    CHAPTER 1 : INTRODUCTION

    1.1 PRODUCT BACKGROUND

    The Mangonel is what many people think of when they think of a catapult. From the Latin word

    "manganon" meaning engine of war. The Mangonel was invented by the Romans in 400 BC. The

    Mangonel consists of a long wood arm with a bucket (early models used a sling) with a rope

    attached to the end. The arm is then pulled back (from natural 90 o angle) then energy was stored

    in the tension of the rope and the arm. Then the bucket would be loaded. When released the

    Mangonel's arm would return to its equilibrium position, when it came in contact with the beam

    the arm would stop but the missiles stored in the bucket would continue to launch toward the

    enemy. The Mangonel fired projectiles in an overhead arc, the angle of the path of the projectile

    could be determined by a block placed on the beam that stopped the Mangonel's arm by using a

    block that stopped the arm earlier than 90 o angle would result in a path angle (above the

    horizontal) equal to the the angle between the arm and the 90 o angle. The Mangonel was capable

    of firing 1,300 ft. The Mangonel was easy to construct and wheels were added to the design to

    increase mobility.

    Figure 1.1 : The model of mangonel catapult

  • 8/12/2019 Chapter 1 mangonel

    2/14

    BDA 40203 - MECHANICAL ENGINEERING DESIGN 2UNIVERSITI TUN HUSSEIN ONN MALAYSIA

    -------------

    Page 2

    Based on the entire characteristic and the criteria of the mangonel catapult, we have to

    form a group and create our own mangonel catapult to fulfill the project of Design II subject. The

    mangonel has to fulfill the condition of the project which is the requirement has been given the

    size of the mangonel that should be followed. There are fundamental principles to invent the new

    mangonel and necessary to take into consideration important factor such as weight, design, type

    of material and the correct angle to get the long distance results.

    1.2 PROBLEM FOR EXISTING PRODUCT

    As we knew that mangonel is the invention from 400 BC so there are many problem that we can

    see from this original catapult. Major disadvantage of a mangonel are the inconsistent accuracy

    because of the material that chose to build the catapult. Most of the original catapult use twisted

    rope as the material to throw the projectile. Ropes can lose their elasticity so the accuracy of the

    catapult are not too accurate and it cannot survive a long distance of the thrown projectile.

    Figure 1.2 : Twisted ropes that used by original catapults

  • 8/12/2019 Chapter 1 mangonel

    3/14

    BDA 40203 - MECHANICAL ENGINEERING DESIGN 2UNIVERSITI TUN HUSSEIN ONN MALAYSIA

    -------------

    Page 3

    1.3 PRODUCT SIGNIFICANCE

    To obtain the objective and the design specification of this project, a new design of

    mangonel catapult must be designed. In the new design of the mangonel, we will consider about

    the design, safety, ergonomic, dimension and type of material that used. This mangonel catapult

    will produce the long range of thrown projectile than the original catapult. This mangonel also

    will use the new design and new type of material that also will help to get the good distance

    when the projectile will be thrown.

    1.4 PROJECT OBJECTIVE

    The objectives of this project are;

    1) To comply with Design II Subject requirement to create an Mangonel Catapult

    2) To be qualified in the Mangonel tournament held by Design II Subject

    3) To study the mechanical analysis of the design

    4) To study the history of ancient weapon use in medieval

    5) To build the mangonel based on the qualities of long range effort and Ergonomic

    1.5 PROJECT SCOPE

    To finish this project require a scope of work and a systematic plan should be conducted and

    follow because this project must go through a various process before we produce it. The scopes

    for this project are:

    i) To lift a maximum weight of 5kg load.

    ii) To throw the load with a range between 5 meter to 10 meter.

    iii) The size of Mangonel ranges between 30 x 30 x 35 cm

    iv) All the design is made by 3D modelling by using solid works software.

  • 8/12/2019 Chapter 1 mangonel

    4/14

  • 8/12/2019 Chapter 1 mangonel

    5/14

    BDA 40203 - MECHANICAL ENGINEERING DESIGN 2UNIVERSITI TUN HUSSEIN ONN MALAYSIA

    -------------

    Page 5

    1.6.1 Profile Of Members

    Name : Mohd Munir Mahfuz Bin Md Nasir

    Matric No. : CD 110392

    Age : 23

    Education : - Diploma in Mechanical (Polytechnic)

    - Bachelor in Mechanical Engineering and Manufacturing (UTHM)

    Experience : Technician at OYL SDN. BHD

    Position : Project leader

    Motto : Learn more get more

  • 8/12/2019 Chapter 1 mangonel

    6/14

    BDA 40203 - MECHANICAL ENGINEERING DESIGN 2UNIVERSITI TUN HUSSEIN ONN MALAYSIA

    -------------

    Page 6

    Name : Syahril Bin Abdul Razak

    Matric No. : CD 110320

    Age : 24

    Education : - Diploma in Mechanical (Polytechnic)

    - Bachelor in Mechanical Engineering and Manufacturing (UTHM)

    Experience : Technician at MTBE/Polypropylene PETRONAS Malaysia SDN BHD

    Position : Project designer

    Motto : Follow the flow

  • 8/12/2019 Chapter 1 mangonel

    7/14

    BDA 40203 - MECHANICAL ENGINEERING DESIGN 2UNIVERSITI TUN HUSSEIN ONN MALAYSIA

    -------------

    Page 7

    Name : Ahmad Syakir Bin Mohamad Jamil

    Matric No. : CD 110319

    Age : 24

    Education : - Diploma in Mechanical (Polytechnic)

