Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
1 | P a g e
Progress Report No. 14
For the Period Ending July 16th, 2020
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Kandee Engle Southwest Licking Local Schools
Debra Moore Southwest Licking Local Schools
Catherine Spindler Southwest Licking Local Schools
John Vincent Southwest Licking Local Schools
Roger Zeune Southwest Licking Local Schools
Kasey Perkins Southwest Licking Local Schools
Richard Jones Southwest Licking Local Schools
Robert Jennell Southwest Licking Local Schools Consultant
Nathan Jones Ohio Facilities Construction Commission
Eric Baltzell Garmann-Miller Architects Engineers
Curt South Garmann-Miller Architects Engineers
Brian Wolf Garmann-Miller Architects Engineers
Julie Taggart Hill International
Michael Maxwell Hill International
Construction Manager:
Robertson Construction Services, Inc.
1801 Thornwood Drive
Heath, Ohio 43056
Architects:
Garmann-Miller Architects Engineers
38 South Lincoln Drive
P.O. Box 71
Minster, Ohio 45865
Owner’s Agent:
Hill International, Inc.
2 Easton Oval #110
Columbus, Ohio 43219
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, June 16th, 2020
2 | P a g e
Table of Contents
PROJECT CONTACTS .............................................................................................................. 3
PROJECT FLOOR PLANS ........................................................................................................ 4
New 4-5 Elementary School ................................................................................................... 4
New 9-12 High School ............................................................................................................ 5
EXECUTIVE SUMMARY ........................................................................................................... 6
PROJECT BUDGETS ................................................................................................................ 7
Owner Contingency ................................................................................................................ 7
CMR Contingency .................................................................................................................. 8
PROJECT SCHEDULE .............................................................................................................. 9
Site Improvements Package ................................................................................................... 9
New 4-5 Elementary School ..................................................................................................10
New High School ...................................................................................................................11
PROJECT DOCUMENTATION .................................................................................................12
New 4-5 Elementary School ..................................................................................................12
New High School ...................................................................................................................13
QUALITY CONTROL ................................................................................................................14
New 4-5 Elementary School, Site Improvements Package, and New High School ................14
SAFETY ....................................................................................................................................15
New 4-5 Elementary School ..................................................................................................15
Site Improvements and New High School ..............................................................................16
PROGRESS PHOTOS ..............................................................................................................17
New 4-5 Elementary School ..................................................................................................17
Elementary School Drone Footage ........................................................................................18
New 9-12 High School ...........................................................................................................19
High School Drone Footage ..................................................................................................20
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, June 16th, 2020
3 | P a g e
PROJECT CONTACTS
All Projects
Eric Baltzell, Garmann-Miller (419) 628-4240
Tom Dutton, Garmann-Miller (419) 628-4240
Clay Keith, Robertson (614) 374-4857
Jessica Post, Robertson (740) 814-6742
Site Improvements Package
Shira Elder, Garmann-Miller (419) 628-4240
Mark Keith, Robertson (740) 404-1805
Kevin Mohler, Robertson (740) 503-7218
New 4-5 Elementary School
Curt South, Garmann-Miller (419) 628-4240
Clyde McIntire, Robertson (740) 404-0111
AJ Saunders, Robertson (740) 348-6932
New High School
Brian Wolf, Garmann-Miller (419) 628-4240
Mark Keith, Robertson (740) 404-1805
Kevin Mohler, Robertson (740) 503-7218
Etna Elementary Renovation
Curt South, Garmann-Miller (419) 628-4240
Clyde McIntire, Robertson (740) 404-0111
AJ Saunders, Robertson (740) 348-6932
September 15, 2019 Drone Photo
May 11,2019 Drone Photo
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
4 | P a g e
PROJECT FLOOR PLANS
New 4-5 Elementary School
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
5 | P a g e
PROJECT FLOOR PLANS
New 9-12 High School
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
6 | P a g e
EXECUTIVE SUMMARY
This report has been prepared to provide a project update for the Southwest Licking New 4-5 Elementary School and New High
School. It is intended to provide a summary review of the status of the project through July 16th, 2020.
