CHAPTER 8 ADDITIONAL STUDIES
-
Upload
cidconmiacom -
Category
Documents
-
view
247 -
download
1
Transcript of CHAPTER 8 ADDITIONAL STUDIES
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
1/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 1 of 91
CESE, IIT Mumbai CIDCO
Chapter-8
Additional Studies8.0 INTRODUCTION
Based on the TOR specified by the Ministry of Environment & Forest, number of
additional studies was carried out to fulfill the requirement of EIA study. The studies
are:
a) Legal Opinion on Permissibility of Activities in CRZ Area.
b) Re-coursing Channel.
c) Re-orientation of runway study.
d) Ground Water Study.
e) Vaghvli Island and coastal line study.
f) Mathematical & Physical Model study.
g) Mangrove analysis, plantation and management study.
h) Air & Noise Assessment.
i) Rehabilitation & Re-settlement ( R & R ) Plan
8.1 Legal Opinion on Permissibility of Activities in CRZ Area
The various activities, such as, mangrove cutting/destruction, diversion and training
of rivers, quarrying and cutting of mountain and earth, reclamation, alteration in tidal
pattern, permissibility of airport related activities pointed out in the approved Terms
of Reference prescribed by Ministry of Environment & Forest for Environment
Impact Assessment (EIA) needs to be examined legally in the light of CRZ
Regulation, 1991 Notification as amended upto 15th May, 2009. Our legal
Consultant, M/s.Hemant Sahai & Associates, one of the top 5 Law Firms of India in
the field of Projects, Infrastructure & Energy, have examined the permissibility of
above activities and offered their legal opinion quoted below:
BACKGROUND FACTS :
1. City and Industrial Development Corporation of Maharashtra Limited
(CIDCO) has been appointed as the nodal agency for implementation of the
Navi Mumbai International Airport (NMIA). The site selected for the Project
falls in the Navi Mumbai area and certain parts of the site fall within the
Coastal Regulation Zone (CRZ) as per the approved Coastal Zone
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
2/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 2 of 91
CESE, IIT Mumbai CIDCO
Management Plan (the CZMP) of Navi Mumbai. CIDCO has presented its
proposals before the Maharashtra Coastal Zone Management Authority
(MCZMA) and subsequently before the Ministry of Environment and Forests
(MoEF) for CRZ clearance and approval of the Terms of Reference (TOR)
for environment clearance, respectively. The MCZMA has recommended the
case to the MoEF for CRZ clearance. The MoEF has finalized the TOR for
project for carrying E.I.A. study for environment clearance.
2. We also understand that the land area earmarked for the development of the
NMIA includes land which is intended to be developed for aeronautical
related activities as well as for non - aeronautical activities such as office,
residential and other economic activities for supporting the airport.
Furthermore we have also been given to understand that to make available
the land required for the proposed airport development CIDCO proposes to
train and divert two rivers viz. Gadhi and Ulwe that presently run their
respective courses through the proposed site for the NMIA.
3. Diverse correspondence has been exchanged between CIDCO, MCZMA,
MoEF and other authorities, the relevant ones of which have been referred to
in our opinion herein below.
4. CIDCO has sought our opinion generally on several issues and in particular
on the following issues :
(i) Mangrove cutting/destruction
(ii) Diversion & Training of rivers
(iii) Quarrying & cutting of mountain and earth.
(iv) Reclamation
(v) Alteration in tidal pattern
(vi) Clarification required related to High Court Orders on destruction of
mangrove.
(vii) Permissibility of airport related activities (such as, office, residential,
Hotel, etc.).
5. In the above background, we have been asked to provide our legal opinion
on diverse issues relating to the environmental aspects of the project. These
queries can broadly be classified under the following heads :
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
3/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 3 of 91
CESE, IIT Mumbai CIDCO
(i) Legal interpretation of the CRZ Notification dated 19 February, 1991 as
amended vide order/circular bearing number S.O.114 (E) dated 15 May,
2009;
(ii) What permissible construction and other activities can be undertaken by the
developer of the airport/CIDCO on the airport project site;
(iii) Steps to be taken by CIDCO in relation to the presence of mangroves on the
site, especially in view of the judgment of the Honble High Court of Bombay
dated 6 October, 2005 in W.P (lodging) No.3246/2004 later renumbered as
PIL No. 87 of 2006;
(iv) Any other issues.
DOCUMENTS REVIEWED :
1. We have examined the following documents and statutes:
(i) In principal approval of the Ministry of Civil Aviation dated 6 July 2007 for
setting up Green Field Airport at Navi Mumbai
(ii) GoM GR dated 30 July 2008 granting approval to the Airport at Navi Mumbai.
(iii) Gazette Notification S.O No.1243 (E) dated 15 May 2009 regarding
amendment of CRZ Notification, 1991;
(iv) CRZ Notification, 1991 issued by MoEF vide S.O 114 (E) with amendment
upto 15 May 2009 [except S.O 635(E)];
(v) Mumbai High Court Order dated 6 October 2005 in W.P (lodging)
No.3246/2004;
(vi) High Court Order dated 29 April 2009 in Notice of Motion 116/2009in PIL No.
87/ 2006;
(vii) High Court Order dated 28 July 2008 in Notice of Motion Nos. 538/ 2006 and
245/ 2006 in PIL W.P No. 87/ 2007;
(viii) High Court Order dated 8 October 2008 in Notice of Motion Nos. 538/ 2006
and 245/ 2006 in PIL W.P No. 87/ 2007;
(ix) Proposed Terms of Reference (Proposed TOR) dated 16 June 2009 by
CIDCO to MoEF.
(x) Draft report on the Re-orientation of Runways to save mangroves
(xi) Plans depicting proposed amendments to the approved Navi Mumbai CZMP
submitted by CIDCO to MCZMA for CRZ Clearance
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
4/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 4 of 91
CESE, IIT Mumbai CIDCO
(xii) Letter dated 3 July 2009 by CIDCO to MCZMA requesting for CRZ Clearance
and setting out action taken and summary of the studies undertaken by
CIDCO.
(xiii) Presentation by CIDCO dated 16 July, 2009 and its minutes of the 54th
Meeting of the MCZMA dated 16 July 2009 (Minutes);
(xiv) Presentation by CIDCO dated 21 July 2009 to the Expert Appraisal
Committee (EAC), MoEF on NMIA;
(xv) Minutes of 78th Meeting held on 20 to 22 July 2009 of the EAC for CRZ,
Infrastructure Development and Miscellaneous projects; and
(xvi) Terms of Reference (TOR) dated 4 August 2009 issued by the Expert
Advisory Committee (EAC) of the Ministry of Environment and Forest
(MoEF);
(xvii) Letter dated 7 August 2009 by MCZMA to the MoEF recommending the
proposal of CIDCO for the development of NMIA along with the Minutes of its
54th Meeting;
(xviii) Airport Authority of India Act, 1994 (the AAI Act);
(xix) Aircraft Act, 1934 (the Act);
(xx) Information furnished during conferences.
A. Legal interpretation of the CRZ Notification dated 19 February, 1991and
amendment dated 15 May 2009 to the CRZ notification.
1. By virtue of the CRZ Notification dated 19 February, 1991 (the Notification)
the Central Government has declared the coastal stretches of seas, bays,
estuaries, creeks, rivers, and backwaters which are influenced by tidal action
in the landward side upto 500/100 (in creek area) metres from the High Tide
Line (HTL) and the land between the Low Tide Line (LTL) and the HTL as
Coastal Regulation Zone (CRZ). The Central Government has further
imposed certain restrictions on the setting up and expansion of industries,
operations or processes within the CRZ.
2. The said Notification has been amended from time to time. Vide an
order/circular bearing number S.O.114 (E) dated 15 May, 2009 the Ministry of
Environment and Forests (the MoEF) amended the Notification and
exempted the development of the NMIA from the list of prohibited activities,
however, this exemption has been made subject to certain conditions,
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
5/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 5 of 91
CESE, IIT Mumbai CIDCO
including conducting of a detailed scientific study and incorporation of
adequate environmental safeguard measures for neutralizing damage to
coastal environment in the Navi Mumbai region.
3. The Proviso to clause (i) of paragraph 2 of the CRZ Notification dealing with
Prohibited Activities reads as follows Provided further that the development
of green field Airport at Navi Mumbai shall be undertaken subject to detailed
scientific study for incorporating adequate environmental safeguard measures
required for neutralizing damage to coastal environment as may be
appropriate to the Navi Mumbai region.
