2010 would have resulted in the loss of a potential future breeding pair.  All trees used by ospreys for nesting purposes will therefore be excluded from felling as part of the mitigation measures outlined in the ornithology chapter.   Disturbance caused by construction operations may directly displace birds  from breeding sites  and/or  foraging  areas.    In  addition,  the  active  nests  of  nearly  all  bird  species  are protected against destruction by  the  law and  it  is necessary  to  take measures  to ensure compliance with the appropriate legislation.  It was considered that, based on a literature review of disturbance distances for each species, it was  possible that one pair each of hen harrier and merlin, plus one  lekking black grouse may be disturbed  in  the  short‐term by unmitigated construction activity.   However,  these birds would  likely be able  to continue unaffected as the topography of chosen nest/lekking areas shield the birds from visual and noise disturbance.  Depending on the exact location of future nesting sites, a small number of golden plover and curlew breeding pairs may be disturbed during construction, although these would be insignificant in the context of the Natural Heritage Zone populations.  Potentially  significant disturbance effects on protected  species will also be minimised by employing  Best  Practice  measures  during  construction  (e.g.  timing  and  location  of construction activities  to avoid breeding birds, cordoning off specified construction areas prior to the breeding season to discourage nesting) and by enhancing habitat for all species 

    Clyde Extension Wind Farm Non‐Technical Summary    Environmental Statement 

Page 10    October 2011 

elsewhere via the Habitat Management Plan.    In areas where work  is unavoidable during the breeding season, visual deterrent devices may be placed within a restricted area well in advance  so  that  birds  are  deterred  from  nesting within  that  locality.    Although  a  non‐breeding osprey pair was recorded within potential construction disturbance distances, any nearby  forest  felling activity of any breeding nest will  take place outside of  the breeding season and risks will be minimised.    Displacement due to an operational wind farm effectively leads to exclusion from areas of suitable habitat, which in turn, can lead to reduced breeding success and individual survival or abandonment of the territory.  There were no predicted significant displacement effects on hen harrier or merlin due to the species’ apparent abilities of tolerating wind farms, and the availability of alternative nesting habitat away from recognised displacement distances.  For  osprey  and  black  grouse,  the  distances  to  the  nearest  turbines,  and  shielding topography are  sufficient  to avoid disturbance‐displacement effects.   A  reduction of  the breeding population of up to seven pairs of golden plover and twelve pairs of curlew may occur within the core development area in the long‐term (worst‐case scenario), but this is not  considered  significant  in  terms  of  the  overall  regional  populations,  despite  recent declines in numbers.  Collision risk modelling was run for the key species potentially at risk: pink‐footed goose, hen harrier, merlin, peregrine, osprey, golden plover, curlew and snipe. The collision  risk assessment demonstrated  that  there will be no  significant  impact  to  any of  the  species modelled.    The  majority  of  species  recorded  using  or  passing  through  the  site  are considered  to  be  at  negligible  or  low  risk  because  of  their  behaviour  (e.g.  low  altitude flights), scarcity on the site, or relatively high regional populations.  Although collision risk modelling predicted  that a number of pink‐footed goose may  collide with  turbines each year, when comparing the potential effects at the relevant scale (the national/flyway level), it was concluded that the additional mortality will be not significant (up to 0.42% of the UK mortality  rate),  and  that  the  conservation  status  of  the  species  (which  is  currently favourable) will be unaffected by the Development.  Since the area is not part of any daily commute for geese from roost to feeding sites, any barrier effects which would alter flight paths of flocks would be negligible in terms of overall energy expenditure, compared to the overall  flight  distance  for  each  bird.    No  barrier  effects  were  predicted  for  any  other species.  The assessment of the likely effects of the Development during the construction, operation and decommissioning  stages  concluded  that, provided best practice  is  followed  to avoid disturbance  to  breeding  birds,  plus  species–specific  mitigation  measures  to  minimise displacement effects are  implemented, there will be no significant effects on any species, either  alone  or  in‐combination with  other  projects  in  the  area,  and  their  conservation status will be maintained.  There are also no predicted effects on any designated sites. 