UPCOMING MEETINGS:
July 22nd at 10:00 am – Core Team Meeting (Every Two Weeks)
July 21st at 12:30 pm - New High School Progress Meeting (Every Tuesday)
July 21st at 2:00 pm - New 4-5 Elementary School Progress Meeting (Every Tuesday)
July 22nd at 1:00 pm – Site Improvements Package Progress Meeting (Every Other Wednesday)
New 4-5 Elementary School CALENDAR DAYS TO COMPLETE
Substantial Completion (Nov 19, 2020) 126
SCHEDULE & WORK COMPLETED
• Area A
o Metal Roof Panels Area A1 – 100%
o Metal Roof Panels Area A2 – 100%
o Terrazzo Install Area A – 70%
o Masonry Veneer Area A – 98%
o Install Aluminum Window Area A –100%
o Metal Stud Framing Area A Admin. -100%
o Drywall Hang & Finish 2nd Floor Area A – 100%
o Drywall Hang & Finish 1st Floor Area A – 60%
o Mechanical, Electrical, and Plumbing Rough-Ins
1st and 2nd Floor Area A – 100%
o Prime and 1t Coat Paint 2nd Floor Area A – 100%
• Area B
o Masonry Veneer – 100%
o Metal Roof Panels – 100%
o Metal Stud Framing Area B – 70%
o Mechanical, Electrical, & Plumbing (MEP)
Rough-In Area B – 95%
o Terrazzo Install Area B- 100%
• Area C
o Install Aluminum Windows Area C – 100%
o Metal Soffits & Fascia Area C -30%
o Prime and 1st Coat Paint 2nd Floor – 100%
o Mechanical, Electrical, and Plumbing Rough-Ins
1st and 2nd Floor Area C – 100%
o Terrazzo Install 1st Floor Area C – 90%
o Install Casework 1st Floor Area C – 75%
o Install Ceiling Grid 1st Floor Area C – 75%
o Install Light Fixtures 1st Floor Area C – 75%
CURRENT ISSUES
• Technology Equipment Package Finalized Late due to
budget issues. Potential concerns with technology
materials coming from China.
• COVID-19 has impacted the job. The elevator delivery
is delayed four weeks.
New High School CALENDAR DAYS TO COMPLETE
Substantial Completion (Apr 29, 2021) 287
Topsoil, Reseed, Asphalt (May 28, 2021) 316
SCHEDULE & WORK COMPLETED
• Area A
o Concrete SOG Area A – 30%
o Area A Masonry Bearing Walls – 30%
o Area A2 Back of Stage Precast Plank – 90%
o Area A Stage High Roof Membrane Roofing – 99%
• Area B
o Interior CMU walls – Area B Kitchen 95%
o Roof Structural Steel Areas B Kitchen – 95%
• Area C
o HVAC Duct Mains/ Branches Dining – 100%
o Metal Roof Panels Area C Dining – 90%
• Area D
o Area D Auxiliary Gym Masonry Bearing – 95%
• Area E
o Metal Roofing Area E Gymnasium – 100%
o Hydronic Piping Area E Gym – 10%
• Area F/G
o Masonry Veneer – Area F/G 95%
o Mech., Elec. and Plumb. Rough-Ins - 100%
o Drywall Area F2-G2 – 100%
o Drywall Area F2-G2 – 10%
• Area H/J
o Masonry Veneer – Area H/J - 80%
o Mechanical, Electrical, Plumbing Rough-Ins 100%
o Roof Ice and Water Shield Dry-in H2/J2 – 100%
o Wood Fascia Areas H-J – 100%
o Mechanical, Electrical, Plumbing Rough-Ins - 20%
CURRENT ISSUES
• Failed Auditorium Masonry Wall Re-Build Replacement:
• Overtime costs are still being evaluated by the Insurance
Company; This is causing a delay in the attempts to recover
the lost time. Discussions continue/ No Change.
• Continue procedures pursuant COVID-19 and Stay at Home
Order extended July 8th, 2020.