4. Hence, while the Notification discourages setting up of new industries and
expansion of existing industries within the CRZ, vide the amendment dated
15 May, 2009, the Notification specifically exempts the development of the
NMIA subject to the conditions stated above. It can also be observed that the
amendment to the Notification has factored in the possibility and obvious
impact/damage which will necessarily be caused to the coastal environment
in and surrounding the area earmarked for the development of NMIA. The
language of the Notification clearly implies that the Developer of the NMIA is
expected to develop the NMIA all the while ensuring that adequate
environmental safeguard measures are adopted to neutralize the damage
that will necessarily be caused due to the development activities.
B. What are the permissible construction and other activities that can be
undertaken by the developer of the airport/CIDCO on the airport project site?
1. For the purposes of developing the NMIA at the site selected for the airport, CIDCO
would be required to undertake several activities such as land reclamation, bunding,
training of rivers etc. The provisions of clause (viii) of paragraph 2 of the said
Notification dated 19 February, 1991 specifically prohibits - Land reclamation,
bunding or disturbing the natural course of sea water except where required for
construction, modernization or expansion of ports, harbours, and for other
facilities that are essential for activities permissible under the notification. Since the
development of the NMIA is exempted as a prohibited activity under the Notification
and the activities related to its development would be termed as essential, the
restrictions in this clause would not be applicable to the NMIA project, i.e. the
Developer/CIDCO will be permitted to undertake construction including training &
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
6/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 6 of 91
CESE, IIT Mumbai CIDCO
diverting the natural course of creek water for developing the airport and its various
facilities including aeronautical and non-aeronautical activities.
2. It may also be noted that the proviso to clause (viii) of paragraph 2 specifically
provides that reclamation for commercial purposes such as shopping, housing
complexes, hotels and entertainment activities shall not be permissible.
Furthermore, Clause (xi) of paragraph 2 of the CRZ Notification dated 19 February,
1991 prohibits construction activities except as permitted in the Coastal Area
Classification and Development Regulations (the Regulations). The Regulations
classify the coastal areas within 500 meters of the HTL on the landward side into
four categories/ zones CRZ-I, CRZ-II. CRZ-III and CRZ-IV, for the purpose of
regulating development activities in such areas.
(a) Category I (CRZ-I) includes areas that are (i) ecologically sensitive and
important and (ii) Area between the LTL and the HTL.
(b) Category II (CRZ-II) includes areas that are already developed up to and
close to the shoreline
(c) Category III (CRZ-III) includes areas that are relatively undisturbed and those
which do not belong to either Category I or II.
(d) Category IV (CRZ- IV) includes the coastal stretches in the Andaman and
Nicobar, Lakshwadeep and small islands, except those designated as CRZ-I,
CRZ-II or CRZ-III.
3. The Regulations specify various norms to regulate permissible activities as well as
the development/ construction activities in the different categories set out above, at
the State/ Union Territory (UT) level. The relevant norms are as follows:
(a) CRZ- I: For areas between the HTL and the LTL falling in the CRZ- I
category, and which are not ecologically sensitive and important, the
development of the Greenfield airport and related activities at Navi Mumbai is
permitted.
(b) CRZ- II: For areas falling in CRZ-II category, the development/ construction of
facilities for receipt and storage of petroleum products such as Aviation Fuel,
High Speed Diesel; and Liquefied Natural Gas (LNG) is permitted. Further the
development of the Greenfield airport and related activities at Navi Mumbai
may also be permitted in these areas.
(c) CRZ- III: For areas falling in CRZ-III category, the development of the
Greenfield airport and related activities at Navi Mumbai is permitted. Further
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
7/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 7 of 91
CESE, IIT Mumbai CIDCO
the development of vacant plots between 200 and 500 metres of the HTL in
designated areas may be permitted with the prior approval of the MoEF for
construction of hotels/ beach resorts for temporary occupation of tourists/
visitors subject to the conditions set out in clause 7(1) of the Notification
dated 19 February, 1991, in this behalf.
4. Therefore, on the face of it, in view of the aforesaid provisions, it would appear that
the development of the NMIA is permitted in CRZ-I (ii), CRZ-II and CRZ-III.
However, in view of our discussions below, eventually these restrictions may not
apply to the project since, these and other restrictions specified in the CRZ
Notification dated 19 February, 1991 would be attracted only so long as an area
qualifies as a CRZ. Once an area ceases to be a CRZ, then the provisions of the
CRZ Notification dated 19 February, 1991 would cease to be applicable and
therefore, the restrictions under the aforesaid clauses of the Notification too would
not be applicable. Therefore it follows that, once the site or parts thereof of the NMIA
airport project cease to be a CRZ, the restrictions contained in the CRZ Notification
dated 19 February, 1991 would also cease to be applicable.
5. The first relevant issue to be considered in this context is - what constitutes a CRZ
area? The answer is provided in the CRZ Notification dated 19 February, 1991 itself,
which defines a CRZ area as follows - the Central Government hereby declares the
coastal stretches of seas, bays, estuaries, creeks, rivers and backwaters which are
influenced by tidal action (in the landward side) upto 500 meters from the High Tide
Line (HTL) and the land between the Low Tide Line (LTL) and the HTL as Coastal
Regulation Zone1;
6. A reading of the above definition clearly indicates that a CRZ is identified and
designated based on the tidal action of a specified water body, including a river that
is influenced by tidal action in the landward side. Thus any area falling within 500
meters from the HTL and also the land falling between the HTL and the LTL (the
Inter Tidal area) is defined as the CRZ.
7. To more clearly understand the import of the definition of a CRZ, the said notification
also describes the term HTL as, For the purposes of this notification, the HTL
means the line on the land upto which the highest water line reaches during the
1The definition of HTL was amended vide Notification S.O.550(E) dated 21.5.02.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
8/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 8 of 91
CESE, IIT Mumbai CIDCO
spring tide2.Asper the said Notification, the HTL is to be demarcated uniformly in
all parts of the country by the demarcating authority or authorities so authorized by
the Central Government, in accordance with the general guidelines issued in this
regard. Similarly, the LTL is proposed to be defined as the line on land up to which
the lowest water line recedes during spring tide. The Notification further states that
the distance from the HTL shall apply to both sides in the case of rivers, creeks and
backwaters and the HTL may be modified on a case to case basis for reasons to be
recorded in writing while preparing the Coastal Zone Management Plan (CZMP) of
the State. Therefore, a CRZ is to be determined with reference to the HTL and LTL
at the relevant site itself. It is also an admitted position that due to the flow and ebb
of the tidal action this demarcation would vary from time to time. Therefore, since
determination of an area as a CRZ is dependent on the basis of the tidal action of a
specified water body, implicitly such CRZ determination is dynamic and is amenable
to change depending on the ground conditions at a specific site, such as the site for
the NMIA.
8. A perusal of the site maps provided to us show that only certain sections in the
proposed site for the NMIA currently fall within the definition of a CRZ. These are the
areas around the rivers Gadhi and Ulwe (the said Rivers) that pass through the site
and which have been classified as CRZ in the CZMP for Navi Mumbai area as
approved by the MoEF. Thus, these areas around the said Rivers are the only
sections of the project site, to which the provisions of the CRZ Notification dated 19
February, 1991, including the restrictions on construction contained therein, will be
applicable. Further, factually the mountain area proposed to be razed to reclaim the
area under water and CRZ areas, falls in the non CRZ area of the airport area site.
Hence quarrying or cutting of the mountain would not attract the CRZ Notification.
The proposed activity would however have to be dealt with as a matter of course
under the provisions of the EIA notification while preparing the EIA report for the
project.
9. We understand that, as part of the airport development, it is proposed to train and
divert the said Rivers such that they run their individual courses well outside the
periphery of the said project site. It is clear that the training of the said rivers will
require prior MoEF approval. However, once the course of the said rivers are altered
2When the sun and moon are aligned, there are exceptionally strong gravitational forces, causing very high and very low tides
which are called spring tides, though they have nothing to do with the season.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
9/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 9 of 91
CESE, IIT Mumbai CIDCO
with the approval of the MoEF, then clearly, the logical consequences would be that
the CRZ area too would have to be realigned and re-defined with reference to the
diverted course of the said rivers.
10. The Maharashtra State Government had submitted and got approved a Coastal
Zone Management Plan (CZMP) for Mumbai and Navi Mumbai respectively.
Realignment of the CRZ within an approved CZMP is permissible as is seen from
our discussions above. However this will require some minor changes in the
approved CZMP for Navi Mumbai. For this purpose the prior approval of the
MCZMA and the MoEF will be required.
11. The MCZMA has, vide the decisions taken in its 54th meeting and recorded in its
minutes dated 16 July, 2009, decided to recommend the case of NMIA to the MoEF.