9 Ecology 

An  ecological  impact  assessment  has  been  carried  out  in  accordance  with  Institute  of Ecology  and  Environmental Management  (IEEM)  (2006)2 Guidelines.    This was based on data  from a  series of ecological  surveys, consultations and desk based  literature  reviews that  followed  recognised ecological guidelines.   The  information was used  to generate a picture of the ecological baseline and assess the effects of the proposed development on the ecological interests of the area.   

                                                            2 IEEM (2006) Guidelines for Ecological Impact Assessment in the United Kingdom (version 7 July 2006) 

Clyde Extension Wind Farm     Environmental Statement    Non‐Technical Summary 

October 2011    Page 11 

 The desk‐based assessment  identified  five  statutory designated  sites within 15km of  the survey  area.    This  includes  Special  Areas  of  Conservation  (SAC)  and  Sites  of  Special Scientific  Interest (SSSI).   The closest such site  is the River Tweed SAC/SSSI  located 1.3km from  the  survey area.   This  site  is designated  for a  range of protected  species  including Atlantic Salmon, Brook, Sea and River Lamprey, otter and a number of  invertebrates and vascular plants.  No non‐statutory sites were identified within 15km of the survey area.   The survey area  is dominated by upland peatland habitats,  including a mosaic of blanket bog,  heathland  and  acid  grassland.    Additionally  large  areas  of  commercial  conifer plantation are  located  to  the east.   A number of  small burns  run across  the  survey area feeding into Camps Reservoir and the Tweed catchment.   Species that were recorded within the survey area considered to be of conservation value and/or  requiring  legal  consideration  include  otter,  common  pipistrelle  bat,  soprano pipistrelle bat, brown long eared bat, noctule bat and common lizard.  However bat activity was predominantly associated with sheltered features outwith the development footprint such as Camps Reservoir and woodland edges at the lower reaches of the site.  Very little bat activity was recorded within the turbine envelope, with this area being at a relatively high altitude and very exposed.   Red squirrel were not confirmed  in  the survey area but may be present in forestry at low density.  Protection measures will be implemented if this species is found within the survey area at the pre‐construction/ construction phases.   Potential effects on  the habitats and  species  found  to be present within  the survey area include habitat loss, displacement, direct mortality, disturbance and indirect effects.  These effects were minimised during the design of the wind farm, by  locating the wind turbines away from the most sensitive habitat features such as watercourses, woodland edges and Camps Reservoir.  Access tracks and other infrastructure have been located to use existing tracks where possible and to minimise loss of valuable habitats such as blanket bog.   Survey results and a detailed assessment have identified the majority of effects on ecology as being not significant.  However, although minimised through the design process, the loss of blanket bog habitat as a  result of  the development has been assessed as a significant effect  given  the  national  value  of  this  habitat  and  the  extent  of  loss.    In  light  of  this significant  effect  it  is  proposed  to  provide  compensation  through  an  outline  Habitat Management Plan (HMP).  Within this document it is proposed to restore afforested areas of blanket bog and manage existing blanket bog habitats to prevent further degradation.    Wider  biodiversity  benefits  are  proposed  through  native  woodland  planting  which  will contribute  to  South  Lanarkshire  Council’s Woodland  Habitat  Action  Plan,  benefit  black grouse habitat, and provide  insect‐rich  foraging areas  for bats.   Woodland planting along watercourses  is  also  likely  to benefit otters by providing  cover  in  the  long‐term.    These benefits further off‐set residual effects.    Overall, taking into consideration current proposed compensation in relation to effects on peatland habitats,  there  is considered  to be no significant  residual effect on blanket bog habitats as a result of the proposed Development.    A number of consented and proposed wind  farms are  located within 10km of the survey area.  However a cumulative assessment taking into consideration such developments has not predicted any further significant effects on ecology.  