• Scope for Auditorium Lighting and Sound System Design/
Pricing and allowance usage. Material procurement Lead
Time is primary concern for upcoming Auditorium work.
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
7 | P a g e
New 4-5 Elementary School
Owner Contingency Usage
Approved Change Orders Pending Change Orders
Remaining Contingency Site Work Approved Change Orders
Site Work Pending Change Orders
New High School
Owner Contingency Usage
Approved Change Orders Pending Change Orders
Remaining Contingency Site Work Approved Change Orders
Site Work Pending Change Orders
PROJECT BUDGETS
Owner Contingency
Owner Contingency
Elementary School
Original Amount $484,786.40
Approved Change Orders $(655,874.04)
Pending Change Orders $51,926.86
Remaining Contingency $1,088,733.58
Site Work Approved Change Orders $3,659.01
Site Work Pending Change Orders $47,658.57
Owner Contingency
High School
Original Amount $1,304,165.46
Approved Change Orders $99,559.03
Pending Change Orders $152,937.24
Remaining Contingency $1,051,669.19
Site Work Approved Change Orders $8,958.27
Site Work Pending Change Orders $129,828.51
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
8 | P a g e
Site Improvements Package
CMR Contingency Usage
Approved Change Orders Pending Change Orders
Remaining Contingency
New 4-5 Elementary School
CMR Contingency Usage
Approved Change Orders Pending Change Orders
Remaining Contingency
New High School
CMR Contingency Usage
Approved Change Orders Pending Change Orders
Remaining Contingency
CMR Contingency
CMR Contingency
Site Work
Original Amount $84,760.00
Approved Change Orders $34,657.95
Pending Change Orders $646.40
Remaining Contingency $49,455.65
CMR Contingency
Elementary School
Original Amount $343,225.00
Approved Change Orders $97,873.76
Pending Change Orders $39,928.70
Remaining Contingency $205,422.54
CMR Contingency
High School
Original Amount $665,549.00
Approved Change Orders $69,469.63
Pending Change Orders $25,805.62
Remaining Contingency $570,273.75
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
9 | P a g e
PROJECT SCHEDULE
Site Improvements Package
RCS Internal Verification Dates
SCHEDULE FROM BID SCHEDULED STATUS
Notice to Proceed February 28, 2019 Complete
Build Building Pad – Elementary School June 10, 2019 Complete
Build Building Pad – High School June 26, 2019 Complete
Substantial Completion of Elementary School November 10, 2020
Substantial Completion of All Work (less Items Below) April 29, 2021
Spread Topsoil, Reseed, and Top Coat of Asphalt May 28, 2021
Schedule Two Week Look Ahead
• Final Jetting/ Cameras of Sanitary lines completed June 17th, 2020.
• Re-Seal of sanitary structures lids completed June 15th, 2020.
• Continue final grading around New 4-5 Elementary
• Continue final Storm roof leaders at the new 4-5 Elementary
• New Storm Structure 35, at Rt. 40, per PR-011 in fabrication.
• Connector Road soil remediation, Cement stabilization and grading is in process. Per
CTL May 15th report, Connector Road Field Directive sub-grade cement stabilization
work is complete. Grading to commence after required set time. Weather contingent,
grading Work for connector road anticipated to be completed this month.
