City of Buda Wastewater Master Plan

19
PLANNING | ENGINEERING | PROGRAM MANAGEMENT City of Buda Wastewater Master Plan Final Report Presentation Graham Moore, PE October 16, 2012

Transcript of City of Buda Wastewater Master Plan

PLA

NN

ING

|

EN

GIN

EE

RIN

G

| P

RO

GR

AM

MA

NA

GE

ME

NT

City of BudaWastewater Master Plan

Final Report Presentation

Graham Moore, PE

October 16, 2012

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Summary

Purpose:

Provide a plan for the City as to the required improvements and

additions necessary to convey and treat wastewater through 2040.

Agenda:

• Background

• Council Direction on WWTP Location

• Growth Projections

• Sewer CAD Model Development and Analysis

• Recommendations

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Background

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Buda WWTP Sunfield WWTPExisting Capacity 1.5 MGD 0.25 MGDTreatment Process Complete‐mix Extended‐aerationExisting Permit

(CBOD – TSS – N – P) 7 – 12 – 2 – 1.2 5 – 5 – 2 – 1

Future Capacity (Permitted)

1.5 MGD 0.99 MGD

Future Permit(CBOD – TSS – N – P) 5 – 12 – 2 – 0.8 5 – 5 – 2 – 1

Ultimate Capacity(Possible On Site)

4.0 MGD 5‐7 MGD

Ultimate Treatment Process Complete‐mix Complete‐mixPotential Re‐use Type I Type I

Ultimate Needs for Sunfield ‐ 3.0 MGD

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Wastewater Treatment Plant - Options

Options Considered:

• Option 1 – Approx. 1.0 MGD of Buda wastewater treated at Sunfield

WWTP & 3.0 MGD treated at Buda WWTP

• Option 2 – Buda WWTP converted to a lift station (LS) and all Buda

wastewater treated at Sunfield WWTP

• Option 3 – All Buda wastewater treated at Buda WWTP

• Option 4 – Buda WWTP limited to 1.5 MGD & Sunfield WWTP

expanded 2.5 MGD

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Wastewater Treatment Plant - Options

Options Considered:

• Option 1 – Approx. 1.0 MGD of Buda wastewater treated at Sunfield

WWTP & 3.0 MGD treated at Buda WWTP

• Option 2 – Buda WWTP converted to a lift station (LS) and all Buda

wastewater treated at Sunfield WWTP

• Option 3 – All Buda wastewater treated at Buda WWTP

• Option 4 – Buda WWTP limited to 1.5 MGD & Sunfield WWTP

expanded 2.5 MGD

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Option Selected by Council on January 3, 2012

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Option 4 Development

Scenario Highlights

• Requires agreement with GBRA to expand the Sunfield WWTP

• Sunfield WWTP becomes a regional plant

• Existing “Downtown” WWTP stays at current 1.5 MGD capacity

• Requires new regional lift station to replace the Night Hawk lift

station to convey flow from west to east

• Convert flows from South Buda WCID #1 to discharge directly to

Sunfield WWTP

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Growth Projections

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

11,024

15,061

19,912

25,452

31,690

38,574

45,987

2.80

3.013.17

3.293.38 3.45 3.50

0.0

1.0

2.0

3.0

4.0

0

10,000

20,000

30,000

40,000

50,000

2010 2020 2030 2040

Avg. Hou

seho

ld Size

Popu

latio

n

Year

Population Growth

Avg. Household Size

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Sewershed Map – Growth Projections

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Sewershed Map – Growth Projections

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Sewer CAD Model Development and Analysis

Model Setup:

• Entered actual flowline data from as-built drawings for the City

• Average daily flows were entered into the model based on lot counts

or water meter size

• Setup controls for lift stations to simulate actual operations

• Model estimated average flows of 1.017 MGD for the existing

condition; recorded inflow was 1.005 MGD (1.2 % error)

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Sewer CAD Model Development and Analysis

Residential Diurnal Curve:

• Peaks in morning (~7:30AM)

and in Evening (~9:30PM)

• Peak is 1.5 times average flow

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Non-Residential Diurnal Curve:

• Peaks between 8 AM and 6 PM

• Peak is 2.0 times average flow

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Sewer CAD Model Development and Analysis

Analysis:

• Future growth demands were loaded into the model based on the

future projections discussed previously

• Model was run to simulate ultimate conditions (2040) to identify

system deficiencies and ultimate capacities

• Model was then run to simulate years 2030, 2020 and 2015 to identify

timing and phasing of proposed improvements

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Map of Improvements

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Recommendations

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Priority Rank Proposed BudgetYear(s)

Project Title

1 2011‐2013 DowntownWastewater Rehab2 2012‐2013 Sportsplex Sewer Line Upsize3

2012‐2013Bradfield‐Lifschutz‐Stonefield

Interceptor (BLSI) Flow Monitoring Study

4 2013‐2014 Garlic Creek Lift Station5 2013‐2014 Lifschutz Bottleneck Replacement6 2013‐2015 S. Loop 4 LS Decommissioning & 

Gravity Extension7 2013‐2015 Stonefield LS and Force Main to 

Sunfield8 2014‐2015 Sunfield WWTP 0.5 MGD Capacity9 2016‐2017 Oxbow Interceptor

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Recommendations

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Priority Rank Proposed BudgetYear(s)

Project Title

10‐A 2016‐2020 WCID #1 LS Relocation & Hillside Terrace Interceptor

10‐B 2016‐2020 Main Street FM Phase 110‐C 2016‐2020 Sunfield WWTP 1.0 MGD Capacity 

(Cumulative)10‐D 2016‐2020 Overlook LS & FM Improvements10‐E 2016‐2020 Old Nighthawk LS Decommissioning15‐A 2021‐2030 Main Street FM Phase 215‐B 2021‐2030 Night Hawk LS Upgrade15‐C 2021‐2030 Sunfield WWTP 1.5 MGD Capacity 

(Cumulative)15‐D 2021‐2030 Meadows at Buda Interceptor

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Recommendations

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Priority Rank Proposed BudgetYear(s)

Project Title

15‐E 2021‐2030 West FM 967 Upsize15‐F 2021‐2030 West FM 967 LS & FM21‐A 2031‐2040 Buda Elementary LS Upgrade21‐B 2031‐2040 FM 2001 Wastewater 

Improvements21‐C 2031‐2040 Sunfield WWTP 2.5 MGD Capacity 

(Cumulative)21‐D 2031‐2040 Onion Creek Interceptor21‐E 2031‐2040 SE Buda LS & FM #2

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

Recommendations

Non-Project Related Recommendations:

• Flows at Downtown WWTP will likely pass the 75% threshold by next

Summer – triggers design for next treatment phase

• Continue to monitor growth to determine when projects need to occur

• Update SewerCAD model with new sewer lines/development every

other year (or as needed)

• Use the Master Plan with developers for discussions related to sewer

service to new areas

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

GBRA Partnering

Memorandum of Understanding (MOU):

• Staff has discussed an MOU with GBRA for preliminary engineering

on the Sunfield Plant.

• MOU will be brought to Council on 10/30.

• City’s participation in preliminary engineering will be capped at

$40,000.

• MOU states that future agreements are anticipated that will discuss

plant ownership, phasing, operations, etc.

• MOU will expire in approximately 6 months unless extended by

Parties; City has right to terminate if it gives 30 days notice.

PLANNING | ENGINEERING | PROGRAM MANAGEMENT

PLA

NN

ING

|

EN

GIN

EE

RIN

G

| P

RO

GR

AM

MA

NA

GE

ME

NT

QUESTIONS