    Clyde Extension Wind Farm Non‐Technical Summary    Environmental Statement 

Page 12    October 2011 

10 Traffic and Transportation 

The  Traffic  and  Transportation  chapter  has  assessed  potential  roads  and  traffic  effects identified during the scoping of the environmental assessment.  The  road  network  in  the  study  area  features  several  strategic  A‐class  roads  and  the M74/A74(M), which  leads ultimately between  the Scotland/England border  to Edinburgh and Glasgow.   Between  these  there  is a network of  local  roads  linking communities and settlements.   The proposed  site  is easily accessed using a well developed  road network, without the need to use local roads.  National and  local transport policies were reviewed to allow a desktop hierarchy of roads to be prepared, and site visits were undertaken to gain a visual review of conditions, and to identify sensitive receptors.   Potential routes  for construction traffic were derived, based upon their suitability to carry the types and numbers of construction vehicles predicted.  The quantities of plant, equipment and materials required for the construction effort were considered,  and  a  delivery  profile  established,  identifying  the  average  number  of construction  vehicle movements.   These movements were  then  compared  in  relation  to historic  traffic  flow data  to  allow  the  level of  impact of  increased  traffic  volumes  to be assessed.    The  additional  traffic  associated  with  the  construction  of  the  Development (including abnormal loads) is numerically low although at some locations this is classified as being medium  in  statistical  terms  from  the  impact magnitude  analysis  undertaken.    A worst‐case scenario has been assessed assuming that the generated construction vehicles would exclusively use the routes considered,  in fact they might disperse prior to reaching the receptors assessed, and assuming that ready mix concrete is delivered to site, when in fact it is hoped that concrete can be batched on‐site. The impact magnitude is quantified in this worst‐case scenario as being  low or medium resulting  in no significant environmental effects.    To  offset  any  limited  effects  of  the  construction  traffic,  the  developer  could employ a range of options that can  influence construction traffic behaviour, the details of which would be discussed with the appropriate transport authorities. The effects described in  this  chapter  are  described  in  terms  of  statistical  significance  and  not  in  practical significance.   The  introduction of a  low number of additional HGV movements on a route that does not currently have a large number of HGV trips will be recorded as being highly statistically significant, even though the actual numbers of additional trips are small.  Considering the abnormal  loads  in  isolation, each turbine will result  in an average of nine abnormal loads.  In order to transport the sections in safety, various small scale mitigation works  such  as  the  temporary  removal  of  street  furniture  and  cutting  back  overgrown vegetation  are  likely  to  be  required.    It  should  be  noted  that  all  the  abnormal  load deliveries will be travelling to the site under escort and require police approval for transit. 

11 Hydrology and Hydrogeology 

The effects of the Development have been assessed with regard to the water environment (surface water, groundwater and  soil) within  the development  site and  its  surroundings.  The effects of all activities associated with the Development  including forestry operations have been assessed.  The  surface  water  and  groundwater  assessment  comprised  a  desk  based  information review,  including  consultation  with  SEPA,  Scottish  Borders  Council,  South  Lanarkshire Council, Scottish Water, and  the Tweed and Clyde  fishery  foundations, and a number of 

