Click to edit Master subtitle style
3/15/12
DEPARTMENT OF ENERGY
2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCEREPORT
![Page 2: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/2.jpg)
Click to edit Master subtitle style
3/15/12
Presentation
•Introduction• Branch Performance Reviews
• Support Services (COO, Corporate Services, CFO, Special Programmes and Outreach Projects)
• Hydrocarbons and Energy Planning• Electricity, Nuclear and Clean Energy
• Conclusion
![Page 3: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/3.jpg)
3/15/12
Introduction
Department highlights for the period• Hosting of COP 17 – 23 energy side events,• Completion of the IPP bidding process and announcement of successful
bids for 1415MW,• Launch of the South African Renewable Energy Initiative (SARI),• New Multipurpose Pipeline commissioned, • International engagements, • Relocation of the Department to the old Land Bank building in Pretoria,• Awareness and information sharing sessions held during this period
include ( the PPAA and licensing process), and• Department’s annual planning session held in November 2011.
33
![Page 4: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/4.jpg)
3/15/12
Support ServicesCOO’s Office• November - Department’s annual strategic planning and mid-term
review, submission of Annual Performance Plans, • SOE – oversight; quarterly performance reports to the shareholder,
2012/13 MTEF strategic plan, 2012/13 Annual Performance Plans submitted and discussed, changes in governance structures,
• Department signed agreements/declaration of intent with South Korea, Ghana, Denmark, Lesotho, DRC, International Energy Agency (IEA) and SARI [Germany, Norway, UK, Denmark and the European Investment Bank],
• The agreements cover – access to capacity building, funding, technology, exchange of information and development of energy infrastructure, increase generation capacity
44
![Page 5: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/5.jpg)
3/15/12
Support ServicesCorporate Services Branch• Human Resources
– Total staff compliment as at end December 2011 was 566– Vacancy rate for the period was 7.77%, with 44 vacant posts
mainly from the newly established IPP Unit– The HR Plan was approved end September 2011 and its
implementation is on track– In terms of the Skills Development Plan of the department, a
total of 347 employees received training to enhance performance and productivity, to date,
– Completed the consultation process on the final macro-organisational structure.
55
![Page 6: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/6.jpg)
3/15/12
Support ServicesCorporate Services Branch• Communication
– Public participation Programme – six events for the quarter– 96% of Presidential Hotline queries addressed (INEP and
petroleum licensing), and– 100% media queries responded to.
66
![Page 7: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/7.jpg)
Click to edit Master subtitle style
3/15/12
Support ServicesSpecial Programmes and Outreach Projects
•Women empowerment programmes• C3E Clean Energy women empowerment - Working Groups
institutionalized (mentorships, internships, couching, clean energy ambassadorships, etc)
• Research/study in partnership with UNDP developed for the Barefoot India Women Solar Engineer Project
• 16 Days of Activism for No Violence Against Women and Children• Establishment of the DOE Men’s Forum• In partnership with the Department of Settlements, 16 Solar Panels for
16 Houses during the 16 Days were installed for families of abused and disabled women in Ermelo.
![Page 8: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/8.jpg)
Click to edit Master subtitle style
3/15/12
Hydrocarbons and Energy Planning
Hydrocarbons
•New Multi-product Pipeline:
Q1 and Q2 payments made. Q3 payment effected in January 2012 – payments made in arrears after receipt of progress reports from Transnet.•Regulatory Accounting System (RAS):The RAS margin models and the Regulatory Manual / Guidelines were approved during November 2011.
The RAS margins were incorporated into the December 2011 fuel prices - “Rapid RAS”
• Improve Bio-fuels uptake:The final reports on blending value and break-even costs were submitted via a Ministerial Submission on the 21 December 2011.
The bio-fuels Mandatory Blending Regulations were published on 16 September 2011 for public comments and closed on 18 November 2011.
![Page 9: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/9.jpg)
Click to edit Master subtitle style
3/15/12
Hydrocarbons and Energy PlanningHydrocarbons• Pro-poor (pro-low income households) pricing initiatives – on
paraffin: The Chief Director signed off the submission on 21 December
2011. The purpose of the submission was to request approval to publish the final report for public comments.
• ntegrated Energy Centres (IeCs) established: The construction company for Ulundi IeC moved on site
during December 2011 to prepare the area. The construction for QwaQwa IeC will commence in the first
quarter of 2012. The Chief Directorate wrote submissions to request the extension of the completion deadline to the new financial year.
![Page 10: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/10.jpg)
Click to edit Master subtitle style
3/15/12
Hydrocarbons and Energy PlanningHydrocarbons (contd.)• Strategic Stocks The Draft Strategy document and Cabinet Memorandum
forwarded for approval. The submission has since been approved by the Minister and look set to be presented during March 2012.