This is further evidenced by the MCZMAs letter dated 7 August, 2009 to the MoEF,
recommending the case of the NMIA including, a recommendation that the said
Rivers be permitted to be trained and their course diverted, subject to certain
conditions specified therein. These recommendations are currently pending before
the MoEF.
12. We have been advised that diverting the course of the said Rivers is a necessary
and incidental activity to the development of the NMIA. Without re-alignment of the
said Rivers, the NMIA cannot be developed as is reflected by the analysis of the
studies carried out by CIDCO contained in the report on Re-Orientation of Runways
to save mangroves. We have also been made to understand that the said Rivers are
creeks which essentially channel creek water and are subject to the tidal actions of
the sea. As noted above, the MoEF has vide its order/circular bearing number
S.O.114 (E) dated 15 May, 2009 amended the CRZ Notification dated 19 February,
1991 and exempted the development of the NMIA from the list of prohibited
activities within a CRZ, subject to certain conditions. With this amendment, the
enabling provisions under the CRZ Notification dated 19 February, 1991 that permit,
inter alia, the disturbance of the natural course of creek water as required for
construction, modernization or expansion of ports, harbours, and for other
facilities that are essential for activities permissible under the notification will be
available to the NMIA project. Therefore, in our view, diversion of the said Rivers is a
permissible activity under the CRZ Notification dated 19 February, 1991, as
amended.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
10/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 10 of 91
CESE, IIT Mumbai CIDCO
13. In the above circumstances, in our view, altering the course of the said rivers being
essential for construction of the NMIA airport and its facilities including the runways,
terminal etc, is therefore, a permissible activity under the Notification read with the
amendment dated 15 May, 2009. In our view, the MoEF will be required to grant its
approval to divert the said Rivers, however, in doing so, it may impose certain
conditions as recommended by the MCZMA, which will have to be complied with by
the Developer.
14. Once the said rivers are diverted, as above, the CRZ would be re-aligned along the
course of the diverted rivers and, based on the maps submitted by CIDCO to
MCZMA and forwarded to MoEF for CRZ clearance, the site would automatically
cease to be a CRZ (except for certain areas around the periphery/boundary of the
site along the trained and diverted Rivers.. Once the site ceases to be a CRZ, the
provisions of the CRZ Notification dated 19 February, 1991, including the restrictions
on construction contained therein, would cease to apply to the NMIA site.
C. Issues related to presence of Mangroves and Steps to be taken by CIDCO in
view of the judgment of the Bombay High Court
1. A perusal of the maps provided to us show that the mangrove growth within
the Airport Zone is of varying density and is limited to certain sections of the
Airport Zone. In order to carry out the proposed development within the
Airport Zone, deforestation of these mangroves appears to be imperative.
However, destruction of mangroves is expressly prohibited by the orders and
judgment of the Honble Bombay High Court3.
2. It is clear, therefore, that destruction of any mangroves for the development of
the NMIA will require a prior approval of the Bombay High Court. Some of the
relevant judgment and orders of the Bombay High Court having a bearing on
this issue are discussed below:
(i) Bombay High Court Order dated 12April 2005 in W.P No. 3246/ 2004 (PIL
87/2006) & 2208/2004:
This Writ Petition was filed with respect to mangroves being/ were in the
process of being indiscriminately destroyed in five areas in Mumbai, viz.,
3 Bombay High Court Order dated 6th October 2005 in W.P. (lodging) No. 3246/2004
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
11/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 11 of 91
CESE, IIT Mumbai CIDCO
Seven Bungalows, Andheri; Kanjurmarg; Link Road, Goregaon; Gorai; and
Malvani village, Malad. The Honble Court by virtue of this Order imposed a
freeze on further developmental activity in the area which would destruct or
denudate the mangroves. The Honble Court also directed the State of
Maharashtra not to sanction such activities and to seek the permission of the
Court before affording such sanctions.
(ii) Bombay High Court Order dated 6 October 2005 in W.P (lodging)
No.3246/2004 (PIL 87/2006:
This order was passed pursuant to the cited Public Interest Litigation filed by
NGOs like Bombay Environmental Action Group (BEAG) and others
seeking urgent measures for protection and preservation of the mangrove
forests in Maharashtra from systematic destruction by land grabbers and
encroachers. Several directions were issued by the Court under this order for
the protection, conservation and rejuvenation of mangroves and the State
Government was directed to designate a senior officer, the Collector and
Deputy Commissioner of Police/ Superintendent of Police (DCP/SP) to
oversee the implementation of the directions.
The Court inter alia, directedthe State to continue to use the services of the
Maharashtra Remote Sensing Application Centre (MRSAC) to prepare
Phase-II of the mangroves mapping study in order to precisely identify the
mangrove areas in the State and specifically in Mumbai and Navi Mumbai.
Thereafter the State was directed to use the data and transfer the details of
the mangroves on to the City Survey/ Village maps (Cadestral maps). On
transfer of the data the areas having mangroves and which were identified as
government owned, were to be declared as Protected Forests and the areas
having mangroves and which are identified as privately owned were to bedeclared and notified as Forests. The Forest Department was to be handed
over the possession of the land/ areas identified and declared as protected
forests and the Revenue Department was directed to update its records to
ensure that the government lands were shown as protected forests. In case
of private lands, the Revenue Department was directed to update its records
to ensure that the private lands were shown as forests.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
12/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 12 of 91
CESE, IIT Mumbai CIDCO
The order also inter alia, directed that :
(i) there shall be a total freeze on the destruction and cutting of mangroves in
the entire State of Maharashtra;
(ii) All construction and rubble/ garbage dumping on the mangrove areas shall
be stopped forthwith;
(iii) Regardless of ownership all construction taking place within 50 metres on all
sides of all mangroves shall be forthwith stopped;
(iv) No development permission whatsoever shall be issued by any authority in
the State in respect of any area under mangroves;
(v) The Municipal Commissioner of Greater Mumbai shall forthwith issue
necessary directions to the MCGM Building Proposals department not to
entertain any applications for development (as defined in the MRTP Act,
1966) in respect of mangrove lands regardless of nature of ownership;
(iii) Bombay High Court Order dated 24 January 2007 in Notice of Motion
663/2006 in PIL No.87/2006:
The Court accepted the recommendations of the expert body for widening the
Mahul creek better flow of rain water and permitted modification of the Order
dated 6 October 2005 on the condition that the Bombay Municipal
Corporation (BMC), shall ensure that the mangroves were removed only
where such removal was necessary.
(iv) Bombay High Court Order dated 28 July 2008 in Notice of Motion Nos.538/ 2006 and 245/ 2006 in PIL W.P No. 87/ 2007:
This order was passed pursuant to the cited Notice taken out by CIDCO and
the Central Railway respectively for modifying the order dated 6 October
2005 on the ground that the projects mentioned in the Notice be exempted as
they fall in the categories mentioned in the order. By virtue of the said order
the Court observed the following:
(i) Category 1 projects: consisting of Infrastructure projects such as roads,
bridges, railways, culverts, pipe outlets water supply/ sewerage system
etc. which did not involve cutting of mangroves but which fell within 50mtrs from the mangroves. On the mutual agreement of both parties to
the petition, it was agreed that since the projects did not involve cutting
of mangroves and were required in larger public interest, all projects
situated on the landward side of the HTL may be allowed to be taken
up.
(ii) Category 3 projects: consisting of using land in CRZ- I as permitted
uses viz., as part of the Golf course project, without cutting mangroves.
(iii) Category 4 projects: consisting of cleaning and maintenance of artificial
channels and holding ponds developed as storm water drainage
systems, specifically holding ponds at Sanpada, Dronagiri, Kalamboli,
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
13/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 13 of 91
CESE, IIT Mumbai CIDCO
Panvel and Ulwe. On the mutual agreement of both parties to the
petition, it was agreed that maintenance works which are critical, in
these areas may be taken up as per technical requirements and in other
places the works would be taken up as per the suggestions of experts
including Bombay Environmental Action Group (BEAG).
(iv) Category 5 projects: consisting of Infrastructure projects involving the
cutting of mangroves. Specifically the construction of bridges along the
Palm Beach Marg extension of Ghansoli and the Railway embankment
project at Nerul were discussed.
The Court observed that it would take up other Notices of motion on a case to
case basis wherein there is no cutting of mangroves and the development is
on the landward side of the HTL but within 50 metres of the existing
mangroves.