Clyde Extension Wind Farm     Environmental Statement    Non‐Technical Summary 

October 2011    Page 13 

site visits to  identify the watercourse network, water features, water dependent habitats and private water supplies.   The site is located in the headwaters of both the River Clyde and the River Tweed SAC/SSSI.  There are many natural watercourses and man‐made drainage channels on the agricultural land and throughout the forested land.    The site is located within the surface water catchment of two public drinking water supply reservoirs, owned and operated by Scottish Water, Camps Water and Coulter Reservoir.  The Camps Reservoir is also used as a recreational fishing facility.  The public water supply reservoirs Cowgill Upper Reservoir  and Cowgill  Lower Reservoir  are outwith  the  surface water  catchment  from  the Development.    Flooding on  the  site does not generally occur with the exception of the Grains Burn and the Camps Water.  No new infrastructure as part of this development is proposed within flood risk areas.  There are a number of private water supplies within the vicinity of the site.   The majority are  not  supplied  with  water  originating  from  the  wind  farm  development  area,  and therefore will not be affected by the Development.  Two potable private water supplies are taken  from  the  Glenbreck  Burn,  these  supplies  are  a  considerable  distance  from  any proposed  infrastructure  and  the  infrastructure  in  this  catchment  has  been  kept  to  a minimum.   The two private water supplies and the River Tweed  (SAC and SSSI) are down gradient of proposed forestry operations.  A  pollution  incident  affecting  Surface  Water  Quality  during  the  construction  period  is potentially the most significant effect on the water environment.  Other effects associated with the construction and operation of the Development, including the removal of forested areas, include: 

Erosion and sediment transport;  

Changes to soil and water quality;   

Alteration of natural drainage patterns/runoff volumes and rates; and 

Increase in the magnitude or frequency of flood events.    

In  addition  to  influencing  the  design  of  the  wind  farm  layout  through  micro‐siting  of turbines, access tracks and borrow pits as far as practical away from watercourses, water sources  and water  supplies,  best  practice management  strategies  have  been  developed and  will  be  followed  to  minimise  the  potential  effects  on  the  water  environment.  Management strategies include; appropriate construction methods for tracks, watercourse crossings and drainage  systems  including  the  incorporation of  surface water attenuation ponds;  adhering  to  the  pollution  prevention  guidelines  issued  by  SEPA;  Good  Practice Guidelines During Windfarm Construction  (SEPA, SNH, Scottish Renewables and Forestry Commission), and  the production of an emergency  response plan  for potential pollution incidents.  These measures focus on reducing and controlling runoff from access tracks and preventing/managing spills,  leaks or concrete contamination of groundwater and surface water.     With  the  implementation  of  standard  erosion  control  techniques,  sediment  control structures and other best practice measures as described  in  the accompanying drat Site Environmental Management Plan (Appendix 5.4) and the site specific mitigation measures during forestry operations as described within Chapter 11: Hydrology and Hydrogeology of the  ES,  the  effects  of  the  development  on  the  water  environment  during  forestry operations, construction and operation are concluded to be negligible to minor/moderate.   

    Clyde Extension Wind Farm Non‐Technical Summary    Environmental Statement 

Page 14    October 2011 

 Overall, it is considered that no significant residual effects are predicted on hydrology and hydrogeology  provided  best  practice  and  site  specific  mitigation  procedures  are maintained. 

