Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Transcript of Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk...

Page 1: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Mads Hembre

Leading Advisor Risk Management in Projects

Risk Management – “A picture of understanding and prioritization”

Page 2: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Page 3: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Page 4: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Summary Slide

•Step by step…

•Continuous improvement

•Homepage Network

•Presentations, tools, request, examples…

•Risk module users

•The Risk Management process

•Users from different BU’s

•From web to R3

•Risk module

Page 5: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Summary Slide (cont.)

•Risk actions and quality control activities

•Risk based monitoring

•Functional Description - QRM

•Stakeholder and risk management

•Cost assessment

•Cost impact

•Ambition to Action - risks

•Aggregation of Risk Management

•Network and seminars with participation outside PRC

•Participating in external boards, networks, seminars

Page 6: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Step by step…2007 2008 2009 2010 2011 2012 2015

Revision of WR2404

WR2404 “Shall” WR2365

PRO UPN, TNE, INT, NG, GBS

WR2365

RM in FR05

GLxx One documentAggregation

Risk strategy

Global

“Customers”

Governing documents

GL DGSP GL Stakeholder

Mgt

Page 7: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Step by step…2007 2008 2009 2010 2011 2012

New Scale

Risk Lite

R3

”Logical aggregation”

Contingency vs Register

Action calculation

Available checklists

“Total risk picture”

Risk profile

New Web

Target Cost

Risk based Monitoring

Development

”Reports across”

”aggregation”

Page 8: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Continuous improvement2007 2008 2009 2010 2011 2012 2015

Risk based Monitoring

•Context•Description•Action strategy

”More quantitative”

Project Managers agenda

Aligned scales

Aligned cause categories

Aligned – terms/process

Awareness

“Standard”

Risk based processes“Risk Mgt for Mgt”

Risk based experience

Page 9: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Homepage Network

Page 10: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Presentations, tools, request, examples…

Page 11: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Risk module users

Development users - Risk module

0

200

400

600

800

1000

1200

Octber

- 20

07

Janu

ary - 2

008

May

- 20

08

Septe

mbe

r - 2

008

Octobe

r - 2

008

Novem

ber -

200

8

Decem

ber -

200

8

Janu

ary - 2

009

Febru

ary -

200

9

Mar

ch -

2009

April -

200

9

May

- 20

09

June

- 20

09

July

- 200

9

Augus

t - 20

09

Septe

mbe

r - 2

009

Octobe

r - 2

009

No of users

Page 12: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

The Risk Management process

Page 13: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Users from different BU’s

87

593

3682 97

649

554

0

100

200

300

400

500

600

700

GBS UPN INT M&M NG PRO TNE

User pr BU last 6 months

* Some few CFO users added to GBS

Page 14: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Risk module

Matrixes

Action list

Risks list

Risk

Action

Reports

Page 15: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Risk actions and quality control activities

Project Subprojects Contracts

Risk Identification Risk Action

Quality System

Audit

Contract/discipline

Examination

Assignment Notify Prepare Execute Report

Observations

Close-outFollow up

Disciplines

Risk Assessment Risk Control

Page 16: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

A

Input

Risk based Monitoring

Risk Module

Risk Breakdown Structure / WBS

Monitoring Module-Quality-HSE

Categories /Disciplines

1. Target

2. Outcome

3. Objectives/

strategy

Page 17: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Risk based monitoring

•Monitoring Activities are one of the tools we have to mitigate threats

•Risk actions can be classefied as follow up or monitoring activity.