The Court also clarified that CIDCO would have to obtain the required
environmental clearances, for implementation of all the (above) projects
undertaken by them. The order further required CIDCO to give an
undertaking that it would abide by the terms and conditions and stated that
other reliefs sought by CIDCO would be considered subsequently as and
when the contingency arose. Further more the CIDCO was directed toapproach the competent authority under the MoEF and the Authorities
constituted thereunder and seek necessary directions at different levels and
subsequently approach the High Court. The order stated that on obtaining
such clearances and sanctions, the Court would pass appropriate orders on a
case to case basis.
(v) Bombay High Court Order dated 8 October 2008 in Notice of Motion
Nos. 538/ 2006 and 245/ 2006 in PIL W.P No. 87/ 2007:
This order merely reiterated that both the cited Notice of Motion had beendisposed off by the Courts order dated 28 July 2008.
(vi) Bombay High Court Order dated 18 March 2009 in Notice of Motion Nos.
379/ 2007 and 260/2007 in PIL W.P No. 87/ 2006:
The BMC had moved this Notice to modify the Order dated 6October 2005 in
order to repair and maintain various public works primarily for sewerage
disposal. The BMC sought permission to cut and remove mangroves which
were obstructing their activities. The Honble High Court after taking into
consideration all the facts allowed the Notice on the grounds that the
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
14/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 14 of 91
CESE, IIT Mumbai CIDCO
activities sought to be executed by the BMC were essential services and
provision of basic civic amenities such as sewerage treatment and disposal.
The Honble High Court directed the BMC to make all necessary efforts to
restore the mangroves as far as possible during and after the completion of
the project so that there is minimal intervention in cutting and removing the
mangroves. The Honble High Court further directed afforestation of
mangroves in twice the area by applying the methodology of restitution at an
alternate site for all other purposes. The Court in the said order directed the
BMC to file an undertaking of the Municipal Commissioner in the matter of
compliance of an order of restoration before commencement of the project by
stating the time frame and identifying the alternate site for the said purpose.
Thus it is clear that the Honble Court permitted the BMC to undertake
construction of its sewerage disposal plant, which would entail destruction of
significant mangrove cover on the condition of restoring affected mangroves
and afforesting twice the affected area. The primary consideration that
weighed with the Court appeared to be the larger public interest being served
by such project.
(vii) Bombay High Court Order dated 29 April 2009 in Notice of Motion116/2009in PIL No. 87/ 2006.
This order was passed pursuant to CIDCOs application seeking the Courts
clarification that the order dated 6 October 2005 passed in the cited PIL did
not bar the MoEF from considering CIDCOs request for amending the CRZ
Notification, 1991 and thereafter amending the said Notification. The order
inter alia, clarified that the order dated 6 October 2005 did not seek to restrict/
restrain any authority from exercising its statutory powers in accordance with
law.In view of the above, the MoEF proceeded to amend the CRZ Notification
dated 19 February, 1991 vide its order dated 15 May, 2009.
3. In our view, the NMIA is a project that has significant public interest and is an
essential project for the development of the State, the Mumbai Metropolitan
Region, as well as India.. The development of the NMIA in a sustainable
manner will ease the burden on the existing infrastructure due to congestion
at the old airport and ensure economic prosperity of the region and its people,
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
15/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 15 of 91
CESE, IIT Mumbai CIDCO
which will in turn benefit the State and the country. This is apparent from the
bare fact that the GoI amended the CRZ Notification dated February 19, 1991
to specifically permit the construction of the NMIA. This is a clear indication of
the importance and significance of the said project. It is also clear that the
Honble High Court has in specific instances modified the impact of the Order
dated 6 October 2005 on the basis of the principle of sustainable
development to the extent as is required for carrying out activities which are
in the larger interests of the community or public. In this context, a review of
the various orders passed by the Bombay High Court in relation to mangrove
areas from time to time, indicate that the High Court tends to permit projects
that are required for larger public interest, subject to any measures that may
be required to be undertaken, such as prescription for minimal damage and
impact to ecologically sensitive areas such as mangroves and any conditions
that may be imposed with regard to compensatory afforestation etc. These
orders have been specifically restricted to their application with regard to
mangrove areas and would act as precedents in similar cases. The principles
established in these orders regarding public interest etc. would be followed by
the High Court in future cases too, such as in the case of the NMIA. In our
view, if the High Court is satisfied that all the required environmental studies
relating to preservation/ minimal destruction and compensatory afforestation
of mangroves have been satisfactorily conducted for the NMIA project and
the measures required to be taken are clearly etched out to minimize the
damage to the mangrove areas and that the MoEF has given its approval to
the same, the High Court ought to be inclined to approve such projects. In
the past too, the High Court has given its approval to various projects,
mentioned herein, where mangrove areas form part of a larger project having
significant public interest. It would appear that the NMIA project should also
qualify as a project of public interest and of significant public and economic
importance and hence an application for modification of the order dated 6
October 2005 for the NMIA project should reasonably be considered by the
High Court for approval.
4. In our view, an appropriate application ought to be filed before the Bombay
High Court setting out the importance of the NMIA project to the development
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
16/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 16 of 91
CESE, IIT Mumbai CIDCO
of Region, the economic and other benefits that will flow to the region and the
urgency in developing the project to take some of the load off from the
existing Mumbai airport. Other economic and public benefit arguments should
also be preferred. The application should seek approval to clear the site of
mangroves to undertake the development and construction of the project, by
setting out the methodology to be adopted by the Developer for
compensatory afforestation of the mangroves which will inevitably be
damaged due to the developmental activities, at the site and/or at alternate
sites.
5. To expedite the process, it would be desirable to first obtain the environment
and CRZ clearance of the MoEF, with minor changes in the approved CZMP
of Navi Mumbai region and thereafter, approach the Bombay High Court on
the limited issue of mangroves. The issue to be brought before the Bombay
High Court is only in relation to mangroves and nothing else. The order dated
29 April, 2009 of the Bombay High Court, discussed above, clearly provides
that the order dated 6 October, 2005 did not seek to restrict/ restrain any
authority from exercising its statutory powers in accordance with law. MoEF is
the only central authority having the powers to consider and decide on the
environmental feasibility of a project of this nature. Therefore, there is no
order of the Bombay High Court that prevents the MoEF from exercising its
statutory powers, which includes granting environmental approval for the
diversion of the said rivers, quarrying etc., except that to the extent that
mangroves are involved, the MoEF approval will be subject to the orders of
the Bombay High Court. MoEF should examine and look at the NMIA
proposal from a technical perspective viz., whether the project is
environmentally feasible; and thereafter give/ reject its approval. Therefore,
the MoEF has the authority to grant environmental and CRZ clearance to the
project, subject to the Bombay High Court approving the cutting and/or
rehabilitation and afforestation of the mangroves. While reviewing the impact
of any modification of their earlier order dated 6 October 2005, the Bombay
High Court would reasonably rely on the MoEF report/ approval for
understanding whether the project is likely to irreversibly affect mangrove
areas or not while deciding on whether to permit the project. Therefore it is
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
17/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 17 of 91
CESE, IIT Mumbai CIDCO
imperative that MoEF evaluate and decide on the Environmental Clearance
before CIDCO moves the High Court for permission to modify the order dated
6 October 2005 for the NMIA project.
6. Pursuant to the aforesaid approval of the MoEF, CIDCO may approach the
Bombay High Court and seek its permission to cut the mangroves at the site
and provide for compensatory afforestation at an alternate site in lieu thereof.
In considering such application, the Bombay High Court may have regard to
the approval granted by the MoEF and may grant its approval subject not only
to the recommendations and conditions that may be imposed by the MoEF
but also such other conditions that it may deem fit to impose.
7. To conclude, in our view, the orders of the Bombay High Court do not in any
manner prevent or restrict the statutory authority or functions of the MoEF
from considering and granting on terms it deems fit, the environmental and
CRZ clearance for the project. The limited restriction on the powers of the
MoEF is with regards to the mangroves in the State. Any project proponent
would require the further approval of the Bombay High Court in addition to the
approval of the MoEF, for handling mangroves. CIDCO may obtain this
approval subsequently. We are in the process of reviewing various other
orders passed by the Bombay High Court in this and other connected matters
and will provide you our analysis of the same at a later date.
D. Any other issues
1. One other issue that needs to be highlighted is the application of the AAI Act
to the development of the NMIA. The relevant issues are discussed below.
2. We understand that the Project is proposed to be developed on a PPP basis
and the concession for the operation and management of the NMIA would be
granted by the Government of Maharashtra to a private party. It is proposed
that the private party will hold 74% of the equity in the project company, thus
becoming a majority shareholder in the project company and the balance
equity will be held through CIDCO. It is also anticipated that AAI may also
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
18/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 18 of 91
CESE, IIT Mumbai CIDCO
eventually hold certain equity in the project, however, such equity will not
dilute the private sector shareholding.