12 Cultural Heritage and Archaeology 

The  cultural  heritage  chapter  has  considered  the  potential  effects  of  the  Development upon  cultural  heritage  assets,  defined  here  as  relict  features  predating  the  First  Edition Ordnance  Survey map,  selected  later  features  of  historic  interest,  such  as wartime  and industrial  features,  and  all  designated  assets  such  as  listed  buildings  and  scheduled monuments.   Potential  effects upon  the physical  fabric  and  setting of  assets have been considered.  A  desk‐based  study, walkover  survey  and  site  visits  have  been  carried  out  in  order  to identify  assets  that  may  be  affected  by  the  Development  and  establish  their  current condition.    This work  also  provided  information  upon which  to  base  the  assessment  of archaeological potential.  Within  the  Inner  Study  Area  there  are  seven  scheduled monuments  and  a  further  29 undesignated cultural heritage assets.   There  is  low  to moderate potential  for previously unrecorded  archaeological  features  to  be  present.    This  potential  is  greatest  below 400mAOD  where  both  in  the  historic  and  prehistoric  periods,  activity  has  been  more intense, but successive phases of activity have removed surface traces of earlier features.  There are 45 scheduled monuments and  ten  listed buildings within 5km of  the proposed development.  The cable route outwith  the core development area runs along the  line of the scheduled Roman road (HA78) for a distance of some 500m.  The line of the road will be crossed by a cable trench up to 2m wide and the surface will be reinstated following cable installation.  The effect on  the Roman  road will be offset  through a programme of  recording  that will allow for the preservation by record of affected elements.  Work within the scheduled area will require Scheduled Monument Consent and  the recording work will be undertaken  in line with a Written Scheme of Investigation to be agreed with Historic Scotland.  Potential effects on cultural heritage assets have been avoided as far as possible through the design process.  No construction effects are predicted for any known cultural heritage asset.  The potential for previously unrecorded cultural heritage assets above 400m AOD is low and it is highly unlikely that unknown assets in this area will fall within the construction footprint.    Below  400mAOD  the  potential  for  previously  unrecorded  cultural  heritage assets  is moderate and  the potential  for  them  to be affected by groundworks  is  likewise considered moderate.  Potential effects on previously unrecorded assets below 400mAOD will be mitigated through the implementation of a programme of archaeological works that will allow for the preservation by record of the assets affected.  The effect significance for previously unrecorded cultural heritage assets cannot be meaningfully assessed; as neither the sensitivity of  the  receptor, nor  the magnitude of  the effect  is known.   Consequently, the significance of residual construction effects is unknown.  The predicted operational effects of the Development were considered for all designated cultural  heritage  assets  in  the  surrounding  5km.    The  potential  for  such  impacts  was considered at  the design stage and changes made  to prevent/reduce  impacts.   Following this,  it was  concluded  that effects were  confined  to  the  setting of  four  cultural heritage 

Clyde Extension Wind Farm     Environmental Statement    Non‐Technical Summary 

October 2011    Page 15 

assets: Great Hill Cairn, Windgate House, Camps Knowe Wood Fort and Normangill Henge.  These  effects  have  been  assessed  as  ranging  from  negligible  to minor  significance.   No mitigation  is  proposed  for  these  operational  effects  and  they  will  persist  through  the lifetime of the Development and cease upon decommissioning.  The potential operational effect on the palimpsest landscape of the adjacent Tweed Valley was also considered.  It was concluded that due to the nature of the palimpsest landscape and  the  location  of  the  turbines  in  relation  to  this  landscape  that  there  would  be  no operational effect.  The potential for cumulative impacts resulting from this Development and other wind farm developments within 10km have been considered.  It has been concluded that there will be no cumulative effects on cultural heritage assets.  It  is concluded that the proposed development will have no effects of greater than minor significance on cultural heritage assets.  Such effects are not significant in the terms of the EIA Regulations. 

13 Noise 

Noise  will  be  emitted  by  equipment  and  vehicles  used  during  construction  and decommissioning of the wind farm and by the turbines during operation.  The level of noise emitted by the sources and the distance from those sources to the receiver  locations are the main factors determining levels of noise at receptor locations.  Construction Noise Construction noise has been assessed by a desk based  study of a potential  construction programme  and by assuming  the wind  farm  is  constructed using  standard and  common methods.   Noise  levels have been calculated for receiver  locations closest to the areas of work  and  compared with  guideline  and baseline  values.   Construction noise, by  its  very nature, tends to be temporary and highly variable and therefore much less likely to cause an adverse impact.  Various mitigation methods have been suggested to reduce the impact of construction noise, the most important of these being suggested restrictions of hours of working.    It  is  concluded  that  overall  impacts  relating  to  noise  generated  through construction activities will be negligible.  De‐commissioning  is  likely  to  result  in  less noise  impact  than during  construction of  the wind farm.  The construction phase has been considered to have a negligible noise impact, therefore de‐commissioning will, in the worst case, also have a negligible noise impact.  Operational Noise Operational turbines emit noise from the rotating blades as they pass through the air.  This noise  can  sometimes  be  described  as  having  a  regular  ‘swish’.    The  amount  of  noise emitted tends to vary depending on the wind speed.  When there is little wind the turbine rotors will  turn  slowly and produce  lower noise  levels  than during high winds when  the turbine  reaches  its maximum output and maximum  rotational  speed.   Background noise levels at nearby properties will also change with wind  speed,  increasing  in  level as wind speeds rise due to wind in trees and around buildings, etc.  Noise levels from operation of the turbines have been predicted for those locations around the site most  likely  to be affected by noise.   Known baseline noise  levels at a number of these properties were referenced.   Noise  limits have been derived from data gathered on 