Page 18: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Stakeholder and risk management

Page 19: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Cost assessment

50% ? %

Contingency

Deviation

•Cost•Progress•Both

Reserve

CCE

Page 20: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Cost impact

Page 21: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Aggregation

Business Cluster

Field Projects

Projects

Top 10 pr. MPPx

Top 10 pr.

field1

Top 10 domen

e

ODV

MPPx

Oseberg Troll Gullfaks Other

V&M XB&B YPRO MODProject A

V&M X

B&B YPRO MODProject A

V&M ZV&M CB&B APRO MODProject A

V&M AB&B APRO MODProject A

Page 22: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Network and seminars with participation outside PRC

•Risk network meeting 2008

•Quality and risk network meetings with external participations

– 2009 (8/10 score from participants)

– 2010 (8/10 score from participants)

•Risk day with UPN, training of risk mgt resources UPN

•Training of Contractors in UPN (V&M)

•Risk Management presentations (SINTEF, Forsvaret, Proactima, UiS, other internal departments, TNE, GBS, INT)

•Understanding Statoil Way (internal participations)

Page 23: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Participating in external boards, networks, seminars

•Prosjekt 2009

– Leading adv risk management : Speech

•Energy Project Management 2009

– Leading adv. risk management : Speech

•Lifecycle Risk Management For Offshore Renewable

– Risk Management: Speech

•Kvalitetsdagene 2010: Leading advisor risk management : Speech

•Local seminars NFKR: Speeches (Stavanger)

•Presentation of Risk Mgt for different students (Stavanger, Trondheim)

Page 24: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Supporting universities/academia/corporate trainees, coursesMASTER STUDENTS

• Several master students have had leading advisors as during the master thesis work

– Camilla Knatten, Hanne Eng Sørlid, Valiander Shaila

• These activities secure recruitment of young professionals into project control, provides good relations with academia and provide the leading advisor with new ideas.

• PROJECT ACADEMY

– Basic, Essential, Field Dev.

– One day risk course (4 times a year)

– Business Development – Risk Course

– ½ day risk based monitoring

– ½ day risk management GBS

• PUS – Praktisk usikkerhetsstyring (Statoil, Telenor, Forsvaret, Vegvesnet, Jernbaneverket, Statsbygg) – research program 2006-2010

– Several master students, 1 doctor Hans Petter Krane

– Several workshops, forum days with involved partners (Statoil arrange 1)

Page 25: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

From web to R3

Risk module

Monitoring module

Supplier info.EXperienceTRAnsfermodule

•Risk Management Module

•Monitoring Module

•Experience Transfer Module

•Link supplier information

Page 26: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Adjustments…

P1-25

P1-5 P5-25 P50-100

P50-75 P75-100

Page 27: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Aggregation of Risk Management

PRO LED

Business Cluster

Business Unit

Field Projects

Projects

Top 10 pr. cluster2

Top 10 pr. unit2

Top 10 pr.

field1

Top 10 pr.

project1

PRO Top 10 Risk Register2

PRO

PRO ONO

PRO ONO Bergen

Oseberg Troll Gullfaks Other

Project AProject BProject C

Project AProject BProject C

Project AProject BProject C

Project AProject BProject C

Page 28: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

41

Sleipner

MPPx

MPPB MPPN

SnorreStatfjord

Huldra

Norne SnøhvitNjordKristinHeidrunKvitebjørn

HeimdalGullfaksGraneGlitneGimleBrage

Åsgard

MPPS

OsebergTordisVeslefrikk Troll

Aibel

VisundVolve

AOP tampen

Reinertsen

Aker/ Reinertsen

Deutag/KCASeawell

Odfjell

Keppel

AOPMaersk

Ved aggregering fra ”underliggende” domener vil Ved aggregering fra ”underliggende” domener vil all relevant identifikasjons informasjon bli all relevant identifikasjons informasjon bli aggregert opp til overliggende domener aggregert opp til overliggende domener

SNOREV

RS2010

Page 29: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Distribute risks

SDT Project ASub Project level

Project B

Project C

Project D

Page 30: Classification: Internal 2010-11-26 Mads Hembre Leading Advisor Risk Management in Projects Risk Management – “A picture of understanding and prioritization”

Classification: Internal 2010-11-26

Risk Management – A picture of understanding and prioritization

Mads HembreLeading Advisor Risk Management in [email protected], tel: +47 51 99 00 00www.statoil.com

Thank you

47

“the essence of project management is risk management”