CLIC09, Oct. 12-16 T. Higo (KEK)

28
Engineering perspectives on quadrants (1/2) Experience on our first quad (Higo) (2/2) Perspective on quad (Higashi) CLIC09, Oct. 12-16 T. Higo (KEK)

description

Engineering perspectives on quadrants (1/2) Experience on our first quad (Higo) (2/2) Perspective on quad (Higashi). CLIC09, Oct. 12-16 T. Higo (KEK). Contents . Quadrant Fabrication of quads Surface treatment Assembly of four quads Tuning Vacuum c hamber SiC material. - PowerPoint PPT Presentation

Transcript of CLIC09, Oct. 12-16 T. Higo (KEK)

Page 1: CLIC09,    Oct.  12-16 T. Higo (KEK)

Engineering perspectives on quadrants

(1/2) Experience on our first quad (Higo)(2/2) Perspective on quad (Higashi)

CLIC09, Oct. 12-16T. Higo (KEK)

Page 2: CLIC09,    Oct.  12-16 T. Higo (KEK)

Contents

• Quadrant– Fabrication of quads– Surface treatment– Assembly of four quads– Tuning– Vacuum chamber

• SiC material

2CLIC092009/10/12

Page 3: CLIC09,    Oct.  12-16 T. Higo (KEK)

KEK’s version: 50 micron chamfer

Made of CuZr without heat treatment.

50 micron rounding: shape with angles and bumps.

Reference planes were formed by milling in a few micron level without re-chucking for shaping cells.

Assembly was done within ten micron level.

3CLIC092009/10/12

Page 4: CLIC09,    Oct.  12-16 T. Higo (KEK)

Possible cause of high dark currentField enhancement due to round chamfer

• Simulation of field enhancement– 1.4 ~ 1.6 at radius– with gap<radius/5, step<radius/2.5

• Only a few tool passes – to shape 50 micron radius– with radius tool of 2mm• If three passed tangential discontinuity by about 30

degree• Can be relaxed by such as EP in future

2009/10/12-18 4CLIC09 Higo

Page 5: CLIC09,    Oct.  12-16 T. Higo (KEK)

Electric field enhancement in a shallow channel with round chamfer

Gap (micron) Bump (micron) Emax / Enominal

0 0 1.39

0 20 1.57

10 20 1.58

Calculation done by T. Abe by CST MS. Waveguide field.

2009/10/12-18 5CLIC09 Higo

Page 6: CLIC09,    Oct.  12-16 T. Higo (KEK)

Detailed shape at R0.05 chamfer

Cell #9

Cell #10

Cell #11

Only 2~3 tool passes over R0.05 90deg rounding.

Not tangential connection from smooth surface.30-40 degree edge emerges.

Sharp edges or bumps exist at the rim.

6CLIC092009/10/12

Page 7: CLIC09,    Oct.  12-16 T. Higo (KEK)

Production of quadrant Q1-1

7CLIC092009/10/12

Green lines are ±2.5 microns.Followings shows worst part out of four measured areas along the axis.

Local shape is smoothly connected.

Page 8: CLIC09,    Oct.  12-16 T. Higo (KEK)

Cleaning: no etching • Alcohol bath – with ultra-sonic vibration for 5 minutes.

• Acetone bath twice – with ultra-sonic vibration for 5 minutes.

• Nitrogen blow• Storage in a deccicator– Initially filled with nitrogen gas.– Storage for more than a month.

8CLIC092009/10/12

Page 9: CLIC09,    Oct.  12-16 T. Higo (KEK)

Carry and storage

Edge inspection

First hanging

Check ball diameter

Prepare next quad approach

Second hanging

Assembly

9CLIC092009/10/12

Page 10: CLIC09,    Oct.  12-16 T. Higo (KEK)

Fine adjustment

Fixing by bolt

Completion of stack

Alignment checking

RF setupManual adjustment before final pressing, without ball and groove mechanism. Misalignment: within ten microns.Reproducibility: a few microns.