    Clyde Extension Wind Farm Non‐Technical Summary    Environmental Statement 

Page 16    October 2011 

the  existing  noise  environment  following  the  method  stipulated  in  national  planning guidance.   Predicted operational noise  levels have been  compared  to  the  limit values  to demonstrate that turbines of the type and size which would be installed can operate within the limits so derived.  It is concluded therefore that operational noise levels from the wind farm will be within levels deemed, by national guidance, to be acceptable for wind energy schemes. 

14 Other Considerations 

Other considerations include: 

Telecommunications, aviation and other infrastructure; 

Land‐use, tourism and recreation, and socio‐economics; 

Shadow flicker; 

Safety of structures in extreme weather;  

Driver distraction; and 

Climate and carbon emissions. 

14.1 TELECOMMUNICATIONS, AVIATION AND OTHER INFRASTRUCTURE 

Due  to  their  size  and  nature,  wind  turbines  have  the  potential  to  interfere  with electromagnetic  signals.    Infrastructure  that  could be  affected  includes  civil  and military aviation  operations  including  impacts  on  radar,  telecommunication  links,  and  television reception.  Desk  based  study  and  extensive  consultation  was  undertaken  in  order  to  identify  and assess existing telecommunications and utilities infrastructure and aviation facilities within a specific distance from the Development. 

14.1.1 Aviation and Radar 

No civil aerodromes or aviation operations are  likely to be affected by the Development.  The Applicant is currently working closely with NERL to mitigate the consented Clyde Wind Farm, and will assess the effectiveness of that mitigation  for the Development when  it  is operational.    It  is noted from their scoping response that the MOD do not anticipate any effects resulting from the Development on TTA20.    In relation to the Eskdalemuir seismic recording  station,  should  any  issues  be  raised  by  the MOD  it  is  believed  that  suitable mitigation can be developed.  

14.1.2 Television and Telecommunications 

Structures such as wind turbines, and others with similar characteristics, have the potential to cause interference with television and telecommunication transmissions.  The BBC Wind Farm Tool shows there to be the potential for up to one dwelling with no alternate off‐air television  service  to  be  affected  by  the  Development.    The  Applicant will  undertake  a television survey in the area surrounding the Development to determine the extent of any television reception effects. 

14.1.3 On‐site Utilities 

No on‐site utilities have been identified. 

14.2 LAND‐USE, TOURISM AND RECREATION, AND SOCIO‐ECONOMICS 

14.2.1 Land‐Use 

The Development  encompasses  areas of  forestry  and open‐ground  constituted of  rough grazing moorland.   Construction activities will accommodate agricultural activities on‐site, however  site  infrastructure will  result  in a  land‐take of around 0.93%.   Operation of  the 

Clyde Extension Wind Farm     Environmental Statement    Non‐Technical Summary 

October 2011    Page 17 

Development will  also  require  that  trees  are  felled  as  outlined  in  Chapter  5  of  the  ES.  These effects on land‐use are considered to be not significant. 

14.2.2 Tourism and Recreation 

A  desk  based  study  identified  on‐site  and  nearby  tourism  and  recreation  resources.  Potential effects on  tourism and  recreation  resources could be direct physical effects, or indirect  effects  (such  as  changes  in  views).    The  study  concluded  that  during  the construction phase some sections of recreation routes would have restricted access to fulfil health and safety requirements, and that nearby resources could experience  intermittent noise and  increased traffic  levels.   During the operational phase of the Development  land and access tracks within the site boundary will be accessible to the public at all times of the year, except during times where essential maintenance  is required.   No significant effects on tourism and recreation are predicted. 