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
10 | P a g e
PROJECT SCHEDULE
New 4-5 Elementary School
RCS Internal Verification Dates
SCHEDULE FROM BASELINE SCHEDULE SCHEDULED STATUS
Notice to Proceed February 28, 2019 Complete
Temporary Dry-In March 5, 2020 On Track
Permanent Dry-In May 21, 2020 Substantially Complete
Final HVAC Start-Up May 12, 2020 In progress. Start 07/10/202
Substantial Completion November 10, 2020
Schedule Two Week Look Ahead
Site Work
• Downspout Leader Install
• Start Final Grading & Spreading of Top
Soil
• Placement of Curbs and Sidewalks
Area B
• Install Fire Suppression System
• Install Metal Stud Framing & Drywall at
Stage and Soffits in Student Dining
• Prime & Paint Gym
• Install Gym Equipment
Area C – 1st Floor
• Continue Install of Casework
• Continue Install of Ceramic Tile in
Restrooms
• Continue Install of Terrazzo
• Complete Install of Ceiling Grid
• Install LVT Flooring in Classrooms
Area C – 2nd Floor
• Install Technology and Fire Alarm
Cabling
• Install Ceiling Grid
• Install Casework
Area A – 1st Floor
• Hang and Finish Drywall
• Complete Install of Veneer at Main Entry
• Install Epoxy Flooring in Restroom
• Continue Install of Terrazzo
Area A – 2nd Floor
• Continue Insulating Duct and Piping
• Install Technology and Fire Alarm
Cabling
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
11 Page
PROJECT SCHEDULE
New High School
RCS Internal Verification Dates
MILESTONE SCHEDULE FROM BID SCHEDULED STATUS
Notice to Proceed May 24, 2019 Complete
Substantial Completion of All Work (less items below) April 29, 2021 19 days behind schedule
Spread Topsoil, Reseed, and Top Coat of Asphalt May 28, 2021
Schedule Two Week Look Ahead
Area A – Mechanical/ North of Stage
• Continue Critical Path - Masonry CMU
Bearing Walls north of Stage
• Prep- for topping slab over Pre-Cast
Concrete Plank – Mechanical Room
A201
• Pour Concrete SOG Area A – East and
Area A back of stage
• Begin Area A2-East second floor Steel
Joists and Decking
Area B - Kitchen
• Complete Low Roof Structural Steel
Area B - Auditorium
• Install Metal Roofing System
Area C – Student Dining
• Begin above ceiling Electrical Rough-In
• Pour lower risers of Monumental Stair
• Install C2 Membrane Roof System
Area D – Auxiliary Gym/Locker Room
• Complete remaining Masonry Walls
• Prepare Roof Steel for High Roof of
Aux. Gym
Area E – Main Gymnasium
• Complete Electrical Rough-in
• Begin Fire Suppression Rough-In
• Begin Painting Block Fill
Area F and G – 1st Floor
• Start Gypsum Wall Board over Metal
Studs
• Continue Duct Insulation
• Paint/ Prime 1st coat CMU Complete
Area F and G – 2nd Floor
• Install Metal Roofing System
• Paint/ Prime 1st coat CMU Complete
Area H and J – 1st Floor
• Complete remaining Interior Non-
Bearing Masonry
• Complete Exterior Brick Veneer (East)
Area H and J – 2nd Floor
• Continue H2/J2 Duct and VAVs
• Begin Hydronic Piping Above Ceiling
Rough-Ins
• Plumbing Above Ceiling Rough-ins
• H2/J2 Ice and Water Shield is complete
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
12 Page
New 4-5 Elementary School
Request for Information
Open RFIs Closed RFIs
Total RFIs:
Open RFIs:
122
3
PROJECT DOCUMENTATION
New 4-5 Elementary School
The timely flow of all information is critical to any construction project. Specifically, Submittals (Shop Drawings)
and Request for Interpretation are two critical areas that need to be closely monitored to assure a lack of information
does not impede the project schedule. The following is a brief summary of the current Submittal and RFI status and
is intended to highlight critical items to all parties.
The following items may present potential concerns to the project schedule:
Submittal/RFI Responsibility Schedule Concern
New 4-5 Elementary School
Submittals
Approved Submittals Pending Submittals
Closeout Submittals Outstanding Submittals
Total Submittals:
Approved:
Pending:
Outstanding:
Closeout:
1074
722
10
86
256
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
13 Page
New High School
Request for Information
Open RFIs Closed RFIs
Total RFIs:
Open RFIs:
140
2
PROJECT DOCUMENTATION
New High School
The timely flow of all information is critical to any construction project. Specifically, Submittals (Shop Drawings)
and Request for Interpretation are two critical areas that need to be closely monitored to assure a lack of information
does not impede the project schedule. The following is a brief summary of the current Submittal and RFI status and
is intended to highlight critical items to all parties.