10CLIC092009/10/12

Page 11: CLIC09,    Oct.  12-16 T. Higo (KEK)

Final alignment

-10 -8 -6 -4 -2 0 2 4 6 8 10

-10

-8

-6

-4

-2

0

2

4

6

8

10Output side (C-plane)

Q1-2

Q1-1

Q2-1

Q2-2

-10 -8 -6 -4 -2 0 2 4 6 8 10

-10

-8

-6

-4

-2

0

2

4

6

8

10

Input sideQ1-1

Q1-2

Q2-1

Q2-2

X

Y

Z

C-plane

IN OUTMisalignment of each quadrantw.r.t. the average of four quadrants (units are in micron)

11CLIC092009/10/12

Page 12: CLIC09,    Oct.  12-16 T. Higo (KEK)

Elastic tuning with a ball being kept push

4mm stainless ball pushed by minus watch driver.Pushing by turning with Higo’s hand full force.Elastic deformation kept, meaning that the tuning pins are kept pushing the balls.

12CLIC092009/10/12

Page 13: CLIC09,    Oct.  12-16 T. Higo (KEK)

Notice: Deformed cavity wall

Cell 3(×35)

Cell 3(×100)Cell3 deformation: 0.053mm

Cell 8(×35)

Cell 8(×100)Cell8 deformation: 0.167mm

Cell 10(×35)

Cell 10(×100)Cell10 no tuning

13CLIC092009/10/12

Page 14: CLIC09,    Oct.  12-16 T. Higo (KEK)

Field smoothness after tuning good.

3

3.5

4

4.5

5

0 5 10 15 20

Raw amplitude of bead pull measurementbead pull # 14-20-28-32

Amp 14amp 20Amp 28

Amp 32

Amplitude

LabVIEW Cell #14CLIC092009/10/12

Page 15: CLIC09,    Oct.  12-16 T. Higo (KEK)

Vacuum chamber design

U-tight seal (round metal gasket)VCR connector for cooling water connectionThin H-bend being vac sealed with bellowsVac evacuation from CF114 mounted on chamber with IP 70l/s and from WR90 at just 0.5m from structure

15CLIC092009/10/12

Page 16: CLIC09,    Oct.  12-16 T. Higo (KEK)

Installation into chamber

16CLIC092009/10/12

Page 17: CLIC09,    Oct.  12-16 T. Higo (KEK)

Evacuation with quad structure

10-5

10-4

10-3

10-2

0.1 1 10 100 1000

VacantChamberEvacuation

CCG Vacant chamberChamber RRGBetween TMPCCG [Pa] with Quad structureChamber FRG [Pa]Between TMP

CCG, FRG [Pa]

Evacuation period [hour]

as of 090612

With quads need baking of quad

Bare chamber after bake OK

17CLIC092009/10/12

Page 18: CLIC09,    Oct.  12-16 T. Higo (KEK)

First installation to Nextef but,

10-6

10-5

10-4

10-3

10-2

80 160 240 320 400 480

Chamber EvacuationCCG Vacant chamberChamber RRGBetween TMPCCG [Pa] with Quad structure 1stChamber FRG [Pa]Between TMPCCG [Pa] with Quad structure 2ndChamber FRG [Pa]Between TMP

CCG, FRG [Pa]

Evacuation period [hour]

as of 090622

1. Firstly baked without quads at ~200C Reached 10^-5Pa2. Quad into chamber 10^-4Pa3. Then baked with quads ~200C Reached 10^-6Pa4. Moved to Nextef but the

stuck gaskets prevent quad from connection to waveguide Removed gaskets by oil-less milling with cutting flange surface Reinstalled into chamber without baking.

18CLIC092009/10/12

1.

2.

3.

4.