3. The AAI Act inter alia, applies to- allairports whereat air transport services
are operated or are intended to be operated, other than airports and airfields
belonging to or subject to the control of any armed force of the Union4; all
private airports in so far as it relates to providing air traffic service5, to issue
directions under Section 37 to them and for the purposes of Chapter VA6
4. The terms Airport and Private Airport have been defined in Section 2 of the
AAI Act. Section 2(b) defines Airport as a landing and taking off area for
aircrafts, usually with runways and aircraft maintenance and passenger
facilities and includes aerodrome as defined in clause (2) of Section 2 of the
Aircraft Act, 19347. Further Section 2 (nn) of the AAI Act, defines a private
airport as a private airport means an airport owned, developed or managed
by - (i) any person or agency other than the Authority or any State
Government, or(ii) any person or agency jointly with the Authority or any State
Government or both where the share of such person or agency as the case
may be in the assets of the private airport is more than fifty per cent.
5. A reading of the said definitions clearly indicate that, since the majority
shareholding in the NMIA project company will be held by private parties,
NMIA will be a Private Airport as defined above.
6. Extent of the AAIs authority over Private Airports:
(i) The AAI Act provides for the functions of the Authority constituted under
the AAI Act (the Authority) which inter alia, include establishment of
airports, providing assistance in the establishment of private airports by
rendering such technical, financial or other assistance as the Central
Government may consider necessary for such purpose8.
4Section 1(3)(a) of the AAI Act
5As per Section 2 (d) of the AAI Act, includes flight information service, alerting service, air traffic advisory service, air traffic
control service, area control service, approach control service and airport control service.6
Section 1(3)(aa) of the AAI Act7
The definition of the term aerodrome is set out in clause 3.3.3 below8 Section 12(3)(aa)of the AAI Act.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
19/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 19 of 91
CESE, IIT Mumbai CIDCO
(ii) Further in case of private airports engaged in the business of providing
air traffic service the Authority is authorized to issue directions under
Section 37.Subsection 1 of section 37 states that, The Authority or any
officer specially authorized by it in this behalf may, from time to time, by
order, issue directions, consistent with the provisions of the Aircraft Act,
1934, and the rules made there under, with respect to any of the
matters specified in clauses (f), (h),(i),(j),(k),(m),(p),(qq) and (r) sub-
section (2) of section 5 of that Act(i.e. the Aircraft Act), to any person or
persons engaged in aircraft operations or using any airport, heliport,
airstrip or civil enclave, in any case where the Authority or the officer is
satisfied that in the interests of the security of India or for securing the
security of the aircraft it is necessary to do so.
(iii) Thus it can be seen that the AAI can exert its authority over a private
airport providing air traffic service only to the limited extent provided in
the AAI Act. These limited functions and authority over the NMIA as a
private airport may be exercised by AAI under the provisions of the AAI
Act/Aircraft Act alone, and not in its capacity as a shareholder partner in
the project company.
(iv) Save as set out above, the management and operation of Private
Airports is governed as per the provisions of the Aircraft Act, 1934 and
the Aircraft Rules, 1937. Section 2 (2) of the said Act defines an
Aerodrome as, any definite or limited ground or water area intended
to be used, either wholly or in part, for the landing or departure of
aircraft, and includes all buildings, sheds, vessels, piers and other
structures thereon or appertaining thereto. These aerodromes are
required to obtain a license from the Directorate General of Civil
Aviation (DGCA), Ministry of Civil Aviation (MCA), Government of
India (GoI) prior to commencement of operations.9 Further the Central
Government has the power to make rules pertaining to inter alia, the
licensing, inspection and regulation of aerodromes, the conditions under
which aerodromes may be maintained, the prohibition or regulation of
the use of unlicensed aerodromes10. Thus, the NMIA would be
9Rule 78 of the Aircraft Rules.
10 Section 5 (2) (b) of the Act
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
20/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 20 of 91
CESE, IIT Mumbai CIDCO
governed by the provisions of the Aircrafts Act and Rules, with the AAI
having limited authority to issue directions with respect to circumstances
specified in the AAI Act, as set out above.
7. Do restrictions on construction and activities contained in the AAI Act
apply to Private Airports under the Aircraft Act, such as the NMIA?
(i) As discussed above, the NMIA will be a Private Airport as defined
under the AAI Act, and it will operate under a license from the DGCA
under the Aircraft Act. Consequently the restrictions on the development
of an airport as stipulated under the AAI Act would not apply to the
NMIA. It is clear from a reading of the above note that, the NMIA would
be governed primarily by the Aircraft Act, the conditions imposed in the
license issued by the DGCA and to a limited extent, by the Authority,
under the AAI Act.
(ii) We further find that the provisions of the Aircraft Act or Rules do not
provide for the activities that can be conducted or place any restrictions
on activities that can be conducted by a Developer within an
aerodrome. The provisions under the AAI Act that cover the AAIs
limited scope of authority over a private airport do not touch upon anydevelopmental restrictions of a private party within a private airport.
(iii) Therefore, in our view, there are no provisions under the AAI Act or the
Aircraft Act applicable to NMIA that restrict or prescribe the nature of
activities that can be undertaken by the Developer of the NMIA/CIDCO.
The NMIA will in respect of the development activities be subject to the
restrictions contained in the zoning and other rules, regulations and bye
laws of the local town planning authority, which in this case would be
the Navi Mumbai General Development Control Rules (Navi MumbaiGDCR) framed by the local town planning authority, i.e. CIDCO.
(iv) In our view, therefore, the Developer of the NMIA can plan, design and
develop the NMIA in any manner that it deems necessary and may build
offices, housing and other economic projects to support the airport as
per its plans, subject to the Navi Mumbai GDCR. (Unquote)
In view of the above, the various activities, such as, mangrove
cutting/destruction, diversion and training of rivers, quarrying and cutting
of mountain and earth, reclamation, alteration in tidal pattern, are
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
21/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 21 of 91
CESE, IIT Mumbai CIDCO
permissible in CRZ area based on CRZ Regulation, 1991 Notification as
amended upto 15th May, 2009. However, it is mandatory to approach
the Hon. Bombay High Court for obtaining Leave of the Court before
implementing the Navi Mumbai International Airport project in the
mangrove area after obtaining the environment clearance from the
competent authority i.e. Ministry of Environment & Forest.
8.2 Recoursing Channel.
A study was carried out in accordance with the TOR specified by MoEF on the
recoursing of the ulwe creek , cost implication for providing engineering solutions
and design changes in order to avoid change in the in creek. The following
paragraphs narrates the details of the studies carried out.
8.2.1 Background
The Navi Mumbai International Airport has been planned with two
independent parallel runways placed at 1.55 km. apart with a design capacity
of 60 MPPA. With the above configuration of runways, an area of about 1300
Ha consisting of 1160 Ha for aeronautical use and rest for off-site physical
infrastructure, is required for airport zone for the efficient functioning of
airport.
Ulwe creek is flowing through the airport zone. It runs from South to North
passing through almost the middle of the airport crossing both the runways
and finally meet to Panvel Creek. The total area covered under these rivers is
about 245 Ha.To make the land available for airport zone admeasuring about
1300 Ha., the option available is to retain the rivers as it is and to built the
airport over this or recourse Ulwe creek suitably.
8.2.2 Need for Recoursing of Ulwe Creek.
The first option of retaining the Ulwe creek, as it is, is examined taking into
consideration the various factors, such as; the construction of airport on stilt,
runway orientation, security, operation & maintenance, environment and cost
implication are described below:
i) Airport on Stilt: The development of airport partly on stilt and partly on
firm ground to the extent required have not been experimented in
anywhere in the world, because of its unique behavior and problems
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
22/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 22 of 91
CESE, IIT Mumbai CIDCO
associated with it, which would be difficult to simulate to work out an
engineering solution. The 245 Ha.area is required to be built on the
pillars numbering about 6000 going up to the rock strata and coming at
a level where the creek can be desilted and maintained using
mechanical means. On this area, no structures above will be allowed,
otherwise this will increase the airport development level further to suit
the structural requirement of activities coming over this. As such the
airport loose the utilization 20 percent it valuable land working area
affecting severely capacity of airport.
ii) Runway orientation: Based on air traffic forecast, designed capacity of
airport is 60 million passenger per annum for which two independent
runways with 1.55 km spacing between the runway is required.