The following items may present potential concerns to the project schedule:
Submittal/RFI Responsibility Schedule Concern
RFI-136: CMU Structural Condition @ Hydronic GMAE Structural condition at CMU due to design of Duct
and HVAC Piping adjacencies and full height CMU
between Steel Trusses. Item addressed July 8th.
New High School
Submittals
Approved Submittals Pending Submittals
Closeout Submittals Outstanding Submittals
Total Submittals:
Approved:
Pending:
Outstanding:
Closeout:
1284
698
8
176
402
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
14 Page
QUALITY CONTROL
New 4-5 Elementary School, Site Improvements Package, and New High School
The monitoring of safety and quality of work is an important issue, which Robertson Construction Services and the
Subcontractors take very seriously. Robertson continually monitors the Subcontractor’s safety practices and quality
of work via on-site inspections.
Quality Control
We are reviewing all of the “work in place” to verify it was installed as designed. Any discrepancies from the
Contract Documents are listed in field reports and distributed to the proper Subcontractor for corrections. We also
discuss the items in our weekly subcontractor meetings to ensure each concern has proper closure. The entire
Design Team has taken a thorough and proactive approach to items. Robertson continues to monitor the reports from
Geotechnical Consultants Inc. Corrections are being made in response to these reports.
Additionally, pre-installation meetings are being scheduled with the Architect and appropriate subcontractors to
ensure the work is consistent with the contract specifications and on par with quality standards.
Thus far we have held the following pre-installation meetings:
• Elementary Cast-In-Place Concrete (Footings) – July 23rd at 3:00 pm
• High School Cast-In-Place Concrete (Footings) – August 8th, 2019
• Elementary & High School Unit Masonry – July 30th at 3:00 pm
• Elementary & High School Cast-In-Place Concrete (Slab on Grade) – August 27th at 1:00 pm
• Elementary & High School Membrane and Sheet Metal Roofing – October 8th at 3:00 pm
• Elementary & High School Mechanical Materials/Methods – November 5th at 10:00 am
• Elementary & High School Fire Protection Materials/Methods – November 19th at 10:00 am
• Elementary & High School Plumbing Materials/Methods – November 19th at 9:00 am
• Site Work Clearing and Grubbing – March 7th, 2019
• Elementary & High School Stone Masonry Veneer
• Elementary & High School Storefronts, Curtain Walls, and Glazing – March 17th
• Elementary Resinous Matric Terrazzo – May 26th at 10:00 am
• Technology Kick-Off Meeting – June 10th at 2:00 pm
• Elementary Resilient Flooring and Tiling – July 7th at 10:00 am
• Elementary Hydraulic Elevators – July 8th at 9:00 am
• Educational and Library Casework – June 23rd at 9:30 am
The following Pre-Installation Meetings are to be scheduled:
• Elementary TAB Kick-Off Meeting
The Following Pre-Installation Meetings are to be held per the Specifications:
• Wood Flooring
• Sound, Video, & Communication Systems
• High School Theater & Stage Equipment
• Communication Metal Support
• HS-Resinous Matrix Terrazzo and Quartz Flooring
• Window Shades
• Telescoping Bleachers
• Playground Grading and Soft Surface
• Polished Concrete Floor System
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
15 Page
SAFETY
New 4-5 Elementary School
June 2019 – There have been no safety issues this month.
July 2019 – There have been no safety issues this month. A safety audit was held by Robertson on July 2nd, 2019
with no safety violations observed.
August 2019 – There have been no safety issues this month.
September 2019 – There have been no safety issues this month.
October 2019 – A safety audit was held by Robertson on September 19th, 2019. Five (5) safety violations were noted
on the audit, all violations were abated that day.
November 2019 – A third-party inspection was conducted by Ogle on October 23rd, 2019. There were eight (8)
violation that were noted and abated immediately. Subcontractors instituted scaffolding tag-out and tag-
in procedures on site.