Page 19: CLIC09,    Oct.  12-16 T. Higo (KEK)

Installed into Nextef

Nextef setup

3dB phase check

Input connection

19CLIC092009/10/12

Page 20: CLIC09,    Oct.  12-16 T. Higo (KEK)

Evacuation of quad at Nextef

1.00 10.00 100.00 1000.00 1E-06

1E-05

1E-04

1E-03CCGFRG

Hours

Pa

Quadrant chamber vacuum

Evacuation with TMP through CF114Prepare IP with baking, while evacuation by TMP through ICF70

Start evacuation by IP

Evacuation July 17-24

-50.00 0.00 50.00 100.00 150.00 200.00 250.00 1E-07

1E-06

1E-05

ChamberACC-INACC-OUTChamberACC-INACC-OUT

7/31RF ON

Evacuation with IP

Reached 10^-6Pa with IP Then RF-ON

20CLIC092009/10/12

Page 21: CLIC09,    Oct.  12-16 T. Higo (KEK)

Vacuum of quad

• Base pressure reached 10-6Pa– Nearly one order of magnitude worse than T18_Disk (a

few 10-7Pa)– Taking good vacuum conductance from gauge to RF

pass, vacuum level inside is estimated to be close to T18_Disk

• Gas activity with RF– Should carefully be studied to see what is happening

inside due to RF and sometimes breakdowns– We may get some hint to understand breakdown

2009/10/12 CLIC09 21

Page 22: CLIC09,    Oct.  12-16 T. Higo (KEK)

Hitachi’s second try of quad fab.

• Hitachi engineer tried again a quad test production.

• It reached the similar level as those of Quad#5.• Milling done with 3D milling machine but adding

another rotational motion.

• Company engineers are interested in the quad production.

• They are watching our perspective.

2009/10/12 CLIC09 22

Page 23: CLIC09,    Oct.  12-16 T. Higo (KEK)

Conclusion to pass to Higashi’s talk• First Quad by KEK was now in high power test.• Many features are still in question – responsible for the poor high gradient property?

• However, we want to use it as our education to understand breakdown.

• Quad approach: – We need to establish high gradient first, – Taking mass production perspective in mind. – Higashi

2009/10/12 CLIC09 23

Page 24: CLIC09,    Oct.  12-16 T. Higo (KEK)

Some information on Lossy material

• SiC being studied by Y. Takeuchi– Based on material for HOM absorber of KEKB

500MHz cavity • SuperB chose low current/low emittance design• No extra funding for higher frequency development

– Tried tuning to higher frequency• By changing doping amount

– Mostly by two companies• Covalent and Hitachi chemical

24CLIC092009/10/12

Page 25: CLIC09,    Oct.  12-16 T. Higo (KEK)

Adjustment of the permittivity of SiC ceramics

Schematic Model of SiC Ceramics Two-layer Model and Equivalent Circuit

By doping Al-compound, we have tried to increase the carrier concentration in the grain. >>>>> The relaxation time (~ CdRg) will change.

Y. TAKEUCHI (KEK) and M. ANDO (Covalent Materials Corporation)

Y. Takeuchi (KEK)

25CLIC092009/10/12

Page 26: CLIC09,    Oct.  12-16 T. Higo (KEK)

Al : 420 ppm(wt)Relaxation time t ~1.6x10-10 secResistance 19 MW (1 cm)* Relaxation frequency = 1/(2pt)

Al : 650 ppm(wt)Relaxation time t ~1.6x10-11 secResistance 0.8 MW (1 cm)

Results of the doping (preliminary)Y. Takeuchi (KEK)

26CLIC092009/10/12

Covalent work in collaboration with KEK.

Page 27: CLIC09,    Oct.  12-16 T. Higo (KEK)

SiC ceramics for higher frequencyproduced by HITACHI CHEMICAL

For KEKB ARES cavity Developed to higher frequency

Y. Takeuchi (KEK)

27CLIC092009/10/12

Hitachi Chemical did try and KEK measured.

Page 28: CLIC09,    Oct.  12-16 T. Higo (KEK)

For further info on SiC• Please contact Takeuchi for further info in general.• You can directly contact Covalent or Hitachi

Chemical, for technical info and for production capability.

• KEK may make for accelerator structure use, depending on the success of TD24.

• If more for PETS– probably better to control production process by those

who make PETS with the actual production company.

2009/10/12 CLIC09 28