Assuming that Ulwe creek will be allowed to cut across the airport by
constructing bridges at many locations, would make airport constantly
subjected to security threat as well as loss of full utilization air side area
thereby loss of airport capacity. Possibility of changing the runway
position towards South is also examined and the same was ruled out
because of non-availability of space and presence of road, railway and
Karnala hill.
iii) Security: The large area below stilt admeasuring about 245 ha needs
to be secured from all sides on 24X7 basis which is costly and
impossible task owing poor accessibility and it will adversely affect
financial health of the airport. The security requirement prescribed by
Bureau of Civil Aviation Security, Ministry of Civil Aviation prevents such
type airport development.
iv) Operation & Maintenance: Ulwe Creek will required to be desilted at
regular interval owing to obstruction created in terms of large no pillars
to maintained its discharging capacity. Maintaining creek below stills
will require special technique and skills associated with permanent and
recurring cost implication on the airport operation. Similarly the
maintenance of stilt structures will add a constant problem owing to the
saline environment.
v) Environment: Development of part of the Airport on stilt requiring large
number of pillar foundations would defeat the very purpose of retaining
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
23/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 23 of 91
CESE, IIT Mumbai CIDCO
the geomorphology of creek. There is an equal chance of alteration in
the hydraulic regime of the creek. More over it will prevent growth of
mangroves, vegetation and may affect adversely the aquatic life
because of absence of sunlight and proper ventilation.
vi) Cost implication: The construction of part of the airport on the stilt will
be a task by itself. A rough estimate based on the number of pillars,
beams/girders, deck slab at the rate of Rs.70,000/Sqmt for 245 Ha. of
airport area works out to Rs.16,000 Cr. Besides this there will be
recurring expenditure at the rate of 2% per annum would be Rs.336 Cr.
This cost once included in the project cost would make the airport
project totally unviable.
Based on the above parameters, the development of airport without
recoursing of the Ulwe is ruled out and the option available is to make
available the airport land by recousing the Ulwe creek on the Southern
boundary of the airport. The study on recoursing Ulwe creek is
described below:
8.2.3 Proposed Recoursing Of Uwle Creek
The techno-economic feasibility study of recoursing of Ulwe creek was
carried out in 2000-01 by conducting 1D mathematical model study by
CWPRS, Pune and the study concluded that the proposed airport
development does not cause any rise in the flood level estimated with
CIDCOs airport development - by recoursing Ulve river at the mouth of
Thane creek.
Upon In principle approval of Navi Mumbai International Airport project by
the Govt. of India, the CWPRS has conducted 1D mathematical model study
for the entire stream of Panvel Creek to predict the flow conditions in Panvel
Creek with the development of airport considering Probable Maximum Flood
(PMF) resulting from PMP and 100 years return period flood and spring/neap
tide as boundary condition. A detailed 2D mathematical model study was
also carried out by CWPRS to predict the condition of flood in Panvel creek
on upstream and down stream and around proposed NMIA for the same.
A vast amount of data consisting of 50 years of hydrological data,
topographical survey of rivers from high tide mark upto 12 kms. upstream,
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
24/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 24 of 91
CESE, IIT Mumbai CIDCO
bathmetric survey of Panvel and part of Thane creek and tidal and velocity
observed for one month. The above study concluded that the airport
development does not increase the flood level in the streams. The study was
also reviewed by the Expert Reviewer from DHI, who in turn concluded that
the study carried out by CWPRS is thorough and in a competent manner.
Based on the maximum predicted water surface level along the airport
boundary for PMP of 6 hours storm with peak of hydrograph at spring tide
high water level and 120 mts. wide channel for Ulve river, the safe grade
elevatorn of proposed airport has been worked out which varies from 8 mts.
towards East to 7 mts. towards the West from the centre of airport area. The
above safe grade elevation of proposed airport has been arrived after
considering the provision of free board of 2 mts. and 0.5 mts. for sea rise
level due to climate change.
The recoursing of Ulwe creek will commence from the downstream of the
bridge located on the SH54 with a curve of 250 mts. for smooth flow. The
commencement of both the banks will start just downstream of the SH54
bridge with a trapezoidal section. Both the banks will have side slope of
1:2.5 to 1:3 with stabilizing berm of 5 mts. width in between. The Invert level
of SH54 bridge and 60 mts. bridge on Aamra Marg was kept unaltered
resulting in the bed slope of Ulve river in 1:10,295. The total length of this
diversion is about 3.2 kms. of which 1.5 kms. is in rock in which both the
banks will be vertical. The width of the channel has been kept as 120 mts.
through out..Based on the current rate, the cost of recoursing of Ulwe river
works out Rs.92 Cr..The details of the recoursing of Ulwe River is given in
Figures 8.1, and 8.2.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
25/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 25 of 91
CESE, IIT Mumbai CIDCO
Fig: 8.1Details of Recourse Channel
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
26/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 26 of 91
CESE, IIT Mumbai CIDCO
Fig: 8.2Cross Sections for Proposed Recourse Channel
Thus, the recoursing of Ulwe river for the development of airport is cost
effective, environment friendly, hydraulically efficient and easy for
construction, maintenance and operation point of view and, therefore,
adopted for implementation.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
27/91
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
28/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 28 of 91
CESE, IIT Mumbai CIDCO
hills. The vicinity of airport site is surrounded by a series of North-South
hill ranges such as Matheran Hill Range, Panvel-Mumbra Hill Range,
Karnala Hill Range etc. The Matheran hill falls in the approach surface
area of Navi Mumbai Airport and meets the criteria of ' Precipitous
terrain' requiring special consideration in planning of instrumental
approach.
With the 90-270 runway orientation one of the hills of Matheran need
to be shaved by about 40m to meet the criteria of instrumental approach
as well as the ICAO s prescribed glide slope of 2.75 3.0 To
avoid shaving of hills in the eco-sensitive area as well as to meet the
crieteria of glide slope, the above runway orientation to be further fine
tuned to the runway orientation to 83- 263.
iii) Spacing between Runways:
Based on air traffic forecast reports, the MMR air travel demand is
estimated to the tune of 119 MPPA by 2030-31 and after allocating the
40 MPPA to existing Mumbai airport, the Navi Mumbai International
airport must be designed for more than 60 MPPA. With the projected air
traffic demand of 60 MPPA, minimum two parallel runways are required
and that too with independent operations. The runway length require for
large aircraft at the elevation of airport site at Navi Mumbai, works out to
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
29/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 29 of 91
CESE, IIT Mumbai CIDCO
3700m and accordingly the length of airport taking into consideration for
airport lighting stop, stop and clear area results in about 6Km.
As per ICAO norms, simultaneous instrument operations on parallel
runways for independent parallel approach requires a distance more
than 1525 m between the centre line of two runways. Distance less than
this would make the operation of runways dependent thereby reducing
the capacity of the airport less than the designed capacity of 60 MPPA..
iv) Compatibility with Mumbai Airport
Mumbai airport has two runways, the main runway oriented along 09-27
(91-271 with reference to North) and an intersecting runway oriented
at 14-32 used only 10% of time. Since NMIA is very close to Mumbai
airport, it is very crucial that the runway orientation of the new airport
should not hamper the operations at both the airports. Providing parallel
runways with similar orientation in both airports will ensure efficient use
of airspace and safe operations with minimum conflict between the two
airports.
In order to assess the safe and independent inter operability of both the
airport, a simulation study with the Mumbai & Navi Mumabi runway
orientation was carried out through ICAO at NAV Canada. This study
concluded that with appropriate procedure in place the simultaneous
operation of both Mumbai & Navi Mumbai aiport is feasible.
8.3.3. NMIA Runway Orientation:
Keeping the above criterias in view as well as the projected travel demand
of 60 mppa, the runway orientation works out to 83-263 with a spacing of 1.
55 km. with mid terminal. With the required length of airport 6Km, the width
of about 3 Km and area required for additional supporting activity incidental to
airport the boundary of airport is delineated. The figure below shows the
runway orientation of Navi Mumbai International Airport.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
30/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 30 of 91
CESE, IIT Mumbai CIDCO
The above runway orientation worked out with the usability factor of 99.99%,
cross wind component of 20 Knots compatibility with the main runway of
Mumbai Airport, the glide slope of 3
and no shaving of hills in eco-sensitive
area of Matheran.
The airport area so worked out doesnt leave any scope for further
modification in airport boundary owing to presence of Panvel & Taloja creek
in the North, National Highway 4B, Gadhi river & Panvel township in the East,
SH41 Panvel-Uran railwayline, NH4-B & Karnala hill in the South and Amra
Marg with Thane creek in the west.