14.2.3 Socio‐Economics 

Investment  in  the  Development  has  the  potential  to  generate  opportunities  for  local business and may also result in contract opportunities for local and regional contractors.    

14.3 SHADOW FLICKER 

Shadow Flicker is an effect that can occur when the sun moves behind a wind turbine rotor and  the  shadow of  a moving wind  turbine blade passes over  a  small opening  (window) within  a  property,  briefly  reducing  the  intensity  of  light within  the  room  and  causing  a flickering to be perceived.  The likelihood and duration of shadow flicker depends upon the positioning of the sun, turbine and window locations, turbine orientation, time of day, time of the year and weather conditions.  Guidance states that only properties within 130 degrees either side of north relative to the turbines  can  be  affected;  as  shadows  are  not  cast  to  the  south  and  that  at  distances greater  than 10  rotor diameters  the  likelihood of  flicker  is very  low.   No dwellings were found  to  be within  10  rotor  diameters  and  130  degrees  north  of  the  proposed  turbine locations, therefore no effects are predicted. 

14.4 SAFETY OF STRUCTURE IN EXTREME WEATHER 

Due  to  the exposed nature of wind  farm  sites, wind  turbines are designed  to withstand extreme weather conditions.  Wind turbines are equipped with features to safely deal with extreme weather conditions such as extreme winds, lightning strike and ice throw. 

14.5 DRIVER DISTRACTION 

The closest public highway  to  the site  is  located approximately 1.33km  from  the nearest turbine  (turbine  44),  this  is  the  A701  which  passes  through  Broughton  and  Moffat.  Evidence  from existing wind  farms would suggest  that  the presence of  the Development would not directly cause any decrease in highway safety. 

14.6 CLIMATE AND CARBON EMISSIONS 

The operation of wind  farms offsets  carbon  from other  forms of energy generation, but there are  carbon  costs associated with  the  construction of wind  farms, especially where they  are  located  in  carbon  rich  soils  such  as peatlands.   A  carbon  assessment has been undertaken  in  accordance  with  Scottish  Government  recommended  methodology,  the carbon calculator predicts an average carbon payback period of between 2.0 and 2.8 years depending  on  whether  a  “fossil  fuel  mix”  or  “grid  mix”  emissions  factor  is  used  for comparison.  

    Clyde Extension Wind Farm Non‐Technical Summary    Environmental Statement 

Page 18    October 2011 

   

This page is intentionally blank 

!

0 10 205 km

±Scale @ A31:500,000

Site LocationFigure NTS 1

Clyde Extension Wind FarmEnvironmental Statement

KeyClyde Extension Site Location

Reproduced from, or based upon the OS map with the sanction of HM Stationery Office Crown Copyright Reserved 100034870CLYDE Ext_FIGURES_Fig 1.1 Site Location

Scale @ A3

!(

Access Route 1

Access Route 1

Access Route 2

Access Route 3

PMM3

PMM2

PMM1

T6ET5E

T9E

T8E

T7E

T4E

T3ET2E

T1E

T42E

T12E

T57E

T10E

T11E

T13ET14E

T17ET16ET15E

T18E

T19ET21E

T20ET23E

T22E

T24E T25ET26E

T27E T28E

T33ET32E

T35ET34E

T31E

T36E T40ET39E

T41ET38ET37E

T43E

T48E

T45ET46E

T47ET49E

T50E

T53E T51E

T54E T56ET55E

T30ET29E

T44E

T52E

0 1 20.5 km

±1:60,000

Application SiteFigure NTS 2

Clyde Extension Wind FarmEnvironmental Statement

Key! Welfare/Store Building & CompoundE Turbine! Permanent Met Mast

Internal Track LayoutAccess RoutesElectrical Control Building & CompoundClyde Substation Building & CompoundCore Development AreaApplication Boundary

Reproduced from, or based upon the OS map with the sanction of HM Stationery Office Crown Copyright Reserved 100034870CLYDE Ext_FIGURES_Fig 1.2 Application Site