    - Bachelor in Mechanical Engineering and Manufacturing (UTHM)

    Experience : Technician at YORK SDN BHD

    Position : Project Engineer

    Motto : Life with successful

  • 8/12/2019 Chapter 1 mangonel

    8/14

    BDA 40203 - MECHANICAL ENGINEERING DESIGN 2UNIVERSITI TUN HUSSEIN ONN MALAYSIA

    -------------

    Page 8

    Name : Mohammad Zulkhairi Bin Ahmad

    Matric No. : CD 110352

    Age : 24

    Education : - Diploma in Mechanical (Polytechnic)

    - Bachelor in Mechanical Engineering and Manufacturing (UTHM)

    Experience : Technician at Semambu Engineering SDN BHD (S.E.S)

    Position : Research and Delopment

    Motto : Live Big, Breath Deep

  • 8/12/2019 Chapter 1 mangonel

    9/14

    BDA 40203 - MECHANICAL ENGINEERING DESIGN 2UNIVERSITI TUN HUSSEIN ONN MALAYSIA

    -------------

    Page 9

    Name : Mohd Aidil Janatun Bin Razali

    Matric No . : CD 110366

    Age : 24

    Education : - Diploma in Mechanical (Polytechnic)

    - Bachelor in Mechanical Engineering and Manufacturing (UTHM)

    Experience : Technician at ENC Teguh SDN BHD

    Position : Mechanical Engineer

    Motto : Impossible is nothing

  • 8/12/2019 Chapter 1 mangonel

    10/14

    BDA 40203 - MECHANICAL ENGINEERING DESIGN 2UNIVERSITI TUN HUSSEIN ONN MALAYSIA

    -------------

    Page

    10

    1.6.2 ORGANIZATION OF COMBINED GROUP I-MECH & WARLOCK

    Chart 2: Group Organizational Chart

    PROJECTLEADER

    MUHAMMADAZHAR

    DESIGN

    SHAHROLHILMI

    NADZARUDDIN

    TECHNICALAIDIL JANATUN

    RIDHWAN

    AZIZAN

    RESEARCH

    AHMAD SYAKIR

    ZULKHAIRI

    TREASURER

    SYAHRIL

    PROJECT

    ASSISTANTMUNIR MAHFUZ

  • 8/12/2019 Chapter 1 mangonel

    11/14

    BDA 40203 - MECHANICAL ENGINEERING DESIGN 2UNIVERSITI TUN HUSSEIN ONN MALAYSIA

    -------------

    Page

    11

    1.7 DESIGN PROCESS

    Design process is most important with engineering designs to classified as inventions-devices or

    systems that are created by human effort and did not exist before or are improvement over

    existing device or systems. Inventions, or designs, do not suddenly appear from nowhere. They

    are result from design process is bringing together technologies to meet human needs or to solve

    the problems.

    Figure 3: Pahl and Beitzs Design Process Model

  • 8/12/2019 Chapter 1 mangonel

    12/14

    BDA 40203 - MECHANICAL ENGINEERING DESIGN 2UNIVERSITI TUN HUSSEIN ONN MALAYSIA

    -------------

    Page

    12

    1.8 GENERAL TASK DELEGATION

    The followings show the task delegation for each team members (Combined Group):

    1. Project Leader

    i. Acting group leader for both mini groups and project manager.

    ii. Responsible in delegating tasks to all group members

    iii. Involved in report writing Conceptual Design

    iv. Involve in concept idea

    2. Project Assistant

    i. Acting secretary for both mini groups.

    ii. Involved in report writing Introduction and Summary

    iii. Recording minute meeting

    3. Design

    i. Involve in report writing Define Task

    ii. Involve in designing concept of the productiii. Involve in concept idea

    4. Treasurer

    i. Involve in report writing Introduction and Summary

    ii. Involve in designing concept of the product

    iii. Involve in concept idea

    5. Technical

    i. Involve in report writing Embodiment Design and Analysis

    ii. Involve in designing concept of the product

    iii. Involve in concept idea

  • 8/12/2019 Chapter 1 mangonel

    13/14

    BDA 40203 - MECHANICAL ENGINEERING DESIGN 2UNIVERSITI TUN HUSSEIN ONN MALAYSIA

    -------------

    Page

    13

    6. Research and Development

    i. Involve in report writing Conceptual Design

    ii. Involve in designing concept of the product

    iii. Involve in concept idea

    1.9 PROJECT PLANNING AND SCHEDULING

    Table 1: Project Planning Gantt chart

  • 8/12/2019 Chapter 1 mangonel

    14/14

    BDA 40203 - MECHANICAL ENGINEERING DESIGN 2UNIVERSITI TUN HUSSEIN ONN MALAYSIA

    -------------

    Page

    1.9.1 BUDGET SCHEDULING

    Table 2: Budget Scheduling

    1.9.2 Overall Cost Estimation

    Table 3: Overall Cost Estimation

    No Type Dimension Description Price

    1 Angle iron 1 x 1 Thick RM 100

    2 Bolt, Nut and Washer 4/8 x 1 &

    4/8 x 3/2

    3 unit RM 1 per

    unit

    3 Solid wood beam 1 x 1 Thick RM 50

    Bil Component Initial cost Costing By

    Progress

    1. Structure Rm 150 Rm 200

    2. Accessories Rm 150 Rm 200

    Overall cost Rm 300 Rm 400