8.3.4 Presence of Mangroves in Airport areaThe runway orientation so work out with airport boundary is overlapped on
airport area showing the presence of mangrove and the findings are
That the mangroves along Ulwe river, which crosses through the centre line
of both the runways and in the mid of airport where the various airside
activities will be located for operation of airport, thereby the saving of
mangroves is not feasible.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
31/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 31 of 91
CESE, IIT Mumbai CIDCO
Similarly, the second runway falls on the mangroves along the Gadhi River
bank and on the periphery of Vagivili Island and saving of these mangroves is
not feasible also.
An exercise was carried out by reducing the runway spacing to 1.6Km as well
as reorienting the runways within the extent of +/-10 and then overlapping
the airport boundary on the map of mangroves and same is described in
following para.
8.3.5 Reducing runway spacing
An exercise was carried out by reducing the runway spacing to minimum
1.55 km to accommodate the mid terminal between the runways as well as
meeting the 1525m spacing criteria of ICAO. The map indicating the runway
and mangroves is shown below.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
32/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 32 of 91
CESE, IIT Mumbai CIDCO
This alternative also doesnt save the mangroves since both the runways
cross the mangroves along Ulwe River and the 2nd runway passes through
the mangroves along the Gadhi River & Vaghvli Island.
8.3.6 Reorienting the runways:
The runway orientation of 83-263 is reoriented to 93-273 keeping the
limitation of extent of + or 10 and accordingly the following scenario
emerges.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
33/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 33 of 91
CESE, IIT Mumbai CIDCO
This orientation is not feasible due to presence of high rise buildings and hill
ranges in close proximity of runways warranting the shaving of hill in
Matheran eco-sensitive area, which falls in approach surface of airport. Also,in this case the mangroves cannot be saved since both the runways are
passing through the mangroves along Ulwe as well as Gadhi river.
Thus the above exercises bring out the fact that the reorientation of runway
and decreasing the distance between the runways to the minimum of 1.55 km
there is no saving of mangroves.
Thus the runway orientation of 83-263 with a spacing of 1. 55 km worked
out based on the determining criteria and has to be adopted with the
plantation of mangroves.
8.4 Ground Water Study
The terms of reference for carrying out EIA study given by the Ministry of
Environment & Forest has suggested to carry out a scientific study to explain
the quality and quantity of ground water in the impact zone, due to proposed
training and diversion of Gadhi & Ulwe rivers respectively.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
34/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 34 of 91
CESE, IIT Mumbai CIDCO
The Hydrogeological Study in the Impact Zone for Navi Mumbai International
Airport groundwater study was carried out by Groundwater Survey and
Development Agency, (GSDA) Water Supply & Sanitation Department, Govt.
of Maharashtra. The original report of above study is enclosed in
ANNEXURE-IV. This study reveals the following:
i) Diversion of Ulve River This River forms the main drainage of
mini watershed WF40/7. The water holding capacity of the aquifer in
the mini watershed is limited, hence the dugwells yield less, due to
which there are no agricultural activities in Rabi Season. Few
farmers cultivate vegetables. Diversion of Ulve River near the creek
will not have any adverse effect on groundwater in this mini
watershed. The runoff in the Ulve River can be reduced by
construction of few Water Conservation Structures from Village
Garade to Village Bhangarpada.
ii) The hydrogeological study observed that there is no effect on ground
water regime. Also the drainage is not controlled by structures. The
water level in the whole area behave in a normal way and no evidence
are observed that there is a control of any structure.
iii) The 49 water quality network stations indicates that the water quality
of Panvel City, Taloja and Ulve have very high TDS ranging from 2000
ppm to 14,000 ppm. High concentration of Chloride is found near
Turbhe, Kamothe and Kharghar area. The unconfined aquifers are
yielding sweet water, but in some cases the deeper confined aquifers
are polluted, due to sea water intrusion and industrial waste from the
Industrial area.
iv) The ground water level observed in observation wells indicates that
there is a rising trend which shows that the optimal uses of water for
agriculture is not done. The stage of development indicates that there
is a further scope of ground water uses. Due to urbanization, drinking
water is supplied through pipe water scheme. Hence, the dependency
on ground water is reduced.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
35/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 35 of 91
CESE, IIT Mumbai CIDCO
8.5 Vaghvli Island & Coastal line Study:
The terms of reference for carrying out EIA study given by the Ministry of
Environment & Forest has suggested to carry the study to know whether the
island has merged with the land area due to sedimentation as compared to
position in 2003 as well as examine the details of erosion of soil/coastal line
in last 50 years. The following paragraph narrates the details of study and its
findings.
Vaghvli Island is located at the mouth of Panvel creek & on the estuary of five
westerly flowing rivers from Shyadhri. Taloja & Kasadi rivers come from the
North, Kalundri & Gadhi river from the East & Ulwe river in the South. It is the
meeting point of Panvel creek from the East, and the rivers from the other
directions giving rise to the island owing to hydrological behavior of streams.
The area of island is about 2.80 SqKm and majority of the area is low lying
which gets inundated during high tide. A small settlement exists on the island
where the level is above +3m. Taloja & Gadhi river confluence is located in
the North-East corner where as the Ulwe river flows South of Vaghvli island
with a link to Gadhi river. The island being very ancient, an exercise is
carried out to understand the change in shape, if any, as well as its coastal
line surrounding it, in the last 40 years, based on the available data.
8.5.1 Methodology;
To examine the shape and the surrounding coastal lines the Survey of India
(SoI) map 1970 was used on which the shape of island as well as coastal
lines around it were digitized. The approximate area of island works to
280.85 Ha and the area of creeklet located South of island linking the Gadhi
creeklet is about 10.30 Ha.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
36/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 36 of 91
CESE, IIT Mumbai CIDCO
Fig.No.8.3
Digitized shape of Vaghvli island & the coastal lines imagery
T
h
e
digitized lines are geo-referenced to the available satellite imagery of 1992,
1995, 2001, 2006 & 2009. The findings of the exercise is given below-
i) Imagery 1992
The line showing the shape of lsland and its surrounding coastal lines
were geo-referenced on the LAND SAT imagery (1992) of NRSA having
resolution of 25m. The line showing the shape of the island of 1970
overlaps on this imagery more precisely on the South-East & South-
west direction whereas the shape of the island has undergone slight
modification in Northern & western side.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
37/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 37 of 91
CESE, IIT Mumbai CIDCO
Fig.No.8.4Digitized shape of Vaghvli island & the coastal lines imagery 1992.
The reason could be that the reclamation work carried out by CIDCO in
Northern side in early 1980 influenced the flow condition in the regime
of Gadhi river. This observation is further reinforced by reduction of
area of Vghivali island to 268.65Ha from 280.85Ha. Further, the
creeklet shows increase in area from 10.30 Ha to 12.26 Ha.
ii) Imagery 1995
Similar exercise was carried out by geo-referencing the line showing the
shape of lsland and its surrounding coastal lines on the LAND SAT
imagery (1995) of NRSA having resolution of 25m. The line showing
the shape of the island of 1970 overlaps on this imagery more precisely
on the Eastern side & South-west direction, whereas the shape of the
island has undergone slight modification on South- Eastern side.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
38/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 38 of 91
CESE, IIT Mumbai CIDCO
Fig.No.8.5Digitized shape of Vaghvli island & the coastal lines imagery 1995.
T
h
e
shape of island and its coastal line has remained more or less same.
The area of island is about 268.40Ha and the creeklet is 11.65 Ha,which is marginal change as compared to findings from Imagery of
1992.
iii) Imagery 2001
Similar exercise was carried out by geo-referencing the line showing the
shape of lsland and its surrounding coastal lines on the Ikonos imagery
of resolution of 1m. The line showing the shape of the island of 1970
overlaps on this imagery more precisely on the Eastern side & South-
west direction, whereas the shape of the island has undergone slightmodification on the confluence Taloja& Gadhi rivers in the form of
widening of mouth of Gadhi river.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
39/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 39 of 91
CESE, IIT Mumbai CIDCO
Fig.No.8.6Digitized shape of Vaghvli island & the coastal lines on Ikonos imagery 2001.