December 2019 – A safety audit was held by Robertson on December 5th, 2019. Five (5) safety violations were
noted on the audit, all violations were abated that day.
January 2020 – A third-party inspection was conducted by Ogle on January 6th, 2020. Ten (10) safety violations
were noted on the audit and were abated immediately.
February 20, 2020 – A safety audit was held by Robertson on February 20th, 2020. Thirteen (13) safety violations
were noted on the audit and all items were abated that day.
March 27, 2020 – A safety audit was held by Robertson on March 27th, 2020. Four (4) safety violations were noted
on the audit and all items were abated.
May 2020 – A safety audit was conducted by Ogle on May 8th, 2020. There were four (4) violations that noted and
were abated.
June 2020 – A safety audit was conducted by Ogle on June 9th, 2020. There were seven (7) violations that were
noted and abated.
RCS also continues to perform monthly safety audits, and the Subcontractors quickly abate any concerns noted
during the walkthrough.
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
16 Page
SAFETY
Site Improvements and New High School
June 2019 – There have been no safety issues this month.
July 2019 – There have been no safety issues this month. A safety audit was held by Robertson on July 2nd, 2019
with no safety violations observed.
August 2019 – There have been no safety issues this month.
September 2019 – There have been no safety issues this month.
October 2019 – A safety audit was held by Robertson on September 19th, 2019. Two (2) safety violations were noted
on the audit, all violations were abated that day.
November 2019 – A third-party inspection was conducted by Ogle on October 23rd, 2019. There were two (2)
violation that were noted and abated immediately.
December 2019 – A safety audit was held by Robertson on December 5th, 2019. One (1) safety violation was noted
on the audit and it was immediately abated.
December 6th, 2019 – Masonry wall at Auditorium fell. No serious injuries. Insurance carriers and engineers are
reviewing conditions. (01/13/2020) The cleanup has been completed.
January 2020 – A third-party inspection was conducted by Ogle on January 6th, 2020. Three (3) safety violations
were noted and they were abated that day.
February 20, 2020 – A safety audit was held by Robertson on February 20th, 2020. Seven (7) safety violations were
noted on the audit and all items were abated that day.
March 27, 2020 – A safety audit was held by Robertson on March 27th, 2020. One (1) safety violation was noted on
the audit and it was abated that day.
May 2020 – A safety audit was conducted by Ogle on May 8th, 2020. There was one (1) violation that noted and was
abated immediately.
June 2020 – A safety audit was conducted by Ogle on June 9th, 2020. There were eight (8) violations that were noted
and were abated.
RCS also continues to perform monthly safety audits, and the Subcontractors quickly abate any concerns noted
during the walkthrough.
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
17 Page
PROGRESS PHOTOS
New 4-5 Elementary School
Area C1 Casework, Paint, and Ceiling Grid
July 10, 2020
Area C
Standing Seam
Metal Roof
July 10, 2020
Area C Restroom
Ceramic Tile
July 10, 2020
Area A2 Paint at Corridor
July 10, 2020
Area C1
Restroom
Ceramic Tile
and Paint
July 10, 2020
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
18 Page
PROGRESS PHOTOS
Elementary School Drone Footage
South View of Elementary School
July 9, 2020
West View of Elementary School
July 9, 2020
East View of Both Elementary
and High Schools
July 9, 2020
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
19 Page
PROGRESS PHOTOS
New 9-12 High School
View of Stage from the
Auditorium
July 10, 2020
Area F Prime & 1st Coat Paint
July 10, 2020
View of
Auditorium
from the Stage
July 10, 2020
Exterior Masonry
Veneer
July 10, 2020
Student Dining
and
Monumental
Stair
July 10, 2020
Southwest Licking Local Schools
New High School and New 4-5 Elementary
Progress Report No. 14, July 16th, 2020
20 Page
PROGRESS PHOTOS
High School Drone Footage
South View of High School
July 9, 2020
North View of High School
July 9, 2020
Ariel View of Auxiliary Gym Concrete Pour
July 9, 2020