• Storage and Distribution/Infrastructure Gap Analysis Report. Infrastructure update done a monthly basis.• Increased domestic refining capacity 20 YLFIRM - 80% of the data has since been collected. Analysis of
the received data has begun with the working groups involved. Furthermore, an extension of the deadline was granted by the Minister to accommodate the expedited Refinery Audit.
• Development of regulations on Liquefied Petroleum Gas (LPG) pricing and LPG licensing framework The Draft LPG Strategy document together with the Cabinet
Memorandum forwarded for internal review.
![Page 11: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/11.jpg)
Click to edit Master subtitle style
3/15/12
Hydrocarbons and Energy PlanningHydrocarbons (contd.)• Revised Fuel Specifications and Standards (Clean Fuels 2) / Regulations
promulgated. CF2 cost recovery mechanism/incentives challenges Stakeholder workshop on Draft Regulations held and the Draft
Regulations sent to Legal Unit for perusal • Legislative Programme
Gas Amendment Bill - internal review done; forwarded for Cabinet presentation
Petroleum Products Amendment Bill – Internal drafting process underway
![Page 12: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/12.jpg)
Click to edit Master subtitle style
3/15/12
Hydrocarbons and Energy PlanningOffice of the Petroleum Controller• One Arbitration request received the Q3– This was not processed
within the 14 day turn around time period. The Complexity of arbitration legal documents and voluminous
supporting documents to be considered in processing the arbitration requests.
• Number of site Inspections 411 Site inspections conducted.
• Educate the public on the PPAA and Licensing Mpumalanga, Limpopo, Durban, Northern Cape, Eastern Cape
and Western Cape conducted their own Awareness Campaign and a schedule for all regions has been set.
![Page 13: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/13.jpg)
Click to edit Master subtitle style
3/15/12
Hydrocarbons and Energy PlanningEnergy Planning• An expert on Scenario Planning was appointed to conduct a review of
the methodology used to determine the scenarios for the IEP. This review is concluded.
• An inter-governmental steering committee on the development of the IEP met on the 17 November 2011. This meeting is part of stakeholder consultation on the IEP.
• Final consultation with the State Law Advisor on the Regulations for the Provision of Energy Data was completed and comments from SLA incorporated. A submission requesting approval of the final regulations by the Minister was circulated before the proclamation by the President.
![Page 14: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/14.jpg)
Click to edit Master subtitle style
3/15/12
Hydrocarbons and Energy PlanningEnergy Planning• The DG’s approval has been obtained for the release of the Energy
Balance data for 2009.• The 2010 Price Report (with data for 2009 and 2010 reports) has been
published. • A Policy Analysis Framework for the IEP has been developed.
![Page 15: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/15.jpg)
Click to edit Master subtitle style
3/15/12
Electricity, Nuclear and Clean EnergyElectricity• Grid connections – Eskom = 43 235, Municipalities 13 463.• Non-grid – 5 764 connections• Two substations completed and 8 under construction• Implementation of IBT in additional municipalities – introduced in Eskom, further implementation in municipalities
Electricity Distribution Infrastructure • Development of a detailed report and implementation plan for each of the 6 Metros on status of the distribution infrastructure the process was completed and a cabinet memo submitted for internal approval
![Page 16: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/16.jpg)
Click to edit Master subtitle style
3/15/12
Electricity, Nuclear and Clean EnergyNuclear• Establishment of the National Nuclear Radioactive Waste Disposal Institute (NRWDI) – NRWDI was listed. No funds allocated yet.• Improvement of legislation governing the nuclear sector – workshop held in November 2011• Nation Nuclear Energy Executive Coordinating Committee has been established, department leads the interdepartmental team
![Page 17: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/17.jpg)
Click to edit Master subtitle style
3/15/12
Electricity, Nuclear and Clean EnergyClean EnergyIPP• First window of the Renewable Energy Independent Power
Producers programme closed on 4th November 2012. 54 proposals received and evaluated. 28 preferred bidders were selected for the REIPP programme.
Solar Water Heaters• 729 from fiscus funding, 47 470 on rebate programme,
Solar park initiative – tender documents have been issued for the feasibility study
![Page 18: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/18.jpg)
Click to edit Master subtitle style
3/15/12
Electricity, Nuclear and Clean EnergyEnergy Efficiency• Energy Efficiency Campaign Strategy was finalised and launched in
December 2011• Energy Efficiency Accord – energy efficiency leadership network and
industry pledges, launched in December 2011.• Energy Efficiency Regulations and tax incentive regulations – Energy
Efficiency regulations were published and closed for public comment on 15 November 2011
Clean Development Mechanism• Transport Sector booklet finalised and printed.• Five workshops held (four provincial and 1 sector)
![Page 19: Click to edit Master subtitle style 3/15/12 DEPARTMENT OF ENERGY 2011/12 FINANCIAL YEAR THIRD QUARTER PERFORMANCE REPORT.](https://reader036.fdocuments.net/reader036/viewer/2022082820/56649e765503460f94b776f0/html5/thumbnails/19.jpg)
3/15/12 1919