The reason for widening of the mouth of Gadhi river, could the
construction of bridge over creeklet connecting Gadhi river & Ulwe river,resulting in reduction in discharge from the creeklet. The shape of island
and its coastal line has remained more or less same. The area of island
is about 266.57Ha and the creeklet is 11.93 Ha, which is marginal
variation as compared to earlier image of 1995.
iv) Imagery 2006
The exercise was reapeated by geo-referencing the line showing the
shape of lsland and its surrounding coastal lines on the quickbird
imagery(2006) of resolution of 0.6m. The line showing the shape of the
island of 1970 overlaps on this imagery more precisely on the Eastern
side & South-west direction, whereas the shape of the island has
undergone further slight modification on the confluence of Taloja&
Gadhi rivers in the form of widening of mouth of Gadhi river. Further, the
marginal modification is also observed on the creeklet joinging the
Gadhi river. The imagery also shows the reduction in depth of water in
this creeklet owing to probable siltation.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
40/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 40 of 91
CESE, IIT Mumbai CIDCO
Fig.No.8.7Digitized shape of Vaghvli island & the coastal lines on imagery 2006.
The reason for widening of the mouth of Gadhi river, could the
construction of bridge over creeklet connecting Gadhi river & Ulwe river,
resulting in reduction in discharge from the creeklet. The shape of island
and its coastal line has remained more or less same. The area of island
is about 269.48Ha and the creeklet is 10.34 Ha, which is marginal.
v) Imagery 2009
The exercise was repeated by geo-referencing the line showing the
shape of lsland and its surrounding coastal lines on the Google imagery
of resolution of 1m. The line showing the shape of the island of 1970overlaps on this imagery more precisely on the Eastern side & South-
west direction, whereas the shape of the island has undergone slight
modification on the confluence of Taloja& Gadhi rivers.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
41/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 41 of 91
CESE, IIT Mumbai CIDCO
Fig.No.8.8Digitized shape of Vaghvli island & the coastal lines on imagery 2009.
.
T
h
e
shape of island and its coastal lines has remained more or less samewhen compared to imagery 2006. The area of island is about 273.17Ha
and the creeklet is 11.61 Ha, which is marginally more when compared
with imagery 2006 .
Keeping in view the limitation of this exercise, broadly it can be
concluded that the shape of Vaghvli island and its surrounding coastal
lines remained more or less same in last 40 years. There is no major
evidence of erosion in the coastal lines in and around the Vaghvli
island and in five rivers joining to it. Further, the Vaghvli island is notmerging with the main land although there is reduction in discharge
from the creeklet owing to probably construction of bridge, resulting in
siltation which gets flushed out during the monsoon. The above
findings are equally matches with our day-to-day ground observations
while working on Navi Mumbai projects.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
42/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 42 of 91
CESE, IIT Mumbai CIDCO
8.6 Mathematical & Physical Model Study
The terms of reference for carrying out EIA study given by the Ministry of
Environment & Forest has specified to carry the mathematical and physical
model study by CWPRS to assess the impact of activities relating to project
on hydrodynamics/flow in the river/backwater/creeks. Further, the
examination in detail for the probability of flooding of agricultural land,
residential area and other area due to proposed development/construction of
the airport is also to be studied considering unprecedented rainfall event of
26th July 2005.
CWPRS had carried out the 1D mathematical model study during the Tehno-
economic Feasibility Study during 2001 and concluded that the airport
development will not cause any additional rise in flood level in Panvel Creek
with the rest of CIDCO development.
CWPRS was entrusted to carry out the 1D & 2D Mathematical model study
with the fresh data for the entire Panvel Creek from the mouth of Panvel
Thane Creek upto 12 kms. upstream from the reach of high tide of five (5)
Rivers. The above study has been completed and the major findings are as
follows:
These 1-D and 2-D studies have shown that the flood levels in these river
channels except Ulwe and in the Panvel creek channel along north boundary
of airport area were more or less unaffected. In the Panvel creek reach
between Gadhi-Taloja confluence to Belapur-Ulwe bridge, a marginal rise in
the flood levels of about 0.15 to 0.20 m was predicted for a very short
duration at the time of high water. For remaining period, the water levels were
more or less same or even slightly lower as a result of channelization of flow,
reduced tidal prism and diversion of Ulwe River. Along Ulwe river, due to
diversion of river the rise in water level at location of diversion (Panvel - Ulwe
road bridge on SH54) will be about 1.6 m for 6 hour duration PMP rainfall
and 120 m wide Ulwe diversion channel.
The original report of above study is enclosed in ANNEXURE-V. The
CWPRS was also entrusted the work of carrying out the physical model
study by extending the existing Mumbai Port Model (scale of 1:400 H and
1/80 V) for accommodating the Panvel Creek. The laying of the physical
model has been completed and the calibration of the model is in the
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
43/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 43 of 91
CESE, IIT Mumbai CIDCO
progress. The study of diversion of Gadhi & Ulwe river will be carried out
from hydraulic point of view after the calibration of the model.
The CWPRS Report on 1D & 2D model study was reviewed by DHI
Consultant, Netherland. The process of review was interaction with the
officials of CIDCO, CWPRS and CIDCOs Hydraulic Advisor Mr.J.S.
Tarapore followed by site visit. The consultant also visited the CWPRS and
reviewed the work of 1D and 2D model and thereafter submitted the Review
Report. The DHI Consultant is of the opinion that the study carried out by
CWPRS is thorough and in competent manner. The Review Report is
enclosed at Annexue-V.
8.7 Mangrove Analysis, Plantation & Management Study:
The terms of reference for carrying out EIA study given by the Ministry of
Environment & Forest has specified to examine and submit the details of
mangrove area, destruction of mangroves and management measures in
detail with the help of satellite imagery of the last 15 years. The following
paragraph describes the field observation, analysis and location of mangrove
likely to be destroyed due to project, compensatory plantation and its
management.
8.7.1 Field Observation:
The field observation indicate that there are only degrading mangrove strands
predominantly between the two Rivers and to the NE side of the site. The
mangroves are dominated by Avicennia marina which in most of the places,
appears stunted, growing barely above 1 to 1.5m tall and with a perimeter of
canopy barely 1.5 m. There are sparse Bruguira cylindrical syn. Bruguira
caryophylloides and Aegiceros corniculata plants noticeable particularly
towards the hillside of Ulwe River. Along the banks of Ulwe River there is a
somewhat continuous and healthier growth ofAvicennia marina with patches
of Salvadora persica . At several places, the plants seem to be dying and
dried stems are left behind. Wherever there has been considerable
degradation of the true mangroves, the associate mangroves, mainly
Acanthus ilicifoiius has come up. So as to compete with the receding A.
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
44/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 44 of 91
CESE, IIT Mumbai CIDCO
marina plants, the stem of these A. ilicifolius plant has grown very tall with
leaves along the tip.
At places Acanthus longifolia is also seen growing among the A. marina.
Along the banks of Ulwe River facing North, towards Gadhi River the A
.marina plants are seen associated with healthy Sessmium portulacatum
plants. The channels that extend out from Ulwe River and Gadhi River where
the circulation of sea water is properly maintained, the mangroves are seen to
form healthy thickets though elsewhere there is only a sparse growth of
stunted plants . At a few places in NE region, where the tidal water seems to
spread, there are clumps of Clerodendrom inermis, with fewer and smaller
leaves as well as weak stem. Surprisingly, Salvadora persica plants are
sparse except for some locations. In contrast with the whitish and olive green
colour of A. marina, the clumps of S. persica are seen with parrot green,
smooth, almost glistening leaves. Salt tolerant grasses like Settaria sp., Coix
lachryma-joba, Scirpus maritimus, Eleucine sp. are found to associate with
the mangroves and mangrove associates. Away from the waterfront, these
grasses that dominate the landscape replace the mangroves. Though in the
summer season, when the current survey was done, the grasses were found
to have dried at places where the moisture was retained to sufficient extent,
these grasses were found lush green and fresh . Monsoon is the flowering
season of Avicennia marinaand subsequently the fruits drop from the parent
plants. They start germinating soon as the pericarp disintegrates. The
germinating seeds could be seen in large numbers at several locations along
the site. Despite this, the saplings ofAvicennia apparently fail to survive so
that the young plants were hardly seen. The frequency of mangroves
remained same at all collection sites.
In post-monsoon season, the saplings ofAvicennia marina that had come up
at a few places had already dried and even the Acanthus longifolia had
started drying . The stands were appearing just as they were in pre-monsoon
at most places. Salvadora persica was seen flowering.
8.7.2 Density and Dispersal
Dispersion of plant species in a community (frequency) their numerical
strength (density), and dominance can be studied, following the methods
given by Misra (1968) and Pandeya et al. (1968).Two hundred quadrats of
-
8/6/2019 CHAPTER 8 ADDITIONAL STUDIES
45/91
Chapter 8EIA Study of Navi Mumbai International Airport Sheet 45 of 91
CESE, IIT Mumbai CIDCO
size (5m x5 m